CN205822221U - Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure - Google Patents

Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure Download PDF

Info

Publication number
CN205822221U
CN205822221U CN201620704814.8U CN201620704814U CN205822221U CN 205822221 U CN205822221 U CN 205822221U CN 201620704814 U CN201620704814 U CN 201620704814U CN 205822221 U CN205822221 U CN 205822221U
Authority
CN
China
Prior art keywords
concrete
post
advanced water
cast strip
strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620704814.8U
Other languages
Chinese (zh)
Inventor
吴善艳
吴万仁
吴建功
徐礼赞
彭浩
张顺
史训兰
程莲清
刘燕
黄欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN WUJIAN SECOND CONSTRUCTION CO Ltd
Original Assignee
HENAN WUJIAN SECOND CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN WUJIAN SECOND CONSTRUCTION CO Ltd filed Critical HENAN WUJIAN SECOND CONSTRUCTION CO Ltd
Priority to CN201620704814.8U priority Critical patent/CN205822221U/en
Application granted granted Critical
Publication of CN205822221U publication Critical patent/CN205822221U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure, including by the reinforced concrete floor first watering armoured concrete slab and post-cast strip is constituted, it is horizontally set on top layer reinforced mesh and the bottom layer of the reinforcing steel mesh sheet of reinforced concrete floor top and bottom, is vertically set on post-cast strip and the steel fabric sheet first watering armoured concrete slab joining place;It is positioned at below post-cast strip and is disposed with advanced water-stopping reinforced concrete floor, fish tail and waterproof layer, waterproof layer and concrete cushion from top to bottom;It is positioned at the both sides bottom post-cast strip and is longitudinally respectively arranged with armored concrete preform strip along it.This utility model advantage is the material leakage problem having stopped between advanced water-stopping reinforced concrete floor and steel fabric sheet.Meanwhile, armored concrete preform strip is partially embedded into first waters in armoured concrete slab, effectively prevent the displacement of armored concrete preform strip in concreting process, pours the concrete not spillage of molding, effective.

Description

Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure
Technical field
This utility model relates to Base isolation system reinforced concrete structure, especially relates to Base isolation system advanced water-stop post-pouring zone Steel bar concrete foundation slab structure.
Background technology
In construction, for preventing monolithic reinforced concrete structure from may produce owing to autogenous shrinkage is uneven or sedimentation is uneven Raw harmful cracks, according to design or job specfication requirement, stays at sole plate relevant position needs and sets temporary construction seam, if through After the dry time, then this temporary construction seam is carried out disturbing concrete construction, form post-cast strip and sole plate is linked to be entirety.Basis Raft board post poured band includes: bed course, waterproof layer, fish tail and waterproof layer, advanced water-stopping reinforced concrete floor, first water armoured concrete slab and Post-cast strip is constituted.Post-cast strip and sole plate joining place need arranged orthogonal steel fabric sheet, to prevent from entering when casting concrete Enter in construction joint.But, between advanced water-stopping reinforced concrete floor and steel fabric sheet, often have space, therefore, this position Spillage is the most universal;Entering the slurry in construction joint must be by manually rejecting to ensure the quality of post-cast strip, and construction joint space Narrow and small and have reinforced mesh, artificial Weeding difficulty is big, wastes time and energy.
Summary of the invention
This utility model purpose is to provide a kind of Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab knot Structure.
For achieving the above object, this utility model takes following technical proposals:
Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure described in the utility model, including by elder generation Water armoured concrete slab and the reinforced concrete floor of post-cast strip composition, be horizontally set on described reinforced concrete floor top respectively The top layer reinforced mesh of portion and bottom and bottom layer of the reinforcing steel mesh sheet, and be vertically set on described post-cast strip with described first water reinforcing bar mix The steel fabric sheet of concrete board joining place;Be positioned at below post-cast strip be disposed with from top to bottom advanced water-stopping reinforced concrete floor, Fish tail and waterproof layer, waterproof layer and concrete cushion;It is positioned at the both sides bottom post-cast strip and is longitudinally respectively arranged with reinforced concrete along it Soil preform strip, described armored concrete preform strip is partially embedded into first waters armoured concrete slab and advanced water-stopping reinforced concrete floor In, embed the armored concrete preform strip end first watered in armoured concrete slab and align with described steel fabric sheet, armored concrete The top of preform strip flushes with described bottom layer of the reinforcing steel mesh sheet.
Described concrete cushion is inverted trapezoidal groove structure, and described fish tail and waterproof layer is positioned at the bottom of described inverted trapezoidal groove, institute State advanced water-stopping reinforced concrete floor to be arranged in inverted trapezoidal groove.
This utility model advantage is to be blocked steel fabric sheet lower space completely by armored concrete preform strip, stops Material leakage problem between advanced water-stopping reinforced concrete floor and steel fabric sheet.Meanwhile, armored concrete preform strip is the most embedding Enter and first water in armoured concrete slab, effectively prevent the displacement of armored concrete preform strip in concreting process, water and build up The concrete of type not spillage, effective.
Accompanying drawing explanation
Fig. 1 is cross-sectional configuration schematic diagram of the present utility model.
Detailed description of the invention
As it is shown in figure 1, Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab described in the utility model knot Structure, including by the reinforced concrete floor first watering armoured concrete slab 1.1,1.2 and post-cast strip 2 is constituted, is horizontally set on respectively The top layer reinforced mesh 3 of reinforced concrete floor top and bottom and bottom layer of the reinforcing steel mesh sheet 4, and it is vertically set on post-cast strip 2 With the steel fabric sheet 5.1,5.2 first watering armoured concrete slab 1.1,1.2 joining place;It is positioned at below post-cast strip 2 the most successively It is provided with advanced water-stopping reinforced concrete floor 6, fish tail and waterproof layer 7 and concrete cushion 8;Fish tail and waterproof layer 7 and concrete cushion 8 Between be provided with waterproof layer, concrete cushion 8 is inverted trapezoidal groove structure, and fish tail and waterproof layer 7 and waterproof layer are laid on inverted trapezoidal groove Bottom, advanced water-stopping reinforced concrete floor 6 is arranged in inverted trapezoidal groove;It is positioned at the both sides bottom post-cast strip 2 along it the most respectively Being provided with armored concrete preform strip 9.1,9.2, armored concrete preform strip 9.1,9.2 is partially embedded into first waters armored concrete In plate 1.1,1.2 and advanced water-stopping reinforced concrete floor 6, embed and first water the armored concrete in armoured concrete slab 1.1,1.2 Align with corresponding steel fabric sheet 5.1,5.2 in preform strip 9.1,9.2 end, the top of armored concrete preform strip 9.1,9.2 with Bottom layer of the reinforcing steel mesh sheet 4 flushes.

Claims (2)

1. a Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure, including by first watering armoured concrete slab The reinforced concrete floor constituted with post-cast strip, is horizontally set on described reinforced concrete floor top and the top layer of bottom respectively Reinforced mesh and bottom layer of the reinforcing steel mesh sheet, and it is vertically set on described post-cast strip and the described armoured concrete slab joining place that first waters Steel fabric sheet;It is positioned at below post-cast strip and is disposed with advanced water-stopping reinforced concrete floor, fish tail and waterproof layer, waterproof from top to bottom Layer and concrete cushion;It is characterized in that: being positioned at both sides bottom post-cast strip, to be longitudinally respectively arranged with armored concrete along it pre- Bar processed, described armored concrete preform strip is partially embedded into first waters in armoured concrete slab and advanced water-stopping reinforced concrete floor, Embedding the armored concrete preform strip end first watered in armoured concrete slab to align with described steel fabric sheet, armored concrete is prefabricated The top of bar flushes with described bottom layer of the reinforcing steel mesh sheet.
Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure the most according to claim 1, its feature Being: described concrete cushion is inverted trapezoidal groove structure, described fish tail and waterproof layer is positioned at the bottom of described inverted trapezoidal groove, described super Front sealing reinforced concrete floor is arranged in inverted trapezoidal groove.
CN201620704814.8U 2016-07-06 2016-07-06 Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure Active CN205822221U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620704814.8U CN205822221U (en) 2016-07-06 2016-07-06 Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620704814.8U CN205822221U (en) 2016-07-06 2016-07-06 Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure

Publications (1)

Publication Number Publication Date
CN205822221U true CN205822221U (en) 2016-12-21

Family

ID=57564031

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620704814.8U Active CN205822221U (en) 2016-07-06 2016-07-06 Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure

Country Status (1)

Country Link
CN (1) CN205822221U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107083776A (en) * 2017-06-20 2017-08-22 中冶建工集团有限公司 A kind of basement raft foundation rear pouring tape construction method
CN109629608A (en) * 2017-10-09 2019-04-16 上海宝冶集团有限公司 Prevent the construction method of raft board concrete construction joint spillage
CN109706953A (en) * 2019-01-21 2019-05-03 吉林建筑大学 Mold and drawing-die construction method for assembly concrete hypogee sole plate
CN112112292A (en) * 2020-07-28 2020-12-22 中建八局第四建设有限公司 Construction method for preventing concrete from permeating into two sides of post-cast strip of bottom plate of garage
CN115354699A (en) * 2022-08-23 2022-11-18 中建八局天津建设工程有限公司 Bottom plate post-cast strip structure and construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107083776A (en) * 2017-06-20 2017-08-22 中冶建工集团有限公司 A kind of basement raft foundation rear pouring tape construction method
CN107083776B (en) * 2017-06-20 2019-02-05 中冶建工集团有限公司 A kind of basement raft foundation rear pouring tape construction method
CN109629608A (en) * 2017-10-09 2019-04-16 上海宝冶集团有限公司 Prevent the construction method of raft board concrete construction joint spillage
CN109706953A (en) * 2019-01-21 2019-05-03 吉林建筑大学 Mold and drawing-die construction method for assembly concrete hypogee sole plate
CN109706953B (en) * 2019-01-21 2023-10-13 吉林建筑大学 Die for foundation slab of assembled concrete underground building and drawing die construction method
CN112112292A (en) * 2020-07-28 2020-12-22 中建八局第四建设有限公司 Construction method for preventing concrete from permeating into two sides of post-cast strip of bottom plate of garage
CN115354699A (en) * 2022-08-23 2022-11-18 中建八局天津建设工程有限公司 Bottom plate post-cast strip structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN205822221U (en) Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure
CN106869172B (en) In-situ deposited prefabricated split-mounting type subway underground station construction method
CN105649113B (en) The structure and construction method of a kind of basement post-pouring zone
CN204676609U (en) The reinforced waterproof construction of a kind of basement bottom plate rear pouring tape
CN101696580A (en) Outboard template construction method of post-pouring belt of outer wall of underground structure
CN204456224U (en) A kind of structure of basement post-pouring zone
CN105780976A (en) Compound concrete shear wall structure and concrete pouring method thereof
CN104631513A (en) Construction method for closing basement exterior wall post-cast strip
CN109577377A (en) Basement post-pouring zone structure and its construction method
CN105863089A (en) Post-cast strip water-proof structure and treatment method
CN209723033U (en) Pipe jacking working well applicable to desert waterless sand layer area
CN209211748U (en) A kind of structure node of assembled ceiling radiating system
CN108331154A (en) Basement reconstruction construction method with raft foundation building
CN107083776B (en) A kind of basement raft foundation rear pouring tape construction method
CN204418691U (en) A kind of for cast-in-place vertical member and horizontal member junction concrete blocking apparatus
CN209538214U (en) A kind of late poured band structure of outer wall of basement
CN204238264U (en) A kind of sole plate post-poured strip structure
CN106320569A (en) Assembly-type shear wall embedded steel bar connection process
CN207348280U (en) A kind of novel precast floor slab
CN108130889B (en) Manufacturing method of stepped construction joint between main bottom plate of pump brake and side wall of runner layer
CN204608839U (en) Ater-casting anti-corrosion structure
CN206570961U (en) A kind of outer wall precast slab is combined late poured band structure
CN204530784U (en) Ater-casting foreign material cleaning structure
CN211200755U (en) Basement roof movement joint waterproof construction structure
CN210946907U (en) High-strength and high-waterproofness high-low span structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant