KR200197089Y1 - Waterproofing repair and reinforced construction of a tunnel - Google Patents

Waterproofing repair and reinforced construction of a tunnel Download PDF

Info

Publication number
KR200197089Y1
KR200197089Y1 KR2020000010338U KR20000010338U KR200197089Y1 KR 200197089 Y1 KR200197089 Y1 KR 200197089Y1 KR 2020000010338 U KR2020000010338 U KR 2020000010338U KR 20000010338 U KR20000010338 U KR 20000010338U KR 200197089 Y1 KR200197089 Y1 KR 200197089Y1
Authority
KR
South Korea
Prior art keywords
tunnel
construction
attached
waterproofing
reinforced construction
Prior art date
Application number
KR2020000010338U
Other languages
Korean (ko)
Inventor
한혜선
Original Assignee
한혜선
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한혜선 filed Critical 한혜선
Priority to KR2020000010338U priority Critical patent/KR200197089Y1/en
Application granted granted Critical
Publication of KR200197089Y1 publication Critical patent/KR200197089Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

터널벽체에 록크볼트를 천공 설치하고 부직포를 부착하여 앵커볼트로 고정한 후 코어드레인을 겹이음 부착하여 누수를 유도 및 방지하며 철망과 시멘트 모르터 라이닝을 1 회이상 다수층으로 시행하는 터널의 치수 보강공법이다.It is a dimensional reinforcement method for tunnels in which lock bolts are drilled on tunnel walls, nonwoven fabrics are fixed with anchor bolts, core drains are attached, and the leaks are induced and prevented. .

터널 누수 대책공법으로 방수가 확실하고 일부 차량통행이 가능하며 공사비가 적게 드는 유용하고 경제적인 방식이다.The tunnel leak prevention method is a useful and economical method that ensures waterproofness, allows some vehicles to pass, and low construction costs.

Description

터널의 치수 보강공법{Waterproofing repair and reinforced construction of a tunnel}Waterproofing repair and reinforced construction of a tunnel

본 고안은 터널의 보강 방수공법에 관한것으로 상세하게는 특히, 공간 몰타르 라이닝공법에 의하는 터널의 치수 보강에 관한것이다.The present invention relates to the reinforcement waterproofing method of the tunnel, and more particularly, to the dimensional reinforcement of the tunnel by the spatial mortar lining method.

재래식 터널은 대부분 암벽에 무근 콘크리트로 라이닝하며 일반적으로 누수가 심한 기존도로 터널 내부에 특수 방수 공법까지 동원하여 방수공사를 시행하였으나 실패하는 경우가 많았다. 또한 방수 및 라이닝 보강 목적으로 대부분 긴터널에서는 값이 비싼 이동식 철재 거푸집을 이용하여 두께(t) 20 cm 이상의 콘크리트 이중벽 설치를 시행하는것이 일반적인 공법으로 사용되고 있으나 이공법은 시공시 교통이 완전히 통제되는 불편이 따르고 특히 산악 터널과 같은 우회도로가 없는 위치에서는 적용할수가 없으며 시공이 복잡하고 공기 및 공비가 많이 소용되고 시공후엔 터널의 단면 부족 현상이 발생하는가 하면 차량 통행으로 인한 진동, 터널 배면의 압력수등으로 인하여 누수가 재발하는 사례가 많았다.Conventional tunnels are mostly lined with plain concrete on rock walls, and in general, watertight construction was carried out using special waterproofing methods inside the tunnels with heavy leakage. In addition, for the purpose of waterproofing and lining reinforcement, in most long tunnels, the installation of concrete double walls with a thickness (t) of 20 cm or more using expensive mobile formwork is used as a general construction method. In particular, it is not applicable to locations without bypass roads such as mountain tunnels, and the construction is complicated, air and aerobics are used, and the tunnel section lacks after construction. There were many cases of recurrence of leakage due to back pain.

본 고안은 이러한 결점을 시정하는 공법으로 록크 볼트를 이용한 이중벽 설치 공법으로서 시공시 가도나 우회도로가 필요없이 차량소통에 큰지장을 주지않으며 거푸집이 필요하지 않고 용이하게 시공할수 있는 터널 보강 치수 공법을 제공하려는 것이다.The present invention is a method for correcting these shortcomings. It is a double wall installation method using lock bolts, which does not require highways or bypass roads, does not interfere with vehicle communication, and does not require formwork. Is to provide.

도 1 은 본 고안에 의하는 터널의 단면도1 is a cross-sectional view of the tunnel according to the present invention

도 2 는 본 고안의 구조 단면도2 is a structural cross-sectional view of the present invention

도 3 은 본 고안의 요부 확대도3 is an enlarged view of main parts of the present invention;

(가)는 앵크 볼트 설치방법을 나타내는 단면도(A) is sectional drawing showing how to install an anchor bolt

(나)는 록크 볼트 설치 방법을 나타내는 단면도(B) is sectional drawing which shows how to install lock bolt

*도면 중 주요 부호의 설명** Description of Major Symbols in Drawings *

10 : 터널 벽체 11 : 록크볼트10: tunnel wall 11: lock bolt

12 : 부직포 13 : 코어드레인12 nonwoven fabric 13 core drain

14 : 철망 15 : 모르터14: wire mesh 15: mortar

17 : 에폭시 퍼티17: epoxy putty

본 고안은 기존 터널 벽면에 드레인을 긴 록크 볼트를 박아 붙이고 철망을 록크 볼트에 걸어 붙인 다음 시멘트 몰타르로 5-6회 미장하고 또 철망을 걸어 붙인 다음 5-6회 시멘트 몰탈로 미장하여 마감하는 터널 라이닝 치수 보강공법이다.The design of the present invention is to insert a long lock bolt to drain the existing tunnel wall and fasten the wire mesh to the lock bolt, and then plaster it 5-6 times with cement mortar, and then attach the wire mesh and finish with 5-6 times cement mortar. Lining dimension reinforcement method.

본 고안을 양호한 실시예 및 첨부 도면을 참조하여 더욱 자세히 설명한다.The invention is described in more detail with reference to the preferred embodiments and the accompanying drawings.

도 1 , 도 2 , 도 3 에서 터널내부를 깨끗이 청소하고 누수가 심한곳은 배수파이프를 설치하여 측구로 배수한다.In Figures 1, 2, and 3, the inside of the tunnel is cleaned and drained to the side by installing a drain pipe where the leak is severe.

너털 내부 벽체(10)에 천공하여 지름 20mm 길이 200mm의 록크볼트(11)를 설치한다. 배수를 원활히 하기 위하여 부직표(12)를 벽면(10)에 부착하여 앵커볼트(11')로 고정시킨다. 다음 코어드레인(13)을 부착 시키는데 이때 앵커볼트(11'), 록크볼트(11) 구멍 및 코어드레인(13) 이면부위에 에폭시 퍼티 실링제(17)(도 3 참조)등을 충전하여 누수가 되지 않도록 시공한다.The lock bolt 11 having a diameter of 20 mm and a length of 200 mm is installed by drilling into the inner wall of the nut. In order to facilitate drainage, the nonwoven table 12 is fixed to the anchor bolt 11 'by attaching it to the wall surface 10. Next, the core drain 13 is attached. At this time, the anchor bolt 11 ', the lock bolt 11 hole, and the backside of the core drain 13 are filled with an epoxy putty sealing agent 17 (see FIG. 3) and the like. Do not install.

코어드레인(13)을 부착시에 앵커볼트(11')를 사용하여 부착하고 겹이음을 충분히 하여 누수가 되지않도록한다. 이때 상부 측면에서 누수되는 물은 부직포(12)와 코어드레인(13)을 따라 유도되게 되므로 이를 측구 배수로(20)로 유도한다.When the core drain 13 is attached, it is attached using an anchor bolt 11 'and the overlapping is sufficient to prevent leakage. At this time, the water leaking from the upper side is guided along the nonwoven fabric 12 and the core drain 13, so it is guided to the side opening 20.

다음, 1차 철망(14)을 몰타르가 잘 부착 될수 있는 규격품(메탈라스 243)을 사용하여 록크볼트(11)에 용접 접합한다. 1 : 1 비율 초조강 시멘트모르터(15)를 바르는데 양생시 진동으로 인한 처짐을 방지하여야 한다.Next, the primary wire mesh 14 is welded to the lock bolt 11 using a standard product (Metalas 243) that can be attached to the mortar well. 1: 1 ratio roughened cement mortar (15) is applied to prevent sagging due to vibration during curing.

2차 철망(14')을 부착하고 다시 모르터(15')를 발라 타설하고 모르터 양생시 건조 수축을 방지하기 위하여 습윤양생을 한다.Attach the secondary wire mesh 14 'and apply mortar 15' again to wet and cure the mortar to prevent dry shrinkage during curing.

이때 터널크기와 형상에 따라 라이닝 두께와 철망 강선의 굵기가 구조해석으로 결정되어야 하며 모르터는 수축이 크므로 수축이 작게 일어나는 무수축시멘트를 사용하며, 신축이음은 10 m 이내 간격으로 촘촘히 두어야 하며 모르터 바르기는 표면 건조가 되지 않도록 덧바르기를 하여야 한다.Depending on the tunnel size and shape, the thickness of the lining and the thickness of the wire mesh should be determined by the structural analysis. The mortar has a large shrinkage, so it uses a non-cemented cement that causes a small shrinkage, and the expansion joint should be closely spaced within 10 m. Applying should be done to prevent surface drying.

본 고안에 의한 터널 보강 보수치수공법은 종전공법에서 필요하였든 이동식 거푸집 및 콘크리트 펌프가 필요없으며 공사기간을 단축하고 공사중 차량 통행이 가능하며 타설작업상 필요한 최소 콘크리트 라이닝 두께보다 얇은 두께로도 가능하므로 터널을 통한 차도 공간의 손실이 작고 공사비도 적게 든다.Tunnel reinforcement repair dimension method according to the present invention does not require mobile formwork and concrete pump, which is needed in the previous method, shorten the construction period, allow the vehicle to pass during construction, and can be thinner than the minimum concrete lining thickness required for pouring work. Driveway loss of space is small and construction cost is low.

기존 터널의 라이닝 콘크리트가 역학적으로 부족하지않다면 본 고안의 공법은 터널 누수 대책공법으로 방수가 확실하고 일부 차량통행이 가능하며 공사비가 적게 드는 유용하고 경제적인 방식이다.If the lining concrete of the existing tunnel is not mechanically insufficient, the method of the present design is a tunnel leak prevention method, which is a useful and economical method of ensuring waterproofness, allowing some vehicles to pass, and low construction cost.

Claims (1)

터널벽체에 록크볼트를 천공 설치하고 부직포를 부착하여 앵커볼트로 고정한 후 코어드레인을 겹이음 부착하여 누수를 유도 및 방지하며 철망과 시멘트 모르터라이닝을 1 회이상 다수층으로 시행하는것을 특징으로하는 터널의 치수 보강공법After installing the lock bolt on the tunnel wall and attaching the non-woven fabric to fix it with anchor bolts, the core drain is attached to the joint to induce and prevent leakage, and the wire mesh and cement mortar lining are carried out in multiple layers more than once. Dimension reinforcement method
KR2020000010338U 2000-04-11 2000-04-11 Waterproofing repair and reinforced construction of a tunnel KR200197089Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020000010338U KR200197089Y1 (en) 2000-04-11 2000-04-11 Waterproofing repair and reinforced construction of a tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020000010338U KR200197089Y1 (en) 2000-04-11 2000-04-11 Waterproofing repair and reinforced construction of a tunnel

Publications (1)

Publication Number Publication Date
KR200197089Y1 true KR200197089Y1 (en) 2000-09-15

Family

ID=19651466

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020000010338U KR200197089Y1 (en) 2000-04-11 2000-04-11 Waterproofing repair and reinforced construction of a tunnel

Country Status (1)

Country Link
KR (1) KR200197089Y1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100432782B1 (en) * 2002-03-12 2004-05-24 세역산업 주식회사 Supporting structure for tunnel and underground tunnel construction method using the same
AT514032A1 (en) * 2013-02-25 2014-09-15 Rene Semeliker draining
US20220275599A1 (en) * 2017-08-18 2022-09-01 Drff, Llc Forming, drainage and ventilation system for agriculture, irrigation and athletic fields
CN116163768A (en) * 2022-09-19 2023-05-26 中建三局集团有限公司 Tunnel waterproof structure and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100432782B1 (en) * 2002-03-12 2004-05-24 세역산업 주식회사 Supporting structure for tunnel and underground tunnel construction method using the same
AT514032A1 (en) * 2013-02-25 2014-09-15 Rene Semeliker draining
AT514032B1 (en) * 2013-02-25 2018-05-15 Semeliker Rene draining
US20220275599A1 (en) * 2017-08-18 2022-09-01 Drff, Llc Forming, drainage and ventilation system for agriculture, irrigation and athletic fields
CN116163768A (en) * 2022-09-19 2023-05-26 中建三局集团有限公司 Tunnel waterproof structure and construction method thereof
CN116163768B (en) * 2022-09-19 2024-03-08 中建三局集团有限公司 Tunnel waterproof structure and construction method thereof

Similar Documents

Publication Publication Date Title
US5002438A (en) Method of rehabilitating manholes by custom lining/relining
KR102066495B1 (en) Underground composite construction of waterproof combination
JP2000282493A (en) Water-stopping shield device
KR101017117B1 (en) Method and device for waterproofing steel pipe loop structure by a water drainage process for constructing underground structure by non-excavation
KR100402805B1 (en) System pumpingout side a partition for tunnel
KR200197089Y1 (en) Waterproofing repair and reinforced construction of a tunnel
KR20100042441A (en) Inducing waterproof structure of underground diaphragm wall
KR100310457B1 (en) Waterproofing method of concrete structure
KR20020013686A (en) Waterproof sheet for tunnel waterproofing
KR200236381Y1 (en) Waterproof sheet for tunnel waterproofing
KR20030027346A (en) Construction method for installing concrete underground structures
CN111779157A (en) Underground outdoor wall structure and construction method thereof
KR100901184B1 (en) Stonework wall repair reinforcement method of box sewage passage
KR100461492B1 (en) Maintenace and Reinforce Engineering Method of Structure Under Ground
KR101188709B1 (en) Anchor hole sealing apparatus in an diaphragm walls
KR970000495B1 (en) Tunnel repair work method
CN217710879U (en) Basement post-cast strip protective structure
CN210658739U (en) Flange waterproof device
CN219588298U (en) Waterproof shutoff structure of basement outer wall steam pipeline
CN218644336U (en) Drainage device for treating water seepage of tunnel construction joint and deformation joint
KR100367517B1 (en) Stabilization method of a underground construction
JPH1136334A (en) Cut-off structure in connection part of pc wall and floor slab concrete
KR200391938Y1 (en) Inserted nut concrete pipe
JP3199866B2 (en) Underground outer wall and construction method
KR200221236Y1 (en) Joint structure for repair reinforcement of expansion joint for tunnel retaining wall