AU2010350042B2 - Method and assembly for constructing a diaphragm wall - Google Patents

Method and assembly for constructing a diaphragm wall Download PDF

Info

Publication number
AU2010350042B2
AU2010350042B2 AU2010350042A AU2010350042A AU2010350042B2 AU 2010350042 B2 AU2010350042 B2 AU 2010350042B2 AU 2010350042 A AU2010350042 A AU 2010350042A AU 2010350042 A AU2010350042 A AU 2010350042A AU 2010350042 B2 AU2010350042 B2 AU 2010350042B2
Authority
AU
Australia
Prior art keywords
primary
casting
section
sacrificial
assembly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
AU2010350042A
Other versions
AU2010350042A1 (en
Inventor
Ping Cheung Chan
Alain Deletang
Olivier Haye
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
VSL International Ltd
Original Assignee
VSL International Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by VSL International Ltd filed Critical VSL International Ltd
Publication of AU2010350042A1 publication Critical patent/AU2010350042A1/en
Application granted granted Critical
Publication of AU2010350042B2 publication Critical patent/AU2010350042B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/13Foundation slots or slits; Implements for making these slots or slits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • E02D19/185Joints between sheets constituting the sealing aprons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A method is disclosed for constructing a diaphragm wall by casting alternate primary (10, 11) and secondary (20) panels in the ground. The primary panels (10, 11) are excavated and cast first, and a cutter joint (15) or similar jointing profile is then milled into the side faces of the primary panels (10, 11) before casting the secondary panels (10). The primary panel casting regions are prepared for casting by positioning sacrificial displacement elements (31) in the regions where joint milling is to be performed. The sacrificial displacement elements (31) may be hollow elements or blocks of relatively easily millable material such as lightweight concrete. Primary panels (10, 11) cast in this way can be milled more easily, and particularly when the milling tool is at an angle to the surface being milled.

Description

1 Method and assembly for constructing a diaphragm wall The present invention relates to the field of civil engineering, and in particular to the excavation and construction of cast concrete structures, such as diaphragm walls, below ground level. 5 Diaphragm walls, also known as slurry walls, are constructed to form a water-blocking and earth-retaining barrier surrounding underground structures such as tunnels, basements or roadway cuttings. A diaphragm wall is essentially an impermeable vertical concrete wall which is cast in situ in the ground. In order to construct such a diaphragm wall, 10 a trench is first excavated which defines the casting volume for the concrete. The trench is kept full of slurry until the concrete is poured, in order to keep the sides of the trench from falling in. After the trench has been excavated, reinforcing steel is lowered into the trench, and the concrete is then poured, displacing the slurry and filling the volume around the reinforcing steel. 15 In prior art methods of constructing diaphragm walls, the wall is conventionally constructed in alternating sections. First, a number of spaced apart primary wall panels are excavated, poured and allowed to harden. In the following description, the panels which are cast first are referred to as primary panels or primary sections. The spaces between the hardened primary panels 20 are then excavated and filled with concrete to form a set of secondary panels, also known as closing panels. In both cases, rebar cages are usually placed into the trenches before the concrete is poured. When the secondary panels are excavated, using a hydromill, for example, the side faces of the primary panels can also be milled to remove any soil from the concrete, and to create a 25 clean, textured surface against which the concrete of the secondary panel can be cast. The milling removes concrete from the side face of the primary panels and creates a cutter-milled joint, or similar profile, which will ensure a soil-free joint with the concrete of the adjacent secondary panel when it is poured. The excavation of the secondary panels is conventionally performed 30 using a hydromill, which is a large vertical excavation machine, lowered into the 2 trench by crane. Hydromills are typically 2.8m in width, and from 60cm to 1.5m in thickness. At its lower extremity, a conventional hydromill has two sets of counter-rotating toothed wheels which remove material from the trench. The hydromill's toothed wheels also remove some material from the sides of the 5 adjacent primary panels, creating the cutter-joint profiles referred to above. The milled profile may for example consist of a series of vertical grooves milled deep (50mm to 100mm) into the concrete of the primary panels. The purpose of these recesses is to create a clean interlocking bond between the primary and secondary panels when the concrete for the latter is poured. The shape of 10 the milled profile may be a regular pattern of grooves or indentations, or simply a roughened surface, depending on the type of milling wheel and teeth arrangement used. Once the milling and excavation of the casting volume for the secondary panels is complete, the secondary reinforcement cage is lowered 15 into the excavated secondary casting volume, and the concrete is poured around it and allowed to cure. After curing, the primary and secondary panels form a continuous concrete wall in the ground, each pair of neighbouring panels being strongly mechanically joined to each other by the cutter joint profile described above. 20 In some constructions, such as a curved diaphragm wall, it may be necessary for some or all of the primary and secondary panels to be positioned at an angle to each other. However, conventional hydromills or cutters generally have fixed-orientation milling heads with toothed wheels which are designed to cut a rectangular section, which means that, where such a hydromill or cutter is 25 used to excavate a secondary panel which is angled to its neighbouring primary panel, the milling will be performed at an angle to the side face of the primary panel. As a result of this angled milling, the amount of material to be removed during milling of the primary panel sides will vary significantly across 30 the side face of the primary panel. Instead of milling all across the joint at a roughly equal depth into the primary panel concrete (generally 50mm to 200mm 3 in the case of coplanar abutting panels), the angle of the hydromill may be such that the depth of milling may be as much as 600mm at the inner edge of the milled joint, or even more, depending on the angle and thickness of the wall panels. Milling such a large amount of material out of the primary panel is time 5 consuming, wasteful of good quality concrete, increases the amount of waste material to be removed and shortens the life of the cutter tools. Embodiments of the invention may propose the use of sacrificial void formers, also referred to as displacement elements, which can be milled away to create a clean edge against which the adjacent section can be cast. It is 10 known to use sacrificial elements in the casting of concrete structures. W02003/006750, for example, discloses the use of corrugated tubular elements which fill the width of an empty trench, acting as temporary shuttering for successive sections. The empty, open-ended tube is fixed to the reinforcing cage and placed in the trench. The tube is then filled with gravel or sand to give 15 it enough strength to withstand the pressure of the concrete during casting. During the excavation of the adjacent section the tube is broken up and removed, together with its contents. This method has the disadvantage that the tube must be sealed and filled with gravel or sand after it is placed in the trench. This is a time-consuming process and can lead to gravel and sand 20 falling into the trench, thereby compromising the integrity of the casting in the lower region of the trench. Once the reinforcement cage and the tube have been lowered into the trench, there is no longer any way of excavating material which subsequently falls into trench. Furthermore, the bentonite slurry normally used to fill the trench before casting can begin to "cake" on to the walls of the 25 trench, and any delay in the pouring of concrete results in increased caking, with consequently reduced concrete coverage. For this reason, it is important to minimise the amount of time between the placing of the reinforcement cage and tube, and the pouring of the concrete. Having to fill the tube with sand and gravel adds significantly to this time. Furthermore, the concave faces which 30 remain once the tube and its contents have been excavated using the method of W02003/006750 cannot be milled directly, so a two-stage excavation process is used, in which half of the tube is removed using a convention grab or hydromill, and the other half is excavated using a specially-shaped grab with a semi-circular profile.
4 An embodiment of the present invention, therefore, may provide a method of constructing a diaphragm wall which will enable the side faces of the primary panels to be milled more quickly, while affording maximum clearance 5 for fitting the rebar cage, without the need for specially shaped excavation tools, without the risk of spilling foreign matter into the trench, while reducing wastage of good concrete and with reduced wear of the cutter tools, even when the milling cutter is oriented at an angle to the primary panel. In this application the terms primary panel and primary section are 10 used interchangeably, as are the terms secondary panel and secondary section. The term milling is used to mean any process for removing material from the surface of the primary panels. Such processes can include mechanical abrasion by the toothed wheels of a hydromill, for example, or high-pressure water jets or other suitable mechanical processes. 15 A first aspect of the invention provides a method for casting a diaphragm wall comprising two primary sections joined by a secondary section, the method comprising a first step of excavating a casting volume for each primary section, a second step of casting the primary sections in the primary casting volumes, a third step of excavating a secondary casting volume for 20 casting the secondary section, a fourth step of forming a joining surface profile on each primary section by milling an adjoining region of each adjacent primary section, the second step comprises arranging a prefabricated sacrificial displacement element in the sacrificial joining region of one or both of the primary casting volumes, positioned such that the casting material of the 25 primary sections is displaced by the sacrificial displacement element in the or each joining region and such that the removal of the or each sacrificial joining region performed in the fourth step includes the removal of the or each sacrificial displacement element. In an embodiment, the third and/or fourth steps comprise removing the sacrificial displacement elements.
5 According to a variant of the method of the invention, the third and fourth steps are performed simultaneously. Excavating and milling in the same operation, for example, saves time and equipment. According to another variant of the method of the invention, the 5 primary and secondary sections are substantially planar and vertical, and the secondary section is cast in a plane which is at an angle other than 180 to the plane of at least one of the primary sections. Angled sections such as these are often used in the construction of containment tanks, for example, or deep shafts. 10 According to another variant of the method of the invention, the second step includes constructing a casting preparation assembly comprising a reinforcement element for reinforcing each primary section, securing the sacrificial displacement elements to the reinforcing element, and arranging the casting preparation assembly in the respective primary casting volume. In this 15 way, the reinforcement and the sacrificial displacement elements can all be lowered into the trench at once, and casting can begin without any delay. According to another variant of the method of the invention, the second step includes arranging separator elements to hold each sacrificial displacement element in position at a predetermined distance from the 20 reinforcing element. According to another variant of the method of the invention, each prefabricated sacrificial displacement element is made of a material which is more easily millable than the concrete used for casting the primary section in which said each prefabricated sacrificial displacement element is cast. 25 Another aspect of the invention provides a casting preparation assembly for placing into an excavated primary casting volume for casting a primary section of a concrete diaphragm wall, the primary section having at least one adjoining region, the or each adjoining region being a region of the primary section to be milled for creating a joining surface profile for joining the 30 primary section to an adjacent secondary section of the diaphragm wall, 6 wherein the assembly comprises at least one prefabricated sacrificial displacement element, the or each sacrificial displacement element being made of a more easily millable material than the concrete used for casting the primary section, the or each sacrificial displacement element being positioned in the 5 casting preparation assembly such that, when the casting preparation assembly is placed into the primary casting volume and the primary section has been cast, the or each sacrificial displacement element is in an adjoining region for being removed during milling of the adjacent secondary section. According to another variant of the invention, the assembly 10 comprises a reinforcement structure for providing reinforcement for the primary section when the primary section is cast, the or each sacrificial displacement element being secured to the reinforcement structure. According to another variant of the invention, the material of each prefabricated sacrificial displacement element is softer, or more brittle, or more 15 friable, or less dense than the concrete used to cast the primary sections. According to another variant of the invention, the joining surface profile comprises one or more grooves formed in the material of the primary section. According to another variant of the invention, each prefabricated 20 sacrificial displacement element comprises at least two more prefabricated modules. By assembling the sacrificial displacement elements in modular fashion, the assembly process can be simplified and speeded up. According to another variant of the invention, each prefabricated sacrificial displacement element has a prism shape of substantially triangular or 25 trapezoidal cross-section. The shape of the displacement elements can be selected to suit an angled orientation between the primary and secondary sections, for example, thereby reducing the amount of casting concrete which must be milled in order to create the required angled joint.
7 According to another variant of the invention, the or each sacrificial displacement element comprises one or more void forming members for excluding concrete from one or more regions of the primary casting volume. According to another variant of the invention, one or more of the 5 prefabricated sacrificial displacement elements or modules encloses a hollow void. According to another variant of the invention, one or more of the prefabricated sacrificial displacement elements or modules comprises a solid block. 10 According to another variant of the invention, the secondary section volume is excavated using a hydromill. According to another variant of the invention, one or both of the primary casting volumes are excavated using a hydromill. According to another variant of the invention, the hydromill is slightly 15 wider than the distance separating the two primary casting volumes. The relative widths can be predetermined so that a single pass of the hydromill can achieve the desired (angled, if appropriate) milling on both of the adjacent primary sections. Embodiments of the invention will now be described, by way of 20 example only, with reference to the accompanying non-limiting drawings, in which: Figure 1 shows a schematic cross-sectional view of a typical prior art method of constructing the primary panels for a diaphragm wall. Figure 2 shows in schematic cross-section a view of the prior art 25 method of constructing the secondary panels, and milling the edges of the primary panels, to create a diaphragm wall.
8 Figures 3a and 3b show schematic elevation and plan views illustrating the regions to be milled when the primary and secondary panels are mutually angled. Figures 4a and 4b show in schematic plan and perspective view an 5 example of diaphragm wall sections constructed according to an embodiment of the present invention. Figures 4c, 4d and 4e show in schematic plan view a sequence of constructing a closing (secondary) panel using a method according to an embodiment of the present invention. 10 Figures 5a, 5b and 5c show in schematic elevation view an example of how a primary panel casting can be prepared according to an embodiment of the invention. Figure 6 shows in more detail a schematic elevation view of the prepared primary section casting assembly according to an embodiment of the 15 invention. The accompanying figures are intended as an aid to understanding the invention, and are not intended to imply any limitation of the scope of the invention. Where the same reference signs are used in different drawings, these reference signs are intended to refer to the same or corresponding 20 features. The prior art method of constructing a diaphragm wall will now be described in more detail with reference to figures 1, 2, 3a and 3b. In figure 1, the process of excavating, preparing and casting the primary panels is shown. Regions 10, 11, 12, 13 and 14 are five primary section casting regions in the 25 ground 3 which show successive stages of excavating and casting the primary panels. Region 10 shows a primary panel region before excavation, while region 11 shows a primary panel region being excavated using a crane mounted (8) scoop grab tool, although a hydromill 9 can also be used for this excavation step. The excavated trench is kept filled with water or slurry (not 9 shown) to prevent the sides of the trench from falling inwards. Region 12 is shown fully excavated, and having a steel reinforcement (rebar) cage 4 lowered into it. Region 13 shows the concrete 5 being poured into the primary casting region around the steel of the reinforcement cage 4, with the concrete being 5 introduced using pipe or chute 6, and region 14 is shown after the casting is completed and the primary panel has been allowed to cure. Figure 1 also shows four regions 20, 21, 22 and 23 which are to be excavated for the casting of secondary panels. Figure 2 shows the arrangement of figure 1 in which the casting of 10 the primary panels has been completed ready for the casting of four secondary panels 20 to 23 between primary panels 10 to 14. Region 20 shows a secondary panel casting region before excavation. Region 21 is shown in the process of being excavated using a hydromill 9 which removes the soil and mills the side faces of the neighbouring primary panels, in order to facilitate a 15 good bond between the two adjacent sections, and thereby achieve a joint which has good water-blocking properties. The hydromill 9 is shown being lowered down into the excavation zone 21 by crane 8. Secondary panel 22 is shown in the process of being cast, with the rebar cage already in position, and panel 23 is shown in its cured and completed state, forming a continuous 20 diaphragm wall with neighbouring primary panels 13 and 14. Figure 3a illustrates how, when primary panels 10, 11, 12 are set at an angle to their neighbouring secondary panels, the amount of material 16 to be milled from the side faces of the primary panels is less towards the outer edge of the side and greater towards its inner edge. "Inner" in this case refers to 25 the side of the panels on which the joining angle of two adjacent panels is less than 180 degrees. "Outer" refers to the side of two adjacent panels on which the joining angle of two adjacent panels is greater than 180 degrees. Reference 15 in the figures indicates the cutter joint profile to be milled into the side face of each primary panel. 30 A plan view of the arrangement of figure 3a is shown in figure 3b, which also indicates where the material for secondary panels 20 and 21 is to be excavated and milled. In the illustrated example, a great deal of material 16 10 must be removed from the primary panels 10, 11, 12 in order to achieve the desired cutter joint profile 15 across the whole side faces of the primary panels 10, 11, 12. The concrete used for casting the primary panels is usually of a high specification, being very hard and impermeable to water. Removing the wedges 5 16 of very hard concrete presents a tough challenge to the hydromill 9, which must consequently be lowered much more slowly than when the neighbouring panels are aligned with each other in coplanar fashion. The removal of so much hard concrete also means significantly increased wear on the expensive hydromill milling machinery. Varying the depth of concrete to be milled also 10 means that there is an increased risk of the hydromill being diverted from the vertical plane as it progresses downwards. Figures 4a, 4b, 4c and 4d show the principle behind an embodiment of the present invention. Figures 4a and 4b show, in plan and perspective views respectively, a primary panel rebar cage 30 which has two sacrificial 15 displacement elements 31 secured to it. Sacrificial displacement elements 31 are essentially means for excluding the concrete used for casting the primary panels from predetermined regions of the primary panel casting volume, and in particular from the regions which are to be removed when the joint milling is to be performed. The sacrificial displacement elements need not be hollow - their 20 function is to create a region of the casting volume from which the high specification concrete is excluded when it is poured. As such, the sacrificial displacement elements 31 can be prefabricated, solid blocks of lightweight concrete, for example, or they can be prefabricated hollow shapes such as lengths of hollow pipe pre-sealed against the ingress of concrete, and optionally 25 pre-filled with soft concrete or soft, loose materials such as sand. The sacrificial displacement elements 31 are fixed to the rebar cage 30 for convenience, using fixing elements 32, so that the prefabricated sacrificial displacement elements 31 and the rebar cage 30 can be lowered together into the trench in a single operation, and concrete pouring can commence immediately. Fixing elements 30 32 can be pieces of steel rebar tacked to the rebar cage 30, for example. Since it is likely that the fixing elements 32 will intrude into the area to be milled, they must be of such shape and material that they do not significantly interfere with the milling of the cutter joint 15.
11 The sacrificial displacement elements 31 are positioned so that, when the rebar cage assembly 30 (complete with attached sacrificial displacement elements 31) is lowered into its primary panel casting volume, and the high-specification concrete is cast around the rebar 30 and the 5 sacrificial displacement elements 31, the sacrificial displacement elements 31 will form regions 16 of the primary panel which will be removed when the neighbouring secondary sections are excavated. Figure 4c shows in plan view where the joint profile 15 is to be milled by removing the material of the sacrificial displacement elements 31 and milling into the hard concrete of the 10 primary panels 10, 11. In figure 4c, primary panels 10 and 11 are in their completed, ready-to-be-milled state, after the concrete 25 has been cast around the rebar cages 30 and the sacrificial displacement elements 31 and after the cast concrete has been allowed to cure. The casting volume for secondary panel 20 is then excavated/milled as previously described, removing 15 the material of the sacrificial displacement elements 31 and creating joint profile 15 in the hard material of the primary panels 10, 11. A certain amount of the dense, high-specification concrete must in any case be removed in order to achieve a sound joint between adjacent panels, but the method of the invention minimises the amount of this dense, high-specification concrete which must be 20 milled, especially when the adjacent panels are at an angle to each other. Figure 4d then shows the completed excavation of the secondary casting volume 20, with the milled joint faces 15 ready for casting the secondary panel. Figure 4e shows the secondary panel 20, including rebar cage 26, cast and cured between primary panels 10 and 11. Panels 10, 11 and 25 20 should now be mechanically bonded by the joints 15 to form a continuous, more impermeable diaphragm wall structure. Figures Sa, 5b and 5c illustrate an example of how the sacrificial displacement elements can be assembled prior to lowering the primary panel rebar into the trench. In these figures, the sacrificial displacement elements 31 30 are shown secured to the rebar cage 30 by means of fixings 32, but held away from the rebar cage by separator elements 33. By keeping the sacrificial displacement elements 31 away from the rebar cage 30, it can be ensured that the subsequent joint milling is performed in a region which does not run the risk 12 of intruding into the region of the rebar cage 30. If such an intrusion happens, this could damage the milling machinery and/or significantly compromise the strength and integrity of the primary panel being cast. The separator elements 33 are preferably attached to the rebar cage 5 30, and can be shaped not only to create a space between sacrificial displacement elements 31 and rebar cage 30, but also to support the sacrificial displacement elements 31 before and during casting. Before casting, the separator elements are required to be able to support the weight of the sacrificial displacement elements 31. During casting, the separator elements 33 10 must also be capable of holding the sacrificial displacement elements 31 in position against any upward buoyancy forces exerted on the sacrificial displacement elements 31 when they are immersed in the slurry, and/or when the relatively more dense concrete is poured around the sacrificial displacement elements 31. The separator elements 33 can also be made of an easily 15 millable, void-forming material such as lightweight concrete. As shown in the example of figures 5a to 5c, the sacrificial displacement elements 31 can be attached in modular fashion, with each successive set of modules being attached as the rebar cage is lowered into the excavated trench 12. Note that figure 5c shows a particular example situation, in which the sacrificial 20 displacement elements 31 are fitted in the lower and mid-sections of the panel, but not in the upper section. Many hydromills only work effectively when the milling head is submerged in the slurry. In the upper section of the panel, therefore, the joints between the primary panel and its neighbouring secondary panels are formed using conventional temporary "stop-end" steel joints which 25 are then removed before starting excavation of the secondary panels. This is just one variant of the invention, however, and the sacrificial displacement elements 31 may be positioned wherever required. While the present invention has been described in the context of structures fabricated in the ground using reinforced concrete, the invention may 30 be used to construct any structure in which a milled-type joint is required to be created between two adjacent cast elements, and in which at least one of the elements can be cast so that it has a joint-forming region comprising a sacrificial void-forming element.
13 It is to be understood that, if any prior art publication is referred to herein, such reference does not constitute an admission that the publication forms a part of the common general knowledge in the art, in Australia or any other country. 5 In the claims which follow and in the preceding description of the invention, except where the context requires otherwise due to express language or necessary implication, the word "comprise" or variations such as "comprises" or "comprising" is used in an inclusive sense, i.e. to specify the presence of the 10 stated features but not to preclude the presence or addition of further features in various embodiments of the invention.

Claims (17)

1. Method for casting a diaphragm wall comprising two primary sections joined by a secondary section, the method comprising a first step of excavating a primary casting volume for each primary 5 section, a second step of casting the primary sections in the primary casting volumes, a third step of excavating a secondary casting volume for casting the secondary section, 10 a fourth step of removing a sacrificial joining region of one or both adjacent primary sections, wherein the second step comprises arranging a prefabricated sacrificial displacement element in the sacrificial joining region of one or both of the 15 primary casting volumes, positioned such that the casting material of the primary sections is displaced by the sacrificial displacement element in the or each joining region and such that the removal of the or each sacrificial joining region performed in the fourth step includes the removal of the or each sacrificial displacement element. 20
2. Method according to claim 1, in which the primary and secondary sections are substantially planar and vertical, and in which the secondary section is cast in a plane which is at an angle other than 180 to the plane of at least one of the adhjacent primary sections. 25
3. Method according to claim 1 or claim 2, in which the second step includes constructing a casting preparation assembly comprising a reinforcement element for reinforcing each primary section, securing the prefabricated sacrificial displacement elements to the reinforcing element, and arranging the casting preparation assembly in the respective primary casting 30 volume. 15
4. Method according to claim 3, in which the second step includes arranging separator elements to hold each sacrificial displacement element in position at a predetermined distance from the reinforcing element.
5. Casting preparation assembly for placing into an excavated 5 primary casting volume for casting a primary section of a concrete diaphragm wall, the primary section having at least one adjoining region, the or each adjoining region being a region of the primary section to be milled for creating a joining surface profile for joining the primary section to an adjacent secondary section of the diaphragm wall, 10 wherein the assembly comprises at least one pre-fabricated sacrificial displacement element, the or each sacrificial displacement element being made of a more easily millable material than the concrete used for casting the primary section, 15 the or each sacrificial displacement element being positioned in the casting preparation assembly such that, when the casting preparation assembly is placed into the primary casting volume and the primary section has been cast, the or each sacrificial displacement element is in a joining region for being removed during milling of the adjacent secondary section. 20
6. Assembly according to claim 5, comprising a reinforcement structure for providing reinforcement for the primary section when the primary section is cast, the or each sacrificial displacement element being secured to the reinforcement structure.
7. Method according to any one of claims 1 to 4, or assembly 25 according to claim 5 or 6, in which the material of each prefabricated sacrificial displacement element is softer, or more brittle, or more friable, or less dense than the material used to cast the primary sections.
8. Method according to any one of claims 1 to 4, or assembly according to claim 5 or 6, in which the joining surface profile comprises one or 30 more grooves formed in the material of the primary section. 16
9. Method according to any one of claims 1 to 4, or assembly according to claim 5 or 6, in which each prefabricated sacrificial displacement element comprises at least two prefabricated modules.
10. Method according to any one of claims 1 to 4, or assembly 5 according to claim 5 or 6, in which each prefabricated sacrificial displacement element has a prism shape of substantially triangular or trapezoidal cross section.
11. Method according to any one of claims 1 to 4, or assembly according to claim 5 or 6, in which one or more of the prefabricated sacrificial 10 displacement elements or modules encloses a hollow void.
12. Method according to one of claims 1 to 4, or assembly according to one of claims 5 or 6, in which one or more of the prefabricated sacrificial displacement elements or modules comprises a solid block.
13. Method according to one of claims 1 to 4, or assembly according 15 to one of claims 5 or 6, in which the secondary section volume is excavated using a hydromill.
14. Method according to one of claims 1 to 4, or assembly according to one of claims 5 or 6, in which one or both of the primary casting volumes are excavated using a hydromill. 20
15. Method or assembly according to claim 13 or 14, in which the hydromill is slightly wider than the distance separating the two primary casting volumes.
16. A method for casting a diaphragm wall substantially as herein described with reference to Figures 4a to 6. 25
17. A casting preparation assembly for placing into an excavated primary casting volume for casting a primary section of a concrete diaphragm wall substantially as herein described with reference to Figures 4a to 6.
AU2010350042A 2010-03-30 2010-03-30 Method and assembly for constructing a diaphragm wall Active AU2010350042B2 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/EP2010/054178 WO2011120557A1 (en) 2010-03-30 2010-03-30 Method and assembly for constructing a diaphragm wall

Publications (2)

Publication Number Publication Date
AU2010350042A1 AU2010350042A1 (en) 2012-08-16
AU2010350042B2 true AU2010350042B2 (en) 2015-08-20

Family

ID=42133788

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2010350042A Active AU2010350042B2 (en) 2010-03-30 2010-03-30 Method and assembly for constructing a diaphragm wall

Country Status (9)

Country Link
EP (1) EP2553175B1 (en)
KR (1) KR20130015267A (en)
CN (1) CN102959157B (en)
AU (1) AU2010350042B2 (en)
ES (1) ES2445575T3 (en)
HK (1) HK1177955A1 (en)
PL (1) PL2553175T3 (en)
SG (1) SG183803A1 (en)
WO (1) WO2011120557A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258647A (en) * 2019-06-04 2019-09-20 广州穗岩土木科技股份有限公司 A kind of attachment device and construction method of new, old diaphram wall

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB201706643D0 (en) 2017-04-26 2017-06-07 Ccmj Systems Ltd Diaphragm walls
FR3071259B1 (en) * 2017-09-19 2019-09-13 Sefi-Intrafor SPACING PLATE FOR GUIDING A WALL MOLDING IN THE SOIL AND METHOD OF MAKING A MOLDED WALL USING THE SPACING PLATE
FR3071535B1 (en) 2017-09-25 2019-09-27 Soletanche Freyssinet DRILLING MACHINE FOR CARRYING OUT A NON-RECTILINE TRENCH
GB2566970A (en) * 2017-09-29 2019-04-03 Ccmj Systems Ltd Spacers
DE202019102494U1 (en) 2019-05-03 2019-05-13 Bauer Spezialtiefbau Gmbh reinforcing cage
EP3733975B1 (en) 2019-05-03 2022-09-28 BAUER Spezialtiefbau GmbH Reinforcing cage and method for producing a slotted wall
KR102317138B1 (en) * 2020-08-28 2021-10-25 주식회사 와이앤피기술 Construction method of cast in place concrete pile for retaining wall
CN113653030A (en) * 2021-07-22 2021-11-16 中国建筑第八工程局有限公司 Construction method of underground continuous wall of ultra-low clearance and ultra-deep foundation pit under high-voltage line
CN114855849A (en) * 2022-05-25 2022-08-05 暨南大学 Rigid-flexible combined underground diaphragm wall anti-seepage joint and construction method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003006750A1 (en) * 2001-07-13 2003-01-23 Intrafor Method and device for creating a reinforced concrete wall in the ground

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1658773B1 (en) * 1968-02-28 1971-08-26 Wolff & Mueller Tunneling method
US4005582A (en) * 1975-08-12 1977-02-01 Icos Corporation Of America Method of constructing underground concrete walls and reinforcement cage therefor
JPH05125722A (en) * 1991-10-31 1993-05-21 Hazama Gumi Ltd Locking structure of reinforcing bar cage and its method
JP2789991B2 (en) * 1993-04-20 1998-08-27 株式会社大林組 Reinforcing cage for continuous underground wall construction
JPH09158175A (en) * 1995-12-07 1997-06-17 Bauaa Japan Kk Joint construction method of underground continuous wall and embedding material of concrete cutting area
JPH11303065A (en) * 1998-04-16 1999-11-02 Ohbayashi Corp Execution method for diaphragm wall
CN1102188C (en) * 1998-12-28 2003-02-26 石午江 Construction method and equipment for continuous underground wall
JP2000345557A (en) * 1999-06-08 2000-12-12 Ohbayashi Corp Cage used for diaphragm wall method
JP3829705B2 (en) * 2001-12-03 2006-10-04 株式会社大林組 Circular continuous underground wall drilling rig
EP1964980A1 (en) * 2007-02-28 2008-09-03 Etienne Heirwegh Excavating means and method to cast in-situ cast walls
CN101041962A (en) * 2007-04-13 2007-09-26 中铁一局集团有限公司 Underground continuous wall milling joint and construction technique thereof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003006750A1 (en) * 2001-07-13 2003-01-23 Intrafor Method and device for creating a reinforced concrete wall in the ground

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258647A (en) * 2019-06-04 2019-09-20 广州穗岩土木科技股份有限公司 A kind of attachment device and construction method of new, old diaphram wall

Also Published As

Publication number Publication date
EP2553175A1 (en) 2013-02-06
SG183803A1 (en) 2012-10-30
HK1177955A1 (en) 2013-08-30
CN102959157B (en) 2015-11-25
ES2445575T3 (en) 2014-03-04
WO2011120557A1 (en) 2011-10-06
EP2553175B1 (en) 2013-11-06
KR20130015267A (en) 2013-02-13
AU2010350042A1 (en) 2012-08-16
PL2553175T3 (en) 2014-05-30
CN102959157A (en) 2013-03-06

Similar Documents

Publication Publication Date Title
AU2010350042B2 (en) Method and assembly for constructing a diaphragm wall
KR100736241B1 (en) Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
EP2732101B1 (en) Diaphragm wall apparatus and methods
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
JP3893056B2 (en) Construction method of underground structure
KR20110052360A (en) Downward construction method of underground structure that enables continuous basement wall using non-wale and diaphragm action of concrete slab
JP6656901B2 (en) Construction method of segments and submerged structures
JP3930954B2 (en) Construction method of structure
JP4153456B2 (en) Construction method of steel element / concrete type underground structure
JP2000291398A (en) Underground structure and construction method therefor
KR101219451B1 (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
JP6506902B2 (en) Pile foundation structure and construction method of pile foundation structure
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
JP6948908B2 (en) Construction method of segments, buried structures and buried structures
CN111827265A (en) Construction method of steel reinforced concrete underground continuous wall
JP4612356B2 (en) How to create a slope
KR100592397B1 (en) storey spacing support ssoldier pile soil retaining wall
WO2000065158A1 (en) Improved formation of capping beams for piles
JP4146250B2 (en) Open caisson bottom plate construction method
JP4319231B2 (en) Approach caisson and method for constructing tunnel approach section composed of caisson
JP2018066138A (en) Segment wall body and tunnel lining body
JP2023001683A (en) Construction method of underground structure and underground structure as well as precast concrete side wall or intermediate wall/column therefor
JPH0781274B2 (en) How to build a beam on an underground wall
CN111827267A (en) Underground continuous wall construction method

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)