KR20130036890A - Tied arched p.s.c girder for bridge and construction method for bridge by it - Google Patents
Tied arched p.s.c girder for bridge and construction method for bridge by it Download PDFInfo
- Publication number
- KR20130036890A KR20130036890A KR1020110101104A KR20110101104A KR20130036890A KR 20130036890 A KR20130036890 A KR 20130036890A KR 1020110101104 A KR1020110101104 A KR 1020110101104A KR 20110101104 A KR20110101104 A KR 20110101104A KR 20130036890 A KR20130036890 A KR 20130036890A
- Authority
- KR
- South Korea
- Prior art keywords
- girder
- construction
- bridge
- tension
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
- E01D19/125—Grating or flooring for bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/02—Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
본발명은 PSC거더의 전 지간 내지 적어도 지점부로부터 일정한 구간까지 지상에서 제작되는 제작거더(1,100)의 복부 높이(W1)가 최종 교량 완성후의 복부높이(W3)보다 작은 소정의 높이로 형성되고, 거더의 하부플랜지(3)의 하면의 종방향 형상을 아치형상으로 제작함으로서 ┴형단면(22)이 포함된 아치형 거더를 구비하며, 상기 아치형 하부플랜지(3) 하면 아래에 노출된 상태로 직선 배치되며 거더의 양 단부의 정착구(5)에서 지지되는 외부 케이블(4)을 설치함으로서,
이른바 ┴형단면을 가지는 타이드 아치형 PSC거더(1,100)를 구현하는 것과
상기 아치형 PSC거더를 크레인으로 가설한후 타이드 아치 거더로 지지된 상태에서 추가 시공분(AH)을 안전하게 소정의 블록(23)단위로 시공하는 단계별 시공을 함으로서,
크레인 거치전의 거더 자중은 최소로 하고 교대 또는 교각의 양 지점(16)상에 거더를 거치한 후에는 아치구조로 인해 내하력의 증가가 가능한 시공방법에 관한 것이다.
타이드 아치교, PSC거더, 캔킬레버공법
In the present invention, the abdominal height (W1) of the production girder (1,100) produced on the ground from the entire area to at least a point portion of the PSC girder is formed at a predetermined height smaller than the abdominal height (W3) after the completion of the final bridge, By arranging the longitudinal shape of the lower surface of the lower flange 3 of the girder in the shape of an arch, the arched girder includes a curved cross section 22, and is disposed in a straight line in the exposed state below the lower surface of the arched lower flange 3. And by installing an external cable 4 supported at the fixing holes 5 at both ends of the girder,
Implementing a so-called tide arched PSC girder (1,100)
By constructing the arched PSC girder with a crane and then carrying out the step-by-step construction to safely construct additional construction parts (AH) in predetermined block units in a state supported by the tide arch girder,
It is related to a construction method that can increase the load capacity due to the arch structure after mounting the girders on both points 16 of the alternating or pier to minimize the weight of the girder before mounting the crane.
Tide arch bridge, PSC girder, cantilever method
Description
본발명은 제작장에서 PSC거더를 제작(1,100)한후 크레인으로 들어올려 가설 위치의 두 지점(16)상에 거더를 거치한후 거치된 거더가 추가 시공분(AH)에 해당하는 하중을 지지토록 하는 거더교에 관한것으로서,In the present invention, after manufacturing (1,100) the PSC girder in the workshop, lift it with a crane and mount the girder on two
상기 크레인으로 들어올리는 제작거더의 자중을 최소화하기 위해 I형 단면을 기준으로 볼 때,When viewed based on the I-shaped cross section to minimize the weight of the production girder lifted by the crane,
상부플랜지(17)와 복부(2) 상면부(W2)가 생략되어 하부플랜지(3)와 복부 하면부(2)로 구성된 형태인 ┻형 단면(22)이,The
적어도 지점부(15)로부터 일정한 구간까지 설치되는 것 내지는 거더 전 지간에 걸쳐 설치되며,It is installed over at least one point from the
종방향으로는 하부플랜지(3) 하면의 형상이 아치형상으로 제작되며 하부플랜지 하면 아래에는 거더 양단부(5,11)에 지지되며 직선 배치되는 외부 케이블(4)에 의해 양단부에서 지지된 아치형 제작거더(1,100)에 관한 것으로서,In the longitudinal direction, the shape of the
상기 제작된 거더를 크레인으로 가설위치로 거치후 일반적인 단순구조 상태로 추가 시공하중을 지지하는 형식이 아닌,After mounting the girder to the construction position by a crane is not a type to support the additional construction load in a general simple structure state,
아치구조인 상태로 지지하게 함으로서 추가 하중에 대한 내하력을 증가시킬수 있고 수개의 블록단위로 나누어 단계별로 시공하며 각 시공단계마다 설치된 긴장재(13,8)를 긴장함으로서,By supporting in an arched state, the load capacity for additional load can be increased, and divided into several block units to construct step by step, and by tensioning the
제작거더의 하부에 설치된 외부 케이블(4)의 장력증가를 제어할수 있으며 종국에는 장력의 제거가 가능하게 하는 새로운 형식의 거더교량이다.It is a new type girder bridge that can control the increase in tension of the external cable (4) installed in the lower part of the manufacturing girder, and in the end it is possible to remove the tension.
도8은 양 단부(11)가 하현재(18)로 구속된 종래의 타이드 아치교이며 일반적으로 하현재가 교량 바닥판에 해당된다. 구조적으로는 아치거더(19)는 압축력이, 하현재는 인장력이 발생한다.8 is a conventional tide arch bridge with both
도6은 종래의 PSC-I 거더교로서 크레인 공법으로 가설하여 시공성은 좋으나 상기 아치 구조보다는 내하력이 작아 장지간의 가설에 제약을 받으며 또한 장지간 가설시 거더 자중이 커져 크레인 가설기계 용량이 커지게 된다. 또한 하면의 종방향 형상이 아치형상인 거더 형식도 종래의 PSC거더교와 동일한 단순구조 형식이 된다.Figure 6 is a conventional PSC-I girder bridge is constructed by the crane construction method is good construction work, but the load capacity is less than the arch structure is limited to the construction between the long jijanggi also increases the capacity of the crane construction machine because the girder self-weight is increased during the inter-janggae construction. In addition, the girder type in which the longitudinal shape of the lower surface is arcuate becomes the simple structure type similar to the conventional PSC girder bridge.
도9는 종래 통상적으로 시행되는 캔틸레버 가설공법으로서 별도의 가설작업차(20)가 필요하며 현장타설로 인해 시공속도가 매우 느려 공기가 많이 소요되는 형식이다.Figure 9 is a conventional cantilever temporary installation method is required a separate
이 형식의 장점은 지점부(15)로부터 중앙부를 향하여 한 블록(23)씩 균형을 맞추어 시공하며 지점부(16)에 발생하는 큰 시공중 응력을 매 단계마다 설치된 긴장재(13)를 긴장하여 응력의 제어가 가능함으로서 도10과 같은 대단면을 시공할수 있으며 따라서 장지간의 시공이 가능한 시공방법이 된다.The advantage of this type is that by constructing each
이에 장지간으로 건설되는 거더 형식의 교량 건설 비용을 줄이기 위해서는 크레인 공법이 효과적인데,In order to reduce the cost of constructing the girder type bridge which is constructed in the long span, the crane method is effective.
크레인으로 장지간의 교량 형식을 가설하기 위해서는 제작장에서 제작되는 거더의 자중을 줄여야 하며,In order to construct a bridge type between cranes and cranes, it is necessary to reduce the weight of the girder manufactured in the workshop.
또한 크레인으로 들어올려 거치시킨후 추가 시공분(AH)에 해당되는 하중에 대한 충분한 내력을 확보하는 구조 형식이 필요하게 된다.In addition, it is necessary to have a structural form to secure a sufficient strength for the load corresponding to the additional construction (AH) after lifting by the crane.
따라서 크레인 가설이 가능한 PSC거더교와 하중에 대한 내하력이 우수한 아치구조의 장점을 가지면서 단계별 시공으로 대단면의 시공을 가능하게 하여 장지간 교량 건설이 가능한 캔틸레버공법을 결합시킨 새로운 형식의 교량 가설공법이 요구된다.Therefore, PSC girder bridge, which can be used for crane construction, and arch structure with excellent load-bearing capacity, and a new type of bridge construction method that combines cantilever method that enables construction of long section bridges by allowing construction of large sections through step-by-step construction Required.
상기 크레인으로 들어올리는 제작거더의 자중을 최소화하기 위해 I형 단면을 기준으로 볼 때When viewed based on the I-shaped cross section to minimize the weight of the production girder lifted by the crane
상부플랜지(17,SL)와 복부 상면부(W2)가 생략되어 하부플랜지(3)와 복부 하면부(W1)로 구성된 형태인 ┴형 단면(22)이 적어도 지점부(15)로부터 일정한 구간까지 설치되는 것 내지는 거더 전 지간에 걸쳐 설치되며,The
또한 거더 제작시 ┻형 단면의 복부(2) 위로 수직철근(9)과 수평철근(10)을 노출시켜 거더 거치후에 추가 복부철근의 조립을 생략하게 한다.In addition, when manufacturing the girder to expose the vertical reinforcement (9) and the horizontal reinforcement (10) over the abdomen (2) of the X-shaped cross-section to omit the assembly of additional abdominal reinforcement after the girder.
종방향으로는 하부플랜지(3) 하면의 형상이 아치형상으로 제작되며,In the longitudinal direction, the shape of the bottom of the lower flange (3) is made in the shape of an arch,
상기 거더 양 단부에 구멍(6)이 형성된 케이블 정착구(5)가 구비되며,
하부플랜지(3) 하면 아래에는 거더 양 단부(11)에 구비된 정착구(5)의 구멍을 관통해서 지지되고 직선 배치된 외부케이블(4)이 설치되어, 케이블(4)로 양 단부에서 지지된 아치형상으로 제작되며,Under the
제작된 거더(1,100)를 크레인으로 들어올려 가설되는 두 개의 지점(16)상에 거치한 후에After mounting the fabricated girders (1,100) on the two points (16) to be lifted by a crane
상기 타이드 아치형 제작 거더(1,100)가 추가 시공분(AH)에 대한 지지 거더의 역할을 하는 상태에서 제작거더의 상면에 제작거더(1,100)와 일체로 복부 콘크리트(W2) 및 상부 슬래브(SL,12)를 수 개의 블록(23)으로 나누어 블록 단위의 단계별로 타설하되,Abdominal concrete (W2) and upper slab (SL, 12) integrally with the production girder (1,100) on the top surface of the production girder in the state that the tide arched manufacturing girder (1,100) serves as a support girder for the additional construction (AH) ) Into several blocks (23) to pour step by step,
교각부의 지점부(15)로부터 지간 중앙부를 향하여 좌,우 양 쪽으로 균형이 맞도록 동시에 시공하는 것 내지는 좌우 교대로 시공하며,From the
나중에 친 콘크리트블록에 의해 먼저 친 콘크리트 블록의 상부슬래브(12)에서 발생하는 인장응력 및 제작거더의 하면(3)에 발생하는 인장응력을 제거하는 것 내지,Later to remove the tensile stress generated in the
외부 케이블(4)의 장력을 제거할 목적으로 설치되며,Installed to remove the tension of the external cable (4),
상기 소정의 블록단위로 타설된 상부 슬래브(12)의 내부에 배치된 쉬스관에 내삽되어 있는 긴장재(13)를 콘크리트 양생후에 시공이음된 단부(24)에서 긴장후 정착하거나,After tensioning the
제작거더의 하부플랜지(3)에 구비되어 있는 긴장재(8)를 긴장후 정착함으로서By tensioning and fixing the
제작거더의 하부에 설치된 외부 케이블(4)의 장력증가를 제어할수 있으며The tension increase of the external cable (4) installed in the lower part of the manufacturing girder can be controlled
종국에는 긴장재(13,8)에 더 큰 긴장력을 도입하여 케이블(4) 제거가 가능하게 된다.Eventually, a greater tension is introduced into the
이렇게 함으로서 최종 교량의 종방향 형상이 하부플랜지(3)가 아치형상으로, 지점부(15)의 단면 높이가 높고 중앙부가 작은 변단면 형식의 장지간 교량이 구현될수 있다.In this way, the longitudinal shape of the final bridge is the lower flange (3) is arcuate, long cross-section bridge of the long cross-section type of the high cross-section height of the
본 발명으로 구현된 교량의 중간지점부(15)의 하면은 일반적으로 큰 압축응력이 걸리므로 이를 대처하기 위해,In order to cope with the lower surface of the
종방향으로 2경간 이상이며, 횡방향으로 2개이상으로 거더(1,100)가 배열된후 각각의 거더의 하부플랜지(3)를 소정의 두께로 연결 타설하여 교량 하부(14)가 폐합된 단면을 구성하며 상기 폐합된 단면의 구간이 전 지간 내지 적어도 중간지점부(15)로부터 지간의 1/4 이하로 설치되는 것을 특징으로 하는 것을 포함한다.After the two girders (1,100) are arranged in the longitudinal direction and two or more in the transverse direction, the lower flange (3) of each girder is connected to a predetermined thickness, and the end surface of the
거더 단면상에서 복부 상면부(W2)와 상부플랜지(12,SL)의 생략으로 인해 제작거더(1,100)의 중량을 감소시켜 장지간의 교량 건설에 크레인 공법을 적용할수 있으며,Due to the omission of the upper part of the upper part (W2) and the upper flanges (12, SL) on the girder cross-section can reduce the weight of the manufacturing girder (1,100) can be applied to the crane construction method in the bridge construction between the long,
양 단부(11)에서 지지되며 거더의 하부에 외부로 노출된 케이블(4)을 설치하 여 아치구조 형식으로 안전하게 추가 가설하중(AH)을 지지할수 있게 되고 또한By installing the cable 4 which is supported at both
캔틸레버 공법과 같은 블록 단위의 단계별 타설과 매 단계마다 설치된 긴장재(13,8)에 긴장력을 도입함으로서 각 단계의 콘크리트 타설하중에 의한 제작거더(1,100)의 하부 케이블(4)에 증가되는 장력을 긴장재(13,8)로의 전이를 용이하게 한다.By applying tension to block tensions (13, 8) installed in each block and the step of concrete placing, such as the cantilever method, tension is increased in the lower cable (4) of the production girder (1,100) by the concrete placing loads in each stage. Facilitates the transition to (13,8).
즉 임의의 시공단계 동안 제작거더의 응력증가는 그 임의의 시공단계에 타설되는 하중만큼 발생하게 되고 콘크리트가 양생이 된후 그 단계에 배치된 긴장재(13)에 긴장력을 도입하여 제작거더에 걸린 응력증가를 소거하게 되어 결국 제작거더의 내력은 모든 시공단계를 걸쳐 하나의 시공단계에 해당하는 블록하중만을 지지할수 있으면 충분하게 되므로 제작거더의 강성이 대단히 클 필요는 없으면서 캔틸레버 공법이 가지는 장점을 그대로 가질수가 있다.In other words, the increase in the stress of the production girder during any construction stage is generated by the load placed in the construction stage, and after the concrete is cured, the stress applied to the fabrication girder is introduced by introducing tension force to the
즉 장지간의 교량 가설이 가능해진다. 무엇보다도 별도의 상부 가설용 작업차(20)가 필요없고 공기가 대폭 단축된다.In other words, it is possible to construct a bridge between the long sections. Above all, there is no need for a separate upper
도6과 도7은 통상의 PSC거더교의 종단면도와 횡단면도이다. 보통 제작시의 제작빔의 구성은 상부플랜지(17)와 복부(2) 및 하부플랜지(3)로 구성되며 I형 단면이 많이 사용된다. 이때 상부플랜지(17)와 하부플랜지(3)는 수평을 유지하게 된다.6 and 7 are longitudinal cross-sectional views of a conventional PSC girder bridge. In general, the fabrication beam is composed of an
근래에는 미관을 고려해서 하부플랜지(3)의 하면형상이 아치형상인 경우도 사용되는 경우가 있는데 이때에도 상부플랜지(17)는 수평을 유지하고 있고 구조적으로도 일반적인 PSC거더교와 동일한 단순구조로 거동한다.Recently, in consideration of aesthetics, the lower surface of the
도8은 양단이 하현재로 구속된 타이드 아치구조이다.8 is a tide arch structure in which both ends are constrained to the lower chord.
통상적인 교량 형식에 비교하여 본 발명의 특징을 설명하기로 한다.Features of the present invention will be described in comparison to conventional bridge formats.
본발명은 가설시의 구조형식에 대한 사항이며 교량 완공후에는 일반적인 거더교와 동일한 거동을 하게 된다. 즉 가설시의 구조 형식이 통상의 PSC거더교와 타이드 아치구조 형식을 결합시킨 형태로 가설하게 된다.The present invention is about the structural form at the time of construction, and after completion of the bridge, it will behave like the general girder bridge. In other words, the construction form at the time of construction is hypothesized to combine ordinary PSC girder bridge and tide arch structure form.
더욱더 상세히 설명하면 제작거더(1,100)의In more detail, the manufacturing girder (1,100)
형상이 거더 길이방향으로 볼 때 하부플랜지(3)의 하면형상이 중앙부의 ELEVATION(높이)이 높고 지점부가 낮은 아치 형상으로 이루어지며 거더 양 단부(11)에 구비된 정착부(5)에서 지지되고 거더 하부플랜지(3) 아래로 노출된채 수평 배치된 외부케이블(4)에 의해 보강된 구조이다When the shape is viewed in the longitudinal direction of the girder, the lower surface of the
또한 통상의 PSC거더교와는 달리 복부를 거더 제작시와 거더 거치후로 두 번 타설하는 형식으로 이는 하부플랜지(3)만을 아치형상으로 하는 형식과 구별되는데 하부플랜지만을 아치형상으로 하는 형식은 동일한 조건에서 지점부(15) 자중 증가로 인해 거더 중량이 너무 커지게 된다.In addition, unlike ordinary PSC girder bridge, the abdomen is cast twice when manufacturing the girder and after the girder is mounted. This is distinguished from the type in which only the
따라서 본 발명의 특징중 하나는 PSC거더의 전 지간 내지 적어도 지점부(15)로부터 일정한 구간까지 지상에서 제작되는 제작거더(1,100)의 복부 높이(W1)가 최종 교량 완성후의 복부높이(W3)보다 작은 소정의 높이로 형성되어 ┴형단면(22)이 포함된 아치형 거더가 구비된다는 것이다.Therefore, one of the features of the present invention is that the abdominal height (W1) of the production girder (1,100) produced on the ground from the entire length of the PSC girder to at least a certain section from the
따라서 거더의 하부플랜지(3)의 하면의 종방향 형상을 아치형상으로 제작하고, 상기 아치형 하부플랜지(3) 하면 아래에 노출된 상태로 직선 배치되며 거더의 양 단부의 정착구(5)에서 지지되는 외부 케이블(4)을 설치함으로서, 이른바 ┴형단면(22)을 가지는 타이드 아치형 PSC거더(1,100)를 구현하는 것이다.Therefore, the longitudinal shape of the lower surface of the lower flange (3) of the girder is formed in an arc shape, and is arranged in a straight line exposed under the lower surface of the arcuate lower flange (3) and supported by the fixing holes (5) at both ends of the girder. By installing the external cable 4, a tide arched PSC girder 1,100 having a so-called
상기 ┻형단면(22)의 설치 구간은 거더 전 길이에 걸쳐 설치되거나, 적어도 양 지점부(15)로부터 지간의 15%이상 설치된다. 한편 거더의 복부를 제작시와 거치후에 2번에 걸쳐 분할시공하는 중요한 이유는 거더 지점부의 자중을 감소시키는 것 이외에도 2경간 이상의 교량의 시공시The installation section of the
통상의 거더교의 중간지점부(15)의 연결보다도 연속된 거더의 연결을 확실히 할 수 있다. 생략된 복부(W2)와 상부플랜지(17,SL)만큼 연결 타설되는 공간이 많기 때문이다.The connection of the continuous girder can be assured more than the connection of the
그리고 더욱더 중요한 것은 중간지점부(15)로부터 거더 중앙부로 소정의 블록단위로 시공을 나누어 시공하는 단계별시공을 가능하게 함으로서 거더 거치후의 타설하중(AH)에 대한 제작거더(1,100)의 부담하중을 중간지점부(15)의 단면으로 전이 시킬수 있다.And more importantly, the construction of the construction girders (1,100) against the pour load (AH) after the girder through the construction by enabling the step-by-step construction by dividing the construction by a predetermined block unit from the
이것은 각 단계의 상부슬래브(12)에 긴장재(13)를 구비하고 양생후 긴장력을 도입함으로서 실현된다.This is realized by providing a
이것을 좀 더 상세히 기술하면 다음과 같다.This is described in more detail as follows.
복부(W2) 및 상부플랜지(17)가 생략된 ┴형단면(22)이며 종방향으로 아치형상이고 양단이 케이블(4)로 지지된 타이드 아치 PSC거더(1,100)가 제작되고 크레인으로 인양후 가설장소의 두지점(16)상에 거치된다. 이 과정을 반복하여 2경간 이상에 걸쳐 연속되게 거치한후 중간지점부(16)부터 거치이후에 추가로 시공해야할 추 가시공분(AH)이 시공된다.Tide arch PSC girder (1,100) with an abdominal shape (W2) and an upper flange (17) omitted, an arcuate shape in the longitudinal direction, and both ends supported by a cable (4), and then lifted by a crane It is mounted on two
즉 상기 추가시공분(AH)에 대해서 상기 아치형 제작거더(1,100)가 추가되는 하중만큼 처지게 된다. 이때 거더 구조상태는 단순구조가 아닌 아치 구조로 거동하며 응력증가의 대부분은 콘크리트 거더 단면부(22)가 아닌 하부에 배치되어 있는 케이블(4)에 장력증가로 형태로 발생된다. 중간지점부(15) 블록의 시공시 상부슬래브(12) 내부에 긴장재(13)를 배치하며 블록(23)이 양생된후에 긴장재(13)에 진장력을 도입하게 된다.In other words, the arc-shaped manufacturing girder (1,100) is sagging by the additional load for the additional construction (AH). At this time, the girder structural state behaves as an arch structure rather than a simple structure, and most of the stress increase occurs in the form of an increase in tension in the cable 4 disposed below the concrete
그러면 구조계는 이미 중간지점부(15)가 연결되었기 때문에 연속구조가 되며 중간지점부의 상부슬래브(12) 내에 도입된 긴장력에 의해 제작거더(1,100)에 솟음을 유발한다. 즉 각 단계의 타설되는 콘크리트 블록(23)자중에 의해 발생하는 제작거더(1,100)의 처짐을 현장타설되는 상부슬래브(12)내에 배치된 긴장재(13)에 긴장력을 도입하여 제어할수 있다.Then, the structural system is a continuous structure because the
또한 제작시에 미리 제작거더의 하부플랜지(3)내에 설치해둔 긴장재(8)에 긴장력을 도입함으로도 제어할수 있다.In addition, it can also be controlled by introducing a tension force to the tension member (8) installed in the lower flange (3) of the production girder in advance.
여기에 더해서 처짐보다 더 큰 솟음량에 해당하는 긴장력을 도입하면 제작거더(1,100)의 케이블(4) 초기장력을 제거할수 있게 되어 최종 교량 완성후에는 케이블(4)의 제거가 가능하다.In addition to this, when the tension corresponding to the amount of rise greater than the deflection is introduced, the initial tension of the cable 4 of the production girder 1,100 can be removed, and the cable 4 can be removed after the final bridge is completed.
물론 가설위치에 따라 교량 하부공간이 제약이 없다면 교량 완성후에도 케이블(4)이 존치될수 있으며 본 발명의 기술적 범위가 교량 완성후에 케이블이 존치되는 경우와 제거되는 경우 모두를 포함하고 있다.Of course, if there is no restriction in the bridge lower space according to the construction position, the cable (4) can exist even after the completion of the bridge and the technical scope of the present invention includes both the case of the cable is present and removed after completion of the bridge.
상기의 예는 연속교량의 경우이며 지간이 하나인 단순교량에서도 마찬가지이다.The above example is the case of a continuous bridge, and the same is true of a simple bridge having one span.
즉, 단순교량일 경우에도 연속교량에서와 마찬가지로 타이드 아치형 제작거더(1,100)가 추가하중에 대해 아치구조로 가설중의 하중을 지지하게 되며, 양 지점부(16)로부터 중앙부쪽을 향하여 수개의 블록(23)단위로 나누어 시공할수 있으며, 각 단계의 콘크리트 블록자중에 의해 제작거더(1,100)에 처짐이 발생하게 된다.That is, even in the case of a simple bridge, as in the continuous bridge, the tide arch-shaped manufacturing girder (1,100) supports the load under construction in an arch structure for additional load, and several blocks from both
이때 상기 처짐은 제작시에 미리 제작거더의 하부플랜지(3)내에 설치해둔 긴장재(8)에 긴장력을 도입하여 제어가 가능하다.At this time, the deflection can be controlled by introducing a tension force to the
일반적으로 PSC거더교량의 형식은 크레인으로 가설하여 시공성이 좋으며, 특히 공기면에서 타시공법(예로 현장타설 캔틸레버 시공법, 동바리공법등)에 비해 유리하다.In general, PSC girder bridges are constructed with cranes and have good constructional properties, and are particularly advantageous in terms of air compared with other construction methods (for example, field-casting cantilever construction, copper-barrier construction, etc.).
반면, 거더 중량의 과대, 중간지점부의 완전한 연속성 부족)등에 의해 최대 가능지간이 제약을 받아 왔다. 본 발명으로 구현된 교량은 궁극적으로 캔틸레버 현장타설공법을 대체하기 위한 것을 최대목적으로 가지고 있다.On the other hand, the maximum possible space has been limited by excessive girder weight and lack of complete continuity at the mid-point. The bridge embodied by the present invention ultimately has a purpose to replace the cantilever on-site casting method.
즉 켄틸레버 공법은 일반적으로 중간지점부(15)로부터 지간 중앙부쪽으로 한 블록(23)씩 균형을 맞추면서 시공해나가는데 이때 한개의 블록의 길이가 4M정도로 매우 작다. 그러므로 전 지간을 시공하기 위해서는 너무나도 많은 시간이 소요되며 별도의 가설용 작업차(20)가 필요하다. 물론 단면이 하부플랜지가 폐합된 폐단면으로 구성되어지고 단면 자체가 대단면이 된다.In other words, the cantilever method is generally constructed by balancing one block (23) from the middle point portion (15) toward the center portion of the trunk, and the length of one block is very small, such as 4M. Therefore, it takes too much time to construct the whole space and requires a separate
이에 본 발명은 복부(W2)와 상부플랜지(17)가 생략되어 충분히 크레인 공법 으로 제작거더(1,100)를 한번에 들어올릴 수 있고 또한 거더 위에서 가설되는 블록자중을 장지간 상태에서도 충분히 지지할수 있는 아치구조로 구성되며 일단 주두부인 중간지점부(15)가 연결되면 연속 아치구조로 시공하중을 지지하게 되는 장점이 있어 기존의 장지간 교량시공법인 캔틸레버공법을 대체할 수 있다.In the present invention, the abdomen (W2) and the upper flange (17) is omitted, it is possible to fully lift the production girders (1,100) at a time by the crane construction method, and also the arch structure that can fully support the block weight that is installed on the girder even in the long-term state Once the
본 발명으로 구현된 교량의 중간지점부(15)의 하면은 일반적으로 큰 압축응력이 걸리므로 이를 대처하기 위해,In order to cope with the lower surface of the
종방향으로 2경간 이상이며, 횡방향으로 2개이상으로 거더가 배열된후 각각의 거더의 하부플랜지(3)를 소정의 두께로 연결 타설하여 교량 하부(14)가 폐합된 단면형태로 구성되며 상기 폐합된 단면의 구간이 전 지간 내지 적어도 중간지점부(15)로부터 지간의 1/4 이하로 설치되는 것을 특징으로 하는 것을 포함한다.2 or more spans in the longitudinal direction, two or more girders are arranged in the transverse direction, and the
도1은 본 발명으로 구현된 제작거더의 종단면도이다. 복부 (2)가 전 지간에 걸쳐 거더 제작시와 거더 거치후로 두 번 분할 타설하는 형식(┴형단면형식)이며 도2는 상기 형식의 지점부와 중앙부에서의 횡단면도이다. 그림에서와 같이 제작거더의 복부 상면위로 수직 철근(9)과 수평철근(10)이 기 시공되어 노출되어 있다. 이것은 거더 거치된 이후의 거더철근 조립 공정을 생략하기 위함이다. 또한 복부 시공 경계면에서 완전한 연결성을 보증해주는 역할을 수행한다. 또한 거더 단부(11)에 있는 케이블 정착구(5)가 관통된 구멍(6)을 가지고서 구비된다.1 is a longitudinal sectional view of a manufacturing girder implemented by the present invention. The abdomen 2 is divided into two parts during the girder fabrication and after the girder is placed (shape cross section) throughout the entire region, and FIG. 2 is a cross-sectional view at the point and the center of the form. As shown in the figure, the vertical reinforcing bar 9 and the horizontal reinforcing
도3은 본 발명으로 구현된 또 다른 형식이며 복부(2)를 분할타설하는 구간(┻형단면구간)이 거더 전장이 아닌 양 지점부(16)로부터 일정한 거리까지 설치된다. 상기 분할타설구간 이외의 구간은 일반적인 PSC거더 단면과 마찬가지로 상부플 랜지(17) ,복부(2), 하부플랜지(3)로 구성된 I형단면으로 구성된다. 이 형식도 상기 도1의 형식과 동일한 거동을 한다.3 is another form embodied by the present invention, and the section (shape section) for partitioning the
상기 도 1과 도 3의 거더와 같이 케이블(4)이 거더 제작시에 거더 단부 정착구(5)에 지지되어 구비되는 형식과는 다르게 정착구가 거더(1,100)에 설치되지 않고 거더가 거치된 이후에 거더를 2개이상 횡방향으로 배열한 이후 단부에 설치하는 양쪽 단부 가로보(거더와 거더를 횡방향으로 연결하는 보)에 설치되는 경우도 본발명이 제시하는 기술범위 내에 포함된다.Unlike the type in which the cable 4 is supported by the
도5는 본 발명으로 구현되는 하나의 예인 3경간 연속교량의 시공순서도이다.Figure 5 is a construction sequence diagram of a three-span continuous bridge as an example implemented in the present invention.
[도 1] : 전 지간에 걸쳐 ┴형 단면으로 구성되는 타이드 아치형 PSC거더의 종단면도1: Longitudinal cross-sectional view of a tide arched PSC girder composed of a curved cross section over the entire span
[도 2] :전 지간에 걸쳐 ┴형 단면으로 구성되는 타이드 아치형 PSC거더의 횡단면도Fig. 2: Cross sectional view of a tide arched PSC girder composed of an arcuate cross section over the whole section.
[도 3] :지점부로부터 소정의 구간까지 ┻형 단면으로 구성되는 타이드 아치형 PSC거더의 종단면도3: Longitudinal cross-sectional view of a tide arched PSC girder composed of an arcuate cross section from a point portion to a predetermined section.
[도 4] :지점부로부터 소정의 구간까지 ┻형 단면으로 구성되는 타이드 아치형 PSC거더의 횡단면도4 is a cross-sectional view of a tide arched PSC girder composed of an arcuate section from a point portion to a predetermined section.
[도 5] :본 발명으로 구현되는 하나의 예인 3경간 연속교량의 시공순서도5 is a construction sequence diagram of a three-span continuous bridge that is one example implemented by the present invention
[도 6] :종래의 PSC 거더의 종단면도6: Longitudinal sectional view of a conventional PSC girder
[도 7] :종래의 PSC 거더의 횡단면도7: Cross sectional view of conventional PSC girder
[도 8] :종래의 타이드 아치교의 종단면도8: Longitudinal cross-sectional view of a conventional tide arch bridge
[도 9] :종래의 캔틸레버공법으로 시공되는 교량의 종단면도9: Longitudinal sectional view of the bridge constructed by the conventional cantilever method
[도 10] :종래의 캔틸레버공법으로 시공되는 교량의 횡단면도10 is a cross sectional view of a bridge constructed by a conventional cantilever method.
<도면의 주요부분에 대한 부호 설명><Description of Signs of Main Parts in Drawings>
1: 전지간에 걸쳐 ┴형 단면으로 구성된 타이드 아치형 PSC 제작거더1: Tide arched PSC fabrication girder consisting of a curved cross section across cells
2: 복부2: abdomen
3:하부플랜지3: lower flange
4: 외부 케이블4: external cable
5: 단부 정착구5: end fixture
6: 관통 구멍6: through hole
7:긴장재 정착구7: tension anchorage
8: 하부플랜지내에 배치되는 긴장재8: tension member disposed in the lower flange
9:수직철근9: vertical rebar
10:수평철근10: horizontal rebar
11: 단부11: end
12:상부슬래브12: Upper slab
13:상부슬래브내에 배치되는 긴장재13: tension material disposed in the upper slab
14: 단면 폐합용 하부플랜지14: Lower flange for single side closing
15: 중간 지점부15: middle point
16: 지점16: branch
17:상부플랜지17: Upper flange
18: 하현재18: the present
19: 아치거더19: Arch Girder
20:작업차20: working car
21:하부플랜지 상면의 내민부21: Interior department of upper flange
22:┻형상으로 제작되는 단면22: Cross section manufactured in the shape of ┻
23:블록23: Block
24:시공이음된 단부24: Construction joint end
100: 지점부에서 소정의 구간에 걸쳐 ┻형 단면으로 구성된 타이드 아치형 PSC 제작거더100: Tide arched PSC manufacturing girder consisting of a curved cross section over a predetermined section at the point portion
W1:제작거더의 복부높이W1: Abdomen height of the production girder
W2:제작거더를 거치한 후에 추가로 타설되는 복부높이W2: Additional abdominal height after placing production girder
SL:제작거더를 거치한 후에 추가로 타설되는 상부슬래브 높이SL: Top slab height added after mounting production girder
AH:제작거더의 거치 후 추가 시공분의 높이AH: Height of additional construction after installation
BH:거더 제작시의 높이BH: Height at the time of girder production
W3:교량완성후의 최종 복부높이W3: Final abdominal height after bridge completion
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110101104A KR20130036890A (en) | 2011-10-05 | 2011-10-05 | Tied arched p.s.c girder for bridge and construction method for bridge by it |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110101104A KR20130036890A (en) | 2011-10-05 | 2011-10-05 | Tied arched p.s.c girder for bridge and construction method for bridge by it |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20130036890A true KR20130036890A (en) | 2013-04-15 |
Family
ID=48438050
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020110101104A Ceased KR20130036890A (en) | 2011-10-05 | 2011-10-05 | Tied arched p.s.c girder for bridge and construction method for bridge by it |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20130036890A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105350454A (en) * | 2015-11-02 | 2016-02-24 | 中铁大桥局集团有限公司 | Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge |
CN105672134A (en) * | 2016-01-26 | 2016-06-15 | 河海大学 | Through concrete-filled steel tube tied-arch bridge erection construction method |
RU2657562C1 (en) * | 2017-10-06 | 2018-06-14 | Акционерное общество "Спецремпроект" | Method of the bridge span structure reinforced concrete beam strengthening |
CN108262325A (en) * | 2017-11-29 | 2018-07-10 | 上海市政工程设计研究总院(集团)有限公司 | A kind of super-span all-glass fibre reinforced plastic deodorizing cover plate and foul smell collection device |
KR101989004B1 (en) * | 2018-03-13 | 2019-09-24 | 원용석 | Double composite girder for bridge |
CN110863431A (en) * | 2019-11-22 | 2020-03-06 | 中国十七冶集团有限公司 | Method for reinforcing steel guide cable pipe of suspension bridge suspender and improving installation precision |
CN112252154A (en) * | 2020-11-05 | 2021-01-22 | 重庆交通大学 | Novel anchor structure of short jib of half-through arch bridge |
CN112411342A (en) * | 2020-12-16 | 2021-02-26 | 昆山同济市政工程有限公司 | Construction method of prefabricated steel box girder pedestrian landscape bridge |
KR102263272B1 (en) | 2020-08-14 | 2021-06-14 | (주)주성이앤씨 | Bridge variable thickness girder for flood disaster prevention and construction method thereof |
CN115559229A (en) * | 2022-10-20 | 2023-01-03 | 北京市政路桥科技发展有限公司 | Reinforcing structure and construction method of main arch ring structure of a vertical hollow arch bridge |
KR102522672B1 (en) | 2023-01-04 | 2023-04-18 | (주)주성이앤씨 | Prestressed hybrid concrete girder with different concrete strength at center part and end part and method for manufacturing the same |
CN118153176A (en) * | 2024-05-09 | 2024-06-07 | 西华大学 | Tie rod tension optimization method based on Transformer model and GWO algorithm |
-
2011
- 2011-10-05 KR KR1020110101104A patent/KR20130036890A/en not_active Ceased
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105350454B (en) * | 2015-11-02 | 2017-01-11 | 中铁大桥局集团有限公司 | Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge |
CN105350454A (en) * | 2015-11-02 | 2016-02-24 | 中铁大桥局集团有限公司 | Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge |
CN105672134A (en) * | 2016-01-26 | 2016-06-15 | 河海大学 | Through concrete-filled steel tube tied-arch bridge erection construction method |
RU2657562C1 (en) * | 2017-10-06 | 2018-06-14 | Акционерное общество "Спецремпроект" | Method of the bridge span structure reinforced concrete beam strengthening |
CN108262325B (en) * | 2017-11-29 | 2024-05-24 | 上海市政工程设计研究总院(集团)有限公司 | Ultra-large-span all-glass fiber reinforced plastic deodorizing cover plate and odor collecting device |
CN108262325A (en) * | 2017-11-29 | 2018-07-10 | 上海市政工程设计研究总院(集团)有限公司 | A kind of super-span all-glass fibre reinforced plastic deodorizing cover plate and foul smell collection device |
KR101989004B1 (en) * | 2018-03-13 | 2019-09-24 | 원용석 | Double composite girder for bridge |
CN110863431A (en) * | 2019-11-22 | 2020-03-06 | 中国十七冶集团有限公司 | Method for reinforcing steel guide cable pipe of suspension bridge suspender and improving installation precision |
KR102263272B1 (en) | 2020-08-14 | 2021-06-14 | (주)주성이앤씨 | Bridge variable thickness girder for flood disaster prevention and construction method thereof |
CN112252154A (en) * | 2020-11-05 | 2021-01-22 | 重庆交通大学 | Novel anchor structure of short jib of half-through arch bridge |
CN112411342A (en) * | 2020-12-16 | 2021-02-26 | 昆山同济市政工程有限公司 | Construction method of prefabricated steel box girder pedestrian landscape bridge |
CN115559229A (en) * | 2022-10-20 | 2023-01-03 | 北京市政路桥科技发展有限公司 | Reinforcing structure and construction method of main arch ring structure of a vertical hollow arch bridge |
KR102522672B1 (en) | 2023-01-04 | 2023-04-18 | (주)주성이앤씨 | Prestressed hybrid concrete girder with different concrete strength at center part and end part and method for manufacturing the same |
CN118153176A (en) * | 2024-05-09 | 2024-06-07 | 西华大学 | Tie rod tension optimization method based on Transformer model and GWO algorithm |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20130036890A (en) | Tied arched p.s.c girder for bridge and construction method for bridge by it | |
KR100536489B1 (en) | Manufacturing method for prestressed steel composite girder and prestressed steel composite girder thereby | |
KR101171039B1 (en) | Partially and fully earth-anchored cable-stayed bridge using main span prestressing appratus and construction method for the same | |
KR101456635B1 (en) | Bridge construction method using of form traveller for through bridge and rebar structure | |
KR100943823B1 (en) | Girder compounded with the concrete and steel | |
KR101335382B1 (en) | Constrution method of Prestressed Composite Truss girder with internal hinge structure | |
CN109338896B (en) | Construction method of broad-width concrete PK box girder support system | |
KR101208231B1 (en) | Method for constructing continuous supporting structure of corrugated steel web PSC beam | |
KR101052305B1 (en) | Construction method of composite ramen bridge which is manufactured in simple beam form and minimizes bending moment generated at the point | |
CN112267367A (en) | Method for converting arch-first beam-later system of self-anchored steel box tied arch bridge | |
KR101308792B1 (en) | Various Section Box Girder And Manufacturing Method thereof, And Bridge Construction Method Using The Same | |
KR101688517B1 (en) | Continuous bridge construction method using support pier girder and continuous tendon of pier | |
KR20130090709A (en) | Construction method for corrugated steel plate web-psc composite beam | |
KR101198376B1 (en) | Fcm pier table construction method using girder | |
KR100981982B1 (en) | Precast coping lifting system | |
KR100592196B1 (en) | Multi-point support bracket installed to support bridge using brackets with multiple support devices and its installation method | |
KR101165572B1 (en) | Middle span plate girder bridge and construction method thereof | |
CN112681150B (en) | Prefabricated hoisting system for box-type arch bridge and construction method | |
JP2020063598A (en) | Hinge part reinforcement method and reinforcement structure in hinged girder bridge with pc | |
CN112227216A (en) | Triangular area cable buckling and sling combined construction method for steel diagonal bracing continuous rigid frame bridge | |
KR101136992B1 (en) | Psc box girder bridge with open-type lower flange | |
KR20150032499A (en) | Construction method of prestressed composite girder bridge | |
KR101734304B1 (en) | Manufacturing Method of Efficient Steel-Concrete Composite Girder, Construction Method of Continuous Bridges using such Composite Girder, and Continuous Bridges constructed by such Method | |
KR101739658B1 (en) | steel box girder bridge of wide slab and all slab concrete section used as compression member and slab assemblied with steel box | |
KR102206777B1 (en) | Top-opened single-span steel composite girder and its fabrication method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20111005 |
|
PA0201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
PE0902 | Notice of grounds for rejection |
Comment text: Notification of reason for refusal Patent event date: 20130325 Patent event code: PE09021S01D |
|
PG1501 | Laying open of application | ||
E601 | Decision to refuse application | ||
PE0601 | Decision on rejection of patent |
Patent event date: 20130624 Comment text: Decision to Refuse Application Patent event code: PE06012S01D Patent event date: 20130408 Comment text: Notification of reason for refusal Patent event code: PE06011S01I Patent event date: 20130325 Comment text: Notification of reason for refusal Patent event code: PE06011S01I |
|
E601 | Decision to refuse application | ||
PE0601 | Decision on rejection of patent |
Patent event date: 20130708 Comment text: Decision to Refuse Application Patent event code: PE06012S01D Patent event date: 20130408 Comment text: Notification of reason for refusal Patent event code: PE06011S01I Patent event date: 20130325 Comment text: Notification of reason for refusal Patent event code: PE06011S01I |