KR20020085104A - A method of construction for earth-protection walls of building - Google Patents
A method of construction for earth-protection walls of building Download PDFInfo
- Publication number
- KR20020085104A KR20020085104A KR1020010024386A KR20010024386A KR20020085104A KR 20020085104 A KR20020085104 A KR 20020085104A KR 1020010024386 A KR1020010024386 A KR 1020010024386A KR 20010024386 A KR20010024386 A KR 20010024386A KR 20020085104 A KR20020085104 A KR 20020085104A
- Authority
- KR
- South Korea
- Prior art keywords
- construction
- piles
- ground
- panel
- thumb
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/801—Ground anchors driven by screwing
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
본 발명은 건축용 흙막이 공법에 관한 것이다.The present invention relates to a construction mudstone method.
종래의 흙막이 벽체는 엄지말뚝과 수평널 벽체, 강널말뚝(Steel Sheet Pile)벽체, 주열식 흙막이 벽체(Contiguous Pile Walls) 및 현장타설 콘크리트 말뚝벽체 그리고 지하연속벽체(Diaphragm Wall) 등으로 나눌 수 있는데 이들중 지하연속벽체만 건축물의 본체 구조물(영구벽체)로서 제한적인 사용이 가능할 뿐 나머지 벽체들은 가설벽체로서 주변건축물에 침하등의 피해를 주거나 각종 안전사고를 유발할 위함이 많았었다.Conventional retaining walls can be divided into thumb piles and horizontal board walls, steel sheet pile walls, contiguous pile walls, cast-in-place concrete pile walls, and diaphragm walls. Only underground continuous walls could be used as a main body structure (permanent wall) of the building, and the rest of the walls were temporary walls, which were often used to damage surrounding buildings and to cause various safety accidents.
그리고 종래의 지하연속벽체의 경우 굴착면의 붕괴와 지하수의 침투를 방지하기 위해 일정한 폭의 도랑(trench)에 안정액을 공급하면서 원하는 깊이까지 도랑을 굴착한 후 지중에 무근, 철근콘크리트의 개개의 패널을 연속적으로 형성하는 것으로서 시공단면이 크기때문에 벽체공사중에 주변건축물에 피해를 줄 수 있었고, 공사기간이 길어지고 공사비가 많이 들었었으며, 안정액에 의한 환경오염문제를 유발했었고, 시공하는데 고도의 기술이 요구되었었으며, 영구구조물로 활용하기 위해서는 미흡한 등의 문제점이 있었다.In the case of the conventional underground continuous wall, in order to prevent the collapse of the excavation surface and the penetration of the groundwater, the trench is excavated to the desired depth while supplying a stabilizer to a trench of a certain width, and then the individual panels of the reinforced and reinforced concrete in the ground As the continuous cross section was formed, it could damage the surrounding buildings during the construction of the wall due to the large construction section, the construction period was long, the construction cost was high, and it caused the environmental pollution problem by the stabilizer. It was required, and there was a problem such as insufficient to use as a permanent structure.
따라서 종래의 흙막이 벽체들은 시공후 건축물의 본체구조물로서 콘크리트 옹벽을 별도로 시공해야만 하는 것이었기 때문에 공사기간이 길고, 공사비가 많이 들었었을 뿐 아니라 안전사고 방지성이 미흡한 등의 문제점이 있었다.Therefore, the conventional retaining walls have a problem that the construction period is long, the construction cost is high, as well as the lack of safety accident prevention, because the concrete retaining wall had to be separately constructed as a main structure of the building after construction.
본 발명은 건축물의 본체 구조물로도 활용할 수 있는 건축용 흙막이 공법을 제공하는데 기술적 과제를 둔 것이다.The present invention has been made in order to provide a construction mudpole construction method that can also be utilized as the main body structure of the building.
도 1은 본 발명에 적용되는 엄지말뚝의 한 형태를 예시한 사시도.1 is a perspective view illustrating a form of a thumb pile applied to the present invention.
도 2a ∼ 도 2d는 본 발명에 의한 공법의 공정을 보인 평면도.2A to 2D are plan views showing the process of the process according to the present invention.
도 3a는 본 발명에 의한 공법으로 완성된 벽체의 종단면도.Figure 3a is a longitudinal cross-sectional view of the wall completed by the method according to the present invention.
도 3b는 도 3a의 I - I선 단면도.3B is a cross-sectional view taken along the line II of FIG. 3A.
본 발명은 도 1에 예시한 바와 같이 H형강(10)에 연결철근(12)들을 V자형으로 용접한 엄지말뚝(14)을 도 2a에 예시한 바와 같이 지반(A)에 어스드릴(Earth Drill)을 이용하여 일정한 간격으로 천공한 구멍(16)에 박아넣고, 모래(18)를 주입하며, 지반(10) 위로 노출된 엄지말뚝(14)들의 상단부에 버팀보용띠장(20)을 고정시켜서 엄지말뚝(14)들을 지지시키는 단계와, 도 2b에 예시한 바와 같이 엄지말뚝(14)의 앞쪽에서 엄지말뚝(14)들 사이를 터파기하여 작업공간(22)을 확보하고, 엄지말뚝(14)들의 뒷쪽에는 뒤패널(24)을 밀착되게 삽입하며, 엄지말뚝(14)들의 연결철근(12)을 펴서 보강철근(26)의 양쪽을 연결철근(12)들과 연결한 후 엄지말뚝(14)들의 앞쪽에는 앞패널(28)을 밀착시키고, 작업공간(22)을 제자리 흙으로 되메우기 하고 이 되메워진 흙(30)을 다져주어 앞패널(28)을 견고하게 고정시켜주는 단계와, 도 2c에 예시한 바와 같이 앞패널(28)과, 뒤패널(24) 사이에 콘크리트(32)를 타설한 직후 뒤패널(24)을 뽑아내어 뒤패널(24)이 있던 자리에도 콘크리트(32)가 채워지도록 한 상태에서 콘크리트(32)를 양생시키는 단계와, 도 2d에 예시한 바와 같이 앞패널(28)들의 앞쪽지반(A)을 모두 터파기하고 앞패널(28)들을 모두 제거하여 건축물의 본체구조물을 이루는 영구벽체를 겸하는 흙막이 옹벽(B)을 완성하는 단계로 이루어진 것이다.As shown in FIG. 1, the present invention provides an earth drill to the ground A as shown in FIG. 2A of a thumb pile 14 welded to the H-shaped steel 10 with V-shaped welded reinforcing bars 12. ) Into the perforated hole 16 at regular intervals, injecting sand 18, and fixing the support belt length 20 to the upper end of the thumb piles 14 exposed above the ground 10. Supporting the piles 14, and as shown in Figure 2b to dig between the thumb piles 14 in front of the thumb pile 14 to secure the work space 22, the thumb piles 14 of The rear panel 24 is inserted in close contact with the back, and the connecting bars 12 of the thumb piles 14 are extended to connect both sides of the reinforcing bar 26 with the connecting bars 12, and then the thumb piles 14 The front panel 28 is in close contact with the front panel, the work space 22 is backfilled with soil, and the backfilled soil 30 is chopped to secure the front panel 28. 2C, and the rear panel 24 is pulled out immediately after pouring the concrete 32 between the front panel 28 and the rear panel 24, as illustrated in FIG. 2C. Curing the concrete 32 in a state where the concrete 32 is filled even in the place where it was, and as shown in FIG. 2d, all the front grounds A of the front panels 28 are destroyed and the front panel 28 is removed. ) To complete the retaining wall (B) to serve as a permanent wall forming the body structure of the building by removing all).
이와 같은 흙막이 옹벽(B)의 앞쪽에는 도 2d, 도 3a 및 도 3b에 예시한 바와 같이 통상의 방수벽(C)과 방수보호벽(D)을 차례로 시공할 수 있게 된다.As shown in FIGS. 2D, 3A, and 3B, the front wall of the retaining wall B can be constructed with the normal waterproof wall C and the waterproof protective wall D in sequence.
도면중 미설명 부호 E는 슬래브연결용철근이다.In the figure, reference numeral E denotes rebar for slab connection.
본 발명에 있어서, 엄지말뚝(14)이 박혀진 구멍(16)에 모래(18)를 주입하는 이유는 공사중 H형강(10)과 연결철근(12)에 이물질이 들어붙지 않도록 보존하고, 구멍(16) 주위의 지반과의 압력차이에 의한 주변건축물의 지반침하를 방지함과 아울러서 패널(24), (28)을 H형강(10)과 밀착되도록 쉽게 삽입할 수 있고, H형강(10) 주위로 타설되는 콘크리트(32)의 피복상태를 좋게 해줄 수 있기 때문이다.In the present invention, the reason for injecting the sand 18 into the hole 16 in which the thumb pile 14 is embedded is to preserve the H-shaped steel 10 and the connecting reinforcing bar 12 so that foreign matter does not get into the hole, 16) In addition to preventing ground subsidence of the surrounding buildings due to pressure differences with the surrounding ground, the panels 24 and 28 can be easily inserted to be in close contact with the H-shaped steel 10, and the H-shaped steel 10 can be easily inserted. This is because it can improve the coating state of the concrete 32 to be poured.
또 콘크리트(32)를 타설한 직후 뒤패널(24)을 뽑아내는 이유는 H형강(10)의 뒷쪽도 콘크리트(32)로 피복함과 아울러서 지반(A)의 흙막이 대상흙의 토사와 콘크리트(32)의 시멘트성분이 섞이면서 양생되도록 하여 흙막이옹벽(B)의 차수성을 좋게해 줄 수 있기 때문이다.The reason why the rear panel 24 is pulled out immediately after pouring the concrete 32 is that the back side of the H-beam 10 is also covered with concrete 32, and the soil and concrete of the soil of the ground A are covered (32). This is because it is possible to improve the orderability of the retaining wall (B) by allowing the cement components of) to be cured while being mixed.
그리고 엄지말뚝(14)들 사이를 터파기하는 것과, 보강철근(26)의 연결 및 콘크리트(32)를 타설하는 공정들은 흙막이 공사의 규모나 지반상태 등을 고려하여서 엄지말뚝(14)들 전체를 대상으로 하여 한번에 실시하거나 도 2b, 도 2c에 예시한 바와 같이 2개의 엄지말뚝(14)을 한조로 하여서 한조 건너 한조씩 나누어서 실시할 수 도 있다.And the process of digging between the thumb piles 14, the connection of the reinforcing steel (26) and the process of pouring concrete 32 to the whole of the thumb piles 14 in consideration of the size of the earth construction, ground conditions, etc. It may be carried out at a time as a target or divided into two pairs by one pair of two thumb piles 14 as illustrated in Fig. 2b, 2c.
본 발명은 건축물의 본체구조물을 이루는 영구벽체를 겸하는 흙막이옹벽을 얻을 수 있기 때문에 흙막이 벽체와, 영구벽체를 이루는 옹벽을 각각 시공해왔었던 종래에 비하여서 공사기간을 크게 단축시켜 줄 수 있고, 공사비용도 크게 절감할 수 있으며, 지하층 내부의 가용면적을 증대시켜 줄 수 있는 등의 장점이 있다.The present invention can obtain a retaining wall that also serves as a permanent wall constituting the main structure of the building, it can significantly shorten the construction period compared to the conventional construction of retaining wall and retaining wall forming a permanent wall, construction cost It can also greatly reduce, there is an advantage such as to increase the available area inside the basement floor.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2001-0024386A KR100401330B1 (en) | 2001-05-04 | 2001-05-04 | A method of construction for earth-protection walls of building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2001-0024386A KR100401330B1 (en) | 2001-05-04 | 2001-05-04 | A method of construction for earth-protection walls of building |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20020085104A true KR20020085104A (en) | 2002-11-16 |
KR100401330B1 KR100401330B1 (en) | 2003-10-17 |
Family
ID=27703744
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2001-0024386A KR100401330B1 (en) | 2001-05-04 | 2001-05-04 | A method of construction for earth-protection walls of building |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100401330B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101052641B1 (en) * | 2008-08-25 | 2011-07-28 | 엄기형 | Steel structure for soil wall used to form main wall and main wall forming method using same |
CN102704491A (en) * | 2012-06-11 | 2012-10-03 | 上海强劲地基工程股份有限公司 | Sectional steel and reinforced concrete beam combination foundation pit supporting protection surrounding purlin and construction method of purlin |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101173045B1 (en) * | 2012-03-19 | 2012-08-13 | 주식회사 스페이스테크놀로지 | Earth retaining-cum-retaining wall, and construction method thereof |
CN102943481A (en) * | 2012-12-12 | 2013-02-27 | 上海强劲地基工程股份有限公司 | Reinforced concrete beam and steel beam combined connecting structure for foundation pit supporting and construction method thereof |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH073072B2 (en) * | 1988-03-01 | 1995-01-18 | 株式会社スリー・ユー | Construction method of all underground type underground structure |
JPH03286029A (en) * | 1990-03-31 | 1991-12-17 | Fudo Constr Co Ltd | Steel underground wall and its construction |
JP2684961B2 (en) * | 1993-07-06 | 1997-12-03 | 鹿島建設株式会社 | How to build a building basement wall |
KR970002571B1 (en) * | 1994-02-15 | 1997-03-06 | 이창남 | Process for defensing earth with the arch shape blocking pile in basement construction |
KR100327547B1 (en) * | 1998-10-09 | 2002-11-04 | (주)신화엔지니어링종합건축사사무소 | Composite retaining wall construction method |
KR100346622B1 (en) * | 1999-10-30 | 2002-08-03 | 삼성중공업 주식회사 | Underground construction method using permanent structural members as temporary struts |
KR200221897Y1 (en) * | 2000-11-06 | 2001-04-16 | 주식회사경기기술단 | Mud-plastered wall structure using cast-in-place bar for prevention of earth and sand from being collapsed |
-
2001
- 2001-05-04 KR KR10-2001-0024386A patent/KR100401330B1/en not_active IP Right Cessation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101052641B1 (en) * | 2008-08-25 | 2011-07-28 | 엄기형 | Steel structure for soil wall used to form main wall and main wall forming method using same |
CN102704491A (en) * | 2012-06-11 | 2012-10-03 | 上海强劲地基工程股份有限公司 | Sectional steel and reinforced concrete beam combination foundation pit supporting protection surrounding purlin and construction method of purlin |
Also Published As
Publication number | Publication date |
---|---|
KR100401330B1 (en) | 2003-10-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101179778B1 (en) | Method for constructing underground structure | |
KR101014018B1 (en) | Composite Wall Using Angled Channel | |
KR20090007826A (en) | Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut | |
KR100375020B1 (en) | a pole for mud wall and constrution method of fence for mud | |
KR101021915B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
KR100442712B1 (en) | Construction establishment method and the structure for underground tunnel formation | |
KR101078080B1 (en) | Earth retaining wall and it's construction method using the precast pile and ground reinforcement | |
JPH0960028A (en) | Method for increasing strength of existing steel pipe pile | |
KR100401330B1 (en) | A method of construction for earth-protection walls of building | |
KR101974826B1 (en) | The Precast Pile Having Interlocking Secant and The Earth Retaining Wall Method Constructed by It's Continuous Pile | |
JP4485006B2 (en) | Construction method for underground structures | |
KR101021913B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
KR200296444Y1 (en) | Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method | |
KR100793510B1 (en) | Tension soil nail and construction method of underground wall using the same | |
KR100432782B1 (en) | Supporting structure for tunnel and underground tunnel construction method using the same | |
KR100477357B1 (en) | Construction method for retaining of earth | |
KR100429283B1 (en) | Construction Method using Precast Concrete for Diaphragm Wall | |
KR100327547B1 (en) | Composite retaining wall construction method | |
KR102610909B1 (en) | Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking | |
KR102625776B1 (en) | Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function | |
JP2587309B2 (en) | Protective structure of concrete underground structure and its construction method | |
KR102479045B1 (en) | Tunnel construction method using upper earth pressure support steel plate for installation of structures for excavation of unexcavated underground tunnels | |
JPS6018769B2 (en) | Construction method of underground structure | |
KR200222445Y1 (en) | The ground reinforcement structure used soil nailing | |
KR20040023915A (en) | Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
N231 | Notification of change of applicant | ||
N231 | Notification of change of applicant | ||
GRNT | Written decision to grant | ||
LAPS | Lapse due to unpaid annual fee |