KR102464866B1 - Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same - Google Patents

Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same Download PDF

Info

Publication number
KR102464866B1
KR102464866B1 KR1020210166929A KR20210166929A KR102464866B1 KR 102464866 B1 KR102464866 B1 KR 102464866B1 KR 1020210166929 A KR1020210166929 A KR 1020210166929A KR 20210166929 A KR20210166929 A KR 20210166929A KR 102464866 B1 KR102464866 B1 KR 102464866B1
Authority
KR
South Korea
Prior art keywords
stage
panel
reinforcing bar
binding
soundproof wall
Prior art date
Application number
KR1020210166929A
Other languages
Korean (ko)
Inventor
정만식
박흥수
박소민
Original Assignee
(주)이지오산업
정만식
박흥수
박소민
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)이지오산업, 정만식, 박흥수, 박소민 filed Critical (주)이지오산업
Priority to KR1020210166929A priority Critical patent/KR102464866B1/en
Application granted granted Critical
Publication of KR102464866B1 publication Critical patent/KR102464866B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F8/00Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic
    • E01F8/0005Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic used in a wall type arrangement
    • E01F8/0023Details, e.g. foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0046Production methods using prestressing techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Sustainable Development (AREA)
  • Architecture (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The present invention relates to a soundproof wall foundation construction method, and a soundproof wall foundation constructed by the same. The soundproof wall foundation construction method comprises a drilling pile fixing step, a first stage panel assembly and lower binding step, a first stage reinforcement mesh embedding and upper binding step, a second stage panel assembly reinforcement mesh embedding and binding step, and a concrete pouring and curing step. The method is applied to a PC panel, a reinforcement mesh, and cast-in-place, such that the bottom portion of the soundproof wall foundation constructed to be erected vertically on the ground is buried under the ground to a predetermined length to be firmly fixed, thereby reducing the construction period. Additionally, the construction method further includes a joint reinforcement binding step which is performed after the first stage panel assembly and lower binding step and after the second stage panel assembly in the second stage panel assembly reinforcement mesh embedding and binding step, thereby reinforcing the binding structure for a contiguous part of the PC panel, reinforcing the strength of the joint part of the panel, and stably preventing damages or deformation.

Description

방음벽 기초의 시공방법 및 그에 의해 시공된 방음벽 기초{Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same}Construction method for soundproof wall foundation and soundproof wall foundation constructed thereby

본 발명은 방음벽 기초의 시공방법 및 그에 의해 시공된 방음벽 기초에 관한 것으로서, 더욱 상세하게는 터파기 파일고정단계, 1단 패널조립 하부결속단계, 1단 철근망 근입 상부결속단계, 2단 패널조립 철근망 근입 결속단계, 콘크리트 타설 양생단계를 포함하는 PC패널과 철근망 및 현장 타설이 적용되는 공법으로 적용함으로써 지면에 수직으로 기립 시공되는 방음벽 기초의 하단 부분에 대해 지중에 일정길이 매립되게 하면서 견고하게 고정함과 동시에 공사기간을 단축할 수 있도록 하는 한편, 1단 패널조립 하부결속단계 이후 및 2단 패널조립 철근망 근입 결속단계에서의 2단 패널조립 이후에 진행되는 이음매 보강 결속단계를 더 포함함으로써 PC패널의 연이어진 부분에 대해 결속 구조를 보강하면서 패널의 이음 부분에 대한 강도를 보강함과 동시에 파손이나 변형을 안정적으로 방지할 수 있도록 한 방음벽 기초의 시공방법 및 그에 의해 시공된 방음벽 기초에 관한 것이다.The present invention relates to a construction method of a soundproof wall foundation and a soundproof wall foundation constructed thereby, and more particularly, to a digging pile fixing step, a first-stage panel assembly lower binding stage, a one-stage rebar mesh rooting upper binding stage, a two-stage panel assembly By applying a method that applies a PC panel including a rebar mesh reinforcing bonding step and a concrete pouring curing step, as well as a rebar mesh and on-site casting, the lower part of the soundproof wall foundation erected perpendicular to the ground is buried in the ground for a certain length and is firm At the same time, it is possible to shorten the construction period at the same time, and further includes a seam reinforcement and bundling step that is carried out after the first panel assembly lower binding step and after the second panel assembly in the second panel assembly rebar mesh reinforcing bonding step. By doing so, the construction method of the soundproof wall foundation and the soundproof wall foundation constructed by it, which reinforces the strength of the joint part of the panel while reinforcing the bonding structure of the continuous part of the PC panel and at the same time can stably prevent damage or deformation. it's about

일반적으로 도로나 철도와 같은 교통시설물의 주변으로는 교통시설물 내에서 발생되는 소음이 외부로 퍼져 나가는 것을 방지하거나 저감시키기 위한 방음벽을 설치한다.In general, soundproof walls are installed around traffic facilities such as roads or railroads to prevent or reduce noise generated within the traffic facilities from spreading to the outside.

이러한 방음벽은 차량이 사고로 인해 외부로 튕겨나가는 것을 방지하기 위하여 안전난간의 역할을 함께 수행하게 되는 것이 일반적이며, 이를 위해서는 방음벽을 지지하기 위한 방음벽 기초를 지면에 견고히 고정하게 된다.It is common for these sound barriers to perform the role of a safety rail together to prevent the vehicle from being thrown out due to an accident.

상기와 같은 종래의 방음벽 기초는 현장에서 거푸집을 설치한 후, 콘크리트를 타설하여 현장 타설을 통해 시공하거나, 공장에서 다양한 크기 즉, 각 도로에서 요구하는 폭을 갖는 방음벽 기초용 단위블록을 생산하여 조립식으로 조립시공하는 방법이 있었다.The conventional soundproof wall foundation as described above is prefabricated by installing a formwork on site, then pouring concrete and constructing it through on-site pouring, or by producing unit blocks for soundproof wall foundations of various sizes, ie, widths required by each road, in a factory. There was a way to assemble it.

전자의 경우에는 현장에서 지반에 설치공간을 파고, 설치공간에 철근을 배근 한 상태에 철근의 외부에 거푸집을 설치한 후 상기 거푸집 내부에 콘크리트를 충진하여 일정기간 동안 자연 양생하여 방음벽 기초를 성형하게 된다.In the former case, the installation space is dug in the ground at the site, the formwork is installed on the outside of the rebar with the reinforcing bars in the installation space, and then the concrete is filled inside the formwork and cured naturally for a certain period to form the soundproof wall foundation. do.

그리고 상기 콘크리트가 양생되면 작업자들은 조립된 거푸집을 해체한 후 완성된 방음벽 기초의 외면을 매끄럽게 후 작업을 하여 방음벽 기초를 완성하였다.And when the concrete was cured, the workers dismantled the assembled formwork, and then smoothed the outer surface of the completed soundproof wall foundation to complete the soundproof wall foundation.

상기와 같은 현장 타설 방법에 의한 방음벽 기초의 시공은 현장 조건에 알맞게 다양한 두께 등을 조절하여 시공할 수 있는 장점 및 견고한 시공의 장점은 있으나, 작업자가 일일이 거푸집을 설치하고 해체하여야 하는 노동력이 과다하게 소요될 뿐만 아니라, 양생 기간 등이 길게 되어 공사기간 지연 등으로 인한 작업능률 저하 및 공사비가 많이 소요되는 등의 결점이 내재되어 있었다.The construction of the soundproof wall foundation by the on-site casting method as described above has the advantage that it can be constructed by adjusting various thicknesses to suit the site conditions and has the advantage of strong construction, but the labor force that the worker must install and dismantle the formwork is excessive. Not only did it take a long time, but it also had drawbacks such as a decrease in work efficiency and a high cost of construction due to a delay in the construction period due to a long curing period.

후자의 경우에는 전자의 문제점 등을 감안하여 공장에서 다양한 폭을 갖는 방음벽 기초용 단위블록을 현장의 주문에 의해 운반한 후 주문된 방음벽 기초용 단위블록을 길이방향으로 연결하면서 시공함에 따라 공사기간이 짧고 간편하여 공사기간 단축 및 시공비는 절감할 수 있으나, 공장에서 생산된 방음벽 기초용 단위블록이 중량물인 관계로 물류비가 과다하게 소요되고, 현장의 조건에 따라 방음벽 기초용 단위블록의 두께가 다양한 변화를 주지 못하기 때문에 정확한 크기의 방음벽 기초용 단위블록을 주문하여야 하는 번거로움 및 잘못된 주문시 반품하고 다시 운반하여야 하는 번거로운 결점 및 시공 현장에 따른 시공을 호환성 있게 할 수 없는 등의 문제점이 야기되었다.In the latter case, considering the problems of the former, the construction period is shortened by transporting unit blocks for soundproof wall foundations of various widths from the factory by order of the site and then connecting the ordered soundproof wall foundation unit blocks in the longitudinal direction. It is short and simple, so it is possible to shorten the construction period and reduce the construction cost. However, since the unit block for soundproof wall foundation produced at the factory is heavy, the logistics cost is excessive, and the thickness of the soundproof wall foundation unit block varies according to the conditions of the site. It caused problems such as the inconvenience of having to order a unit block for the foundation of a soundproof wall of the correct size, the inconvenience of returning and transporting the wrong order, and the inability to compatibility with the construction according to the construction site.

또한, 현장에서 공장에서 다량 생산한 방음벽 기초용 단위블록을 현장에서 주문하여 방음벽 기초용 단위블록을 길이방향으로 연결하면서 시공함에 따라 공사기간이 짧고 간편하여 공사기간 단축 및 시공비는 절감할 수 있으나, 포장된 도로의 상부에 올려져 있는 상태에서 길이 방향으로 설치된 각각의 방음벽 기초용 단위블록만을 고정하였기 때문에, 시공 완료 후 차량의 강한 충격이나 토압 및 수압발생시 방음벽 기초용 단위블록이 연이어 시공된 방음벽 기초 전체가 충격받은 반대쪽으로 밀리거나 전도되어 작업 종사자가 수시로 점검하거나 해체 후 재시공하여야 등 보수 유지 관리비가 과다하게 소요되는 문제점 등이 야기되었다.In addition, the construction period can be shortened and the construction cost can be reduced because the construction period is short and simple by ordering the unit blocks for the soundproof wall foundation produced in large quantities at the site and constructing the soundproof wall foundation unit blocks in the longitudinal direction. Since only the unit blocks for the soundproof wall foundation installed in the longitudinal direction were fixed while being placed on the top of the paved road, the soundproof wall foundation in which the soundproof wall foundation unit blocks were successively constructed in the event of a strong impact from the vehicle, earth pressure, or water pressure after construction was completed The whole was pushed or overturned to the opposite side of the impact, causing problems such as frequent inspection by workers or excessive maintenance costs, such as having to reconstruct after dismantling.

더욱이, 현장에서 공장에서 다량 생산한 방음벽 기초용 단위블록을 현장에서 주문하여 방음벽 기초용 단위블록을 길이방향으로 연결하면서 시공함에 따라 공사기간이 짧고 간편하여 공사기간 단축 및 시공비는 절감할 수 있으나, 횡방향으로 서로 연속되어 설치되는 방음벽 기초용 단위블록은 서로 접합되어지는 접합면을 일체로 결합시키기 위해서, 방음벽 기초용 단위블록이 접합되어지는 부분에 철근을 추가로 타설하고 방수작업을 실시한 후, 몰탈 또는 접착몰탈을 충진하여 시공하는 방법이 사용되고 있다.Furthermore, the construction period can be shortened and the construction cost can be reduced because the construction period is short and simple by ordering the soundproof wall foundation unit blocks produced in large quantities at the site and constructing the soundproof wall foundation unit blocks in the longitudinal direction. In order to unite the joint surfaces to be joined to each other in the unit blocks for soundproof wall foundation installed in succession in the lateral direction, additional reinforcing bars are placed in the part where the soundproof wall foundation unit blocks are joined and waterproofing is performed. A method of filling in mortar or adhesive mortar is used.

그러나 이러한 시공방법은 철근을 추가적으로 배근하기 때문에 공기가 길어지게 되는 문제점이 존재하고 있으며, 또한 접착몰탈을 충진할 경우에는 방음벽 기초용 단위블록 간의 결합강도가 다소 떨어지기 때문에 외부충격에 의해 방음벽 기초용 단위블록의 연이어진 부분이 쉽게 손상됨에 따라 수명이 저하되는 문제점이 여전히 존재하고 있다.However, this construction method has a problem of lengthening the air due to the additional reinforcement of reinforcing bars. Also, when the adhesive mortar is filled, the bonding strength between the unit blocks for the soundproof wall foundation is somewhat lowered. As the continuous part of the unit block is easily damaged, there is still a problem that the life is reduced.

그러므로 PC패널과 철근망 및 현장 타설 공법을 적용함으로써 지면에 수직으로 기립 시공되는 방음벽 기초의 하단 부분에 대해 지중에 일정길이 매립되게 하면서 견고하게 고정함과 동시에 공사기간을 단축할 수 있도록 하는 한편, PC패널의 연이어진 부분에 대해 결속 구조를 보강하면서 패널의 이음 부분에 대한 강도를 보강함과 동시에 파손이나 변형을 안정적으로 방지할 수 있도록 한 방음벽 기초의 시공방법 및 그에 의해 시공된 방음벽 기초에 대해 연구 및 개발이 요구되는 실정이다.Therefore, by applying the PC panel, reinforcing bar mesh, and on-site casting method, the lower part of the soundproof wall foundation erected perpendicular to the ground is buried in the ground for a certain length and firmly fixed while at the same time shortening the construction period. Regarding the soundproof wall foundation construction method and the soundproof wall foundation constructed by reinforcing the cohesive structure of the continuous part of the PC panel, while reinforcing the strength of the joint part of the panel and stably preventing damage or deformation at the same time Research and development are required.

대한민국 등록특허 제1036507호 2011.05.17. 등록.Republic of Korea Patent Registration No. 1036507 2011.05.17. registration. 대한민국 공개특허 제2012-0062184호 2012.06.14. 공개.Republic of Korea Patent Publication No. 2012-0062184 2012.06.14. open. 대한민국 등록특허 제1581938호 2015.12.24. 등록.Republic of Korea Patent Registration No. 1581938 2015.12.24. registration. 대한민국 등록특허 제1732716호 2017.04.26. 등록.Republic of Korea Patent Registration No. 1732716 2017.04.26. registration. 대한민국 등록특허 제1947038호 2019.02.01. 등록.Republic of Korea Patent Registration No. 1947038 2019.02.01. registration. 대한민국 등록특허 제2186472호 2020.11.27. 등록.Republic of Korea Patent No. 2186472 2020.11.27. registration. 대한민국 등록특허 제2197072호 2020.12.23. 등록.Republic of Korea Patent No. 2197072 2020.12.23. registration.

상기와 같은 문제점을 해결하기 위하여, 본 발명은 터파기 파일고정단계, 1단 패널조립 하부결속단계, 1단 철근망 근입 상부결속단계, 2단 패널조립 철근망 근입 결속단계, 콘크리트 타설 양생단계를 포함하는 PC패널과 철근망 및 현장 타설이 적용되는 공법으로 적용함으로써 지면에 수직으로 기립 시공되는 방음벽 기초의 하단 부분에 대해 지중에 일정길이 매립되게 하면서 견고하게 고정함과 동시에 공사기간을 단축할 수 있도록 한 방음벽 기초의 시공방법을 제공하는 것을 목적으로 한다.In order to solve the above problems, the present invention comprises a digging pile fixing step, a first-stage panel assembly lower binding step, a first-stage reinforcing bar mesh upper binding step, a two-stage panel assembly rebar network rooting binding step, and a concrete pouring curing step. By applying a construction method that includes PC panels, reinforcing bar mesh, and on-site casting, the lower part of the soundproof wall foundation erected perpendicular to the ground is buried in the ground for a certain length and firmly fixed and the construction period can be shortened. An object of the present invention is to provide a construction method of a soundproof wall foundation.

본 발명에 따른 기술의 다른 목적은 터파기 파일고정단계, 1단 패널조립 하부결속단계, 1단 철근망 근입 상부결속단계, 2단 패널조립 철근망 근입 결속단계, 콘크리트 타설 양생단계를 포함하는 PC패널과 철근망 및 현장 타설이 적용되는 공법으로 적용하되, 1단 패널조립 하부결속단계 이후 및 2단 패널조립 철근망 근입 결속단계에서의 2단 패널조립 이후에 진행되는 이음매 보강 결속단계를 더 포함함으로써 PC패널의 연이어진 부분에 대해 결속 구조를 보강하면서 패널의 이음 부분에 대한 강도를 보강함과 동시에 파손이나 변형을 안정적으로 방지할 수 있도록 함에 있다.Another object of the technology according to the present invention is a digging pile fixing step, a one-stage panel assembly lower binding step, a one-stage rebar network reinforcing upper binding step, a two-stage panel assembly rebar network reinforcing bonding step, and a concrete pouring curing step. It is applied as a method that applies panel, reinforcing bar network, and cast-in-place, but further includes a seam reinforcement and bundling step that is carried out after the first stage panel assembly lower binding stage and after the second stage panel assembly in the second stage panel assembly rebar mesh reinforcing binding stage By doing so, the strength of the joint part of the panel is reinforced while reinforcing the binding structure for the continuous part of the PC panel, and damage or deformation can be stably prevented at the same time.

전술한 목적을 달성하기 위한 본 발명은 다음과 같다. 즉, 본 발명에 따른 방음벽 기초의 시공방법은 방음벽 기초를 설치하기 위해 터파기 작업을 통해 함몰 형성된 홈 바닥면의 길이방향으로 일정간격을 가지고 H-파일의 상단으로부터 일정길이만큼이 홈 바닥면으로부터 상향 돌출토록 H-파일을 박아 고정하는 터파기 파일고정단계; 터파기 파일고정단계를 거쳐 함몰 형성된 홈 바닥면에 폭 방향 중앙을 기준으로 양측으로 일정거리 떨어지되 상향 돌출된 H-파일의 양측으로 일정거리 떨어지게 전단연결철근이 돌출된 측이 마주하도록 PC패널을 안착설치하되, 홈 바닥면의 길이방향으로 PC패널이 연이어 맞물려 조립되도록 안착설치하는 한편, 마주하는 PC패널의 최하단에 배치된 전단연결철근에 역 "U" 자형의 결속철근 양단을 걸어 결속고정하는 1단 패널조립 하부결속단계; 마주하는 1단의 PC패널 사이 공간이면서 마주하는 H-파일의 요홈 사이의 공간에 1단철근망을 근입한 후, 마주하는 1단의 PC패널 최상단에 배치된 전단연결철근에 역 "U" 자형의 결속철근 양단을 걸어 결속고정하는 1단 철근망 근입 상부결속단계; 1단 철근망 근입 상부결속단계 이후 진행되며, 2단의 PC패널 상단과 H-파일 상단이 일치하도록 1단의 PC패널 상부에 2단이 되게 2단의 PC패널을 안착설치하고, 마주하는 2단의 PC패널 최하단에 배치된 전단연결철근에 역 "U" 자형의 결속철근 양단을 걸어 결속고정하며, 마주하는 2단의 PC패널 사이공간이면서 마주하는 H-파일의 요홈 사이의 공간에 대해 길이방향 중앙부분에 상향 다수의 앵커볼트 상단이 일정길이 돌출되게 용접고정된 2단철근망을 근입한 후, 마주하는 2단의 PC패널 최상단에 배치된 전단연결철근에 역 "U" 자형의 결속철근 양단을 걸어 결속고정하는 2단 패널조립 철근망 근입 결속단계; 및 2단 패널조립 철근망 근입 결속단계를 거쳐 형성된 1단과 2단의 마주하는 PC패널 사이이면서 H-파일의 요홈 사이 공간에 대해 1단철근망과 2단철근망이 근입배치된 상태로 현장에서 콘크리트를 타설하여 양생시키는 콘크리트 타설 양생단계를 포함한다.The present invention for achieving the above object is as follows. That is, in the construction method of the soundproof wall foundation according to the present invention, a certain length from the top of the H-pile is separated from the groove floor by a certain distance in the longitudinal direction of the groove bottom surface that is recessed through the excavation work to install the soundproof wall foundation. Digging pile fixing step of driving and fixing the H-pile so as to protrude upward; Place the PC panel on the bottom surface of the recess formed through the excavation pile fixing step so that the protruding side of the shear connecting reinforcing bar faces each other at a certain distance from the center in the width direction to both sides of the upwardly protruding H-pile. Seated and installed, but seated and installed so that the PC panels are sequentially interlocked and assembled in the longitudinal direction of the groove floor, while fixing the binding by hooking both ends of the inverted "U"-shaped binding reinforcing bars to the shear connecting reinforcing bars arranged at the bottom of the facing PC panel. One-stage panel assembly lower binding step; After inserting a one-stage rebar network into the space between the facing 1st stage PC panel and the space between the grooves of the opposing H-pillar, the reverse "U" shape is applied to the shear connecting reinforcing bar placed at the top of the facing 1st stage PC panel. The upper binding step of a single-stage reinforcing bar network reinforcing binding by hanging both ends of the binding reinforcing bars of the ; It proceeds after the upper binding stage of the first-stage rebar network, and the second-stage PC panel is seated and installed so that the upper part of the first-stage PC panel becomes two-stage so that the upper part of the second-stage PC panel and the upper part of the H-pillar coincide with each other, and Both ends of the inverted "U"-shaped binding reinforcing bar are hung on the shear connecting reinforcing bar arranged at the bottom of the PC panel of the tier and fixed. After reinforcing a two-tiered reinforcing bar network that is welded and fixed so that the tops of a number of anchor bolts protrude upward for a certain length in the central part of the direction, the reverse “U”-shaped binding reinforcing bars are attached to the shear connecting reinforcing bars placed at the top of the two-tiered PC panel facing each other. A two-stage panel assembly reinforcing bar network reinforcing binding step of fixing both ends by hanging; and two-stage panel assembly between the first and second stages of the PC panel formed through the reinforcing and bonding step, and between the first and second stages of the rebar network and the two-stage reinforcing bar network in the space between the grooves of the H-pile. It includes a concrete pouring curing step of curing by pouring concrete.

상기와 같은 본 발명은 콘크리트 타설 양생단계 이후에 진행되며, 타설 양생된 콘크리트 상부로서 2단의 마주하는 PC패널 사이에 대한 길이방향으로 일정간격을 가지고 각각 다수 개로 돌출된 앵커볼트 상단에 방음벽지주의 하단을 앵커너트를 적용하여 고정설치하는 방음벽지주설치단계 및 방음벽지주설치단계 이후에 진행되며, 방음벽지주설치단계를 거쳐 설치된 방음벽지주의 사이마다 각각 다수의 방음판을 적층 설치하는 방음판 설치단계를 더 포함할 수 있다.The present invention as described above proceeds after the concrete pouring curing step, and as the upper part of the poured hardened concrete, the soundproofing wall paper is placed on the top of the anchor bolts protruding in number with a certain interval in the longitudinal direction between the two facing PC panels. It proceeds after the soundproof wall post installation step and the soundproof wall post installation step in which the lower part is fixedly installed by applying an anchor nut. can do.

또한, 1단 패널조립 하부결속단계 및 2단 패널조립 철근망 근입 결속단계에 적용되는 1단과 2단의 PC패널은 일 면에 전단연결철근이 다수 개로 상하 및 좌우로 일정간격을 가지고 고리 형으로 돌출형성되되 일 면 사방의 모서리 부분에 "ㄴ"자 형상으로 이음철근이 더 돌출형성되는 한편, 1단 패널조립 하부결속단계, 1단 철근망 근입 상부결속단계, 2단 패널조립 철근망 근입 결속단계에서의 1단철근망의 근입 이전과 이후 및 2단철근망의 근입 이전과 이후에는 PC패널에 대한 홈 바닥면 길이방향으로 연이어져 이웃하는 4개의 이음철근에 대해 "ㅁ"자 형상으로 H-파일의 둘레를 함께 감싸면서 이음결속철근으로 결속시키는 이음매 보강 결속단계가 더 진행되는 것이 바람직하다.In addition, the 1st and 2nd stage PC panels applied to the 1st panel assembly lower binding step and the 2nd panel assembly rebar network rebar connection stage have multiple shear connecting reinforcing bars on one side, and are arranged in a ring shape at regular intervals up and down and left and right. The joint reinforcing bars are formed to protrude, but more protruding in a “L” shape at the corners of one side, while the first stage panel assembly lower binding step, the first stage reinforcing bar network upper binding stage, and the second stage panel assembly rebar network reinforcing binding Before and after the reinforcing of the 1st rebar network and before and after the reinforcing of the 2nd reinforcing bar network, it is connected in the longitudinal direction of the bottom surface of the groove for the PC panel in the longitudinal direction of the 4 neighboring reinforcing bars in a "ㅁ" shape. - It is preferable that the seam reinforcement and binding step of binding together with joint binding reinforcing bars while surrounding the perimeter of the pile proceeds further.

그리고 2단 패널조립 철근망 근입 결속단계에서 2단의 PC패널 상단과 H-파일 상단이 일치할 수 있도록, 1단 패널조립 하부결속단계 및 2단 패널조립 철근망 근입 결속단계에 적용되는 1단과 2단의 PC패널은 상하방향 길이에 대해, 터파기 파일고정단계에서의 홈 바닥면으로부터 상향 돌출토록 고정된 H-파일의 돌출된 길이의 1/2 길이인 패널로 적용되는 것이 양호하다.And so that the upper end of the PC panel of the second stage and the upper end of the H-pille can match in the two-stage panel assembly rebar network reinforcing bonding stage, the first stage and The two-stage PC panel is preferably applied as a panel having a length of 1/2 of the protruding length of the H-pile fixed so as to protrude upward from the bottom of the groove in the digging pile fixing step in the vertical direction.

더욱이, 방음벽 기초의 하단부분에 대해 일정길이만큼이 견고하게 고정될 수 있도록, 1단 철근망 근입 상부결속단계 이후에는 터파기 파일고정단계에서의 터파기 작업을 통해 함몰 형성된 홈 바닥면의 상부 공간 중에서, 1단의 PC패널 마주하는 사이 반대 측 공간에 대해 흙 채움을 통해 1단의 PC패널 외부를 지중에 매립시키는 1단 패널매립 과정이 더 진행되는 것이 바람직하다.Moreover, in order to be firmly fixed to the lower part of the soundproof wall foundation by a certain length, after the upper binding step of the first stage rebar mesh reinforcing, the upper space of the bottom surface of the recess formed through the excavation work in the excavation pile fixing step. Among them, it is preferable that the first-stage panel embedding process of embedding the outside of the first-stage PC panel in the ground through soil filling for the space on the opposite side between the first-stage PC panels is further performed.

본 발명에 따른 방음벽 기초의 시공방법 및 그에 의해 시공된 방음벽 기초의 효과를 설명하면 다음과 같다.The construction method of the soundproof wall foundation according to the present invention and the effect of the soundproof wall foundation constructed thereby will be described as follows.

첫째, 터파기 파일고정단계, 1단 패널조립 하부결속단계, 1단 철근망 근입 상부결속단계, 2단 패널조립 철근망 근입 결속단계, 콘크리트 타설 양생단계를 포함하는 PC패널과 철근망 및 현장 타설이 적용되는 공법으로 적용함으로써 지면에 수직으로 기립 시공되는 방음벽 기초의 하단 부분에 대해 지중에 일정길이 매립되게 하면서 견고하게 고정함과 동시에 공사기간을 단축할 수 있다.First, PC panel, rebar network, and on-site casting including excavation pile fixing step, 1st panel assembly lower bonding step, 1st rebar mesh reinforcing upper bonding step, 2nd panel assembly rebar mesh reinforcing bonding step, and concrete pouring curing step By applying this applied method, the lower part of the soundproof wall foundation erected perpendicular to the ground is buried in the ground for a certain length and fixed firmly and the construction period can be shortened.

둘째, 터파기 파일고정단계, 1단 패널조립 하부결속단계, 1단 철근망 근입 상부결속단계, 2단 패널조립 철근망 근입 결속단계, 콘크리트 타설 양생단계를 포함하는 PC패널과 철근망 및 현장 타설이 적용되는 공법으로 적용하되, 1단 패널조립 하부결속단계 이후 및 2단 패널조립 철근망 근입 결속단계에서의 2단 패널조립 이후에 진행되는 이음매 보강 결속단계를 더 포함함으로써 PC패널의 연이어진 부분에 대해 결속 구조를 보강하면서 패널의 이음 부분에 대한 강도를 보강함과 동시에 파손이나 변형을 안정적으로 방지할 수 있다.Second, PC panel, reinforcing bar network, and on-site casting including excavation pile fixing step, 1st panel assembly lower bonding step, 1st rebar mesh reinforcing upper bonding step, 2nd panel assembly rebar mesh reinforcing bonding step, and concrete pouring curing step The continuous part of the PC panel by further including a seam reinforcement and bundling step that proceeds after the first panel assembly lower binding step and after the second panel assembly in the second panel assembly rebar mesh reinforcing binding step It is possible to reliably prevent damage or deformation while at the same time reinforcing the strength of the joint part of the panel while reinforcing the binding structure.

도 1은 본 발명에 따른 방음벽 기초의 시공방법을 단계별로 나타낸 블록도.
도 2 내지 8은 본 발명에 따른 방음벽 기초의 시공방법을 이용한 방음벽 기초 및 방음벽을 시공하는 과정을 시공순서에 따라 순차적으로 나타낸 시공 공정도.
1 is a block diagram showing the construction method of the soundproof wall foundation in accordance with the present invention step by step.
2 to 8 are construction process diagrams sequentially showing the process of constructing the soundproof wall foundation and soundproof wall using the construction method of the soundproof wall foundation according to the present invention according to the construction sequence.

이하, 첨부된 도면을 참조하여 본 발명에 따른 방음벽 기초의 시공방법 및 그에 의해 시공된 방음벽 기초의 바람직한 실시예를 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, a method of constructing a soundproof wall foundation according to the present invention and a preferred embodiment of the soundproof wall foundation constructed thereby will be described in detail.

도 1은 본 발명에 따른 방음벽 기초의 시공방법을 단계별로 나타낸 블록도이다.1 is a block diagram showing the construction method of the soundproof wall foundation according to the present invention step by step.

도 2 내지 8은 본 발명에 따른 방음벽 기초의 시공방법을 이용한 방음벽 기초 및 방음벽을 시공하는 과정을 시공순서에 따라 순차적으로 나타낸 시공 공정도이다.2 to 8 are construction process diagrams sequentially showing the process of constructing the soundproof wall foundation and soundproof wall using the soundproof wall foundation construction method according to the present invention according to the construction sequence.

도 1 내지 8을 참고하면, 본 발명의 바람직한 실시예에 따른 방음벽 기초의 시공방법은 PC패널과 철근망 및 현장 타설이 적용되는 공법으로 적용하여 지면에 수직으로 기립 시공되는 방음벽 기초의 하단 부분에 대해 지중에 일정길이 매립되게 하면서 견고하게 고정함과 동시에 공사기간을 단축할 수 있는 것으로, 크게 분류하면 터파기 파일고정단계(S110, 1단 패널조립 하부결속단계(S120), 1단 철근망 근입 상부결속단계(S130), 2단 패널조립 철근망 근입 결속단계(S140) 및 콘크리트 타설 양생단계(S150)를 포함한다.1 to 8, the construction method of the soundproof wall foundation according to a preferred embodiment of the present invention is applied as a method to which a PC panel, a reinforcing bar network, and an on-site casting are applied. It can be firmly fixed while being buried in the ground for a certain length, and the construction period can be shortened at the same time. It includes an upper binding step (S130), a two-stage panel assembly reinforcing bar network rooting binding step (S140), and a concrete pouring curing step (S150).

구체적으로, 상기 터파기 파일고정단계(S110)는 방음벽 기초를 설치하기 위해 터파기 작업을 통해 함몰 형성된 홈 바닥면(10)의 길이방향으로 일정간격을 가지고 H-파일(100)의 상단으로부터 일정길이만큼이 홈 바닥면(10)으로부터 상향 돌출토록 H-파일(100)을 박아 고정하는 과정으로 이루어진다.Specifically, the excavation pile fixing step (S110) is a constant interval from the top of the H-pile 100 with a predetermined interval in the longitudinal direction of the groove bottom surface 10 formed by excavating through the excavation work to install the soundproof wall foundation. It consists of a process of driving and fixing the H-pile 100 so as to protrude upward from the groove bottom surface 10 by the length.

상기와 같은 터파기 파일고정단계(S110)에서, 터파기 작업을 통해 함몰 형성된 홈 바닥면(10)의 깊이는 프리캐스트 콘크리트 패널로 기제작을 통해 제공되는 PC패널(200)의 상하방향 길이와 대응되는 길이로 함몰 형성됨이 바람직한 것이다.In the excavation pile fixing step (S110) as described above, the depth of the recessed bottom surface 10 formed through the excavation work is the vertical length of the PC panel 200 provided through pre-fabrication as a precast concrete panel and It is preferable that the depression is formed to a corresponding length.

또한, 상기 1단 패널조립 하부결속단계(S120)는 터파기 파일고정단계(S110)를 거쳐 함몰 형성된 홈 바닥면(10)에 폭 방향 중앙을 기준으로 양측으로 일정거리 떨어지되 상향 돌출된 H-파일(100)의 양측으로 일정거리 떨어지게 전단연결철근(210)이 돌출된 측이 마주하도록 PC패널(200)을 안착설치되, 홈 바닥면(10)의 길이방향으로 PC패널(200)이 연이어 맞물려 조립되도록 안착설치하는 과정을 포함한다.In addition, in the first panel assembly lower binding step (S120), a predetermined distance from the center in the width direction to the groove bottom surface 10 recessed through the digging pile fixing step (S110), the H- protruding upward The PC panel 200 is seated and installed so that the side from which the shear connecting reinforcing bar 210 protrudes is facing each other at a predetermined distance apart from both sides of the pile 100, and the PC panel 200 is sequentially connected in the longitudinal direction of the groove bottom surface 10. It includes the process of seating and installing so that it is interlocked and assembled.

이러한 1단 패널조립 하부결속단계(S120)는 특히, 홈 바닥면(10)의 길이방향으로 PC패널(200)이 연이어 맞물려 조립되도록 안착설치하는 과정 이후에, 마주하는 PC패널(200)의 최하단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하는 과정이 더 진행되는 것이다.This single-stage panel assembly lower binding step (S120) is, in particular, after the process of seating and installing the PC panels 200 in the longitudinal direction of the groove bottom surface 10 so that they are sequentially engaged and assembled, the lowermost end of the PC panel 200 facing each other. The process of fixing the binding by hanging both ends of the inverse "U"-shaped binding reinforcing bar 200a on the shear connecting reinforcing bar 210 disposed in the .

한편, 상기 1단 철근망 근입 상부결속단계(S130)는 마주하는 1단의 PC패널(200) 사이 공간이면서 마주하는 H-파일(100)의 요홈(110) 사이의 공간에 1단철근망(300)을 근입한 후, 마주하는 1단의 PC패널(200) 최상단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하는 과정으로 이루어진다.On the other hand, the upper binding step (S130) of the single-stage reinforcing bar network reinforcing bar network is a space between the facing one-stage PC panels 200 and the space between the recesses 110 of the H-pilles 100 facing each other. 300), and then hooking both ends of the inverted "U"-shaped binding reinforcing bars 200a to the shear connecting reinforcing bars 210 disposed on the top end of the PC panel 200 of the first stage facing the process of binding and fixing.

이때, 상기 1단철근망(300)은 H-파일(100)의 요홈(110) 폭과 대응되는 폭을 갖는 다수의 장방형 와이어 철근과 이러한 다수의 장방형 와이어 철근을 있도록 용접연결되는 수평 와이어 철근으로 구성됨이 바람직한 것이다.At this time, the single-stage reinforcing bar network 300 is a plurality of rectangular wire reinforcing bars having a width corresponding to the width of the groove 110 of the H-pile 100 and a horizontal wire reinforcing bar that is welded to have such a plurality of rectangular wire reinforcing bars. It is preferable to be constructed.

그리고 상기 2단 패널조립 철근망 근입 결속단계(S140)는 1단 철근망 근입 상부결속단계(S130) 이후 진행되며, 먼저 2단의 PC패널(200) 상단과 H-파일(100) 상단이 일치하도록 1단의 PC패널(200) 상부에 2단이 되게 2단의 PC패널(200)을 안착설치하고, 마주하는 2단의 PC패널(200) 최하단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하는 과정으로 진행된다.And the two-stage panel assembly reinforcing bar network reinforcing and binding step (S140) proceeds after the first-stage rebar network reinforcing upper binding step (S130), and first, the upper end of the two-stage PC panel 200 and the upper end of the H-file 100 coincide The two-stage PC panel 200 is seated and installed on top of the one-stage PC panel 200 so that it becomes two-stage, and the opposite shear connecting reinforcing bar 210 disposed at the lowermost end of the two-stage PC panel 200 is reversed. It proceeds to the process of fastening the binding by hanging both ends of the "U"-shaped binding reinforcing bar 200a.

이러한 2단 패널조립 철근망 근입 결속단계(S140)는 마주하는 2단의 PC패널(200) 최하단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하는 과정 이후, 마주하는 2단의 PC패널(200) 사이공간이면서 마주하는 H-파일(100)의 요홈(110) 사이의 공간에 대해 길이방향 중앙부분에 상향 다수의 앵커볼트(410) 상단이 일정길이 돌출되게 용접고정된 2단철근망(400)을 근입한 후, 마주하는 2단의 PC패널(200) 최상단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하는 과정이 더 진행되는 것이다.In this two-stage panel assembly reinforcing bar network reinforcing bar connection step (S140), both ends of the inverted "U"-shaped binding reinforcing bar 200a are hung and bound to the shear connecting reinforcing bar 210 disposed at the lowermost end of the two-stage PC panel 200 facing each other. After the fixing process, the top of the plurality of anchor bolts 410 upward in the longitudinal direction with respect to the space between the facing two-stage PC panel 200 and the space between the grooves 110 of the H-pile 100 facing each other. After reinforcing the two-stage reinforcing bar network 400 that is welded and fixed to protrude a certain length, the reverse "U"-shaped binding reinforcing bar ( 200a) The process of binding and fixing by hanging both ends is further progressed.

여기서, 상기 2단철근망(400)은 H-파일(100)의 요홈(110) 폭과 대응되는 폭을 갖는 다수의 장방형 와이어 철근(미부호)과 이러한 다수의 장방형 와이어 철근(미부호)을 있도록 용접연결되는 수평 와이어 철근(미부호)으로 구성되되, 특히 상단의 길이방향 중앙부분에 일정간격을 가지고 다수의 앵커볼트(410)가 상향 일정길이 돌출되게 하단 부분이 용접고정됨이 바람직하다.Here, the two-stage reinforcing bar network 400 is a plurality of rectangular wire reinforcing bars (unsigned) having a width corresponding to the width of the groove 110 of the H-pile 100 and a plurality of rectangular wire reinforcing bars (unsigned). It is composed of a horizontal wire reinforcing bar (unsigned) that is welded so as to be connected, and in particular, a plurality of anchor bolts 410 with a predetermined interval in the longitudinal central portion of the upper portion are preferably welded and fixed so that a certain length of the anchor bolts 410 protrude upward.

이때, 상기 앵커볼트(410)는 2개를 한 쌍으로 하여 고정할 수 있도록 'U'자 형상으로 제공되어 양측의 상단 일정길이에 걸쳐 나사산이 형성되는 앵커볼트로 제공됨이 더욱 바람직한 것이다.At this time, it is more preferable that the anchor bolts 410 are provided in a 'U' shape so that they can be fixed as a pair and are provided as anchor bolts in which threads are formed over a certain length of the upper ends of both sides.

또한, 상기 콘크리트 타설 양생단계(S150)는 2단 패널조립 철근망 근입 결속단계(S140)를 거쳐 형성된 1단과 2단의 마주하는 PC패널(200) 사이이면서 H-파일(100)의 요홈(110) 사이 공간에 대해 1단철근망(300)과 2단철근망(400)이 근입배치된 상태로 현장에서 콘크리트(C)를 타설하여 양생시키는 과정으로 이루어진다.In addition, the concrete pouring curing step (S150) is between the first and second stages of the PC panel 200 facing the first and second stages formed through the two-stage panel assembly reinforcing bar network rooting and binding step (S140), and the groove 110 of the H-pile 100. ) with respect to the space between the first-stage reinforcing bar network 300 and the second-stage reinforcing bar network 400, the concrete (C) is poured and cured at the site in a state in which the reinforcing bars are placed.

즉, 상기와 같은 콘크리트 타설 양생단계(S150)를 거쳐 현장에서 타설한 콘크리트(C)가 양생이 완료되면, 방음벽지주(510) 및 방음판(520)의 설치를 위한 방음벽 기초에 대해 시공이 완료될 수 있는 것이다.That is, when the curing of the concrete (C) poured at the site through the concrete pouring curing step (S150) as described above is completed, the construction for the soundproof wall foundation for the installation of the soundproof wall post 510 and the soundproofing plate 520 is completed. it can be

물론, 상기 콘크리트 타설 양생단계(S150)는 현장에서 콘크리트(C)를 타설할 때 콘크리트(C)에 대해 1단의 PC패널(200) 사이 공간으로부터 외부로 방출되지 않도록, 1단의 PC패널(200)이 연이어진 최 선단 개방부분과 최 후단 개방부분에 대해 흙 채움을 통해 밀폐시킴이 바람직하다.Of course, in the concrete pouring curing step (S150), when pouring the concrete (C) at the site, the one-stage PC panel ( 200), it is desirable to seal the open part at the leading end and the open at the rear end through soil filling.

아울러, 상기 콘크리트 타설 양생단계(S150)는 현장에서 콘크리트(C)를 타설할 때 콘크리트(C)에 대해 2단의 PC패널(200) 사이 공간으로부터 외부로 방출되지 않도록, 2단의 PC패널(200)이 연이어진 최 선단 개방부분과 최 후단 개방부분에 대해 별도의 밀폐용 거푸집 등을 적용하면서 밀폐시킴이 더욱 바람직한 것이다.In addition, the concrete pouring curing step (S150) is a two-stage PC panel ( 200), it is more preferable to seal the open part at the leading end and the open end at the rear end while applying a separate sealing form.

한편, 전술한 바와 같은 과정들로 이루어진 본 발명에 따른 방음벽 기초의 시공방법은 특히, 1단 패널조립 하부결속단계(S120) 및 2단 패널조립 철근망 근입 결속단계(S140)에 적용되는 1단과 2단의 PC패널(200)은 일 면에 전단연결철근(210)이 다수 개로 상하 및 좌우로 일정간격을 가지고 고리 형으로 돌출형성되되 일 면 사방의 모서리 부분에 "ㄴ"자 형상으로 이음철근(250)이 더 돌출형성되는 것이 바람직하다.On the other hand, the construction method of the soundproof wall foundation according to the present invention consisting of the above-described processes is, in particular, the first stage applied to the first panel assembly lower binding step (S120) and the two-stage panel assembly reinforcing bar network rooting binding step (S140). The two-stage PC panel 200 is formed with a plurality of shear connecting reinforcing bars 210 on one side, protruding in an annular shape with regular intervals up and down and left and right, and joint reinforcing bars in a “L” shape at the corners of one side. It is preferable that 250 is further formed to protrude.

아울러, 본 발명에 따른 방음벽 기초의 시공방법은 1단 패널조립 하부결속단계(S120), 1단 철근망 근입 상부결속단계(S130), 2단 패널조립 철근망 근입 결속단계(S140)에서의 1단철근망(300)의 근입 이전과 이후 및 2단철근망(400)의 근입 이전과 이후에는 PC패널(200)에 대한 홈 바닥면(10) 길이방향으로 연이어져 이웃하는 4개의 이음철근(250)에 대해 "ㅁ"자 형상으로 H-파일(100)의 둘레를 함께 감싸면서 이음결속철근(200b)으로 결속시키는 이음매 보강 결속단계가 더 진행되는 것이 더욱 바람직하다.In addition, the construction method of the soundproof wall foundation according to the present invention is 1 in the first panel assembly lower binding step (S120), the one-stage rebar mesh upper binding step (S130), and the two-stage panel assembly reinforcing bar network rooting binding step (S140). Before and after the reinforcing of the single reinforcing bar network 300 and before and after the reinforcing of the double reinforcing bar network 400, the four joint reinforcing bars ( With respect to 250), it is more preferable that the seam reinforcement binding step of binding with the joint binding reinforcing bar 200b while surrounding the circumference of the H-pille 100 in a "ㅁ" shape is further progressed.

이때, "ㅁ"자 형상이라 함은 H-파일(100)의 둘레와 함께 4개의 이음철근(250) 수직부분을 걸어 감싸는 형상을 평면에서 바라본 형상을 말하는 것이며, 이러한 이음결속철근(200b)은 일정길이의 철근으로 적용하여 "ㅁ"자 형상이 되도록 H-파일(100)의 둘레와 함께 4개의 이음철근(250) 수직부분을 걸어 감싼 상태에서 양단을 꼬아서 마감함이 바람직한 것이다.At this time, the "ㅁ" shape refers to the shape viewed from the plane of the shape surrounding the vertical part of the four joint reinforcing bars 250 along with the circumference of the H-pille 100, and these joint binding reinforcing bars 200b are It is desirable to finish by twisting both ends in a state in which the vertical portions of the four jointed reinforcing bars 250 are hung together with the circumference of the H-pille 100 to form a “ㅁ” shape by applying a reinforcing bar of a certain length.

즉, 전술한 바와 같은 이음매 보강 결속단계를 통해, PC패널(200)에 대한 홈 바닥면(10) 길이방향으로 연이어져 이웃하는 4개의 이음철근(250)에 대해 "ㅁ"자 형상으로 H-파일(100)의 둘레를 함께 감싸면서 이음결속철근(200b)으로 결속시킴으로써 PC패널(200)의 길이방향으로 연이어진 부분에 대한 상호 마주하는 사이에 H-파일(100)이 배치된 상태로 견고한 결속고정이 이루어질 수 있으며, 이를 통하여 종래에 PC패널(200) 등의 방음벽 기초에 대한 연이어진 부분이 쉽게 파손되거나 변형되는 것을 안정적으로 방지할 수 있게 되는 것이다.That is, through the seam reinforcement and binding step as described above, the groove bottom surface 10 for the PC panel 200 is connected in the longitudinal direction to the adjacent four joint reinforcing bars 250 in a "ㅁ" shape in the shape of H- While wrapping the circumference of the pile 100 together, by binding it with a joint binding reinforcing bar 200b, the H-pile 100 is placed between facing each other in the longitudinal direction of the PC panel 200. The binding and fixing can be made, and through this, it is possible to stably prevent the conventionally connected portion of the soundproof wall base such as the PC panel 200 from being easily damaged or deformed.

전술한 바와 같은 이음매 보강 결속단계를 더 포함하는 본 발명에 따른 방음벽 기초의 시공방법은 H-파일(100)의 요홈(110)과 직교하는 양측 면의 길이방향 중앙 라인에 대해, PC패널(200)의 길이방향 끝단이 상호 맞물려 조립되는 것이다.The construction method of the soundproof wall foundation according to the present invention further comprising the seam reinforcement and binding step as described above for the longitudinal center line of both sides orthogonal to the groove 110 of the H-pile 100, PC panel 200 ), the longitudinal ends are interlocked and assembled.

더욱이, 상기 1단 패널조립 하부결속단계(S120) 및 2단 패널조립 철근망 근입 결속단계(S140)에 적용되는 1단과 2단의 PC패널(200)은 상단과 하단이 맞물리면서 길이방향 일단과 타단이 맞물리게 조립될 수 있도록 하는 것이 중요하다.Furthermore, the first and second stages of the PC panel 200 applied to the one-stage panel assembly lower binding step (S120) and the two-stage panel assembly reinforcing bar network reinforcing binding step (S140) have one end and the other end in the longitudinal direction while the upper and lower ends are engaged. It is important to ensure that these can be interlocked.

이에 따라, 상기 1단 패널조립 하부결속단계(S120) 및 2단 패널조립 철근망 근입 결속단계(S140)에 적용되는 1단과 2단의 PC패널(200)은 상단과 하단 및 일단과 타단에 대해 돌기(미부호)와 홈(미부호)이 형성된 프리캐스트 콘크리트 패널로 제공된다.Accordingly, the first and second stages of the PC panel 200 applied to the one-stage panel assembly lower binding step (S120) and the two-stage panel assembly reinforcing bar network rooting binding step (S140) are the upper and lower ends and the one and the other ends. It is provided as a precast concrete panel with projections (unsigned) and grooves (unsigned) formed.

또한, 전술한 바와 같은 과정들로 이루어진 본 발명에 따른 방음벽 기초의 시공방법은 2단 패널조립 철근망 근입 결속단계(S140)에서 2단의 PC패널(200) 상단과 H-파일(100) 상단이 일치할 수 있도록 하는 것이 중요하다.In addition, the construction method of the soundproof wall foundation according to the present invention consisting of the above-described processes is the upper end of the two-stage PC panel 200 and the upper end of the H-pillar 100 in the two-stage panel assembly rebar network reinforcing and binding step (S140). It is important to be able to match.

이를 위하여, 1단 패널조립 하부결속단계(S120) 및 2단 패널조립 철근망 근입 결속단계(S140)에 적용되는 1단과 2단의 PC패널(200)은 상하방향 길이에 대해, 터파기 파일고정단계(S110)에서의 홈 바닥면(10)으로부터 상향 돌출토록 고정된 H-파일(100)의 돌출된 길이의 1/2 길이인 패널로 적용되는 것이 바람직하다.To this end, the first and second stages of the PC panel 200 applied to the one-stage panel assembly lower binding step (S120) and the two-stage panel assembly rebar network reinforcing binding step (S140) for the vertical length, the dug pile is fixed It is preferable to be applied as a panel having a length of 1/2 of the protruding length of the H-pile 100 fixed to protrude upward from the groove bottom surface 10 in step (S110).

아울러, 본 발명은 방음벽 기초의 하단부분에 대해 일정길이만큼이 견고하게 고정될 수 있도록, 1단 철근망 근입 상부결속단계(S120) 이후에는 터파기 파일고정단계(S110)에서의 터파기 작업을 통해 함몰 형성된 홈 바닥면(10)의 상부 공간 중에서, 1단의 PC패널(200) 마주하는 사이 반대 측 공간에 대해 흙 채움을 통해 1단의 PC패널(200) 외부를 지중에 매립시키는 1단 패널매립 과정이 더 진행되는 것이 더욱 바람직한 것이다.In addition, the present invention provides a digging operation in the excavation pile fixing step (S110) after the one-stage rebar network rooting upper binding step (S120) so that a certain length can be firmly fixed to the lower part of the soundproof wall foundation. Among the upper space of the groove bottom surface 10 that is recessed through the first stage, one stage of embedding the outside of the one stage PC panel 200 in the ground through soil filling for the space on the opposite side between the one stage PC panel 200 facing each other It is more preferable that the panel embedding process proceed further.

한편, 전술한 바와 같은 과정들로 이루어진 본 발명에 따른 방음벽 기초의 시공방법은 방음벽지주(510) 및 방음판(520)의 설치를 통해 방음벽체의 시공을 완료할 수 있도록, 방음벽지주설치단계(S160) 및 방음판 설치단계(S170)를 더 포함할 수 있다.On the other hand, the construction method of the soundproof wall foundation according to the present invention consisting of the above-described processes is to complete the construction of the soundproof wall through the installation of the soundproofing wall post 510 and the soundproofing plate 520, the soundproofing wall post installation step (S160) ) and a soundproofing plate installation step (S170) may be further included.

이때, 상기 방음벽지주설치단계(S160)는 도 7에서 보는 바와 같이, 콘크리트 타설 양생단계(S150) 이후에 진행되며, 타설 양생된 콘크리트(C) 상부로서 2단의 마주하는 PC패널(200) 사이에 대한 길이방향으로 일정간격을 가지고 각각 다수 개로 돌출된 앵커볼트(410) 상단에 방음벽지주(510)의 하단을 앵커너트를 적용하여 고정설치하는 과정으로 이루어진다.At this time, the soundproof wall post installation step (S160) proceeds after the concrete pouring curing step (S150), as shown in FIG. It consists of a process of fixing and installing the lower end of the soundproof wall post 510 on the upper end of the anchor bolt 410 protruding in number at a predetermined interval in the longitudinal direction with respect to the anchor nut.

또한, 상기 방음판 설치단계(S170)는 도 8에서 보는 바와 같이, 방음벽지주설치단계(S160) 이후에 진행되며, 방음벽지주설치단계(S160)를 거쳐 설치된 방음벽지주(510)의 사이마다 각각 다수의 방음판(520)을 적층 설치하는 과정으로 이루어진다.In addition, the sound insulation board installation step (S170) proceeds after the sound insulation wall post installation step (S160), as shown in FIG. It consists of a process of laminating the soundproofing plate 520 .

상기와 같은 방음판 설치단계(S170)에서, 특히 방음벽지주(510)의 사이마다 각각 다수의 방음판(520)에 대한 적층 설치는 방음벽지주(510)의 마주하는 양측에 구비된 홈 부분에 방음판(520)의 양단이 슬라이딩 되도록 하면서 적층 설치하는 과정으로 진행됨이 바람직한 것이다.In the soundproofing plate installation step (S170) as described above, in particular, the laminated installation of a plurality of soundproofing plates 520 between each of the soundproofing wall posts 510 is a soundproofing plate 520 in grooves provided on opposite sides of the soundproofing wallpost 510. ), it is preferable to proceed with the process of laminating and installing while sliding both ends.

전술한 바와 같은 과정들로 이루어진 본 발명에 따른 방음벽 기초의 시공방법 및 그에 의해 시공된 방음벽 기초에 의하면, 터파기 파일고정단계, 1단 패널조립 하부결속단계, 1단 철근망 근입 상부결속단계, 2단 패널조립 철근망 근입 결속단계, 콘크리트 타설 양생단계를 포함하는 PC패널과 철근망 및 현장 타설이 적용되는 공법으로 적용함으로써 지면에 수직으로 기립 시공되는 방음벽 기초의 하단 부분에 대해 지중에 일정길이 매립되게 하면서 견고하게 고정함과 동시에 공사기간을 단축할 수 있다.According to the construction method of the soundproof wall foundation according to the present invention comprising the above-described processes and the soundproof wall foundation constructed thereby, the excavation pile fixing step, the first panel assembly lower binding step, the first stage rebar mesh rooting upper binding step, A certain length in the ground for the lower part of the soundproof wall foundation erected perpendicular to the ground by applying the method to which the PC panel including the two-tier panel assembly rebar mesh rooting and bonding step, and the concrete pouring curing step, as well as the rebar mesh and on-site casting are applied. It can be firmly fixed while being buried and shorten the construction period.

더욱이, 터파기 파일고정단계, 1단 패널조립 하부결속단계, 1단 철근망 근입 상부결속단계, 2단 패널조립 철근망 근입 결속단계, 콘크리트 타설 양생단계를 포함하는 PC패널과 철근망 및 현장 타설이 적용되는 공법으로 적용하되, 1단 패널조립 하부결속단계 이후 및 2단 패널조립 철근망 근입 결속단계에서의 2단 패널조립 이후에 진행되는 이음매 보강 결속단계를 더 포함함으로써 PC패널의 연이어진 부분에 대해 결속 구조를 보강하면서 패널의 이음 부분에 대한 강도를 보강함과 동시에 파손이나 변형을 안정적으로 방지할 수 있는 것이다.In addition, PC panel, rebar network, and on-site casting including excavation pile fixing step, 1st panel assembly lower binding step, 1st rebar mesh reinforcing upper binding step, 2nd panel assembly rebar mesh reinforcing bonding step, and concrete pouring curing step The continuous part of the PC panel by further including a seam reinforcement and bundling step that proceeds after the first panel assembly lower binding step and after the second panel assembly in the second panel assembly rebar mesh reinforcing binding step It is possible to reliably prevent damage or deformation while at the same time reinforcing the strength of the joint part of the panel while reinforcing the binding structure.

이상에서 본 발명의 구체적인 실시예를 상세히 설명하였으나, 본 발명은 이에 한정되는 것은 아니며, 본 발명은 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 의해 다양한 변형의 실시가 가능하며, 이러한 변형은 본 발명의 범위에 포함된다.Although specific embodiments of the present invention have been described in detail above, the present invention is not limited thereto, and various modifications can be made by those skilled in the art to which the present invention pertains. are included within the scope of the present invention.

10: 홈 바닥면
100: H-파일
110: 요홈
200: PC패널
210: 전단연결철근
250: 이음철근
200a: 결속철근
200b: 이음결속철근
300: 1단철근망
400: 2단철근망
410: 앵커볼트
510: 방음벽지주
520: 방음판
C: 콘크리트
10: groove bottom
100: H-file
110: groove
200: PC panel
210: shear connection reinforcement
250: joint reinforcement
200a: binding reinforcing bar
200b: joint binding reinforcement
300: single reinforcing bar network
400: double reinforcing bar network
410: anchor bolt
510: soundproof wall post
520: sound insulation board
C: Concrete

Claims (6)

방음벽 기초를 설치하기 위해 터파기 작업을 통해 함몰 형성된 홈 바닥면(10)의 길이방향으로 일정간격을 가지고 H-파일(100)의 상단으로부터 일정길이만큼이 홈 바닥면(10)으로부터 상향 돌출토록 H-파일(100)을 박아 고정하는 터파기 파일고정단계(S110); 터파기 파일고정단계(S110)를 거쳐 함몰 형성된 홈 바닥면(10)에 폭 방향 중앙을 기준으로 양측으로 일정거리 떨어지되 상향 돌출된 H-파일(100)의 양측으로 일정거리 떨어지게 전단연결철근(210)이 돌출된 측이 마주하도록 PC패널(200)을 안착설치하되, 홈 바닥면(10)의 길이방향으로 PC패널(200)이 연이어 맞물려 조립되도록 안착설치하는 한편, 마주하는 PC패널(200)의 최하단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하는 1단 패널조립 하부결속단계(S120); 마주하는 1단의 PC패널(200) 사이 공간이면서 마주하는 H-파일(100)의 요홈(110) 사이의 공간에 1단철근망(300)을 근입한 후, 마주하는 1단의 PC패널(200) 최상단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하는 1단 철근망 근입 상부결속단계(S130); 1단 철근망 근입 상부결속단계(S130) 이후 진행되며, 2단의 PC패널(200) 상단과 H-파일(100) 상단이 일치하도록 1단의 PC패널(200) 상부에 2단이 되게 2단의 PC패널(200)을 안착설치하고, 마주하는 2단의 PC패널(200) 최하단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하며, 마주하는 2단의 PC패널(200) 사이공간이면서 마주하는 H-파일(100)의 요홈(110) 사이의 공간에 대해 길이방향 중앙부분에 상향 다수의 앵커볼트(410) 상단이 일정길이 돌출되게 용접고정된 2단철근망(400)을 근입한 후, 마주하는 2단의 PC패널(200) 최상단에 배치된 전단연결철근(210)에 역 "U" 자형의 결속철근(200a) 양단을 걸어 결속고정하는 2단 패널조립 철근망 근입 결속단계(S140); 및 2단 패널조립 철근망 근입 결속단계(S140)를 거쳐 형성된 1단과 2단의 마주하는 PC패널(200) 사이이면서 H-파일(100)의 요홈(110) 사이 공간에 대해 1단철근망(300)과 2단철근망(400)이 근입배치된 상태로 현장에서 콘크리트(C)를 타설하여 양생시키는 콘크리트 타설 양생단계(S150)를 포함하되,
1단 패널조립 하부결속단계(S120) 및 2단 패널조립 철근망 근입 결속단계(S140)에 적용되는 1단과 2단의 PC패널(200)은 일 면에 전단연결철근(210)이 다수 개로 상하 및 좌우로 일정간격을 가지고 고리 형으로 돌출형성되되 일 면 사방의 모서리 부분에 "ㄴ"자 형상으로 이음철근(250)이 더 돌출형성되는 한편,
1단 패널조립 하부결속단계(S120), 1단 철근망 근입 상부결속단계(S130), 2단 패널조립 철근망 근입 결속단계(S140)에서의 1단철근망(300)의 근입 이전과 이후 및 2단철근망(400)의 근입 이전과 이후에는 PC패널(200)에 대한 홈 바닥면(10) 길이방향으로 연이어져 이웃하는 4개의 이음철근(250)에 대해 "ㅁ"자 형상으로 H-파일의 둘레를 함께 감싸면서 이음결속철근(200b)으로 결속시키는 이음매 보강 결속단계가 더 진행되는 것을 특징으로 하는 방음벽 기초의 시공방법.
To install the soundproof wall foundation, a certain length from the top of the H-pile 100 with a predetermined interval in the longitudinal direction of the groove bottom surface 10 recessed through excavation work to protrude upward from the groove bottom surface 10 H-pile (100) by driving and fixing the digging pile fixing step (S110); The shear connecting reinforcing bar ( The PC panel 200 is seated and installed so that the protruding side 210 faces the protruding side, but the PC panel 200 is seated and installed so that the PC panel 200 is sequentially engaged and assembled in the longitudinal direction of the groove bottom surface 10, while the facing PC panel 200 ) one-stage panel assembly lower binding step (S120) of fastening both ends of the inverted "U"-shaped binding reinforcing bar 200a to the shear connecting reinforcing bar 210 disposed at the lowermost end of the unit; After inserting the single-stage reinforcing bar network 300 into the space between the facing one-stage PC panels 200 and the space between the grooves 110 of the H-pillar 100 facing each other, the facing one-stage PC panel ( 200) an upper binding step (S130) of attaching both ends of the inverted "U"-shaped binding reinforcement 200a to the shear connection reinforcement 210 disposed at the uppermost stage and fixing the binding; It proceeds after the upper binding step (S130) of the one-stage reinforcing bar network, so that the upper end of the two-stage PC panel 200 and the upper end of the H-pillar 100 coincide with the second stage on the upper part of the PC panel 200 of the first stage 2 The PC panel 200 of one stage is seated and installed, and both ends of the inverted "U"-shaped binding reinforcing bar 200a are hung on the shear connecting reinforcing bar 210 disposed at the lowermost end of the PC panel 200 of the two tiers facing each other, and the binding is fixed. , The top of a plurality of anchor bolts 410 upward in the longitudinal direction with respect to the space between the two-stage PC panel 200 and the space between the grooves 110 of the H-pile 100 facing each other protrudes a certain length After reinforcing the two-stage reinforcing bar network 400 fixed by welding, both ends of the inverted "U"-shaped binding reinforcing bar 200a are applied to the shear connecting reinforcing bar 210 disposed on the uppermost end of the two-stage PC panel 200 facing each other. A two-stage panel assembly reinforcing bar network rooting and binding step (S140) of hanging and fixing; And for the space between the groove 110 of the H-pile 100 and between the PC panel 200 facing the first and second stages formed through the two-stage panel assembly reinforcing bar network reinforcing and binding step (S140), the single-stage reinforcing bar network ( 300) and a concrete pouring curing step (S150) of pouring and curing the concrete (C) at the site in a state in which the two-stage reinforcing bar network 400 is placed in a reinforcing position,
The 1st and 2nd stage PC panel 200 applied to the 1st panel assembly lower binding step (S120) and the 2nd panel assembly rebar network reinforcing bar binding step (S140) has a plurality of shear connecting reinforcing bars 210 on one side. And the joint reinforcement 250 is formed to protrude in an annular shape with a predetermined interval from side to side, and the joint reinforcing bar 250 is further protruded in a “L” shape at the corners of one side of the four sides,
Before and after the reinforcing and Before and after the reinforcing of the two-stage reinforcing bar network 400, it is connected in the longitudinal direction of the groove bottom surface 10 for the PC panel 200 in a "ㅁ" shape for the four adjacent reinforcing bars 250. The construction method of the soundproof wall foundation, characterized in that the joint reinforcement binding step of binding the joint with the joint binding reinforcing bar (200b) is further carried out while surrounding the perimeter of the pile together.
제1항에 있어서,
콘크리트 타설 양생단계(S150) 이후에 진행되며, 타설 양생된 콘크리트(C) 상부로서 2단의 마주하는 PC패널(200) 사이에 대한 길이방향으로 일정간격을 가지고 각각 다수 개로 돌출된 앵커볼트(410) 상단에 방음벽지주(510)의 하단을 앵커너트를 적용하여 고정설치하는 방음벽지주설치단계(S160) 및
방음벽지주설치단계(S160) 이후에 진행되며, 방음벽지주설치단계(S160)를 거쳐 설치된 방음벽지주(510)의 사이마다 각각 다수의 방음판(520)을 적층 설치하는 방음판 설치단계(S170)를 더 포함하여 이루어지는 것을 특징으로 하는 방음벽 기초의 시공방법.
According to claim 1,
It proceeds after the concrete pouring curing step (S150), and as the upper part of the pouring cured concrete (C), a plurality of anchor bolts 410 protruding at regular intervals in the longitudinal direction between the PC panels 200 facing two stages. ) A soundproofing wall post installation step (S160) of fixing and installing the lower end of the soundproofing wallpost 510 on the upper end by applying an anchor nut, and
It proceeds after the soundproofing wall post installation step (S160), and a soundproofing plate installation step (S170) of stacking and installing a plurality of soundproofing plates 520, respectively, between each of the soundproofing wall posts 510 installed through the soundproofing wall post installation step (S160). Construction method of soundproof wall foundation, characterized in that made by.
삭제delete 제1항에 있어서,
2단 패널조립 철근망 근입 결속단계(S140)에서 2단의 PC패널(200) 상단과 H-파일(100) 상단이 일치할 수 있도록,
1단 패널조립 하부결속단계(S120) 및 2단 패널조립 철근망 근입 결속단계(S140)에 적용되는 1단과 2단의 PC패널(200)은 상하방향 길이에 대해, 터파기 파일고정단계(S110)에서의 홈 바닥면(10)으로부터 상향 돌출토록 고정된 H-파일(100)의 돌출된 길이의 1/2 길이인 패널로 적용되는 것을 특징으로 하는 방음벽 기초의 시공방법.
According to claim 1,
In the two-stage panel assembly rebar network rooting and binding step (S140), the upper end of the two-stage PC panel 200 and the upper end of the H-file 100 can match,
The first and second stages of the PC panel 200 applied to the one-stage panel assembly lower binding step (S120) and the two-stage panel assembly rebar network reinforcing binding step (S140) are for the vertical length, the dug pile fixing step (S110) ) The construction method of the soundproof wall foundation, characterized in that it is applied as a panel having a length of 1/2 of the protruding length of the H-pile 100 fixed to protrude upward from the groove bottom surface 10 in the .
제1항에 있어서,
방음벽 기초의 하단부분에 대해 일정길이만큼이 견고하게 고정될 수 있도록,
1단 철근망 근입 상부결속단계(S120) 이후에는 터파기 파일고정단계(S110)에서의 터파기 작업을 통해 함몰 형성된 홈 바닥면(10)의 상부 공간 중에서, 1단의 PC패널(200) 마주하는 사이 반대 측 공간에 대해 흙 채움을 통해 1단의 PC패널(200) 외부를 지중에 매립시키는 1단 패널매립 과정이 더 진행되는 것을 특징으로 하는 방음벽 기초의 시공방법.
According to claim 1,
so that it can be firmly fixed for a certain length to the lower part of the soundproof wall foundation,
After the upper binding step (S120) of the one-stage reinforcing bar network rooting, in the upper space of the groove bottom surface 10 that is recessed through the excavation work in the excavation pile fixing step (S110), the one-stage PC panel 200 faces A construction method of a soundproof wall foundation, characterized in that the one-stage panel embedding process of embedding the outside of the one-stage PC panel 200 in the ground through soil filling for the space on the opposite side during the process is further carried out.
제1항 내지 제2항 및 제4항 내지 제5항 중 어느 한 항에 따른 방음벽 기초의 시공방법에 의해 시공되는 것을 특징으로 하는 방음벽 기초의 시공방법에 의해 시공된 방음벽 기초.
A soundproof wall foundation constructed by the soundproof wall foundation construction method, characterized in that it is constructed by the soundproof wall foundation construction method according to any one of claims 1 to 2 and 4 to 5.
KR1020210166929A 2021-11-29 2021-11-29 Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same KR102464866B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210166929A KR102464866B1 (en) 2021-11-29 2021-11-29 Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210166929A KR102464866B1 (en) 2021-11-29 2021-11-29 Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same

Publications (1)

Publication Number Publication Date
KR102464866B1 true KR102464866B1 (en) 2022-11-09

Family

ID=84040306

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210166929A KR102464866B1 (en) 2021-11-29 2021-11-29 Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same

Country Status (1)

Country Link
KR (1) KR102464866B1 (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040076516A (en) * 2003-02-26 2004-09-01 전대우 Mold-Reinforcing Rod One Body Type Precast Concrete Pannel and Fabrication Structure of The Same
KR101036507B1 (en) 2010-12-13 2011-05-24 (주) 태평양지질 Soundproof wall base structure and it's constructing method
KR20120062184A (en) 2010-12-06 2012-06-14 (주) 태평양지질 Noise barrier base structure with a function of stiffness reinforcement using micro pile and the method for constructing thereof
KR20130017518A (en) * 2011-08-11 2013-02-20 (주)한맥기술 Soundproof walls basis structure and soundproof walls manufacturing method
KR101581938B1 (en) 2014-02-28 2015-12-31 고려개발 주식회사 The noise barrier foundation and its construction method
KR101732716B1 (en) 2016-08-09 2017-05-04 이승희 Soundproofing wall foundation and method for constructing this same
KR101947038B1 (en) 2017-09-29 2019-02-12 한국콘크리트산업 주식회사 Vertical wall type soundproof wall foundation construction
KR102186472B1 (en) 2019-06-24 2020-12-03 주식회사 케이씨산업 Base structure for soundproof wall of roadway
JP2020197015A (en) * 2019-05-31 2020-12-10 株式会社安藤・間 Construction method of foundation
KR102197072B1 (en) 2020-08-20 2020-12-30 (주)국성건설엔지니어링 Soundproof wall foundation structure and soundproof wall construction method using same

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040076516A (en) * 2003-02-26 2004-09-01 전대우 Mold-Reinforcing Rod One Body Type Precast Concrete Pannel and Fabrication Structure of The Same
KR20120062184A (en) 2010-12-06 2012-06-14 (주) 태평양지질 Noise barrier base structure with a function of stiffness reinforcement using micro pile and the method for constructing thereof
KR101036507B1 (en) 2010-12-13 2011-05-24 (주) 태평양지질 Soundproof wall base structure and it's constructing method
KR20130017518A (en) * 2011-08-11 2013-02-20 (주)한맥기술 Soundproof walls basis structure and soundproof walls manufacturing method
KR101581938B1 (en) 2014-02-28 2015-12-31 고려개발 주식회사 The noise barrier foundation and its construction method
KR101732716B1 (en) 2016-08-09 2017-05-04 이승희 Soundproofing wall foundation and method for constructing this same
KR101947038B1 (en) 2017-09-29 2019-02-12 한국콘크리트산업 주식회사 Vertical wall type soundproof wall foundation construction
JP2020197015A (en) * 2019-05-31 2020-12-10 株式会社安藤・間 Construction method of foundation
KR102186472B1 (en) 2019-06-24 2020-12-03 주식회사 케이씨산업 Base structure for soundproof wall of roadway
KR102197072B1 (en) 2020-08-20 2020-12-30 (주)국성건설엔지니어링 Soundproof wall foundation structure and soundproof wall construction method using same

Similar Documents

Publication Publication Date Title
KR100495782B1 (en) A Facing panel for reinforced earth wall and its construction method
KR101344063B1 (en) The construction method of steel-concrete underpass
US20080104909A1 (en) Modoular Wall System with Footing Form
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
JP4060323B2 (en) Bracket support type downward frame driving system and downward frame driving method using the same
KR20090094971A (en) Under ground top-down method
KR100938395B1 (en) The Construction Method of Underpass using Steel-Concrete Composite Wall Pile
KR101221970B1 (en) Construction Method for Basement Structure without Temporary Structure
KR101780370B1 (en) Composite structure using shear connector made of anchor and socket shoe
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
KR101051978B1 (en) Basement structure construction method using PC member
KR100650411B1 (en) Tunnel cover plate
JP3690437B2 (en) Seismic reinforcement structure for existing buildings
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR102464866B1 (en) Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same
JP6368584B2 (en) Foundation construction method
KR102386348B1 (en) Girder installed strengthen and space cap device
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
KR101736009B1 (en) Top-Down Construction Method For Underground Structure
KR102482691B1 (en) Foundation structures using strut-tie reinforcement and its construction method
JP2021001453A (en) Top plate construction method of vertical shaft and top plate structure
JPS63280153A (en) Underground inverted lining method
KR20090042395A (en) Retainning wall and its construction method
KR102386349B1 (en) Girder installed precast panel

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant