KR102625776B1 - Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function - Google Patents

Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function Download PDF

Info

Publication number
KR102625776B1
KR102625776B1 KR1020220138112A KR20220138112A KR102625776B1 KR 102625776 B1 KR102625776 B1 KR 102625776B1 KR 1020220138112 A KR1020220138112 A KR 1020220138112A KR 20220138112 A KR20220138112 A KR 20220138112A KR 102625776 B1 KR102625776 B1 KR 102625776B1
Authority
KR
South Korea
Prior art keywords
wall
ground
constructing
column
walls
Prior art date
Application number
KR1020220138112A
Other languages
Korean (ko)
Inventor
임용관
Original Assignee
주식회사 예승종합기술공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 예승종합기술공사 filed Critical 주식회사 예승종합기술공사
Priority to KR1020220138112A priority Critical patent/KR102625776B1/en
Application granted granted Critical
Publication of KR102625776B1 publication Critical patent/KR102625776B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 토압에 대응하여 충분한 강도를 확보하면서도 높은 차수 효과를 가질 수 있으며, 시공 중 천공홀 내부로의 지하수 유입과 천공홀 공벽 붕괴 및 배면지반 침하를 방지할 수 있는 개량된 주열식 현장타설 콘크리트(C.I.P) 흙막이벽체의 시공방법에 관한 것으로, 보다 상세하게는 a) 흙막이 대상 지반의 지중에 원지반 토사와 고화제를 교반 및 혼합시켜 복수의 주열식강화벽체를 시공하는 단계; b) 상기 주열식강화벽체가 형성된 영역을 따라 일정 간격으로 천공홀을 형성하고, 선택된 천공홀에 철근망 또는 H빔을 포함하는 보강재를 삽입하는 단계; 및 c) 상기 보강재가 삽입된 천공홀에 콘크리트를 타설 후, 양생하여 상기 주열식강화벽체가 시공된 지반 상에 지지벽체를 시공하는 단계;를 포함하는 것이 특징이다.The present invention is an improved cast-in-place concrete that can secure sufficient strength in response to earth pressure and have a high order effect, and can prevent groundwater inflow into the borehole, collapse of the borehole wall, and subsidence of the back ground during construction. (C.I.P) relates to a construction method of an earth retaining wall, and more specifically, a) the step of constructing a plurality of column-type reinforced walls by stirring and mixing the original ground soil and solidifying agent in the ground of the earth retaining target; b) forming drilling holes at regular intervals along the area where the column-type reinforced wall is formed, and inserting reinforcing materials including reinforcing bar nets or H-beams into the selected drilling holes; and c) pouring concrete into the drilled hole into which the reinforcement material is inserted, curing it, and constructing a support wall on the ground on which the column-type reinforced wall was constructed.

Description

차수 강화 및 지반침하 방지기능이 향상된 CIP 흙막이벽체의 시공방법{Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function}Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function}

본 발명은 토압에 대응하여 충분한 강도를 확보하면서도 높은 차수 효과를 가질 수 있으며, 시공 중 천공홀 내부로의 지하수 유입과 천공홀 공벽 붕괴 및 배면지반 침하를 방지할 수 있는 개량된 주열식 현장타설 콘크리트(C.I.P) 흙막이벽체의 시공방법에 관한 것이다.The present invention is an improved cast-in-place concrete that can secure sufficient strength in response to earth pressure and have a high order effect, and can prevent groundwater inflow into the borehole, collapse of the borehole wall, and subsidence of the back ground during construction. (C.I.P) Concerns the construction method of earth retaining walls.

국내 흙막이벽체 조성공법으로는 H-Pile 토류벽체, 쏘일시멘트벽체(S.C.W), 고강도 흙막이벽체(H.S.W), 현장타설 콘크리트벽체(C.I.P), 콘크리트 지하연속벽체(Slurry Wall) 조성공법 등이 있으며, 각각의 특징이 있어서 설계과정에서 현장조건에 가장 유리한 흙막이벽체 조성공법을 선정하여 적용한다.Domestic earth retaining wall construction methods include H-Pile earth wall, soil cement wall (S.C.W), high-strength earth retaining wall (H.S.W), cast-in-place concrete wall (C.I.P), and concrete underground continuous wall (slurry wall) construction method, respectively. Due to its characteristics, the most advantageous retaining wall construction method for site conditions is selected and applied during the design process.

도심지 및 연약한 지층조건에서 지하층 굴착깊이가 비교적 깊은 흙막이 가시설 벽체 조성시 주로 적용되는 공법은 주열식 현장타설 콘크리트 벽체(C.I.P)인데, 별도의 도면으로 도시하지 않았지만, 이 공법은 천공 후 철근이나 H형강 등의 보강재를 넣은 후 콘크리트를 채워 넣은 콘크리트 말뚝을 연속적으로 시공하여 주열식 흙막이 벽체를 형성하는 공법이다.In urban areas and soft strata conditions, the method mainly applied when constructing a temporary earth retaining wall with a relatively deep underground excavation depth is the column-type cast-in-place concrete wall (C.I.P.). Although not shown in a separate drawing, this method uses rebar or H-beam steel after drilling. This is a method of forming a column-type earth retaining wall by continuously constructing concrete piles filled with concrete after adding reinforcing materials such as reinforcing materials.

이러한 주열식 현장타설 흙막이벽체(C.I.P) 조성공법은 가설 흙막이 벽체로서 도심지의 협소한 지역 및 연약지반 조건에 주로 적용되나, 지하층 굴착시 현장타설 콘크리트 흙막이벽체(C.I.P)만으로 배면지반으로부터 유입되는 지하수에 대한 차수효과를 100% 기대할 수 없기 때문에 가설 흙막이벽체 배면에 별도의 차수그라우팅을 해야 하며, 차수그라우팅의 품질에 문제가 발생될 경우에는 지하층 굴착 중 흙막이 벽체 배면지반의 침하 및 공동 발생 등이 흙막이 가시설 붕괴의 주요 원인이 될 수 있다.This cast-in-place concrete retaining wall (C.I.P.) construction method is a temporary retaining wall and is mainly applied to narrow areas and soft ground conditions in urban areas. However, when excavating underground floors, only the cast-in-place concrete retaining wall (C.I.P.) is used to prevent groundwater flowing in from the back ground. Because a 100% water blocking effect cannot be expected, separate water blocking grouting must be done on the back of the temporary retaining wall. If a problem occurs with the quality of the retaining wall, the settlement and cavities in the ground behind the retaining wall during underground layer excavation may cause damage to the temporary retaining wall. This can be a major cause of collapse.

한편, 대한민국 공개특허공보 제10-2017-0059298호의 스크래치 구조물을 이용한 CIP공법의 차수벽 제작방법에서는 CIP공법에서 별도의 차수그라우팅 없이 차수성을 확보하는 방법을 제시하였지만 작업공정이 복잡하고, 시공 중 품질관리에 대한 어려움이 단점으로 나타나고 있다.Meanwhile, the method of manufacturing a water barrier using the CIP method using a scratch structure in Korean Patent Publication No. 10-2017-0059298 suggests a method of securing water barrier without separate water barrier grouting in the CIP method, but the work process is complicated and the quality is poor during construction. Difficulty in management appears to be a disadvantage.

특히 종래 기술에 따른 CIP공법에서는 사질토층(모래층)으로 구성된 동해안 지역이나 연약지반(점토층)으로 구성된 서해안과 같은 지층조건의 시공 대상 지반에 대한 공학적 토질특성을 고려하지 않은 상태에서 지반에 대한 천공을 실시하게 되므로 지반 천공 중 천공 홀 내부로 지하수의 유입 및 콘크리트 타설 후 케이싱 인발과정에서 공벽 붕괴가 유발될 수 있으며, 더 나아가 흙막이 벽체의 시공 후에도 흙막이 벽체사이로 유입되는 누수로 인하여 배면지반에 침하가 발생됨으로 인하여 흙막이 가시설의 붕괴와 같은 대형 사고로 이어질 수 있다는 문제점이 있다.In particular, in the CIP method according to the prior art, drilling into the ground is performed without considering the engineering soil characteristics of the ground under construction, such as the east coast area composed of sandy soil layer (sand layer) or the west coast composed of soft ground (clay layer). As this is done, the inflow of groundwater into the hole during ground drilling and the collapse of the hollow wall during the casing pulling process after concrete pouring may occur. Furthermore, even after the construction of the retaining wall, settlement may occur in the rear ground due to water leakage flowing between the retaining walls. There is a problem that this may lead to a major accident such as the collapse of temporary earth retaining facilities.

대한민국 공개특허공보 제10-2017-0059298호Republic of Korea Patent Publication No. 10-2017-0059298

따라서 본 발명은 상술한 문제점을 해결하기 위한 안출된 것으로, 토압에 대응하여 충분한 강도를 확보하면서도 높은 차수 효과를 가질 수 있으며, 공벽 붕괴 및 흙막이 가시설 배면지반의 침하를 방지할 수 있는 개량된 주열식 현장타설 콘크리트(C.I.P) 흙막이벽체의 시공방법을 제공하는 것이 목적이다.Therefore, the present invention was devised to solve the above-mentioned problems, and is an improved column type that can have a high order effect while securing sufficient strength in response to earth pressure, and can prevent the collapse of the hollow wall and the settlement of the ground behind the temporary earth retaining facility. The purpose is to provide a construction method for cast-in-place concrete (C.I.P.) retaining walls.

상술한 문제점을 해결하기 위한 수단으로서 본 발명의 차수 강화 및 지반침하 방지기능이 향상된 CIP 흙막이벽체의 시공방법(이하 "본 발명의 시공방법"이라 칭함)은, a) 흙막이 대상 지반의 지중에 원지반 토사와 고화제를 교반 및 혼합시켜 복수의 주열식강화벽체를 시공하는 단계; b) 상기 주열식강화벽체가 형성된 영역을 따라 일정 간격으로 천공홀을 형성하고, 선택된 천공홀에 철근망 또는 H빔을 포함하는 보강재를 삽입하는 단계; 및 c) 상기 보강재가 삽입된 천공홀에 콘크리트를 타설 및 양생한 후, 상기 주열식강화벽체가 시공된 지반 상에 지지벽체를 시공하는 단계;를 포함하는 것이 특징이다.As a means to solve the above-mentioned problems, the construction method of the CIP earth retaining wall with improved water resistance and ground settlement prevention function of the present invention (hereinafter referred to as the "construction method of the present invention") is: a) the original ground in the ground of the earth retaining target; Constructing a plurality of column-type reinforced walls by stirring and mixing soil and solidifying agent; b) forming drilling holes at regular intervals along the area where the column-type reinforced wall is formed, and inserting reinforcing materials including reinforcing bar nets or H-beams into the selected drilling holes; and c) pouring and curing concrete into the drilled hole into which the reinforcing material is inserted, and then constructing a support wall on the ground on which the column-type reinforced wall was constructed.

하나의 예로써, 상기 b)단계 내지 c)단계는, 상기 주열식강화벽체가 형성된 지반을 따라 상호 일정한 이격을 갖도록 복수의 제 1천공홀을 형성하는 단계; 상기 제 1천공홀에 철근망 또는 H빔을 포함하는 보강재를 삽입하는 단계; 상기 보강재가 삽입된 제 1천공홀에 콘크리트를 타설, 양생하여 제 1지지벽체를 시공하는 단계; 인접하는 양 제 1지지벽체 사이에서 배면 토압이 작용하는 방향으로부터 상기 제 1지지벽체가 시공되는 열보다 상대적으로 먼 거리에 위치하면서 주면이 양 제 1지지벽체의 주면과 접하도록 복수의 제 2천공홀을 형성하는 단계; 및 상기 제 2천공홀에 콘크리트를 타설, 양생하여 상기 제 1지지벽체와 이어지는 제 2지지벽체를 시공하는 단계;를 포함하는 것이 특징이다.As an example, steps b) to c) include forming a plurality of first drilling holes at a constant distance from each other along the ground on which the column-type reinforced wall is formed; Inserting a reinforcing material including a reinforcing bar network or an H beam into the first drilling hole; Constructing a first support wall by pouring and curing concrete into the first perforated hole into which the reinforcement material is inserted; A plurality of second perforations are located at a relatively greater distance from the direction in which the back earth pressure acts between the two adjacent first supporting walls than the row in which the first supporting walls are constructed, and the main surfaces are in contact with the main surfaces of both first supporting walls. forming a hole; and pouring and curing concrete into the second perforation hole to construct a second support wall connected to the first support wall.

하나의 예로써, 인접하는 양 제 2지지벽체 간의 이격된 공간에 차수그라우팅을 시공하는 단계;를 더 포함하는 것이 특징이다.As an example, it is characterized by further including the step of constructing water blocking grouting in the spaced apart space between the two adjacent second support walls.

하나의 예로써, a) 단계에서, 상기 주열식강화벽체는 상호 중첩 시공되는 것이 특징이다.As an example, in step a), the column-type reinforced walls are characterized in that they are constructed overlapping each other.

이와 같이 본 발명의 시공방법에 의하면, 고강도 심층혼합처리공법(High strength D.C.M ; H.D.C.M) 등을 통해 흙막이 벽체가 시공될 대상 지반을 선행적으로 보강한 후, 해당 지반에 구조체로서 기능을 하는 지지벽체를 후시공하게 됨으로써, 토압에 대응하여 충분한 강도를 확보하면서도 높은 차수 효과를 가질 수 있게 되며, 특히 흙막이 벽체 형성을 위한 천공 과정에서 발생할 수 있는 공벽 붕괴 및 배면지반의 침하를 방지할 수 있는 이점이 있다.According to the construction method of the present invention, the ground on which the retaining wall is to be constructed is reinforced in advance through a high-strength deep mixing method (High strength D.C.M.; H.D.C.M.), and then a supporting wall functions as a structure in the ground. By post-construction, it is possible to secure sufficient strength in response to earth pressure and have a high order effect. In particular, there is an advantage in preventing the collapse of the hollow wall and subsidence of the underlying ground that may occur during the drilling process to form an earth retaining wall. there is.

또한 연약지반 상에서 흙막이 벽체를 시공함에 있어 요구되는 케이싱 관입 공정이 불필요하므로 시공 시간은 물론 시공 비용이 절감되어 시공성이 우수할 뿐 아니라 경제성이 향상되는 이점이 있다. In addition, since the casing penetration process required when constructing an earth retaining wall on soft ground is unnecessary, not only the construction time but also the construction cost is reduced, which not only improves constructability but also improves economic efficiency.

도 1은 본 발명의 시공방법을 나타내는 블록도이다.
도 2는 본 발명의 시공방법에 의해 구축되는 흙막이 벽체의 기본 예를 나타내는 평면도.
도 3은 본 발명의 다른 실시 예에 따라 시공되는 안정성이 보강된 흙막이 벽체를 나타내는 평면도.
도 4a는 일반적인 주열식 흙막이 벽체의 차수그라우팅 시공 포인트를 나타내는 평면도.
도 4b는 본 발명의 다른 실시 예에 따라 시공되는 흙막이 벽체의 차수그라우팅 시공 포인트를 나타내는 평면도.
1 is a block diagram showing the construction method of the present invention.
Figure 2 is a plan view showing a basic example of an earth retaining wall constructed by the construction method of the present invention.
Figure 3 is a plan view showing an earth retaining wall with reinforced stability constructed according to another embodiment of the present invention.
Figure 4a is a plan view showing the waterline grouting construction points of a typical main heat retaining wall.
Figure 4b is a plan view showing water grouting construction points of an earth retaining wall constructed according to another embodiment of the present invention.

본 발명을 설명함에 있어서, 본 명세서 및 청구범위에 사용된 용어나 단어는 발명자가 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합되는 의미와 개념으로 해석되어야만 한다.In describing the present invention, the terms and words used in the specification and claims are based on the principle that the inventor can appropriately define the concept of the term in order to explain the invention in the best way. It must be interpreted with meaning and concepts consistent with the technical ideas of.

이하에서는 도면을 참조하여 본 발명의 바람직한 실시 예를 설명한다.Hereinafter, preferred embodiments of the present invention will be described with reference to the drawings.

도 1 및 도 2를 참조하면, 본 발명의 시공방법은 같이 흙막이 대상 지반의 지중에 원지반 토사와 고화제를 교반 및 혼합시켜 복수의 주열식강화벽체(10)를 시공하는 단계(S100)와, 상기 주열식강화벽체(10)가 형성된 영역을 따라 일정 간격으로 천공홀을 형성하고, 선택된 천공홀에 철근망 또는 H빔을 포함하는 보강재(200)를 삽입하는 단계(S200) 및 상기 보강재(200)가 삽입된 천공홀에 콘크리트를 타설 및 양생한 후, 상기 주열식강화벽체(10)의 시공으로 강화된 지반 상에 복수의 지지벽체(20)를 시공하는 단계(S300)를 포함한다.Referring to Figures 1 and 2, the construction method of the present invention includes the step (S100) of constructing a plurality of heat-type reinforced walls (10) by stirring and mixing the original soil and solidifying agent in the ground of the ground to be retained. Forming drilling holes at regular intervals along the area where the column-type reinforced wall 10 is formed, inserting reinforcing material 200 including a reinforcing bar network or H beam into the selected drilling hole (S200), and the reinforcing material 200 ) includes the step (S300) of pouring and curing concrete into the inserted drill hole and then constructing a plurality of support walls 20 on the ground strengthened by the construction of the main heat-reinforced wall 10.

상기 S100단계는 흙막이 벽체를 시공하기에 앞서 선행적으로 시공 대상 지반을 고화 및 개량시켜 보강하는 공정이다.The S100 step is a process of solidifying and improving the ground for construction prior to constructing the retaining wall and reinforcing it.

본 단계(S100)는 고강도 심층혼합처리공법(High strength D.C.M ; H.D.C.M)을 이용하여 지반 영역을 고화 및 개량할 수 있다.In this step (S100), the ground area can be solidified and improved using the high strength deep mixing treatment method (High strength D.C.M. (H.D.C.M)).

일 예로 본 단계(S100)는 도면에 도시된 바 없으나 지반영역으로 오거장치를 관입하여 천공벽을 형성하는 단계와, 상기 오거장치를 이용하여 천공벽이 형성된 지중으로 고화제를 공급하는 단계와, 상기 오거장치를 이용하여 원지반 토사와 고화제를 교반 및 혼합하고 천공벽을 다지는 단계 및 상기 오거장치를 상기 지반영역으로부터 인발시켜 분리하는 단계를 포함하여 구성될 수 있다.As an example, this step (S100), which is not shown in the drawing, includes forming a perforated wall by penetrating an auger device into the ground area, and supplying a solidifying agent to the ground where the perforated wall is formed using the auger device, It may be configured to include the steps of stirring and mixing the original ground soil and solidifying agent using the auger device and compacting the perforation wall, and the step of pulling out and separating the auger device from the ground area.

본 단계(S100)는 상술한 세부 과정을 반복하여 흙막이 대상 지반을 주열식으로 연속 시공함으로써 복수의 주열식강화벽체(10)를 형성하게 된다.In this step (S100), a plurality of column-type reinforced walls 10 are formed by repeating the above-described detailed process and continuously constructing the earth retaining ground in a column type.

이때 연속 시공되는 상기 주열식강화벽체(10)는 상호 중첩 시공되게 하여 흙막이 벽체가 시공될 지반 상에서 보강 구간의 단절이 발생되지 않게 함이 바람직하다.At this time, it is preferable that the column-type reinforced walls 10, which are continuously constructed, are constructed overlapping each other to prevent disconnection of the reinforcement section on the ground where the retaining wall is to be constructed.

이에 따라 더욱 효과적인 차수 성능을 가질 수 있게 하며, 후공정의 지지벽체(20)를 시공하는 과정에서 공벽 붕괴 및 천공홀 내부로 지하수 유입에 따른 배면지반의 침하 등을 방지할 수 있게 된다.Accordingly, it is possible to have more effective water blocking performance, and during the construction of the support wall 20 in the post-process, it is possible to prevent collapse of the hollow wall and subsidence of the back ground due to groundwater inflow into the drilling hole.

그리고 상기 고화제는 지반에 대한 오염을 최소화할 수 있도록 친환경 고화제를 사용하는 것이 바람직하다.Additionally, it is desirable to use an eco-friendly solidifying agent to minimize contamination to the ground.

상기 오거장치는 고강도 흙막이 연속벽체 또는 심층혼합처리공법을 위한 천공 장치로 연약지반에 관입되는 과정에서 토사가 분산 및 교란되는 것을 제어함으로써 슬라임 배출을 억제시킬 수 있으며, 일 장치를 통해 고화제를 분사한 후 고화제와 토사 간의 기계적 교반을 수행하도록 구성될 수 있다.The auger device is a drilling device for a high-strength earth retaining continuous wall or a deep mixing treatment method. It can suppress slime discharge by controlling the dispersion and disturbance of soil in the process of penetrating into soft ground, and sprays a solidifying agent through one device. After this, it can be configured to perform mechanical stirring between the solidifying agent and the soil.

여기서 상기 오거장치는 원지반의 토질과 작업 환경 등을 고려하여 공지의 다양한 장치들 중 적합한 하나를 선택하여 사용할 수 있는 바, 이에 대한 구체적인 설명은 생략한다.Here, the auger device can be used by selecting an appropriate one among various known devices in consideration of the soil quality of the original ground and the working environment, etc., and a detailed description thereof will be omitted.

한편 상기 S200단계는 상기 주열식강화벽체(10)가 형성된 영역을 따라 일정 간격으로 천공홀을 형성하고, 선택된 천공홀에 철근망 또는 H빔을 포함하는 보강재(200)를 삽입하는 과정이다.Meanwhile, step S200 is a process of forming drilling holes at regular intervals along the area where the column-type reinforced wall 10 is formed, and inserting reinforcing material 200 including a reinforcing bar network or H beam into the selected drilling hole.

상기 S200단계에서는 상기 오거장치의 관입을 가이드하여 천공홀의 연직도를 확보할 수 있도록 사전에 안내벽 시설을 설치할 수 있다.In step S200, a guide wall facility can be installed in advance to guide the penetration of the auger device and secure the verticality of the drilling hole.

안내벽 시설이 시공에 적용될 경우, 상기 안내벽 시설의 안치 및 설치를 위한 지반의 줄파기와, 안내벽 시설의 측면부 지반의 되메움 및 다짐과 같은 추가적인 과정이 더 포함될 수 있다.When a guide wall facility is applied to construction, additional processes such as line digging of the ground for placement and installation of the guide wall facility, and backfilling and compaction of the ground on the side of the guide wall facility may be further included.

상기 S300단계는 상기 S200단계에 의해 형성되는 천공홀에 콘크리트를 타설 후, 양생하여 선시공된 주열식강화벽체(10) 영역 내에 흙막이 지지벽체(20)를 시공하는 과정이다.Step S300 is a process of pouring concrete into the hole formed in step S200, curing it, and constructing an earth retaining support wall 20 within the area of the pre-constructed main heat reinforced wall 10.

즉 본 발명의 시공방법은, 고강도 심층혼합처리공법(High strength D.C.M ; H.D.C.M) 등을 통해 흙막이 벽체가 시공될 대상 지반을 선행적으로 보강한 후, 해당 지반에 구조체로서 기능을 하는 지지벽체(20)를 후시공하게 되는 것이다.That is, the construction method of the present invention is to first reinforce the ground on which the retaining wall is to be constructed through a high-strength deep mixing method (High strength D.C.M.; H.D.C.M.), and then build a support wall (20) that functions as a structure in the ground. ) will be installed later.

이처럼 본 발명에서는 주열식강화벽체(10)와 지지벽체(20)가 동일 지반 영역에서 중첩 시공됨으로써, 토압에 대응하여 충분한 강도를 확보하면서도 높은 차수 효과를 가질 수 있게 되며, 특히 지지벽체(20)를 형성하는 과정에서 발생할 수 있는 천공홀 내부로의 지하수 유입, 공벽 붕괴 및 배면지반의 침하 등을 방지할 수 있게 된다.In this way, in the present invention, the column-type reinforced wall 10 and the support wall 20 are constructed overlapping in the same ground area, thereby ensuring sufficient strength in response to earth pressure and having a high order effect. In particular, the support wall 20 It is possible to prevent groundwater inflow into the bore hole, collapse of the cavity wall, and subsidence of the underlying ground that may occur in the process of forming.

뿐만 아니라 연약 지반 상에서 흙막이 벽체의 시공 시 요구되는 케이싱 관입 공정이 불필요하므로 시공 시간은 물론 시공 비용을 절감할 수 있게 된다.In addition, since the casing penetration process required when constructing an earth retaining wall on soft ground is unnecessary, not only construction time but also construction cost can be reduced.

한편 본 발명의 일 실시 예에서는 도 3에 도시된 바와 같이 상기 주열식강화벽체(10)가 형성된 지반 상에서 상기 지지벽체(20)가 상호 이격을 형성하면서 2열 배치되는 구조를 가질 수 있다.Meanwhile, in one embodiment of the present invention, as shown in FIG. 3, the support walls 20 may be arranged in two rows while being spaced apart from each other on the ground on which the column-type reinforced wall 10 is formed.

구체적으로 본 실시 예에 따른 상기 S200단계 내지 S300단계는, 상기 주열식강화벽체(10)가 형성된 지반을 따라 상호 일정한 이격을 갖도록 복수의 제 1천공홀을 형성하는 단계와, 상기 제 1천공홀에 철근망 또는 H빔을 포함하는 보강재(200)를 삽입하는 단계 및 상기 보강재(200)가 삽입된 제 1천공홀에 콘크리트를 타설 후, 양생하여 제 1지지벽체(21)를 시공하는 단계를 포함할 수 있다.Specifically, steps S200 to S300 according to the present embodiment include forming a plurality of first drilling holes so as to have a certain distance from each other along the ground on which the column-type reinforced wall 10 is formed, and the first drilling holes The steps of inserting reinforcing material 200 including a reinforcing bar network or H beam into the concrete, pouring concrete into the first drill hole into which the reinforcing material 200 is inserted, curing it, and constructing the first support wall 21. It can be included.

그리고 인접하는 양 제 1지지벽체(21) 사이에서 배면 토압이 작용하는 방향으로부터 상기 제 1지지벽체(21)가 시공되는 열보다 상대적으로 먼 거리에 위치하면서 주면이 양 제 1지지벽체(21)의 주면과 접하도록 복수의 제 2천공홀을 형성하는 단계 및 상기 제 2천공홀에 콘크리트를 타설 후, 양생하여 상기 제 1지지벽체(21)와 이어지는 제 2지지벽체(22)를 시공하는 단계를 포함할 수 있다.And, between the two adjacent first support walls 21, the first support walls 21 are located at a relatively greater distance from the direction in which the back earth pressure acts than the row in which the first support walls 21 are constructed, and have both main surfaces. Forming a plurality of second perforated holes to be in contact with the main surface of and pouring concrete into the second perforation holes, curing it, and constructing the second supporting wall (22) connected to the first supporting wall (21). may include.

이때 도 3에 따르면 상기 제 2지지벽체(22)는 보강재(200)가 배재된 상태의 무근 벽체로 도시되어 있으나, 본 발명이 이에 한정되는 것은 아니며 제 1지지벽체(21)와 마찬가지로 제 2천공홀에 철근망 또는 H빔을 포함하는 보강재(200)를 삽입하는 단계를 더 포함할 수 있다.At this time, according to FIG. 3, the second support wall 22 is shown as a bare wall with the reinforcement material 200 excluded, but the present invention is not limited to this and, like the first support wall 21, the second support wall 22 has a second perforation. The step of inserting a reinforcing material 200 including a rebar network or an H beam into the hole may be further included.

즉 본 실시 예에서는 주열식강화벽체(10)가 형성된 지반 상에서 토압을 직접적으로 받게 되는 전방에 일정 간격을 따라 복수의 제 1지지벽체(21)를 상호 이격 배치하고, 그 후방으로 상기 제 1지지벽체(21)의 사이마다 제 2지지벽체(22)의 주면이 접하도록 지지벽체를 시공하게 되는 것이다.That is, in this embodiment, a plurality of first support walls 21 are arranged to be spaced apart from each other at a certain interval in front of the ground where the column-type reinforced wall 10 is formed, and where earth pressure is directly applied, and the first support walls 21 are placed behind them. A support wall is constructed between the walls 21 so that the main surface of the second support wall 22 is in contact with them.

일반적으로 천공홀을 형성하기 위한 오거장치는 전단에 과도한 하중이 부여되므로 지지벽체(20)의 시공을 위해 천공홀을 형성하는 과정에서 오거장치의 관입 수직도를 보정하면서 작업을 실시한다. In general, since the auger device for forming the drilling hole imposes an excessive load on the shear, the work is performed while correcting the penetration verticality of the auger device in the process of forming the drilling hole for the construction of the support wall 20.

그러나 이러한 보정 작업은 관입 초기에 효과적으로 유효할 뿐 오거장치가 지중의 하부로 내려갈수록 오차가 발생하기 때문에 오거장치의 관입 수직도가 점차 틀어져 연속 시공되는 천공홀 간 경계면에 이격이 발생하게 된다. 이는 지지벽체(20)의 일렬 시공시 지지벽체(20) 간 틈새를 형성하여 지반굴착 중 지하수의 유입 포인트로서 작용할 수 있게 된다.However, this correction work is only effective at the beginning of penetration, and errors occur as the auger device goes lower into the ground, so the penetration verticality of the auger device gradually becomes distorted, causing separation at the interface between continuously constructed drilling holes. This forms a gap between the supporting walls 20 during construction of the supporting walls 20 in a row, allowing it to function as an inflow point of groundwater during ground excavation.

이에 본 실시 예에서는 복수의 제 1지지벽체(21)를 선 시공한 후, 제 1지지벽체(21)의 후단에서 제 1지지벽체(21) 간 사이마다 제 2지지벽체(22)를 시공하게 되는 바, 선시공된 제 1지지벽체(21) 간에 형성된 이격 공간으로 오거장치의 관입이 가이드될 뿐 아니라 제 2천공홀이 형성되는 과정에서 오거장치는 양 제 1지지벽체(21)의 주면에 지지된 상태를 유지한체 천공이 실시될 수 있다.Accordingly, in this embodiment, after constructing a plurality of first support walls 21, a second support wall 22 is constructed between the first support walls 21 at the rear end of the first support wall 21. As such, not only is the penetration of the auger device guided into the separation space formed between the pre-constructed first support walls (21), but also the auger device is supported on the main surfaces of both first support walls (21) during the process of forming the second drilling hole. Drilling can be performed as long as the condition is maintained.

따라서 선시공된 제 1지지벽체(21)와 신규로 형성되는 제 2천공홀 간에 균일한 경계면이 형성되게 하여, 결과적으로 제 2천공홀에 콘크리트의 타설 및 양생으로 시공되는 제 2지지벽체(22)와의 틈새 발생을 방지할 수 있게 되는 것이다.Therefore, a uniform boundary surface is formed between the pre-constructed first support wall 21 and the newly formed second perforation hole, resulting in the second support wall 22 being constructed by pouring and curing concrete in the second perforation hole. It is possible to prevent the occurrence of a gap with the.

뿐만 아니라, 구조적으로 제 1지지벽체(21)는 흙막이 벽체의 구조체로서 토압의 작용 시 토압을 인접한 제 2지지벽체(22)로 전달하여 효과적으로 배면 토압에 저항할 수 있게 되며, 제 1지지벽체(21) 간 사이에서 확보되는 공간부에는 제 2지지벽체(22)가 접하도록 배치됨으로써, 배면토압 작용 시 제 1지지벽체(21)에 누름 효과가 작용하여 벽체 간 구속력과 차수 성능을 더욱 강화하는 효과를 제공할 수 있다.In addition, structurally, the first support wall 21 is a structure of an earth retaining wall, and when earth pressure is applied, the earth pressure is transmitted to the adjacent second support wall 22, so that it can effectively resist the back earth pressure, and the first support wall ( 21) The second supporting wall 22 is placed in contact with the space secured between the walls, so that when the back earth pressure is applied, a pressing effect is applied to the first supporting wall 21, further strengthening the binding force and water blocking performance between the walls. It can provide an effect.

그리고 본 실시 예에서는 도 4b에 도시된 바와 같이 인접하는 양 제 2지지벽체(22) 간의 이격된 공간에 차수그라우팅(30)을 시공하는 단계를 더 포함할 수 있다.And, in this embodiment, as shown in FIG. 4B, the step of constructing water blocking grouting 30 in the spaced apart space between the two adjacent second support walls 22 may be further included.

흙막이 벽체를 시공함에 있어 상대적으로 취약할 수 있는 벽체 간 경계부위에는 지하수의 유입을 방지하여 수밀성을 확보하기 위한 목적으로 차수그라우팅(30)을 실시하게 된다.When constructing an earth retaining wall, water-blocking grouting (30) is performed on the boundary between walls, which may be relatively vulnerable, for the purpose of preventing the inflow of groundwater and securing watertightness.

일반적으로 도 4a에서와 같이 지지벽체(20)를 일렬 시공할 경우, 각각의 지지벽체(20) 간 경계부위마다 그라우팅 시공을 해야한다.In general, when the support walls 20 are constructed in a row as shown in Figure 4a, grouting must be done at each boundary between each support wall 20.

이에 반하여 본 실시 예에 따른 시공방법에 의하면, 도 4b에 도시된 바와 같이 양 제 2지지벽체(22) 간의 이격된 공간에 1개소의 차수그라우팅(30) 시공만으로 두 벽체 간의 경계부위 모두를 커버할 수 있게 된다.On the other hand, according to the construction method according to this embodiment, as shown in FIG. 4b, the entire boundary area between the two walls is covered by only constructing one spot of water grouting 30 in the space spaced apart between the two second support walls 22. You can do it.

따라서 지하수 유입 포인트가 최소화될 뿐 아니라, 벽체의 일렬 배치 구조와 대비하여 상대적으로 차수그라우팅(30)의 시공 개소가 줄어들기 때문에 차수그라우팅(30)에 소요되는 시공 시간은 물론 시공 비용을 모두 절감할 수 있는 효과가 있다.Therefore, not only are the groundwater inflow points minimized, but the construction locations for the water cut grouting (30) are relatively reduced compared to the linear arrangement structure of the wall, so not only the construction time required for water cut grouting (30) but also the construction cost can be reduced. There is a possible effect.

이때 상기 차수그라우팅에 사용되는 차수재의 경우 상술한 바와 같이 충분한 누름 효과를 도모하기 위해서 상기 제 1지지벽체(21) 및 제 2지지벽체(22)의 구축 시 타설되는 콘크리트보다 상대적으로 소프트한 수밀성 재질을 사용하는 것이 바람직하며, 원지반의 공학적 토질특성을 고려하여 무수축 차수 혼화재 등이 첨가될 수도 있음은 당연하다.At this time, in the case of the water barrier material used in the water barrier grouting, in order to achieve a sufficient pressing effect as described above, it is relatively softer and watertight than the concrete poured when constructing the first and second support walls 21 and 22. It is desirable to use the material, and it is natural that non-shrinkage order admixtures, etc. may be added considering the engineering soil characteristics of the original ground.

이상에서 본 발명의 바람직한 실시예에 대하여 상세하게 설명하였지만 본 발명의 권리범위는 이에 한정되는 것은 아니고 다음의 청구범위에서 정의하고 있는 본 발명의 기본 개념을 이용한 당업자의 여러 변형 및 개량 형태 또한 본 발명의 권리범위에 속하는 것이다.Although the preferred embodiments of the present invention have been described in detail above, the scope of the present invention is not limited thereto, and various modifications and improvements made by those skilled in the art using the basic concept of the present invention defined in the following claims are also possible. falls within the scope of rights.

10 : 주열식강화벽체 20 : 지지벽체
21 : 제 1지지벽체 22 : 제 2지지벽체
30 : 차수그라우팅 200 : 보강재
10: Main heat reinforced wall 20: Support wall
21: first support wall 22: second support wall
30: Water grouting 200: Reinforcement material

Claims (4)

흙막이 대상 지반의 지중에 원지반 토사와 고화제를 교반 및 혼합시켜 복수의 주열식강화벽체를 시공하되, 연속된 주열식강화벽체 간이 상호 중첩되게 시공하는 단계(S100);
상기 복수의 주열식강화벽체가 형성된 영역을 따라 상호 일정한 이격을 갖도록 지반에 복수의 제 1천공홀을 형성하는 단계(S200);
상기 제 1천공홀에 철근망 또는 H빔을 포함하는 보강재를 삽입하는 단계(S300);
상기 보강재가 삽입된 제 1천공홀에 콘크리트를 타설 및 양생하여 선시공된 상기 주열식강화벽체 영역 내에서 제 1지지벽체를 나란히 시공하는 단계(S400);
인접하는 양 제 1지지벽체 사이에서 배면 토압이 작용하는 방향으로부터 상기 제 1지지벽체가 시공되는 열보다 상대적으로 먼 거리에 위치하면서 주면이 양 제 1지지벽체의 주면과 접하도록 복수의 제 2천공홀을 형성하는 단계(S500);
상기 제 2천공홀에 콘크리트를 타설 및 양생하여 선시공된 상기 주열식강화벽체 영역 내에서 상기 제 1지지벽체와 이어지는 제 2지지벽체를 시공하는 단계(S600); 및
인접하는 양 제 2지지벽체 간의 이격된 공간에 차수그라우팅을 시공하는 단계(S700);를 포함하되,
상기 S100단계는,
지반영역으로 오거장치를 관입하여 천공벽을 형성하는 단계와, 상기 오거장치를 이용하여 천공벽이 형성된 지중으로 고화제를 공급하는 단계와, 상기 오거장치를 이용하여 원지반 토사와 고화제를 교반 및 혼합하고 천공벽을 다지는 단계 및 상기 오거장치를 상기 지반영역으로부터 인발시켜 분리하는 단계를 반복하여 시공되는 것을 특징으로 하는 차수 강화 및 지반침하 방지기능이 향상된 CIP 흙막이벽체의 시공방법.
A step (S100) of constructing a plurality of column-type reinforced walls by stirring and mixing the original ground soil and solidifying agent in the ground of the target ground for earth retaining, and constructing the continuous column-type reinforced walls so that they overlap each other;
Forming a plurality of first drilling holes in the ground so as to have a certain distance from each other along the area where the plurality of column-type reinforced walls are formed (S200);
Inserting a reinforcing material including a reinforcing bar network or an H beam into the first drilling hole (S300);
Step (S400) of pouring and curing concrete into the first perforated hole where the reinforcing material is inserted and constructing the first support wall side by side within the pre-constructed column-type reinforced wall area;
A plurality of second perforations are located at a relatively greater distance from the direction in which the back earth pressure acts between the two adjacent first supporting walls than the row in which the first supporting walls are constructed, and the main surfaces are in contact with the main surfaces of both first supporting walls. Forming a hole (S500);
A step (S600) of pouring and curing concrete into the second perforation hole to construct a second support wall connected to the first support wall within the pre-constructed main heat reinforced wall area; and
Includes a step (S700) of constructing water blocking grouting in the spaced apart space between the two adjacent second support walls,
In step S100,
A step of penetrating an auger device into the ground area to form a perforated wall, supplying a solidifying agent to the ground where the perforated wall is formed using the auger device, agitating the original ground soil and a solidifying agent using the auger device, and A method of constructing a CIP retaining wall with improved water protection and ground subsidence prevention functions, characterized in that the steps of mixing and consolidating the perforated wall and the step of pulling and separating the auger device from the ground area are repeated.
삭제delete 삭제delete 삭제delete
KR1020220138112A 2022-10-25 2022-10-25 Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function KR102625776B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220138112A KR102625776B1 (en) 2022-10-25 2022-10-25 Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220138112A KR102625776B1 (en) 2022-10-25 2022-10-25 Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function

Publications (1)

Publication Number Publication Date
KR102625776B1 true KR102625776B1 (en) 2024-01-16

Family

ID=89719250

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220138112A KR102625776B1 (en) 2022-10-25 2022-10-25 Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function

Country Status (1)

Country Link
KR (1) KR102625776B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06220841A (en) * 1993-01-28 1994-08-09 Kawasaki Steel Corp Construction method for continuous underground wall using steel pipe pile
JP2001303553A (en) * 2000-04-24 2001-10-31 Shimizu Corp Underground continuous wall and its construction method
KR20110043017A (en) * 2009-10-20 2011-04-27 이복우 The earth retaining wall and waterproof construction technique for which cast in place concrete pile and grouting column was used
KR20170059298A (en) 2015-11-20 2017-05-30 김종성 Method for constructing breast wall of cip technical by using scratch structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06220841A (en) * 1993-01-28 1994-08-09 Kawasaki Steel Corp Construction method for continuous underground wall using steel pipe pile
JP2001303553A (en) * 2000-04-24 2001-10-31 Shimizu Corp Underground continuous wall and its construction method
KR20110043017A (en) * 2009-10-20 2011-04-27 이복우 The earth retaining wall and waterproof construction technique for which cast in place concrete pile and grouting column was used
KR20170059298A (en) 2015-11-20 2017-05-30 김종성 Method for constructing breast wall of cip technical by using scratch structure

Similar Documents

Publication Publication Date Title
KR100927186B1 (en) Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
KR20100068597A (en) A shoring method using arch plate pile and h-pile
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR20100065521A (en) A shoring method using arch plate pile and h-pile
KR20020046904A (en) A method of construction for the breast wall
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
KR102625776B1 (en) Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function
KR200362565Y1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JP4485006B2 (en) Construction method for underground structures
US20220356663A1 (en) Load Transfer System
KR102299540B1 (en) Construction method of cross-sectional expansion type columnar barrier wall
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR100476839B1 (en) Construction method for installing concrete underground structures
CN111042144B (en) Excavation method for foundation pit of underground beam under condition of continuous flow of riverway in cold region
KR100477357B1 (en) Construction method for retaining of earth
JP3760343B2 (en) Drilling bottom stabilization method and construction method of underground building
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
KR100654973B1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
KR100401330B1 (en) A method of construction for earth-protection walls of building
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
JP4612356B2 (en) How to create a slope
KR100429283B1 (en) Construction Method using Precast Concrete for Diaphragm Wall
JP2005146756A (en) Earth retaining impervious wall construction method and earth retaining impervious wall formed by it

Legal Events

Date Code Title Description
AMND Amendment
X091 Application refused [patent]
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant