JP3724320B2 - Construction method for underground structures - Google Patents
Construction method for underground structures Download PDFInfo
- Publication number
- JP3724320B2 JP3724320B2 JP2000076029A JP2000076029A JP3724320B2 JP 3724320 B2 JP3724320 B2 JP 3724320B2 JP 2000076029 A JP2000076029 A JP 2000076029A JP 2000076029 A JP2000076029 A JP 2000076029A JP 3724320 B2 JP3724320 B2 JP 3724320B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- underground structure
- existing
- constructed
- existing underground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【0001】
【発明の属する技術分野】
この発明は既存の地下構造物が建つ敷地内に、既存の地下構造物を解体しながら、主要構造体が鉄骨鉄筋コンクリート構造(以下、「SRC構造」という)または鉄骨構造(以下、「S構造」という)からなる地下構造物を新たに構築する地下構造物の構築工法に関する。
【0002】
【従来の技術】
既存の地下構造物を解体し、その後に主要構造体がSRC構造またはS構造の地下構造物を新たに構築する方法として、これまで地下構造物の外周に予め山留め壁を構築し、切梁やアースアンカーで山留め壁を支持しながら先に既存の地下構造物を解体し、所定深さまで地盤を掘り下げた後、基礎を構築し、この基礎の上に地下構造物の鉄骨を新たに組み立て、基礎から上方に順次躯体を新たに構築していく方法が一般に行なわれている。
【0003】
【発明が解決しようとする課題】
しかし上記の方法で、例えば山留め壁を切梁で支持するとすると、切梁は多段にわたって架け渡され、しかも切梁を支持する棚杭が林立するため、きわめて障害の多い中で既存構造物の解体と掘削作業を強いられ、非常に作業効率が悪いものであった。
【0004】
山留め壁を支持する他の方法として、アースアンカー工法も知られているが、近年の市街地での建設工事においては、隣地近接により敷地外にアースアンカーを用いることができず、採用できない場合が多い。
また、切梁やアースアンカーを使用せず、本設の床を山留め壁の支持材と作業床として利用し、上階から地下に向かって構築しながら地下を掘り進む逆打ち(さかうち)工法も知られているが、この工法では特に本設床を支持する構真柱をあらかじめ設置する必要があり、この構真柱は既存構造物の躯体を貫通して設置する必要があることから、多大な工期と工事費がかかってしまう等の課題があった。
【0005】
この発明は、以上の課題を解決するためになされたもので、既存の地下構造物が建つ敷地内に、主要構造体がSRC構造またはS構造からなる新規の地下構造物を新たに構築する際、既存の地下構造物の解体から新規の地下構造物の構築までを切梁などの山留め支保工を使用しないできわめて効率的かつ経済的に行えるようにした地下構造物の構築工法を提供することを課題とする。
【0006】
【課題を解決するための手段】
請求項1記載の地下構造物の構築工法は、既設地下構造物を解体した敷地内に、当該既設地下構造物と同じ規模の新設地下構造物を構築する地下構造物の構築工法であって、既設地下構造物の外周に山留め壁を構築した後、前記既設地下構造物の外周部分および中央部分の地下一階分を全体にわたって解体し、次に前記既設地下構造物の外周部分に支持地盤まで到達する構真柱を施工し、かつ当該構真柱および前記山留め壁に支持させて新設地下構造物の地上一階の周囲床を構築し、前記既設地下構造物の中央部分は最下階まで解体し、その後に新設地下構造物の中央部分の鉄骨軸組を最下階から最上階まで順に構築し、かつ当該新設地下構造物の中央部分の最上階と地上一階の前記周囲床との間に鉄骨梁を架け渡し、次に前記既設構造物の外周部分を地下二階部分から最下階まで順次解体しつつ、その後に新設地下構造物の外周部分の各階の床を地下二階から最下階まで順次構築し、かつ各階の周囲床と中央部分の各階間に鉄骨梁をそれぞれ架け渡すことを特徴とするものである。
【0008】
【発明の実施の形態】
図1〜図5は、この発明に係る地下構造物の構築工法の一例を示し、以下、施工方法を順を追って説明する。
【0009】
▲1▼ 最初に、既存の地下構造物(以下、「既設地下構造物」という)1の周囲に山留め壁2を構築する(図1(1)参照)。山留め壁2は既設地下構造物1解体し、さらにその後に後述する新規の地下構造物(以下、「新設地下構造物」という)を構築するまでの間、周囲の土圧を支持するために構築するもので、例えば連続山留め工法などで構築する。
【0010】
▲2▼ 次に、既設地下構造物1の地下一階部分B1Fを、中央部分Aと外周部分Bの全体にわたって解体する(図1(2),(3)参照)。なお、この解体工事は、これまで一般に使用されている重機で行うものとする。
【0011】
▲3▼ 次に、既設地下構造物1の中央部分Aについては、引き続き地下二階部分B2F、地下三階部分B3Fとさらに解体作業を継続し、最下階まで解体する(図1(4),図2(1)参照)。一方、既設地下構造物1の外周部分Bにおいては、地下一階部分B1Fの床の上で構真柱3を施工する(図1(4)参照)。
【0012】
構真柱3は既存の地下構造物1解体し、さらにその後に後述する新設地下構造物を構築するまでの間、仮設柱として働き、さらに施工方法によっては新設地下構造物の柱にもなるものである。
【0013】
したがって、構真柱3は、地上一階の床部分まで立ち上げ、かつ既設地下構造物1の地下一階部分B1Fの床およびこれより下方の全階の床を貫通し、支持地盤まで確実に到達するように施工するものとし、例えば全旋回オールケーシング工法などで施工する。
【0014】
なお、既設地下構造物1の中央部分Aを解体するまでの間、特に外周部分Bを残すこととしたのは、山留め壁2を支持する支持体として外周部分Bを利用するためである。
【0015】
したがって、中央部分Aを解体する間、残置する外周部分Bの幅は、既設地下構造物1の深さと既設地下構造物1が建設される敷地の地盤条件などによって決められる。図では、既設地下構造物1の1スパン分が山留め壁2の支持体として残されている。
【0016】
▲4▼ 次に、外周部分Bに地上一階の床4Aを構築する(図2(4)参照)。この床4Aはその後の作業を行うための作業床として利用されるものであり、周囲の山留め壁2と構真柱3に支持させて構築する。また、床4Aは施工方法によっては後から構築される新設地下構造物の地上一階部分の床にもなる。
【0017】
▲5▼ 次に、中央部分Aの解体が最下階まで進んだら、さらにその下側地盤を所定の深さまで掘り下げて根切り地盤面5とする(図3(3)参照)。なお、この根切り工事では、地山の崩落事故などの発生を未然に防止し、作業の安全を図るべく、周囲に法面6を設けるものとする。
【0018】
▲6▼ 次に、根切り地盤面5の上に新設地下構造物の基礎7を構築し(図3(3)参照)、その上に新設地下構造物の鉄骨軸組8を最下階から最上階まで順次組み立てる(図3(3)参照)。そして、最上階の鉄骨梁8aと周囲の床4との間に鉄骨梁9Aを架け渡す。
【0019】
なお、鉄骨梁9Aは既設地下構造物1の外周部分Bを解体するまでの間、山留め壁2を支持する切梁の働きをなすものであり、施工方法によっては、鉄骨軸組8の最上階の鉄骨梁として残置されるものである。
【0020】
▲7▼ 次に、既設地下構造物1の外周部分Bを地下二階部分B2F、地下三階部分B3Fと、上の階から順に最下階まで解体する(図3(1),(2),(3)参照)。その際特に、各階ごとに解体した後に床4Aと同様の働きをする床4B、4C、4Dを構築する。また、この各階の床4B、4C、4Dと鉄骨軸組8の各階間に鉄骨梁9Aと同じ働きをする鉄骨梁9B、9C、9Dをそれぞれ架け渡す(図3(1),(2),(3)参照)。
【0021】
なお、鉄骨梁9A、9B、9C、9Dを切梁として作用させると、各鉄骨梁の断面が大きくなってきわめて不経済になる場合もあることから、鉄骨梁9A、9B、9C、9Dに代えてコンクリート床10A、10B、10C、10Dを施工し、このコンクリート床10A、10B、10C、10Dを切梁として作用させる方法でもよい。
【0022】
▲8▼ こうして、既設地下構造物1の外周部分Bの解体が最下階まですべて完了したら、さらにその下側地盤を中央部分の根切り地盤面5まで掘り下げ(図4(1)参照)、その後に新設地下構造物の基礎7を中央部分Aの基礎7と一体に構築する(図4(2)参照)。なお、外周部分Bの根切り工事に際しても、地山の崩落事故などの発生を未然に防止し、作業の安全を図るべく、周囲に法面6を設けるものとする。
【0023】
以上の工程により、既設地下構造物1の解体から新設地下構造物(鉄骨軸組8)の構築までを、切梁などの山留め支保工を特に必要としないできわめて効率的かつ経済的に連続して行うことができる。
【0024】
【発明の効果】
この発明は以上説明した通りであり、既設地下構造物の外周部分を残し、これを既設地下構造物の外周部分を解体するまでの間、山止め壁の支持体として利用することにより、これまで山留め壁を支持するために必ず必要とされた切梁やアースアンカーなどの山留め支保工を省略することができる。
【0025】
したがって、既設地下構造体の主要部分の解体とその下部の掘削工事が効率的におこなうことができ、工期の短縮と工事費の低減が達成される。
【0026】
また、留め壁の支持体として残しておいて後から解体する範囲については、逆打ち工法により一階レベルに作業床を早期に構築することで、大規模な作業台を設ける必要がない。また、中央部分の上部躯体工事を地下工事と同時に進めることができ、工期の短縮化が図れる。
【0027】
このように、既設地下構造物を解体しながら新設地下構造物を構築するにあたり、本来工事の障害となる既設地下構造物を仮設山留め材の代わりに有効利用することで、解体工事、掘削工事、地下躯体工事が効率的に行うことができ、工期の短縮と仮設工事費の低減が図れる。
【図面の簡単な説明】
【図1】 (1)〜(4)は、山留め壁の施工から構真柱の施工までを示す工程図である。
【図2】 (1)〜(4)は、中央部分の解体から基礎の施工までを示す工程図である。
【図3】 (1)〜(3)は、新設構造物の鉄骨軸組の組み立てから外周部分の解体までを示す工程図である。
【図4】 (1)、(2)は外周部分の根切りから基礎の施工までを示す工程図である。
【図5】山留め壁と構真柱の配置例を示す平面図である。
【符号の説明】
1 既設地下構造物(既存の地下構造物)
2 山留め壁
3 構真柱
4A 床
4B 床
4C 床
4D 床
5 根切り地盤面
6 法面
7 基礎
8 鉄骨軸組
8a 鉄骨梁
9A 鉄骨梁
9B 鉄骨梁
9C 鉄骨梁
9D 鉄骨梁
10A コンクリート床
10B コンクリート床
10C コンクリート床
10D コンクリート床[0001]
BACKGROUND OF THE INVENTION
In the present invention, a main structure is a steel reinforced concrete structure (hereinafter referred to as “SRC structure”) or a steel structure (hereinafter referred to as “S structure”) while dismantling the existing underground structure in a site where the existing underground structure is built. It is related to the construction method of the underground structure that newly constructs the underground structure consisting of
[0002]
[Prior art]
As a method of dismantling an existing underground structure and then constructing a new underground structure whose main structure is an SRC structure or S structure, a retaining wall has been previously constructed on the outer periphery of the underground structure so far. While supporting the mountain retaining wall with the earth anchor, dismantle the existing underground structure first, dig the ground to a predetermined depth, build the foundation, and assemble the steel frame of the underground structure on this foundation, In general, a method of newly constructing a housing in order from the top to the bottom is performed.
[0003]
[Problems to be solved by the invention]
However, with the above method, for example, if the retaining wall is supported by a cut beam, the cut beam will be spanned in multiple stages, and the shelf pile supporting the cut beam will be forested. He was forced to dig, and the work efficiency was very poor.
[0004]
As another method for supporting the retaining wall, the earth anchor method is also known. However, in recent construction work in urban areas, it is often impossible to use an earth anchor outside the site due to the proximity of the adjacent land. .
In addition, there is a reverse casting method in which the main floor is used as a support for the retaining wall and work floor without using beams and earth anchors, and the basement is dug into the basement while building from the upper floor to the basement. As is known, it is necessary to install a construction pillar that supports the main floor in advance, and this construction pillar must be installed through the frame of an existing structure. There were problems such as a long construction period and construction costs.
[0005]
The present invention has been made to solve the above-described problems. When a new underground structure whose main structure is an SRC structure or an S structure is newly constructed in a site where an existing underground structure is built, To provide a method for constructing an underground structure that can be used from the dismantling of an existing underground structure to the construction of a new underground structure, without the use of timber support works such as beams. Is an issue.
[0006]
[Means for Solving the Problems]
The construction method of the underground structure according to
[0008]
DETAILED DESCRIPTION OF THE INVENTION
FIGS. 1-5 shows an example of the construction method of the underground structure based on this invention, and demonstrates a construction method later on in order.
[0009]
(1) First, a
[0010]
(2) Next, the underground first floor portion B1F of the existing
[0011]
(3) Next, for the central part A of the existing
[0012]
The
[0013]
Therefore, the
[0014]
The reason why the outer peripheral portion B is particularly left until the central portion A of the existing
[0015]
Therefore, while dismantling the central portion A, the width of the outer peripheral portion B to be left is determined by the depth of the existing
[0016]
(4) Next, the
[0017]
(5) Next, when the dismantling of the central portion A proceeds to the lowest floor, the lower ground is further dug down to a predetermined depth to form a root-cutting ground surface 5 (see FIG. 3 (3)). It should be noted that in this root cutting work,
[0018]
(6) Next, the
[0019]
The
[0020]
(7) Next, disassemble the outer peripheral part B of the existing
[0021]
In addition, if the
[0022]
(8) When the dismantling of the outer peripheral part B of the existing
[0023]
Through the above process, the process from the dismantling of the existing
[0024]
【The invention's effect】
The present invention is as described above, and by leaving the outer peripheral portion of the existing underground structure and using it as a support for the retaining wall until the outer peripheral portion of the existing underground structure is dismantled, It is possible to omit the supporting work such as a cut beam and a ground anchor which are necessary for supporting the retaining wall.
[0025]
Therefore, the dismantling of the main part of the existing underground structure and the excavation work under the main part can be efficiently performed, and the construction period can be shortened and the construction cost can be reduced.
[0026]
Moreover, about the range which leaves as a support body of a retaining wall and is demolished later, it is not necessary to provide a large-scale work table by constructing a work floor at the first floor level at an early stage by the reverse driving method. In addition, the upper frame work in the central part can be carried out simultaneously with the underground work, and the construction period can be shortened.
[0027]
In this way, when constructing a new underground structure while dismantling the existing underground structure, by effectively using the existing underground structure, which is originally an obstacle to the construction, instead of the temporary mountain retaining material, demolition work, excavation work, Underground building construction can be carried out efficiently, shortening the construction period and reducing temporary construction costs.
[Brief description of the drawings]
FIG. 1 (1) to (4) are process diagrams showing from the construction of a retaining wall to the construction of a structural pillar.
FIG. 2 (1) to (4) are process diagrams showing from the dismantling of the central part to the construction of the foundation.
FIGS. 3 (1) to (3) are process diagrams showing the process from assembling the steel frame of the newly-constructed structure to disassembling the outer peripheral portion.
FIGS. 4A and 4B are process diagrams showing from the root cutting of the outer peripheral portion to the construction of the foundation.
FIG. 5 is a plan view showing an arrangement example of a retaining wall and a true pillar.
[Explanation of symbols]
1 Existing underground structure (existing underground structure)
2
10A concrete floor
10B Concrete floor
10C concrete floor
10D concrete floor
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000076029A JP3724320B2 (en) | 2000-03-17 | 2000-03-17 | Construction method for underground structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000076029A JP3724320B2 (en) | 2000-03-17 | 2000-03-17 | Construction method for underground structures |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001262594A JP2001262594A (en) | 2001-09-26 |
JP3724320B2 true JP3724320B2 (en) | 2005-12-07 |
Family
ID=18593828
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000076029A Expired - Lifetime JP3724320B2 (en) | 2000-03-17 | 2000-03-17 | Construction method for underground structures |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3724320B2 (en) |
Families Citing this family (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3977700B2 (en) * | 2002-07-11 | 2007-09-19 | 鹿島建設株式会社 | Demolition and new construction method using existing underground structure |
JP2005307688A (en) * | 2004-04-26 | 2005-11-04 | Nippon Steel Corp | Construction method for earth retaining wall for newly built underground skeleton and construction method for newly built skeleton by use of its method |
KR100736241B1 (en) | 2006-09-07 | 2007-07-06 | 주식회사 백산종합개발 | Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall |
JP5132464B2 (en) * | 2008-07-29 | 2013-01-30 | 大成建設株式会社 | Excavation method |
JP5303381B2 (en) * | 2009-07-09 | 2013-10-02 | 戸田建設株式会社 | Demolition method for existing buildings |
JP5525850B2 (en) * | 2010-02-15 | 2014-06-18 | 戸田建設株式会社 | Mountain fastening method |
JP5811389B2 (en) * | 2010-11-17 | 2015-11-11 | 清水建設株式会社 | Construction method for underground structures |
JP6274406B2 (en) * | 2013-12-27 | 2018-02-07 | 清水建設株式会社 | Construction method of new underground structure with dismantling of existing underground structure |
JP6424060B2 (en) * | 2014-10-10 | 2018-11-14 | 株式会社竹中工務店 | How to rebuild a structure |
JP6103667B1 (en) * | 2016-03-14 | 2017-03-29 | 大成建設株式会社 | Construction method of underground structure |
JP6827256B2 (en) * | 2016-08-02 | 2021-02-10 | 大成建設株式会社 | How to rebuild the building |
JP6988047B2 (en) * | 2016-10-20 | 2022-01-05 | 株式会社竹中工務店 | How to reconstruct the underground skeleton |
JP7293567B2 (en) * | 2018-01-24 | 2023-06-20 | 株式会社竹中工務店 | Construction method of structures |
-
2000
- 2000-03-17 JP JP2000076029A patent/JP3724320B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2001262594A (en) | 2001-09-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101014796B1 (en) | Top-down underground construction method using prefabricated concrete column member as temporary bridge column | |
KR101205783B1 (en) | The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously | |
JP3724320B2 (en) | Construction method for underground structures | |
JP2001262595A (en) | Building construction method of underground building frame | |
JP2596798B2 (en) | Existing building seismic isolation method | |
JP4050816B2 (en) | Construction method of underground part of steel reinforced concrete building | |
JP4115095B2 (en) | Reverse strike method | |
JP2001271497A (en) | Temporary bearing construction method for existing building | |
JP2020125630A (en) | Building construction method | |
JP2000087348A (en) | Steel segment, underground reinforced concrete columnar structure and construction method thereof | |
JP6832761B2 (en) | How to rebuild the building | |
JP3977700B2 (en) | Demolition and new construction method using existing underground structure | |
JPH0559728A (en) | Sheathing work above underground structure | |
KR101256311B1 (en) | Structual deepening method | |
KR100592397B1 (en) | storey spacing support ssoldier pile soil retaining wall | |
JP4879582B2 (en) | How to extend the basement floor under the foundation of an existing building | |
JPS63280153A (en) | Underground inverted lining method | |
JP2571426B2 (en) | Construction method of retaining wall | |
JPH07150565A (en) | Earth retaining construction method | |
JPH03147926A (en) | construction method for basement | |
JP3809340B2 (en) | Reverse strike method | |
JP6851180B2 (en) | How to rebuild the building | |
JP2926151B2 (en) | Building structure and construction method | |
JP2894217B2 (en) | Building structural frame | |
JP3281554B2 (en) | How to rebuild underground structures |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050210 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050222 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050422 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050524 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050721 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050830 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050912 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3724320 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110930 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110930 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140930 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |