CN204608839U - Ater-casting anti-corrosion structure - Google Patents

Ater-casting anti-corrosion structure Download PDF

Info

Publication number
CN204608839U
CN204608839U CN201520227391.0U CN201520227391U CN204608839U CN 204608839 U CN204608839 U CN 204608839U CN 201520227391 U CN201520227391 U CN 201520227391U CN 204608839 U CN204608839 U CN 204608839U
Authority
CN
China
Prior art keywords
ater
casting
reinforced mesh
passage
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520227391.0U
Other languages
Chinese (zh)
Inventor
李喆骁
周荣
陆金晶
张飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Greenland Construction Group Co Ltd
Original Assignee
Shanghai Greenland Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Greenland Construction Group Co Ltd filed Critical Shanghai Greenland Construction Group Co Ltd
Priority to CN201520227391.0U priority Critical patent/CN204608839U/en
Application granted granted Critical
Publication of CN204608839U publication Critical patent/CN204608839U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to technical field of building construction, specifically a kind of ater-casting anti-corrosion structure is disclosed, comprise sole plate, one passage is set in the middle part of described sole plate, passage both sides are reinforced mesh, described reinforced mesh is provided with steel plate waterstop strip, and described reinforced mesh side is provided with stiffened wire lath.The utility model advantage is, owing to being provided with steel plate waterstop strip on reinforced mesh, avoids the generation of ater-casting Seepage, prevents the problem that ater-casting reinforcing bar is corroded.Simultaneously set up stiffened wire lath in reinforced mesh side, when preventing the concreting of passage both sides in admission passage.

Description

Ater-casting anti-corrosion structure
Technical field
The utility model relates to technical field of building construction, refers to a kind of ater-casting anti-corrosion structure especially.
Background technology
For the differential settlement in solution engineering loading procedure and distortion, general needs arranges ater-casting between two annexes.
Traditional ater-casting, ultra-deep high water level basis adopts traditional method to be the steel fabric sheet colligation of both sides, basic ater-casting, after Base isolation system concreting being caused like this, ater-casting reinforcing bar easily the hidden danger of quality such as not easily to be ensured by ater-casting internal water accumulation corrosion, construction quality, the construction at position, ater-casting, basis brings and such as affects programming, and construction quality is difficult to ensure.
Utility model content
The purpose of this utility model is to provide a kind of ater-casting anti-corrosion structure, and this structure can solve the problem, and prevents percolating water in ater-casting to cause the problem of ater-casting corrosion.
To achieve these goals, the utility model have employed following technical scheme: a kind of ater-casting anti-corrosion structure, comprise sole plate, one passage is set in the middle part of described sole plate, passage both sides are reinforced mesh, described reinforced mesh is provided with steel plate waterstop strip, and described reinforced mesh side is provided with stiffened wire lath.
The beneficial effects of the utility model are: after adopting said structure: owing to being provided with steel plate waterstop strip on reinforced mesh, avoid the generation of ater-casting Seepage, prevent the problem that ater-casting reinforcing bar is corroded.Simultaneously set up stiffened wire lath in reinforced mesh side, when preventing the concreting of passage both sides in admission passage.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment technical scheme, below the accompanying drawing used required in describing embodiment is briefly described, apparently, accompanying drawing in the following describes is only that the utility model is in order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, below the accompanying drawing used required in p-embodiment or description of the prior art is briefly described, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
Ater-casting anti-corrosion structure as shown in Figure 1, comprise sole plate (1), described sole plate (1) middle part arranges a passage (4), passage (4) both sides are reinforced mesh (2), described reinforced mesh (2) is provided with steel plate waterstop strip (3), and described reinforced mesh (2) side is provided with stiffened wire lath.
This ater-casting operates according to the following steps when constructing:
1, line setting: adopt transit unwrapping wire, from oriented axial control network, measure out position, ater-casting, determine the accurate location of ater-casting, put bed course size outside from position, ater-casting, squeeze into spacer bars around the corner, draw and establish nylon wire, spill lime line.According to the lime line of location, dig to design elevation under adopting artificial vertical, the degree of depth is generally easy is 650mm, measures cutting depth with level gauge and Sopwith staff simultaneously.From ater-casting, the position line measures outer unwrapping wire accurately, squeezes into spacer bars at turning, draws and establishes nylon wire, spills lime line; At the bottom of from outer edge lime line to the ater-casting of having excavated, obliquely excavate the unnecessary earthwork or sandstone.After excavation, certain finishing is carried out to groove.The local place of backbreaking should backfill.Frog hammer ramming more than three times is back and forth adopted to substrate, inclined-plane is made real, guarantee the groove earthwork or sandstone closely knit, concrete cushion construction completes.
2, enhancement Layer structure construction: concrete cushion construction completes and starts enhancement Layer structure of constructing on the 3rd day.Enhancement Layer general thickness is easily 300mm, and reinforcement cover controls at 50mm, first places longitudinal reinforcement 12, can carry out overlap joint colligation according to 30d, and then place cross direction profiles muscle, vertical lateral dimension is generally easy is 200mm × 150mm, and reinforcing bar binding is even.Acceptance(check) after reinforcing bar binding, starts to build C30 concrete, with watering with the Troweling press finishing that vibrates.Build complete covered with plastic film and woollen blanket carries out maintenance.
3, rubber water-proof sheet construction: with the thick rubber water-proof sheet of paving 10mm, rubber water-proof sheet width is preferably outside both sides, ater-casting and puts >=200mm.Rubber water-proof oblique cut grafting length is no less than 200mm, and the full glue of glue special connects.Rubber water-proof sheet is laid on top after laying reinforced mesh (2), lateral length is put 250mm outside the size of ater-casting.
4, fish tail and waterproof layer construction: construction waterproof cover concrete, with watering with the Troweling press finishing that vibrates.Build complete covered with plastic film and woollen blanket carries out maintenance.
5, sole plate (1) construction: after topping construction; first use and a concreting 50mm wide same base plate protection layer the same thick coagulation earth steps of basis with label; control thickness of protection tier, after intensity reaches, carry out steel mesh reinforcement colligation under base plate again.Ф 12 longitudinally fixing reinforcing bar is longitudinally set at position, ater-casting before the colligation of baseplate reinforcing bar net, in altitude range every 100mm together, for the steel fabric sheet of blocking in the altitude range of ater-casting, after treating bottom layer of the reinforcing steel colligation, be spot welded on bottom layer of the reinforcing steel with vertical reinforcement and be fixed, vertical reinforcement longitudinally every 500mm together.In the altitude range of ater-casting, carry out lock raft by upper and lower two pieces of close order double-layer wire mesh sheet, in sole plate (1) reinforcing bar bottom range, increase by one stiffened wire lath, with shutoff lateral bottom plates concrete.
Sole plate (1) middle part increases by one steel plate waterstop strip (3), and steel plate waterstop strip (3) jointing adopts full weld.After bottom reinforcement bars construction, measure the horizontal absolute altitude of waterstop, adopt welding reinforcing bar is fixed.
Sole plate (1) concrete is poured into a mould, and before treating concrete final set, the cement paste of removing inflow ater-casting, covers double-deck colour bar cloth and bamboo slab rubber is protected, and falls in ater-casting to prevent foreign material.The order from centre to both sides is easily followed in sole plate (1) concreting, is conducive to ponding and discharges to surrounding.
6, ater-casting capping protection: apart from basic ater-casting 100mm place, every limit cement mortar smear the checkdam of a 50mm × 50mm or build 2 skin common brick cement mortar by laying bricks or stones and whitewash, upper enclosure plank.Ater-casting is entered to prevent construction water and foreign material.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (1)

1. an ater-casting anti-corrosion structure, comprise sole plate (1), it is characterized in that, described sole plate (1) middle part arranges a passage (4), passage (4) both sides are reinforced mesh (2), described reinforced mesh (2) is provided with steel plate waterstop strip (3), and described reinforced mesh (2) side is provided with stiffened wire lath.
CN201520227391.0U 2015-04-15 2015-04-15 Ater-casting anti-corrosion structure Active CN204608839U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520227391.0U CN204608839U (en) 2015-04-15 2015-04-15 Ater-casting anti-corrosion structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520227391.0U CN204608839U (en) 2015-04-15 2015-04-15 Ater-casting anti-corrosion structure

Publications (1)

Publication Number Publication Date
CN204608839U true CN204608839U (en) 2015-09-02

Family

ID=53961400

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520227391.0U Active CN204608839U (en) 2015-04-15 2015-04-15 Ater-casting anti-corrosion structure

Country Status (1)

Country Link
CN (1) CN204608839U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107044171A (en) * 2017-06-02 2017-08-15 中联世纪建设集团有限公司 Butyl putty steel plate water-stopping rear pouring tape construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107044171A (en) * 2017-06-02 2017-08-15 中联世纪建设集团有限公司 Butyl putty steel plate water-stopping rear pouring tape construction method

Similar Documents

Publication Publication Date Title
CN101403218B (en) Processing method for basement water-proof concrete construction joint
CN207987983U (en) A kind of waterproof construction being used for underground engineering main body construction seam and post-cast strip
CN203531009U (en) Macadam layer hydrophobic structure for basement base plate
CN204000956U (en) A kind of basement bottom plate rear pouring tape structure
CN206768880U (en) A kind of waterproof construction for seashore pipe gallery
CN105862873A (en) Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit
CN104060781A (en) Cast-in-situ cranked slab stair without seams at stair sections and construction method
CN105862928B (en) A kind of post-cast strip exterior wall advanced water-stopping processing structure and its construction technology
CN104652495A (en) Waterproof construction process for joint of inner support upright post of foundation pit and bottom plate
CN105756100A (en) Basement post-pouring belt system and making method thereof
CN206090638U (en) Underground side wall post -cast strip waterproof construction
CN104890434A (en) Plastic-stone landscape making method
CN205822221U (en) Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure
CN104631513A (en) Construction method for closing basement exterior wall post-cast strip
CN204608839U (en) Ater-casting anti-corrosion structure
CN110295630A (en) The late poured band structure of multilayer constraint antiseep
CN106884436B (en) A kind of construction method of the waterproof connecting structure of foundation pit uplift pile and structure base slab
CN204608831U (en) Ater-casting substructure
CN204608842U (en) The saturating structure of deep foundation ater-casting base impervious
CN204530783U (en) Structure strengthened by deep foundation ater-casting bottom
CN204530784U (en) Ater-casting foreign material cleaning structure
CN102535493B (en) Method for constructing inverted type foundation beam
CN204530785U (en) A kind of deep foundation post empiricism structure
CN204781012U (en) Clean - structure in post -cast strip
CN107386298A (en) A kind of depth hole composite supporting construction and its construction method with water-proof function

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant