KR20060103309A - Gradual bottom-up slice and gradual infilling method for removing underground retaining wall - Google Patents

Gradual bottom-up slice and gradual infilling method for removing underground retaining wall Download PDF

Info

Publication number
KR20060103309A
KR20060103309A KR1020060086412A KR20060086412A KR20060103309A KR 20060103309 A KR20060103309 A KR 20060103309A KR 1020060086412 A KR1020060086412 A KR 1020060086412A KR 20060086412 A KR20060086412 A KR 20060086412A KR 20060103309 A KR20060103309 A KR 20060103309A
Authority
KR
South Korea
Prior art keywords
retaining wall
underground
sequential
pile
raker
Prior art date
Application number
KR1020060086412A
Other languages
Korean (ko)
Other versions
KR100736241B1 (en
Inventor
김상현
Original Assignee
주식회사 백산종합개발
김상현
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 백산종합개발, 김상현 filed Critical 주식회사 백산종합개발
Priority to KR1020060086412A priority Critical patent/KR100736241B1/en
Publication of KR20060103309A publication Critical patent/KR20060103309A/en
Application granted granted Critical
Publication of KR100736241B1 publication Critical patent/KR100736241B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings
    • E04G23/082Wrecking of buildings using shears, breakers, jaws and the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/02Shores or struts; Chocks non-telescopic

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

건물의 지하옹벽을 제거하는 새로운 공법을 제공한다. 종래 지하옹벽제거공사는 흙막이 토공사 및 토사의 중복반입과 중복반출로 인해 공기(工期)의 지연과 공비의 증가가 불가피했다. 본 발명은 철거대상 지하옹벽이 인접 대지경계에 극히 가깝게 접하고 있어서 옹벽의 외측에 옹벽을 제거하기 위한 토공사 공간을 확보하기 어려운 경우조차도 그 인접대지를 침범함이 없이 옹벽 내측으로부터 경제적으로 옹벽제거공사를 진행할 수 있어서 주변 이웃들의 민원의 소지를 근본적으로 없앨 수 있는 방법을 제공한다. Provide a new method for removing underground retaining walls of buildings. Conventional underground retaining wall removal construction is inevitable due to the delay of air and increase of public affairs due to the overlapping and overloading of earthen and earthwork. According to the present invention, even when the underground retaining wall to be demolished is very close to the adjacent land boundary, it is difficult to secure earthwork space for removing the retaining wall on the outside of the retaining wall. It can provide a way to fundamentally eliminate the complaints of neighbors.

본 발명의 공법은 철거하고자 하는 지하옹벽을 소정의 지지구조물로 지지시킨 상태에서 옹벽의 내측에서 휠쏘컷터 등을 사용하여 그 하단부부터 제거하여 올라옴과 동시에 그 제거되는 높이만큼의 토사 되메우기 과정을 반복적으로 실시하는 방법이다. 본 공법에 따라 지하옹벽은 그 하단측으로부터 위쪽을 향하여 상향식으로 순차 제거되어 나온다.According to the method of the present invention, while the base retaining wall to be removed is supported by a predetermined support structure, the soil reclamation process is repeatedly carried out by removing the lower part of the retaining wall from the lower end by using a wheel saw cutter or the like. It is a method to carry out. According to this method, the basement retaining wall is sequentially removed from the bottom side upwards upward.

지하, 지하옹벽, 철거, 흙막이, 상향식, 레이커, 휠쏘컷터 Underground, Underground Retaining Walls, Demolition, Blocks, Bottom-Up, Raker, Wheel Saw Cutters

Description

지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법{Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall} Gradient Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall}

도 1은 본 발명에 따른 지하옹벽 제거공법의 공정을 도시한 불록도이다.1 is a block diagram showing the process of the underground retaining wall removal method according to the present invention.

도 2a는 지하옹벽 내부구조물 제거공정의 일례를 나타내는 부분단면도이다. Figure 2a is a partial cross-sectional view showing an example of the process of removing the inner retaining wall internal structure.

도 2b는 지하옹벽 내부구조물 제거공정의 일례를 나타내는 부분절개 사시도이다. 2B is a partial cutaway perspective view illustrating an example of a process of removing an underground retaining wall internal structure.

도 3a는 레이커파일 및 레이커 설치공정을 나타내는 단면도이다.3A is a cross-sectional view showing the raker pile and the raker installation process.

도 3b는 레이커파일 및 레이커 설치공정을 나타내는 사시도이다.Figure 3b is a perspective view showing the raker pile and the raker installation process.

도 3c는 레이커 설치의 상세도로서 도 3b의 A부분 및 B 부분 상세도이다. 3C is a detail view of the portion A and B of FIG. 3B as a detailed view of the raker installation.

도 3d는 레이커 설치이후 임시유지 구조물 제거를 나타내는 단면도이다.Figure 3d is a cross-sectional view showing the removal of the temporary structure after the installation of the raker.

도 4a는 옹벽지지파일 설치 단면도이다.Figure 4a is a sectional view of the retaining wall support pile installation.

도 4b는 옹벽지지파일 설치 정면도이다.Figure 4b is a front view of the retaining wall support pile installation.

도 4c는 옹벽지지파일을 연결판을 통해 옹벽에 부착고정하는 공정을 나타내는 부분상세사시도이다.4C is a partial detailed perspective view illustrating a process of attaching and retaining the retaining wall support pile to the retaining wall through the connecting plate.

도 4d는 옹벽에 레이커 및 옹벽지지파일의 설치가 완료된 상태를 나타내는 부분사시도이다.Figure 4d is a partial perspective view showing a state in which the installation of the raker and the retaining wall support pile on the retaining wall is completed.

도 5a는 옹벽외측에 차수층을 형성하기 위하여 지하수위 이하의 옹벽에 대하여 차수재 주입구멍을 뚫어 그 구멍을 통해 차수재를 주입하는 것을 도시한 부분사시도이다.FIG. 5A is a partial perspective view showing a filler injection hole for the retaining wall below the groundwater level and injecting the filler material through the hole to form the order layer on the outer side of the retaining wall.

도 5b는 옹벽외측에 차수층을 형성하기 위하여 지하옹벽 외측에서 지상으로부터 지중으로 향하여 수직방향으로 차수재 주입구멍을 뚫어 그 구멍을 통해 차수재를 주입하는 것을 도시한 부분사시도이다. FIG. 5B is a partial perspective view showing a filler injection hole in the vertical direction from the ground to the ground outside the base retaining wall to form a barrier layer outside the retaining wall and injecting the filler material through the hole; FIG.

도 6은 옹벽의 하부에 부착되어 남아있던 기초부를 제거하는 상태를 도시한 사시도이다. FIG. 6 is a perspective view illustrating a state in which a base portion remaining attached to a lower portion of a retaining wall is removed.

도 7a는 옹벽하단부로부터의 대략 장방형 절단 불록체를 절개하는 상태를 나타내는 단면도이다. It is sectional drawing which shows the state which cut | disconnects the substantially rectangular cutting block from the lower part of a retaining wall.

도 7b는 지하옹벽 절단블록체의 경사절단 및 그 인양전 뒷다짐 과정을 도시한 단면도이다.Figure 7b is a cross-sectional view showing the inclined cutting of the basement retaining wall cutting block body and its lifting before compaction.

도 7c는 지하옹벽 절단블록체를 정면에서 보았을 때 상광하협(上廣下狹)과 상협하광(上狹下廣)의 사다리꼴 모양이 횡방향으로 교대로 형성되는 경우를 도시한 절개형상정면도이다. FIG. 7C is a cutaway front view showing a case where trapezoidal shapes of the upper and lower narrow beams and the upper and lower lower beams are alternately formed in the transverse direction when the basement retaining wall cutting block body is viewed from the front.

도 7d는 옹벽절단블록체를 정면에서 보았을 때 상광하협(上廣下狹)과 상협하광(上狹下廣)의 사다리꼴 모양이 횡방향으로 교대로 형성되는 경우에 옹벽 절단블록체의 대략 1/2높이 만큼 토사가 채워진 상태에서 먼저 상협하광형(上狹下廣形)의 것이 제거되는 것을 도시한 정면도이다.Fig. 7D shows approximately 1 / th of the retaining wall cut block when the trapezoidal shape of the upper and lower narrow beams and the upper and lower narrow beams are alternately formed in the transverse direction when the retaining wall cutting block is viewed from the front. This is a front view showing that the upper narrow bottom type is removed first when soil is filled by 2 heights.

도 7e는 옹벽절단블록체를 정면에서 보았을 때 상광하협(上廣下狹)과 상협하광(上狹下廣)의 사다리꼴 모양이 횡방향으로 교대로 형성되는 경우에 먼저 상협하광형(上狹下廣形)이 제거된 이후에 옹벽절단블록체의 대략 2/3 내지 3/4높이만큼 토사가 더 채워진 상태에서 상광하협형(上廣下狹形)의 것이 제거되는 것을 도시한 정면도이다. FIG. 7E is a first upper and lower beam type when the trapezoidal shape of the upper and lower narrow beams and the upper and lower beams are alternately formed in the transverse direction when the retaining wall cutting block is viewed from the front. It is the front view which shows that the thing of the upper and lower narrowing form is removed in the state which the soil was further filled by about 2/3 to 3/4 height of the retaining wall cutting block body after the removal of the shape.

도 7f는 전술한 도 7a 내지 도 7efh 도시한 방식을 통해 옹벽의 하단부로부터 또다시 부분절개 제거공정이 순차 진행됨에 따라 더 이상 옹벽지지가 필요하기 않게 된 하단측 레이커의 제거 및 상단측 재설치개념을 도시한 단면도이다.7F illustrates the removal and top-side re-installation concept of the lower side raker, which is no longer required for retaining wall support as the partial incision removal process is sequentially performed from the lower end of the retaining wall through the above-described method of FIGS. 7A to 7EF. It is sectional drawing.

도 7g는 도 7f의 과정을 진행함에 있어서 토사되메움이 진행되어 더 이상 옹벽지지의 필요가 없게 된 하단측 레이커를 제거하는 한편 옹벽의 제거가 완료된 부분에 대해서는 그 옹벽을 지지하는데 사용되었던 레이커파일을 인발하는 개념을 도시한 단면도이다.FIG. 7G shows the raker pile used to support the retaining wall for the portion where the retaining wall is removed while removing the bottom side raker which is soil-filled and no longer needs the retaining wall support in the process of FIG. 7F. A cross-sectional view showing the concept of drawing.

도 7h는 도 7g의 과정을 더 진행함에 있어서 지하층고가 높은 옹벽 쪽에 대한 지지기능을 담당하고 있던 레이커파일 중에서 그 공정의 진행에 따라 사명을 다하여 더 이상 존치의 필요가 없어진 경우 이를 제거하는 개념을 도시한 단면도이다.FIG. 7h illustrates a concept of removing the case where the necessity of maintaining no longer exists due to the progress of the process among the raker piles that were in charge of supporting the retaining wall with a high basement floor in the process of FIG. 7g. One cross section.

도 7i는 레이커가 역활을 다함에 따라 최종적으로 남아있던 레이커지지파일에 대해서도 그 인발을 행하는 것을 나타내는 단면도이다.FIG. 7I is a cross-sectional view showing the drawing of the raker support pile that remained as the raker plays its role.

도 7j는 지하옹벽이 모두 제거되고 그라운드라인까지 토사되메우기가 이루어진 상태에서, 지중에 수직으로 매립되어 잔류되어 있던 지하옹벽지지파일을 최종적 으로 인발해 내는 것을 도시한 단면도이다.FIG. 7J is a cross-sectional view illustrating the final drawing of the underground retaining wall support pile, which is buried vertically in the ground, with all underground retaining walls removed and ground filled to the ground line.

도 8은 도7j까지의 공정이 모두 종료되어 지중에 아무런 장애물이 없는 상태를 도시한 단면도이다. FIG. 8 is a cross-sectional view illustrating a state in which all the processes up to FIG. 7J are completed and there are no obstacles in the ground.

(주요도면부호에 대한 설명)(Explanation of main drawing code)

10 : 지하옹벽 12 : 옹벽 내부의 내력벽10: underground retaining wall 12: bearing wall inside the retaining wall

14 : 옹벽측 기둥 16 : 바닥슬라브14: retaining wall side pillars 16: floor slab

18 : 보 20 : 기초바닥콘크리트 18: beam 20: foundation concrete

30 : 레이커파일(엄지말뚝) 32 : 레이커(경사버팀부재)30: Raker pile (thumb pile) 32: Raker (tilt member)

34: 연결판 36 : 앵커볼트34: connecting plate 36: anchor bolt

40 : 옹벽지지파일 42 : 앵커볼트40: retaining wall support pile 42: anchor bolt

43 : 옹벽지지파일의 플랜지부에 형성된 앵커볼트체결구멍43: anchor bolt fastening hole formed in the flange portion of the retaining wall support pile

44 : 연결판 45 : 용접부44: connecting plate 45: weld

46 : 옹벽 절개홈 46: retaining wall incision

50 : 지하수위 52, 56 : 차수재 주입구멍 50: groundwater level 52, 56: water filler injection hole

54 , 58 : 차수재 54, 58: Lee Jae-jae

D1, D2 : 기초바닥 잠정적 잔존길이 D1, D2: Provisional remaining length of foundation floor

D3 : 옹벽지지파일간의 수평방향 설치간격 D3: Horizontal installation spacing between retaining wall support piles

H1 : 옹벽지지파일 연결판간의 수직방향 배치간격 H1: Vertical spacing between retaining wall support pile connecting plate

H2 : 절개홈 사이의 수직간격H2: Vertical gap between incision grooves

W1 : 절개홈의 수평길이W1: Horizontal length of incision groove

W2 : 옹벽지지파일의 폭W2: Width of retaining wall support pile

GL: 그라운드라인GL: Ground Line

본 발명은 건물을 철거하는 공법에 관한 것이며, 더 구체적으로는 건물의 지하옹벽을 제거하는 새로운 공법에 관한 것이다.The present invention relates to a construction method for demolishing a building, and more particularly to a new construction method for removing underground retaining walls of a building.

건물의 지하층을 구축하기 위한 토목공사의 주요 내용중의 하나는 터파기와 관련한 흙막이 공사이다. 여러 가지 흙막이공법 적용에 따라 지하옹벽이 구축된 다음 흙막이 토목공사용 가설부재(흙막이 파일, 토류판, CIP 등)는 인발되어 제거되거나 일부는 지중에 매립존치됨으로써 구축된 지하옹벽은 직접 흙에 접하여 토압을 지지한다. 재령(材齡) 30년이 넘는 국내 건물들은 그 건물이 상당규모의 바닥면적 을 갖는 빌딩으로서 지하층을 갖는 경우일지라도 대부분 그 지하층의 깊이가 대략 3층 이하이며 깊이는 약 4~17m정도가 되는데, 오래된 건물들이 이처럼 비교적 낮은 지하층을 가지는 이유는 과거에는 차량 대수가 많지 않아 지하 주차공간의 확보가 필수불가결한 요청이 아닌 것과 관련한다. 철거대상이 되는 재령 30년이상의 과거건물들의 지하옹벽은 흙막이 파일과 토류벽 및 엄지말뚝을 사용하거나 지반의 조건에 따라 CIP를 사용한 토공사에 기초하여 구축된 것이 대부분이다. One of the main contents of civil engineering work to build the basement of the building is the earthquake related to the trench. Underground retaining walls are constructed according to the application of various soil blocking methods, and then the temporary retaining members (soil pile, earth plate, CIP, etc.) for earthwork are removed and partially removed. I support it. Most Korean buildings over 30 years old have a large floor area, even if they have a basement floor. Most of them have a depth of about 3 floors or less and a depth of about 4 ~ 17m. The reason why older buildings have such a relatively low basement is that the number of vehicles in the past was not so large that securing underground parking spaces was not an indispensable request. Most of the underground retaining walls of past buildings over 30 years of age are to be demolished based on earthwork using soil piles, earth walls and thumb piles, or CIP depending on soil conditions.

본 발명에 의한 옹벽철거공법이 적용될 수 있는 지하층의 깊이는 기본적으로 대략 지하 1층~지하 3층 정도인 경우에 유용하나 기존건물 구조와 관련한 옹벽지지 방식에 따라 그 이상도 가능하다. 따라서 일반적으로 철거의 대상으로 되는 건물들의 재령이 대부분 30년이 넘는 노후된 건물로서 그 지하층의 깊이가 대개 지하 3층 이하인 것을 감안할 때 본 발명에 따른 옹벽 철거공법은 지하층을 포함한 건물 전체를 철거한 후 동일한 대지 경계 내에 건물을 신축하고자 하는 경우의 국내 대부분의 노후된 건물들에 대하여 무리없이 적용될 수 있다. The depth of the basement layer to which the retaining wall demolition method according to the present invention can be applied is basically useful in the case of approximately one basement level to three underground levels, but more than that is possible depending on the retaining wall supporting method related to the existing building structure. Therefore, the retaining wall demolition method according to the present invention, after demolition of the entire building including the basement floor, considering that most of the buildings that are subject to the demolition are old buildings that are more than 30 years old and the depth of the basement floor is usually 3 floors or less. It can be applied to most old buildings in Korea in case of building new buildings within the same site boundary.

지하층을 갖는 건물을 철거한 이후에 동일한 대지경계 내에 새 건물을 신축하고자 할 경우, 구건물 지상부(地上部)에 대한 철거는 비교적 어려움이 없으나, 그 지하부분, 특히 지하옹벽은 상당한 토압을 받고 있는 부분이기 때문에 지하옹벽으로 둘러싸인 내부의 공간, 즉 지하실 내부공간으로부터 직접 그 옹벽을 무단 파괴하여 철거할 경우에는 토압을 지탱하던 내력벽이 한순간에 없어지는 결과로 되어 그 옹벽의 철거와 동시에 그 옹벽에 의해 버텨지고 있던 토압이 한꺼번에 작용함으로써 철거공간 내로 일시에 흙이 무너져 내릴 수 있기 때문에 대단히 큰 위험이 상 존한다. If a new building is to be constructed within the same site boundary after the removal of the basement-level building, the removal of the ground above the old building is relatively difficult, but the basement, especially the underground retaining wall, is under considerable earth pressure. For this reason, if the retaining wall is directly removed from the inner space surrounded by the underground retaining wall, that is, the inner space of the basement, the bearing wall supporting earth pressure disappears at once, and the retaining wall is destroyed by the retaining wall at the same time. There is a great risk because the earth pressure that has been lost can act at once and the soil can collapse into the demolition space at once.

이러한 이유로 건물의 철거공사시 지하층의 내부기둥을 포함한 바닥슬라브의 대부분이 모두 철거된 경우일지라도 토압을 받고 있는 건물의 외벽인 지하옹벽은 철거할 수 없는 경우가 많아 결국 그 옹벽을 그대로 남겨둔 상태에서 지하내부 공간 전체를 신속히 외부 반입토사로 되메우기 하게 된다.For this reason, even when most of the floor slabs including the inner columns of the basement are demolished during the demolition work, the underground retaining wall, which is the outer wall of the building under pressure, cannot be demolished. The entire interior space is quickly filled with external incoming soil.

이 경우 다음 공정인 신축건물 지하 터파기 공사시 신축하고자 하는 건물의 지하옹벽 라인이 철거대상이었던 잔류된 지하옹벽라인과 겹치는 경우에 흙막이공사를 위한 파일 천공작업 등에 문제점이 발생 하는데 이를 해결하기 위하여 부득히 그 존치된 지하옹벽을 제거하기 위한 목적의 흙막이 공사 및 굴토를 시행하여 잔류되었던 지하옹벽을 제거한 다음에 또다시 2차 되메우기를 함으로써 신축하고자 하는 대지경계 내의 지중에 아무런 장애물이 없는 나대지(裸垈地) 상태를 만들고, 이처럼 지중에 아무런 장애물이 없는 나대지에 대하여 비로소 신축하고자 하는 건물의 지하옹벽선에 맞춘 토공사를 재시작하지 않으면 안된다.  In this case, when the underground retaining wall line of the building to be constructed overlaps with the remaining underground retaining wall line, which was the object of demolition, the construction of pile drilling works for the earthquake works occurs. A land without any obstacles in the ground within the land boundary to be constructed by removing the remaining underground retaining wall by removing the remaining underground retaining wall by carrying out construction and excavation for the purpose of removing the retained underground retaining wall. The earthwork must be restarted in line with the underground retaining wall of the building to be newly constructed for the bare land without any obstacles in the ground.

본 발명에 따른 철거공법은 문제로 되는 지하옹벽을 철거하기 위하여 이처럼 대단히 번거롭고 공기가 길며 비용이 많이 드는 토공사가 필요한 경우, 특히 신축하고자 하는 건물의 지하옹벽 라인이 철거대상으로 되는 지하옹벽라인과 겹치는 경우의 적용시 매우 효과적이다. The demolition method according to the present invention requires such a very troublesome, long air and expensive earthwork to remove the problematic underground retaining wall, in particular, the underground retaining wall line of the building to be constructed overlaps with the underground retaining wall line to be removed. Very effective in the application of the case.

그런데 위와 같이 번거롭고 비용이 많이 드는 경우조차도 존치된 지하옹벽의 외부로부터 그 존치된 옹벽을 제거하기 위한 목적의 흙막이 공사 및 굴토를 시행하고자 할 경우, 그 옹벽 외부로부터 흙막이 공사를 하기 위하여 그 토공사에 필요한 장비반입공간 등을 확보하지 않으면 안되기 때문에 불가피하게 주변도로 등에 대하여 점용허가 등을 얻지 않으며 안되는 경우도 드물지 않은데 이는 소음, 인접건물에 대한 균열의 우려 및 대지경계의 불가피한 침입 등에 따른 대단히 큰 민원을 야기한다. 뿐만 아니라 만일 철거하고자 하는 지하옹벽이 인접 대지경계에 극히 가깝게 접하고 있어서 옹벽의 외측에 옹벽을 제거하기 위한 필요 최소한의 토공사 공간을 확보할 수 없을 경우와 같이 도저히 지하옹벽 철거공사 자체를 불가능하게 하는 경우도 없지 않다. 이는 도심의 지가(地價)가 대단히 고가여서 건축주들이 가능한 한, 땅 한 평이라도 더 넓혀서 건축하기 위해 대부분의 건물들을 대지경계선에 바로 인접하여 그 지하옹벽을 구축하는 실정과도 무관하지 않다. However, even in the case of the cumbersome and expensive case as described above, when the earth retaining work and the excavation for the purpose of removing the retained retaining wall from the outside of the retained basement retaining wall are to be carried out, Since it is necessary to secure equipment carrying space, it is inevitable to obtain a spot permit for surrounding roads, which is not uncommon, which causes very large civil complaints due to noise, fear of cracking into adjacent buildings, and inevitable intrusion of the land boundary. do. In addition, if the underground retaining wall to be removed is in close contact with the adjacent land boundary, it is impossible to make the underground retaining wall demolition work itself, such as when the minimum earthwork space required for removing the retaining wall cannot be secured outside the retaining wall. There is no. This is irrelevant to the fact that the land price of the city is so expensive that the owners build the basement retaining wall in the immediate vicinity of the land boundary to build as much land as possible.

본 발명에 따른 지하옹벽 제거공법은 이처럼 종래 지하옹벽을 제거함에 있어서 필요한 흙막이 토공사 및 토사의 중복반입과 중복반출에 다른 공기(工期)의 지연과 공비의 증가를 배제할 수 있을 뿐만 아니라, 특히 지하옹벽이 인접 대지경계에 극히 가깝게 접하고 있어서 옹벽의 외측에 옹벽을 제거하기 위한 토공사 공간을 확보하기 어려운 경우조차도 그 인접대지를 침범함이 없이 옹벽 내측으로부터 손쉽게 공사를 진행할 수 있어서 주변 이웃의 민원의 소지를 근본적으로 없앨 수 있는 획기적인 방법을 제공한다. The underground retaining wall removal method according to the present invention can not only eliminate the delay of the air and increase the cost of the air, but also the underground of the earthwork and earthwork. Even if the retaining wall is in close contact with the adjacent land boundary, and it is difficult to secure earthwork space for removing the retaining wall outside the retaining wall, the construction can be easily carried out from the inside of the retaining wall without invading the adjacent site. It provides a groundbreaking way to radically eliminate the problem.

또한 본 발명에 따른 지하옹벽 제거공법은 주변건물이나 지반에 대하여 균열이나 침하 등과 같은 악영향을 일으키지 않으며 소음없이 시공할 수 있는 간편한 공법을 제공한다. In addition, the underground retaining wall removing method according to the present invention provides a convenient method that can be installed without noise without causing adverse effects such as cracks or settlements on the surrounding buildings or ground.

본 발명은 다음과 같은 기술적 과제를 해결하기 위한 것이다.The present invention is to solve the following technical problem.

첫째, 지하옹벽을 제거하기 위한 별도의 흙막이 가설공사를 시행하지 않고도 지하옹벽을 직접 안전하게 철거함과 아울러 동시적으로 진행되는 단 한 번의 옹벽내측 토사되메우기만으로 신축하고자 하는 옹벽라인상에 아무런 지중장애물이 존재하지 않는 형태의 나대지를 만들 수 있음으로써 건물 신축의 토공사 공기를 대폭 단축하고 공비를 크게 절감할 수 있는 경제적인 지하옹벽제거공법을 제공한다.First, there is no underground obstacles on the retaining wall line that is intended to be constructed by only dismantling the underground retaining walls directly and simultaneously filling the sediment inside the retaining wall without the need for a separate block construction to remove the underground retaining walls. By making bare land of non-existent form, it provides economic underground retaining wall removal method that can drastically reduce earthwork of building construction and greatly reduce public expenses.

둘째, 지하옹벽을 그 철거하고자 하는 지하옹벽의 내측으로부터 직접 철거함으로써 종래 지하옹벽 철거시 빈번한 민원의 소지였던 인접대지에 대한 악영향, 특히 주변건물에 대하여 균열 또는 지반의 침하문제, 소음문제, 공용도로의 점용문제 등과 같은 민원을 일으키지 않는 새로운 지하옹벽제거공법을 제공한다.Second, by removing the basement wall directly from the inside of the basement wall to be removed, the adverse effect on the adjacent site, which was frequently a complaint during the demolition of the basement wall, especially the surrounding building, cracking or ground subsidence problem, noise problem, public road It provides a new underground retaining wall removal method that does not cause civil complaints such as problems of private use.

세째, 철거하고자 하는 지하옹벽이 인접 대지경계에 극히 가깝게 접하고 있거나 그밖의 이유로 지하옹벽을 철거하기 위한 가설공사용 여유공간을 확보할 수 없는 등 기존의 공법을 적용하기 힘든 난공사(難工事)에 대해서도 용이하게 적용할 수 있는 새로운 지하옹벽제거공법을 제공한다.Third, it is easy for difficult construction work that is difficult to apply existing methods, such as the underground retaining wall that is to be demolished is very close to the adjacent land boundary, or for other reasons, it is not possible to secure the temporary construction work space for removing the underground retaining wall. It provides a new underground retaining wall removal method that can be applied.

네째, 신축하고자 하는 건물의 지하옹벽라인과 철거하고자 하는 구건물의 지하옹벽라인이 서로 중첩되는 경우에 특히 유용하게 적용할 수 있는 새로운 지하옹벽제거공법을 제공한다. Fourth, it provides a new underground retaining wall removal method that can be particularly useful when the underground retaining wall line of the building to be built and the underground retaining wall line of the old building to be removed overlap each other.

이하 본 발명의 구성을 그 실시예로서 도시한 첨부도면을 인용하여 이하 상 세히 설명한다. Hereinafter, with reference to the accompanying drawings showing the configuration of the present invention as an embodiment thereof will be described in detail.

본원 발명은 도 1에 도시한 바와 같이 기본적으로 다음 일곱 단계의 공정으로 이루어지는 것을 특징으로 한다. 이들 일곱단계 중 일부의 단계들은 필수공정으로도 또는 부가공정으로도 적용될 수 있는데 그 필수 또는 부가여부의 구체적 내용은 이하의 설명으로부터 잘 이해될 수 있을 것이다. As shown in FIG. 1, the present invention is basically characterized by the following seven steps. Some of these seven steps may be applied as essential processes or as additional processes, and the details of the essential or additional steps will be well understood from the following description.

제1공정 : First step: 지하옹벽의Basement wall 내부구조물 제거공정 Internal structure removal process

철거하고자 하는 건물의 지상부분이 철거된 이후에 행해지는 지하부분 제거공정으로서, 토압을 받고 있는 지하옹벽 이외의 부분인 바닥 슬라브와 내부기둥 및 보를 제거하는 공정이다. 단, 도 2a 및 도 2b에 도시한 바와 같이, 옹벽(1 )내부에서 옹벽에 접하는 내력벽(12), 옹벽에 근접한 기둥(14) 및 그 옹벽(10)과 내력벽(12) 사이에 설치된 바닥슬라브(16) 및/또는 내력벽과 옹벽 사이에 걸쳐진 보(18)는 본 발명에 따른 초기공정의 진행 동안 옹벽을 지지하는 데에 조력(助力)할 수 있으므로 본 공정에서는 제거되지 않고 후술하는 제2공정이 완료되기까지 잠정적으로 더 존치될 수 있다. 아울러 이 공정에서 지하 최저층의 바닥슬라브(20)는 그 바닥면적 전부를 제거하지 않고 옹벽라인으로부터 소정거리 떨어진 거리(D1) 만 큼(예컨대 약 2m 정도)을 옹벽라인을 따라 남겨두는 것이 옹벽의 거동을 억제할 수 있어서 바람직하다. The underground part removal process is performed after the ground part of the building to be demolished is removed, and is a process of removing floor slabs, internal pillars, and beams other than the underground retaining wall under earth pressure. However, as shown in FIGS. 2A and 2B, a bearing wall 12 in contact with the retaining wall in the retaining wall 1, a column 14 adjacent to the retaining wall, and a floor slab provided between the retaining wall 10 and the bearing wall 12. (16) and / or the beam 18 spanning between the bearing wall and the retaining wall may be assisted in supporting the retaining wall during the progress of the initial process according to the present invention, so it is not removed in this step and is the second step described below. It may be potentially further maintained until this is completed. In addition, in this process, the floor slab 20 of the lowest basement layer does not remove all of its floor area, but leaves the retaining wall line along the retaining wall line as much as a distance D1 from the retaining wall line (for example, about 2m). It is preferable because it can suppress.

제2공정 : Second Step: 레이커파일Laker Pile  And 레이커Laker 설치공정 Installation process

지하옹벽이 내측방향으로 전도(顚倒)되는 것을 방지하기 위한 지지말뚝으로서, 도 3a에 도시한 바와 같이 철거된 공간내 지중에 레이커파일(Raker Pile:엄지말뚝)(30)을 박는다. 레이커파일의 설치간격은 토압과 구조물(지하옹벽)의 상태에 따라 구조설계에 의해 다르게 결정되는 것이지만, 대체로 레이커간 수평방향 간격은 내력벽이 있는 곳을 제외하고는 5m를 넘지 않게 설치하는 것이 바람직하며, 레이커파일의 지중근입량(地中根入量)은 지질상태에 따라야 하나 최소한 1.5m-2m이상을 유지하는 것이 바람직하다.As a support pile for preventing the underground retaining wall from falling inwardly, a raker pile 30 is placed in the ground in the demolished space as shown in FIG. 3A. The installation interval of the raker pile is determined differently by the structural design according to the earth pressure and the condition of the structure (underground retaining wall), but in general, the horizontal distance between the rakers should be installed not more than 5m except where the bearing wall is located. Underground raker piles should be at least 1.5m-2m, depending on geological conditions.

레이커파일(30)의 설치 이후 이 레이커파일(30)에 지지되는 옹벽버팀용 레이커(32)를 경사를 달리하여 소정의 단수(段數)(예컨대 3단)로 설치하며, 이때 옹벽측 레이커단부의 지하옹벽면에 대한 지지는 도 3 b 및 도 3c에 도시한 바와 같이 레이커를 소정 두께(예컨대 t=15mm)의 거셋플레이트(Gusset Plate)(34) 등을 통해 지하옹벽(10)에 근입된 복수개의 앙카볼트(36)(예컨대 직경 25 mm짜리)에 체결함으로써 또는 이에 부가하여 2차 케미칼앵커링 처리함으로써 행할 수 있다.After the installation of the raker pile 30, the retainer wall support raker 32 supported by the raker pile 30 is installed in a predetermined number of stages (for example, three stages) with different inclinations, and at this time, the retainer wall side raker end portion The support for the underground retaining wall surface of the rocker is mounted on the underground retaining wall 10 through a gusset plate 34 having a predetermined thickness (for example, t = 15 mm) as shown in FIGS. 3B and 3C. This can be done by fastening to a plurality of anchor bolts 36 (for example, 25 mm in diameter) or by adding a secondary chemical anchoring treatment.

레이커파일(30) 및 레이커(32)의 설치가 완료된 이후, 도 3d에 도시한 바와 같이, 제1공정에서 존치되었던 옹벽(10 ) 내부의 옹벽측 기둥(14) 및 옹벽 내측의 내력벽(12), 그 내력벽(12)과 옹벽(10) 사이에 설치된 바닥슬라브(16) 및/또는 내력벽(12)과 옹벽(10) 사이에 걸쳐진 보(18), 그리고 옹벽라인으로부터 대략 2m정도 유지시켰던 바닥기초(20)를 소정길이(D2), 즉 대략 옹벽의 1m 이내까지 제거하여(D2≤1m) 차후 옹벽기초를 제거하기 쉽도록 한다.After the installation of the raker pile 30 and the raker 32 is completed, as shown in FIG. 3D, the retaining wall side pillars 14 inside the retaining wall 10 that existed in the first process and the bearing wall 12 inside the retaining wall are shown. A floor slab 16 installed between the bearing wall 12 and the retaining wall 10 and / or a beam 18 between the bearing wall 12 and the retaining wall 10, and a floor foundation maintained about 2 m from the retaining wall line. 20 is removed to a predetermined length D2, i.e., within about 1 m of the retaining wall (D2? 1 m) so that it is easy to remove the retaining wall foundation thereafter.

본 공정에서 레이커의 설치는 한 쪽에서 일정방향으로 차례대로 시공하는 것을 원칙으로 하며, 임시로 유지시켰던 옹벽측 기둥과 지하중간층 바닥 슬라브 등을 레이커의 설치와 병행하여 제거토록 하는 것은 이후에 진행되는 후술하는 공정과 관련하여 지하옹벽의 내측 중량을 최대한 줄이기 위한 것이다.In this process, the installation of the raker is to be carried out in one direction in order from one side, and the retaining wall pillar and the basement floor slab which were temporarily maintained in parallel with the installation of the raker are to be removed later. In connection with the process to reduce the inner weight of the basement retaining wall as much as possible.

제3공정 : Third process: 지하옹벽지지파일Underground retaining wall support pile 설치공정  Installation process

지하옹벽의 높이가 낮아 지하옹벽 전체의 하중의 크기가 비교적 적을 경우에는(예컨대, 지하 1층, 옹벽깊이 1~4m ), 레이커(32)에 의한 경사버팀지지만으로도 충분히 지하옹벽(10)을 들어올린 상태를 유지할 수 있어서(즉, 지하옹벽이 토압 등을 받아 옹벽 내측으로 전도(顚倒)하려는 수평방향력 및 지하옹벽이 자중에 의해 침강하려는 수직력을 레이커(32)가 모두 지지), 다수의 레이커(32)가 지하옹벽(10)을 들어올린 상태를 유지하는 동안에 그 지하옹벽을 그 하단부로부터 절개, 제거해 낼 수 있으나, 만약 지하옹벽의 높이가 비교적 높아서(예컨대 지하 2층 이상, 옹벽높이 5m 이상) 지하옹벽 자체의 무게와 옹벽외측 토압이 많을 때에는 복수의 레이커를 사용하더라도 그 레이커만으로는 지하옹벽을 떠받치기 어려운 경우도 있다. 따라서 이러한 경우에도 본 발명에 따른 상향식 슬라이스공법을 적용하기 위해서는 지하옹벽을 아래로부터 잘라내어 제거하는 동안 지하옹벽이 수직방향으로 침강하지 않도록 더 안정적으로 떠받쳐 지지하기 위한 별도의 수직력버팀부재가 필요하다. When the height of the basement retaining wall is low and the load of the entire basement retaining wall is relatively small (for example, the first basement, the retaining wall depth is 1 to 4m), the basement retaining wall 10 is sufficiently lifted even by the inclined support by the raker 32. Rake 32 can maintain the raised state (i.e., both the horizontal force under which the underground retaining wall is subjected to earth pressure, etc. and the vertical force under which the underground retaining wall is settled by its own weight). While the raker 32 maintains the basement wall 10 in a lifted state, the basement wall can be incised and removed from its lower end, but if the basement wall is relatively high (e.g., more than 2 stories below, 5m height of the retaining wall) Above) When the weight of the underground retaining wall itself and the earth pressure outside the retaining wall are high, it may be difficult to support the underground retaining wall with only the raker even if a plurality of rakers are used. Therefore, even in such a case, in order to apply the bottom-up slice method according to the present invention, a separate vertical force support member is required to support the base wall more stably so that the base wall does not settle in the vertical direction while the base wall is cut and removed from below.

본 공정은 이러한 경우에 필요한 필수적 또는 부가적 공정으로서, 그 시공순서는 전술한 제2공정 직후이며, 도 4a 내지 도 4d에 도시한 바와 같이, 레이커(32)의 설치가 완전히 끝난 후 옹벽측 바닥 기초부분을 소정간격(D3), 예컨대 약 5~7m 간격으로 절단 내지 파취하여 기초콘크리트를 완전히 제거시켜 바닥을 노출시킨 다음 본 공정의 핵심요소인 옹벽지지파일(40)을 5~7m 간격으로 설치한다. 이 옹벽지지파일(40)은 본 발명의 공법에 의해 지하옹벽을 그 아래로부터 제거해낼 수 있도록 지하옹벽을 떠받친 상태로 안정적으로 유지하는 기능을 갖는다. This process is an essential or additional process required in this case, and the construction procedure is immediately after the second process described above, and as shown in Figs. 4A to 4D, after the installation of the raker 32 is completed, the retaining wall side bottom is completed. The foundation part is cut or drilled at predetermined intervals (D3), for example, at intervals of about 5 to 7 m to completely remove the foundation concrete to expose the floor, and then install retaining wall support piles 40, which are the core elements of the process, at intervals of 5 to 7 m do. The retaining wall support pile 40 has a function of stably maintaining the underground retaining wall in a supported state so that the underground retaining wall can be removed from the bottom by the method of the present invention.

지하옹벽지지파일 설치공정은 구체적으로, 도 4a 내지 도 4d에 도시한 바와 같이, 지하옹벽(10)에 대하여 소정높이(H1)(예컨대 H1=1.5m) 간격으로 복수개씩(예컨대 6~9개씩) 군(群)을 이루어 삽입된 앙카볼트(42)(예컨대 25mm)에 소정 형상(예컨대 사각형)의 금속제 연결판(44)을 체결하고, 이 연결판에 옹벽(10)에 대해 수직으로 밀착시켜 세운 지하옹벽지지파일을 용접하는 방식에 의해 옹벽(10)과 옹벽지지파일(40)을 완전히 일체화함으로써 이루어지며, 이 옹벽지지파일(40)의 하단은 지중에 충분히 근입되어 견고하게 지지된다. 따라서 지하옹벽(10)은 그 하중이 옹벽지지파일(40)을 통해 수직방향으로 지반에 전달되며 수평방향으로의 전도력은 전술한 레이커(32) 및 레이커파일(30)에 의해 지지된다. Specifically, as shown in FIGS. 4A to 4D, the process of installing the basement retaining wall supporting piles is provided in plural numbers (for example, 6 to 9) at a predetermined height H1 (for example, H1 = 1.5m) with respect to the basement retaining wall 10. ) To the anchor bolt 42 (for example, 25 mm) inserted in a group to fasten the metal connecting plate 44 of a predetermined shape (for example, a square), and to the connecting plate perpendicularly to the retaining wall 10. The retaining wall 10 and the retaining wall support pile 40 are completely integrated by welding the underground retaining wall supporting pile, and the lower end of the retaining wall supporting pile 40 is sufficiently embedded in the ground and is firmly supported. Therefore, the base retaining wall 10 has its load transmitted to the ground in the vertical direction through the retaining wall support pile 40 and the conduction force in the horizontal direction is supported by the above-described raker 32 and the raker pile 30.

한편, 옹벽지지파일(40)이 설치된 부분에 대해서는 수평방향으로 휠쏘컷터날 이 통과할 수 없기 때문에, 도 4b에 도시한 바와 같이, 옹벽지지파일(40)을 옹벽(10)에 부착하여 세우기 이전에 그 옹벽지지파일이 위치하게 될 수직부분에 대하여 미리 상하방향 소정간격(H2)(예컨대, H2=1~1.2m)으로 수평절단금(46)을 넣어두어야 한다. 옹벽지지파일이 접하는 옹벽에 미리 넣어지는 이 수평절단금(46)의 수평방향 폭(W1)은 당연히 옹벽지지파일의 플랜지 폭(W2)보다 더 크게 한다(W1>W2). On the other hand, since the wheel saw blade cannot pass in the horizontal direction with respect to the portion where the retaining wall support pile 40 is installed, as shown in FIG. 4B, the retaining wall support pile 40 is attached to the retaining wall 10 before being erected. In the vertical portion where the retaining wall support pile is to be placed, the horizontal cutting metal 46 must be put in advance at a predetermined interval H2 (for example, H2 = 1 to 1.2 m). The horizontal width W1 of this horizontal cutting metal 46, which is preliminarily inserted into the retaining wall in contact with the retaining wall support pile, is naturally larger than the flange width W2 of the retaining wall support pile (W1> W2).

본 발명에 따른 지하옹벽 제거공법에 있어서 지하옹벽이 그 하단부로부터 순차 제거되어 나오면 그 순차 제거되는 양만큼 되메우기도 동시에 순차적으로 이루어지는 것이기 때문에 옹벽지지파일(40)이 지중에 지지되는 상태(매립깊이)도 지하옹벽제거공사의 경시적(經時的) 진행이 비례하여 더욱 깊어져 견고하게 지지되며, 아울러 옹벽지지파일(40)이 지지하는 지하옹벽의 하중의 크기는 지하옹벽제거공사의 경시적(經時的) 진행이 비례하여 점점 작아지게 된다. In the underground retaining wall removing method according to the present invention, when the underground retaining wall is sequentially removed from the lower end thereof, the retaining wall support pile 40 is supported in the ground because the amount of backfilling is sequentially made at the same time. The progression of the underground retaining wall removal construction is deeper and proportionally deeper, and the size of the load of the underground retaining wall supported by the retaining wall support pile 40 is time-dependent ( The progression becomes smaller proportionally.

한편, 레이커(32)의 제거 및 옹벽에 대한 옹벽지지파일(40) 연결부(앵커볼트에 의해 옹벽(10)과 옹벽지지파일(40)이 접합된 부위)의 연결해제는 후술하는 공정에 의해 그 해당높이만큼의 옹벽제거 및 토사 되메우기가 이루어졌을 때 행하여진다. On the other hand, the removal of the raker 32 and the disconnection of the retaining wall support pile 40 connection to the retaining wall (where the retaining wall 10 and the retaining wall support pile 40 are joined by the anchor bolt) are performed by the process described below. It is done when the retaining wall is removed and the soil refill is made by the height.

본 공정에서 미설명부호 43(도 4c)은 옹벽지지파일(40)의 연결판(44)에 대한 용접부(45)의 접착(용접)강도가 부족할 경우에 옹벽지지파일(40)의 플랜지부를 관통하여 체결되는 볼트를 나타낸다. In this process, reference numeral 43 (FIG. 4C) denotes a flange portion of the retaining wall support pile 40 when the adhesion (welding) strength of the welding portion 45 to the connecting plate 44 of the retaining wall support pile 40 is insufficient. Represents a bolt fastened through.

본 공정은 지하옹벽의 하중이 큰 경우, 예컨대 철거하고자 하는 지하옹벽의 높이가 지하 2층 이상인 때에 적용하는 것이 바람직한 경우로서 설명하였지만 지하 2층 미만인 경우에도 안전을 고려하여 적용할 수 있음은 물론이다. Although the present process has been described as a case where the load of the underground retaining wall is large, for example, when the height of the underground retaining wall to be removed is two or more underground levels, it can be applied in consideration of safety even when the underground retaining wall is less than two underground levels. .

제4공정 : 4th process: 차수(遮水)그라우팅Order grouting 공정 fair

제4공정은 필수적인 공정이 아니라 필요에 따라 선택적으로 추가할 수 있는 부가공정으로서, 제거하고자 하는 지하옹벽의 바깥쪽에 건수(乾水)가 흐르는 경우에 지하옹벽(10)을 그 하단부로부터 상향식으로 순차 수평 슬라이싱하여 제거할 때, 철수된 지하공간 내로 건수유입과 토사의 유실을 막기 위한 공정이다. 도 5a는 지하옹벽(10) 내측으로부터 지하옹벽을 바라본 사시도로서 도면 부호 50은 지하수위이고, 도면부호 52는 차수 그라우팅재를 주입하기 위하여 코어드릴로 지하옹벽(10)을 천공한 구멍을 나타낸다. 이 차수재 주입구멍(52)을 통해 옹벽 외측을 향하여 차수재(54)가 가압주입된다. 이 차수그라우팅재 주입용 천공구멍(52)은 차후에 후술하는 지하옹벽 절단블록체를 인양하기 위한 강철심 와이어를 체결하기 위한 구멍으로 활용될 수도 있다. The fourth step is not an essential step, but an additional step that can be selectively added as needed. When dry water flows to the outside of the underground retaining wall to be removed, the underground retaining wall 10 is sequentially moved upward from the lower end thereof. When removing by horizontal slicing, it is a process to prevent dry water inflow and loss of soil into the withdrawn underground space. FIG. 5A is a perspective view of the underground retaining wall from the inside of the underground retaining wall 10. The reference numeral 50 is an underground water level, and the reference numeral 52 indicates a hole drilled through the underground retaining wall 10 with a core drill for injecting the order grouting material. The filler 54 is pressurized through this filler injection hole 52 toward the outer side of the retaining wall. This order grouting material injection hole 52 may be used as a hole for fastening the steel core wire for lifting the underground retaining wall cutting block body to be described later.

도 5b는 지하옹벽 외측에 공사에 필요한 여유공간이 있을 경우, 전술한 도 5a에 따른 차수공정 대신에 옹벽 외측에서 수직방향으로 지반을 굴착하여 그 굴착된 구멍(56)을 차수재(58) 주입구멍으로 하는 것을 도시한 것이다. FIG. 5B shows that when there is a free space necessary for construction outside the basement retaining wall, the ground is excavated in the vertical direction at the outer side of the retaining wall instead of the ordering process according to FIG. It is shown to be a hole.

제5공정 : 5th process: 지하옹벽의Basement wall 기초바닥 제거공정  Foundation floor removal process

도 3b 에 도시된 것처럼 레이커파일(30) 및 레이커(32)에 의해지하옹벽(10)이 전도 및 침하되지 되지 않도록 견고하게 지지된 상태로 되면, 또는 이에 더하여 도 4d에 도시된 것처럼 옹벽(10)이 지하옹벽지지파일(40)에 의해 더욱 지지된 상태로 되면, 도 6에 도시된 바와 같이, 옹벽 하단부에 잔존하여 부착되어 있는 기초(20)가 제거된다. 이 작업은 휠쏘컷팅날을 사용하여 행하여도 되고 이와 아울러 착암기와 같은 브레이커를 병용하여도 좋다. 이러한 과정에 의해 옹벽 하단에 부착되어 있던 기초가 모두 제거되고 그 제거된 부위에 토사가 충진되면 이어서 이하의 공정이 시행된다. If the underground retaining wall 10 is firmly supported by the raker pile 30 and the raker 32 as shown in FIG. 3B to prevent it from falling down and sinking, or in addition, the retaining wall 10 as shown in FIG. 4D. ) Is further supported by the underground retaining wall support pile 40, the foundation 20 remaining and attached to the lower end of the retaining wall is removed, as shown in FIG. This operation may be performed using a wheel sawing blade, or may be used in combination with a breaker such as a rock drill. This process removes all the foundation attached to the bottom of the retaining wall, and when the soil is filled in the removed portion, the following process is performed.

제6공정 : 6th Step: 지하옹벽Underground retaining wall 상향식 순차제거 및 순차매립공정  Bottom-up Sequential Removal and Sequential Landfill Process

도 7a 내지 도 7e는 본 발명의 중심 공정인 지하옹벽 상향식 순차제거 및 순차매립공정을 나타내며, 지금까지 설명한 전술한 공정들은 본 공정을 실시하기 위한 준비공정에 해당한다고 볼 수 있다. 7A to 7E illustrate the underground retaining wall bottom-up sequential removal and sequential landfill processes, which are the central processes of the present invention, and the above-described processes may be considered to correspond to preparation steps for carrying out the present process.

도 7a는 본 발명의 핵심적 기술사상이 구현되는 방식을 알 수 있는 도면으로서, 도시한 바와 같이, 휠쏘커터날에 의해 옹벽(10)이 그 하단부로부터 소정의 폭만큼씩 수평으로 절개되어 제거되고 그 제거된 부위에 토사(S)가 반입된다. 7A is a view showing how the core technical idea of the present invention is implemented. As shown, the retaining wall 10 is horizontally cut from the lower end by a predetermined width and removed by a wheel saw cutter blade. Earth and sand (S) is carried in in the removed site | part.

옹벽(10)은 수평방향으로 소정의 폭(W2)과 높이(H2)만큼씩, 바람직하게는 가로(W2)×세로(H2) = 3~4m×1~1.2m 크기의 대략 직사각형 모양의 절단블록체(10B)형태로 지하옹벽 모체(10)로부터 분리된다. 이때 사용하는 지하옹벽 절단수단으로는 각종 커터(Cutter)가 사용될 수 있으며, 바람직하게는 콘크리트 및 철근콘크리트를 절단할 수 있으면서 절단반경이 70cm를 넘는 경우에도 사용할 수 있는 장비인 휠쏘컷터(Wheel Saw Cutter)가 현재로서 유용하다. 그러나 본 발명에서 옹벽절단수단으로서 사용하는 도구가 반드시 휠쏘커터에 국한되는 것은 아니며, 경우에 따라서는 와이어쏘컷터(Wire Saw Cutter), 레이저커터 내지 워터제트커터 등을 사용할 수도 있을 것이다.The retaining wall 10 is cut in a substantially rectangular shape by a predetermined width W2 and height H2 in the horizontal direction, preferably horizontal W2 × height H2 = 3 to 4 m × 1 to 1.2 m. It is separated from the base retaining wall matrix 10 in the form of a block 10B. Various cutters can be used as the means for cutting the underground retaining wall. Preferably, the wheel saw cutter is an equipment that can be used even when the cutting radius exceeds 70 cm while cutting concrete and reinforced concrete. ) Is useful at the moment. However, in the present invention, the tool used as the retaining wall cutting means is not necessarily limited to the wheel saw cutter, and in some cases, a wire saw cutter, a laser cutter, a water jet cutter, or the like may be used.

휠쏘커터는 지하옹벽에 접하여 설치되는 별도 수평레일기구에 장착되어 원격제어에 의해 무인구동된다. 휠쏘커터의 작동 메카니즘은 교량절단 등 이미 다른 분야에서 사용된 예에서와 같이 널리 공지되어 있으므로 본 명세서에서는 이에 대한 상세한 설명은 생략한다. The wheel saw cutter is mounted on a separate horizontal rail mechanism that is installed in contact with the underground retaining wall, and is unmanned by remote control. Since the operating mechanism of the wheel saw cutter is well known as in the example already used in other fields such as bridge cutting, the detailed description thereof is omitted here.

도 7b는 대략 직사각형 형태로 절개된 지하옹벽 절단블록체(10B)를 강철심 와이어(미도시) 등을 걸어 백호우(Back Hoe) 등에 의해 인양하기에 앞서 미리 지하옹벽 절단블록체(10B) 높이(H2)의 소정부분만큼, 예컨대 (1/2)×H2 정도만큼의 토사되메우기를 선행(先行)함으로써, 지하옹벽 절단블록체(10B)의 인발 이후 그 인발된 공간에 대한 토사충전(되메우기) 시간을 가능한 한 줄일 수 있도록 하는 것이며, 지하옹벽을 그 제거되는 동안 조금이나마 더 안정적으로 지지하는 데에 기여한다.FIG. 7B illustrates a height of the underground retaining wall cutting block 10B in advance before lifting the underground retaining wall cutting block 10B cut into a substantially rectangular shape by a back hoe or the like through a steel core wire (not shown). Soil filling (backfilling) time for the drawn space after drawing of the underground retaining wall cutting block 10B by preceding the soil refilling by a predetermined portion of H2), for example, (1/2) × H2. It is possible to reduce the energy loss as much as possible, and contributes to supporting the basement wall a little more stably during its removal.

또한 도 7b는 전술한 바와 같이 지하옹벽을 그 하부로부터 수평방향으로 소정높이만큼씩 절개하여 인발해 냄에 있어서 그 인발작업을 용이하게 하기 위하여 그 슬라이싱 각도를 옹벽 바깥쪽 하단을 향하여 경사지도록 한 것을 도시하고 있다 . 이 도면에 의해 알 수 있듯이, 지하옹벽 절단블록체(10B)의 절개면이 옹벽외측을 향하여 소정각도(θ)만큼 하향 경사짐으로써, 점선으로 표시한 것처럼, 그 지하옹벽 절단블록체()를 옹벽 내측으로 소정각도(예컨대 30°~ 45°) 기울여 화살표 A1방향으로 인발할 때에 그 기울여 빼내는 작업이 용이해진다. In addition, FIG. 7B shows that the slicing angle is inclined toward the outer bottom of the retaining wall in order to facilitate the drawing work when the basement retaining wall is cut out by a predetermined height in the horizontal direction from the lower part as described above. It is shown. As can be seen from this figure, the cut surface of the basement retaining wall cutting block 10B is inclined downward by a predetermined angle θ toward the outer side of the retaining wall, so that the basement retaining wall cutting block body When it draws in the direction of arrow A1 by inclining a predetermined angle (for example, 30 degrees-45 degrees) inside a retaining wall, the inclination work becomes easy.

한편, 이처럼 지하옹벽 절단블록체(10B)의 상단부를 옹벽 내측으로 소정각도(θ) 기울여 인발해 냄에 있어서, 예컨대 지하옹벽 절단블록체(10B)의 상단을 45°전방으로 기울인 상태에서 그 기울인 지하옹벽 절단블록체(10B)의 뒷면에 토사를 충진한 다음 그 지하옹벽 절단블록체(10B)를 전방으로 기울이기 이전의 직립상태로 되돌려 가압함으로써 그 인발부에 대한 뒷다짐을 행하면서 인발해 낼 수 있는데, 토양에 따라서는 이러한 화살표 A2 방향으로의 동작을 수회 반복하면서 지하옹벽 절단블록체(10B) 조금씩 순차적으로 인발해 내는 것이 바람직하다. On the other hand, in drawing the upper end of the basement retaining wall cutting block 10B at a predetermined angle θ toward the inside of the retaining wall, for example, the inclined upper end of the basement retaining wall cutting block 10B is tilted forward by 45 °. The soil is filled in the back surface of the basement retaining wall cutting block 10B and then pulled back while pressing the basement retaining wall cutting block 10B back to an upright state before tilting forward. It is preferable to draw out the underground retaining wall cutting block 10B little by little while repeating the movement in the direction of arrow A2 several times depending on the soil.

도 7c는 지하옹벽 절단블록체(10B)를 정면에서 보았을 때 그 형상이 직사각형 형상이 아니라, 예컨대 상광하협(上廣下狹)과 상협하광(上狹下廣)의 사다리꼴 모양이 횡방향으로 교대로 형성된 경우를 도시한 것이며, 도 7d 내지 도 7e는 이처럼 교대로 절개된 사다리꼴 옹벽절단블록체(10B)를 인발(引拔)하는 순서 및 그 인발순서와 관련한 토사되메우기량과의 관계를 도시한 도면이다. 7C shows that when the basement retaining wall cutting block 10B is viewed from the front, its shape is not rectangular, for example, the trapezoidal shape of the upper and lower narrow beams and the upper and lower beams alternate in the transverse direction. 7D to 7E illustrate the order of drawing the trapezoidal retaining wall cutting block bodies 10B thus alternately cut and the relationship with the amount of soil filling in relation to the drawing order. Drawing.

지하옹벽 절단블록체(10B)를 이처럼 상광하협(上廣下狹)의 사다리꼴 모양이 횡방향으로 교대로 형성되도록 절개할 경우에는 다음과 같은 이점이 있다. 즉, 도 7d에 도시한 것처럼 먼저 이들 교대로 인접하는 두 형상의 절단블록체 중 어느 것도 먼저 제거해 내기 이전에 전체적인 토사(S) 되메우기량을 지하옹벽 절단블록 체(10B) 높이(H2)의 대략 절반인 (1/2)×H2 높이까지 충전한 상태에서 인접하는 지하옹벽 절단블록체(10B) 중에서 하나 걸러씩 상협하광형(上狹下廣) 지하옹벽 절단블록체들(10B-1)를 1차로 제거하고, 그 상태에서 도 7e에 도시한 바와 같이 다시 토사(S) 되메우기를 지하옹벽 절단블록체(10B) 높이(H2)의 (2/3)×H2 내지 (3/4)×H2 높이까지 충전하며, 이어서 하나 걸러씩 남아있던 상광하협(上廣下狹)의 사다리꼴 지하옹벽 절단블록체(10B-2)를 2차로 제거해 낼 수 있다. 이 경우 2차로 제거되는 상광하협형 지하옹벽 절단블록체(10B-2)는 그 매립되어 있는 깊이가 1차로 인발되었던 상협하광형 지하옹벽 절단블록체(10B-1)보다 더 깊지만 그 형상이 상광하협(上廣下狹)으로서, 윗변에 비해 지중에 박힌 아래변이 짧아 인발에 필요한 힘에 그만큼 작아지기 때문에 문제로 되지 않는다. 이러한 절단 블록체의 형상 및 인발순서, 토사되메우기 높이의 차등시공은 절단블록체(10B)의 인발시 옹벽외측의 토사가 옹벽 내측으로 흘러들어올 개구면적을 최소화하는 데에 기여하며, 지하옹벽 절단블록체의 인발 이후에 그 제거된 하단부에 추가로 충전할 토사량 및 충전에 소요되는 시간을 줄이는 결과로 되어 지하옹벽의 저면을 신속하고 안정적으로 지중에 지지하는 데에 기여한다.When the basement retaining wall cutting block 10B is cut in such a way that the trapezoidal shape of the upper and lower straits is alternately formed in the transverse direction, there are the following advantages. That is, as shown in FIG. 7D, the total earth and sand S refilling amount is approximately equal to the height of the underground retaining wall cutting block sieve 10B before first removing any one of the two alternately shaped cutting block sieves as shown in FIG. 7D. In the state of being filled to half (1/2) × H2 height, each of the adjacent underground retaining wall cutting block bodies (10B) is replaced with the upper and lower beam type underground retaining wall cutting block bodies (10B-1). Removed first, and as shown in FIG. 7E, backfill the soil (S) again as (2/3) × H2 to (3/4) × H2 of the height H2 of the underground retaining wall cutting block body 10B. After filling up to the height, the trapezoidal underground retaining wall cutting block body 10B-2 of the Sanggwang Strait can be removed secondarily. In this case, the upper and lower narrow type underground retaining wall cutting block bodies 10B-2, which are secondarily removed, are deeper than the upper narrow type underground retaining wall cutting block bodies 10B-1 having their first embedded depths. It is not a problem because the lower side embedded in the ground is shorter than the upper side because it is smaller in the force required for drawing. The differential construction of the shape and drawing order of the cutting block body, and the fill-up level of the soil is contributed to minimizing the opening area of the soil outside the retaining wall when the cutting block body 10B is drawn into the retaining wall. The result is a reduction in the amount of soil to be additionally charged and the time taken for filling after the drawing of the sieve, which contributes to supporting the bottom of the underground retaining wall quickly and stably in the ground.

한편, 위와 같은 상광하협 지하옹벽 절단블록체(10B-1,2)간의 교차인발(交叉引拔) 및 되메우기 차등충전(差等充塡)시에 있어서도 그 상단 슬라이싱면은, 도 7b에 도시한 바와 같이, 지하옹벽 절단블록체를 옹벽 내측으로 소정각도 기울여 인발할 때에 그 기울여 빼내는 작업을 용이하게 할 수 있도록 하기 위하여 그 슬라이싱 각도를 옹벽 바깥쪽 하단을 향하여 소정각도(θ) 경사지도록 하는 것이 바람직함은 물론이다. On the other hand, the upper slicing surface is also shown in Fig. 7b at the time of the cross drawing and backfill differential charging between the above-mentioned Sanggwangha River Underground Retaining Wall Cutting Blocks 10B-1,2. As described above, it is preferable that the slicing angle be inclined at a predetermined angle θ toward the outer bottom of the retaining wall so that the base retaining wall cutting block body can be inclined at a predetermined angle inside the retaining wall to facilitate the pulling out of the retaining wall. Of course.

절단블록체가 기존 옹벽으로부터 분리되어 제거되면 즉시 적어도 그 해체되어 나온 이후의 옹벽 하단선 이상의 높이까지 토사 되메우기를 하며 동시에 장비를 이용하여 다짐을 줌으로써 옹벽 밖의 토사가 옹벽 내측으로 유입되어 들어오는 것을 방지하는 한편 옹벽하단의 지반에 대한 지지를 도모한다.As soon as the cutting block is separated from the existing retaining wall and removed, the soil is refilled to at least the height of the retaining wall below the retained wall at the same time, and the equipment is compacted to prevent the soil from entering the retaining wall. Promote support for the ground beneath the retaining wall.

위와 같은 순차적 상향식 슬라이스 공법에 의해 지하옹벽 제거과정은 도 7f내지 도 7i에 도시한 것처럼, 그 하단부로부터 점증적으로 제거되어 나옴과 동시에 그 순차 제거되는 높이만큼씩 되메우기가 동시에 순차적으로 이루어지는 것이며 옹벽 하단부로부터 제거가 이루어짐에 따라 옹벽을 다단으로 경사지지하고 있던 레이커(32)도 그 맨 아래쪽 레이커로부터 순차제거되고 필요에 따라 상단을 지지하기 위해 재설치되며 레이커가 모두 제거된 경우에는 레이커파일(30)도 제거된다. The process of removing the underground retaining wall by the sequential bottom-up slice method as shown in FIGS. 7F through 7I is gradually removed from the lower end thereof, and the backfill is sequentially sequentially removed by the height of the retaining wall at the same time. The raker 32, which was supporting the retaining wall in multiple stages as it is removed from the bottom, is also sequentially removed from the bottom raker and reinstalled to support the top if necessary, and the raker pile 30 when all the rakers are removed. Removed.

구체적으로 도 7g는 도 7f의 과정을 진행함에 있어서 토사되메움이 진행되어 더 이상 옹벽지지의 필요가 없게 된 하단측 레이커를 제거하는 한편 옹벽의 제거가 완료된 부분에 대해서는 그 옹벽을 지지하는데 사용되었던 레이커파일을 인발하는 개념을 도시한 것이며, 도 7h는 도 7g의 과정을 더 진행함에 있어서 지하층고가 높은 옹벽 쪽에 대한 지지기능을 담당하고 있던 레이커파일 중에서 그 공정의 진행에 따라 사명을 다하여 더 이상 존치의 필요가 없어진 경우 이를 제거하는 개념을 도시한 것이며, 도 7i는 레이커가 역활을 다함에 따라 최종적으로 남아있던 레이커지지파일에 대해서도 그 인발을 행하는 것을 나타내는 단면도, 그리고 도 7j는 지하옹벽이 모두 제거되고 그라운드라인까지 토사되메우기가 이루어진 상태에서, 지중 에 수직으로 매립되어 잔류되어 있던 지하옹벽지지파일을 최종적으로 인발해 내는 것을 도시한 단면도이다. Specifically, FIG. 7G is used to support the retaining wall for the portion where the retaining wall has been removed while removing the bottom side raker, which is no longer needed for retaining wall support due to the soil filling in the process of FIG. 7F. Figure 7h shows the concept of drawing the raker pile, Figure 7h is further maintained in the mission of the process according to the progress of the process among the raker pile that was in charge of the retaining wall side with a high basement floor in the process of Figure 7g Figure 7i is a cross-sectional view showing the removal of the last remaining raker support pile as the raker plays a role, and Figure 7j is a removal of all the underground retaining wall Landfill vertically to the ground, with the soil filled to the ground line It is a sectional view showing that that it eventually drawn into an underground retaining wall supporting files that have been retained air.

제7공정 : 7th Step: 지하옹벽지지파일Underground retaining wall support pile 인발제거공정Drawing Removal Process

전술한 제6공정이 모두 끝남으로써 지하옹벽이 모두 제거되고 이와 동시에 그라운드라인(Ground Line)까지 토사 되메우기가 이루어진 다음에는 최종적으로 지하옹벽지지파일(40)이 인발되어 제거됨으로써, 도 8에 도시된 바와 같이, 신축하고자 하는 대지의 지중에는 아무런 장애물이 매립되어 있지 않은 순수한 형태의 나대지를 얻게 되며, 이로써 본 발명에 따른 공법에 의한 지하옹벽 제거공사가 종료한다. After all of the sixth process is completed, all the underground retaining walls are removed, and at the same time, after the soil refilling is completed to the ground line, the underground retaining wall support pile 40 is finally drawn out and removed, thereby being shown in FIG. 8. As described above, in the ground of the site to be constructed, a bare land in a pure form without any obstacles is obtained, thereby completing the underground retaining wall removal construction by the construction method according to the present invention.

전술한 본 발명에 따른 공법의 시행에 있어서 레이커파일이나 레이커 또는 옹벽지지파일 등과 같은 구조부재의 갯수 내지 그 치수, 각 파일들의 지중근입량산정, 앵커볼트의 크기 및 정착길이, 연결판 등에 대한 볼트접합 또는 용접접합길이, 절단블록체의 크기 등과 같은 각 디멘젼은 현장조건에 따른 정확한 구조역학적 설계치수에 의해 구해질 수 있는 것으로서, 당연히 본 명세서에서 예시적으로 제시된 치수와 다를 수 있는 것으로 이해되어야 한다. 이는 본 명세서의 특허청구범위에 기재된 것을 특징으로 하는 공법의 적용시, 철거하고자 하는 대상물의 현장조건(건물조건, 지질조건, 인접환경조건 등)에 따라 정확한 구조계산이 뒷받침되어야 하는 것을 의미하는 것이며, 본 발명의 권리범위가 본 명세서에서 예시적으로 제시된 물 리적인 부재치수 등에 국한되게 해석되어서는 안된다는 것을 의미하는 것이다. In the implementation of the method according to the present invention described above, the number and dimensions of structural members such as raker piles, rakers, or retaining wall support piles, calculation of underground root penetration of each pile, size and anchoring length of anchor bolts, connecting plates, etc. It is to be understood that each dimension, such as the length of the joint or the welded joint, the size of the cutting block, etc., may be determined by the exact structural design dimension according to the field conditions, and may be different from the dimensions exemplarily shown in the present specification. . This means that when applying the method characterized in that it is described in the claims of the present specification, accurate structural calculation must be supported according to the site conditions (building conditions, geological conditions, adjacent environmental conditions, etc.) of the object to be removed. It is meant that the scope of the present invention should not be construed as being limited to the physical absent dimensions, etc., which are presented by way of example herein.

본 발명에 따른 전술한 바와 같은 지하옹벽제거공법은 기존 흙막이 공사에 비하여 토사의 중복반입과 중복반출, 반입된 토사의 내부 굴토 등 번거로운 작업을 없앨 수 있어서 공기를 현저히 단축시킬 수 있고, 기존 흙막이 공사에 비하여 공사비를 상당한 수준으로 줄일 수 있을 뿐만 아니라, 옹벽외부의 파일천공으로 인한 도로점용 등 흙막이 공사와 관련하여 추가 준비하여야할 제반사항을 일시에 해결할 수 있으며, 소음, 기타 민원 등을 사전에 차단할 수 있으며, 지하옹벽제거가 대단히 어려운 난공사에 대해서도 유용하게 적용할 수 있다.  Underground retaining wall removal method as described above according to the present invention can eliminate the cumbersome work, such as overlapping the carry-in and over-export of the soil, and the internal excavation of the soil to be carried out compared to the existing earthquake construction can significantly shorten the air, the existing earthquake construction Compared to this, the construction cost can be reduced to a considerable level, and additional matters to be prepared in connection with the construction of the retaining wall, such as road use due to pile drilling outside the retaining wall, can be solved at once, and noise and other civil complaints can be blocked in advance. In addition, it can be usefully applied to difficult construction that is difficult to remove the underground retaining wall.

Claims (8)

토압을 받고 있는 지하옹벽을 제외한 옹벽 내측 지하구축물을 제거하는 지하옹벽 내부구조물 제거공정과;A process of removing the internal structure of the underground retaining wall to remove the internal structure of the retaining wall except the underground retaining wall under earth pressure; 지하옹벽 내부의 구조물이 제거됨으로써 생긴 공간의 지중에 레이커파일을 박고 이 레이커파일에 옹벽버팀용 레이커를 걸어 옹벽을 지지하는 레이커파일 및 레이커 설치공정(제1공정)과; A raker pile and a raker installation process (first step) that puts the raker pile in the ground of the space created by the removal of the structure inside the basement wall and hangs the retainer wall retainer on the raker pile to support the retaining wall; 지하옹벽을 그 아래측으로부터 소정의 형상과 크기로 절개하는 지하옹벽 부분절개공정(제2공정)과; 그리고,An underground retaining wall partial cutting step (second step) for cutting the underground retaining wall into a predetermined shape and size from a lower side thereof; And, 상기 제2공정에 의해 옹벽의 하단부로부터 부분절개된 지하옹벽 절단블록체를 인양하여 제거함과 아울러 적어도 그 지하옹벽 절단블록체가 제거된 높이 이상으로 토사 되메우기를 실시하는 과정을 반복적으로 실시함으로써 지하옹벽을 그 하단측으로부터 위쪽으로 향하여 상향식으로 제거하는 지하옹벽 절단블록체 순차인양 및 토사 순차 되메우기공정(제3공정);By removing the base retaining wall cutting block body partially cut from the lower end of the retaining wall by the second step, and repeating the process of refilling the soil by at least the height at which the underground retaining wall cutting block body is removed, the base retaining wall is repeatedly formed. Sequential lifting of the underground retaining wall cutting block sieve to be removed from the bottom side upwards from the bottom side and backsoil sequential refilling (third step); 을 포함하는 것을 특징으로 하는 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법.Bottom-up sequential removal and sequential landfill method for removing the underground retaining wall comprising a. 제1항에 있어서, The method of claim 1, 지하옹벽의 절개는 휠쏘컷터(Wheel Saw Cutter)에 의해 이루어지는 것을 특 징으로 하는 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법. Bottom-up sequential removal and sequential reclamation method for removing the underground retaining wall, characterized in that the cutting of the underground retaining wall is made by a wheel saw cutter. 제1항에 있어서,The method of claim 1, 상기 제1공정 이후 제2공정 이전에 소정간격을 두어 지하옹벽지지파일을 옹벽에 일체화시켜 그 지하옹벽지지파일로 하여금 지하옹벽의 수직하중을 지반에 지지시키는 지하옹벽지지파일설치공정이 더 실시되는 것을 특징으로 하는 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법.The basement retaining wall support pile installation step of integrating the retaining wall support pile into the retaining wall at a predetermined interval after the first step and before the second process allows the base retaining wall supporting pile to support the vertical load of the retaining wall on the ground. Bottom-up sequential removal and sequential landfill method for removing the underground retaining wall, characterized in that. 제3항에 있어서, The method of claim 3, 지하옹벽지지파일설치공정은 지하옹벽에 소정높이 간격으로 복수개씩 군을 이루어 삽입된 앙카볼트에 대하여 소정 형상의 금속재 연결판을 체결하고, 이 연결판에 대하에 옹벽에 수직으로 밀착시켜 세운 지하옹벽지지파일을 접합함으로써 옹벽과 옹벽지지파일을 일체화시키는 한편, 지하옹벽지지파일의 하단이 지중에 근입되어 지반에 지지됨으로써 옹벽의 하중이 지하옹벽지지파일에 의해서 지중에 전달되도록 하는 것을 특징으로 하는 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법. In the process of installing the base retaining wall support pile, the base retaining wall is formed by fastening a metal connecting plate of a predetermined shape to an anchor bolt inserted into a plurality of groups at a predetermined height interval to the underground retaining wall and vertically adhering to the retaining wall. The retaining wall and the retaining wall support pile are integrated by joining the support piles, while the lower end of the underground retaining wall support pile enters the ground and is supported by the ground so that the load of the retaining wall is transferred to the ground by the underground retaining wall support pile. Bottom-up Sequential Removal and Sequencing to Remove Retaining Walls. 제3항 또는 제4항에 있어서,The method according to claim 3 or 4, 상기 옹벽지지파일을 옹벽에 부착하여 세우기 이전에 미리 그 옹벽지지파일이 위치하게 될 옹벽의 수직부분에 대하여 상하방향 소정간격을 두어 수평절개홈을 형성하며, 이 때 그 수평절개홈의 수평방향 폭은 옹벽지지파일의 폭보다 더 큰 것을 특징으로 하는 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법. Before attaching the retaining wall support pile to the retaining wall, the horizontal cut groove is formed with a predetermined interval in the vertical direction with respect to the vertical portion of the retaining wall where the retaining wall support pile is to be placed in advance, wherein the horizontal width of the horizontal cut groove is Bottom-up sequential removal and sequential landfill method for removing the underground retaining wall, characterized in that greater than the width of the retaining wall support pile. 제3항 또는 제4항에 있어서,The method according to claim 3 or 4, 상기 제3공정을 그라운드레벨까지 완료한 이후 지하옹벽지지파일을 인발하여 제거하는 공정을 더 실시하는 것을 특징으로 하는 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법. The bottom-up sequential removal and sequential reclamation method for removing the underground retaining wall further comprising the step of drawing and removing the underground retaining wall support pile after completing the third step to the ground level. 제1항 또는 제3항에 있어서,The method according to claim 1 or 3, 상기 제2공정에 앞서서 지하옹벽에 차수재 주입구멍을 뚫거나 옹벽의 외측에서 그 옹벽에 바로 접하여 지중에 수직방향으로 이 차수재 주입구멍을 뚫고, 그 차수재주입구멍을 통해 옹벽의 외측을 향하여 차수재를 가압주입하는 공정이 더 실시되는 것을 특징으로 하는 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법. Prior to the second step, drill a filler injection hole in the basement retaining wall or directly contact the retaining wall on the outer side of the retaining wall and drill the filler injection hole in the vertical direction in the ground, and through the filler refilling hole toward the outside of the retaining wall. Bottom-up sequential removal and sequential landfill method for removing the underground retaining wall, characterized in that the pressure injection process is further carried out. 제1항 또는 제 3항에 있어서, The method according to claim 1 or 3, 상기 제2공정에 따라 상기 지하옹벽이 그 아래측으로부터 소정의 형상과 크기로 부분절개되는 절단블록체는 상협하광사다리꼴과 상광하협사다리꼴이 수평방향으로 교대로 반복형성되는 형태의 것이고, 그 제거순서는 상협하광사다리꼴 절단블록체들이 먼저 제거된 다음 이어서 상광하협 사다리꼴이 제거되며, 이때 상협하광 사다리꼴 절단블록체들을 제거할 때의 토사되메움높이보다 상광하협 사다리꼴 절단블록체들을 제거할 때의 토사되메움높이가 더 높은 것을 특징으로 하는 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법. According to the second step, the cutting block body in which the basement retaining wall is partially cut from the lower side into a predetermined shape and size is of a type in which the upper and lower trapezoids and the upper and lower trapezoids are alternately repeatedly formed in the horizontal direction, and the removal order thereof is removed. When the upper and lower trapezoidal cutting block bodies are first removed, and then the upper and lower trapezoidal trapezoids are removed, and when the upper and lower trapezoidal cutting block bodies are removed, Bottom-up sequential removal and sequential reclamation method for removing underground retaining walls characterized by a higher filling height.
KR1020060086412A 2006-09-07 2006-09-07 Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall KR100736241B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060086412A KR100736241B1 (en) 2006-09-07 2006-09-07 Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060086412A KR100736241B1 (en) 2006-09-07 2006-09-07 Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall

Publications (2)

Publication Number Publication Date
KR20060103309A true KR20060103309A (en) 2006-09-28
KR100736241B1 KR100736241B1 (en) 2007-07-06

Family

ID=37623362

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060086412A KR100736241B1 (en) 2006-09-07 2006-09-07 Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall

Country Status (1)

Country Link
KR (1) KR100736241B1 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101410471B1 (en) * 2014-01-16 2014-06-23 주식회사 백산이앤티건설 Method for buttom-up removal of underground retaining wall by using h-piles remained in earth retaining work of existed building
CN108166770A (en) * 2017-11-27 2018-06-15 广东精特建设工程有限公司 Exempt from a kind of cutting method of support about the cutting of building structure column
JP2019206860A (en) * 2018-05-30 2019-12-05 花田 卓蔵 Demolition method of underground structure
KR20210053497A (en) * 2019-11-04 2021-05-12 박차순 Fileless-up wall demolition method
KR102301605B1 (en) 2021-01-22 2021-09-10 차상호 A Method of Bottom-up Removal of Underground Structures
KR102400229B1 (en) 2021-12-20 2022-05-20 박차순 Method for demolishing underground building
CN115012428A (en) * 2022-06-22 2022-09-06 中国二十二冶集团有限公司 Basement deep foundation pit replacing support and construction method thereof
CN115306300A (en) * 2022-08-22 2022-11-08 苏州大学 Horizontal long-distance obstacle clearing device and omnibearing high-pressure injection grouting method
KR102551029B1 (en) 2022-05-02 2023-07-04 박차순 Low noise and low vibration safely cutting and demolishing method of building structure
KR20230105190A (en) 2022-01-03 2023-07-11 박차순 Method for demolishing underground building

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100877974B1 (en) * 2008-03-06 2009-01-14 주식회사 백산이앤티건설 Reverse removing method of underground retaining wall using bottom-up cut and gradual land infilling with struts
JP5971546B2 (en) * 2012-01-27 2016-08-17 花田 卓蔵 Demolition method of underground concrete structure near boundary
KR101481073B1 (en) 2014-03-17 2015-01-13 주식회사 승일토건 Method for removing underground structure
KR20210051326A (en) 2019-10-30 2021-05-10 박차순 Batch down wall demolition method
KR102499297B1 (en) * 2022-08-17 2023-02-14 이기환 Structure and Method for Supporting Retaining Wall using Raker
KR102503595B1 (en) 2022-09-23 2023-02-24 주식회사 이산하이테크 Energy reduction underground retaining wall demolition method
KR102550128B1 (en) 2022-09-23 2023-06-30 주식회사 이산하이테크 Demolition and new construction method of underground retaining wall using H-beam technology to which tensile stress is applied
KR102542559B1 (en) * 2023-02-07 2023-06-14 이기환 Structure and Method for Supporting Retaining Wall using Raker

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3724320B2 (en) 2000-03-17 2005-12-07 鹿島建設株式会社 Construction method for underground structures
KR100412162B1 (en) 2001-09-25 2003-12-24 (주)신성엔지니어링 Method of construction for excavating the ground by using trusstype support structures
KR100450575B1 (en) * 2002-08-20 2004-10-06 한국산업안전공단 a land-side protection wall for trench excavation work
KR100502489B1 (en) * 2003-04-11 2005-07-21 박노일 machin for removary of the obstacles a steel-concrete building

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101410471B1 (en) * 2014-01-16 2014-06-23 주식회사 백산이앤티건설 Method for buttom-up removal of underground retaining wall by using h-piles remained in earth retaining work of existed building
CN108166770A (en) * 2017-11-27 2018-06-15 广东精特建设工程有限公司 Exempt from a kind of cutting method of support about the cutting of building structure column
JP2019206860A (en) * 2018-05-30 2019-12-05 花田 卓蔵 Demolition method of underground structure
KR20210053497A (en) * 2019-11-04 2021-05-12 박차순 Fileless-up wall demolition method
KR102301605B1 (en) 2021-01-22 2021-09-10 차상호 A Method of Bottom-up Removal of Underground Structures
KR102400229B1 (en) 2021-12-20 2022-05-20 박차순 Method for demolishing underground building
KR20230105190A (en) 2022-01-03 2023-07-11 박차순 Method for demolishing underground building
KR102551029B1 (en) 2022-05-02 2023-07-04 박차순 Low noise and low vibration safely cutting and demolishing method of building structure
CN115012428A (en) * 2022-06-22 2022-09-06 中国二十二冶集团有限公司 Basement deep foundation pit replacing support and construction method thereof
CN115306300A (en) * 2022-08-22 2022-11-08 苏州大学 Horizontal long-distance obstacle clearing device and omnibearing high-pressure injection grouting method

Also Published As

Publication number Publication date
KR100736241B1 (en) 2007-07-06

Similar Documents

Publication Publication Date Title
KR100736241B1 (en) Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall
US20110142550A1 (en) Method for constructing a chair-type, self-supported earth retaining wall
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
KR101410471B1 (en) Method for buttom-up removal of underground retaining wall by using h-piles remained in earth retaining work of existed building
CN110042716B (en) Widening construction method for high-fill roadbed with foamed light soil
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
AU2010350042B2 (en) Method and assembly for constructing a diaphragm wall
KR100967497B1 (en) Method for constructing an underground structure
KR102234513B1 (en) Block type reinforcement retaining wall structure and constructing method for the same
KR101041274B1 (en) Retaining wall grouting structure and method for constructing thereof
JP5937488B2 (en) Temporary support method for foundation
KR100877974B1 (en) Reverse removing method of underground retaining wall using bottom-up cut and gradual land infilling with struts
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR20110096339A (en) Construction method of undergroud structure using phc pile
KR20130021952A (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
KR102617795B1 (en) Retaining wall system combine H-piles with steel reinforcement structure
KR101117924B1 (en) Composite type steel temporary construction and construction method thereof
KR102150531B1 (en) Retaining wall structure using vertical underground insert and its construction method
JP3930954B2 (en) Construction method of structure
CN210087321U (en) Pile foundation pre-reinforcing and supporting structure for controlling tunnel settlement
KR102292152B1 (en) Top-down construction method with underground utility
KR20110034831A (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR100477357B1 (en) Construction method for retaining of earth

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130628

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140612

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150420

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160628

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170623

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180828

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20190604

Year of fee payment: 13