KR102268423B1 - Precaste Bridge - Google Patents

Precaste Bridge Download PDF

Info

Publication number
KR102268423B1
KR102268423B1 KR1020190030370A KR20190030370A KR102268423B1 KR 102268423 B1 KR102268423 B1 KR 102268423B1 KR 1020190030370 A KR1020190030370 A KR 1020190030370A KR 20190030370 A KR20190030370 A KR 20190030370A KR 102268423 B1 KR102268423 B1 KR 102268423B1
Authority
KR
South Korea
Prior art keywords
precast
fixing
steel pipe
tension member
precast girder
Prior art date
Application number
KR1020190030370A
Other languages
Korean (ko)
Other versions
KR20200110892A (en
Inventor
김태식
Original Assignee
김태식
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김태식 filed Critical 김태식
Priority to KR1020190030370A priority Critical patent/KR102268423B1/en
Publication of KR20200110892A publication Critical patent/KR20200110892A/en
Application granted granted Critical
Publication of KR102268423B1 publication Critical patent/KR102268423B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

본 발명에 따르면, 강관 기초(100); 상기 강관 기초(100) 상부에 거치된 하부 프리캐스트 거더(200); 및 상기 하부 프리캐스트 거더(200) 상부에 거치된 상부 프리캐스트 거더(300);를 포함하되, 상기 강관 기초(100)와 상기 하부 프리캐스트 거더(200)를 결합시키는 하부 긴장재(410); 및 상기 하부 프리캐스트 거더(200)와 상기 상부 프리캐스트 거더(300)를 결합시키는 상부 긴장재(420);를 포함하는 것을 특징으로 하는 프리캐스트 교량이 제공된다.
본 발명에 따르면, 현장시공을 최소화하여 프리캐스트 교량을 간이하고 단기간에 시공할 수 있는 효과가 있다.
According to the present invention, the steel pipe foundation 100; a lower precast girder 200 mounted on the steel pipe foundation 100; and an upper precast girder 300 mounted on the lower precast girder 200; a lower tension member 410 for coupling the steel pipe foundation 100 and the lower precast girder 200 to each other; and an upper tension member 420 for coupling the lower precast girder 200 and the upper precast girder 300 to each other.
According to the present invention, there is an effect that the precast bridge can be constructed in a short period of time by minimizing on-site construction.

Description

프리캐스트 교량 및 이를 이용한 교량의 시공방법{Precaste Bridge}Precast bridge and construction method of bridge using same {Precaste Bridge}

본 발명은 토목, 건축분야에 관한 것으로서 프리캐스트 교량에 관한 것이다. 보다 상세하게는 강관 기초 및 프리캐스트 거더를 이용하여 교량을 쉽게 시공할 수 있도록 한 것으로서, 현장 시공의 난이도를 낮추면서도 교량의 구조적 안전성을 확보할 수 있도록 한 프리캐스트 교량 및 이를 이용한 교량의 시공방법에 관한 것이다. The present invention relates to the field of civil engineering and construction, and to a precast bridge. More specifically, a precast bridge and a bridge construction method using the steel pipe foundation and precast girder to facilitate the construction of the bridge, and to ensure the structural safety of the bridge while lowering the difficulty of on-site construction. is about

산이나 하천 상의 상부에 시공되는 산책로 등의 소규모 교량의 시공을 위해 프리캐스트 방식으로 제조된 거더를 기초 상부에 축조하는 방식이 사용되고 있다.For the construction of small-scale bridges such as walkways constructed on the upper part of a mountain or river, a method of constructing a girder manufactured by a precast method on the upper part of the foundation is used.

다만, 종래에 제시되었던 프리캐스트 콘크리트 거더 교량은 장경간 교량의 시공을 위한 기술 발명이 주를 이루었고, 큰 사용 하중을 고려하지 않고 단기간에 시공을 완료할 수 있는 소규모 교량을 위한 기술은 전무한 실정이다. However, in the conventionally presented precast concrete girder bridge, the invention of technology for the construction of long-span bridges was mainly, and there is no technology for small-scale bridges that can be completed in a short period of time without considering the large use load. .

종래의 프리캐스트 교량의 시공방법에 관한 선행기술의 목록은 이하와 같다. The list of prior art related to the construction method of the conventional precast bridge is as follows.

-대한민국 등록특허 10-1283535-Korea Registered Patent 10-1283535

-대한민국 등록특허 10-1546951-Korea Registered Patent 10-1546951

-대한민국 등록특허 10-0500382-Korea Registered Patent 10-0500382

본 발명의 목적은 상술된 바와 같이 종래 기술에서는 고려되지 않았던 소규모 교량의 시공을 위한 프리캐스트 공법으로 도출된 것으로서 본 발명의 목적은 시공이 간이하고 단기간에 시공을 완료할 수 있는 프리캐스트 교량 및 이를 이용한 교량의 시공방법에 관한 것이다. As described above, the object of the present invention is as a precast method for the construction of a small-scale bridge that has not been considered in the prior art, and an object of the present invention is to provide a precast bridge that is easy to construct and can be completed in a short period of time, and It relates to the construction method of the used bridge.

본 발명의 다른 목적은 긴장재를 이용한 각 부재의 결합을 통해 시공의 간이성 및 구조적 안전성을 확보할 수 있는 프리캐스트 교량 및 이를 이용한 교량의 시공방법에 관한 것이다. Another object of the present invention relates to a precast bridge capable of securing the simplicity of construction and structural safety through the coupling of each member using a tension member, and a construction method of the bridge using the same.

본 발명의 일 측면에 따르면, 강관 기초(100); 상기 강관 기초(100) 상부에 거치된 하부 프리캐스트 거더(200); 및 상기 하부 프리캐스트 거더(200) 상부에 거치된 상부 프리캐스트 거더(300);를 포함하되, 상기 강관 기초(100)와 상기 하부 프리캐스트 거더(200)를 결합시키는 하부 긴장재(410); 및 상기 하부 프리캐스트 거더(200)와 상기 상부 프리캐스트 거더(300)를 결합시키는 상부 긴장재(420);를 포함하는 것을 특징으로 하는 프리캐스트 교량이 제공된다. According to one aspect of the invention, the steel pipe foundation 100; a lower precast girder 200 mounted on the steel pipe foundation 100; and an upper precast girder 300 mounted on the lower precast girder 200; a lower tension member 410 for coupling the steel pipe foundation 100 and the lower precast girder 200 to each other; and an upper tension member 420 for coupling the lower precast girder 200 and the upper precast girder 300 to each other.

이 경우 상기 하부 프리캐스트 거더(200)의 하면에는 상기 강관 기초(100)의 두부가 인입되는 거치홈(210)이 형성되며, 상기 하부 프리캐스트 거더(200)에는 상기 하부 긴장재(410)가 인입되는 제1 관통홀(220)이 형성되고, 상기 하부 프리캐스트 거더(200)의 상면에는 상기 제1 관통홀(220)을 통해 인입된 상기 하부 긴장재(410)의 두부가 정착되는 제1 정착홈(230)이 형성된 것을 특징으로 하는 프리캐스트 교량일 수 있다. In this case, a mounting groove 210 into which the head of the steel pipe foundation 100 is introduced is formed on the lower surface of the lower precast girder 200 , and the lower tension member 410 is introduced into the lower precast girder 200 . A first through hole 220 is formed, and the upper surface of the lower precast girder 200 has a first fixing groove in which the head of the lower tension member 410 introduced through the first through hole 220 is fixed. It may be a precast bridge, characterized in that 230 is formed.

또한, 상기 상부 프리캐스트 거더(300)에는 상기 상부 긴장재(420)가 인입되는 제2 관통홀(310)이 형성되며, 상기 상부 프래캐스트 거더(300)의 상면에는 상기 제2 관통홀(310)을 통해 인입된 상기 상부 긴장재(420)의 두부가 정착되는 제2 정착홈(320)이 형성된 것을 특징으로 하는 프리캐스트 교량일 수 있다. In addition, a second through hole 310 through which the upper tension member 420 is introduced is formed in the upper precast girder 300 , and the second through hole 310 is formed in the upper surface of the upper precast girder 300 . It may be a precast bridge, characterized in that the second fixing groove 320 in which the head of the upper tension member 420 introduced through the is fixed is formed.

또한, 상기 상부 프리캐스트 거더(300)의 하면에는 상부를 향해 함몰된 작업홈(330)이 형성되되,상기 작업홈(330)은 상기 제1 정착홈(230)에 대응되는 위치에 형성된 것을 특징으로 하는 프리캐스트 교량일 수 있다. In addition, the lower surface of the upper precast girder 300 is formed with a working groove 330 recessed toward the top, wherein the working groove 330 is formed in a position corresponding to the first fixing groove (230) It may be a precast bridge with

본 발명의 다른 일 측면에 따르면, 상기 강관 기초(100)를 형성하는 제1 단계(S100); 상기 강관 기초(100)의 중공(110)에 콘크리트 타설용 플레이트(500)를 설치하는 제2 단계(S200); 상기 중공(110)에 콘크리트를 타설함과 아울러, 상기 하부 긴장재(410)의 하단을 상기 중공(110)에 타설되는 콘크리트에 매설하는 제3 단계(S300); 및 상기 하부 프리캐스트 거더(200)를 상기 강관 기초(100) 상부에 거치시킴과 아울러, 상기 하부 긴장재(410)의 두부를 상기 제1 정착홈(230)에 정착시키는 제4 단계(S400);를 포함하되, 상기 하부 프리캐스트 거더(200)에는 상기 상부 긴장재(420)의 하단이 매설된 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법이 제공된다. According to another aspect of the present invention, the first step of forming the steel pipe foundation 100 (S100); a second step (S200) of installing a plate 500 for concrete pouring in the hollow 110 of the steel pipe foundation 100; A third step (S300) of pouring concrete into the hollow 110 and embedding the lower end of the lower tension member 410 in the concrete to be poured into the hollow 110; and a fourth step of mounting the lower precast girder 200 on the steel pipe foundation 100 and fixing the head of the lower tension member 410 in the first fixing groove 230 (S400); However, there is provided a method of constructing a precast bridge, characterized in that the lower end of the upper tension member 420 is buried in the lower precast girder 200 .

이 경우 상기 콘크리트 타설용 플레이트(500)는, 상기 중공(110)에 타설되는 콘크리트의 하부 거푸집으로 사용되는 플레이트 부재(510); 및 상기 플레이트 부재(510)를 상기 중공(110)의 소정의 위치에 고정시키는 고정부재(520);를 포함하되, 상기 고정부재(520)는 일단은 상기 플레이트 부재(510)와 결합되며, 타단은 상기 강관 기초(100)의 상단에 결합되는 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법일 수 있다. In this case, the plate for concrete pouring 500 includes a plate member 510 used as a lower formwork for concrete to be poured into the hollow 110; and a fixing member 520 for fixing the plate member 510 to a predetermined position in the hollow 110, wherein one end of the fixing member 520 is coupled to the plate member 510 and the other end may be a method of constructing a precast bridge characterized in that it is coupled to the upper end of the steel pipe foundation 100 .

또한 ,상기 고정부재(520)의 타단은 상기 강관 기초(100)의 상단에 거치되는 갈고리인 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법일 수 있다. In addition, the other end of the fixing member 520 may be a method of constructing a precast bridge, characterized in that the hook mounted on the upper end of the steel pipe foundation (100).

또한, 상기 제3 단계(S300)는, 상기 하부 긴장재(410)의 상단의 위치를 고정하는 위치 고정 캡(600)을 상기 강관 기초(100) 상부에 설치하는 위치 고정 캡 설치 단계(S310); 및 상기 중공(110)에 타설된 콘크리트의 양생이 완료된 이후 상기 위치 고정 캡(600)을 제거하는 위치 고정 캡 제거 단계(S320);를 포함하는 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법일 수 있다. In addition, the third step (S300), a position fixing cap installation step (S310) of installing a position fixing cap 600 for fixing the position of the upper end of the lower tension member 410 on the steel pipe foundation 100; and a position fixing cap removal step (S320) of removing the position fixing cap 600 after curing of the concrete poured into the hollow 110 is completed (S320); It can be a method of constructing a precast bridge comprising a; have.

또한, 상기 위치 고정 캡(600)은 상기 강관 기초(100) 상부에 고정되는 본체(610); 및 상기 하부 긴장재(410)의 상단의 위치를 고정하는 위치고정부(620);를 포함하되, 상기 위치고정부(620)는 상기 본체(610) 상면에 형성된 격자형 플레이트(621); 및 상기 격자형 플레이트(621)를 관통한 상기 하부 긴장재(410)의 상단을 구속하는 구속부재(622);를 포함하는 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법일 수 있다. In addition, the position fixing cap 600 is a body 610 fixed to the top of the steel pipe foundation 100; And a position fixing part 620 for fixing the position of the upper end of the lower tension member 410; including, wherein the position fixing part 620 is a grid-type plate 621 formed on the upper surface of the main body 610; and a restraining member 622 for restraining the upper end of the lower tension member 410 passing through the grid plate 621; it may be a method of constructing a precast bridge comprising a.

또한, 상기 상부 프리캐스트 거더(300)를 상기 하부 프리캐스트 거더(200)의 상부에 거치시킴과 아울러, 상기 상부 긴장재(420)의 두부를 상기 제2 정착홈(320)에 정착시키는 제5 단계(S500);를 더 포함하는 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법일 수 있다. In addition, a fifth step of mounting the upper precast girder 300 on the upper part of the lower precast girder 200 and fixing the head of the upper tension member 420 in the second fixing groove 320 . (S500); may be a method of constructing a precast bridge, characterized in that it further comprises.

본 발명에 따르면, 현장시공을 최소화하여 프리캐스트 교량을 간이하고 단기간에 시공할 수 있는 효과가 있다. According to the present invention, there is an effect that the precast bridge can be constructed in a short period of time by minimizing on-site construction.

본 발명에 따르면, 긴장재를 이용한 각 부재의 결합을 통해 프리캐스트 교량 시공의 간이성 및 구조적 안전성을 확보할 수 있는 효과가 있다. According to the present invention, there is an effect that can secure the simplicity and structural safety of the precast bridge construction through the coupling of each member using the tension member.

도 1은 본 발명의 일 실시예에 따른 프리캐스트 교량의 횡단면도.
도 2는 본 발명의 다른 일 실시예에 다른 프리캐스트 교량의 횡단면도.
도 3 내지 도 12는 본 발명의 일 실시예에 따른 프리캐스트 교량의 시공방법을 나타낸 도면.
도 13은 본 발명의 일 실시예에 따른 프리캐스트 교량의 시공방법에 있어 하부 긴장재의 콘크리트 양생시 위치 고정 방법을 나타낸 도면.
도 14는 본 발명의 일 실시예에 다른 위치 고정 캡의 구조를 나타낸 도면.
도 15는 본 발명의 일 실시예에 따른 콘크리트 타설용 플레이트의 설치 방법을 나타낸 도면.
1 is a cross-sectional view of a precast bridge according to an embodiment of the present invention.
Figure 2 is a cross-sectional view of a precast bridge according to another embodiment of the present invention.
3 to 12 are views showing a construction method of a precast bridge according to an embodiment of the present invention.
13 is a view showing a method of fixing the position of the lower tension member during concrete curing in the construction method of the precast bridge according to an embodiment of the present invention.
14 is a view showing the structure of a position fixing cap according to an embodiment of the present invention.
15 is a view showing a method of installing a plate for pouring concrete according to an embodiment of the present invention.

본 발명에 따른 프리캐스트 교량 및 이를 이용한 교량의 시공방법의 실시예를 첨부도면을 참조하여 상세히 설명하기로 하며, 첨부 도면을 참조하여 설명함에 있어, 동일하거나 대응하는 구성 요소는 동일한 도면 번호를 부여하고 이에 대한 중복되는 설명은 생략하기로 한다.An embodiment of the precast bridge according to the present invention and the construction method of the bridge using the same will be described in detail with reference to the accompanying drawings, and in the description with reference to the accompanying drawings, the same or corresponding components are given the same drawing numbers and a redundant description thereof will be omitted.

또한, 이하 사용되는 제1, 제2 등과 같은 용어는 동일 또는 상응하는 구성 요소들을 구별하기 위한 식별 기호에 불과하며, 동일 또는 상응하는 구성 요소들이 제1, 제2 등의 용어에 의하여 한정되는 것은 아니다.In addition, terms such as first, second, etc. used below are merely identification symbols for distinguishing the same or corresponding components, and the same or corresponding components are limited by terms such as first, second, etc. no.

또한, 결합이라 함은, 각 구성 요소 간의 접촉 관계에 있어, 각 구성 요소 간에 물리적으로 직접 접촉되는 경우만을 뜻하는 것이 아니라, 다른 구성이 각 구성 요소 사이에 개재되어, 그 다른 구성에 구성 요소가 각각 접촉되어 있는 경우까지 포괄하는 개념으로 사용하도록 한다.In addition, in the contact relationship between each component, the term "coupling" does not mean only the case where each component is in direct physical contact with each other, but another component is interposed between each component, so that the component is in the other component. It should be used as a concept that encompasses even the cases in which each is in contact.

본 발명은 프리캐스트 교량 및 이를 이용한 교량의 시공방법에 관한 것이다. The present invention relates to a precast bridge and a method of constructing a bridge using the same.

본 발명의 일 실시예에 따른 프리캐스트 교량은 강관 기초(100), 강관 기초(100) 상부에 거치된 하부 프리캐스트 거더(200) 및 하부 프리캐스트 거더(200) 상부에 거치된 상부 프리캐스트 거더(300)를 포함한다(도 1). The precast bridge according to an embodiment of the present invention is a steel pipe foundation 100, a lower precast girder 200 mounted on the steel pipe foundation 100, and an upper precast girder mounted on the lower precast girder 200. 300 (FIG. 1).

강관 기초(100)는 중공관 형태의 강재 기둥으로 형성된다. The steel pipe foundation 100 is formed of a hollow tube-shaped steel column.

또한 본 발명의 일 실시예에 따른 프리캐스트 교량은 강관 기초(100)와 상기 하부 프리캐스트 거더(200)를 결합시키는 하부 긴장재(410) 및 하부 프리캐스트 거더(200)와 상부 프리캐스트 거더(300)를 결합시키는 상부 긴장재(420)를 더 포함할 수 있다. In addition, the precast bridge according to an embodiment of the present invention has a lower tension member 410 and a lower precast girder 200 and an upper precast girder 300 for coupling the steel pipe foundation 100 and the lower precast girder 200 . ) may further include an upper tension member 420 for coupling.

상부 긴장재(420) 및 하부 긴장재(410)는 복수의 강선 또는 강봉으로 이루어지며, 프리캐스트 거더와 강관 기초(100)에 결합력을 제공한다. The upper tension member 420 and the lower tension member 410 are made of a plurality of steel wires or rods, and provide a bonding force to the precast girder and the steel pipe foundation 100 .

본 발명의 일 실시예에 따른 프리캐스트 교량의 하부 프리캐스트 거더(200)의 하면에는 강관 기초(100)의 두부가 인입되는 거치홈(210)이 형성된다(도 1). On the lower surface of the lower precast girder 200 of the precast bridge according to an embodiment of the present invention, a mounting groove 210 into which the head of the steel pipe foundation 100 is introduced is formed (FIG. 1).

이에 따라 프리캐스트 교량의 시공에 있어 강관 기초(100) 상부에 하부 프리캐스트 거더(200)의 거치 작업을 용이하게 수행할 수 있다. Accordingly, it is possible to easily perform the installation of the lower precast girder 200 on the steel pipe foundation 100 in the construction of the precast bridge.

또한, 하부 프리캐스트 거더(200)에는 하부 긴장재(410)가 인입되는 제1 관통홀(220)이 형성되고, 하부 프리캐스트 거더(200)의 상면에는 제1 관통홀(220)을 통해 인입된 하부 긴장재(410)의 두부가 정착되는 제1 정착홈(230)이 형성될 수 있다(도 1). In addition, the lower precast girder 200 is formed with a first through hole 220 through which the lower tension member 410 is introduced, and the upper surface of the lower precast girder 200 is introduced through the first through hole 220 . A first fixing groove 230 in which the head of the lower tension member 410 is fixed may be formed (FIG. 1).

이에 더하여, 상부 프리캐스트 거더(300)에는 상부 긴장재(420)가 인입되는 제2 관통홀(310)이 형성되며, 상부 프래캐스트 거더(300)의 상면에는 제2 관통홀(310)을 통해 인입된 상부 긴장재(420)의 두부가 정착되는 제2 정착홈(320)이 형성될 수 있다(도 1). In addition, a second through hole 310 through which the upper tension member 420 is introduced is formed in the upper precast girder 300 , and the upper surface of the upper precast girder 300 is introduced through the second through hole 310 . A second fixing groove 320 in which the head of the upper tension member 420 is fixed may be formed (FIG. 1).

이에 따라 선 제작된 하부 프리캐스트 거더(200) 및 상부 프리캐스트 거더(300)를 적층하고 하부 긴장재(410) 및 상부 긴장재(420)를 긴장하여 정착시키는 것 만으로 교량의 시공을 완료할 수 있다. Accordingly, the construction of the bridge can be completed only by stacking the pre-fabricated lower precast girder 200 and the upper precast girder 300 and fixing the lower tension member 410 and the upper tension member 420 by tension.

정착 작업이 완료된 이후 제1 정착홈(230) 및 제2 정착홈(320)은 마감 콘크리트에 의해 충전된다. After the fixing operation is completed, the first fixing groove 230 and the second fixing groove 320 are filled with the finished concrete.

마감 콘크리트는 무수축 콘크리트를 사용하는 것이 바람직하다. It is preferable to use non-shrinkable concrete as the finishing concrete.

본 발명의 일 실시예에 따른 프리캐스트 교량의 상부 프리캐스트 거더(300)의 하면에는 상부를 향해 함몰된 작업홈(330)이 형성되되, 작업홈(330)은 제1 정착홈(230)에 대응되는 위치에 형성될 수 있다(도 1). On the lower surface of the upper precast girder 300 of the precast bridge according to an embodiment of the present invention, a working groove 330 recessed toward the top is formed, and the working groove 330 is in the first fixing groove 230 . It may be formed at a corresponding position (FIG. 1).

이에 따라 시공 후 교량의 유지 보수 작업을 파괴 작업 없이 원활하게 수행할 수 있다. Accordingly, the maintenance work of the bridge after construction can be performed smoothly without destructive work.

관리자는 작업홈(330)에 의해 형성된 공간을 이용하여 하부 긴장재(410)의 긴장 상태 및 하부 긴장재(410)가 정착된 제1 정착홈(230)을 채우는 마감 콘크리트의 마감 상황을 용이하게 체크하여 교량 관리에 필요한 유지 보수 계획을 수립할 수 있다. The manager uses the space formed by the work groove 330 to easily check the tension state of the lower tension material 410 and the finishing condition of the finished concrete filling the first anchoring groove 230 in which the lower tension material 410 is fixed. It is possible to establish a maintenance plan necessary for bridge management.

이하 본 발명의 일 실시예에 따른 프리캐스트 교량을 시공하는 방법에 대해 설명한다. Hereinafter, a method for constructing a precast bridge according to an embodiment of the present invention will be described.

본 발명에 따른 프리캐스트 교량을 시공하는 방법은 강관 기초(100)를 형성하는 제1 단계(S100), 강관 기초(100)의 중공(110)에 콘크리트 타설용 플레이트(500)를 설치하는 제2 단계(S200), 중공(110)에 콘크리트를 타설함과 아울러 하부 긴장재(410)의 하단을 중공(110)에 타설되는 콘크리트에 매설하는 제3 단계(S300), 하부 프리캐스트 거더(200)를 강관 기초(100) 상부에 거치시킴과 아울러 하부 긴장재(410)의 두부를 제1 정착홈(230)에 정착시키는 제4 단계(S400) 및 상부 프리캐스트 거더(300)를 하부 프리캐스트 거더(200)의 상부에 거치시킴과 아울러 상부 긴장재(420)의 두부를 제2 정착홈(320)에 정착시키는 제5 단계(S500)를 포함한다(도 3 내지 도 11). The method of constructing a precast bridge according to the present invention includes a first step (S100) of forming a steel pipe foundation 100, a second step of installing a plate 500 for concrete pouring in the hollow 110 of the steel pipe foundation 100 Step (S200), the third step (S300) of pouring concrete into the hollow 110 and burying the lower end of the lower tension member 410 in the concrete to be poured into the hollow 110, the lower precast girder 200 A fourth step (S400) of fixing the head of the lower tension member 410 to the first fixing groove 230 while mounting the steel pipe foundation 100 on the upper part (S400) and the upper precast girder 300 are mounted on the lower precast girder 200 ) and a fifth step (S500) of fixing the head of the upper tension member 420 to the second fixing groove 320 as well as mounting on the upper part (FIGS. 3 to 11).

이 경우 하부 프리캐스트 거더(200)는 상부 긴장재(420)의 하단이 매설된 상태로 제작된다. In this case, the lower precast girder 200 is manufactured in a state in which the lower end of the upper tension member 420 is embedded.

제2 단계(S200)의 콘크리트 타설용 플레이트(500)는 강관 기초(100)의 중공(110) 상부 공간에만 콘크리트를 타설시키기 위한 부재로서, 중공(110)에 타설되는 콘크리트의 하부 거푸집으로 사용되는 플레이트 부재(510) 및 플레이트 부재(510)를 중공(110)의 소정의 위치에 고정시키는 고정부재(520)를 포함한다(도 4). The plate 500 for concrete pouring of the second step (S200) is a member for pouring concrete only in the upper space of the hollow 110 of the steel pipe foundation 100, and is used as a lower formwork of the concrete poured into the hollow 110. It includes a plate member 510 and a fixing member 520 for fixing the plate member 510 to a predetermined position in the hollow 110 ( FIG. 4 ).

이 경우 고정부재(520)는 일단은 플레이트 부재(510)와 결합되며, 타단은 상기 강관 기초(100)의 상단에 결합된다. 고정부재(520)의 타단은 강관 기초(100)의 상단에 거치되는 갈고리 형상으로 형성될 수 있다. In this case, one end of the fixing member 520 is coupled to the plate member 510 , and the other end is coupled to the top of the steel pipe foundation 100 . The other end of the fixing member 520 may be formed in the shape of a hook mounted on the upper end of the steel pipe foundation (100).

이에 따라 중공(110) 상부의 일정공간에만 콘크리트를 타설시키는 것이 가능하다. Accordingly, it is possible to pour concrete only in a certain space above the hollow 110 .

제3 단계(S300)는 하부 긴장재(410)의 상단의 위치를 고정하는 위치 고정 캡(600)을 강관 기초(100) 상부에 설치하는 위치 고정 캡 설치 단계(S310) 및 중공(110)에 타설된 콘크리트의 양생이 완료된 이후 상기 위치 고정 캡(600)을 제거하는 위치 고정 캡 제거 단계(S320)를 포함할 수 있다. The third step (S300) is a position fixing cap installation step (S310) of installing a position fixing cap 600 for fixing the position of the upper end of the lower tension member 410 on the steel pipe foundation 100, and pouring in the hollow 110 It may include a position fixing cap removal step (S320) of removing the position fixing cap 600 after the curing of the concrete is completed.

중공(110)에 충전된 콘크리트의 양생이 완료되기 전까지는 하부 긴장재(410)가 기립된 상태를 유지할 수 있는 지지력이 제공되지 아니하므로, 위치 고정 캡(600)을 이용하여 하부 긴장재(410)의 기립 상태를 유지할 수 있는 지지력을 제공한다(도 13). Until curing of the concrete filled in the hollow 110 is completed, the lower tension member 410 is not provided with a supporting force to maintain an erected state, so using the position fixing cap 600, the lower tension member 410 of the Provides support for maintaining a standing state (FIG. 13).

위치 고정 캡(600)은 강관 기초(100) 상부에 고정되는 본체(610) 및 하부 긴장재(410)의 상단의 위치를 고정하는 위치고정부(620)를 포함할 수 있다(도 13, 도 14). The position fixing cap 600 may include a position fixing part 620 for fixing the position of the upper end of the main body 610 and the lower tension member 410 fixed to the upper part of the steel pipe foundation 100 ( FIGS. 13 and 14 ). ).

본체(610)는 강관 기초(100)의 외주면을 둘러쌀 수 있는 원통형으로 형성될 수 있다. 본체(610)는 소정의 결합부재를 이용하여 강관 기초(100)에 직접 결합될 수 있으며, 다른 방식으로는 강관 기초(100)의 외면에 형성된 지지부(120) 상부에 거치되어 강관 기초(100)와 결합되는 것도 가능하다. The body 610 may be formed in a cylindrical shape that can surround the outer circumferential surface of the steel pipe base 100 . The body 610 may be directly coupled to the steel pipe foundation 100 using a predetermined coupling member, and in another method is mounted on the support part 120 formed on the outer surface of the steel pipe foundation 100 to the steel pipe foundation 100 . It is also possible to combine with

위치고정부(620)는 본체(610) 상면에 형성된 격자형 플레이트(621) 및 격자형 플레이트(621)를 관통한 하부 긴장재(410)의 상단을 구속하는 구속부재(622)를 포함할 수 있다(도 14). The position fixing unit 620 may include a lattice plate 621 formed on the upper surface of the body 610 and a restraining member 622 for restraining the upper end of the lower tension member 410 penetrating the lattice plate 621 . (Fig. 14).

더하여 위치 고정 캡(600)은 콘크리트 타설 호스가 인입되는 인입홀(630)을 포함할 수 있다. 인입홀(630)은 본체(610) 측부 또는 In addition, the position fixing cap 600 may include an inlet hole 630 through which a concrete pouring hose is introduced. The inlet hole 630 is the main body 610 side

격자형 플레이트(621)를 이용하여 다양한 위치에 형성되는 하부 긴장재(410)의 상단을 고정시키는 것이 가능하다. 즉, 실시예 1 및 실시예 2와 같이 하부 긴장재(410)의 형성 위치를 임의적으로 조절하여 시공되는 교량의 크기에 맞추어 최적의 구조적 안전성을 확보하는 것이 가능하다. It is possible to fix the upper end of the lower tension member 410 formed in various positions by using the lattice plate 621 . That is, it is possible to secure optimal structural safety according to the size of the bridge to be constructed by arbitrarily adjusting the formation position of the lower tension member 410 as in the first and second embodiments.

본 발명의 일 실시예에 따른 프리캐스트 교량을 시공하는 방법은 제5 단계(S500) 이후에 상부 프리캐스트 거더(300) 상부에 난간(700)을 설치하는 제6 단계(S600)를 더 포함할 수 있다(도 12). The method of constructing a precast bridge according to an embodiment of the present invention may further include a sixth step (S600) of installing the handrail 700 on the upper precast girder 300 after the fifth step (S500). can be (Fig. 12).

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above has only been described with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention as noted should not be construed as being limited to the above embodiments, and It will be said that the technical idea and the technical idea with the root are all included in the scope of the present invention.

100: 강관 기초
200 : 하부 프리캐스트 거더
300 : 상부 프리캐스트 거더
400 : 긴장재
500 : 콘크리트 타설용 플레이트
600 : 위치 고정 캡
700 : 난간
100: steel pipe base
200: lower precast girder
300: upper precast girder
400: tension material
500: plate for pouring concrete
600: position fixing cap
700: handrail

Claims (10)

프리캐스트 교량을 시공하는 방법에 있어서,
상기 프리캐스트 교량은
강관 기초(100);
상기 강관 기초(100) 상부에 거치된 하부 프리캐스트 거더(200); 및
상기 하부 프리캐스트 거더(200) 상부에 거치된 상부 프리캐스트 거더(300);를 포함하되,
상기 강관 기초(100)와 상기 하부 프리캐스트 거더(200)를 결합시키는 하부 긴장재(410); 및
상기 하부 프리캐스트 거더(200)와 상기 상부 프리캐스트 거더(300)를 결합시키는 상부 긴장재(420);를 포함하고,
상기 하부 프리캐스트 거더(200)의 하면에는 상기 강관 기초(100)의 두부가 인입되는 거치홈(210)이 형성되며,
상기 하부 프리캐스트 거더(200)에는 상기 하부 긴장재(410)가 인입되는 제1 관통홀(220)이 형성되고,
상기 하부 프리캐스트 거더(200)의 상면에는 상기 제1 관통홀(220)을 통해 인입된 상기 하부 긴장재(410)의 두부가 정착되는 제1 정착홈(230)이 형성되며,
상기 상부 프리캐스트 거더(300)에는 상기 상부 긴장재(420)가 인입되는 제2 관통홀(310)이 형성되며,
상기 상부 프리캐스트 거더(300)의 상면에는 상기 제2 관통홀(310)을 통해 인입된 상기 상부 긴장재(420)의 두부가 정착되는 제2 정착홈(320)이 형성되고,
상기 강관 기초(100)를 형성하는 제1 단계(S100);
상기 강관 기초(100)의 중공(110)에 콘크리트 타설용 플레이트(500)를 설치하는 제2 단계(S200);
상기 중공(110)에 콘크리트를 타설함과 아울러, 상기 하부 긴장재(410)의 하단을 상기 중공(110)에 타설되는 콘크리트에 매설하는 제3 단계(S300); 및
상기 하부 프리캐스트 거더(200)를 상기 강관 기초(100) 상부에 거치시킴과 아울러, 상기 하부 긴장재(410)의 두부를 상기 제1 정착홈(230)에 정착시키는 제4 단계(S400);를 포함하되,
상기 하부 프리캐스트 거더(200)에는 상기 상부 긴장재(420)의 하단이 매설되며,
상기 콘크리트 타설용 플레이트(500)는,
상기 중공(110)에 타설되는 콘크리트의 하부 거푸집으로 사용되는 플레이트 부재(510); 및
상기 플레이트 부재(510)를 상기 중공(110)의 소정의 위치에 고정시키는 고정부재(520);를 포함하되,
상기 고정부재(520)는 일단은 상기 플레이트 부재(510)와 결합되며, 타단은 상기 강관 기초(100)의 상단에 결합되며,
상기 제3 단계(S300)는,
상기 하부 긴장재(410)의 상단의 위치를 고정하는 위치 고정 캡(600)을 상기 강관 기초(100) 상부에 설치하는 위치 고정 캡 설치 단계(S310); 및
상기 중공(110)에 타설된 콘크리트의 양생이 완료된 이후 상기 위치 고정 캡(600)을 제거하는 위치 고정 캡 제거 단계(S320);를 포함하고,
상기 위치 고정 캡(600)은
상기 강관 기초(100) 상부에 고정되는 본체(610); 및
상기 하부 긴장재(410)의 상단의 위치를 고정하는 위치고정부(620);를 포함하되,
상기 위치고정부(620)는
상기 본체(610) 상면에 형성된 격자형 플레이트(621); 및
상기 격자형 플레이트(621)를 관통한 상기 하부 긴장재(410)의 상단을 구속하는 구속부재(622);를
포함하는 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법.
In the method of constructing a precast bridge,
The precast bridge is
steel pipe foundation 100;
a lower precast girder 200 mounted on the steel pipe foundation 100; and
Including; an upper precast girder 300 mounted on the lower precast girder 200
a lower tension member 410 for coupling the steel pipe foundation 100 and the lower precast girder 200; and
Including; and an upper tension member 420 for coupling the lower precast girder 200 and the upper precast girder 300
A mounting groove 210 into which the head of the steel pipe foundation 100 is introduced is formed on the lower surface of the lower precast girder 200,
A first through hole 220 into which the lower tension member 410 is introduced is formed in the lower precast girder 200,
A first fixing groove 230 in which the head of the lower tension member 410 introduced through the first through hole 220 is fixed is formed on the upper surface of the lower precast girder 200,
A second through hole 310 through which the upper tension member 420 is introduced is formed in the upper precast girder 300 ,
A second fixing groove 320 in which the head of the upper tension member 420 introduced through the second through hole 310 is fixed is formed on the upper surface of the upper precast girder 300,
A first step (S100) of forming the steel pipe foundation (100);
a second step (S200) of installing a plate 500 for concrete pouring in the hollow 110 of the steel pipe foundation 100;
A third step (S300) of pouring concrete into the hollow 110 and embedding the lower end of the lower tension member 410 in the concrete to be poured into the hollow 110; and
A fourth step (S400) of mounting the lower precast girder 200 on the steel pipe foundation 100 and fixing the head of the lower tension member 410 in the first fixing groove 230; including,
The lower end of the upper tension member 420 is embedded in the lower precast girder 200,
The plate 500 for pouring concrete,
a plate member 510 used as a lower formwork of concrete to be poured into the hollow 110; and
A fixing member 520 for fixing the plate member 510 to a predetermined position in the hollow 110; including,
One end of the fixing member 520 is coupled to the plate member 510, and the other end is coupled to the top of the steel pipe foundation 100,
The third step (S300) is,
A position fixing cap installation step (S310) of installing a position fixing cap 600 for fixing the position of the upper end of the lower tension member 410 on the steel pipe foundation 100; and
and a position fixing cap removal step (S320) of removing the position fixing cap 600 after curing of the concrete poured into the hollow 110 is completed;
The position fixing cap 600 is
a body 610 fixed to the top of the steel pipe foundation 100; and
A position fixing part 620 for fixing the position of the upper end of the lower tension member 410; including,
The position fixing unit 620 is
a lattice plate 621 formed on the upper surface of the body 610; and
A restraining member 622 for restraining the upper end of the lower tension member 410 passing through the lattice plate 621;
A method of constructing a precast bridge, comprising:
제1항에 있어서,
상기 고정부재(520)의 타단은 상기 강관 기초(100)의 상단에 거치되는 갈고리인 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법.
According to claim 1,
The other end of the fixing member (520) is a method of constructing a precast bridge, characterized in that the hook mounted on the top of the steel pipe foundation (100).
제2항에 있어서,
상기 상부 프리캐스트 거더(300)를 상기 하부 프리캐스트 거더(200)의 상부에 거치시킴과 아울러, 상기 상부 긴장재(420)의 두부를 상기 제2 정착홈(320)에 정착시키는 제5 단계(S500);를
더 포함하는 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법.
3. The method of claim 2,
A fifth step (S500) of mounting the upper precast girder 300 on the upper part of the lower precast girder 200 and fixing the head of the upper tension member 420 in the second fixing groove 320 (S500) );
Method of constructing a precast bridge, characterized in that it further comprises.
제3항에 있어서,
상기 상부 프리캐스트 거더(300)의 하면에는 상부를 향해 함몰된 작업홈(330)이 형성되되,
상기 작업홈(330)은 상기 제1 정착홈(230)에 대응되는 위치에 형성된 것을 특징으로 하는 프리캐스트 교량을 시공하는 방법.


4. The method of claim 3,
On the lower surface of the upper precast girder 300, a working groove 330 recessed toward the upper portion is formed,
The method of constructing a precast bridge, characterized in that the working groove (330) is formed at a position corresponding to the first fixing groove (230).


삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR1020190030370A 2019-03-18 2019-03-18 Precaste Bridge KR102268423B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190030370A KR102268423B1 (en) 2019-03-18 2019-03-18 Precaste Bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190030370A KR102268423B1 (en) 2019-03-18 2019-03-18 Precaste Bridge

Publications (2)

Publication Number Publication Date
KR20200110892A KR20200110892A (en) 2020-09-28
KR102268423B1 true KR102268423B1 (en) 2021-06-23

Family

ID=72801240

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190030370A KR102268423B1 (en) 2019-03-18 2019-03-18 Precaste Bridge

Country Status (1)

Country Link
KR (1) KR102268423B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102521105B1 (en) * 2022-12-15 2023-04-12 에스비엔지니어링 주식회사 Connected Structure of Column and Precast Coping and its Construction Method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102291172B1 (en) * 2021-02-04 2021-08-20 (주)성원엠엔디 Across river

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101803830B1 (en) * 2015-06-15 2017-12-04 (주)지아이건설 Coping connecting apparatus and a pier construction method using thereof.

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3384820B2 (en) * 1992-10-08 2003-03-10 ケイコン株式会社 Prefabricated bridge pier
KR101310749B1 (en) * 2011-07-25 2013-09-24 김만규 Structure for reinforcing head of steel pile

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101803830B1 (en) * 2015-06-15 2017-12-04 (주)지아이건설 Coping connecting apparatus and a pier construction method using thereof.

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102521105B1 (en) * 2022-12-15 2023-04-12 에스비엔지니어링 주식회사 Connected Structure of Column and Precast Coping and its Construction Method

Also Published As

Publication number Publication date
KR20200110892A (en) 2020-09-28

Similar Documents

Publication Publication Date Title
KR100667921B1 (en) Construction method of pylon using precast concrete beam
CN105804241A (en) Single-layer prefabricated assembly type reinforced concrete beam-column joint
JP2017523330A (en) Tower foundation system and method for installing tower foundation system
CN209891048U (en) Connecting structure of precast concrete pier stud and capping beam
KR102268423B1 (en) Precaste Bridge
KR20130141276A (en) Incremental launching apparatus for launching concrete slab for composite bridge using form of buried type
CN104088291A (en) Annular wedge combined concrete precast block tower crane foundation
CN109372107A (en) The prefabricated assembled beam column crisscross joint of soap-free emulsion polymeization
JP2005097946A (en) Construction method of bridge pier
CN110847599A (en) Special-shaped column formwork filling reinforcement device and construction method thereof
CN103088939B (en) Assembly interlocking prestressing force shear wall system and construction method thereof
KR101086646B1 (en) Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same
KR100712354B1 (en) PC Integrating Construction Method of an Underground Parking Lot and PC Column-Beam Joint System for Long Span PC Beam therein
CN209907420U (en) Wet joint structure among bridge pier, bearing platform and pile foundation
CN204570479U (en) A kind of Hollow Slab Beam Bridge superstructure
CN109898540B (en) Wet joint structure among bridge pier, bearing platform and pile foundation and construction process thereof
KR101043710B1 (en) Through bridge construction method by side beam and slab by box structure without lateral prestressing
JP2016205051A (en) Construction method for structure
KR101170077B1 (en) Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same
KR102235873B1 (en) Fabrication method of partial pier cap, partial pier cap, and construction method of pier using partial pier cap
CN104047381A (en) Assembly integrated type lightly reinforced concrete shear wall structure
KR200395572Y1 (en) Precast concrete panel
KR100403989B1 (en) Bridge slab construction method and precast concrete plate applied therein
KR101325580B1 (en) Prestressed precast segment stone rainbow bridge and construction method
CN205502340U (en) Peripheral coincide unit -installment floor

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant