JP3724320B2 - Construction method for underground structures - Google Patents

Construction method for underground structures Download PDF

Info

Publication number
JP3724320B2
JP3724320B2 JP2000076029A JP2000076029A JP3724320B2 JP 3724320 B2 JP3724320 B2 JP 3724320B2 JP 2000076029 A JP2000076029 A JP 2000076029A JP 2000076029 A JP2000076029 A JP 2000076029A JP 3724320 B2 JP3724320 B2 JP 3724320B2
Authority
JP
Japan
Prior art keywords
floor
underground structure
existing
constructed
existing underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2000076029A
Other languages
Japanese (ja)
Other versions
JP2001262594A (en
Inventor
泰伸 岩崎
厚志 服部
義則 石川
仁 伊藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2000076029A priority Critical patent/JP3724320B2/en
Publication of JP2001262594A publication Critical patent/JP2001262594A/en
Application granted granted Critical
Publication of JP3724320B2 publication Critical patent/JP3724320B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は既存の地下構造物が建つ敷地内に、既存の地下構造物を解体しながら、主要構造体が鉄骨鉄筋コンクリート構造(以下、「SRC構造」という)または鉄骨構造(以下、「S構造」という)からなる地下構造物を新たに構築する地下構造物の構築工法に関する。
【0002】
【従来の技術】
既存の地下構造物を解体し、その後に主要構造体がSRC構造またはS構造の地下構造物を新たに構築する方法として、これまで地下構造物の外周に予め山留め壁を構築し、切梁やアースアンカーで山留め壁を支持しながら先に既存の地下構造物を解体し、所定深さまで地盤を掘り下げた後、基礎を構築し、この基礎の上に地下構造物の鉄骨を新たに組み立て、基礎から上方に順次躯体を新たに構築していく方法が一般に行なわれている。
【0003】
【発明が解決しようとする課題】
しかし上記の方法で、例えば山留め壁を切梁で支持するとすると、切梁は多段にわたって架け渡され、しかも切梁を支持する棚杭が林立するため、きわめて障害の多い中で既存構造物の解体と掘削作業を強いられ、非常に作業効率が悪いものであった。
【0004】
山留め壁を支持する他の方法として、アースアンカー工法も知られているが、近年の市街地での建設工事においては、隣地近接により敷地外にアースアンカーを用いることができず、採用できない場合が多い。
また、切梁やアースアンカーを使用せず、本設の床を山留め壁の支持材と作業床として利用し、上階から地下に向かって構築しながら地下を掘り進む逆打ち(さかうち)工法も知られているが、この工法では特に本設床を支持する構真柱をあらかじめ設置する必要があり、この構真柱は既存構造物の躯体を貫通して設置する必要があることから、多大な工期と工事費がかかってしまう等の課題があった。
【0005】
この発明は、以上の課題を解決するためになされたもので、既存の地下構造物が建つ敷地内に、主要構造体がSRC構造またはS構造からなる新規の地下構造物を新たに構築する際、既存の地下構造物の解体から新規の地下構造物の構築までを切梁などの山留め支保工を使用しないできわめて効率的かつ経済的に行えるようにした地下構造物の構築工法を提供することを課題とする。
【0006】
【課題を解決するための手段】
請求項1記載の地下構造物の構築工法は、既設地下構造物を解体した敷地内に、当該既設地下構造物と同じ規模の新設地下構造物を構築する地下構造物の構築工法であって、既設地下構造物の外周に山留め壁を構築した後、前記既設地下構造物の外周部分および中央部分の地下一階分を全体にわたって解体し、次に前記既設地下構造物の外周部分に支持地盤まで到達する構真柱を施工し、かつ当該構真柱および前記山留め壁に支持させて新設地下構造物の地上一階の周囲床を構築し、前記既設地下構造物の中央部分は最下階まで解体し、その後に新設地下構造物の中央部分の鉄骨軸組を最下階から最上階まで順に構築し、かつ当該新設地下構造物の中央部分の最上階と地上一階の前記周囲床との間に鉄骨梁を架け渡し、次に前記既設構造物の外周部分を地下二階部分から最下階まで順次解体しつつ、その後に新設地下構造物の外周部分の各階の床を地下二階から最下階まで順次構築し、かつ各階の周囲床と中央部分の各階間に鉄骨梁をそれぞれ架け渡すことを特徴とするものである。
【0008】
【発明の実施の形態】
図1〜図5は、この発明に係る地下構造物の構築工法の一例を示し、以下、施工方法を順を追って説明する。
【0009】
▲1▼ 最初に、既存の地下構造物(以下、「既設地下構造物」という)1の周囲に山留め壁2を構築する(図1(1)参照)。山留め壁2は既設地下構造物1解体し、さらにその後に後述する新規の地下構造物(以下、「新設地下構造物」という)を構築するまでの間、周囲の土圧を支持するために構築するもので、例えば連続山留め工法などで構築する。
【0010】
▲2▼ 次に、既設地下構造物1の地下一階部分B1Fを、中央部分Aと外周部分Bの全体にわたって解体する(図1(2),(3)参照)。なお、この解体工事は、これまで一般に使用されている重機で行うものとする。
【0011】
▲3▼ 次に、既設地下構造物1の中央部分Aについては、引き続き地下二階部分B2F、地下三階部分B3Fとさらに解体作業を継続し、最下階まで解体する(図1(4),図2(1)参照)。一方、既設地下構造物1の外周部分Bにおいては、地下一階部分B1Fの床の上で構真柱3を施工する(図1(4)参照)。
【0012】
構真柱3は既存の地下構造物1解体し、さらにその後に後述する新設地下構造物を構築するまでの間、仮設柱として働き、さらに施工方法によっては新設地下構造物の柱にもなるものである。
【0013】
したがって、構真柱3は、地上一階の床部分まで立ち上げ、かつ既設地下構造物1の地下一階部分B1Fの床およびこれより下方の全階の床を貫通し、支持地盤まで確実に到達するように施工するものとし、例えば全旋回オールケーシング工法などで施工する。
【0014】
なお、既設地下構造物1の中央部分Aを解体するまでの間、特に外周部分Bを残すこととしたのは、山留め壁2を支持する支持体として外周部分Bを利用するためである。
【0015】
したがって、中央部分Aを解体する間、残置する外周部分Bの幅は、既設地下構造物1の深さと既設地下構造物1が建設される敷地の地盤条件などによって決められる。図では、既設地下構造物1の1スパン分が山留め壁2の支持体として残されている。
【0016】
▲4▼ 次に、外周部分Bに地上一階の床4Aを構築する(図2(4)参照)。この床4Aはその後の作業を行うための作業床として利用されるものであり、周囲の山留め壁2と構真柱3に支持させて構築する。また、床4Aは施工方法によっては後から構築される新設地下構造物の地上一階部分の床にもなる。
【0017】
▲5▼ 次に、中央部分Aの解体が最下階まで進んだら、さらにその下側地盤を所定の深さまで掘り下げて根切り地盤面5とする(図3(3)参照)。なお、この根切り工事では、地山の崩落事故などの発生を未然に防止し、作業の安全を図るべく、周囲に法面6を設けるものとする。
【0018】
▲6▼ 次に、根切り地盤面5の上に新設地下構造物の基礎7を構築し(図3(3)参照)、その上に新設地下構造物の鉄骨軸組8を最下階から最上階まで順次組み立てる(図3(3)参照)。そして、最上階の鉄骨梁8aと周囲の床4との間に鉄骨梁9Aを架け渡す。
【0019】
なお、鉄骨梁9Aは既設地下構造物1の外周部分Bを解体するまでの間、山留め壁2を支持する切梁の働きをなすものであり、施工方法によっては、鉄骨軸組8の最上階の鉄骨梁として残置されるものである。
【0020】
▲7▼ 次に、既設地下構造物1の外周部分Bを地下二階部分B2F、地下三階部分B3Fと、上の階から順に最下階まで解体する(図3(1),(2),(3)参照)。その際特に、各階ごとに解体した後に床4Aと同様の働きをする床4B、4C、4Dを構築する。また、この各階の床4B、4C、4Dと鉄骨軸組8の各階間に鉄骨梁9Aと同じ働きをする鉄骨梁9B、9C、9Dをそれぞれ架け渡す(図3(1),(2),(3)参照)。
【0021】
なお、鉄骨梁9A、9B、9C、9Dを切梁として作用させると、各鉄骨梁の断面が大きくなってきわめて不経済になる場合もあることから、鉄骨梁9A、9B、9C、9Dに代えてコンクリート床10A、10B、10C、10Dを施工し、このコンクリート床10A、10B、10C、10Dを切梁として作用させる方法でもよい。
【0022】
▲8▼ こうして、既設地下構造物1の外周部分Bの解体が最下階まですべて完了したら、さらにその下側地盤を中央部分の根切り地盤面5まで掘り下げ(図4(1)参照)、その後に新設地下構造物の基礎7を中央部分Aの基礎7と一体に構築する(図4(2)参照)。なお、外周部分Bの根切り工事に際しても、地山の崩落事故などの発生を未然に防止し、作業の安全を図るべく、周囲に法面6を設けるものとする。
【0023】
以上の工程により、既設地下構造物1の解体から新設地下構造物(鉄骨軸組8)の構築までを、切梁などの山留め支保工を特に必要としないできわめて効率的かつ経済的に連続して行うことができる。
【0024】
【発明の効果】
この発明は以上説明した通りであり、既設地下構造物の外周部分を残し、これを既設地下構造物の外周部分を解体するまでの間、山止め壁の支持体として利用することにより、これまで山留め壁を支持するために必ず必要とされた切梁やアースアンカーなどの山留め支保工を省略することができる。
【0025】
したがって、既設地下構造体の主要部分の解体とその下部の掘削工事が効率的におこなうことができ、工期の短縮と工事費の低減が達成される。
【0026】
また、留め壁の支持体として残しておいて後から解体する範囲については、逆打ち工法により一階レベルに作業床を早期に構築することで、大規模な作業台を設ける必要がない。また、中央部分の上部躯体工事を地下工事と同時に進めることができ、工期の短縮化が図れる。
【0027】
このように、既設地下構造物を解体しながら新設地下構造物を構築するにあたり、本来工事の障害となる既設地下構造物を仮設山留め材の代わりに有効利用することで、解体工事、掘削工事、地下躯体工事が効率的に行うことができ、工期の短縮と仮設工事費の低減が図れる。
【図面の簡単な説明】
【図1】 (1)〜(4)は、山留め壁の施工から構真柱の施工までを示す工程図である。
【図2】 (1)〜(4)は、中央部分の解体から基礎の施工までを示す工程図である。
【図3】 (1)〜(3)は、新設構造物の鉄骨軸組の組み立てから外周部分の解体までを示す工程図である。
【図4】 (1)、(2)は外周部分の根切りから基礎の施工までを示す工程図である。
【図5】山留め壁と構真柱の配置例を示す平面図である。
【符号の説明】
1 既設地下構造物(既存の地下構造物)
2 山留め壁
3 構真柱
4A 床
4B 床
4C 床
4D 床
5 根切り地盤面
6 法面
7 基礎
8 鉄骨軸組
8a 鉄骨梁
9A 鉄骨梁
9B 鉄骨梁
9C 鉄骨梁
9D 鉄骨梁
10A コンクリート床
10B コンクリート床
10C コンクリート床
10D コンクリート床
[0001]
BACKGROUND OF THE INVENTION
In the present invention, a main structure is a steel reinforced concrete structure (hereinafter referred to as “SRC structure”) or a steel structure (hereinafter referred to as “S structure”) while dismantling the existing underground structure in a site where the existing underground structure is built. It is related to the construction method of the underground structure that newly constructs the underground structure consisting of
[0002]
[Prior art]
As a method of dismantling an existing underground structure and then constructing a new underground structure whose main structure is an SRC structure or S structure, a retaining wall has been previously constructed on the outer periphery of the underground structure so far. While supporting the mountain retaining wall with the earth anchor, dismantle the existing underground structure first, dig the ground to a predetermined depth, build the foundation, and assemble the steel frame of the underground structure on this foundation, In general, a method of newly constructing a housing in order from the top to the bottom is performed.
[0003]
[Problems to be solved by the invention]
However, with the above method, for example, if the retaining wall is supported by a cut beam, the cut beam will be spanned in multiple stages, and the shelf pile supporting the cut beam will be forested. He was forced to dig, and the work efficiency was very poor.
[0004]
As another method for supporting the retaining wall, the earth anchor method is also known. However, in recent construction work in urban areas, it is often impossible to use an earth anchor outside the site due to the proximity of the adjacent land. .
In addition, there is a reverse casting method in which the main floor is used as a support for the retaining wall and work floor without using beams and earth anchors, and the basement is dug into the basement while building from the upper floor to the basement. As is known, it is necessary to install a construction pillar that supports the main floor in advance, and this construction pillar must be installed through the frame of an existing structure. There were problems such as a long construction period and construction costs.
[0005]
The present invention has been made to solve the above-described problems. When a new underground structure whose main structure is an SRC structure or an S structure is newly constructed in a site where an existing underground structure is built, To provide a method for constructing an underground structure that can be used from the dismantling of an existing underground structure to the construction of a new underground structure, without the use of timber support works such as beams. Is an issue.
[0006]
[Means for Solving the Problems]
The construction method of the underground structure according to claim 1 is a construction method of an underground structure for constructing a new underground structure of the same scale as the existing underground structure in a site where the existing underground structure is demolished, After constructing a retaining wall on the outer periphery of the existing underground structure, disassemble the entire outer peripheral part of the existing underground structure and the first underground floor of the central part, and then to the supporting ground on the outer peripheral part of the existing underground structure Build the structural pillar to reach and support the structural pillar and the retaining wall to construct the surrounding floor of the ground floor of the newly installed underground structure, the central part of the existing underground structure to the lowest floor Dismantled, and then build the steel frame of the central part of the newly installed underground structure in order from the lowest floor to the highest floor, and between the uppermost floor of the central part of the newly installed underground structure and the surrounding floor on the ground floor A steel beam between them, and then the existing structure Sequentially dismantle the perimeter from the second basement to the bottom floor, then build the floor of each floor of the outer periphery of the newly built underground structure sequentially from the second basement to the bottom floor, and the surrounding floor and central part of each floor It is characterized by bridging steel beams between each floor.
[0008]
DETAILED DESCRIPTION OF THE INVENTION
FIGS. 1-5 shows an example of the construction method of the underground structure based on this invention, and demonstrates a construction method later on in order.
[0009]
(1) First, a mountain retaining wall 2 is constructed around an existing underground structure 1 (hereinafter referred to as “existing underground structure”) (see FIG. 1 (1)). The retaining wall 2 is constructed to support the surrounding earth pressure until the existing underground structure 1 is demolished and then a new underground structure (hereinafter referred to as “new underground structure”) is constructed. For example, it is constructed by a continuous mountain fastening method.
[0010]
(2) Next, the underground first floor portion B1F of the existing underground structure 1 is dismantled over the entire central portion A and outer peripheral portion B (see FIGS. 1 (2) and (3)). This dismantling work shall be carried out with heavy machinery that has been generally used so far.
[0011]
(3) Next, for the central part A of the existing underground structure 1, the dismantling work is continued with the second basement part B2F and the third basement part B3F, and dismantling to the lowest floor (Fig. 1 (4), (See Fig. 2 (1)). On the other hand, in the outer peripheral part B of the existing underground structure 1, the construction pillar 3 is constructed on the floor of the first basement part B1F (see FIG. 1 (4)).
[0012]
The structural pillar 3 works as a temporary pillar until the existing underground structure 1 is demolished and then a new underground structure to be described later is constructed. Further, depending on the construction method, the structural pillar 3 can also be a pillar of the new underground structure. It is.
[0013]
Therefore, the structural pillar 3 is raised up to the floor portion of the first floor above the ground, and penetrates the floor of the underground first floor portion B1F of the existing underground structure 1 and the floors of all the floors below it, and surely reaches the supporting ground. For example, it is constructed by the all-swivel all-casing method.
[0014]
The reason why the outer peripheral portion B is particularly left until the central portion A of the existing underground structure 1 is dismantled is to use the outer peripheral portion B as a support for supporting the retaining wall 2.
[0015]
Therefore, while dismantling the central portion A, the width of the outer peripheral portion B to be left is determined by the depth of the existing underground structure 1 and the ground conditions of the site where the existing underground structure 1 is constructed. In the figure, one span of the existing underground structure 1 is left as a support for the retaining wall 2.
[0016]
(4) Next, the floor 4A on the ground floor is constructed in the outer peripheral portion B (see FIG. 2 (4)). This floor 4A is used as a work floor for performing the subsequent work, and is constructed by supporting the surrounding retaining wall 2 and the structural pillar 3. Further, the floor 4A also becomes a floor of the first floor part of the newly installed underground structure to be constructed later depending on the construction method.
[0017]
(5) Next, when the dismantling of the central portion A proceeds to the lowest floor, the lower ground is further dug down to a predetermined depth to form a root-cutting ground surface 5 (see FIG. 3 (3)). It should be noted that in this root cutting work, slopes 6 are provided in the surrounding area in order to prevent the occurrence of accidents such as collapse of natural grounds and to ensure work safety.
[0018]
(6) Next, the foundation 7 of the newly installed underground structure is constructed on the root cutting ground surface 5 (see Fig. 3 (3)), and the steel frame 8 of the newly installed underground structure is placed on it from the lowest floor. Assemble sequentially to the top floor (see Fig. 3 (3)). Then, the steel beam 9A is bridged between the steel beam 8a on the top floor and the surrounding floor 4.
[0019]
The steel beam 9A functions as a cutting beam that supports the retaining wall 2 until the outer peripheral portion B of the existing underground structure 1 is dismantled, and depending on the construction method, the uppermost floor of the steel frame 8 It is left as a steel beam.
[0020]
(7) Next, disassemble the outer peripheral part B of the existing underground structure 1 into the second basement part B2F, the third basement part B3F, and the upper floor in order (Figs. 3 (1), (2), (See (3)). In particular, floors 4B, 4C, and 4D that function in the same manner as floor 4A are constructed after dismantling each floor. Further, steel beams 9B, 9C, 9D having the same function as the steel beam 9A are bridged between the floors 4B, 4C, 4D of each floor and the steel frame 8 (FIGS. 3 (1), (2), (See (3)).
[0021]
In addition, if the steel beams 9A, 9B, 9C, and 9D are acted as cutting beams, the cross section of each steel beam may become large and may be extremely uneconomical. Therefore, the steel beams 9A, 9B, 9C, and 9D are replaced. Alternatively, the concrete floors 10A, 10B, 10C, and 10D may be constructed, and the concrete floors 10A, 10B, 10C, and 10D may be used as a beam.
[0022]
(8) When the dismantling of the outer peripheral part B of the existing underground structure 1 is completed up to the lowest floor in this way, the lower ground is further dug down to the root section 5 of the central part (see Fig. 4 (1)), After that, the foundation 7 of the new underground structure is constructed integrally with the foundation 7 of the central portion A (see FIG. 4 (2)). It should be noted that the slope 6 is provided in the periphery in order to prevent the occurrence of a collapse of a natural ground and the safety of the work in the root cutting work of the outer peripheral portion B.
[0023]
Through the above process, the process from the dismantling of the existing underground structure 1 to the construction of the new underground structure (steel frame 8) can be continued very efficiently and economically without the need for special support work such as beams. Can be done.
[0024]
【The invention's effect】
The present invention is as described above, and by leaving the outer peripheral portion of the existing underground structure and using it as a support for the retaining wall until the outer peripheral portion of the existing underground structure is dismantled, It is possible to omit the supporting work such as a cut beam and a ground anchor which are necessary for supporting the retaining wall.
[0025]
Therefore, the dismantling of the main part of the existing underground structure and the excavation work under the main part can be efficiently performed, and the construction period can be shortened and the construction cost can be reduced.
[0026]
Moreover, about the range which leaves as a support body of a retaining wall and is demolished later, it is not necessary to provide a large-scale work table by constructing a work floor at the first floor level at an early stage by the reverse driving method. In addition, the upper frame work in the central part can be carried out simultaneously with the underground work, and the construction period can be shortened.
[0027]
In this way, when constructing a new underground structure while dismantling the existing underground structure, by effectively using the existing underground structure, which is originally an obstacle to the construction, instead of the temporary mountain retaining material, demolition work, excavation work, Underground building construction can be carried out efficiently, shortening the construction period and reducing temporary construction costs.
[Brief description of the drawings]
FIG. 1 (1) to (4) are process diagrams showing from the construction of a retaining wall to the construction of a structural pillar.
FIG. 2 (1) to (4) are process diagrams showing from the dismantling of the central part to the construction of the foundation.
FIGS. 3 (1) to (3) are process diagrams showing the process from assembling the steel frame of the newly-constructed structure to disassembling the outer peripheral portion.
FIGS. 4A and 4B are process diagrams showing from the root cutting of the outer peripheral portion to the construction of the foundation.
FIG. 5 is a plan view showing an arrangement example of a retaining wall and a true pillar.
[Explanation of symbols]
1 Existing underground structure (existing underground structure)
2 Mountain retaining wall 3 True column 4A Floor 4B Floor 4C Floor 4D Floor 5 Root cut ground surface 6 Slope 7 Foundation 8 Steel frame 8a Steel beam 9A Steel beam 9B Steel beam 9C Steel beam 9D Steel beam
10A concrete floor
10B Concrete floor
10C concrete floor
10D concrete floor

Claims (1)

既設地下構造物を解体した敷地内に、当該既設地下構造物と同じ規模の新設地下構造物を構築する地下構造物の構築工法であって、既設地下構造物の外周に山留め壁を構築した後、前記既設地下構造物の外周部分および中央部分の地下一階分を全体にわたって解体し、次に前記既設地下構造物の外周部分に支持地盤まで到達する構真柱を施工し、かつ当該構真柱および前記山留め壁に支持させて新設地下構造物の地上一階の周囲床を構築し、前記既設地下構造物の中央部分は最下階まで解体し、その後に新設地下構造物の中央部分の鉄骨軸組を最下階から最上階まで順に構築し、かつ当該新設地下構造物の中央部分の最上階と地上一階の前記周囲床との間に鉄骨梁を架け渡し、次に前記既設構造物の外周部分を地下二階部分から最下階まで順次解体しつつ、その後に新設地下構造物の外周部分の各階の床を地下二階から最下階まで順次構築し、かつ各階の周囲床と中央部分の各階間に鉄骨梁をそれぞれ架け渡すことを特徴とする地下構造物の構築工法。 An underground structure construction method for constructing a new underground structure of the same scale as the existing underground structure on the site where the existing underground structure has been demolished, and after building a retaining wall on the outer periphery of the existing underground structure , Dismantling the entire outer peripheral part and central part of the existing underground structure, and then constructing a structural pillar that reaches the supporting ground at the outer peripheral part of the existing underground structure, and The surrounding floor of the ground floor of the new underground structure is constructed by supporting the pillar and the retaining wall, the central part of the existing underground structure is demolished to the lowest floor, and then the central part of the new underground structure is A steel frame is constructed in order from the lowest floor to the highest floor, and a steel beam is bridged between the uppermost floor of the central part of the new underground structure and the surrounding floor of the first floor above the ground, and then the existing structure In order from the second floor of the basement to the lowest floor After dismantling, the floor of each floor of the newly constructed underground structure is constructed sequentially from the second basement floor to the lowest floor, and steel beams are bridged between the surrounding floor of each floor and each floor of the central part Construction method for underground structures.
JP2000076029A 2000-03-17 2000-03-17 Construction method for underground structures Expired - Lifetime JP3724320B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000076029A JP3724320B2 (en) 2000-03-17 2000-03-17 Construction method for underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000076029A JP3724320B2 (en) 2000-03-17 2000-03-17 Construction method for underground structures

Publications (2)

Publication Number Publication Date
JP2001262594A JP2001262594A (en) 2001-09-26
JP3724320B2 true JP3724320B2 (en) 2005-12-07

Family

ID=18593828

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000076029A Expired - Lifetime JP3724320B2 (en) 2000-03-17 2000-03-17 Construction method for underground structures

Country Status (1)

Country Link
JP (1) JP3724320B2 (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3977700B2 (en) * 2002-07-11 2007-09-19 鹿島建設株式会社 Demolition and new construction method using existing underground structure
JP2005307688A (en) * 2004-04-26 2005-11-04 Nippon Steel Corp Construction method for earth retaining wall for newly built underground skeleton and construction method for newly built skeleton by use of its method
KR100736241B1 (en) 2006-09-07 2007-07-06 주식회사 백산종합개발 Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall
JP5132464B2 (en) * 2008-07-29 2013-01-30 大成建設株式会社 Excavation method
JP5303381B2 (en) * 2009-07-09 2013-10-02 戸田建設株式会社 Demolition method for existing buildings
JP5525850B2 (en) * 2010-02-15 2014-06-18 戸田建設株式会社 Mountain fastening method
JP5811389B2 (en) * 2010-11-17 2015-11-11 清水建設株式会社 Construction method for underground structures
JP6274406B2 (en) * 2013-12-27 2018-02-07 清水建設株式会社 Construction method of new underground structure with dismantling of existing underground structure
JP6424060B2 (en) * 2014-10-10 2018-11-14 株式会社竹中工務店 How to rebuild a structure
JP6103667B1 (en) * 2016-03-14 2017-03-29 大成建設株式会社 Construction method of underground structure
JP6827256B2 (en) * 2016-08-02 2021-02-10 大成建設株式会社 How to rebuild the building
JP6988047B2 (en) * 2016-10-20 2022-01-05 株式会社竹中工務店 How to reconstruct the underground skeleton
JP7293567B2 (en) * 2018-01-24 2023-06-20 株式会社竹中工務店 Construction method of structures

Also Published As

Publication number Publication date
JP2001262594A (en) 2001-09-26

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
JP3724320B2 (en) Construction method for underground structures
JP2001262595A (en) Building construction method of underground building frame
JP2596798B2 (en) Existing building seismic isolation method
JP4050816B2 (en) Construction method of underground part of steel reinforced concrete building
JP4115095B2 (en) Reverse strike method
JP2001271497A (en) Temporary bearing construction method for existing building
JP2020125630A (en) Building construction method
JP2000087348A (en) Steel segment, underground reinforced concrete columnar structure and construction method thereof
JP6832761B2 (en) How to rebuild the building
JP3977700B2 (en) Demolition and new construction method using existing underground structure
JPH0559728A (en) Sheathing work above underground structure
KR101256311B1 (en) Structual deepening method
KR100592397B1 (en) storey spacing support ssoldier pile soil retaining wall
JP4879582B2 (en) How to extend the basement floor under the foundation of an existing building
JPS63280153A (en) Underground inverted lining method
JP2571426B2 (en) Construction method of retaining wall
JPH07150565A (en) Earth retaining construction method
JPH03147926A (en) construction method for basement
JP3809340B2 (en) Reverse strike method
JP6851180B2 (en) How to rebuild the building
JP2926151B2 (en) Building structure and construction method
JP2894217B2 (en) Building structural frame
JP3281554B2 (en) How to rebuild underground structures

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050210

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050222

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050422

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050524

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050721

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050830

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050912

R150 Certificate of patent or registration of utility model

Ref document number: 3724320

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110930

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110930

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140930

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term