KR20210051326A - Batch down wall demolition method - Google Patents

Batch down wall demolition method Download PDF

Info

Publication number
KR20210051326A
KR20210051326A KR1020190136450A KR20190136450A KR20210051326A KR 20210051326 A KR20210051326 A KR 20210051326A KR 1020190136450 A KR1020190136450 A KR 1020190136450A KR 20190136450 A KR20190136450 A KR 20190136450A KR 20210051326 A KR20210051326 A KR 20210051326A
Authority
KR
South Korea
Prior art keywords
wall
demolition
strut
construction
pile
Prior art date
Application number
KR1020190136450A
Other languages
Korean (ko)
Inventor
박차순
Original Assignee
박차순
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박차순 filed Critical 박차순
Priority to KR1020190136450A priority Critical patent/KR20210051326A/en
Publication of KR20210051326A publication Critical patent/KR20210051326A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings

Abstract

A conventional underground structure demolition method requires a long construction period and excessive costs to make demolition very difficult. The present invention complements the conventional demolition method and provides a method for safely tearing down a wall without a structural problem in a wall demolition method of a decrepit building. A conventional method uses a wale and a strut in a wall to descend while tearing down the interior (miscellaneous materials and others). The method removes a foundation or drills the position of a PRD, a corner pile, and a middle pile in advance by surveying. The method removes the wale and the strut and backfills while ascending. The present invention generally uses structural calculation, a verified earth retaining method, and a beam and a steel pipe strut (1,000m/m) to tear down a wall in steps of 2-3m from the ground and then install a wale and a strut and descend. The method simultaneously tears down the wall and the interior. The ground of a retaining wall is transferred when inserting a retaining plate into a newly installed retaining wall to mount an existing wall to be torn down (advantage) and install the wale and the strut on the wall. The strut is installed on each floor and then on a lower floor. The foundation is removed by using a wheel saw, a core, and a buster. A middle pile and a corner pile are installed up to the bottom by using 300×200 beams. A penetration depth (diameter of 5m) is driven downwards (a core and a small drill) by a micropile (diameter of 21.5cm) underneath the foundation.

Description

일괄 내림식 벽체철거공법{BATCH DOWN WALL DEMOLITION METHOD}Batch descending wall demolition method {BATCH DOWN WALL DEMOLITION METHOD}

본 발명은 토목분야에 관한 것으로써, 상세하게는 흙막이공사의 지하옹벽 철거에 있어서 비용절감과 공사의 효율성을 높이기 위해 사용되는 일괄 내림식 벽체 철거공법에 관한 것이다. The present invention relates to the field of civil engineering, and more particularly, to a batch-down wall demolition method used to reduce cost and increase the efficiency of construction in the demolition of an underground retaining wall of an earthen barrier construction.

다음은 일괄 내림식 벽체철거공법의 배경이 되는 기술 두 가지로써, The following are two technologies that are the background of the collective unloading wall demolition method.

국내 특허 공개번호 1020100101271(2009.03.09) '하향식 지하 구조물의 철거공법'과 국내 특허 등록번호 1007362410000(2007.06.29) '지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법'의 구조 및 시공방법을 나타낸 것이다.Korean Patent Publication No. 1020100101271 (2009.03.09)'Top-down underground structure demolition method' and domestic patent registration number 1007362410000 (2007.06.29)'Up-down sequential removal and sequential reclamation method for removing the underground retaining wall' structure and construction method. Is shown.

국내 특허 공개번호 1020100101271(2009.03.09)'하향식 지하 구조물의 철거공법'에 대한 시공방법의 설명은 다음과 같다. Domestic Patent Publication No. 1020100101271 (2009.03.09) The description of the construction method for the'Top-down underground structure demolition method' is as follows.

1. 우선 슬래브 구멍을 뚫고 중앙파일 및 코너파일을 설치한다.1. First, drill a hole in the slab and install the central pile and corner pile.

2. 벽체 내부에 띠장, 스트러트를 설치한다. 2. Install strips and struts inside the wall.

3. 슬래브 내부철거를 하면서 바닥까지 내려간다. 3. Go down to the floor while dismantling the inside of the slab.

4. 기초에 포스트파일, 코너파일을 위치시키고 천공작업을 한다. 4. Place post piles and corner piles on the foundation and drill.

5. 되메우기 및 다짐후 각층마다 띠장과 스트러트를 반복적으로 해체하면서 상부로 올라간다.5. After backfilling and compacting, the strip length and strut are repeatedly dismantled for each layer and raised to the top.

6. 토목업체(항타기, 천공)가 사이드파일, 코너파일, 포스트파일, PRD를 천공 및 근입한다.6. A civil engineering company (driving machine, drilling) drills and installs side piles, corner piles, post piles, and PRDs.

7. 토목업체와 철거업체가 동시작업으로 띠장과 스트러트를 설치하면서 토목업체의 터파기와 철거업체의 벽체철거작업이 서로 간섭된다. 7. As civil engineering companies and demolition companies install strips and struts at the same time, the excavation of the civil engineering company and the demolition work of the demolition company interfere with each other.

국내 특허 등록번호 1007362410000(2007.06.29)'지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법'에 대한 시공방법의 설명은 다음과 같다. Domestic Patent Registration No. 1007362410000 (2007.06.29) The explanation of the construction method for the'up-down sequential removal and sequential reclamation method for removing the underground retaining wall' is as follows.

앞서 설명한 국내 특허 공개번호 1020100101271(2009.03.09)'하향식 지하 구조물의 철거공법'의 단계 1번부터 4번까지는 동일한 관계로 생략한다.Steps 1 to 4 of the above-described Korean Patent Publication No. 1020100101271 (2009.03.09)'Top-down underground structure demolition method' are omitted due to the same relationship.

5. 기초철거 시 되메우기작업과 벽체철거를 각층마다 반복적으로 진행하면서 상부로 올라간다.5. When the foundation is demolished, the backfilling work and the wall dismantling are repeatedly carried out for each floor, going up to the top.

6. 상단 나대지 상태에서 파일을 인발한 후 토목업체에 인계한다.6. After drawing the file in the top bare ground condition, hand it over to a civil engineering company.

그런데, 이와 같은 구성을 갖는 종래의 철거방법 2가지는 다음과 같은 점에서 문제점을 야기했다. However, the two conventional demolition methods having such a configuration caused problems in the following points.

국내 특허 공개번호 1020100101271(2009.03.09)'하향식 지하 구조물의 철거공법'은 내부철거하면서 내려가고 기초에 포스트구멍을 뚫고 되메우기와 해체를 하면서 상단에 올라간다. 토목업체가 파일을 천공한 후 토목업체와 철거업체가 동시에 각각 터파기와 벽체철거를 하며 내려간다. 버림 타설 후 띠장 및 스트러트를 해체하면서 올라가므로 내려가고 올라가는 공정이 여러 번 번복된다. 이는 공사의 능률을 저하시킬 뿐 아니라 공사기간이 늘어나게 만드는 요인이 된다. Korean Patent Publication No. 1020100101271 (2009.03.09)'Top-down underground structure demolition method' goes down while internally demolition, drills a post hole in the foundation, backfills and dismantles it, and rises to the top. After the civil engineering company drills the pile, the civil engineering company and the demolition company go down while digging and demolition of the wall, respectively. The process of going down and going up is overturned several times as it goes up while dismantling the strip and strut after throwing away. This not only lowers the efficiency of the construction, but also becomes a factor that increases the construction period.

국내 특허 등록번호 1007362410000(2007.06.29)'지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법' 역시 내부철거하면서 내려가고 기초철거후 벽체철거를 하며 상부로 올라간 다음 하부에서 상부로 역행하며 장비작업을 하게 된다. Domestic patent registration number 1007362410000 (2007.06.29)'Upward sequential removal and sequential reclamation method for removing underground retaining walls' also goes down while internally demolition, removes the wall after basic demolition, goes up to the top, then runs backwards from the bottom to the top, and works on equipment. Will do.

결과적으로, 두 공법 모두 공사의 능률을 저하시켜 공사기간이 늘어나게 되고, 이는 투입비의 과다발생과 공사의 효율성 저하를 초래한다.As a result, both construction methods reduce the efficiency of construction and increase the construction period, which leads to excessive input costs and a decrease in construction efficiency.

국내 특허 공개번호 1020100101271(2009.03.09)'하향식 지하 구조물의 철거공법'Korean Patent Publication No. 1020100101271 (2009.03.09)'Top-down underground structure demolition method' 국내 특허 등록번호 1007362410000(2007.06.29)'지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법'Domestic patent registration number 1007362410000 (2007.06.29)'Up-down sequential removal and sequential reclamation method for removing underground retaining walls'

본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것으로써, 공사기간을 단축하고 투입비를 절감하면서도, 시공이 용이하여 공사의 효율성을 증대시키는 구조의 흙막이공사에 적합한 일괄 내림식 벽체철거공법을 제공하는 것을 그 목적으로 한다.The present invention has been devised to solve the above problems, and provides a batch-down type wall demolition method suitable for the construction of a structure that shortens the construction period, reduces the input cost, and increases the efficiency of the construction due to ease of construction. It is for that purpose.

앞서 말한 내용을 다시 언급하자면 국내 특허 공개번호 1020100101271(2009.03.09) '하향식 지하 구조물의 철거공법'은 내부철거하면서 내려가고 기초에 포스트를 안착시키고 되메우기와 해체를 하면서 상단에 올라간다. 토목업체가 파일을 천공한 후 토목업체와 철거업체가 동시에 각각 터파기와 벽체철거를 하며 내려간다. 버림 타설 후 띠장 및 스트러트를 해체하면서 올라가므로 내려가고 올라가는 공정이 여러 번 번복된다. To reiterate the foregoing, Korean Patent Publication No. 1020100101271 (2009.03.09)'Top-down underground structure demolition method' goes down while being demolished inside, puts a post on the foundation, backfills and dismantles it, and rises to the top. After the civil engineering company drills the pile, the civil engineering company and the demolition company go down while digging and demolition of the wall, respectively. Since the strip and strut are dismantled after casting, the process of going down and up is overturned several times.

국내 특허 등록번호 1007362410000(2007.06.29)'지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법'역시 내부철거하면서 내려가고 기초철거후 벽체철거를 하며 상부로 올라간 다음 하부에서 상부로 역행하며 장비작업을 하게 된다. 이는 공사의 능률을 저하시켜 공사기간이 늘어나게 만들뿐 아니라 투입비의 과다발생을 초래한다. Domestic patent registration number 1007362410000 (2007.06.29)'Upward sequential removal and sequential reclamation method for removing underground retaining walls' also goes down while internally demolition, removes the wall after basic demolition, goes up to the top, then runs backwards from the bottom to the top, and works on equipment. Will do. This not only reduces the efficiency of the construction and increases the construction period, but also causes excessive input costs.

반면에 본 발명은 공사 초반부에 내부철거와 벽체철거 를 동시에 진행하여 시공이 용이하고 전반적인 공정이 빨라지게 된다. 이는 공사기간 단축과 투입비의 절감으로 이어진다. On the other hand, in the present invention, the internal demolition and the wall demolition are simultaneously performed at the beginning of the construction, so that the construction is easy and the overall process is accelerated. This leads to reduction of construction period and input cost.

국내 특허 공개번호 1020100101271(2009.03.09)'하향식 지하 구조물의 철거공법'은 공사 후반부에 토목업체와 철거업체가 동시작업으로 각각 띠장과 스트러트를 설치하게 된다. 이때 토목업체의 터파기와 철거업체의 벽체철거작업이 서로 간섭되면서 공사기간이 늘어나고 투입비가 과다발생하게 된다. Korean Patent Publication No. 1020100101271 (2009.03.09)'Top-down underground structure demolition method' will be installed by a civil engineering company and a demolition company at the same time in the latter part of the construction, respectively. At this time, the construction period is prolonged and the input cost is excessive as the excavation of the civil engineering company and the demolition work of the demolition company interfere with each other.

반면에 본 발명은 토목업체에만 인계하면 되므로 토목업체와 철거업체 간의 간섭이 없게 되면서 공사기간 단축과 투입비 절감의 효과를 얻을 수 있다. On the other hand, since the present invention only needs to be handed over to a civil engineering company, there is no interference between a civil engineering company and a demolition company, thereby reducing the construction period and input cost.

본 발명은 종래의 공법 대비 공사기간을 단축하고 투입비를 절감하면서도, 시공이 용이하여 공사의 효율성을 증대시키는 구조의 흙막이공사에 적합한 일괄 내림식 벽체철거공법을 제공한다. The present invention provides a collective lowering-type wall demolition method suitable for the construction of a structure that shortens the construction period and reduces the input cost compared to the conventional construction method, and increases the efficiency of the construction by being easy to construct.

도1은 본 발명에 의한 흙막이 공사의 지하옹벽 철거에 적합한 일괄 내림식 벽체철거공법을 도시한 것으로써,
도 1은 전체 단면도와 주요부인 A-A부분을 확대한 단면도.
1 is a diagram showing a batch-down type wall demolition method suitable for the demolition of an underground retaining wall in a soil barrier construction according to the present invention,
1 is an enlarged cross-sectional view of the entire cross-sectional view and AA, which is a main part.

본 발명에 관한 시공법과 그로 인한 이점을 단계적으로 상세히 설명하도록 하겠다. The construction method according to the present invention and the advantages thereof will be described in detail step by step.

1. 우선 슬래브 구멍을 뚫고 중앙파일 및 코너파일을 설치한다.1. First, drill a hole in the slab and install the central pile and corner pile.

2. 벽체철거작업후 토류 벽에 띠장 및 스트러트 설치한다. 2. After removing the wall, install strips and struts on the earth wall.

일반적으로는 300×300×10×15인 스트러트를 사용하나, 지름이 800mm인 강관을 사용하는 PPS공법을 적용하여 구조적 안전감을 제공한다. 또한 일반적으로 사용되어져 온 구조적 증명된 가시설 흙막이공법을 적용하여 안전성을 높였다. In general, struts of 300×300×10×15 are used, but structural safety is provided by applying the PPS method using a steel pipe with a diameter of 800mm. In addition, the safety was improved by applying the structurally proven temporary facility earth protection method that has been used in general.

내부철거와 벽체철거 를 동시에 진행하여 시공이 용이하고 전반적인 공정이 빨라지게 된다. 이는 공사기간 단축과 투입비의 절감으로 이어진다.The internal demolition and the wall demolition are carried out at the same time to facilitate construction and speed up the overall process. This leads to reduction of construction period and input cost.

3. 무소음 크략샤 작업 중 기존 토류벽 손상 시에는 재생하며 내려간다.3. When the existing earth wall is damaged during the noiseless cracking operation, it is regenerated and descended.

4. 슬래브 및 벽체철거 를 하면서 각층마다 1단에서 6단 바닥까지 내려간다.4. The slabs and walls are demolished and each floor goes down from the 1st to the 6th floor.

5. 휠쏘, 코어, 버스타로 기초철거 를 제거한다. 이때 수시로 폐기물을 상차한다. 5. Remove the basic demolition with a wheel saw, core, and buster. At this time, load the waste from time to time.

6. 수시로 되메우기 및 다짐을 함과 동시에 띠장 및 스트러트를 해체하면서 6단에서 1단까지 올라간다.6. Ascends from 6th to 1st by dismantling the strip and strut as well as backfilling and consolidating from time to time.

7. 상단 나대지후 인발작업을 실시한다.7. Perform the drawing work after the top bare ground.

8. 토목업체에 인계한다. 토목업체와 철거업체 간 간섭 없이 토목업체에만 인계하면 되므로, 공사기간 단축과 투입비 절감의 효과를 얻을 수 있다. 8. Hand over to a civil engineering company. Since it is only necessary to hand over to the civil engineering company without interference between the civil engineering company and the demolition company, the effect of shortening the construction period and reducing the input cost can be obtained.

1 : STRUT
2 : WALL
3 : 100 TON
4 : 브라켓트 설치
5 : 벽체철거 위치(1차적 : 2M)
6 : 벽체철거 위치(내려가면서 반복 작업)
7 : 기존 : SIDE-PILE
8 : 계단
9 : 기초철거 위치
10 : 코어천공
11 : 마이크로파일 설치(봉 지름 : 21.5CM 설치 : 근 입장 5M) 임시용 설치
12 : 스티프너 설치
13 : WALL. STRUT. 작키. 브라켓트 : 반복 작업하면서 내려감
1: STRUT
2: WALL
3: 100 TON
4: Bracket installation
5: Wall removal location (primary area: 2M)
6: Wall removal location (repeated work while going down)
7: Existing: SIDE-PILE
8: stairs
9: Foundation removal location
10: core drilling
11: Micropile installation (bar diameter: 21.5CM installation: root entry 5M) temporary installation
12: stiffener installation
13: WALL. STRUT. Jockey. Bracket: Down while repetitive work

Claims (7)

기존의 지하철거공법은 철거 투입비가 과다하게 발생하여 비용측면에서 많은 부담이 있었다. 본 발명은 기존의 공법에 비해 공사기간과 투입비를 1/3가량 줄일 수 있는 일괄 내림식 벽체철거공법이다.Existing subway construction method had a lot of burden in terms of cost due to excessive demolition input cost. The present invention is a batch-down wall demolition method that can reduce construction period and input cost by about 1/3 compared to the existing construction method. 타 공법은 상부에서 내려갈 때 슬래브 및 내부철거 만을 한다. 본 발명은 증명된 일반적인 흙막이공법(빔, 강관 스트러트:1000M/M)을 이용하여 벽체철거는 물론 슬래브, 기둥, 기타 전부를 철거 하는 일괄 내림식 벽체철거공법이다. The other construction method only removes the slab and interior when descending from the top. The present invention is a batch-down type wall demolition method that removes all of the slabs, columns, and others as well as the wall demolition using a proven general earthen barrier method (beam, steel pipe strut: 1000M/M). 기존 공법은 하부에서 상부를 벽체 철거할 때 공사기간 및 투입비가 배로 발생한다. 그러나 본 발명은 상부에서 하부로 벽체 철거할 때 공사기간 및 투입비가 절감되는 일괄 내림식 벽체철거공법이다. In the existing construction method, when the wall is removed from the lower part to the upper part, the construction period and input cost are doubled. However, the present invention is a collective lowering-type wall demolition method in which the construction period and input cost are reduced when the wall is removed from the top to the bottom. 기초는 휠쏘, 코어작업, 버스타 작업으로 제거하며 중앙파일과 코너파일은 상부는 300×200파일, 하부는 마이크로파일 21.5CM로 보강하는 단계를 거친다. The foundation is removed with a wheel saw, core work, and buster work, and the center pile and corner pile go through a step of reinforcing the upper part with 300×200 piles and the lower part with 21.5cm micropile. 바닥에서부터 토사 되메우기, 다짐, 띠장 해체, 스트러트를 해체하면서 지상으로 올라가는 단계를 거친다.It goes through the steps of backfilling the soil from the bottom, compacting, dismantling the belt, and dismantling the struts. 끝으로 상부 나대지(되메우기)후 인발작업을 하는 단계를 거친다. Finally, it goes through the step of drawing after the upper bare ground (backfill). 토목업체는 측량작업 후 사이드파일, 천공, 중앙파일 천공, 코너파일 천공, PRD 시공 천공을 하고 터파기를 진행하며 단계를 마무리한다.



After surveying, a civil engineering company completes the steps by drilling side piles, drilling, central pile drilling, corner pile drilling, PRD construction drilling, and digging.



KR1020190136450A 2019-10-30 2019-10-30 Batch down wall demolition method KR20210051326A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190136450A KR20210051326A (en) 2019-10-30 2019-10-30 Batch down wall demolition method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190136450A KR20210051326A (en) 2019-10-30 2019-10-30 Batch down wall demolition method

Publications (1)

Publication Number Publication Date
KR20210051326A true KR20210051326A (en) 2021-05-10

Family

ID=75917433

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190136450A KR20210051326A (en) 2019-10-30 2019-10-30 Batch down wall demolition method

Country Status (1)

Country Link
KR (1) KR20210051326A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102632451B1 (en) * 2023-03-28 2024-02-05 (주)채움구조안전진단사무소 Basement Demolition Method using Established-wall

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100736241B1 (en) 2006-09-07 2007-07-06 주식회사 백산종합개발 Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall
KR20100101271A (en) 2009-03-09 2010-09-17 이동희 Method for removing the superannuated build as top-down type

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100736241B1 (en) 2006-09-07 2007-07-06 주식회사 백산종합개발 Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall
KR20100101271A (en) 2009-03-09 2010-09-17 이동희 Method for removing the superannuated build as top-down type

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102632451B1 (en) * 2023-03-28 2024-02-05 (주)채움구조안전진단사무소 Basement Demolition Method using Established-wall

Similar Documents

Publication Publication Date Title
CN105064397B (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
CN108060683A (en) A kind of middle weathering geology top-down construction method
CN106013053B (en) A kind of steel sheet pile construction method for supporting for being used to build underground garage open caisson
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN104847364B (en) A kind of shield continuous cutting pile foundation passes through residential building group construction method
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN101545376A (en) Execution method for feeding tiny tunnel into ultra heavy section tunnel transversally
CN103074899A (en) Subdepot pier-type foundation pit support structure and construction method
CN108301332A (en) The detachable steel trestle construction method of beret slice
CN110306559A (en) A kind of construction method of subway entrance support pile
CN106545019A (en) For the support-replacing system and construction method of stage differential style Underground Construction
KR100877974B1 (en) Reverse removing method of underground retaining wall using bottom-up cut and gradual land infilling with struts
KR102333978B1 (en) Pileless-up wall demolition method
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
KR20210051326A (en) Batch down wall demolition method
CN105862862A (en) Salvage method for large-diameter pile buried hammer
JP3445129B2 (en) Seismic reinforcement of underground pillars
JP2019148070A (en) Construction method of underground structure
CN108222012A (en) A kind of foundation pit anchor cable excision and the construction method that supporting pile is carried out using anchor cable excision system
CN103334451A (en) Underneath-passing channel formed between high-speed rail piers through secant pile walls and method thereof
KR100615149B1 (en) A method of construction top-down for the ground fabric construction
CN209958372U (en) Railway newly-added second-line platform back way foundation pile pipe curtain supporting structure
CN113958322A (en) Tunnel excavation method at lower layer of existing subway line
JPH0559728A (en) Sheathing work above underground structure

Legal Events

Date Code Title Description
AMND Amendment
E601 Decision to refuse application
X091 Application refused [patent]
E601 Decision to refuse application
E801 Decision on dismissal of amendment