KR20090022502A - Long span psc girder type rahmen bridge and its construction method using moment re-distribution - Google Patents

Long span psc girder type rahmen bridge and its construction method using moment re-distribution Download PDF

Info

Publication number
KR20090022502A
KR20090022502A KR1020070087885A KR20070087885A KR20090022502A KR 20090022502 A KR20090022502 A KR 20090022502A KR 1020070087885 A KR1020070087885 A KR 1020070087885A KR 20070087885 A KR20070087885 A KR 20070087885A KR 20090022502 A KR20090022502 A KR 20090022502A
Authority
KR
South Korea
Prior art keywords
concrete
wall
psc girder
ramen bridge
bracket
Prior art date
Application number
KR1020070087885A
Other languages
Korean (ko)
Other versions
KR100946716B1 (en
Inventor
이종관
Original Assignee
(주)한맥기술
주식회사 장헌산업
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한맥기술, 주식회사 장헌산업 filed Critical (주)한맥기술
Priority to KR1020070087885A priority Critical patent/KR100946716B1/en
Publication of KR20090022502A publication Critical patent/KR20090022502A/en
Application granted granted Critical
Publication of KR100946716B1 publication Critical patent/KR100946716B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Long span PSC girder type framing bridge through the moment redistribution and the construction method thereof are provided that the excessive moment to the wall is prevented. A long span PSC girder type framing bridge through the moment redistribution comprises a concrete wall body(10) of both sides, and an upper structure installed between the concrete wall bodies. The upper structure includes a PSC girder(20) and a concrete deck-plate formed in the PSC girder upper with the integrally.

Description

모멘트 재분배를 통한 장경간 프리스트레스트 콘크리트 거더형 라멘교량 및 그 시공방법 {Long Span PSC Girder Type Rahmen Bridge and its Construction Method Using Moment Re-distribution} Long Span PSC Girder Type Rahmen Bridge and its Construction Method Using Moment Re-distribution}

본 발명은 모멘트 재분배 방식을 통하여 장경간의 프리스트레스트 콘크리트 거더형 라멘교량을 이룰 수 있는 구조와, 그에 적합한 시공기술에 관한 것으로서, 구체적으로는 프리스트레스트 콘크리트 거더(Prestressed Concrete Girder/ 이하 "PSC거더"라고 약칭함)를 이용하여 라멘교량을 시공함에 있어서, 시공단계에서 모멘트를 적절히 재분배하고 벽체와 거더의 단면형상을 새롭게 함으로써, 거더 및 바닥판 하중에 의하여 발생하는 모멘트를 교량의 중앙부로 유도하여 벽체 상단의 부모멘트를 최소화하고, 2차 사하중 및 활하중에 의하여 교량에 작용하는 정, 부 모멘트가 균형을 이루도록 하여 장지간, 저형고의 우수한 경제성을 가지는 라멘교량 및 그 시공방법에 관한 것이다. The present invention relates to a structure capable of forming a prestressed concrete girder-type ramen bridge between long diameters through a moment redistribution method, and a construction technology suitable for the same, specifically, a prestressed concrete girder (hereinafter referred to as a "PSC girder"). In the construction of the ramen bridge, the moments generated by the girder and the bottom plate load are guided to the center of the bridge by appropriately redistributing the moments in the construction stage and renewing the cross-sectional shape of the walls and girders. The present invention relates to a ramen bridge and a construction method having excellent economic feasibility between long distance and low height by minimizing the parent moment and balancing the positive and negative moments acting on the bridge by secondary dead and live loads.

근래에 들어, 빈번한 집중 호우, 하천 수위의 상승, 홍수 등의 영향으로 장지간 저형고의 교량에 대한 수요가 증가하고 있는 상황인데 반하여, 이러한 수요에 부응할 수 있는 적절한 저형고의 교량형식이 없어, 다경간 교량을 적용하거나 도로의 계획고를 높여서 교량을 시공하는 실정이다. In recent years, the demand for bridges between low and long spans has been increasing due to frequent heavy rainfalls, rising river levels, and floods, but there is no appropriate low bridge type to meet these demands. In other words, the construction of bridges by applying multi-span bridges or by increasing the height of roads.

한편, 콘크리트 라멘교량은 교좌 장치가 없고 형고가 낮으며 유지 관리가 용이하다는 장점을 가지고 있어서 소하천에 건설되는 교량형식으로 많이 사용되고 있다. 그런데 이러한 종래의 라멘교량은 지간이 길어질수록 자중에 의한 모멘트가 급격하게 커지고, 특히 벽체와 상부구조 즉, 거더 또는 바닥판이 만나는 지점부의 모멘트가 급격히 증가하게 되어 일반적으로는 지간이 15m 이상인 교량에는 적용하기 어렵다는 한계가 있으므로, 종래의 라멘교량으로는 위와 같은 최근의 교량수요에 그대로 이용하기 어려운 상태이다. On the other hand, the concrete ramen bridge is used as a bridge type to be built in small rivers because it has the advantage that there is no bridge device, low mold height and easy maintenance. However, the conventional ramen bridge has a large moment, and the moment due to its own weight rapidly increases, and in particular, the moment of the point where the wall and the superstructure, that is, the girder or the bottom plate, increases rapidly, so it is generally applied to a bridge having a length of 15 m or more. Since there is a limit that it is difficult to do so, it is difficult to use it as it is with the recent bridge demand as the conventional ramen bridge.

종래의 라멘교량을 장지간의 교량에 직접 적용하기 어려운 구조적인 한계를 좀 더 구체적으로 살펴보면, 우선 라멘교량은 지간이 길어질수록 자중에 의한 모멘트가 급격하게 커지게 된다. 도 1에는 종래의 라멘교량에 등분포 하중이 작용할 경우의 개략적인 모멘트도가 도시되어 있으며, 아래의 수학식 1은 벽체 즉, 수직부재의 고정단에서 작용하는 모멘트(Ma, Mb)의 계산식이고, 수학식 2는 지점부에 작용하는 모멘트(Mc, Md)이고, 수학식 3은 지간 중앙에서 작용하는 모멘트(Me)이다. 아래의 수학식 1 내지 3에서 β는 수평부재의 단면이차모멘트(Ih)와 수직부재의 단면이차모멘트(Iv)의 비 즉, β = Ih/Iv 이고, e는 벽체의 높이 H와 지간 길이 L의 비 즉, e=H/L이며, l은 지간의 길이 즉, L이며, w는 등분포하중 값이다. Looking at the structural limitations that are difficult to apply the conventional ramen bridge directly to the bridge between the jijangji in more detail, first, the longer the length of the ramen bridge, the greater the moment due to its own weight. FIG. 1 shows a schematic moment diagram when a uniform distribution load is applied to a conventional ramen bridge, and Equation 1 below shows the moments (M a , M b ) acting at a fixed end of a wall, that is, a vertical member. Equation 2 is a moment (M c , M d ) acting on the point portion, Equation 3 is a moment (M e ) acting in the center of the interval. In Equations 1 to 3 below, β is the ratio of the cross-sectional secondary moment (I h ) of the horizontal member and the cross-sectional secondary moment (I v ) of the vertical member, that is β = I h / I v , e is the height of the wall H Is the ratio of the length L to the length L, that is, e = H / L, l is the length of the length L, and w is an equally distributed load value.

Figure 112007063408417-PAT00001
Figure 112007063408417-PAT00001

Figure 112007063408417-PAT00002
Figure 112007063408417-PAT00002

Figure 112007063408417-PAT00003
Figure 112007063408417-PAT00003

이와 같이, 지점부에 작용하는 모멘트(Mc, Md)는 지간 길이의 제곱에 비례하므로, 교량의 지간이 2배로 증가하게 되면 지점부의 모멘트(Mc, Md)는 4배가 되고, 온도 및 건조수축 등으로 인한 하중을 고려하게 되면 지점부의 모멘트(Mc, Md)는 4배 이상으로 증가하게 된다.As such, the moments (M c , M d ) acting on the point portion are proportional to the square of the length of the bridge, so if the span of the bridge doubles, the moment (M c , M d ) of the point portion is four times, and the temperature And considering the load due to dry shrinkage, etc. The moment (M c , M d ) of the point portion is increased to more than four times.

이와 같이 지점부의 모멘트 증가는 결국 교량 형고의 증가를 가져온다. 특히 교량의 지간을 콘크리트 구조로 시공하는 경우, 균열 등을 고려한 유효단면을 기준으로 형고를 설계해야 하므로, 실제 교량 지간의 형고는 더욱 커지게 되고, 이러한 형고의 증가는 다시 자중의 증가를 가져오게 되어 지점부의 모멘트 증가 및 그에 따른 형고의 추가적인 증가를 가져오게 되어, 교량의 형고가 지나치게 높아지는 비경제적인 단면을 가진 교량이 될 수밖에 없다. As such, the moment of the point increases, resulting in an increase in bridge height. In particular, when the bridge is constructed with concrete structure, the mold height should be designed based on the effective section considering the crack, etc., so the height between the actual bridges becomes bigger, and the increase in the weight results in the increase of the self weight. As a result, the moment of the point increases, and thus the additional increase in the height of the bridge, which is inevitably becomes a bridge having an uneconomical cross section of the height of the bridge.

종래의 라멘교량을 장지간의 교량에 직접 적용하기 어려운 구조적인 또 다른 한계로는 상부구조와 벽체의 강성비 차이 즉, 거더 또는 바닥판과 벽체의 강성비에 차이에 따른 한계가 있다. 동일한 지간의 라멘교량에 있어서 벽체의 높이가 낮아질수록 지점부에 작용하는 모멘트(Mc)는 증가하게 된다. 즉, 벽체의 상단에 작용하는 모멘트가 커지게 되는 것이다. 그런데 단경간 라멘교량을 지간 길이만 그대로 늘려서 장지간 라멘교량으로 변화시키면 벽체의 높이는 고정된 상태에서 지간만 길어지게 되므로 지간의 증가에 의한 모멘트 증가 이외에도 벽체의 높이와 지간의 비율 즉, 거더 또는 바닥판과 벽체의 강성비 차이에 의한 모멘트가 추가로 발생하게 되어 이에 대한 대응으로 단면이 증가된 교량이 될 수밖에 없고, 결국 비경제적인 교량이 시공되는 한계가 있는 것이다. Another structural limitation that is difficult to apply the conventional ramen bridge directly to the bridge between the jijangji is a difference due to the difference in the stiffness ratio of the superstructure and the wall, that is, the difference in the stiffness ratio of the girder or the bottom plate and the wall. As the height of the wall decreases in the ramen bridge between the same spaces, the moment (M c ) acting on the point increases. In other words, the moment acting on the top of the wall becomes large. However, if the short span ramen bridge is changed to the long span bridge by increasing the length of the span as it is, the height of the wall becomes longer in the fixed state, so the height of the wall is increased. The moment due to the difference in the stiffness ratio between the plate and the wall is generated additionally, in response to this, the cross section is increased, and there is a limit to the construction of an uneconomic bridge.

라멘교량의 지간을 증가시키는 종래의 방안으로는 상부구조를 이루는 거더에 강선을 배치하여 긴장력을 도입하는 것이 제안되었다. 그러나, 거더에 강선에 의한 수평긴장력을 도입하게 되면 상부구조에는 유리할 수 있으나, 강선 긴장으로 인한 추가적인 모멘트가 벽체에 가해지게 되어 벽체의 부담을 증가시키게 되는 문제가 야기된다. 특히, 강선의 긴장력이 결국에는 벽체로 전달되는 것이므로, 지간 중앙에 도입되는 긴장력이 축소되어 긴장력 도입이 불량하게 되는 문제점도 발생하게 된다. As a conventional method for increasing the span of the ramen bridge, it has been proposed to introduce tension by arranging steel wires on girders forming a superstructure. However, the introduction of horizontal tension by the steel wire to the girder may be advantageous to the superstructure, but the additional moment due to the wire tension is applied to the wall causes a problem that increases the burden on the wall. In particular, since the tension force of the steel wire is eventually delivered to the wall, the tension force introduced into the center of the trunk is reduced, which also causes a problem in that the tension force is poorly introduced.

또한, 최대 부모멘트 발생지점 즉, 지점부에 강선이 정착되어야 하므로 구조적으로 불리하게 되며, 최대 부모멘트가 작용하는 벽체의 상단을 보강하기 위하여 연직방향으로 벽체에도 강선을 배치하여 보강해야 하므로, 그에 따른 경제적인 불리함이 수반되는 문제가 있다. In addition, since the steel wire should be fixed to the point where the maximum parental moment occurs, that is, the point is structurally disadvantageous, and in order to reinforce the upper end of the wall on which the maximum parental moment acts, the steel wire must also be placed and reinforced in the vertical direction. There is a problem that is accompanied by economic disadvantages.

본 발명은 위와 같은 종래 기술의 문제점을 해결하기 위하여 개발된 것으로서, 궁극적으로는 장지간, 저형고의 우수한 경제성을 가지는 라멘교량 및 그 시공방법을 제공하는 것을 목적으로 한다. The present invention was developed to solve the above problems of the prior art, and ultimately, it is an object of the present invention to provide a ramen bridge and a construction method having excellent economic efficiency between long and short periods.

구체적으로 본 발명은 장지간에 적합한 효율적인 단면을 가진 PSC 거더로 교량의 상부구조를 형성함으로써 자중에 의한 모멘트를 크게 감소시켜 지간 증가로 인한 자중 증가를 최소화함으로써 교량 형고의 증가 없이 장지간, 저형고의 라멘교량을 이룰 수 있도록 하는 라멘교량 및 그 시공방법을 제공하는 것을 목적으로 한다. Specifically, the present invention forms a superstructure of the bridge with a PSC girder having an efficient cross section suitable for long distances, thereby greatly reducing the moment due to the weight increase and minimizing the increase in the weight due to the increase in the length of the bridge. It is an object of the present invention to provide a ramen bridge and its construction method for achieving a ramen bridge.

또한, 본 발명은 축력과 모멘트를 동시에 받는 벽체를 2분할된 단면으로 형성함으로써, 벽체의 강성을 축소시켜 자중에 의한 모멘트를 감소시킬 뿐만 아니라 온도 및 건조수축 등의 변위로 인한 하중을 감소시켜 장지간 라멘교량에 있어서 문제가 되는 벽체에 대한 과도한 모멘트 발생을 해결함으로써 장지간, 저형고의 라멘교량을 이룰 수 있도록 하는 라멘교량 및 그 시공방법을 제공하는 것을 목적으로 한다. In addition, the present invention forms a wall that receives both the axial force and the moment in two divided sections, thereby reducing the rigidity of the wall to reduce the moment due to its own weight as well as to reduce the load due to displacements such as temperature and drying shrinkage It is an object of the present invention to provide a ramen bridge and a construction method for achieving long and low height ramen bridges by resolving excessive moments on walls that are problematic in inter-lane ramen bridges.

더 나아가 본 발명은 각각의 시공단계에서 발생하는 모멘트를 적절히 재분배할 수 있는 새로운 방식의 시공방법을 도입함으로써, 정, 부모멘트의 균형을 이루도록 하여 장지간, 저형고의 라멘교량을 효율적으로 시공할 수 있도록 하는 새로운 구조의 라멘교량 및 그 시공방법을 제공하는 것을 목적으로 한다.Furthermore, the present invention introduces a new method of construction that can redistribute the moments generated at each construction stage, so that the balance between the static and the parent can be balanced to efficiently construct the long span and low height ramen bridges. The purpose is to provide a ramen bridge with a new structure and construction method thereof.

구체적으로 본 발명에 의하면, 양측의 콘크리트 벽체와, 그 사이에 설치되는 상부구조로 이루어진 라멘교량으로서, 상기 상부구조는, 지간의 중간에서는 상, 하부 플랜지와 웨브로 이루어진 I형 단면을 가지며, 상기 상부구조와 상기 벽체의 상단부가 만나는 지점부에서는 사각형의 충실 단면을 가지는 프리스트레스트 콘크리트 거더(PSC 거더)와, 그 상부에 일체로 형성된 콘크리트 바닥판으로 이루어지며; 상기 콘크리트 벽체의 상부에는 지간 내측으로 돌출된 브라켓이 형성되어 있어, 상기 PSC 거더의 단부는 상기 브라켓 위에 거치되고; 상기 지점부에 콘크리트가 일체로 타설되어 상부구조와 벽체가 일체를 이루어 강결되는 구조를 가지는 것을 특징으로 하는 라멘교량이 제공된다. Specifically, according to the present invention, as a ramen bridge composed of concrete walls on both sides and an upper structure provided therebetween, the upper structure has an I-shaped cross section consisting of an upper, a lower flange and a web in the middle of the span. At the point where the upper structure and the upper end of the wall meets the prestressed concrete girder (PSC girder) having a square faithful cross section and a concrete bottom plate integrally formed thereon; A bracket is formed on the top of the concrete wall and protrudes inwardly between the sections, and an end of the PSC girder is mounted on the bracket; Ramen bridge is provided, characterized in that the concrete is integrally poured to the point portion has a structure in which the upper structure and the wall is integrally rigid.

이와 같은 본 발명의 라멘교량에 있어서, 상기 벽체는, 그 하단 내부에 분할재가 설치되어 벽체의 단면이 지간 내부측과 지간 외부측으로 분할되어 있는 구조를 가질 수 있으며, 상기 브라켓의 상부면과 PSC 거더의 단부 하면 사이에는 탄성 패드가 개재되고, 상기 브라켓의 상부면과 PSC 거더의 단부 하면 사이의 다른 간격 부분에는 채움재로 이루어진 베딩층이 형성될 수도 있다. In the ramen bridge of the present invention, the wall has a structure in which the partition member is installed in the lower end thereof so that the cross section of the wall is divided into the inner side of the stem and the outer side of the stem, and the upper surface of the bracket and the PSC girder. An elastic pad may be interposed between the bottom surfaces of the end portions, and a bedding layer made of a filler may be formed on another gap portion between the top surface of the bracket and the bottom surface of the PSC girder.

또한, 본 발명의 라멘교량에서는, 상기 PSC 거더 단부에는 관통공이 형성되어, 경화된 상태의 지점부 콘크리트와 상기 PSC 거더 단부의 상기 관통공에 보강용 인장부재가 관통 설치되어 고정될 수도 있다. In addition, in the ramen bridge of the present invention, a through hole is formed in the end portion of the PSC girder, a reinforcing tension member may be installed and fixed to the through-hole of the point concrete in the hardened state and the end of the PSC girder.

본 발명에 따른 라멘교량의 또다른 실시예에 의하면, 상기 바닥판은, 지점부의 콘크리트가 타설될 때 함께 콘크리트가 타설되어 상기 PSC 거더의 상부에 형성될 수 있다. According to another embodiment of the ramen bridge according to the invention, the bottom plate may be formed on top of the PSC girder by pouring concrete together when the concrete of the point portion is poured.

본 발명에서는 위와 같은 라멘교량을 시공하는 방법이 제공된다. In the present invention, there is provided a method for constructing such a ramen bridge.

본 발명에 의하면, 벽체 단면의 2분할을 통하여 상부구조와 벽체 간의 강성비율이 증가하게 되어 지점부에서 벽체의 상단부에 작용하는 모멘트가 줄어들게 되고, 벽체의 단면이차모멘트의 감소로 인하여 온도변화 및 건조수축 등의 변위에 의하여 유발되는 하중 역시 감소되어 장지간 라멘교량에 있어서 문제가 되는 벽체에 대한 과도한 모멘트 발생을 해결할 수 있게 되는 효과가 있다. According to the present invention, the stiffness ratio between the superstructure and the wall is increased through two divisions of the wall section, so that the moment acting on the upper end of the wall at the point is reduced, and the temperature is changed and dried due to the reduction of the secondary moment of the wall. The load caused by the displacement of the contraction, etc. is also reduced, so that it is possible to solve the excessive moment generation for the wall, which is a problem in the long-term ramen bridge.

또한, 본 발명에서, PSC 거더의 구조를 지간의 중간에는 상, 하부 플랜지와 웨브로 이루어진 I형 단면을 가지도록 하고, 지점부에서는 사각형의 충실 단면을 가지도록 함으로써, 라멘교량이 장지간으로 되는 경우 상부구조의 자중으로 인한 모멘트 증가를 최소화할 수 있게 되는 효과를 발휘하게 된다. In addition, in the present invention, the structure of the PSC girder has an I-shaped cross section consisting of an upper, a lower flange and a web in the middle of the span, and a rectangular faithful cross section at the point portion, so that the ramen bridge becomes a long span. In this case, it is possible to minimize the increase in moment due to the weight of the superstructure.

특히, 본 발명에서는 시공단계 및 구조형상을 조절하여 모멘트를 재분배함으로써, 상부구조의 자중에 의하여 발생하는 모멘트를 지간의 중앙부로 유도하여 지점부에서 벽체의 상단에 작용하는 부모멘트를 최소화하고, 교량 시공 후 작용하는 포장 등에 의한 2차 고정하중과 활하중 등에 의해 발생하는 정, 부 모멘트가 균형을 이루게 되며, 장지간, 저형고의 라멘교량을 효율적으로 시공할 수 있게 된다. In particular, in the present invention, by redistributing the moment by adjusting the construction stage and structural shape, the moment generated by the self-weight of the superstructure to the center of the trunk to minimize the parent moment acting on the top of the wall at the point, bridge The positive and negative moments generated by secondary fixed loads and live loads due to the pavement acting after construction are balanced, and it is possible to efficiently construct long-term, low-density ramen bridges.

다음에서는 도면을 참조하여 본 발명에 따른 형강 기둥과 콘크리트 바닥판의 접합구조 및 그 접합시공방법을 설명한다. Next, with reference to the drawings will be described the joining structure and the construction method of joining the beam and the concrete deck according to the present invention.

도 2에는 벽체(10)를 설치한 상태를 보여주는 개략적인 측면도가 도시되어 있다. 본 발명에 따른 라멘교량을 시공하기 위하여 우선, 도 2에 도시된 것처럼, 시점부와 종점부의 벽체(10)를 각각 설치한다. 본 발명에 있어서 상기 벽체(10)는 다음과 같은 구조를 가지는 것이 바람직하다. 도 3에는 도 2에서 선A-A에 따른 단면도가 도시되어 있는데, 도 3에 도시된 것처럼, 본 발명에 있어서 벽체(10)는 그 하부의 단면이 2분할되는 구조의 콘크리트 벽체로 이루어지는 것이 바람직하다. 즉, 교축방향으로 합판 등과 같은 분할재(13)가 설치되어 벽체(10)의 단면이 지간 내부측(11)과 지간 외부측(12)으로 분할되는 것이다. 2 is a schematic side view showing the state in which the wall 10 is installed. In order to construct a ramen bridge according to the present invention, first, as shown in FIG. In the present invention, the wall 10 preferably has the following structure. 3 is a cross-sectional view taken along the line A-A in FIG. 2, as shown in FIG. 3, in the present invention, the wall 10 is preferably made of a concrete wall having a structure in which the cross section of the lower part is divided into two. That is, the partition member 13 such as plywood or the like is installed in the axial direction so that the cross section of the wall 10 is divided into the interstitial inner side 11 and the interstitial outer side 12.

벽체(10)는 축력과 모멘트를 동시에 받는 구조물이므로, 벽체의 강성이 작아질수록 상부구조의 자중 및 온도변화 등에 의하여 벽체에 발생하는 모멘트가 작아진다. 따라서 이와 같이 벽체(10)의 단면이 2분할되면, 축력을 받는 단면적은 그대로 유지하게 되므로 축력에 대한 지지력은 그대로지만 2분할된 단면의 강성 및 단면이차모멘트는 1/4로 축소되므로, 상부구조와 벽체 간의 강성비율 즉, 단면이차모멘트의 비율이 증가하게 되어 지점부에서 벽체(10)의 상단부에 작용하는 모멘트가 줄어들게 된다. 또한, 벽체의 단면이차모멘트의 감소로 인하여 온도변화 및 건조수축 등의 변위에 의하여 유발되는 하중 역시 감소되므로, 장지간 라멘교량에 있어서 문제가 되는 벽체에 대한 과도한 모멘트 발생을 해결할 수 있게 된다. 이와 같이, 벽체(10)에서 2분할되는 부분은 벽체(10)의 하단부에서 약 0.5~1.0H 사이의 범위가 되도록 하는 것이 바람직하다(여기서 H는 벽체의 높이이다)Since the wall 10 is a structure that receives axial force and a moment at the same time, the smaller the rigidity of the wall, the smaller the moment generated in the wall due to the change in the weight and temperature of the superstructure. Therefore, when the cross section of the wall 10 is divided into two, the cross-sectional area subjected to the axial force is maintained as it is, so that the bearing force for the axial force remains the same, but the stiffness and cross-sectional secondary moment of the two divided sections are reduced to 1/4, The ratio of the stiffness ratio between the wall and the wall, that is, the ratio of the cross-sectional secondary moment, is increased, thereby reducing the moment acting on the upper end of the wall 10 at the point portion. In addition, since the load caused by the displacement of the temperature change and the drying shrinkage is also reduced due to the reduction of the secondary moment of the cross section of the wall, it is possible to solve the excessive moment generation for the wall which is a problem in the long bridge ramen bridge. As such, it is preferable that the part divided into two parts of the wall 10 is in the range of about 0.5 to 1.0H at the lower end of the wall 10 (where H is the height of the wall).

한편, 본 발명에 있어서, 상기 벽체(10)의 상단에는 지간 내측 방향으로 돌출되어 후술하는 PSC 거더(20)가 거치되었을 때, PSC 거더(20)의 양 단부가 놓여 지지되는 돌출된 형태의 브래킷(14)이 형성된다. Meanwhile, in the present invention, when the PSC girder 20, which will be described later, is mounted on the upper end of the wall 10 and is described later, both ends of the PSC girder 20 are placed and supported to support the bracket. (14) is formed.

시공된 벽체(10)의 상부에는 PSC 거더(20)가 거치된다. 도 4에는 PSC 거더(20)가 거치된 상태의 개략적인 측면도가 도시되어 있다. 상부구조의 자중에 의한 하중 및 모멘트 증가를 방지하기 위하여 PSC 거더(20)는 다음과 같은 구조를 갖는 것이 바람직하다. 도 5에는 본 발명에 따른 PSC 거더(20)의 개략적인 사시도가 도시되어 있고, 도 6a에는 도 5의 선B-B에서의 단면도가 도시되어 있으며 도 6b에는 도 5의 선C-C에서의 단면도가 도시되어 있다. 장지간 라멘교량에서는 자중에 의한 모멘트의 영향이 크므로, 도면에 도시된 것처럼, PSC 거더(20)는 지간의 중간에는 상, 하부 플랜지와 웨브로 이루어진 I형 단면을 가진다. 한편, 지점부의 경우에는 자중이 증가하더라도 거더에 작용하는 모멘트가 증가되지 아니하며 단지 벽체에 대한 축력만이 증가되므로 지점부에 위치하게 되는 PSC 거더(20)의 단부는 사각형의 충실 단면을 가지도록 한다. 이와 같은 단면 구조를 가지는 PSC 거더(20)를 통하여 장지간으로 될 때 발생하게 되는 상부구조의 자중으로 인한 모멘트 증가를 최소화할 수 있게 된다. The PSC girder 20 is mounted on the top of the constructed wall 10. 4 is a schematic side view of a state in which the PSC girder 20 is mounted. In order to prevent an increase in load and moment due to the weight of the superstructure, the PSC girder 20 preferably has the following structure. FIG. 5 shows a schematic perspective view of a PSC girder 20 according to the invention, FIG. 6A shows a cross sectional view at line BB of FIG. 5 and FIG. 6B shows a cross sectional view at line CC of FIG. 5. have. In the long span ramen bridge, since the influence of the moment due to its own weight is large, as shown in the drawing, the PSC girder 20 has an I-shaped cross section consisting of an upper, a lower flange and a web in the middle of the span. On the other hand, in the case of the point portion, the moment acting on the girder does not increase even if its own weight increases, so only the axial force on the wall is increased, so that the end of the PSC girder 20 positioned at the point portion has a square faithful cross section. . Through the PSC girder 20 having such a cross-sectional structure it is possible to minimize the increase in the moment due to the self-weight of the superstructure generated when the long-term interstitial.

도 5에서 부재번호 22는 후술하는 것과 같이 지점부의 콘크리트 타설 후 추가적인 보강을 위하여 보강용 인장부재를 설치하기 위한 관통공(22)이다. In Figure 5, the member number 22 is a through-hole 22 for installing the reinforcing tension member for additional reinforcement after the concrete portion of the point as described later.

위와 같은 단면 구조를 가지는 PSC 거더(20)를 벽체(10)의 상부에 거치함에 있어서, 도 4에 도시된 것처럼 PSC 거더(20)의 단부는 벽체(10)의 브래킷(14) 위에 놓인다. 도 7에는 도 4의 원 D 부분에 대한 상세도가 도시되어 있는데, 도 7에 도시된 것처럼, 상기 PSC 거더(20)의 단부를 브래킷(14) 위에 거치함에 있어서, 브래킷(14)의 상부면과 PSC 거더(20)의 단부 하면 사이에는 탄성 패드(23)를 개재하고, 브래킷(14)의 상부면과 PSC 거더(20)의 단부 하면 사이의 다른 간격 부분에는 무수축 몰탈 등의 채움재로 이루어진 베딩층(21)을 형성하는 구성을 가지는 것이 바람직하다. 이와 같은 탄성 패드(23)와 채움재는 브래킷(14)의 상부면과 PSC 거더(20)의 단부 하면 사이에서, 상재 하중을 균등하게 분포시키는 기능을 하게 된다. In mounting the PSC girder 20 having the cross-sectional structure as above on the top of the wall 10, the end of the PSC girder 20 is placed on the bracket 14 of the wall 10, as shown in FIG. FIG. 7 shows a detail of the circle D portion of FIG. 4, as shown in FIG. 7, in mounting the end of the PSC girder 20 over the bracket 14, the top surface of the bracket 14. And an elastic pad 23 between an end surface of the PSC girder 20 and an end surface of the bracket 14, and a different material between the upper surface of the bracket 14 and the end surface of the end of the PSC girder 20. It is preferable to have a structure which forms the bedding layer 21. Such an elastic pad 23 and the filling material serve to distribute the load directly evenly between the upper surface of the bracket 14 and the lower surface of the end portion of the PSC girder 20.

위와 같이 벽체(10)의 상부에 PSC 거더(20)가 거치되면 지점부에 콘크리트(30)를 타설하여 벽체(10)의 상부와 PSC 거더(20)의 단부가 일체를 이루어 강결 구조를 형성하도록 한다. 도 8에는 위와 같이 콘크리트(30)가 타설된 상태를 보여주는 개략적인 측면도가 도시되어 있다. 도면에 도시된 것처럼, 지점부에 콘크리트(30)를 타설할 때, PSC 거더(20) 상부에 형성되는 바닥판(31)이 동시에 형성되도록 할 수도 콘크리트를 타설할 수도 있으며, 다른 방법으로는 PSC 거더(20)를 설치하고 그 상부에 바닥판(31)을 시공한 이후에, 지점부에만 콘크리트(30)를 타설하여 상부구조 즉, PSC 거더(20) 및 바닥판(31)과 벽체(10)의 상부를 강결로 연결할 수도 있다. When the PSC girder 20 is mounted on the upper portion of the wall 10 as described above, the concrete 30 is poured into the point portion so that the upper portion of the wall 10 and the end of the PSC girder 20 are integrally formed to form a rigid structure. do. 8 is a schematic side view showing a state in which the concrete 30 is poured as above. As shown in the figure, when placing the concrete 30 in the point, the bottom plate 31 formed on the PSC girder 20 may be formed at the same time or may be poured concrete, alternatively PSC After installing the girder 20 and constructing the bottom plate 31 on the upper portion thereof, the concrete 30 is placed only at the point portion so that the upper structure, that is, the PSC girder 20 and the bottom plate 31 and the wall 10 The upper part of) can also be connected by hardening.

도 9에는 도 8의 원 E 부분의 개략적인 상세도가 도시되어 있다. 도 8에 도시된 것처럼 지점부를 보강하기 위하여 철근(32)을 배치할 수 있는데, 이 경우, 벽체(10)와 상부구조의 더욱 견고한 강결을 위하여, 벽체(10) 내에 배치된 수직 철근(16)과 상기 지점부 보강 철근(32)을 커플러(17)를 이용하거나 또는 용접에 의하 여 연결하는 것도 바람직하다. 또한, PSC 거더(20) 내에 배근된 철근(23)을 돌출시켜 상기 지점부 보강 철근(32)과 용접 등의 다양한 방법으로 연결하는 것도 바람직하다. FIG. 9 is a schematic detail of the circle E portion of FIG. 8. Reinforcement 32 may be arranged to reinforce the point as shown in FIG. 8, in which case the vertical reinforcement 16 disposed in the wall 10 for a more robust rigidity of the wall 10 and the superstructure. It is also preferable to connect the reinforcing bar 32 and the point portion using a coupler 17 or by welding. In addition, it is also preferable to connect the reinforcing bars 23 arranged in the PSC girder 20 by various methods such as welding the point reinforcing bars 32.

한편, 필요한 경우, 지점부의 콘크리트가 경화된 후에, 지점부와 상기 PSC 거더(20) 단부의 관통공(22)에 보강용 인장부재(24)를 관통 설치한 후 고정하여 보강하는 것도 바람직하다. 이 때, 보강 효과를 더 증대시키기 위하여 상기 보강용 인장부재(24)를 긴장하여 긴장력을 부여할 수도 있다. On the other hand, if necessary, after the concrete of the branch portion is hardened, it is also preferable to penetrate the fixing portion 24 after the reinforcing tension member 24 is installed through the through hole 22 of the branch portion and the end of the PSC girder 20. At this time, in order to further increase the reinforcing effect, the reinforcing tension member 24 may be tensioned to impart a tension force.

위와 같이, 지점부의 콘크리트 타설과 PSC 거더(20) 상부의 바닥판(31) 설치가 완료된 후에는 도 10에 도시된 것처럼 교량에 필요한 난간(34) 등의 시설물을 설치한 후 차량 통행을 허용하면 된다. As described above, after the installation of the concrete and the bottom plate 31 of the upper portion of the PSC girder 20 is completed, as shown in FIG. do.

다음에서는 도 11에 도시된 모멘트도를 참고하여 각 시공단계에서의 모멘트 재분배 상태를 설명한다. 도 11은 동일한 제원을 가진 종래의 일반적인 라멘교량의 모멘트도와 본 발명에 따른 라멘교량의 모멘트도를 대비하여 도시한 것인데, 좌측의 모멘트도가 종래의 일반적인 라멘교량에 대한 것이고, 우측의 모멘트도는 본 발명에 대한 것이다. 또한 도 11의 (a)는 상부구조 즉, 거더와 바닥판의 자중에 의한 하중이 작용하는 상태에서의 모멘트도이고, 도 11의 (b)는 포장 등과 같은 교량 시설물에 의한 2차 고정하중과 활하중만이 작용하는 상태에서의 모멘트도이며, 도 11의 (c)는 최종적인 사용상태에서의 모멘트도이다. Next, the moment redistribution state at each construction step will be described with reference to the moment diagram illustrated in FIG. 11. FIG. 11 shows a comparison between the moment of the conventional ramen bridge having the same specification and the moment of the ramen bridge according to the present invention. The moment of the left side is for the conventional general ramen bridge. It is about the present invention. In addition, (a) of Figure 11 is a moment diagram in the state that the load due to the weight of the upper structure, that is, the girder and the bottom plate is applied, Figure 11 (b) is a secondary fixed load by the bridge facilities such as pavement It is a moment diagram in the state which only a live load acts, and FIG.11 (c) is a moment diagram in a final use state.

도 11의 (a)에서 좌측에 도시된 것처럼, 종래의 라멘교량의 경우에는 교량 상부구조의 시공을 위하여 동바리 등의 가시설을 설치하고 콘크리트를 타설한 후 콘크리트가 경화된 후 가시설을 철거하게 되므로 상부구조에 의한 하중에 의하여 지점부에도 Msn의 모멘트가 작용하게 된다. 그런데, 본 발명의 경우, 도 3에 도시된 것처럼 PSC 거더(20)의 단부가 벽체(10)의 브래킷(14) 위에 놓여 PSC 거더(20)가 벽체(10) 사이에 거치된 상태에서 바닥판을 타설하게 되면 도 11의 (a)에서 우측에 도시된 것처럼, 지점부가 굳지 않은 콘크리트가 하중에 저항하지 못하게 되므로 거더의 자중과 바닥판 하중에 대해서는 힌지와 같은 거동을 하게 된다(Msn1=0). As shown on the left side in FIG. 11 (a), in the case of the conventional ramen bridge, the construction of the upper structure of the bridge to install the temporary facility, such as a copper bar and cast concrete after the concrete is hardened and then the temporary facility is to be removed Moment of M sn acts on the point part by load by structure. However, in the case of the present invention, as shown in Figure 3, the end of the PSC girder 20 is placed on the bracket 14 of the wall 10, the bottom plate in a state where the PSC girder 20 is mounted between the walls 10 If the concrete is placed on the right side of Fig. 11 (a), the concrete that is not hardened at the point does not resist the load, so the weight of the girder and the bottom plate load are behaved like a hinge (M sn1 = 0). ).

2차 고정하중과 활하중만이 작용하는 상태에서는 종래의 라멘교량과 본 발명의 라멘교량이 동일한 모멘트를 받게 된다. 따라서 도 11의 (c)에 도시된 것처럼, 최종적인 사용상태에서의 모멘트 상태는, 도 11의 (a)에 도시된 모멘트도와 도 11의 (b)에 도시된 모멘트도를 합한 상태가 되는데, 본 발명에서의 지간 중앙부 모멘트(Mp1)는 종래의 라멘교량에서의 지간 중앙부 모멘트(Mp) 보다 더 커지게 되지만, 지점부 모멘트에 있어서는 본 발명의 지점부 모멘트(Mn1)가 종래의 라멘교량에서의 지점부 모멘트(Mn)보다 더 작아지게 된다. In the state where only the secondary fixed load and the live load act, the conventional ramen bridge and the ramen bridge of the present invention receive the same moment. Therefore, as shown in (c) of FIG. 11, the moment state in the final use state is a state in which the moment diagram shown in (a) of FIG. 11 and the moment diagram shown in (b) of FIG. In the present invention, the interstitial center moment M p1 becomes larger than the interstitial center moment M p in the conventional ramen bridge, but in the point moment, the point moment moment M n1 of the present invention is the conventional ramen. It becomes smaller than the point moment M n at the bridge.

이와 같이, 본 발명에서는 시공단계 및 구조형상을 조절하여 모멘트를 재분배함으로써, 상부구조의 자중에 의하여 발생하는 모멘트를 지간의 중앙부로 유도하여 지점부에서 벽체(10)의 상단에 작용하는 부모멘트가 최소화되고, 교량 시공 후 작용하는 포장 등에 의한 2차 고정하중과 활하중 등에 의해 발생하는 모멘트는 부모멘트가 정모멘트 보다 크게 되므로 모든 작용하중에 대한 모멘트를 합할 경우 정, 부 모멘트가 균형을 이루게 된다. As described above, in the present invention, by adjusting the construction stage and the structural shape, redistributing the moment, the parent moment acting on the upper end of the wall 10 at the point part by inducing the moment generated by the self-weight of the superstructure to the center of the trunk. The moment generated by the secondary fixed load and live load due to the pavement acting after the bridge construction is minimized, and the parent moment is greater than the positive moment, so the positive and negative moments are balanced when the moments for all the working loads are added together.

도 1은 종래의 라멘교량에 등분포 하중이 작용할 경우의 개략적인 모멘트도이다. 1 is a schematic moment diagram when a uniform distribution load is applied to a conventional ramen bridge.

도 2는 본 발명에 따른 라멘교량의 시공을 위하여 벽체를 설치한 상태를 보여주는 개략적인 측면도이다. Figure 2 is a schematic side view showing a state in which a wall is installed for the construction of the ramen bridge according to the present invention.

도 3은 도 2에서 선A-A에 따른 단면도이다. 3 is a cross-sectional view taken along the line A-A in FIG.

도 4는 본 발명에 따른 PSC 거더가 벽체 위에 거치된 상태를 보여주는 개략적인 측면도이다. 4 is a schematic side view showing a state in which the PSC girder is mounted on a wall according to the present invention.

도 5는 본 발명에 따른 PSC 거더의 개략적인 사시도이다. 5 is a schematic perspective view of a PSC girder according to the present invention.

도 6a는 도 5의 선B-B에서의 단면도이며, 도 6b는 도 5의 선C-C에서의 단면도이다. FIG. 6A is a cross sectional view taken along the line B-B of FIG. 5, and FIG. 6B is a cross sectional view taken along the line C-C of FIG.

도 7은 도 3의 원 D 부분에 대한 상세도이다. FIG. 7 is a detail of the circle D portion of FIG. 3. FIG.

도 8은 지점부에 콘크리트가 타설된 상태를 보여주는 개략적인 측면도이다. 8 is a schematic side view showing a state in which concrete is poured in the point portion.

도 9는 도 8의 원 E 부분의 개략적인 상세도이다. 9 is a schematic detail of the circle E portion of FIG. 8.

도 10은 교량에 필요한 난간 등의 시설물을 설치한 후 차량 통행이 허용된 상태에서의 본 발명에 따른 라멘교량의 개략적인 측면도이다. 10 is a schematic side view of the Ramen Bridge according to the present invention in a state in which vehicle traffic is allowed after installing facilities such as railings necessary for the bridge.

도 11은 동일한 제원을 가진 종래의 일반적인 라멘교량의 모멘트도와 본 발명에 따른 라멘교량의 모멘트도를 대비하여 도시한 것이다. FIG. 11 shows the moment diagram of a conventional general ramen bridge having the same specification as the moment diagram of the ramen bridge according to the present invention.

<도면의 주요 부분에 대한 부호의 설명> <Explanation of symbols for the main parts of the drawings>

10 ... 벽체10 ... wall

20 ... 프리스트레스트 콘크리트 거더(PSC 거더)20 ... prestressed concrete girder (PSC girder)

30 ... 지점부의 콘크리트30 ... concrete at the point

31 ... 바닥판31 ... bottom plate

Claims (10)

양측의 콘크리트 벽체(10)와, 그 사이에 설치되는 상부구조로 이루어진 라멘교량으로서, As a ramen bridge composed of concrete walls 10 on both sides, and an upper structure provided therebetween, 상기 상부구조는, 지간의 중간에서는 상, 하부 플랜지와 웨브로 이루어진 I형 단면을 가지며, 상기 상부구조와 상기 벽체(10)의 상단부가 만나는 지점부에서는 사각형의 충실 단면을 가지는 프리스트레스트 콘크리트 거더(PSC 거더)(20)와, 그 상부에 일체로 형성된 콘크리트 바닥판(31)으로 이루어지며; The superstructure has an I-shaped cross section consisting of an upper, a lower flange and a web in the middle of the span, and a prestressed concrete girder having a square faithful cross section at the point where the upper structure and the upper end of the wall 10 meet ( PSC girder) 20 and a concrete base plate 31 integrally formed thereon; 상기 콘크리트 벽체(10)의 상부에는 지간 내측으로 돌출된 브라켓(14)이 형성되어 있어, 상기 PSC 거더(20)의 단부는 상기 브라켓(14) 위에 거치되고; A bracket (14) is formed on the upper portion of the concrete wall (10) so as to protrude inwardly between the sections, and an end of the PSC girder (20) is mounted on the bracket (14); 상기 지점부에 콘크리트(30)가 일체로 타설되어 상부구조와 벽체(10)가 일체를 이루어 강결되는 구조를 가지는 것을 특징으로 하는 라멘교량.  Ramen bridge, characterized in that the concrete portion 30 is integrally poured in the point portion has a structure in which the upper structure and the wall (10) is integrally rigid. 양측의 콘크리트 벽체(10)와, 그 사이에 설치되는 상부구조로 이루어진 라멘교량으로서, As a ramen bridge composed of concrete walls 10 on both sides, and an upper structure provided therebetween, 상기 상부구조는, 지간의 중간에서는 상, 하부 플랜지와 웨브로 이루어진 I형 단면을 가지며, 상기 상부구조와 상기 벽체(10)의 상단부가 만나는 지점부에서는 사각형의 충실 단면을 가지는 프리스트레스트 콘크리트 거더(PSC 거더)(20)와, 그 상부에 일체로 형성된 콘크리트 바닥판(31)으로 이루어지며; The superstructure has an I-shaped cross section consisting of an upper, a lower flange and a web in the middle of the span, and a prestressed concrete girder having a square faithful cross section at the point where the upper structure and the upper end of the wall 10 meet ( PSC girder) 20 and a concrete base plate 31 integrally formed thereon; 상기 벽체(10)는, 그 하단 내부에 분할재(13)가 설치되어 벽체(10)의 단면이 지간 내부측(11)과 지간 외부측(12)으로 분할되어 있는 구조를 가지고 있고; The wall (10) has a structure in which a partition member (13) is provided inside the lower end thereof so that the cross section of the wall (10) is divided into the interplanar inner side (11) and the interplanar outer side (12); 상기 콘크리트 벽체(10)의 상부에는 지간 내측으로 돌출된 브라켓(14)이 형성되어 있어, 상기 PSC 거더(20)의 단부는 상기 브라켓(14) 위에 거치되며; A bracket (14) is formed on the upper side of the concrete wall (10) so as to protrude inwardly between the sections, and an end of the PSC girder (20) is mounted on the bracket (14); 상기 지점부에 콘크리트(30)가 일체로 타설되어 상부구조와 벽체(10)가 일체를 이루어 강결되는 구조를 가지는 것을 특징으로 하는 라멘교량.  Ramen bridge, characterized in that the concrete portion 30 is integrally poured in the point portion has a structure in which the upper structure and the wall (10) is integrally rigid. 제1항 또는 제2항에 있어서, The method according to claim 1 or 2, 상기 브라켓(14)의 상부면과 PSC 거더(20)의 단부 하면 사이에는 탄성 패드(23)가 개재되고, 상기 브라켓(14)의 상부면과 PSC 거더(20)의 단부 하면 사이의 다른 간격 부분에는 채움재로 이루어진 베딩층(24)이 형성되는 것을 특징으로 하는 라멘교량. An elastic pad 23 is interposed between an upper surface of the bracket 14 and an end lower surface of the PSC girder 20, and another gap portion between an upper surface of the bracket 14 and an end lower surface of the PSC girder 20. Ramen bridge, characterized in that the bedding layer (24) made of a filling material is formed. 제1항 또는 제2항에 있어서, The method according to claim 1 or 2, 상기 PSC 거더(20) 단부에는 관통공(22)이 형성되어 있고, The through hole 22 is formed at the end of the PSC girder 20, 경화된 상태의 지점부 콘크리트(30)와 상기 PSC 거더(20) 단부의 상기 관통공(22)에는 보강용 인장부재(24)가 관통 설치되어 고정되어 있는 것을 특징으로 하는 라멘교량. Ramen bridge, characterized in that the reinforcing tension member 24 is installed and fixed in the through-hole 22 of the point concrete 30 and the end of the PSC girder 20 in the hardened state. 제1항 또는 제2항에 있어서, The method according to claim 1 or 2, 상기 바닥판(31)은, 지점부의 콘크리트(30)가 타설될 때 함께 콘크리트가 타설되어 상기 PSC 거더(20)의 상부에 형성되는 것을 특징으로 하는 라멘교량. The bottom plate (31), when the concrete portion of the point portion 30 is poured with the concrete is ramen bridge, characterized in that formed on top of the PSC girder (20). 양측의 콘크리트 벽체(10)와, 그 사이에 설치되는 상부구조로 이루어진 라멘교량의 시공방법으로서, As a construction method of the ramen bridge consisting of the concrete wall 10 on both sides, and the upper structure provided therebetween, 상기 상부구조는, 지간의 중간에서는 상, 하부 플랜지와 웨브로 이루어진 I형 단면을 가지며, 상기 상부구조와 상기 벽체(10)의 상단부가 만나는 지점부에서는 사각형의 충실 단면을 가지는 프리스트레스트 콘크리트 거더(PSC 거더)(20)와, 그 상부에 일체로 형성된 콘크리트 바닥판(31)으로 이루어지며; The superstructure has an I-shaped cross section consisting of an upper, a lower flange and a web in the middle of the span, and a prestressed concrete girder having a square faithful cross section at the point where the upper structure and the upper end of the wall 10 meet ( PSC girder) 20 and a concrete base plate 31 integrally formed thereon; 상기 콘크리트 벽체(10)의 상부에 지간 내측으로 돌출된 브라켓(14)을 형성한 상태로 상기 콘크리트 벽체(10)를 시공하는 단계; Constructing the concrete wall (10) in a state in which a bracket (14) protruding inward to the interior of the concrete wall (10) is formed; 상기 PSC 거더(20)를 인양하여 상기 PSC 거더(20)의 단부가 상기 브라켓(14) 위에 놓이도록 상기 PSC 거더(20)를 상기 양측 벽체(10) 사이에 거치하는 단계; 및 Lifting the PSC girder (20) to mount the PSC girder (20) between the two side walls (10) such that the end of the PSC girder (20) rests on the bracket (14); And 상기 상부구조와 벽체(10)가 일체를 이루어 강결되는 구조를 가지도록 상기 지점부에 콘크리트(30)를 일체로 타설하는 단계를 포함하는 것을 특징으로 하는 라멘교량의 시공방법.The method of constructing a ramen bridge comprising the step of integrally pouring concrete 30 to the point portion to have a structure in which the upper structure and the wall 10 are integrally rigid. 제6항에 있어서, The method of claim 6, 상기 벽체(10)를 시공하는 단계에서는 벽체(10)의 단면이 지간 내부측(11)과 지간 외부측(12)으로 분할되도록, 벽체(10)의 하단 내부에 분할재(13)를 설치하는 것을 특징으로 하는 라멘교량의 시공방법.In the step of constructing the wall 10, the partition member 13 is installed inside the lower end of the wall 10 so that the cross section of the wall 10 is divided into the inner side 11 and the outer side 12 between the stems. Construction method of the ramen bridge, characterized in that. 제6항 또는 제7항에 있어서, The method according to claim 6 or 7, 상기 PSC 거더(20)를 상기 양측 벽체(10) 사이에 거치하는 단계에서, In the step of mounting the PSC girder 20 between the two walls 10, 상기 브라켓(14)의 상부면과 PSC 거더(20)의 단부 하면 사이에는 탄성 패드(23)를 설치한 상태에서 PSC 거더(20)의 단부를 상기 브라켓(14) 위에 놓으며; Placing an end of the PSC girder (20) on the bracket (14) with an elastic pad (23) installed between an upper surface of the bracket (14) and an end lower surface of the PSC girder (20); 상기 브라켓(14)의 상부면과 PSC 거더(20)의 단부 하면 사이의 다른 간격 부분에는 채움재를 채워 베딩층(24)을 형성하는 것을 특징으로 하는 라멘교량의 시공방법. The method of constructing a ramen bridge, characterized in that the bedding layer (24) is formed by filling a filler in another gap between the upper surface of the bracket (14) and the lower surface of the end portion of the PSC girder (20). 제6항 또는 제7항에 있어서, The method according to claim 6 or 7, 상기 PSC 거더(20) 단부에는 관통공(22)을 형성하고; A through hole (22) is formed at an end of the PSC girder (20); 지점부의 콘크리트(30)를 타설한 후, 상기 콘크리트(30)가 경화되면 보강용 인장부재(24)를 상기 콘크리트(30)와 PSC 거더(20) 단부의 상기 관통공(22)을 관통하도록 설치하여 고정하는 것을 특징으로 하는 라멘교량의 시공방법.After pouring the concrete 30 of the point portion, when the concrete 30 is hardened, a reinforcing tension member 24 is installed to pass through the through hole 22 at the end of the concrete 30 and the PSC girder 20. Construction method of the ramen bridge characterized in that the fixing. 제6항 또는 제7항에 있어서, The method according to claim 6 or 7, 지점부의 콘크리트(30)를 타설할 때, 상기 PSC 거더(20)의 상부에 바닥판(31)을 일체로 형성되도록 콘크리트를 타설하여 상기 바닥판(31)을 시공하는 것을 특징으로 하는 라멘교량의 시공방법.When pouring the concrete 30 of the point portion, the floor plate 31 is constructed by pouring concrete so that the bottom plate 31 is integrally formed on the upper portion of the PSC girder 20 of the ramen bridge. Construction method.
KR1020070087885A 2007-08-30 2007-08-30 Long Span PSC Girder Type Rahmen Bridge and its Construction Method Using Moment Re-distribution KR100946716B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070087885A KR100946716B1 (en) 2007-08-30 2007-08-30 Long Span PSC Girder Type Rahmen Bridge and its Construction Method Using Moment Re-distribution

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070087885A KR100946716B1 (en) 2007-08-30 2007-08-30 Long Span PSC Girder Type Rahmen Bridge and its Construction Method Using Moment Re-distribution

Publications (2)

Publication Number Publication Date
KR20090022502A true KR20090022502A (en) 2009-03-04
KR100946716B1 KR100946716B1 (en) 2010-03-12

Family

ID=40692367

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070087885A KR100946716B1 (en) 2007-08-30 2007-08-30 Long Span PSC Girder Type Rahmen Bridge and its Construction Method Using Moment Re-distribution

Country Status (1)

Country Link
KR (1) KR100946716B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284097A (en) * 2016-09-28 2017-01-04 中铁六局集团有限公司 The installation method of pier K support on a kind of tubular arch bridge arch
KR102144400B1 (en) * 2020-02-05 2020-08-13 주식회사 신원알피씨 Psc girder for precast slab and construction method thereof
KR20220120346A (en) * 2021-02-23 2022-08-30 (주)세한테크 Gap prevention structure

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100975124B1 (en) 2010-05-20 2010-08-11 (주)홍지디씨에스 Connection method for lateral beam and column member of rahmen typed underground tunnel
KR102071148B1 (en) * 2018-12-19 2020-03-02 (주)피티씨 I-type Prestressed Concrete Girder, Rahmen Bridge using thereof and Construction method for thereof
KR102226723B1 (en) 2020-08-06 2021-03-10 이재성 Constructing method for bridge structure based on principle of action/reaction and bridge structure constructed by the method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100548911B1 (en) * 2003-04-03 2006-02-02 주식회사 용마엔지니어링 bridge and construction process with integral pier-type mixed abutment
KR100543969B1 (en) 2003-12-05 2006-01-20 (주)스틸엔콘크리트 Composite rigid-frame bridge installing prestressed compound beam to the contral point of the slab of rigid-frame bridge and connecting the beam to the steel member installed in the upper of pole, and construction method thereof
KR100694805B1 (en) * 2004-09-25 2007-03-13 아주대학교산학협력단 Hollow prestressed concrete HPC girder and spliced hollow prestressed concrete girder s-HPC bridge construction method
KR100742206B1 (en) 2006-10-25 2007-07-25 (주)한맥기술 Steel-concrete composite rahmen bridge and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284097A (en) * 2016-09-28 2017-01-04 中铁六局集团有限公司 The installation method of pier K support on a kind of tubular arch bridge arch
KR102144400B1 (en) * 2020-02-05 2020-08-13 주식회사 신원알피씨 Psc girder for precast slab and construction method thereof
KR20220120346A (en) * 2021-02-23 2022-08-30 (주)세한테크 Gap prevention structure

Also Published As

Publication number Publication date
KR100946716B1 (en) 2010-03-12

Similar Documents

Publication Publication Date Title
KR100742206B1 (en) Steel-concrete composite rahmen bridge and construction method thereof
KR100946716B1 (en) Long Span PSC Girder Type Rahmen Bridge and its Construction Method Using Moment Re-distribution
KR101012759B1 (en) Box Girder Having Hybrid Cantilever and Bridge Using Such Box Girder
KR100349864B1 (en) The Structural Continuity Method for Prestreseed Concrete Bridge of Composite I-Beam
KR20130036890A (en) Tied arched p.s.c girder for bridge and construction method for bridge by it
JP3844743B2 (en) Box girder bridge structure and its construction method
KR101135634B1 (en) Rahmen bridge construction method using hinge joint in support parts and rigid joint in rahmen conner parts
KR101097273B1 (en) Through bridge using arch reinfocing member and construction method therefor
KR100974305B1 (en) Continuous beam bridge construction method using girder for multi-span
KR101165572B1 (en) Middle span plate girder bridge and construction method thereof
JP3737475B2 (en) Box girder bridge structure and construction method
KR100785634B1 (en) Continuation structure of prestressed concrete composite beam bridge and method thereof
KR200342287Y1 (en) A structure of prestressed preflex steel composite beam prestressed by each construction steps
KR20040017772A (en) Method for construction of steel-pc-synthesized bridge
KR101607485B1 (en) Curved-psc girder with outrigger and curved-psc girder bridge construction method therewith
JP3847604B2 (en) Floor slab replacement method
KR101043710B1 (en) Through bridge construction method by side beam and slab by box structure without lateral prestressing
KR19990068519A (en) The Continuity Method for Prestreseed Concrete Bridge of Composite U-Type Girder
KR20040012496A (en) Method for construction of steel-pc-synthesized bridge
KR101751724B1 (en) Concrete structure constructed integral abutment bridge having shallow height psc i girder due to moment redistribution through control of member stiffness
KR20080105588A (en) The assembly type hollow slab
KR100724739B1 (en) Construction method of PSC Girder bridge using Retensionable and Detensionable anchorage with unbonded tendon
KR100558089B1 (en) Apparatus for repairing and reinforcing box-typed concrete structures by increasing the section of concrete structures, and repairing and reinforcing method using the apparatus
KR100669860B1 (en) Asymmetry Pretensioning Precast Beam Girder- APP Beam Girder
KR20150083446A (en) Construction methods for bridges of rahmen types by using precast P.S girder and steel box girder

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130227

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140303

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20150302

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20160401

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170303

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20180125

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20190227

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20200129

Year of fee payment: 11