KR100432782B1 - Supporting structure for tunnel and underground tunnel construction method using the same - Google Patents

Supporting structure for tunnel and underground tunnel construction method using the same Download PDF

Info

Publication number
KR100432782B1
KR100432782B1 KR10-2002-0013228A KR20020013228A KR100432782B1 KR 100432782 B1 KR100432782 B1 KR 100432782B1 KR 20020013228 A KR20020013228 A KR 20020013228A KR 100432782 B1 KR100432782 B1 KR 100432782B1
Authority
KR
South Korea
Prior art keywords
tunnel
steel
concrete
protective film
excavation
Prior art date
Application number
KR10-2002-0013228A
Other languages
Korean (ko)
Other versions
KR20030073590A (en
Inventor
신박문
Original Assignee
세역산업 주식회사
세역종합건설(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 세역산업 주식회사, 세역종합건설(주) filed Critical 세역산업 주식회사
Priority to KR10-2002-0013228A priority Critical patent/KR100432782B1/en
Publication of KR20030073590A publication Critical patent/KR20030073590A/en
Application granted granted Critical
Publication of KR100432782B1 publication Critical patent/KR100432782B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

본 발명은 메서 실드(Messer Shield) 공법에 의한 굴착시 필수적으로 설치되는 강구조물을 구조적으로 보강하여 안정시키고, 이 강구조물을 라이닝콘크리트 타설과 함께 영구 구조물화시키는 터널 시공방법을 개시한다.The present invention discloses a tunnel construction method for structurally reinforcing and stabilizing steel structures that are essentially installed during excavation by the Messer Shield method, and permanently constructing the steel structures together with lining concrete placing.

본 발명은 터널 단면형상에 따라 굴착된 토사부와 인접하여서 일정간격으로 조립·설치되며, 그 외표면이 유리섬유가 혼입된 에폭시수지로 도막(11)이 형성되어 있는 강재지보(10)와; 상기 강재지보(10)들의 간격사이에 콘크리트를 타설하여 형성한 라이닝 구조물(20)과; 상기 라이닝 구조물(20)의 이면에 주입한 그라우트 (30)와; 상기 라이닝 구조물(20)의 표면에 시트를 이용해 형성한 방수면(40)과; 상기 방수면(40)위에 와이어메쉬를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 형성한 보호막(50)과; 상기 보호막(50)의 외면을 마감하기 위해 부착한 마감면 (60);으로 구성된 것을 특징으로 하는 터널용 지지 구조물 및 그것의 시공방법을 제공한다. 본 발명에 의하면 강재지보의 영구화라는 간단하면서도 효율적인 방법을 통해 공사기간 단축, 공사비용 절감 및 고품질의 터널 구조물을 제공할 수 있는 효과가 있다.The present invention is assembled and installed at a predetermined interval adjacent to the excavated soil portion in accordance with the tunnel cross-sectional shape, the steel support 10, the outer surface of which is formed of a coating film 11 of epoxy resin in which glass fibers are mixed; A lining structure 20 formed by pouring concrete between the gaps of the steel supports 10; Grout 30 injected into the rear surface of the lining structure 20; A waterproof surface 40 formed on the surface of the lining structure 20 using a sheet; A protective film 50 formed by installing a wire mesh on the waterproof surface 40 and casting shotcrete or lightweight concrete; Provides a tunnel support structure and its construction method, characterized in that consisting of; finish surface 60 attached to close the outer surface of the protective film 50. According to the present invention it is possible to reduce the construction period, reduce the construction cost and provide a high-quality tunnel structure through a simple but efficient method of permanentizing the steel support.

Description

터널용 지지 구조물 및 지하터널 시공방법{Supporting structure for tunnel and underground tunnel construction method using the same}Supporting structure for tunnel and underground tunnel construction method using the same}

본 발명은 메서 실드(Messer Shield) 공법을 통해 막장을 굴착한 후 굴착된 가설터널 내부에 영구 콘크리트 구조물을 구축하여 터널 내부의 토압을 지지하는 지하터널 구축 공법에 관한 것으로, 특히 메서 실드 공법에 의한 굴착시 필수적으로 설치되는 강구조물을 구조적으로 보강하여 안정시키고, 이 강구조물을 라이닝콘크리트 타설과 함께 영구 구조물화 시키는 방법을 통해 시공성 및 경제성을 대폭 향상시켜 주는 터널용 지지 구조물 및 지하터널 시공방법에 관한 것이다.The present invention relates to an underground tunnel construction method for supporting earth pressure in a tunnel by constructing a permanent concrete structure in an excavated temporary tunnel after digging a membrane through a Messer Shield method, and in particular, by the method of the method. The present invention relates to a tunnel support structure and underground tunnel construction method that significantly improves workability and economic efficiency by structurally reinforcing and stabilizing steel structures essential for excavation, and permanently structuring the steel structures with lining concrete placement. .

메서 실드 공법은 유압추진기를 이용하여 메서 플레이트를 전방으로 전진시킨 후 굴착하면서, 메서 플레이트의 후방쪽으로 토류판을 강재지보 위에 고정시키는 작업을 반복적으로 수행하여 굴진하는 공법으로서, 메서 플레이트라는 복공 철갑내에서 연속적으로 안전하게 터널을 굴착할 수 있는 시공법이다.Messer shield method is a method that advances the mesmer plate forward with a hydraulic propulsion forward and then excavates, and repeatedly excavation by fixing the earth plate on the steel beam to the rear of the mesmer plate. It is a construction method that can continuously excavate tunnels safely.

즉, 메서 실드 공법은 도1의 도시와 같이, 터널 막장을 굴착할 때 계획된 터널형상에 맞춰 조립된 발진기지에 메서 플레이트(1)를 병렬로 배열하고, 유압추진기(2)로 각 메서 플레이트(1)를 1매씩 압입 전진시키면서 막장을 굴착하는 한편, 메서 플레이트(1)의 진행에 따라 굴착부위가 붕괴되지 않도록 그 후방에 일정간격으로 설치한 강재지보(3)와 강재지보(3) 사이에 토류판(4)을 끼워 굴착면을 받쳐가는 작업을 통해 터널을 굴착하는 공법이다.That is, in the method of shielding the method, as shown in Fig. 1, when the tunnel face is excavated, the method plate 1 is arranged in parallel to the oscillation base assembled in accordance with the planned tunnel shape, and the hydraulic plate 2 is used for each method plate 1. ) And excavation of the membrane while pressing forward one by one, and the earth plate between the steel support (3) and the steel support (3) installed at regular intervals in the rear so that the excavation site does not collapse with the progress of the mesa plate (1). It is a method of excavating a tunnel by inserting (4) to support the excavation surface.

이러한 메서 실드 공법은 1981년 우리나라에 도입된 이래, 고속도로 횡단 터널공사·지하철 터널 공사·전력구 공사·통신구 공사 및 각종 암거 공사 등 여러 분야의 다른 작업 조건하에서 적용되어 왔는데, 터널굴착공사를 무소음 무진동으로 시공할 수 있으며, 높은 안전성이 확보되고, 터널 선형에 따라 정확하면서도 신속한 굴진이 가능하며, 굴착면의 침하를 최소로 하고, 터널 굴진에 필요한 장비가 비교적 간단하고 취급이 용이하며, 여타 공법에 비해 경제적인 시공이 가능한 등 그 효과가 매우 좋은 것으로 평가되고 있다.Since the method was introduced to Korea in 1981, it has been applied under different working conditions in various fields, such as highway crossing tunnel construction, subway tunnel construction, power district construction, telecommunication construction, and various culvert constructions. It can be installed without vibration, ensures high safety, enables accurate and rapid drilling according to the tunnel alignment, minimizes the settlement of the excavation surface, relatively simple and easy to handle the equipment required for tunnel drilling, and other construction methods. Compared with the economical construction, the effect is evaluated to be very good.

그러나 종래 광범위한 메서 실드 공법 적용 현장 중, 특히 고속도로 및 철도 횡단 터널, 소형 보차도를 확보하기 위해 시공된 터널은 공사비 및 공사기간에 있어 너무 비경제적이고 비효율적인 문제점이 있었다.However, in the conventional extensive method of shielding method, especially the highway and railway crossing tunnel, the tunnel constructed to secure a small sidewalk has a problem that is too uneconomical and inefficient in the construction cost and construction period.

도2a 및 도2b는 메서 실드 공법을 통해 터널을 굴착한 후, 영구 콘크리트 구조물을 시공하여 완성한 종래의 고속도로 횡단 터널구조물을 나타내고 있다.Figures 2a and 2b shows a conventional highway crossing tunnel structure completed by constructing a permanent concrete structure after excavating the tunnel through the method shield method.

이들 도면을 참조하여 종래 메서 실드 공법을 적용한 터널공사 방법 및 그 문제점을 상세히 설명하면 다음과 같다.With reference to these drawings will be described in detail the tunnel construction method and its problems to which the conventional method shield method is applied as follows.

우선, 종래 메서 실드 공법을 적용한 터널공사 방법을 간략히 설명하면, 도2a의 도시와 같이 메서 플레이트(1)를 막장에 압입 추진하면서 강재지보(3)와 중간 임시지보재(5)를 설치하면서 강재지보(3)와 강재지보(3) 사이에 토류판(4)을 끼워 넣어 굴착면을 보호하는 상태로 굴착한 다음, 도2b의 도시와 같이 강재지보(3)들의 사이에 1차 콘크리트를 타설하여 1차 콘크리트층(6)을 형성하고, 그 1차 콘크리트층(6) 위에 방수면(7)을 형성한 후, 다시 방수면(7) 내측에 철근을 조립하고 2차 콘크리트를 타설하여 2차 철근콘크리트 라이닝(8)을 형성한 후, 중간 임시지보재(5)를 절단·해체하는 방법을 통해 터널 지지용 콘크리트 구조물을 시공하고 있다.First, the tunnel construction method to which the conventional method of the shield method is applied will be briefly described. As shown in FIG. 2A, the steel support 3 and the intermediate temporary support 5 are installed while pressing and pushing the method plate 1 into the membrane. Insert the earth plate (4) between the (3) and the steel support (3) to excavate in a state to protect the excavation surface, and then cast the primary concrete between the steel support (3) as shown in Figure 2b After forming the primary concrete layer (6), forming the waterproof surface (7) on the primary concrete layer (6), and then assembled the reinforcing bar inside the waterproof surface (7) again, the secondary concrete is poured into the secondary rebar After the concrete lining (8) is formed, the tunnel support concrete structure is constructed by cutting and dismantling the intermediate temporary support material (5).

위와 같이 시공되는 구조물에서 강재지보(3)와 중간 임시지보재(5)들로 조립된 강구조물은 굴착시에만 기능하는 것으로, 강구조물과 1차 콘크리트층(6)은 토사측 수분과 상시 접촉하는 관계로 부식이 예상되어 전혀 구조계산에 포함되지 않는 가설 구조물이며, 2차 철근콘크리트 라이닝(8)이 터널의 주요 하중을 받아주는 영구 구조물로서의 역할을 수행한다.In the structure constructed as above, the steel structure assembled with the steel support 3 and the intermediate temporary support 5 functions only at the time of excavation, and the steel structure and the primary concrete layer 6 are always in contact with the soil-side moisture. It is a temporary structure that is not included in the structural calculation at all because corrosion is expected, and the secondary reinforced concrete lining 8 serves as a permanent structure that receives the main load of the tunnel.

따라서 상기와 같은 종래의 터널 공사 방법은, 첫째 2차 철근콘크리트 라이닝(8) 작업을 하면서 1차 굴착시 설치한 강구조물의 사장으로 인해 경제적 손실이 크고, 1차 콘크리트층(6)과 2차 철근콘크리트 라이닝(8)의 이중설치에 따른 관련공사비용 증가 및 공사기간 연장에 따른 비용이 상대적으로 많이 소요되는 문제점이 있었다.Therefore, the conventional tunnel construction method as described above, due to the president of the steel structure installed during the first excavation while working the first secondary reinforced concrete lining (8), the economic loss is large, the primary concrete layer (6) and secondary reinforcing bars There was a problem that the cost of increasing the related construction cost and the extension of the construction period due to the double installation of the concrete lining (8) is relatively high.

둘째, 굴착시 설치된 중간 임시지보재(5)로 인해 터널내 콘크리트 타설 작업시 작업공간에 대한 간섭을 많이 받게 되어 시공기간이 더욱 늘어날 뿐만 아니라, 터널지지용 2차 철근콘크리트 라이닝(8) 타설 후 중간 임시지보재(5)를 절단하여 제거하므로 절단부분의 미관이 불량하며, 근본적으로 강재 절단부의 방수처리가 복잡하고 여의치 않아 누수 문제를 일으키는 문제점이 있었다.Second, due to the intermediate temporary support material (5) installed during the excavation, there is a lot of interference on the work space during the concrete placing work in the tunnel, which increases the construction period, and also after the second reinforced concrete lining (8) for the tunnel Since the temporary support material 5 is cut and removed, the aesthetics of the cut part is poor, and the waterproofing part of the steel cutting part is complicated, and there is a problem causing leakage problems.

셋째, 고속도로·철로 또는 이와 유사한 현장에서의 메서 실드 공법에 의한 터널굴착은 도로면과 굴착터널 상단의 거리(토피)가 일정 두께(약 3m)이상 확보되어야만 시공이 가능한데, 터널굴착용 강구조물과 터널 지지용 2차 철근콘크리트 라이닝(8) 등 대단히 두꺼운 이중 구조물로 설계되어 터널규격에 비해 굴착공이 크기 때문에 적용 가능한 현장이 제한적일 수밖에 없으며, 연접되는 도로와 단차가 형성되어 차량 주행성을 저하시키는 문제점이 있었다.Third, the tunnel excavation by the method of shielding method on the highway, railway or similar site is possible only when the distance (tope) between the road surface and the top of the excavation tunnel is secured over a certain thickness (about 3m). It is designed as a very thick double structure such as a secondary reinforced concrete lining for support (8), and because the excavation hole is larger than the tunnel standard, the applicable site is limited. .

이에 따라, 본 발명은 메서 실드 공법을 통해 굴착된 가설터널 내부에 영구 콘크리트 구조물을 구축하는 터널공사 방법을 개선하여 메서 실드 공법에 의한 터널굴착 방법의 장점을 살리는 한편 상기와 같은 종래 기술이 가지는 제 문제점을 해결하기 위해 안출한 것이다.Accordingly, the present invention improves the tunnel construction method for constructing a permanent concrete structure inside the temporary tunnel excavated through the method of the shield method to take advantage of the tunnel excavation method by the method shield method while having the advantages of the prior art as described above. It was devised to solve the problem.

따라서, 본 발명의 목적은 메서 실드 공법에 의한 굴착시 필수적으로 설치되는 강구조물을 구조적으로 보강하여 안정시키고, 이 강구조물을 라이닝콘크리트 타설시 영구 구조물화 시키는 방법을 통해 콘크리트 타설작업을 대폭 축소시킴으로써 공사비 및 공사기간을 획기적으로 줄일 수 있는 터널용 지지 구조물 및 지하터널 시공방법을 제공하는데 있다.Accordingly, an object of the present invention is to reduce the construction cost and significantly reduce the concrete placing work through the method of structurally reinforcing the steel structure that is essentially installed during the excavation by the method of the method shield method, and to permanently structure the steel structure when laying lining concrete To provide a tunnel support structure and underground tunnel construction method that can significantly reduce the construction period.

본 발명의 다른 목적은 상단의 강재지보를 받치기 위한 중간 임시지보재를 설치하지 않고 터널굴착 작업을 수행토록 함으로써, 철거 흔적이 전혀 남지 않아 마감면의 미관이 유려할 뿐만 아니라, 강재절단부에서 생길 수 있는 누수원인을 근본적으로 제거하여 주기 위한 터널용 지지 구조물 및 지하터널 시공방법을 제공하는데 있다.Another object of the present invention is to perform the tunnel excavation work without installing the intermediate temporary support material for supporting the steel support of the upper end, there is no trace of demolition at all not only beautiful appearance of the finish surface, but also may occur in the steel cutting section It is to provide a tunnel support structure and underground tunnel construction method to fundamentally eliminate the cause of leakage.

본 발명의 또 다른 목적은 터널용지지 구조물에서 요구되는 구조적 강도를 충족시킬 수 있으면서 벽체 두께를 최소화시킴으로써, 도로상면과 굴착 터널 상단과의 두께 확보면에서 유리하여 토피가 얇은 곳도 적용 가능하고 적용범위를 확대시킬 수 있는 한편, 연접되는 도로와 단차없이 동일한 레벨로의 시공이 가능하여 차량 주행성을 높일 수 있는 터널용 지지 구조물 및 지하터널 시공방법을 제공하는데 있다.Another object of the present invention is to minimize the wall thickness while meeting the structural strength required in the support structure for the tunnel, it is advantageous in terms of securing the thickness of the upper surface of the road and the top of the excavation tunnel is applicable to thinner toffee It is possible to expand the scope, and to provide a tunnel support structure and underground tunnel construction method that can be installed at the same level without stepping with a road to be connected, thereby improving vehicle running.

도1은 메서 실드 공법을 이용한 터널굴착 시공도1 is a tunnel excavation construction using the method shield method

도2a는 종래 고속도로를 횡단 터널을 구축하기 위한 터널 굴착 상태 단면도Figure 2a is a cross-sectional view of the tunnel excavation for building a tunnel crossing the conventional highway

도2b는 메서 실드 공법을 통해 터널을 굴착한 후 영구 콘크리트 구조물을 시공하여 완성한 종래의 고속도로 횡단 터널 구조물을 나타낸 단면도Figure 2b is a cross-sectional view showing a conventional highway crossing tunnel structure completed by constructing a permanent concrete structure after excavating the tunnel through the method shield method

도3은 본 발명에서 사용되는 강재지보를 절단하여 나타낸 사시도Figure 3 is a perspective view showing the cut steel beam used in the present invention

도4a 및 도4b는 본 발명에 따라 강재지보와 메서플레이트를 조립하여 설치한 발진기지의 일측면도 및 정면도Figures 4a and 4b is a side view and a front view of the oscillation base installed by assembling the steel beam and the method plate in accordance with the present invention

도5는 본 발명에 따른 터널굴착 시공도5 is a tunnel excavation construction according to the present invention

도6은 본 발명에 따라 라이닝 구조물을 시공한 상태의 단면도Figure 6 is a cross-sectional view of the construction of the lining structure in accordance with the present invention

도7은 본 발명에 따라 라이닝 구조물의 이면에 그라우트를 주입한 상태의 단면도7 is a cross-sectional view of a state in which grout is injected into the rear surface of the lining structure according to the present invention;

도8은 본 발명에 따라 영구 콘크리트 구조물을 시공하여 완성한 터널 구조물을 나타낸 단면도Figure 8 is a cross-sectional view showing a tunnel structure completed by constructing a permanent concrete structure according to the present invention

< 도면의 주요부분에 대한 부호의 설명 ><Description of Symbols for Major Parts of Drawings>

10:강재지보 11:도막 20:라이닝 구조물10: steel sheet 11: coating 20: lining structure

30:그라우트 40:방수면 50:보호막30: grout 40: waterproof surface 50: protective film

51:1차 와이어메쉬 52:1차 경량콘크리트층 53:2차 와이어메쉬51: 1 primary wire mesh 52: 1 primary lightweight concrete layer 53: secondary wire mesh

54:2차 경량콘크리트층 60:마감면 71:메서 플레이트54: Secondary lightweight concrete layer 60: Finishing surface 71: Messager plate

72:유압추진기 73:토류판 74:쐐기목72: hydraulic propeller 73: earth plate 74: wedge wood

상기 목적들을 달성하기 위한 본 발명의 터널용 지지 구조물은, 터널 단면형상에 따라 굴착된 토사부와 인접하여서 일정간격으로 조립·설치되며, 그 외표면이 유리섬유가 혼입된 에폭시수지로 도막(11)이 형성되어 있는 강재지보(10)와; 상기강재지보(10)들의 간격사이에 콘크리트를 타설하여 형성한 라이닝 구조물(20)과; 상기 라이닝 구조물(20)의 이면에 주입한 그라우트(30)와; 상기 라이닝 구조물(20)의 표면에 시트를 이용해 형성한 방수면(40)과; 상기 방수면(40)위에 와이어메쉬를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 형성한 보호막(50)과; 상기 보호막(50)의 외면을 마감하기 위해 부착한 마감면(60);으로 구성된 것을 특징으로 한다.Tunnel support structure of the present invention for achieving the above objects, is assembled and installed at a predetermined interval adjacent to the excavated soil portion in accordance with the tunnel cross-sectional shape, the outer surface is coated with an epoxy resin glass fiber is mixed (11) Steel beams 10 are formed; A lining structure 20 formed by pouring concrete between the intervals of the steel support 10; Grout 30 injected into the rear surface of the lining structure 20; A waterproof surface 40 formed on the surface of the lining structure 20 using a sheet; A protective film 50 formed by installing a wire mesh on the waterproof surface 40 and casting shotcrete or lightweight concrete; Characterized in that consisting of ;; finish surface 60 attached to close the outer surface of the protective film 50.

상기와 같은 특징의 터널용 지지 구조물을 구축하기 위한 본 발명의 지하터널 시공방법은, 굴착시공할 구간의 입구에서 굴착하고자 하는 터널형상에 따라 강재지보(10)를 조립하고 그 강재지보(10) 외주쪽으로 메서 플레이트(71)를 병렬로 배열시켜 발진기지를 구축한 다음, 메서 플레이트 추진·후방 토류판 삽입·막장 굴착·막장막이 설치·강재지보 설치로 이루어진 일련의 작업을 반복적으로 수행하여 터널굴착 공사를 완료한 후, 굴착된 터널 내부의 토압을 지지하기 위한 구조물을 시공하는 지하터널 시공방법에 있어서,Underground tunnel construction method of the present invention for building a support structure for the tunnel as described above, assembling the steel support 10 according to the tunnel shape to be excavated at the entrance of the section to be excavated construction and the steel support 10 After the oscillation base is constructed by arranging the mesmer plates 71 in parallel to the outer circumference, the tunnel excavation work is repeatedly performed by carrying out a series of operations including mesmer plate propulsion, rear earth plate insertion, membrane excavation, membrane curtain installation, and steel beam installation. In the underground tunnel construction method for constructing a structure for supporting the earth pressure in the excavated tunnel after completion,

상기 터널굴착 공사에서 사용되는 강재지보(10)는 부식을 방지하고 강도를 보강하기 위한 도막(11)이 형성된 것을 사용하고, 상기 콘크리트 구조물은 상기 터널굴착 공사를 완료한 이후, 터널굴착 단면을 따라 설치한 상기 강재지보(10)들의 간격사이에 콘크리트를 타설하여 라이닝 구조물(20)을 형성하고, 상기 라이닝 구조물(20)의 이면에 그라우트(30)를 주입한 다음, 상기 라이닝 구조물(20)의 표면에 시트를 이용한 방수면(40)을 형성하고, 상기 방수면(40)위에 와이어메쉬를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 보호막(50)을 형성시킨 후, 보호막(50)의 외면을 면처리하여 마감면(60)을 형성하는 일련의 작업을 통해, 상기 강재지보 (10)를 영구 구조물화하여 시공함을 특징으로 한다.The steel support 10 used in the tunnel excavation construction is used to form a coating film 11 for preventing corrosion and reinforcing strength, the concrete structure after completing the tunnel excavation construction, along the tunnel excavation cross section The lining structure 20 is formed by pouring concrete between the spaces between the installed steel beams 10, injecting the grout 30 into the rear surface of the lining structure 20, and then After forming the waterproof surface 40 using a sheet on the surface, and installing a wire mesh on the waterproof surface 40 and pouring shotcrete or lightweight concrete to form a protective film 50, the outer surface of the protective film 50 Through a series of operations to form a finish surface 60 by processing, the steel support 10 is characterized by the construction of a permanent structure.

위와 같은 특징의 본 발명에 의하면, 터널에서의 2차공종으로 시공되는 구조물을 시공하지 않고 가설터널을 영구 구조물화 시킴으로써, 기존 메서 실드 공법의 터널에서 1차 굴착시 설치한 강재지보의 사장으로 인한 경제적 손실 및 2차적인 구조물의 구축에 따라 공기가 증대되는 문제를 해결하여 공사기간 및 공사비용을 대폭 줄일 수 있게 된다.According to the present invention having the above characteristics, by constructing a temporary tunnel permanently without constructing the structure to be constructed as a secondary construction in the tunnel, due to the boss of the steel support installed during the first excavation in the tunnel of the existing Messier shield method It can solve the problem of increasing air due to economic loss and construction of secondary structure, which can greatly reduce construction period and construction cost.

또한, 터널굴착공사시 중간 임시지보재를 설치하지 않기 때문에 기존의 강재 절단부에서 발생되는 누수원인이 원천적으로 제거되며, 강재지보를 보강하여 구조적인 안정성을 확보하고 라이닝 구조물의 벽체 두께를 강재지보의 두께로 얇게 형성하기 때문에 굴착단면이 작아지게 되어 상대적으로 토피가 낮은 장소에서도 시공이 가능하게 된다.In addition, because the temporary temporary support material is not installed during the tunnel excavation work, the cause of leakage caused by the existing steel cutting part is eliminated at the source, and the structural support is secured by reinforcing the steel support and the wall thickness of the lining structure is the thickness of the steel support. As it is thinly formed, the excavation cross-section becomes small, and construction is possible even in a place where the toffee is relatively low.

이하, 본 발명의 기술구성을 본 발명의 시공예에 따른 첨부도면을 참조하여 보다 상세히 설명한다.Hereinafter, the technical configuration of the present invention will be described in more detail with reference to the accompanying drawings in accordance with the construction example of the present invention.

메서 실드 공법에 의한 터널굴착에 있어서, 시공에 적합한 토질은 점토(粘土)·실트(silt) 또는 사질토(砂質土)등의 토사층 터널굴착에 가장 적합하다.In tunnel excavation by the method of the shield method, the soil suitable for construction is most suitable for the excavation of soil layer tunnels such as clay, silt, and sandy soil.

본 발명의 특징 중 하나가 토피층이 얇은 장소의 터널굴착공법이므로, 우선 굴착노선의 상세한 지질·지하수위 등을 조사하여 지층도를 작성하고 본 성과도를 검사하여 굴착작업에 위험이 있다고 판단되면 별도의 차수공사 및 연약지반 보강공사 등 여러 가지 보조공법을 검토하고 시행해야 한다.Since one of the features of the present invention is a tunnel excavation method in a place where the toffee layer is thin, if it is determined that there is a risk in the excavation work by first preparing a stratum map by examining detailed geological and groundwater levels of the excavation route, and examining the result map, Various subsidiary construction methods such as separate drawing work and soft ground reinforcement work should be reviewed and implemented.

본 발명에서 사용되는 강재지보(10)는 영구 구조물화 되는 것이므로, 기존의 sws400 강재에서 sws490 강재로 재질을 보강하여 설치간격을 최대화 할 수 있도록 하고, 내구성 향상(부식 방지)을 위해 적절한 도막이 장소에서 피복되어 현장으로 반입되어야 하며, 바람직하기로는 도3의 도시와 같이 유리섬유가 혼입된 에폭시수지로 도막(11)이 형성된 것을 들 수 있다.Since the steel support 10 used in the present invention is to be a permanent structure, by reinforcing the material from the existing sws400 steel to sws490 steel to maximize the installation interval, and to improve the durability (corrosion prevention) in a suitable coating film place It should be coated and brought into the field, and preferably, the coating film 11 is formed of an epoxy resin mixed with glass fibers as shown in FIG.

본 발명에 의한 터널 시공은, 크게 대별하여 굴착공사와 콘크리트 타설공사의 2가지로 나뉘어지며, 굴착공사와 콘크리트 타설공사는 단면형태에 따라 병행하여 시공할 수도 있고 별도의 공종으로 구분하여 시공할 수도 있다.Tunnel construction according to the present invention is largely divided into two types of excavation work and concrete pouring work, excavation work and concrete pouring work can be carried out in parallel according to the cross-sectional shape or divided into separate construction works have.

굴착공사는 발진기지 설치 및 메서 플레이트를 배열한 다음, 메서 플레이트 추진·후방 토류판 삽입·막장 굴착·막장막이 설치·강재지보 설치로 이루어진 일련의 작업을 반복적으로 수행하여 완료하는데, 이들 작업은 다음과 같이 시행된다.The excavation work is completed by repeatedly setting up the oscillation base and arranging the mesa plate, then pushing the mesa plate, inserting the rear earth plate, excavating the membrane, installing the membrane, and installing the steel support. It is implemented together.

우선, 굴착하고자 하는 터널 입구에서 충분한 공간을 확보한 상태에서 바닥강재의 수평을 맞추기 위해 바닥콘크리트를 타설한 후, 그 위에 강재지보(10)를 조립하여 도4a 및 도4b의 도시와 같은 형태의 발진기지를 구축한다. 그리고 메서 플레이트(71)들을 굴착 터널의 단면에 맞추어 강재지보(10)의 상단, 중단 및 양측면에 배열 장착한다.First, in order to level the bottom steel while securing sufficient space at the entrance of the tunnel to be excavated, the bottom concrete is poured, and then the steel beam 10 is assembled thereon, as shown in FIGS. 4A and 4B. Build an oscillation base. And in accordance with the cross section of the excavation tunnel to the meseter plate 71 is mounted on the top, middle and both sides of the steel support (10).

이후, 도5의 도시와 같이 굴착 시공해야 할 구간에 일정한 간격(60~80㎝)으로 보강 강재지보(10)를 설치해 나가면서 유압추진기(72)를 이용해 막장 속으로 메서 플레이트(71)를 1매씩 추진해 나간다.Subsequently, while installing the reinforcing steel support 10 at regular intervals (60 to 80 cm) in a section to be excavated as shown in FIG. 5, the mesers plate 71 is inserted into the membrane using a hydraulic propeller 72. We push forward every single time.

이때, 상기 강재지보(10)들의 연결부를 유리섬유가 혼입된 에폭시수지로 코팅하여 방수처리한다.At this time, the connection of the steel support 10 is coated with an epoxy resin in which glass fibers are mixed to waterproof.

위와 같이 메서 플레이트(71)를 추진하면서 한편으로 메서 플레이트(71) 후미부에 토류판(73)을 삽입하여 토사 하중 및 토압이 균등하게 강재지보(10)에 전달되도록 한다. 또한 쐐기목(74)을 사용하여 토류판(73)을 굴착면에 밀착시켜 흙의 이완을 방지한다.Propelling the mesa plate 71 as described above, while the earth plate 73 is inserted into the rear portion of the mesa plate 71 so that the earth and sand load and earth pressure is evenly transmitted to the steel support 10. In addition, by using the wedge 74 to close the earth plate 73 to the excavation surface to prevent the loosening of the soil.

메서 플레이트(71)의 진입이 완료되면, 막장굴착 작업을 시행하고, 진입된 메서 플레이트 길이만큼의 굴착을 완료하면 즉시 버팀대로 막장막이하여 굴착면을 보호한다.When the entrance of the Messer plate 71 is completed, the membrane digging operation is performed, and when the excavation of the length of the Messer plate is completed, the membrane is immediately protected by the membrane.

본 발명은 위와 같은 일련의 작업을 반복적으로 수행하여서 터널굴착공사를 완료하게 되며, 굴착공사가 완료되면 콘크리트 타설공사를 실시한다.The present invention is to complete the tunnel excavation work by repeatedly performing the above series of operations, and when the excavation is completed, the concrete is poured.

콘크리트 타설공사는 라이닝콘크리트 타설 ·이면 그라우팅 ·방수공사 ·경량콘크리트 설치 ·마감작업 순으로 시행하여 완료하는데, 이들 작업은 다음과 같이 이루어진다.Concrete pouring works are completed in the following order: lining concrete, surface grouting, waterproofing, lightweight concrete installation, and finishing work.

우선, 터널굴착이 끝나면 도6의 도시와 같이 굴착시 설치된 강재지보(10)의 두께로 라이닝 구조물(20)을 타설한다.First, when the tunnel excavation is finished, the lining structure 20 is poured into the thickness of the steel support 10 installed during the excavation as shown in FIG.

이 라이닝 구조물(20)은 무근 콘크리트로 형성할 수도 있고, 콘크리트를 타설하기에 앞서 상기 강재지보(10)들의 사이에 철근을 배근한 후 콘크리트를 타설하여 형성시킬 수도 있다.The lining structure 20 may be formed of non-concrete concrete, or may be formed by placing concrete after reinforcing the steel bars between the steel beams 10 before placing concrete.

콘크리트 타설작업은 강재지보(10)간의 사이에 밀실하게 충진될 수 있도록 해야 하므로 공사비가 다소 높아지더라도 몰탈 채움공으로 시공하는 것이 바람직하다.Concrete pouring work is to be filled tightly between the steel support (10), so it is preferable to construct a mortar-filled hole even if the construction cost is slightly higher.

라이닝 구조물(20)을 형성한 다음에는 라이닝 구조물(20) 이면의 밀실한 충진 및 방수기능을 높이기 위하여 도7의 도시와 같이 상기 라이닝 구조물(20)의 이면에 그라우트(30)를 주입한다.After the lining structure 20 is formed, the grout 30 is injected into the back surface of the lining structure 20 as shown in FIG. 7 in order to increase the filling and waterproofing function of the back surface of the lining structure 20.

이때, 그라우트 주입은 라이닝 구조물(20) 형성시 미리 설치한 그라우트 주입구(미도시)를 통해 실시하며, 그라우트의 밀실한 충진 여부는 역시 라이닝 구조물(20) 형성시 미리 설치한 에어 벤트 파이프(미도시)를 통해 확인한다.At this time, the grout injection is carried out through a grout inlet (not shown) pre-installed when the lining structure 20 is formed, and whether the filling of the grout is tightly filled is also an air vent pipe (not shown) pre-installed when the lining structure 20 is formed. Check with).

그라우트 주입 후에는 도8의 도시와 같이 상기 라이닝 구조물(20)의 표면에 시트를 이용한 방수면(40)을 형성한다.After grout injection, the waterproof surface 40 using the sheet is formed on the surface of the lining structure 20 as shown in FIG. 8.

이와 같은 방수면(40)을 형성함에 있어서, 터널굴착시 중간 임시지보재가 설치될 경우 구체방수 방법이나 내부방수 방법을 택하여야 하나, 본 발명에 따르면 터널굴착시 근본적으로 중간 임시지보재가 설치되지 않기 때문에 기본적으로는 메탈시트 방수 또는 적절한 일반 재질의 시트방수도 가능하며, 특히 천정면의 방수는 부착성을 고려하여 메탈제품과 고무제품을 겸용하는 것이 바람직하다.In forming the waterproof surface 40, when the temporary temporary support material is installed during the tunnel excavation, the concrete waterproof method or the internal waterproof method should be selected, but according to the present invention, the intermediate temporary support material is not basically installed during the tunnel excavation. Therefore, it is basically possible to waterproof the metal sheet or waterproof the sheet of a suitable general material, and in particular, it is preferable to use a metal product and a rubber product in consideration of adhesiveness in waterproofing the ceiling surface.

방수면(40) 형성작업을 마친 후에는 방수면(40)위에 경량콘크리트로 된 보호막(50)을 형성한다.After the waterproofing surface 40 is formed, the protective film 50 made of lightweight concrete is formed on the waterproofing surface 40.

이 보호막(50)은 방수면(40)위에 와이어메쉬를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 형성하는데, 바람직하기로는 도8의 도시와 같이 상기 방수면 (40)위에 1차 와이어메쉬(51)를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 1차 경량콘크리트층(52)을 형성한 후, 그 1차 경량콘크리트층(52) 위에 다시 2차 와이어메쉬(53)를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 2차 경량콘크리트층(54)을 형성하는 것이 외부의 충격에 대한 내구성을 확보하는데 유리하다.The protective film 50 is formed by installing a wire mesh on the waterproof surface 40 and placing shotcrete or lightweight concrete, preferably the primary wire mesh 51 on the waterproof surface 40 as shown in FIG. After the installation of the first light concrete layer 52 by forming the shot concrete or lightweight concrete, and then install the secondary wire mesh 53 on the first lightweight concrete layer 52 and cast the shot concrete or lightweight concrete It is advantageous to form a secondary lightweight concrete layer 54 to ensure durability against external impact.

위와 같이 보호막(50)을 형성시킨 후 도8의 도시와 같은 마감면(60) 형성작업을 시행하는데, 경량콘크리트 자체를 미장으로 마감시에는 미장면 위에 에폭시 계통의 도장을 피복하여 청소가 가능하도록 한다.After the protective film 50 is formed as described above, the finishing surface 60 is formed as shown in FIG. 8, and when the lightweight concrete itself is finished with plastering, the epoxy coating is coated on the plastering surface to enable cleaning. do.

상기 마감면(60)은 수려한 마감을 위해서 보호막(50)의 외면 위에 외장용 강재판넬을 부착하거나 외장용 강재타일을 부착하여 마감하는 등 다양하게 변경할 수 있다.The finishing surface 60 may be variously modified such as attaching an exterior steel panel or an exterior steel tile to the exterior surface of the protective film 50 for a beautiful finish.

이상에서 설명한 바와 같이 본 발명은 터널굴착시 설치되는 강재지보를 보강하고 영구 구조물화 하는 작업을 통해 터널용 지지 구조물 구축공사를 완료하게 되며 다음과 같은 효과가 있다.As described above, the present invention completes the construction of the support structure for the tunnel through the work of reinforcing the steel support installed during the tunnel excavation and permanent structure, and has the following effects.

첫째, 굴착용 가설 강재지보를 보강하여 터널 구조물화 함으로써 공사비 및 공사기간을 획기적으로 줄일 수 있다.First, the construction cost and the construction period can be drastically reduced by reinforcing excavation temporary steel support to form a tunnel structure.

둘째, 굴착단면이 최소화되기 때문에 토피가 상대적으로 얇더라도 메서 실드 공법과 동일한 굴착 방법으로 굴착이 가능해 짐으로써, 메서 실드가 가지는 굴착방법의 이점을 살릴 수 있는 적용범위가 대폭 확대된다.Second, since the excavation cross section is minimized, the excavation can be carried out by the same excavation method as the method of the method of shielding method even though the toffee is relatively thin, thereby greatly expanding the scope of application of the method of excavation method of the method.

셋째, 천정부분에 설치된 빔을 받치기 위한 중간 임시지보재를 설계단계에서 삭제함으로써, 중간 임시지보재의 철거 흔적이 남지 않을 뿐만 아니라, 종래 공법에서 구조적으로 취약했던 누수원인이 원천적으로 제거되어 보다 품질 좋은 터널 구조물을 얻을 수 있다.Third, by deleting the intermediate temporary support material to support the beam installed on the ceiling part in the design stage, not only the trace of dismantling of the intermediate temporary support material is left, but the leak cause, which was structurally weak in the conventional construction method, is eliminated at the source and is of higher quality. Tunnel structure can be obtained.

넷째, 구조적인 안정성이 확보되면서 라이닝 구조물의 두께가 종래 공법에 비해 1m이상 축소되므로 공사비용이 크게 절감될 뿐만 아니라, 연접되는 도로와 단차없이 동일한 레벨로의 시공이 가능하여 차량 주행성이 좋은 도로 구조물을 제공한다.Fourth, as the structural stability is ensured, the thickness of the lining structure is reduced by more than 1m compared to the conventional construction method, which not only greatly reduces the construction cost but also enables construction at the same level without stepping with the road to be connected to the road structure, so that the vehicle can be easily driven. To provide.

다섯째, 라이닝 구조물의 외면을 와이어메쉬로 보강한 경량콘크리트로 처리하였기 때문에 사용 용도에 따라 부응할 수 있는 마감이 가능하여 보다 수려한 터널 구조물을 제공할 수 있다.Fifth, since the outer surface of the lining structure is treated with a lightweight concrete reinforced with a wire mesh, it is possible to provide a more beautiful tunnel structure can be finished according to the intended use.

따라서, 본 발명은 강재지보의 영구화라는 간단하면서도 효율적인 방법을 통해 공사기간 단축, 공사비용 절감 및 고품질의 터널 구조물을 제공할 수 있는 매우 유용한 발명이다.Therefore, the present invention is a very useful invention that can provide a tunnel structure of high quality and shorten the construction period, construction cost reduction through a simple and efficient method of permanentizing the steel support.

Claims (8)

터널 단면형상에 따라 굴착된 토사부와 인접하여서 일정간격으로 조립·설치되며, 그 외표면이 유리섬유가 혼입된 에폭시수지로 도막(11)이 형성되어 있는 강재지보(10)와; 상기 강재지보(10)들의 간격사이에 콘크리트를 타설하여 형성한 라이닝 구조물(20)과; 상기 라이닝 구조물(20)의 이면에 주입한 그라우트(30)와; 상기 라이닝 구조물(20)의 표면에 시트를 이용해 형성한 방수면(40)과; 상기 방수면 (40)위에 와이어메쉬를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 형성한 보호막(50)과; 상기 보호막(50)의 외면을 마감하기 위해 부착한 마감면(60);으로 구성된 것을 특징으로 하는 터널용 지지 구조물.Steel support 10, which is assembled and installed at a predetermined interval adjacent to the excavated soil part according to the tunnel cross-sectional shape, the outer surface of which is formed of an epoxy resin in which glass fibers are mixed; A lining structure 20 formed by pouring concrete between the gaps of the steel supports 10; Grout 30 injected into the rear surface of the lining structure 20; A waterproof surface 40 formed on the surface of the lining structure 20 using a sheet; A protective film 50 formed by installing wire mesh on the waterproof surface 40 and pouring shot concrete or lightweight concrete; Tunnel support structure, characterized in that consisting of ;; finish surface (60) attached to close the outer surface of the protective film (50). 굴착시공할 구간의 입구에서 굴착하고자 하는 터널형상에 따라 강재지보(10)를 조립하고 그 강재지보(10) 외주쪽으로 메서 플레이트(71)를 병렬로 배열시켜 발진기지를 구축한 다음, 메서 플레이트 추진·후방 토류판 삽입·막장 굴착·막장막이 설치·강재지보 설치로 이루어진 일련의 작업을 반복적으로 병행하여 터널굴착 공사를 완료한 후, 굴착된 터널 내부의 토압을 지지하기 위한 구조물을 시공하는 지하터널 시공방법에 있어서,Assemble the steel beams (10) according to the tunnel shape to be excavated at the entrance of the section to be excavated, and construct the oscillation base by arranging the mesger plates (71) in parallel to the outer periphery of the steel beams (10), Underground tunnel construction method for constructing a structure to support earth pressure in the excavated tunnel after completing the tunnel excavation work by repeatedly performing a series of operations including insertion of rear earth plate, excavation of membrane, installation of membrane curtain, and installation of steel support To 상기 터널굴착 공사에서 사용되는 강재지보(10)는 부식을 방지하고 강도를 보강하기 위한 도막(11)이 형성된 것을 사용하고, 상기 콘크리트 구조물은 상기 터널굴착 공사를 완료한 이후, 터널굴착 단면을 따라 설치한 상기 강재지보(10)들의간격사이에 콘크리트를 타설하여 라이닝 구조물(20)을 형성하고, 상기 라이닝 구조물(20)의 이면에 그라우트(30)를 주입한 다음, 상기 라이닝 구조물(20)의 표면에 시트를 이용한 방수면(40)을 형성하고, 상기 방수면(40)위에 와이어메쉬를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 보호막(50)을 형성시킨 후, 보호막(50)의 외면을 면처리하여 마감면(60)을 형성하는 일련의 작업을 통해, 상기 강재지보 (10)를 영구 구조물화하여 시공함을 특징으로 하는 지하터널 시공방법.The steel support 10 used in the tunnel excavation construction is used to form a coating film 11 for preventing corrosion and reinforcing strength, the concrete structure after completing the tunnel excavation construction, along the tunnel excavation cross section Placing concrete between the gap between the installed steel support 10 to form a lining structure 20, injecting the grout 30 on the back surface of the lining structure 20, then of the lining structure 20 After forming the waterproof surface 40 using a sheet on the surface, and installing a wire mesh on the waterproof surface 40 and pouring shotcrete or lightweight concrete to form a protective film 50, the outer surface of the protective film 50 Underground tunnel construction method characterized in that through the series of operations to form a finish surface 60 by processing, constructing the steel support 10 to a permanent structure. 제2항에 있어서, 상기 강재지보(10)의 도막(11)은 유리섬유가 혼입된 에폭시수지로 형성하며, 상기 강재지보(10)들의 연결부를 유리섬유가 혼입된 에폭시수지로 코팅하여 방수처리함을 특징으로 하는 지하터널 시공방법.The method of claim 2, wherein the coating film 11 of the steel support 10 is formed of epoxy resin in which glass fibers are mixed, and the connection portion of the steel support 10 is coated with an epoxy resin in which glass fibers are mixed to be waterproofed. Underground tunnel construction method characterized in that. 제2항에 있어서, 상기 라이닝 구조물(20)은 상기 강재지보(10)들의 사이에 철근을 배근한 후 콘크리트를 타설하여 형성시키는 것을 특징으로 하는 지하터널 시공방법.The method of claim 2, wherein the lining structure (20) underground tunnel construction method characterized in that the reinforcing reinforcement between the steel beams (10) is formed by pouring concrete. 제2항에 있어서, 상기 보호막(50)은 방수면(40)위에 1차 와이어메쉬(51)를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 1차 경량콘크리트층(52)을 형성한 후, 그 1차 경량콘크리트층(52) 위에 2차 와이어메쉬(53)를 설치하고 숏크리트 또는 경량콘크리트를 타설하여 2차 경량콘크리트층(54)을 형성하는 작업을 통해 이루어짐을 특징으로 하는 지하터널 시공방법.According to claim 2, wherein the protective film 50 is installed on the waterproof surface 40, the primary wire mesh 51 and the shot concrete or lightweight concrete is formed by forming the primary lightweight concrete layer 52, the 1 Underground tunnel construction method characterized in that the secondary lightweight wire mesh 53 is installed on the secondary lightweight concrete layer 52, and shot concrete or lightweight concrete is poured to form the secondary lightweight concrete layer 54. 제2항에 있어서, 상기 마감면(60)은 상기 보호막(50)의 외면을 미장처리한 후 그 미장면 위에 에폭시 계통의 도장을 피복하여 형성함을 특징으로 하는 지하터널 시공방법.3. The method of claim 2, wherein the finishing surface 60 is formed by coating the outer surface of the protective film 50 after coating the epoxy-based coating on the plastering surface. 제2항에 있어서, 상기 마감면(60)은 보호막(50)의 외면 위에 외장용 강재판넬을 부착하여 형성함을 특징으로 하는 지하터널 시공방법.The method of claim 2, wherein the finishing surface (60) underground tunnel construction method characterized in that formed by attaching the external steel panel on the outer surface of the protective film (50). 제2항에 있어서, 상기 마감면(60)은 상기 보호막(50)의 외면 위에 외장용 강재타일을 부착하여 마감함을 특징으로 하는 지하터널 시공방법.The method of claim 2, wherein the finishing surface (60) underground tunnel construction method characterized in that the finishing by attaching the exterior steel tile on the outer surface of the protective film (50).
KR10-2002-0013228A 2002-03-12 2002-03-12 Supporting structure for tunnel and underground tunnel construction method using the same KR100432782B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0013228A KR100432782B1 (en) 2002-03-12 2002-03-12 Supporting structure for tunnel and underground tunnel construction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0013228A KR100432782B1 (en) 2002-03-12 2002-03-12 Supporting structure for tunnel and underground tunnel construction method using the same

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020020007301U Division KR200279246Y1 (en) 2002-03-12 2002-03-12 Supporting structure for tunnel

Publications (2)

Publication Number Publication Date
KR20030073590A KR20030073590A (en) 2003-09-19
KR100432782B1 true KR100432782B1 (en) 2004-05-24

Family

ID=32224408

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0013228A KR100432782B1 (en) 2002-03-12 2002-03-12 Supporting structure for tunnel and underground tunnel construction method using the same

Country Status (1)

Country Link
KR (1) KR100432782B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100558260B1 (en) 2004-09-30 2006-03-10 김기홍 Messer shield excavating apparatus and messer shield method
KR100955345B1 (en) 2009-10-30 2010-04-29 (주식회사)문창 Concrete wall watertight type glass tile and methode for manufacture thereof

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100930421B1 (en) * 2007-07-11 2009-12-14 (주)리뉴시스템 Waterproof construction method of concrete station pouring section
KR100949774B1 (en) * 2009-07-28 2010-03-30 염명호 Messer tunnel construction method using upper first excavation method
CN113153373B (en) * 2021-05-24 2024-04-16 辽宁工程技术大学 Reactive resin thin-spraying material coal mine tunnel surface supporting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61126294A (en) * 1984-11-21 1986-06-13 鉄建建設株式会社 Tunnel drilling construction method
US4786206A (en) * 1987-02-06 1988-11-22 Tekken Construction Co., Ltd. Lining tunnel wall made by shield type tunnel excavator
KR900007883A (en) * 1988-11-21 1990-06-02 야마구찌 도시아끼 Process for preparing poly (phenylene sulfide) of improved reactivity
KR20000037062A (en) * 2000-04-06 2000-07-05 유성용 Method and apparatus for pouring grouting into rear cavity of tunnel
KR200197089Y1 (en) * 2000-04-11 2000-09-15 한혜선 Waterproofing repair and reinforced construction of a tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61126294A (en) * 1984-11-21 1986-06-13 鉄建建設株式会社 Tunnel drilling construction method
US4786206A (en) * 1987-02-06 1988-11-22 Tekken Construction Co., Ltd. Lining tunnel wall made by shield type tunnel excavator
KR900007883A (en) * 1988-11-21 1990-06-02 야마구찌 도시아끼 Process for preparing poly (phenylene sulfide) of improved reactivity
KR20000037062A (en) * 2000-04-06 2000-07-05 유성용 Method and apparatus for pouring grouting into rear cavity of tunnel
KR200197089Y1 (en) * 2000-04-11 2000-09-15 한혜선 Waterproofing repair and reinforced construction of a tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100558260B1 (en) 2004-09-30 2006-03-10 김기홍 Messer shield excavating apparatus and messer shield method
KR100955345B1 (en) 2009-10-30 2010-04-29 (주식회사)문창 Concrete wall watertight type glass tile and methode for manufacture thereof

Also Published As

Publication number Publication date
KR20030073590A (en) 2003-09-19

Similar Documents

Publication Publication Date Title
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR100432782B1 (en) Supporting structure for tunnel and underground tunnel construction method using the same
JP2002115260A (en) Extension method for basement
KR20090080230A (en) The grouting structure of tunnel and tunnel construction method using the same
KR100784201B1 (en) Method for construction of tunnel
KR20050020451A (en) Shield tunneling construction method and tunnel structure
KR20090011442A (en) Tunnel boring method using sheet pile and tunnel structure therof
KR100455247B1 (en) Cast-in-site diaphragms wall and the method with benoto method and grouting method of high pressure
CN207228173U (en) A kind of underground project waterproof structure
KR200279246Y1 (en) Supporting structure for tunnel
KR100476839B1 (en) Construction method for installing concrete underground structures
KR101267688B1 (en) The shore protection construction method using a precast finish panel
KR101032408B1 (en) Method of reinforced earth retaining wall for cutting face through reinforcing execution and concrete block
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
JP2816741B2 (en) How to build a large cavity
JP2001271365A (en) Construction method for underground structure
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
KR100401330B1 (en) A method of construction for earth-protection walls of building
JPS6117696A (en) Construction of underground head
KR20210002947A (en) Two-side semicircle arch type leading pipe and structure of non-excavation type tunnel using thereof and method of constructing thereof
KR200341389Y1 (en) Reinforced structure of underground excavation construction and lasting wall type reinforced panel
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee
R401 Registration of restoration
FPAY Annual fee payment

Payment date: 20120510

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20130510

Year of fee payment: 10

LAPS Lapse due to unpaid annual fee