KR101170077B1 - Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same - Google Patents

Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same Download PDF

Info

Publication number
KR101170077B1
KR101170077B1 KR1020090044257A KR20090044257A KR101170077B1 KR 101170077 B1 KR101170077 B1 KR 101170077B1 KR 1020090044257 A KR1020090044257 A KR 1020090044257A KR 20090044257 A KR20090044257 A KR 20090044257A KR 101170077 B1 KR101170077 B1 KR 101170077B1
Authority
KR
South Korea
Prior art keywords
steel
girder
steel wire
prestressed
introduction
Prior art date
Application number
KR1020090044257A
Other languages
Korean (ko)
Other versions
KR20100125504A (en
Inventor
김회준
김창래
Original Assignee
주식회사 젬콘
(주)에스앤씨산업
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 젬콘, (주)에스앤씨산업 filed Critical 주식회사 젬콘
Priority to KR1020090044257A priority Critical patent/KR101170077B1/en
Publication of KR20100125504A publication Critical patent/KR20100125504A/en
Application granted granted Critical
Publication of KR101170077B1 publication Critical patent/KR101170077B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Abstract

본 발명은 건축물의 층간 슬래브를 설치하는데 적용하거나 빔을 사용하는 교량의 슬래브설치시 적용하기 위한 것으로서,The present invention is to apply to install the interlayer slab of the building or to apply when installing the slab of the bridge using a beam,

상기 거더에 압축력이 발생되는 상하부에 선택적으로 프리스트레스미도입부를 설치한 다음, 프리스트레스를 도입한 프리스트레스트콘크리트합성거더(일명, SPC거더)를 거더제작대를 이용하여 제작하고, 상기 빔에 상기 프리스트레스트콘크리트합성거더를 폭방향으로 다수개 밀착 설치하고, 상기 합성거더를 그대로 슬래브로 활용하거나, 상기 합성거더 위에 철근을 배근하고 콘크리트를 타설하여 슬래브로 설치한 다양한 형식의 슬래브구조체를 조립식으로 설치하는 시공방법에 관한 것이다.After the pre-stress has been selectively installed in the upper and lower portions of the girder, the prestressed concrete composite girder (aka SPC girder) with the prestress is manufactured by using a girder fabrication stage, and the beam is prestressed. Install concrete composite girders closely in the width direction, and use the composite girders as slabs, or install slab structures of various types that are installed as slabs by reinforcing reinforcement and placing concrete on the composite girders. It is about a method.

Description

압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더와 이의 제작방법 및 이를 이용한 슬래브구조체와 이의 시공방법{Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same}Prestress concrete composite girder with a pre-stress non-introduction section selectively installed only on the upper and lower parts to which compressive force is applied, and its fabrication method and slab structure and its construction method using pre-stress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method according, slab structure and construction method using the same}

본 발명은 건축물, 공장등과 같이 층간에 설치되는 빔 또는 교대 및 교각 위에 설치된 빔에 프리스트레스트콘크리트합성거더를 조립식으로 거치하여 슬래브를 설치하거나, 상기 거더 위에 콘크리트를 타설하여 슬래브를 설치한 슬래브구조체인 것이다.The present invention is to install a slab by prefabricating the prestressed concrete composite girders to the beam installed on the floor or the beams and alternating and pier, such as buildings, factories, etc., or to install concrete slab on the girder to install the slab structure It is

본 발명은 정부모멘트가 거더에 교차로 작용하는 경우, 상기 발생된 부모멘트에 의하여 거더에 압축력이 발생되는 부분인 상하단면에만 선택적으로 프리스트레스미도입부를 설치하고, 그 이외의 부분에는 프리스트레스를 도입한 프리스트레스트콘크리트합성거더를 거더제작대를 이용하여 제작하고, 건축물의 층간 슬래브 또는 빔 위에 거더를 마루바닥깔듯이 연속으로 설치하여 슬래브를 설치하거나, 또는 상기 거더 위에 콘크리트를 타설하여 슬래브를 조립식으로 설치한 슬래브구조체 의 시공방법에 관한 것이다.In the present invention, when the moment acts to the girder intersection, the pre-stress non-introduction is selectively provided only on the upper and lower cross-section that is the portion where the compressive force is generated in the girder by the generated parent moment, the prestress is introduced to other parts Rest concrete composite girder is manufactured by using girder manufacturing platform, and the slab is installed by installing the girder continuously on the floor slab or beam of the building as floor floor, or the slab is prefabricated by placing concrete on the girder. The construction method of the slab structure.

종래에는 층간의 슬래브를 설치하기 위하여 빔을 설치하고, 상기 빔 위에 철근을 배근하고 거푸집과 동바리를 설치한 다음, 콘크리트를 타설양생하여 슬래브를 설치하거나, 빔을 설치하고 상기 빔 위에 데크플레이트를 설치하고, 그 위에 콘크리트를 타설하여 건축물의 슬래브를 설치하였으며, 교량설치를 위하여 설치된 교대 및 교각위에 빔을 거치하고 그 위에 콘크리트를 타설하여 교량슬래브를 설치하였으나, 콘크리트타설작업에 많은 공사기간이 소요되며, 슬래브 설치를 위하여 타설되는 콘크리트를 지지하기 위하여 동바리를 설치하고, 거푸집을 설치하는 작업이 복잡하여 공기가 많이 소요되는 문제점이 있어 왔다.Conventionally, the beam is installed to install the slabs between the floors, the reinforcing bars are installed on the beam, the formwork and the barb are installed, and the concrete is poured to install the slab, or the beam is installed and the deck plate is installed on the beam. The concrete slab was installed on the building to install the slab of the building, and the bridge slab was installed on the bridges and bridges for the bridge installation. In order to support the concrete to be poured for slab installation, installing a copper bar and installing the formwork has been a problem that requires a lot of air is complicated.

본 발명은 상기의 문제점을 개선하기 위하여, 강선 또는 강봉을 거더의 전단면에 다수개 설치하고, 상기 거더의 부모멘트가 발생되어 거더에는 압축력이 발생되는 거더 상하부에 설치된 강선 또는 강봉의 일정범위에 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 제작하고, 이를 설치할 수 있는 빔을 설치하고, 상기 빔에 프리스트레스트콘크리트합성거더를 설치하여 슬래브로 활용하던지, 또는 상기 거더 위에 콘크리트를 타설하여 조립식으로 슬래브를 설치하면서, 최소한의 콘크리트를 작업을 하면서, 상기 거더를 거푸집으로 이용하여 별도의 거푸집과 동바리를 설치하지 않도록 하고, 상기 설치된 빔에 거치된 거더에 발생된 부모멘트로 인하여 거더에는 압축력이 발생되는 상하부에 일정범위에 걸쳐 선택적으로 설치된 프리스트레스미도입부에 상기 압축력이 전달되어 전달된 압축력이 감소되어 전체적으로 슬래브에 발생되는 부모멘트의 크기를 감소시키도록 한 것이다.The present invention, in order to improve the above problems, install a plurality of steel wires or steel rods on the front end of the girder, the parent of the girder is generated in a certain range of the steel wires or steel rods installed on the upper and lower girder to generate a compressive force Alternatively, a prestressed concrete girder with a prestressed non-introduction part is manufactured, a beam for installing the beam is installed, and a prestressed concrete composite girder is installed on the beam to be used as a slab, or concrete is poured on the girder. While installing the slab in a prefabricated manner, do not install a separate formwork and dongbu by using the girder as a formwork while working with a minimum of concrete, and the compressive force on the girder due to the parents generated in the girder mounted on the installed beam Selective over a certain range in the upper and lower parts where this occurs The prestress is the compressive force is transmitted decreases the transmitted compressive force to the non-introduction section provided to one to reduce the overall size of the negative moment generated in the slab.

본 발명은 전단면에 걸쳐 다수개의 강선 또는 강봉을 설치하고, 상기 거더의 상하부에 설치된 강선 또는 강봉에 압축력이 발생되는 일정부분에만 선택적으로 응고시간지연수지접착제를 도포하여 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 거더제작대를 이용하여 제작하고, 상기 거더를 빔 위에 마루깔듯이 거치하고, 슬래브로 사용하던지, 상기 거더 위에 콘크리트를 타설하여 조립식 으로 슬래브를 설치한 슬래브구조체에 관한 것이다.The present invention installs a plurality of steel wires or steel rods across the shear surface, and pre-stressed non-introduction portion is installed by selectively applying a solidification time delay resin adhesive to a predetermined portion of the compression force is generated in the steel wires or steel rods installed on the upper and lower parts of the girder The present invention relates to a slab structure in which a rest concrete composite girder is manufactured using a girder manufacturing stand, the girder is mounted on a beam, and used as a slab, or a slab structure is prefabricated by placing concrete on the girder.

또한, 상기 프리스트레스트콘크리트합성거더를 제작할 때, 상기 거더를 설치하여 정부모멘트가 교차적으로 반복되어 발생될때, 거더제작대를 이용하여 거더에 발생되는 부모멘트에 의하여 거더에 압축력이 작용되는 상하부의 일정한 부분에 설치된 강선 또는 강봉에만 응고시간지연접착수지재를 도포한 후에 긴장된 강선 또는 강봉을 포함하는 콘크리트를 타설양생한 후에 강선을 릴리스하여 상기 응고시간지연접착수지재를 도포한 부분의 강선 또는 강봉을 포함하는 콘크리트에는 프리스트레스가 도입되지 않도록 한 것이다.In addition, when the prestressed concrete composite girder is manufactured, when the girder is installed and the government moment is repeatedly repeated, the upper and lower portions of the upper and lower portions of the girder are actuated by the parent moment generated in the girder by using the girder manufacturing platform. After applying solidification time delay adhesive resin material only to steel wires or steel rods installed in a certain part, and after curing concrete containing tensioned steel wires or steel rods, the steel wires are released to release the steel wires or steel rods of the part where the solidification time delay adhesive resin material is applied. Prestress is not introduced to the concrete containing the.

향후에, 상기 제작된 프리스트레스트콘크리트합성거더의 단부 또는 수직부의 안착부를 빔에 거치하고, 상기 빔 위에서 거더의 단부가 마주보게 설치된 연결부에는 거더의 단부에 설치된 노출강선의 일정부분이 겹치도록 하고 각각 정착클립을 설치하고, 루프철근으로 상호 교차되도록 설치하고, 상기 연결부에 콘크리트를 타설하여 슬래브를 설치하거나, 또는 상기 연결부를 포함한 거더 위에 콘크리트를 타설하여 조립식으로 슬래브를 설치한 슬래브구조체에 관한 것이다.In the future, the mounting portion of the end portion or vertical portion of the fabricated prestressed concrete composite girder is mounted on the beam, and the connection portion provided so that the end portion of the girder faces the beam is overlapped with a portion of the exposed steel wire installed at the end of the girder, respectively. It relates to a slab structure in which a fixing clip is installed to cross each other with a loop reinforcement, and concrete is installed on the connection part to install a slab, or a concrete is installed on the girder including the connection part to install the slab.

본 발명은 동바리를 사용하지 않고, 거푸집의 사용을 최소화하고, 조립식으로 경제적인 슬래브시공이되도록 하였으며, 설치된 슬래브에 거치된 거더에 정부모멘트가 교차발생될때 발생된 상기 부모멘트에 의하여 거더에 압축력이 작용하는 상하부에 설치된 강선 또는 강봉에 일정범위에 걸쳐 응고시간지연접착수지재를 도포하고, 강선 또는 강봉을 긴장하고, 강선 또는 강봉을 포함하여 콘크리트를 타설하 여 거더를 형성한 후에, 상기 강선 또는 강봉을 릴리스하여 선택적으로 상기 응고시간지연접착수지재가 도포된 부분의 강선 또는 강봉과 주변의 콘크리트에만 프리스트레스를 도입되지 않도록 한 프리스트레스트콘크리트합성거더를 이용하여 슬래브를 설치하여 상기 슬래브에 발생되는 부모멘트에 의하여 거더에 발생된 압축력을 감소시키도록 한 슬래브구조체의 시공방법에 관한 것이다.The present invention is to minimize the use of formwork, and to be economically prefabricated slab construction without using a copper bar, and the compressive force is applied to the girder by the parent moment generated when the government moment crosses the girders mounted on the installed slab After applying the coagulation time delay adhesive resin material over a certain range to the steel wires or steel rods installed on the upper and lower portions, strain the steel wires or steel rods, and cast concrete, including steel wires or steel rods, to form a girder, and then Parents generated on the slab by releasing the steel rod and installing the slab using the prestressed concrete girder to prevent the pre-stress from being introduced only to the steel wire or the steel rod and the surrounding concrete where the solidification time delay adhesive resin material is selectively applied To reduce the compressive force generated by the girder The construction method of a slab structure.

이하, 첨부된 도면에 의하여 본 발명의 구성과 작용을 설명하면 다음과 같다. Hereinafter, the configuration and operation of the present invention by the accompanying drawings as follows.

도 1은 본 발명의 프리스트레스트콘크리트합성거더를 보여주는 도면이며, 도 2는 본 발명의 프리스트레스트콘크리트합성거더의 다른 실시예를 보여주는 도면이며, 도 3(a)(b)는 본 발명의 프리스트레스트콘크리트합성거더의 또 다른 실시예를 보여주는 도면이며, 도 4는 본 발명의 프리스트레스트콘크리트합성거더의 단면에 설치된 강선 또는 강봉과 양측면에 설치된 전단홈을 보여주는 도면이며, 도 5(a)(b)(c)(d)는 본 발명의 프리스트레스트콘크리트합성거더를 거더제작대를 이용하여 제작하는 과정을 보여주는 도면이며, 도 6는 본 발명의 단부지압강판을 보여주는 도면이며, 도 7은 본 발명의 가동지압강판을 보여주는 도면이며, 도 8(a)(b)(c)는 본 발명의 강선체결지압강판과 상기 강선체결지압강판의 강선체결공에 강선의 확대두부가 체결된 것을 보여주는 도면이며, 도 9(a)(b)(c)는 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 연속라멘을 설치하는 과정을 보여주는 도면이며, 도 10(a)(b)(c)(d)는 본 발명의 프리스트레스트콘크리트합성거더를 이용 하여 연속라멘의 다른 설치과정을 보여주는 도면이며, 도 11(a)(b)(c)(d)는 본 발명의 다른 실시예의 프리스트레스트콘크리트합성거더를 이용하여 연속라멘을 설치하는 과정을 보여주는 도면이며, 도 12는 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 빔위에 거치하고, 콘크리트를 타설하여 슬래브를 설치한 것을 보여주는 도면이며, 도 13은 교량설치의 경우, 교각 및 교대에 거치된 프리스트레스트콘크리트빔 위에 본 발명의 프리스트레스트콘크리트합성거더를 설치하고 콘크리트를 타설하여 슬래브를 설치한 것을 보여주는 도면이며, 도 14(a)(b)(c)는 본 발명의 연속라멘의 설치를 위하여 설치된 프리스트레스트콘크리트합성거더의 상하부에 선택적으로 설치된 프리스트레스미도입부의 설치범위가 상기 연속라멘에 작용하는 하중에 의하여 부모멘트가 교차적으로 발생되어 프리스트레스트콘크리트합성거더에 압축력이 발생되는 범위에 설치된 것을 보여주는 모멘트도이며, 상기 발생된 부모멘트가 프리스트레스트콘크리트합성거더의 부재내의 상하부면에 교차적으로 전달되어 상기 프리스트레스트콘크리트합성거더의 프리스트레스가 도입되지 않은 부분에 압축력으로 작용되어, 상기 발생된 부모멘트가 감소되는 것을 보여주는 휨모멘트도이며, 도 15는 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 건축물의 슬래브를 설치하기 위하여 설치한 빔에 거치하여 슬래브를 설치한 것을 평면으로 보여주는 도면이다. 1 is a view showing a prestressed concrete composite girder of the present invention, Figure 2 is a view showing another embodiment of the prestressed concrete composite girder of the present invention, Figure 3 (a) (b) is a prestressed 4 is a view showing another embodiment of the concrete composite girder, Figure 4 is a view showing a steel wire or steel rods and shear grooves provided on both sides of the prestressed concrete composite girder of the present invention, Figure 5 (a) (b) (c) (d) is a view showing a process of manufacturing the prestressed concrete composite girder of the present invention using a girder production table, Figure 6 is a view showing the end pressure plate of the present invention, Figure 7 is a view of the present invention Figure 8 (a) (b) (c) is a view showing the movable acupressure steel plate shows that the expansion head of the steel wire is fastened to the steel wire fastening hole of the steel wire fastening pressure steel plate of the present invention and the steel wire fastening pressure bearing steel plate. 9 (a), (b) and (c) are views showing a process of installing a continuous ramen using the prestressed concrete composite girder of the present invention, and FIGS. 10 (a) (b) (c) ( d) is a view showing another installation process of the continuous ramen using the prestressed concrete composite girder of the present invention, Figure 11 (a) (b) (c) (d) is a prestressed concrete composite of another embodiment of the present invention FIG. 12 is a view showing a process of installing a continuous ramen using a girder, FIG. 12 is a view showing a slab installed by placing concrete on a beam using a prestressed concrete composite girder of the present invention, and FIG. In the case of the bridge installation, the prestressed concrete composite girder of the present invention is installed on the prestressed concrete beam mounted on the bridge piers and shifts, and the slab is installed by pouring concrete. 14 (a) (b) (c) is the parent cement by the load acting on the continuous ramen the installation range of the pre-stressed non-introduction section selectively installed on the upper and lower portions of the prestressed concrete composite girder installed for the installation of the continuous ramen of the present invention Is a moment diagram showing that the cross is generated in the prestressed concrete composite girder is installed in the range in which the compressive force is generated, the generated parent is transmitted to the upper and lower surfaces in the member of the prestressed concrete composite girder cross It is a bending moment diagram showing that the generated parent moment is reduced by applying a compressive force to a portion where the prestress of the concrete composite girder is not introduced, and FIG. 15 shows a slab of a building using the prestressed concrete composite girder of the present invention. Slab is mounted on the installed beam It is a figure which shows one thing in a plane.

본 발명은 건축물, 공장등과 같이 다수의 층이 설치되는 건축물에 있어서, 층을 이루는 슬래브를 설치하기 위하여, 기둥에 설치되는 빔에 압축력이 발생되는 상하면에 설치된 강선 또는 강봉에 선택적으로 프리스트레스미도입부를 설치한 프 리스트레스트콘크리트합성거더를 거더제작대를 이용하여 제작하고, 상기 제작된 프리스트레스트콘크리트합성거더를 빔에 조립식으로 거치한 것을 슬래브로 사용하거나, 상기 거더 위에 콘크리트를 타설하여 슬래브를 설치한 슬래브구조체의 시공방법에 관한 것이다.The present invention is a pre-stress non-introduction portion selectively to the steel wire or steel rods installed on the upper and lower surfaces in which the compressive force is generated in the beam installed on the column in order to install the slab forming the layer in a building, such as a building, a factory, etc. Prepare the prestressed concrete composite girders installed with a girder manufacturing stand, and use the prefabricated concrete composite girders mounted on the beam as a slab, or install the slab by pouring concrete on the girder. The construction method of a slab structure.

또한, 상기 프리스트레스트콘크리트합성거더를 조립식으로 설치한 본 발명의 슬래브구조체의 특징은 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상하면에 압축력이 발생되는 부분에 프리스트레스미도입부를 선택적으로 설치한 프리스트레스트콘크리트합성거더(10)를 이용하여 빔에 다수개 설치하여 슬래브를 설치하거나, 상기 거더 위에 콘크리트를 타설하여 슬래브를 설치할 때, 상기 빔 위에 마주보고 설치된 거더의 단부에 노출된 노출강선의 일정길이가 겹치도록 하고, 상기 겹침부가 감싸지도록 루프철근을 교차설치하고, 상기 노출강선에 정착클립을 설치한 연결부를 설치하거나, 빔 위에 설치된 거더의 단부에 설치된 노출강선에 정착클립을 설치한 연결부를 설치하고, 상기 연결부에 콘크리트를 타설하여 슬래브를 설치하거나, 또는 상기 연결부를 포함하여 거더 위에 콘크리트를 타설하여 상기 거더 위에 설치된 전단연결재와 일체거동하도록 한 슬래브를 설치한 것이다.In addition, the characteristics of the slab structure of the present invention in which the prestressed concrete composite girder is installed in a prefabricated manner is provided with a plurality of steel wires or steel rods at regular intervals on the shear surface, and prestressed non-introduced portion is selected in the portion where the compressive force is generated on the upper and lower surfaces Exposed to the beam using a prestressed concrete composite girder (10) installed by installing a slab, or when installing a slab by placing concrete on the girder, exposed to the end of the installed girder facing the beam The steel wires overlap a certain length of steel wires, and cross-install the reinforcing steel bars so that the overlaps are enclosed, and install a connection part in which the fixing clip is installed in the exposed steel wire, or install a fixing clip in the exposed steel wire installed at the end of the girder installed on the beam. Install one connection part, and install slab by pouring concrete to the connection part Or, it is to install a slab to be integrated with the shear connector installed on the girder by placing concrete on the girder including the connecting portion.

상기 양측에 설치된 빔에 설치된 거더에 정부모멘트가 반복될 경우, 상기 거더의 압축력이 발생되는 상하면에 설치된 강선 또는 강봉의 일정범위에 응고시간지연접착수지재를 도포하고, 긴장한 후에 콘크리트를 타설양생한 후에, 긴장력을 릴리스하면, 상기 도포재가 도포된 부분에는 프리스트레스가 도입되지 않게된다.When the government moment is repeated on the girders installed on the beams on both sides, the solidification time delay adhesive resin material is applied to a certain range of the steel wire or steel rods installed on the upper and lower sides where the compressive force of the girder is generated, and after the tension is poured into concrete Later, when the tension is released, prestress is not introduced into the portion to which the coating material is applied.

상기 프리스트레스가 도입되지 않은 부분에 상기 거더에 발생된 압축력이 전달되어 전달된 압축력이 감소되어 설치된 슬래브의 강성을 증가시키도록 한 것에 특징이 있는 것이다. The compressive force generated in the girder is transmitted to the portion where the prestress is not introduced, so that the transmitted compressive force is reduced to increase the rigidity of the installed slab.

상기 슬래브를 조립식으로 설치할 수 있도록 거더제작대를 이용하여 프리스트레스트콘크리트합성거더를 제작할 때, 상기 빔에 거치된 거더에 하중이 작용할 때 거더에 정부모멘트가 교대로 반복되는 경우, 상기 거더에 발생되는 부모멘트에 의하여 거더에 압축력이 작용하는 부분인 상하부에 설치된 강선 또는 강봉의 일정범위에 응고시간지연접착수지재를 도포하고, 긴장한 후에 콘크리트를 타설양생하고, 강선 또는 강봉을 릴리스하면, 상기 도포재가 도포된 부분에는 프리스트레스가 도입되지 않도록 한 프리스트레스트콘크리트합성거더(10)를 제작한다. When fabricating the prestressed concrete composite girder using the girder fabrication stage to install the slab prefabricated, when the moment is repeated to the girder alternately when the load is applied to the girder mounted on the beam, Applying the coagulation time delay adhesive resin material to a certain range of steel wires or steel rods installed on the upper and lower portions, which are compressive force acting on the girder by the parent moment, and after squeezing the concrete and releasing the steel wire or steel rod, the coating material is A prestressed concrete composite girder 10 is prepared in which the prestress is not introduced to the coated portion.

상기 제작된 프리스트레스트콘크리트합성거더를 층간의 슬래브를 설치하거나 교량슬래브를 설치하기 위하여 설치된 빔에 설치하고, 상기 빔에 마주보게 설치된 거더의 단부에 설치된 노출강선을 겹치도록 하고, 상기 겹침부를 루푸철근이 교차되도록 하고, 상기 노출강선에 정착클립을 설치한 연결부를 설치하고, 상기 연결부에 콘크리트를 타설하여 슬래브로 설치하던지, 또는 연결부를 포함한 거더의 상부에 다수개 설치된 전단연결재에 의하여 타설되는 콘크리트와 일체거동하도록 한 슬래브를 설치한 슬래브구조체이다.       The fabricated prestressed concrete composite girder is installed on a beam installed to install an interlayer slab or a bridge slab, and overlaps the exposed steel wire installed at an end of the girder installed to face the beam, and the overlapping portion is looped And cross-connecting, and install a connection part installed with a fixing clip on the exposed steel wire, and install the concrete in the connection part as a slab, or concrete placed by a plurality of shear connection materials installed in the upper part of the girder including the connection part and It is a slab structure provided with a slab that is configured to be integrated.

또한, 상기 거더(10) 상부에 슬래브를 형성하기 위한 철근을 배근하고, 콘크리트를 타설하여 정착클립에 의하여 노출강선과 슬래브의 콘크리트와 일체설치한 연결부를 형성한 슬래브구조체(80)의 시공방법인 것이다.In addition, the construction method of the slab structure (80) formed by reinforcing the reinforcing bar for forming the slab on the girder (10), and the connection portion integrally installed with the exposed steel wire and the concrete of the slab by the casting clip. will be.

우선, 본 발명의 슬래브구조체(80)를 조립식으로 설치하기 위하여 선택적으로 프리스트레스를 도입하여 제작한 프리스트레스트콘크리트합성거더(10)에 대하여 살펴본 후에, First, after the prestressed concrete composite girder 10 produced by selectively introducing prestress in order to install the slab structure 80 of the present invention,

상기 거더(10)에 프리스트레스를 선택적으로 도입하기 위하여 설치된 거더제작대(30)를 이용하여 거더(10)를 제작하는 과정에 대하여 설명하고,A process of manufacturing the girder 10 using the girder production stand 30 installed to selectively introduce the prestress to the girder 10 will be described.

마지막으로, 상기 선택적으로 프리스트레스가 도입되도록 제작된 프리스트레스트콘크리트합성거더를 이용하여 건축물의 슬래브 또는 교량 슬래브를 설치한 슬래브구조체의 시공방법에 대하여 설명하기로 한다.Lastly, a method of constructing a slab structure in which a slab of a building or a bridge slab is installed using a prestressed concrete composite girder manufactured to selectively introduce prestress will be described.

먼저 프리스트레스트콘크리트합성거더(10)에 대하여 도 1내지 도 4에 의하여 설명하면 다음과 같다.First, the prestressed concrete composite girder 10 will be described with reference to FIGS. 1 to 4.

상기 프리스트레스트콘크리트합성거더(10)는 전체적으로 직육면체로서, 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하되, 거더에 압축력이 발생되는 상하면에 설치된 강선 또는 강봉에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더를 제작하면서, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치한 것이 도 1의 거더(10)로서, 일명 SPC거더이다.The prestressed concrete composite girders 10 are generally rectangular parallelepipeds, and shear grooves 16 are formed on both sides of the longitudinal direction, and a plurality of steel wires or steel bars are installed on the shear surface in the longitudinal direction at regular intervals, and compressive force is applied to the girder. The pre-stress non-introduction portion 25 is selectively installed on the steel wire or steel rods provided on the upper and lower surfaces, and the pre-stress introduction portion 20 is installed in other portions, and the pour is hardened in concrete to manufacture the girder. The girder 10 of FIG. 1 is provided with the exposed steel wire 12 which exposed the steel wire or the steel bar to the so-called SPC girder.

또 다른 실시예로서, In another embodiment,

상기 프리스트레스트콘크리트합성거더(10)는 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하되, 압축력이 발생되는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더(10)를 제작하면서, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것이 도 2의 거더(10)로서, 일명 SPC거더이다.The prestressed concrete composite girder 10 is provided with an inclined portion 14 at both ends of the horizontal portion 13, and a vertical portion 15 formed at the lower portion of the inclined portion 14, and the horizontal portion 13. Shear grooves 16 are formed on both sides of the), and a plurality of steel wires or steel bars 11 are provided at regular intervals on the front end surface of the horizontal portion 13, but the steel wires or steel bars are installed on the upper and lower surfaces of the compressive force ( The prestressed non-introduction portion 25 is optionally provided in 11), and the prestressed introduction portion 20 is provided in the other portions, and the girder 10 is manufactured by pour-hardening concrete, and at both ends of the girder 10. The girders 10 of FIG. 2 are provided with the exposed steel wires 12 exposing the steel wires or the steel rods 11, so-called SPC girders.

또 다른 실시예로서, 도 3의 경우는,As another embodiment, in the case of FIG.

상기 프리스트레스트콘크리트합성거더(10)는 전체적으로 직육면체로서, 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더를 제작하면서, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치한 것이 도 3(a)의 거더(10)로서, 일명 SPC거더이다.The prestressed concrete composite girders 10 are generally rectangular parallelepipeds, and shear grooves 16 are formed on both sides of the longitudinal direction, and a plurality of steel wires or steel bars are installed at regular intervals at regular intervals, and Prestressed non-introduced portion 25 is provided on the steel wires or steel rods provided at both ends, and the prestressed introduction portion 20 is provided on the other portions, and the steel wires or steel rods are placed on both ends of the girder while the concrete is poured and produced. The exposed steel wire 12 is provided as the girder 10 of Fig. 3A, which is called an SPC girder.

또 다른 경우로는, In another case,

상기 프리스트레스트콘크리트합성거더(10)는 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더(10)를 제작하면서, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것이 도 3(b)의 거더(10)로서, 일명 SPC거더이다.The prestressed concrete composite girder 10 is provided with an inclined portion 14 at both ends of the horizontal portion 13, and a vertical portion 15 formed at the lower portion of the inclined portion 14, and the horizontal portion 13. Shear grooves 16 are formed on both sides of the), and a plurality of steel wires or steel bars 11 are provided at regular intervals on the front face of the horizontal portion 13, and the steel wires or steel rods 11 are provided at both ends of the girder. Prestress non-introduction portion 25 is optionally provided), and prestress introduction portion 20 is provided in other portions, and the steel wires are formed at both ends of the girder 10 while the concrete is poured to produce the girder 10. Or as the girder 10 of FIG. 3 (b) which provided the exposed steel wire 12 which exposed the steel bar 11, it is also called SPC girder.

상기 거더(10)의 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하는 방법은 상기 강선 또는 강봉(11)의 일정범위에 응고시간지연수지접착제를 도포하고, 상기 강선 또는 강봉을 긴장하여 콘크리트를 타설경화후, 강선 또는 강봉을 릴리스하여, 상기 응고시간지연수지접착제가 도포된 부분(21)에는 프리스트레스미도입부(25)가 설치되도록 한다.The method of selectively installing the prestressed non-introduction portion 25 on the steel wire or the steel bar 11 installed on the upper and lower surfaces of the girder 10 applies a solidification time delay resin adhesive to a predetermined range of the steel wire or the steel bar 11, and After placing the concrete by stiffening the steel wire or steel bar, the steel wire or steel bar is released, so that the prestress non-introduction part 25 is installed in the portion 21 to which the solidification time delay resin adhesive is applied.

이때, 상기 강봉 또는 강선(11)에 응고시간지연수지접착제를 도포(21)하여 프리스트레스미도입부(25)를 설치하는 선택적인 범위는 거더(10)에 부모멘트의 발생으로 인하여 거더에 압축력이 발생되는, At this time, the selective range of installing the pre-stressed non-introduction portion 25 by applying the coagulation time delay resin adhesive to the steel rod or steel wire 11 is generated in the girder due to the generation of the parent moment in the girder 10 felled,

거더(10)의 상부면에 설치된 강선 또는 강봉(11)의 경우, 중앙부에는 프리스트레스미도입부(25)를 설치하고, 양단부에는 프리스트레스도입부(20)를 설치하고, In the case of the steel wire or the steel bar 11 provided on the upper surface of the girder 10, the prestress non-introduction portion 25 is installed in the center portion, and the prestress introduction portion 20 is provided at both ends,

하부면에 설치된 강선 또는 강봉(11)의 경우, 중앙부에는 프리스트레스도입부(20)를 설치하고, 양단부에는 프리스트레스미도입부(25)를 설치하여 압축력이 발생되는 상하면에 선택적으로 프리스트레스가 미도입되도록 한 것이다.In the case of the steel wire or steel rod 11 installed on the lower surface, the prestress introduction portion 20 is installed in the center portion, and the prestress non-induction portion 25 is installed at both ends so that prestress is selectively not introduced on the upper and lower surfaces where compressive force is generated. .

상기 응고시간지연접착수지재인 에폭시등이 도포된 도포부(21)는, 상부면에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.75L ~ 0.9L이며, 하부면에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.1L ~ 0.25L의 범위에 걸쳐 설치한 것이며, 상기 도포부(21)의 범위는 프리스트레스미도입부(25)의 범위와 같다.The coating unit 21 coated with epoxy, which is the solidification time delay adhesive resin, is 0.75L to 0.9L of the girder length L in the case of the steel wire or the steel rod installed on the upper surface, In this case, it is provided over the range of 0.1L-0.25L of girder length L, and the range of the said coating part 21 is the same as the range of the prestress non-introduction part 25. As shown in FIG.

또 다른 방법의 거더에 프리스트레스미도입부를 설치하는 경우에는 거더의 양단부인 거더길이(L)의 0.1 ~ 0.25L의 범위에 걸쳐 상기 응고시간지연접착수지재인 에폭시등이 도포된 도포부(21)를 설치한다.In the case where the pre-stress non-introduction portion is provided in the girder of another method, the coating portion 21 coated with epoxy or the like as the solidification time delay adhesive resin is applied over the range of 0.1 to 0.25 L of the girder length L, which is both ends of the girder. Install.

상기 도포부(21)의 범위는 프리스트레스미도입부(25)의 범위와 같다. The range of the application portion 21 is the same as the range of the prestress unintroduced portion 25.

도 4와 같이 전단면에 강선 또는 강봉(11)을 설치하고, 양단면의 측면에 전단홈을 설치하고, 거더(10)의 상부에 다수개의 전단연결재(18)를 설치하여 거더를 형성하는 철근을 배근한 후에 콘크리트를 타설경화시켜 제작한 것을 보여주는 것이다.Reinforcing bars to form a girder by installing a steel wire or steel bar 11 on the front end surface, a shear groove on the side surface of both ends, and a plurality of shear connection material 18 on the top of the girder 10 as shown in FIG. After reinforcing the concrete is shown to be made by pour hardening.

상기 거더에서 거더의 상부에 별도의 슬래브를 설치하기 위하여 콘크리트를 타설하는 경우에는 거더의 상부에 전단연결재(18)를 설치하고, 추후에 타설되는 슬래브 콘크리트와 일체화되도록 한다.In the case of placing concrete in order to install a separate slab on the upper part of the girder, the shear connecting member 18 is installed on the upper part of the girder, so as to be integrated with the slab concrete to be poured later.

상기 거더(10)를 직접 슬래브(84)로 사용하는 경우에는 별도의 전단연결재(18)를 설치하지 않는다. When the girder 10 is directly used as the slab 84, a separate shear connector 18 is not installed.

상기 거더(10)의 양단부를 경사지게 한 경사부(14)를 설치한 이유는 빔(81)에 거치할 때 경사부(14)의 경사높이만큼 수평부(13)가 위로 높이 설치되게되어 거더 하부의 공간을 보다 크게 확보할 수 있도록 하며, 동시에 경사부(14)가 헌치부로 자연적으로 설치되도록 하여 우각부를 보강하도록 한 것이다.The reason for installing the inclined portion 14 which inclines both ends of the girder 10 is that the horizontal portion 13 is installed as high as the inclined height of the inclined portion 14 when mounted on the beam 81 so that the bottom of the girder is In order to secure a larger space, and at the same time the inclined portion 14 is to be installed as a haunting portion to reinforce the right angle portion.

또한 상기 경사부(14)의 하부에 수직부(15)를 설치한 것은 상기 수직부(15)의 하단부가 빔 위에 거치될 때 안정성을 갖도록 평평한 부분의 안착부(19)가 설치되도록 한 것이다.In addition, the installation of the vertical portion 15 in the lower portion of the inclined portion 14 is to allow the mounting portion 19 of the flat portion is installed so that the lower end of the vertical portion 15 is mounted on the beam.

상기와 같이 H형강재등의 강재를 사용하지 않고, 강선 또는 강봉 (11)만으로 거더(10)의 전단면에 일정한 간격을 두고 골고루 배치하고, 상기 골고루 배치된 강선 또는 강봉(11)에 프리스트레스인 긴장력을 도입할 때, As described above, without even using steel, such as H-shaped steel, evenly arranged at regular intervals on the shear surface of the girder 10 with only the steel wire or steel rod 11, prestressed to the evenly arranged steel wire or steel rod 11 When we introduce tension

부모멘트의 발생으로 인하여 거더에 압축력이 발생되는, 거더의 상부면에 설치된 강선 또는 강봉(11)의 경우, 중앙부에는 프리스트레스미도입부(25)를 설치하고, 양단부에는 프리스트레스도입부(20)를 설치하고, In the case of the steel wire or steel rod 11 installed on the upper surface of the girder due to the generation of the parent moment, the prestress non-introduction portion 25 is installed at the center portion, and the prestress introduction portion 20 is installed at both ends. ,

하부면에 설치된 강선 또는 강봉(11)의 경우, 중앙부에는 프리스트레스도입부(20)를 설치하고, 양단부에는 프리스트레스미도입부(25)를 설치하여 압축력이 발생되는 상하면에 선택적으로 프리스트레스가 도입되도록 하고, 그 외의 부분에는 프리스트레스가 미도입되도록 하면서 양단부에는 강선 또는 강봉을 일정길이 노출되도록 제작하기 위하여 도 5 내지 도 8과 같은 거더제작대(30)를 이용한다.In the case of the steel wire or steel rod 11 installed on the lower surface, the pre-stress introduction portion 20 is installed in the center portion, and the pre-stress non-induction portion 25 is installed at both ends to selectively introduce the pre-stress on the upper and lower surfaces where the compressive force is generated, The girder manufacturing table 30 as shown in FIGS. 5 to 8 is used to produce the steel wire or the steel bar at a predetermined length while the prestress is not introduced to the outer portion.

상기 프리스트레스트콘크리트합성거더의 다양한 실시예에 의하여 설치되는 장소에 따라 선택하여 적용하도록 하는데, 상기 합성거더를 슬래브로 사용할 때인 도 9와 같은 경우에는 도 1과 도 2의 압축부인 상하부에 선택적으로 프리스트레스미도입부를 설치한 거더를 사용하도록 하고, 도 10 내지 도 13과 같이 상기 거더의 위에 별도로 슬래브로 사용하는 콘크리트를 타설하는 경우에는 도 3의 거더를 사용하도록 한다.The prestressed concrete composite girder may be selected and applied according to the installation location according to various embodiments of the present invention. In the case of using the composite girder as a slab, as shown in FIG. 9, the prestress is selectively provided on upper and lower portions of the compression section of FIGS. 1 and 2. The girder having the unintroduced part is used, and when the concrete used as the slab is separately placed on the girder as shown in FIGS. 10 to 13, the girder of FIG. 3 is used.

도 3과 같은 거더를 사용하는 이유는 거더 위에 별도의 콘크리트를 타설하여 슬래브로 사용할 때 상기 슬래브 위에 작용하는 하중에 의하여 발생되는 모멘트에 의하여 거더에는 압축력이 발생되므로 양단부에 프리스트레스미도입부를 설치한 거 더를 사용하도록 하는 것이다.The reason for using the girder as shown in Fig. 3 is that the pre-stressed non-introduction part is installed at both ends because the compressive force is generated by the moment generated by the load acting on the slab when the concrete is placed on the girder and used as the slab. Is to use more.

즉, 거더에 교차적으로 정부모멘트가 작용하는 경우에는 도 1 및 도 2의 거더를 사용하고, 도 3의 거더를 사용하는 경우에는 거더에 압축력만 작용하는 경우에 적용하도록 한 것이다. In other words, when the moment is applied to the girders alternately acting on the girder of Figs. 1 and 2, when the girder of Fig. 3 is used to apply only when the compressive force acts on the girder.

또한, 본 발명의 거더제작대(30)를 이용하여 거더(10)를 제작할 때, 강선 또는 강봉(11)을 다양한 형태로 배치한 형태, 즉 일반적으로 사용하고 있는 형태의 거더뿐만아니라 거더가 사용되는 장소의 특징을 살릴 수 있는 특정한 형태의 거더를 다양하게 제작할 수 있으며, 동시에 상기 거더제작대를 이용하여 거더의 부위별로 선택적으로 긴장력의 크기를 조절하여 도입하던지 또는 특정의 위치에만 선택적으로 긴장력을 도입할 수 있으며, 다수개 배치된 강선에 각기 다른 크기의 긴장력을 차별적으로 도입할 수 있도록 한 것이다. In addition, when manufacturing the girder 10 using the girder manufacturing table 30 of the present invention, the girder as well as the girder of the form in which the steel wire or steel bar 11 is arranged in various forms, that is, the type generally used. Various types of girders can be produced that can make use of the characteristics of the place to be used, and at the same time, by using the girder manufacturing stand, by selectively adjusting the magnitude of the tension force for each part of the girder or selectively applying the tension force only to a specific position. It is possible to introduce different types of tension to differently arranged steel wires.

상기 거더제작대(30)를 이용하여 거더(10)를 제작하는 과정을 도 5내지 도 8을 참고로 하여 상세히 설명하면,The process of manufacturing the girder 10 using the girder production table 30 will be described in detail with reference to FIGS. 5 to 8.

지반(31) 위에 일정한 간격을 두고 지지대(40)를 마주보게 설치하고, 상기 지지대(40)의 수직지지부(41)에 관통공(43)을 다수개 설치하면서 상기 관통공(43)내에 관(44)을 도 5(a)와 같이 설치한다.The support base 40 is installed to face the ground 31 at regular intervals, and a plurality of through holes 43 are installed in the vertical support part 41 of the support 40 while the pipes in the through holes 43 44) is installed as shown in Fig. 5 (a).

상기 과정이 완료되면, 상기 수직지지부(41)의 양면에 관통공(51)이 다수개 형성된 단부지압강판(50)을 설치하고,When the process is completed, install the end pressure-bearing steel plate 50 is formed with a plurality of through holes 51 on both sides of the vertical support portion 41,

상기 수직지지부(41)의 외측에 다수개의 관통공(61)이 형성된 가동지압강판(60)을 설치하고,A movable acupressure steel plate 60 having a plurality of through holes 61 formed outside the vertical support part 41 is provided.

상기 수직지지부(41)의 내측에 다수개의 관통공(71)과 강선체결공(72)이 동시에 형성된 강선체결지압강판(70)을 설치하고,On the inner side of the vertical support portion 41 is provided with a steel wire fastening pressure steel plate 70 in which a plurality of through holes 71 and steel wire fastening holes 72 are formed at the same time,

상기 수직지지부(41)에 형성된 관통공(43)을 관통하여 내외면에 각각 설치된 가동지압강판(60)과 강선체결지압강판(70)의 관통공(61,71)을 관통하여 강봉(32)으로 상호연결하여 너트(36)로 각각 고정설치한 도 5(b)를 설치한다.Steel bars 32 through the through holes 43 formed in the vertical support portion 41 and through the through-holes 61 and 71 of the movable pressure-bearing steel plate 60 and the steel wire fastening pressure-steel plate 70 respectively installed on the inner and outer surfaces thereof. 5 (b) are installed to be fixed to each of the nuts 36 by interconnecting with each other.

이어서, 도 5(c)와 같이, 상기 강선체결지압강판(70)에 형성된 다수개의 강선체결공(72)에 강선 또는 강봉(11)의 단부가 체결되도록 한다.Subsequently, as shown in FIG. 5 (c), the ends of the steel wire or the steel rod 11 are fastened to a plurality of steel wire fastening holes 72 formed in the steel wire fastening pressure steel plate 70.

상기 과정이 완료되면, 상기 수직지지부(41)와 가동지압강판(60)과의 사이에 유압잭(34)을 설치한 거더제작대(30)를 설치하고,When the process is completed, the girder manufacturing table 30 is installed between the vertical support portion 41 and the movable acupressure steel sheet 60, the hydraulic jack 34 is installed,

상기 설치된 강선 또는 강봉에, 중앙에 수평부를 설치하고, 양측의 경사부와 수직부를 설치하고, 상기 강선 또는 강봉이 수평부의 전단면과 경사부의 일부를 관통하도록 한 다수개의 거더를 설치하고, 상기 거더의 상하면에 설치된 강선 또는 강봉의 일정범위에 걸쳐 선택적으로 응고시간지연접착수지재를 도포한 응고시간지연접착수지재도포부(21)를 형성하거나,In the installed steel wire or steel bar, a horizontal part is provided at the center, and inclination parts and vertical parts on both sides are provided, and a plurality of girders are provided so that the steel wire or steel bar penetrates the front end face of the horizontal part and a part of the inclined part. Forming the coagulation time delay adhesive resin coating portion 21 is coated with a coagulation time delay adhesive resin selectively over a certain range of steel wire or steel rods installed on the upper and lower surfaces,

상기 설치된 강선 또는 강봉에, 전체적으로 직육면체를 형성한 것으로서, 상기 강선 또는 강봉이 전단면에 설치되도록 한 다수개의 거더를 설치하고, 상기 거더의 상하면에 설치된 강선 또는 강봉의 일정범위에 걸쳐 선택적으로 응고시간지연접착수지재를 도포한 응고시간지연접착수지재도포부(21)를 형성하고,The rectangular steel is formed on the steel wire or steel rod as a whole, and a plurality of girders are installed so that the steel wire or steel rod is installed on the shear surface, and the solidification time is selectively over a certain range of the steel wire or steel rods installed on the upper and lower surfaces of the girder. A solidification time delay adhesive resin coating portion 21 coated with a delay adhesive resin material is formed,

상기 유압잭(34)에 스트로크를 발생시켜 가동지압강판(60)을 외측으로 밀면 강봉(32)에 의하여 상호 연결된 강선체결지압강판(70)이 지지대(40)쪽으로 이동하 게되어, 상기 강선체결지압강판(70)의 강선체결공(72)에 체결연결된 강선 또는 강봉(11)도 당겨지게되어 강선 또는 강봉에 긴장력이 도입되도록 하면서 체결너트(35)로 강봉(32)과 수직지지대의 외측면에 매입된 단부지압강판(50)을 체결고정하고,When the movable jack steel plate 60 is pushed outward by generating a stroke in the hydraulic jack 34, the steel wire fastening pressure steel plate 70 interconnected by the steel bar 32 is moved toward the support 40, and the steel wire fastening pressure steel plate The steel wire or steel rod 11 fastened and connected to the steel fastening hole 72 of the 70 is also pulled so that the tension force is introduced into the steel wire or steel rod, and is embedded in the outer surface of the steel rod 32 and the vertical support with the fastening nut 35. Fasten the fixed end pressure plate (50),

상기 양측에 설치된 지지대(40)와의 사이에 설치된 긴장력이 도입된 상태의 다수개의 강선 또는 강봉(11)을 포함하면서 다수개의 거더를 제작할 수 있는 콘크리트를 타설양생하는 작업을 도 5(c)와 같이 하고,5 (c) is a work for pouring the concrete to produce a plurality of girders, including a plurality of steel wires or steel rods 11 in a state in which a tension force installed between the support 40 installed on both sides is introduced as shown in FIG. and,

상기 콘크리트의 양생이 완료된 후에 거더와 거더 사이에 설치된 강선 또는 강봉(11)을 절단하되, 노출강선(12)이 설치되도록 하고, After the curing of the concrete is completed to cut the steel wire or steel rod 11 installed between the girder and the girder, so that the exposed steel wire 12 is installed,

상기 강선체결지압강판(70)에 설치된 강선체결공(72)에 체결된 강선 또는 강봉(11)을 이탈시키는 도 5(d)의 과정을 거쳐, 원하는 부분에만 선별적으로 프리스트레스가 도입된 도 1 내지 3의 프리스트레스트콘크리트합성거더(10)를 다수개 동시에 제작한 것이다.1 through which the prestress is selectively introduced only to a desired part through the process of FIG. 5 (d) of detaching the steel wire or the steel rod 11 fastened to the steel wire fastening hole 72 installed in the steel wire fastening pressure plate 70. A plurality of prestressed concrete composite girders 10 to 3 are simultaneously manufactured.

또 다른 방법으로 거더의 양측단부에만 프리스트레스미도입부를 설치하는 것을 제작할때에는, Alternatively, when manufacturing the prestressed non-introduced part only at both ends of the girder,

전체적으로 직육면체로서, 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더를 제작하면서, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강 선(12)을 설치하거나,As a generally rectangular parallelepiped, shear grooves 16 are formed on both side surfaces in the longitudinal direction, and a plurality of steel wires or steel bars are provided at regular intervals at regular intervals, and the prestress non-introduction portion is provided on the steel wires or steel bars provided at both ends of the girder. (25) is provided, and the other portion is provided with a prestressed introduction portion (20), and the exposed steel wire (12) exposing steel wires or steel bars at both ends of the girder, while preparing the girder by pouring and hardening concrete. do or,

수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더(10)를 제작하면서, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치하여 제작한 것이다.The inclined portion 14 is provided at both ends of the horizontal portion 13, and the vertical portion 15 is formed at the lower portion of the inclined portion 14, and the shear grooves 16 are formed at both side surfaces of the horizontal portion 13. It is formed, and a plurality of steel wires or steel rods 11 at regular intervals on the front end surface of the horizontal portion 13, and pre-stressed non-introduction portion 25 selectively to the steel wires or steel rods 11 provided at both ends of the girder Exposed steel wire is provided to the other parts, the pre-stress introduction portion 20 is installed, and the steel is placed or hardened on both ends of the girder 10 while making the girder 10 by placing and hardening concrete. It was produced by installing (12).

상기와 같이 거더(10)의 원하는 부분에만 프리스트레스가 도입되도록 하기 위하여 에폭시와 같은 응고시간지연접착수지재를 강선 또는 강봉의 표면에 일정한 두께로 도포표면이 거칠게 일정범위에 걸쳐 도포하는 이유는 상기 거더(10)의 상하면의 일정길이에 걸쳐 프리스트레스가 도입되지 않도록 하기 위하여 상기 강선 또는 강봉(11)의 일정범위에 걸쳐 응고시간지연접착수지재를 도포한 다음, 상기 접착수지재가 경화되기 전에 강선 또는 강봉(11)을 긴장한 상태에서, 강선 또는 강봉(11)을 포함하는 콘크리트를 타설경화시키고, 강선 또는 강봉을 강선체결공(72)으로부터 이탈시켜 릴리스하면, 응고시간지연접착수지재가 도포된 강선 또는 강봉에는 상기 접착수지재가 경화되지 않고 겔상태로 있어 콘크리트가 접착되지 않아 강선 또는 강봉에 도입된 프리스트레스가 거더에 도입되지 않는 반면에, 상기 응고시간지연접착수지재가 도포되지 않은 강선 또는 강봉(11)은 콘크리트와 접착되어 강선 또는 강봉에 도입된 프리스트레스가 거더(10)의 콘크리트에 전달되어 프리스 트레스가 도입되도록 한 것이다.The reason for applying the coagulation time delay adhesive resin such as epoxy to the surface of the steel wire or the steel rod at a constant thickness to a predetermined thickness to ensure that the prestress is introduced only to the desired portion of the girder 10 is as described above. In order to prevent the prestress from being introduced over a predetermined length of the upper and lower surfaces of (10), the solidification time delay adhesive resin material is coated over a certain range of the steel wire or steel bar 11, and then the steel wire or steel bar is before the adhesive resin material is cured. When the steel (11) is tense, the steel including the steel wire or steel bar (11) is pour-hardened, and the steel wire or steel bar is released from the steel fastening hole 72 and released, the steel wire or steel bar coated with the solidification time delay adhesive resin material The adhesive resin material is not cured and is in a gel state so that the concrete is not bonded to the steel wire or the steel bar. While the wristless is not introduced to the girder, the steel wire or steel rod 11, to which the solidification time delay adhesive resin material is not applied, is bonded to the concrete and the prestress introduced to the steel wire or steel rod is transferred to the concrete of the girder 10 to freeze. The tress was introduced.

한편, 상기 강선 또는 강봉(11)에 도포된 응고시간지연접착수지재의 경화시간을 24 ~ 36시간이 경과된 후에 경화가 진행되도록 한 것이므로, 콘크리트가 타설되어 경화되고, 콘크리트에 프리스트레스가 도입된 후에, 강선 또는 강봉에 도포된 응고시간지연접착수지재가 경화되어 콘크리트와 일체화되어 프리스트레스가 도입되지 않도록 한 것이며, 강선 또는 강봉에 도포된 표면을 거칠게 일정두께로 한 것은 상기 일정시간 경과되어 접착수지재가 경화되어 콘크리트와 일체화될때 표면의 거친면에 의하여 접착력이 강화되어 일체거동하도록 한 것이다.On the other hand, since the curing time of the coagulation time delay adhesive resin material applied to the steel wire or steel bar 11 to 24 to 36 hours has elapsed, the curing proceeds, after the concrete is poured and cured, prestress is introduced into the concrete , The coagulation time delay adhesive resin applied to the steel wire or steel rod is hardened so that it is integrated with concrete so that prestress is not introduced, and the surface coated on the steel wire or steel rod is roughened to a certain thickness so that the adhesive resin hardens after the predetermined time. When it is integrated with concrete, the adhesive force is strengthened by the rough surface of the surface so as to be integrated.

상기 강선 또는 강봉(11)을 릴리스하여 응고시간지연접착수지재가 경화되기 전에 겔상태로 일정한 시간(24 ~ 36시간)동안 있도록 하여 강선 또는 강봉을 릴리스하여 강선 또는 강봉이 줄어들때에도 상기 강선 또는 강봉외부에 도포된 겔상태에 응력이 전달되지 않도록 하기 위함인 것이다. Release the steel wire or rod 11 so that the coagulation time delay adhesive resin material is hardened for a certain time (24 to 36 hours) in a gel state so that the steel wire or steel bar is released by releasing the steel wire or steel bar to reduce the steel wire or steel bar This is to prevent stress from being transferred to the gel state applied to the gel.

결국, 시간차에 의하여 프리스트레스를 원하는 부분인 정모멘트가 작용하는 거더의 상하면에 선택적으로 프리스트레스가 도입되도록 하면서 그 외의 부분에도 접착수지재가 일정시간이 경과된 후에 경화되어 콘크리트와 접착되어 일체거동하도록 한 것이다.As a result, the prestress is selectively introduced into the upper and lower surfaces of the girder where the positive moment acts as the desired part of the prestress due to the time difference, and the adhesive resin material is also hardened after a certain time has elapsed and bonded to the concrete to act integrally. .

상기 응고시간지연접착수지재인 에폭시등이 도포된 도포부(21)는, 상부단면에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.75L ~ 0.9L이며, 하부단면에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.1L ~ 0.25L의 범위에 걸쳐 설치한 것이며, 상기 도포부(21)의 범위는 프리스트레스미도입부(25)의 범위와 같다.The coating part 21 coated with epoxy, which is the solidification time delay adhesive resin, is 0.75L to 0.9L of the girder length L in the case of the steel wire or the steel bar installed on the upper end surface, and the steel wire or the steel bar installed on the lower end surface. In this case, it is provided over the range of 0.1L-0.25L of girder length L, and the range of the said coating part 21 is the same as the range of the prestress non-introduction part 25. As shown in FIG.

상기와 같이 응고시간지연접착수지재를 도포하여 프리스트레스를 도입하지 않은 부분을 거더(10)의 상하부에 선택적으로 설치한 것은 향후에 설명되는 본 발명의 슬래브구조체(80) 시공시 빔(81)위에 거치된 프리스트레스트콘크리트합성거더(10)를 거치하면서 상기 거더(10)의 양단에 노출된 노출강선(12)에 정착클립을 설치하고, 콘크리트를 타설경화시켜 슬래브를 설치하면서 상기 노출강선에 설치된 정착클립이 콘크리트에 매입되도록 한 연결부를 설치하여 콘크리트의 슬래브와 거더가 일체연결되어 일체거동할 때,As described above, the portion of the slab structure 80 of the present invention which will be described later will be selectively installed on the upper and lower portions of the girder 10 by applying the solidification time delay adhesive resin material. Fixing clips are installed in the exposed steel wire 12 exposed to both ends of the girder 10 while the mounted prestressed concrete composite girder 10 is installed, and the slab is installed by hardening concrete to install the slab. When the slab and the girder of the concrete are integrally connected to each other by installing the connection part so that the clip is embedded in the concrete,

상기 거더에 작용하는 하중에 의하여 거더에 교차적으로 정부모멘트가 발생되어, 상기 작용하는 부모멘트가 거더에는 압축력으로 작용하게되므로, 상기 거더의 상하부만에 선택적으로 설치된 프리스트레스미도입부(25)에 상기 발생된 압축력이 전달되면, 상기 거더(10)의 프리스트레스미도입부에 의하여 발생된 압축력이 감소되도록 한 것이다.The moment is generated in the girders cross-over by the load acting on the girders, the acting parent moment acts as a compressive force to the girders, so that the prestress unintroduced portion 25 selectively installed only on the upper and lower portions of the girders When the generated compressive force is transmitted, the compressive force generated by the prestress unintroduced portion of the girder 10 is reduced.

결국, 일반적인 거더에 발생되는 압축력의 크기보다 획기적으로 크기를 감소시켜 슬래브 자체 또는 연결부의 파괴등을 방지하여 슬래브구조체의 안정성이 보다 크게 확보될 수 있도록 한 것으로서 도 14의 도시된 것과 같이 모멘트가 발생된 부분에 프리스트레스미도입부를 설치한 것이다. As a result, the moment is generated as shown in FIG. 14 as the stability of the slab structure is more secured by significantly reducing the size of the compressive force generated in the general girder to prevent destruction of the slab itself or the connection part. The prestressed non-introduction part is installed in the part which was made.

상기 방법에 의하여 제작된 거더는 상하부에 일정한 간격을 두고 골고루 설치된 다수개의 강선 또는 강봉에 의하여 선택적으로 상하면에 프리스트레스가 도입된 상태이므로 거더의 전단면이 유효한 단면인 반면에,Whereas the girder produced by the above method is a state in which the prestress is selectively introduced on the upper and lower surfaces by a plurality of steel wires or rods evenly spaced at regular intervals on the upper and lower sides, while the shear surface of the girder is an effective cross section,

기존의 콘크리트거더는 상부의 압축부만 유효한 단면이 되므로, 활용성면에 서 기존 거더의 활용범위 보다, 본 발명 거더의 활용범위를 보다 광범위하게 사용할 수 있으며, 거더의 두께를 줄일 수 있는 장점이 있다.Existing concrete girders are effective cross section only the upper compression section, in terms of usability can be used more widely than the range of the existing girder, the scope of use of the girder of the present invention, there is an advantage to reduce the thickness of the girder .

또한, 상기 거더의 상하면에 선택적으로 설치된 프리스트레스미도입부(25)와 노출강선(12)에 설치된 정착클립(83)에 의하여 슬래브 콘크리트가 일체화된 연결부(90)에서 발생되는 모멘트를 감소시켜 연결부(90)가 파괴되는 것을 방지하므로서 슬래브구조체(80)의 내하력을 증강시키도록 한 것이다.In addition, the connection portion 90 by reducing the moment generated from the connection portion 90 is integrated with the slab concrete by the pre-stress non-introduction portion 25 and the fixing clip 83 installed on the exposed steel wire 12 selectively installed on the upper and lower surfaces of the girder. ) To increase the load capacity of the slab structure (80) while preventing destruction.

상기 거더제작대(30)의 각각의 구성을 도면에 의하여 설명하면 다음과 같다.Referring to the drawings, each configuration of the girder production stage 30 is as follows.

상기 지지대(40)는 철근콘크리트로 수직지지부(41)와 수평지지부(42)의 ㄴ자형으로 설치하되, 수평지지부(42)를 지반(31)내에 매입설치하되, 상기 수평지지부(42)가 내측으로 설치되도록 한 것이 도 5(a)이다.The support 40 is installed in the shape of the vertical support portion 41 and the horizontal support portion 42 of the reinforced concrete, the horizontal support portion 42 is embedded in the ground 31, the horizontal support portion 42 is installed inside Figure 5 (a) is to be installed.

상기 수평지지부(42)를 내측으로 일정길이로 설치하면, 수평지지부(42)의 측면에서 유압잭(34)에 의하여 발생되는 스트로크에 의하여 수직지지부(41)가 내측으로 전도되려는 힘을 상기 스트로크힘의 작용방향과 반대방향으로 일정길이 설치되는 수평지지부(42)의 지지력에 의한 힘보다 작게 하여 지지대(40)가 안전하게 지지되어 거더(10)를 제작할 수 있도록 한 것이다.When the horizontal support portion 42 is installed to a predetermined length inwardly, the force that the vertical support portion 41 is to be transferred inwards by the stroke generated by the hydraulic jack 34 on the side of the horizontal support portion 42 is applied to the inner side of the stroke force. The support 40 is safely supported by a force less than the force of the horizontal support portion 42 which is installed at a predetermined length in the direction opposite to the action direction so that the girder 10 can be manufactured.

상기 수직지지부(41)에는 다수개의 관통공(43)이 형성되고, 상기 관통공(43)내에는 관(44)을 삽입한 것이다.A plurality of through holes 43 are formed in the vertical support part 41, and the tube 44 is inserted into the through holes 43.

상기 관통공(43)내에 관(44)을 삽입한 이유는 관(44)내에 향후에 설치되는 강봉(32)이 유압잭(34)에 의하여 관(44)내에서 이동할 때 관통공(43)내에서 원활하게 이동할 수 있도록 안내관의 역할을 하도록 하기 위함이다. The reason why the pipe 44 is inserted into the through hole 43 is that the steel bar 32 which is installed in the pipe 44 in the future is moved in the pipe 44 by the hydraulic jack 34. To act as a guide to move smoothly in the.

도 5(b)는 수직지지부(41)의 내외면에 도 5의 단부지압강판(50)이 매입된 상태를 보여주는 것이다.FIG. 5 (b) shows a state in which the end pressure bearing steel plate 50 of FIG. 5 is embedded in the inner and outer surfaces of the vertical support part 41.

상기 단부지압강판(50)은 직각사각형의 강판으로 다수개의 관통공(51)이 형성된 것이다.The end pressure-bearing steel sheet 50 is a rectangular steel sheet formed with a plurality of through holes 51.

상기 관통공(51)은 수직지지부(41)의 관통구(43)에 일치되게 설치되는 것이다.The through hole 51 is installed to coincide with the through hole 43 of the vertical support part 41.

상기와 같이 단부지압강판(50)의 관통공(51)과 수직지지부(41)의 관통공(43)을 일치시켜 설치하고, 양단부에 나사산(33)이 형성된 강봉(32)을 관통설치한다.As described above, the through hole 51 of the end pressure-bearing steel plate 50 and the through hole 43 of the vertical support part 41 are coincident with each other, and the steel rods 32 formed with the thread 33 are provided at both ends.

상기 단부지압강판(50)을 수직지지부(41)의 내외면에 매입설치하는 이유는 유압잭의 스트로크에 의하여 강선 또는 강봉(11)에 긴장력이 도입될때 수직지지부(41)의 단면을 보강하기 위하여 설치하는 것이다. The reason why the end pressure-bearing steel plate 50 is installed on the inner and outer surfaces of the vertical support part 41 is to reinforce the cross section of the vertical support part 41 when a tension force is introduced into the steel wire or the steel bar 11 by the stroke of the hydraulic jack. It is.

또한, 수직지지부(41)의 외측에서 일정거리 떨어져 설치되는 것으로서, 도 7의 직사각형의 강판으로 다수개의 관통공(61)이 설치된 가동지압강판(60)이다. In addition, it is provided a predetermined distance away from the outside of the vertical support portion 41, the movable steel plate 60 is provided with a plurality of through-holes 61 of the rectangular steel sheet of FIG.

상기 관통공(61)은 상기 단부지압강판(50)의 관통공(51)과 수직지지부(41)의 관통공(43)이 하나의 강봉(32)으로 상호 관통 체결되도록 하기 위한 것이다.The through hole 61 is for allowing the through hole 51 of the end pressure-bearing steel plate 50 and the through hole 43 of the vertical support part 41 to be penetrated through each other by one steel bar 32.

상기 가동지압강판(60)은 향후 유압잭(34)에 의하여 뒤쪽으로 이동하여야 하므로 유압잭의 스트로크 힘을 전부 받아야 하므로 강판의 강성이 높아야 한다.Since the movable acupressure steel sheet 60 should be moved backward by the hydraulic jack 34 in the future, the hydraulic jack should receive all of the stroke force, so the rigidity of the steel sheet should be high.

도 8(a)의 강선체결지압강판(70)은 수직지지부(41)의 내측에서 일정거리 간격을 두고 설치되는 것으로서, 직사각형의 강판에 다수개의 관통공(71)과 강선체결공(72)이 동시에 형성된 것이다.The steel fastening bearing steel sheet 70 of FIG. 8 (a) is installed at a predetermined distance from the inside of the vertical support portion 41, and a plurality of through holes 71 and the steel wire fastening holes 72 are formed in a rectangular steel sheet. It is formed at the same time.

상기 관통공(71)은 수직지지부(41)의 관통공(43)과 상기 수직지지부의 내외면에 매입된 단부지압강판(50)의 관통공(51)과 가동지압강판(60)의 관통공(61)을 모두 관통하여 강봉을 설치하기 위한 것이다.The through hole 71 is a through hole 43 of the vertical support part 41 and a through hole 51 of the end pressure bearing steel plate 50 embedded in the inner and outer surfaces of the vertical support part, and a through hole of the movable pressure steel plate 60. It is for installing a steel bar through all 61.

상기 강봉(32)이 관통공(61,71)에 삽입된 상기 가동지압강판(60)과 강선체결지압강판(70)과 강봉(32)을 너트(36)에 의하여 각각 체결고정한다. The steel bar 32 is fastened and fastened to the movable acupressure steel plate 60, the steel wire fastening pressure steel plate 70, and the steel bar 32 inserted into the through holes 61 and 71 by nuts 36.

상기와 같이 관통공(61,71)에 삽입된 각각의 강판(60,70)을 너트(36)로 고정체결하여야 유압잭(34)에 의하여 가동지압강판(60)이 외측으로 밀리면 강선체결지압강판(70)도 동시에 상기 가동지압강판이 이동한 동일한 양만큼 이동하도록 하기 위함이다. As described above, each steel plate 60 and 70 inserted into the through holes 61 and 71 must be fastened by a nut 36. When the movable pressure steel plate 60 is pushed outward by the hydraulic jack 34, the steel wire fastening pressure plate At the same time as 70, the movable acupressure steel sheet is moved by the same amount moved.

도 8(b)는 상기 강선체결공(72)을 상세히 보여주면서 동시에 강선 또는 강봉(11)의 단부가 체결고정된 것을 보여주는 도면이다.8 (b) shows the wire fastening hole 72 in detail and at the same time shows that the end of the steel wire or steel rod 11 is fastened and fastened.

상기 강선체결공(72)은 열쇠구멍의 형상으로, 상부는 원형구멍(73)이 형성되고 이와 접하여 하부에는 상기 원형구멍(73)보다 폭은 작으나 길이는 길게 형성된 수직구멍(74)이 형성된 것이다. The steel wire fastening hole 72 is in the shape of a key hole, the upper portion is formed with a circular hole 73 is in contact with the lower portion is formed with a vertical hole 74 formed in a smaller width than the circular hole 73 but longer in length. .

상기와 같이 형성된 강선체결구멍(72)에 도 8(c)와 같이 강선 또는 강봉(11)의 단부를 강선 또는 강봉의 직경보다 크게 설치한 확대두부(24)를 상기 원형구멍(73)내에 밀어넣은 다음, 상기 원형구멍(73)의 하부에 연접하여 설치된 수직구멍(74)으로 밀어내리면 도 8(b)와 같이 수직구멍(74)에 강선 또는 강봉의 확대두부(24)가 걸쳐져 체결되는 것이다.Push the enlarged head 24 in which the end of the steel wire or the steel rod 11 is set larger than the diameter of the steel wire or the steel rod as shown in FIG. 8 (c) in the steel wire fastening hole 72 formed as described above. Then, when pushed down to the vertical hole 74 is installed in contact with the lower portion of the circular hole 73, the expansion head 24 of the steel wire or steel rod is fastened to the vertical hole 74 as shown in Figure 8 (b). .

상기와 같이 체결된 강선 또는 강봉(11)을 해체할때에는 반대로 수직구 멍(74)에 체결된 강선 또는 강봉(11)을 위로 올리면 수직구멍(74)보다 직경이 넓은 원형구멍(73)으로 강선 또는 강봉의 확대두부(24)가 올라오면서 원형구멍(73)을 통하여 외부로 빠지게 되는 것이다.When dismantling the steel wire or steel rod 11 fastened as described above, on the contrary, when the steel wire or steel rod 11 fastened to the vertical hole 74 is lifted up, the steel wire is formed into a circular hole 73 having a diameter larger than that of the vertical hole 74. Or as the enlarged head 24 of the steel rod is raised to the outside through the circular hole 73.

이렇게 강선 또는 강봉(11)의 단부를 강선체결지압강판(70)의 강선체결공(72)에 설치하고 강선 또는 강봉을 체결하도록 한 것은 수직지지부(41)와 가동지압강판(60)과의 사이에 설치된 유압잭(34)에 스트로크를 발생시키면 가동지압강판(60)이 외측으로 밀리면서 강봉(32)에 의하여 일체 연결된 강선체결지압강판(70)이 수직지지부(41) 쪽으로 움직이게된다. The end of the steel wire or steel bar 11 is installed in the steel wire fastening hole 72 of the steel wire fastening pressure plate 70 and fastened to the steel wire or steel bar between the vertical support portion 41 and the movable pressure steel plate 60 When the stroke is generated in the hydraulic jack 34 installed in the movable pressure-bearing steel plate 60 is pushed to the outside, the steel wire fastening pressure-bearing steel plate 70 integrally connected by the steel bar 32 is moved toward the vertical support portion 41.

이때 상기 강선체결지압강판(70)에 형성된 강선체결공(72)에 체결된 강선 또는 강봉(11)도 동시에 수직지지부(41) 쪽으로 이동하면 강선 또는 강봉(11)에 긴장력이 도입되게되는 것이다.At this time, when the steel wire or steel rod 11 fastened to the steel wire fastening hole 72 formed in the steel wire fastening pressure plate 70 moves toward the vertical support portion 41 at the same time, a tension force is introduced into the steel wire or steel rod 11.

상기와 같이 강선 또는 강봉(11)에 긴장력이 도입된 상태에서 원하는 부분에만 프리스트레스를 도입하도록 응고시간지연접착수지재를 도포한 다음, 콘크리트를 타설양생하여 거더의 제작이 완료된 후에, 제작이 완료된 거더를 이동하기 위하여 상기 강선체결지압강판(70)에 체결된 강선 또는 강봉(11)을 별도의 해체장비 없이 망치로 수직구멍(74)에 거치된 강선 또는 강봉(11)을 위로 쳐 올리기만 하면 원형구멍(73)으로 이동된 강선 또는 강봉의 확대두부(24)가 원형구멍(73)을 통하여 외부로 간단히 이탈하도록 한 것이다.After applying the coagulation time delay adhesive resin material to introduce the pre-stress only to the desired portion in the state where the tension force is introduced to the steel wire or steel rod 11 as described above, after the concrete is cast and finished the production of the girder, the production girder Simply move the steel wire or steel rod 11 fastened to the steel wire fastening pressure plate 70 to lift the steel wire or steel rod 11 mounted in the vertical hole 74 with a hammer without additional dismantling equipment. The enlarged head 24 of the steel wire or the steel rod moved to the hole 73 is to be easily separated to the outside through the circular hole 73.

즉, 강선 또는 강봉(11)의 체결과 해체를 용이하게 하기 위하여 강선체결공(72)을 열쇠구멍과 같이 설치한 것이다.That is, in order to facilitate the fastening and dismantling of the steel wire or the steel bar 11, the steel wire fastening hole 72 is provided as a key hole.

상기 지반(31)에 설치되는 지지대(40)가 유압잭(34)의 스트로크에 저항하면서 안전하게 거더를 제작할 수 있도록 하기 위한 지지대(40)의 설치조건중에서 전도되지 않고 안전하게 지지될 수 있도록 P x H1〈W x L1가 되어야 한다.P x H1 < so that the support 40 to be installed on the ground 31 can be safely supported without being inverted in the installation conditions of the support 40 for resisting the stroke of the hydraulic jack 34 and making the girders safe. It should be W x L1.

즉, 지지대(40)의 수평지지부(42)를 내측으로 일정길이설치하면, 수직지지부(41)의 외측면의 일정높이(H1)에서 유압잭(14)에 의하여 발생되는 스트로크힘(P)에 의하여 수직지지부(41)가 내측으로 전도되려는 힘에 대항하여 상기 스트로크힘의 작용방향과 반대방향으로 일정길이 내측으로 설치되는 수평지지부(42)의 자체 중량(W)이 작용하는 거리(L1)에 의한 힘보다 작게 하여 지지대(40)가 안전하게 지지되어 거더를 제작할 수 있도록 한 것이다.That is, when the horizontal support portion 42 of the support 40 is provided with a predetermined length inward, the stroke force P generated by the hydraulic jack 14 at a predetermined height H1 of the outer surface of the vertical support portion 41. By the distance (L1) the self-weight (W) of the horizontal support portion 42, which is installed in a predetermined length in the opposite direction to the direction of action of the stroke force against the force that the vertical support portion 41 is to be conducted inwardly Less than the force is to support the support (40) is to make the girder securely.

또한, 상기 지반(31)에 설치되는 지지대(40)가 유압잭(34)의 스트로크에 저항하면서 안전하게 거더를 제작할 수 있도록 하기 위한 지지대(40)의 설치조건중에서 지지대가 활동, 즉 미끄러지지 않도록 하기 위하여 P〈W x μ+C 가 되어야 한다.In addition, in order to prevent the support from being active, that is, slipping, in the installation conditions of the support 40 to allow the support 40 installed on the ground 31 to safely manufacture the girder while resisting the stroke of the hydraulic jack 34. It should be <W x μ + C.

즉, 상기 지지대(40)는 스트로크힘(P)보다 수평지지부(42)의 자체중량(W)과 저면마찰계수(μ)를 곱한 값에 수동토압(C)을 더한 힘이 더 크도록 하여 활동 즉, 지지대(40)가 미끄러지지 않도록 하여야 한다.That is, the support 40 acts to increase the force by adding the manual earth pressure (C) to the value multiplied by the self-weight (W) of the horizontal support portion 42 and the bottom friction coefficient (μ) than the stroke force (P). That is, the support 40 should not slip.

또한, 상기 지반(31)에 설치되는 지지대(40)가 유압잭(34)의 스트로크에 저항하면서 안전하게 거더를 제작할 수 있도록 하기 위한 지지대(40)의 설치조건중에서 지지대(40)의 수직지지부(41)와 수평지지부(42)가 만나는 부분의 단면파괴를 방지하여야 하므로 이를 위하여는 P x h2 /Z〈fa 가 되어야 한다.In addition, the vertical support portion 41 of the support 40 in the installation conditions of the support 40 to enable the support 40 to be installed on the ground 31 to safely manufacture the girder while resisting the stroke of the hydraulic jack 34. And cross-sectional destruction of the portion where the horizontal support portion 42 meets, for this purpose should be P x h2 / Z <fa.

즉, 수평지지부(42)와 수직지지부(41)가 만나는 부분의 단면파괴를 방지하기 위하여 부재의 허용응력(fa)보다 스트로크힘(P)과 수직지지부 작용거리(h2)를 곱한 값을 수직지지부(41)의 단면계수(Z)로 나눈 값의 크기가 작아야 단면이 파괴되지 않아 안전하게 유지될 수 있는 것이다.That is, in order to prevent cross-sectional destruction of the portion where the horizontal support part 42 and the vertical support part 41 meet, the vertical support part is multiplied by the stroke force P and the vertical support part working distance h2 than the allowable stress fa of the member. The value of the value divided by the cross-sectional coefficient (Z) of (41) should be small so that the cross-section is not destroyed so that it can be safely maintained.

결국 상기 지지대(40) 안전조건은 지지대(40)가 전도되지 않고, 활동이 되지 않으며, 동시에 단면파괴가 되지 않도록 설치되어야 하는 것이다.As a result, the safety condition of the support 40 is that the support 40 is not to be inverted, is inactive, and at the same time, it is to be installed so as not to be damaged in section.

또한, 상기 유압잭(34)에 발생된 스트로크에 의하여 강선 또는 강봉(11)에 도입된 긴장력이 유지될 수 있도록 체결너트(35)로 강봉(32)과 수직지지대(41)의 외측면에 매입된 단부지압강판(50)을 체결하여 고정시키도록 한다.In addition, embedded in the outer surface of the steel bar 32 and the vertical support 41 by the fastening nut 35 so that the tension force introduced to the steel wire or steel bar 11 by the stroke generated in the hydraulic jack 34 can be maintained. Fasten by fixing the end pressure plate (50).

상기와 같은 거더제작대(30)를 이용하여, 거더(10)의 전단면에 일정한 간격을 두고 설치된 강선 또는 강봉(11)을 이용하여 거더에 프리스트레스를 도입할 때, 상기 거더의 상하면의 일정부분에만 선택적으로 프리스트레스가 도입되지 않도록 하고, 그 외의 부분에는 프리스트레스가 도입되도록 하면서, 양측단부에 일정길이의 강선 또는 강봉(11)을 거더의 단부 외부로 노출시킨 프리스트레스트콘크리트합성거더(10)를 제작한 것이다.When the prestress is introduced into the girder by using the steel wire or the steel bar 11 provided at regular intervals on the front end surface of the girder 10 by using the girder manufacturing table 30 as described above, a predetermined portion of the upper and lower surfaces of the girder The prestressed concrete girder 10 is fabricated by exposing the prestress to the other side only, and the prestress is introduced to the other part while exposing the steel wire or steel rod 11 of a predetermined length to the outside of the end of the girder at both ends. It is.

또는, 거더의 단면에 설치된 강선 또는 강봉의 양단부에 프리스트레스미도입부를 설치한 거더를 상기 거더제작대를 이용하여 프리스트레스트콘크리트합성거더(10)를 제작한 것이다.Alternatively, the prestressed concrete composite girder 10 is manufactured by using the girder fabrication girder provided with the prestressed non-introduction portion at both ends of the steel wire or the steel rod provided on the cross section of the girder.

또한, 상기 프리스트레스트콘크리트합성거더(10)의 상부면에 다수개의 전단연결재(84)를 다수개 설치하여 추후에 타설되는 슬래브 콘크리트와 접착력이 강화 되어 일체거동하도록 한 것이다.In addition, by installing a plurality of shear connecting members 84 on the upper surface of the prestressed concrete composite girder (10) is to strengthen the adhesive strength with the slab concrete to be poured in the future to be integrated.

상기 제작된 프리스트레스트콘크리트합성거더(10)를 이용하여 조립식으로 슬래브구조체(80)를 시공하는 과정은 도 9 내지 도 13을 참고로 하여 설명하면 다음과 같다.A process of constructing the slab structure 80 in a prefabricated manner using the prepared prestressed concrete composite girder 10 will be described with reference to FIGS. 9 to 13.

본 발명의 조립식 슬라브구조체(80)는 기둥 또는 교대 및 교각(미도시) 위에 다수개 빔(81)을 설치하고, 상기 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 측면이 접하도록 설치하고, 상기 빔(81) 위에 마주보고 설치된 상기 프리스트레스트콘크리트합성거더(10)의 단부에 설치된 노출강선(12)이 겹지도록 하고, 겹칩부(74)분을 감싸도록 루프철근(75)이 교차되게 설치하고, 상기 노출강선에 정착클립(83)을 설치하여 연결부(90)를 설치하고, 상기 연결부(90)에 콘크리트(37)를 타설한 것이거나,In the prefabricated slab structure 80 of the present invention, a plurality of beams 81 are installed on pillars or alternations and piers (not shown), and both ends of the prestressed concrete composite girder 10 are placed on the installed beams 81. While installing the side to be in contact with each other, the exposed steel wire 12 installed on the end of the prestressed concrete composite girder (10) installed facing the beam (81) to overlap, to wrap the overlapping chip portion 74 The roof reinforcement 75 is installed to cross, the fixing clip 83 is installed on the exposed steel wire to install the connection part 90, and the concrete part 37 is poured into the connection part 90,

또는 기둥 또는 교대 및 교각(미도시) 위에 다수개 빔(81)을 설치하고, 상기 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 측면이 접하도록 설치하고, 상기 빔(81) 위에 마주보고 설치된 상기 프리스트레스트콘크리트합성거더(10)의 단부에 설치된 노출강선(12)이 겹치도록 겹침부(74)를 설치하고, 상기 겹칩부를 감싸도록 루프철근(75)을 교차되게 설치하고, 상기 노출강선에 정착클립(83)을 설치하여 연결부(90)를 설치하고, 상기 연결부(90)와 상기 거더(10)의 상부에 설치된 전단연결재(18)를 포함한 콘크리트를 타설한 것이다.Alternatively, a plurality of beams 81 are installed on the pillars or alternating columns and piers (not shown), and both sides of the prestressed concrete composite girder 10 are installed on the beams 81 so as to be in contact with the side surfaces. The overlap reinforcement part 74 is installed to overlap the exposed steel wire 12 installed at the end of the prestressed concrete composite girder 10 facing the beam 81 and the loop reinforcement 75 is wrapped to surround the overlap chip part. It is installed to cross, install a fixing clip 83 to the exposed steel wire to install a connecting portion 90, and cast concrete including the connecting portion 90 and the shear connecting material 18 installed on the top of the girder 10. It is.

상기 빔(81)은 강재의 강재빔이거나 프리스트레스가 도입된 콘크리트거더이 며, 상기 제시된 이외의 모든 부재를 포함한다.The beam 81 is a steel beam of steel or a concrete girder in which prestress is introduced, and includes all members other than those shown above.

상기 조립식으로 설치된 슬래브의 다양한 설치예를 도면에 의하여 설치과정을 설명하면 다음과 같다.Referring to the installation process according to the various installation examples of the slab installed as a prefabricated as follows.

도 9의 경우에는 건축물의 기둥 또는 교량의 교대와 교각(미도시)에 다수개 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 빔(81) 위에 마주보게 설치된 상기 거더(10)의 단부에 설치된 노출강선(12)이 겹치는 겹침부(74)를 설치하고 상기 겹침부를 감싸도록 루프철근(75)을 설치하고, 상기 노출강선에 정착클립(83)을 설치한 연결부(90)를 형성하고, 상기 연결부(90)에 콘크리트(37)를 타설하여 프리스트레스트콘크리트합성거더(10) 자체를 슬래브(84)로 사용하는 것이다.In the case of Figure 9 is installed so that both ends of the prestressed concrete composite girder 10 over the beam 81 installed on a plurality of alternating bridges and piers (not shown) of the pillars or bridges of the building to face the beam 81 The overlapped portion 74 overlaps the exposed steel wire 12 installed at the end of the girder 10, and installs the loop reinforcement 75 to surround the overlapped portion, and installs a fixing clip 83 at the exposed steel wire. The connection portion 90 is formed, and concrete 37 is poured into the connection portion 90 to use the prestressed concrete composite girder 10 itself as the slab 84.

상기 슬래브구조체(80)의 설치방법은 기둥 또는 교대 및 교각(미도시) 위에 다수개 빔(81)을 (a)와 같이 설치하고, In the installation method of the slab structure 80 is installed a plurality of beams 81 (a) on a column or alternating and pier (not shown),

상기 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 측면이 접하도록 설치하고, 상기 빔(81) 위에 마주보고 설치된 상기 프리스트레스트콘크리트합성거더(10)의 단부에 설치된 노출강선(12)이 겹치도록 겹침부(74)를 설치하고, 상기 겹침부를 감싸도록 루프철근(75)을 설치하고, 상기 노출강선에 정착클립(83)을 설치하여 연결부(90)를 도 (b)와 같이 설치하고, Both ends of the prestressed concrete composite girder 10 are installed on the installed beams 81 so that side surfaces thereof are in contact with each other, and the ends of the prestressed concrete composite girder 10 are disposed to face the beams 81. The overlapped portion 74 is installed so that the exposed exposed steel wire 12 overlaps, the loop reinforcement 75 is installed to surround the overlapped portion, and the fixing portion 83 is installed on the exposed steel wire to guide the connection 90. install as (b),

도 (c)와 같이 상기 연결부(90)에 콘크리트(37)를 타설하여 슬래브를 설치한 슬래브구조체(80)인 것이다.It is a slab structure 80 in which a slab is installed by pouring concrete 37 into the connecting portion 90 as shown in (c).

상기 프리스트레스트콘크리트합성거더(10)는 전체적으로 직육면체로서, 양측 면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하되, 부모멘트가 발생되어 거더에는 압축력이 발생되는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더를 제작하되, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것이거나,The prestressed concrete composite girders 10 are generally rectangular parallelepipeds, and shear grooves 16 are formed on both sides of the prestressed concrete girder 10, and a plurality of steel wires or steel bars 11 are provided at regular intervals at regular intervals. The pre-stress non-introduction section 25 is selectively installed in the steel wire or steel bar 11 installed on the upper and lower surfaces where the compressive force is generated and the compressive force is generated, and the prestress introduction section 20 is installed in other portions, and the concrete is poured Produce a girder, but the exposed steel wire 12 is exposed to both ends of the girder 10 to expose the steel wire or steel bar 11,

또는, 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 상기 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하되, 부모멘트가 발생되어 거더에는 압축력이 작용하는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더(10)를 제작하되, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것이다.Or, the inclined portion 14 is provided on both side ends of the horizontal portion 13, the vertical portion 15 is formed in the lower portion of the inclined portion 14, both side surfaces of the horizontal portion 13 shear grooves ( 16) is formed, and a plurality of steel wires or steel rods 11 at regular intervals on the front end surface of the horizontal portion 13, the parent wire is generated, the steel wires or steel rods installed on the upper and lower surfaces to the compressive force acting ( 11) optionally pre-stressed non-introduction portion 25, and other portions of the pre-stressed introduction portion 20 is installed, and the concrete is cast-pour hardened to manufacture the girder 10, but at both ends of the girder 10 Exposed steel wire 12 to expose the steel wire or steel bar 11 is installed.

도 10의 경우에는 도 9와 같은 경우이나, 다만 빔(81)의 하부플랜지(82)에 하부케이싱콘크리트(86)를 타설한 것과, 상기 하부케이싱콘크리트(86)의 상부에 프리스트레스트콘크리트합성거더(10)의 단부가 걸쳐지도록 하고, 상기 거더(10) 상부에 설치된 전단연결재(18)와 빔(10)의 상부플랜지(85)를 포함하여 콘크리트(37)를 타설하여 슬래브(84)를 설치한 것이다.In the case of FIG. 10, the same case as in FIG. 9 is provided, but the lower casing concrete 86 is poured into the lower flange 82 of the beam 81, and the prestressed concrete girder is formed on the upper casing concrete 86. The end of the (10) is covered, and the slab (84) is installed by pouring concrete (37), including the shear connector 18 and the upper flange (85) of the beam 10 installed on the girder (10) It is.

이를 도면에 의하여 설치과정을 설명하면, When explaining the installation process according to the drawings,

기둥 또는 교각 및 교대(미도시) 위에 다수개 빔(81)을 도 (a)와 같이 설치하고, A plurality of beams 81 are installed as shown in FIG.

상기 설치된 빔(81)의 하부플랜지(82)에 하부케이싱콘크리트(86)를 도 (b)와 같이 설치하고,The lower casing concrete 86 is installed on the lower flange 82 of the installed beam 81 as shown in FIG.

도 (c)와 같이 프리스트레스트콘크리트합성거더(10)의 단부가 하부케이싱콘크리트(86) 상부에 걸쳐지게 설치하면서 측면이 접하도록 설치하고, 상기 하부케이싱콘크리트(86) 상부에 설치된 상기 프리스트레스트콘크리트합성거더(10)의 단부에 설치된 노출강선(12)에 정착클립(83)을 설치하여 연결부(90)를 설치하고, As shown in (c), the end of the prestressed concrete girder 10 is installed to be in contact with the side while being installed over the lower casing concrete 86, and the prestressed concrete is installed on the lower casing concrete 86. Install the connection part 90 by installing the fixing clip 83 on the exposed steel wire 12 installed at the end of the composite girder 10,

상기 연결부(90)와 상기 거더(10)의 상부에 설치된 전단연결재(18) 및 빔(81)의 상부플랜지(85)를 포함한 콘크리트(37)를 타설하여 슬래브(84)를 설치한 슬래브구조체(80)인 것이다.A slab structure in which the slab 84 is installed by pouring concrete 37 including the shear connector 18 and the upper flange 85 of the beam 81 installed on the connecting portion 90 and the girder 10 ( 80).

상기 프리스트레스트콘크리트합성거더(10)는 전체적으로 직육면체로서, 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더를 제작하면서, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치한 것이거나,The prestressed concrete composite girders 10 are generally rectangular parallelepipeds, and shear grooves 16 are formed on both sides of the longitudinal direction, and a plurality of steel wires or steel bars are installed at regular intervals at regular intervals, and Prestressed non-introduced portion 25 is provided on the steel wires or steel rods provided at both ends, and the prestressed introduction portion 20 is provided on the other portions, and the steel wires or steel rods are placed on both ends of the girder while the concrete is poured and produced. Installed exposed steel wire 12, or

상기 프리스트레스트콘크리트합성거더(10)는 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강 선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더(10)를 제작하면서, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것이다.The prestressed concrete composite girder 10 is provided with an inclined portion 14 at both ends of the horizontal portion 13, and a vertical portion 15 formed at the lower portion of the inclined portion 14, and the horizontal portion 13. Shear grooves 16 are formed on both sides of the), and a plurality of steel wires or steel rods 11 are provided at regular intervals on the front end surface of the horizontal portion 13, and the steel wires or steel rods provided at both ends of the girder ( The prestressed non-introduction portion 25 is optionally provided in 11), and the prestressed introduction portion 20 is provided in the other portions, and the girder 10 is manufactured by pour-hardening concrete, and at both ends of the girder 10. Exposed steel wire 12 to expose the steel wire or steel bar 11 is installed.

도 11은 상기 도 10과 같은 방법으로 설치하되, 다만 도 3의 거더를 사용한 것과, 상기 도 3의 거더를 하부케이싱콘크리트(86) 상부에 설치할 때 도 3의 (b)의 경우, 상기 거더(10)의 수직부(15)의 안착부(19)가 하부케이싱콘크리트(86) 상부에 설치되도록 한 것에서 차이가 있다.11 is installed in the same manner as in FIG. 10, except that the girder of FIG. 3 is used, and in the case of FIG. 3 (b) when the girder of FIG. 3 is installed on the lower casing concrete 86, the girder ( There is a difference in that the mounting portion 19 of the vertical portion 15 of 10) is installed on the upper casing concrete 86.

도 3(a)의 프리스트레스트콘크리트합성거더(10)는 전체적으로 직육면체로서, 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더를 제작하면서, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치하거나,The prestressed concrete composite girder 10 of FIG. 3 (a) is generally a rectangular parallelepiped, and shear grooves 16 are formed on both sides of the longitudinal direction, and a plurality of steel wires or steel bars are installed at regular intervals at regular intervals. And a prestress non-introduction section 25 is provided on the steel wires or steel rods provided at both ends of the girder, and a prestress introduction section 20 is installed in the other portions, and the pour is hardened in concrete to manufacture the girder. Install the exposed steel wire 12 to expose the steel wire or steel bar, or

수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더(10)를 제작하면서, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것이다.The inclined portion 14 is provided at both ends of the horizontal portion 13, and the vertical portion 15 is formed at the lower portion of the inclined portion 14, and the shear grooves 16 are formed at both side surfaces of the horizontal portion 13. It is formed, and a plurality of steel wires or steel rods 11 at regular intervals on the front end surface of the horizontal portion 13, and pre-stressed non-introduction portion 25 selectively to the steel wires or steel rods 11 provided at both ends of the girder Exposed steel wire is provided to the other parts, the pre-stress introduction portion 20 is installed, and the steel is placed or hardened on both ends of the girder 10 while making the girder 10 by placing and hardening concrete. (12) is installed.

또 다른 방법인 도 12는, 도 9와 같은 방법으로 설치하되, 다만, 빔 위에 설치된 거더(10)를 도 3의 거더를 사용하고, 상기 거더 위에 콘크리트를 타설하여 슬래브를 설치한 것에서 차이가 있다. 12, which is another method, is installed in the same manner as in FIG. 9, except that the girder 10 installed on the beam uses the girder of FIG. 3, and the slab is installed by placing concrete on the girder. .

도 12는 건축물의 기둥 또는 교량의 교대와 교각(미도시)에 다수개 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 빔(81) 위에 상기 거더(10)의 단부가 마주보게 설치된 부분에 설치된 노출강선(12)이 겹쳐지는 겹침부(74)를 설치하고, 상기 겹침부를 감싸도록 루프철근(75)을 교차설치하고, 상기 노출강선에 정착클립(83)을 설치한 연결부(90)를 형성하고, 상기 연결부(90)와 거더의 상부에 설치된 전단연결재(18)를 포함한 콘크리트(37)를 타설하여 슬래브(84)를 설치한 슬래브구조체(80)인 것이다.FIG. 12 shows the girders 10 on the beams 81 while installing both ends of the prestressed concrete composite girder 10 over the beams 81 installed on the alternating bridges and piers (not shown) of the pillars or bridges of the building. Install the overlapping portion 74 overlapping the exposed steel wire 12 is installed in the portion facing the end of the installation, cross-install the reinforcing bar 75 so as to surround the overlapping portion, the fixing clip 83 to the exposed steel wire The slab structure 80 is formed by forming the connection portion 90 is installed, and the slab 84 is installed by pouring concrete 37 including the connecting portion 90 and the shear connection material 18 installed on the top of the girder. .

상기 슬래브구조체의 설치방법은 기둥 또는 교대 및 교각(미도시) 위에 다수개 빔(81)을 설치하고, The method of installing the slab structure is to install a plurality of beams 81 on the column or alternating and pier (not shown),

상기 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 측면이 접하도록 설치하고, 상기 빔(81) 위에 마주보고 설치된 상기 프리스트레스트콘크리트합성거더(10)의 단부에 설치된 노출강선(12)이 겹쳐지도록 겹침부(74)를 설치하고, 상기 겹침부를 감싸도록 루프철근(75)을 설치하고, 상기 노출강선에 정착클립(83)을 설치하여 연결부(90)를 설치하고, Both ends of the prestressed concrete composite girder 10 are installed on the installed beams 81 so that side surfaces thereof are in contact with each other, and the ends of the prestressed concrete composite girder 10 are disposed to face the beams 81. The overlapped portion 74 is installed so that the exposed exposed steel wire 12 overlaps, the loop reinforcement 75 is installed to cover the overlapped portion, and a fixing clip 83 is installed on the exposed steel wire to install the connection portion 90. and,

상기 연결부(90)와 거더의 상부에 설치된 전단연결재(18)를 포함한 콘크리 트(37)를 타설하여 슬래브를 설치한 슬래브구조체(80)인 것이다.It is a slab structure 80 in which the slab is installed by pouring the concrete 37 including the connecting portion 90 and the shear connecting material 18 installed on the upper part of the girder.

상기 프리스트레스트콘크리트합성거더(10)는 전체적으로 직육면체로서, 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더를 제작하면서, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치하 것이거나,The prestressed concrete composite girders 10 are generally rectangular parallelepipeds, and shear grooves 16 are formed on both sides of the longitudinal direction, and a plurality of steel wires or steel bars are installed at regular intervals at regular intervals, and Prestressed non-introduced portion 25 is provided on the steel wires or steel rods provided at both ends, and the prestressed introduction portion 20 is provided on the other portions, and the steel wires or steel rods are placed on both ends of the girder while the concrete is poured and produced. Install exposed steel wire 12, or

수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더(10)를 제작하면서, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것이다.The inclined portion 14 is provided at both ends of the horizontal portion 13, and the vertical portion 15 is formed at the lower portion of the inclined portion 14, and the shear grooves 16 are formed at both side surfaces of the horizontal portion 13. It is formed, and a plurality of steel wires or steel rods 11 at regular intervals on the front end surface of the horizontal portion 13, and pre-stressed non-introduction portion 25 selectively to the steel wires or steel rods 11 provided at both ends of the girder Exposed steel wire is provided to the other parts, the pre-stress introduction portion 20 is installed, and the steel is placed or hardened on both ends of the girder 10 while making the girder 10 by placing and hardening concrete. (12) is installed.

또 다른 방법인 도 13은, 도 9와 같은 방법으로 설치하되, 다만, 사용된 빔이 프리스트레스가 도입된 콘크리트빔이며, 상기 빔 위에 설치된 거더(10)를 도 3의 거더를 사용하고, 상기 거더 위에 콘크리트를 타설하여 슬래브를 설치한 것에서 차이가 있다. FIG. 13, which is another method, is installed in the same manner as in FIG. 9, except that the used beam is a concrete beam into which prestress is introduced, and the girder 10 installed on the beam uses the girder of FIG. 3. The difference is that the slab is installed by pouring concrete on it.

도 13은 건축물의 기둥 또는 교량의 교대와 교각(미도시)에 다수개 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 빔(81) 위에 상기 거더(10)의 단부가 마주보게 설치된 부분에 설치된 노출강선(12)이 겁쳐지도록 겹침부를 설치하고, 상기 겹침부를 감싸도록 루프철근을 교차설치하고, 상기 노출강선에 정착클립(83)을 설치한 연결부(90)를 형성하고, 상기 연결부(90)와 거더의 상부에 설치된 전단연결재(18)를 포함한 콘크리트(37)를 타설하여 슬래브(84)를 설치한 슬래브구조체(80)인 것이다.FIG. 13 shows the girders 10 on the beams 81 while both ends of the prestressed concrete composite girder 10 are installed on the beams 81 installed in the alternating columns and piers (not shown) of the pillars or bridges of the building. The connection portion 90 is provided with an overlapping portion so that the exposed steel wire 12 installed on the end portion facing the end of the cross section, cross-installing the reinforcing steel bars to cover the overlapping portion, and the fixing clip 83 is installed on the exposed steel wire. The slab structure 80 is formed by placing the slab 84 by forming concrete 37 including the connecting portion 90 and the shear connector 18 installed on the upper portion of the girder.

상기 슬래브구조체의 설치방법은 기둥 또는 교대 및 교각(미도시) 위에 다수개 빔(81)을 설치하고, The method of installing the slab structure is to install a plurality of beams 81 on the column or alternating and pier (not shown),

상기 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 측면이 접하도록 설치하고, 상기 빔(81) 위에 마주보고 설치된 상기 프리스트레스트콘크리트합성거더(10)의 단부에 설치된 노출강선(12)이 겹쳐지도록 겹침부를 설치하고, 상기 겹침부가 감싸지도록 루프철근을 교차설치하고, 상기 노출강선에 정착클립(83)을 설치하여 연결부(90)를 설치하고, Both ends of the prestressed concrete composite girder 10 are installed on the installed beams 81 so that side surfaces thereof are in contact with each other, and the ends of the prestressed concrete composite girder 10 are disposed to face the beams 81. The overlapped portion is installed so that the exposed exposed steel wire 12 is overlapped, the loop reinforcement is installed so that the overlapped portion is wrapped, and a fixing clip 83 is installed on the exposed steel wire to install the connection part 90.

상기 연결부(90)와 거더의 상부에 설치된 전단연결재(18)를 포함한 콘크리트(37)를 타설하여 슬래브를 설치한 슬래브구조체(80)인 것이다.It is a slab structure 80 in which the slab is installed by pouring concrete 37 including the connecting portion 90 and the shear connecting material 18 installed on the upper part of the girder.

상기 프리스트레스트콘크리트합성거더(10)는 전체적으로 직육면체로서, 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더를 제작하면서, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치한 것이거나,The prestressed concrete composite girders 10 are generally rectangular parallelepipeds, and shear grooves 16 are formed on both sides of the longitudinal direction, and a plurality of steel wires or steel bars are installed at regular intervals at regular intervals, and Prestressed non-introduced portion 25 is provided on the steel wires or steel rods provided at both ends, and the prestressed introduction portion 20 is provided on the other portions, and the steel wires or steel rods are placed on both ends of the girder while the concrete is poured and produced. Installed exposed steel wire 12, or

수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 콘크리트를 타설경화하여 거더(10)를 제작하면서, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것이다.The inclined portion 14 is provided at both ends of the horizontal portion 13, and the vertical portion 15 is formed at the lower portion of the inclined portion 14, and the shear grooves 16 are formed at both side surfaces of the horizontal portion 13. It is formed, and a plurality of steel wires or steel rods 11 at regular intervals on the front end surface of the horizontal portion 13, and pre-stressed non-introduction portion 25 selectively to the steel wires or steel rods 11 provided at both ends of the girder Exposed steel wire is provided to the other parts, the pre-stress introduction portion 20 is installed, and the steel is placed or hardened on both ends of the girder 10 while making the girder 10 by placing and hardening concrete. (12) is installed.

상기와 같이 다양한 예에 의하여 설치된 슬래브구조체(80)의 특징은 기둥의 수를 줄여 보다 활용성이 큰 공간을 확보하는 것이며, 프리스트레스트콘크리트합성거더(10)에 작용하는 부모멘트에 의한 거더(10)에 발생된 압축력을 상기 프리스트레스트콘크리트합성거더(10)의 상하면에 선택적으로 설치된 프리스트레스미도입부에 전달되어 압축력이 감소되도록 하여 전체적으로 슬래브에 작용하는 부모멘트를 감소시키도록 한 것으로서 건축물 슬래브 및 교량 슬래브에 적용하도록 한 것이다.The characteristics of the slab structure 80 installed by various examples as described above is to ensure a more usable space by reducing the number of columns, girders 10 by the parent acting on the prestressed concrete composite girder 10 The compressive force generated in) is transmitted to the prestressed non-introduction section selectively installed on the upper and lower surfaces of the prestressed concrete composite girder 10 so that the compressive force is reduced to reduce the parent moment acting on the slab as a whole. To apply.

상기 거더(10)의 단부에 설치된 노출강선(12)에 겹침부와 루프철근 및 정착클립(83)을 설치한 연결부(90)를 설치하고, 추후에 슬래브(84)를 설치하기 위하여 타설되는 콘크리트(37)내에 매입되도록 하여 노출강선(12)이 정착클립(83)에 의하여 슬래브(84)와 일체연결되어 결국 프리스트레스트콘크리트합성거더(10)가 노출강선(12)과 겹침부, 루프철근 및 정착클립(83)에 의하여 슬래브(84)와 일체결합되어 작용하는 하중에 의하여 일체거동하도록 한 것이다.Concrete to be installed in the exposed steel wire 12 installed at the end of the girder 10 to install the connecting portion 90, the overlapping portion, the loop reinforcement and the fixing clip 83, and later to install the slab 84 The exposed steel wire 12 is integrally connected with the slab 84 by the fixing clip 83 so that the prestressed concrete composite girder 10 overlaps with the exposed steel wire 12, the loop reinforcement, and the like. It is to be integrally acted by the load acting integrally coupled to the slab 84 by the fixing clip (83).

또 다른 이유로서는, 상기 거더의 양단부 또는 상하부에 압축력이 발생되는 단면에만 선택적으로 프리스트레스미도입부(25)를 설치한 프리스트레스트콘크리트합성거더(10)를 빔(81)에 거치하면서 정착클립(83)에 의하여 노출강선(12)이 슬래브(84)와 일체거동하도록 연결부(90)를 형성하여 상기 연결부(90)에 발생되는 부모멘트에 의하여 거더(10)에는 압축력으로 작용하여, 상기 작용된 압축력이 프리스트레스미도입부(25)에 전달되면, 상기 전달된 압축력이 감소되어 상기 거더(10)와 연결부(90)에 감소된 압축력이 작용되어 결국 부모멘트의 크기가 작아져 슬래브(84)의 안정성을 증가시키도록 한 것이다. As another reason, the fixing clip 83 is mounted on the beam 81 with the prestressed concrete composite girder 10 having the prestressed non-introduced portion 25 selectively installed only at the cross section where the compressive force is generated at both ends or the top and bottom of the girder. By forming the connecting portion 90 so that the exposed steel wire 12 integrally with the slab 84 by acting as a compressive force to the girder 10 by the parent moment generated in the connecting portion 90, the applied compressive force is When transmitted to the prestressed non-introduction portion 25, the transmitted compressive force is reduced to reduce the compressive force is applied to the girder 10 and the connecting portion 90 to increase the stability of the slab 84 to eventually increase the stability of the slab 84 It was made to be.

도 4에서보는바와 같이, 상기 프리스트레스트콘크리트합성거더(10)를 빔(81) 상부에 설치하면서, 빔과 빔이 측면에서 접하도록 연이어서 설치할 때 상기 거더(10)의 측면에 형성된 전단홈(16)에 의하여 공간부인 전단키가 설치되는 것이다.As shown in Figure 4, while the prestressed concrete composite girder 10 is installed on the beam 81, the shear groove formed on the side of the girder 10 when the beam and the beam is subsequently installed to contact the side ( 16) the shear key which is a space part is installed.

상기 발생된 공간부인 전단키내에는 몰탈로 충전한다.The shear key, which is the generated space portion, is filled with mortar.

도 14는 도 9내지 도 13과 같이 다양한 방법으로 설치된 슬래브구조체(80)에 발생되는 휨모멘트를 보여주면서, 상기 슬래브구조체(80)를 설치하기 위하여 사용된 프리스트레스트콘크리트합성거더(10)에 선택적으로 설치된 프리스트레스미도입부(25)의 범위와 상기 거더(10)에 교차적으로 발생되는 정부모멘트의 변곡점(87)의 위치관계를 보여주면서 동시에 발생된 부모멘트가 상기 거더(10)의 선택적으로 설치된 프리스트레스미도입부(25)에 의하여 감소되는 것을 보여주는 것이다.FIG. 14 shows the bending moment generated in the slab structure 80 installed in various ways as shown in FIGS. 9 to 13, and is optional in the prestressed concrete composite girder 10 used to install the slab structure 80. While showing the positional relationship between the range of the pre-stressed non-introduction portion 25 and the inflection point 87 of the government moment generated crosswise to the girder 10, the parent moment generated at the same time is selectively installed in the girder 10. It is shown to be reduced by the pre-stress non-introduction (25).

상기 모멘트도에서보는바와 같이, 슬래브구조체(80)에 설치된 프리스트레스트콘크리트합성거더(10)를 빔에 설치하여 슬래브를 설치한 후에 상기 슬래브에 하중이 작용될때 본 도와 같이 정부모멘트가 상기 거더에 교차적으로 발생하게된다.As shown in the moment diagram, when the load is applied to the slab after installing the slab by installing the prestressed concrete girder 10 installed on the slab structure 80 to the beam as shown in this figure the government moment intersects the girder Will occur as an enemy.

상기 발생된 정부모멘트 중에서 부모멘트가 발생되는 범위에 해당하는 거더의 압축력이 작용하는 상하부에 선택적으로 프리스트레스를 도입하지 않은 부분(25)을 설치하여, 상기 부모멘트에 의하여 거더에 발생되는 압축력이 프리스트레스미도입부(25)에 전달되어 압축력의 크기가 감소되도록 한 것이다. Among the generated moments, a portion 25 in which no prestress is selectively introduced is installed in the upper and lower portions of the girders corresponding to the range where the parent moment is generated, and the compressive force generated in the girder by the parent moment is prestressed. It is transmitted to the non-introduction portion 25 to reduce the amount of compression force.

도 15는 빔(81)에 측면으로 다수게 접하게 설치한 프리스트레스트콘크리트합성거더(10)를 슬래브(84)로 활용하던지 또는 거더(10) 위에 콘크리트를 타설하여 슬래브(84)로 활용하는 슬래브구조체(80)를 평면으로 보여주는 것이다.15 is a slab structure that utilizes the prestressed concrete composite girder 10 installed as a slab 84 or a slab 84 by placing concrete on the girder 10. 80 is shown as a plane.

또한, 상기 거더(10)를 구성하는 골조인 철근의 배근은 너무나 당연한 것으로서 별도로 설명하지 않았으며, 슬래브(84)를 설치하기 전에 철근을 프리스트레스콘크리트합성거더(10) 위에 배근하고, 콘크리트(37)로 타설경화시켜 슬래브를 설치한 슬래브구조체(80)인 것이다. In addition, the reinforcement of the reinforcing bar, which is the frame constituting the girder 10 is not so obvious as described separately, before reinforcing the reinforcing bar on the prestressed concrete composite girder 10 before installing the slab 84, concrete (37) It is a slab structure 80 in which the slab is installed by hardening the furnace.

도 1은 본 발명의 프리스트레스트콘크리트합성거더를 보여주는 도면.1 is a view showing a prestressed concrete composite girder of the present invention.

도 2는 본 발명의 프리스트레스트콘크리트합성거더의 다른 실시예를 보여주는 도면.2 is a view showing another embodiment of the prestressed concrete composite girder of the present invention.

도 3(a)(b)는 본 발명의 프리스트레스트콘크리트합성거더의 또 다른 실시예를 보여주는 도면. Figure 3 (a) (b) is a view showing another embodiment of the prestressed concrete composite girder of the present invention.

도 4은 본 발명의 프리스트레스트콘크리트합성거더의 단면에 설치된 강선 또는 강봉과 양측면에 설치된 전단홈을 보여주는 도면.Figure 4 is a view showing a steel wire or steel rods and shear grooves installed on both sides of the prestressed concrete composite girder of the present invention.

도 5(a)(b)(c)(d)는 본 발명의 프리스트레스트콘크리트합성거더를 거더제작대를 이용하여 제작하는 과정을 보여주는 도면.Figure 5 (a) (b) (c) (d) is a view showing a process of manufacturing the prestressed concrete composite girder of the present invention using a girder production stage.

도 6는 본 발명의 단부지압강판을 보여주는 도면.Figure 6 is a view showing the end pressure plate of the present invention.

도 7은 본 발명의 가동지압강판을 보여주는 도면.7 is a view showing a movable acupressure steel sheet of the present invention.

도 8(a)(b)(c)는 본 발명의 강선체결지압강판과 상기 강선체결지압강판의 강선체결공에 강선의 확대두부가 체결된 것을 보여주는 도면.Figure 8 (a) (b) (c) is a view showing that the expansion head of the steel wire is fastened to the steel wire fastening hole of the steel wire fastening pressure plate of the present invention and the steel wire fastening pressure plate.

도 9(a)(b)(c)는 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 연속라멘을 설치하는 과정을 보여주는 도면.Figure 9 (a) (b) (c) is a view showing a process of installing a continuous ramen using the prestressed concrete composite girder of the present invention.

도 10(a)(b)(c)(d)는 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 연속라멘의 다른 설치과정을 보여주는 도면.Figure 10 (a) (b) (c) (d) is a view showing another installation process of the continuous ramen using the prestressed concrete composite girder of the present invention.

도 11(a)(b)(c)(d)는 본 발명의 다른 실시예의 프리스트레스트콘크리트합성거더를 이용하여 연속라멘을 설치하는 과정을 보여주는 도면.Figure 11 (a) (b) (c) (d) is a view showing a process of installing a continuous ramen using a prestressed concrete composite girder of another embodiment of the present invention.

도 12는 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 빔위에 거치하고, 콘크리트를 타설하여 슬래브를 설치한 것을 보여주는 도면.12 is a view showing that the slab is installed by placing on the beam using the prestressed concrete composite girder of the present invention, the concrete is poured.

도 13은 교량설치의 경우, 교각 및 교대에 거치된 프리스트레스트콘크리트빔 위에 본 발명의 프리스트레스트콘크리트합성거더를 설치하고 콘크리트를 타설하여 슬래브를 설치한 것을 보여주는 도면. 13 is a view showing the installation of the slab by installing the prestressed concrete composite girder of the present invention on the prestressed concrete beam mounted on the piers and bridges in the case of bridge installation.

도 14(a)(b)(c)는 본 발명의 연속라멘의 설치를 위하여 설치된 프리스트레스트콘크리트합성거더의 상하부에 선택적으로 설치된 프리스트레스미도입부의 설치범위가 상기 연속라멘에 작용하는 하중에 의하여 부모멘트가 교차적으로 발생되어 프리스트레스트콘크리트합성거더에 압축력이 발생되는 범위에 설치된 것을 보여주는 모멘트도이며, 상기 발생된 부모멘트가 프리스트레스트콘크리트합성거더의 부재내의 상하부면에 교차적으로 전달되어 상기 프리스트레스트콘크리트합성거더의 프리스트레스가 도입되지 않은 부분에 압축력으로 작용되어, 상기 발생된 부모멘트가 감소되는 것을 보여주는 휨모멘트도. Figure 14 (a) (b) (c) is the installation range of the pre-stress non-introduction section selectively installed in the upper and lower portions of the prestressed concrete composite girder installed for the installation of the continuous ramen of the present invention by the load acting on the continuous ramen It is a moment diagram showing that the cross is generated in the prestressed concrete composite girder is installed in the range where the compressive force is generated, the generated parent moment is transmitted to the upper and lower surfaces in the member of the prestressed concrete composite girder to cross A bending moment showing that the generated parent moment is reduced by acting as a compressive force on the part where the prestress of the rest concrete composite girder is not introduced.

도 15는 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 건축물의 슬래브를 설치하기 위하여 설치한 빔에 거치하여 슬래브를 설치한 것을 평면으로 보여주는 도면.15 is a plan view showing the installation of the slab mounted on the beam installed in order to install the slab of the building using the prestressed concrete composite girder of the present invention.

<도면의 주요부분에 대한 설명><Description of main parts of drawing>

L ; 프리스트레스트콘크리트합성거더길이L; Prestressed concrete composite girder length

10 ; 프리스트레스트콘크리트합성거더10; Prestressed Concrete Composite Girder

11 ; 강선 또는 강봉 12 ; 노출강선11; Steel wire or rod 12; Exposed steel wire

13 ; 수평부 14 ; 경사부13; Horizontal section 14; Slope

15 ; 인장부 16 ; 전단홈15; Tension section 16; Shear groove

17 ; 철근 18 ; 전단연결재17; Rebar 18; Shear connector

19 ; 안착부 20 ; 프리스트레스도입부19; Seating section 20; Prestress introduction part

21 ; 응고시간지연접착수지재도포부21; Coagulation time delay adhesive resin coating

24 ; 확대두부 25 ; 프리스트레스미도입부24; Enlarged head 25; Prestressed non-introduction

30 ; 거더제작대 31 ; 지반30; Girder belt 31; Ground

32 ; 강봉 33 ; 나사산32; Rod 33; Thread

34 ; 유압잭 35 ; 체결너트34; Hydraulic jack 35; Tightening Nut

36 ; 너트 37 ; 콘크리트36; Nut 37; concrete

40 ; 지지대 41 ; 수직지지부40; Support 41; Vertical support

42 ; 수평지지부 43 ;관통공42; Horizontal support 43; Through hole

44 ; 관 44; tube

50 ; 단부지압강판 51 ; 관통공50; End bearing steel plate 51; Through hole

58 ; 앵커 59 ; 정착구58; Anchor 59; Anchorage

60 ; 가동지압강판 61 ; 관통공60; Movable pressure plate 61; Through hole

70 ; 강선체결지압강판 71 ; 관통공70; Steel fastening steel plate 71; Through hole

72 ; 강선체결공 73 ; 원형구멍72; Steel fastening 73; Circular hole

74 ; 수직구멍 74 ; 겹침부74; Vertical hole 74; Overlap

75 ; 루프철근 75; Roof rebar

80 ; 슬래브구조체 81 ; 빔80; Slab structure 81; beam

82 ; 하부플랜지 83 ; 정착클립82; Lower flange 83; Fixing clip

84 ; 슬래브 85 ; 상부플랜지84; Slab 85; Upper flange

86 ; 하부케이싱콘크리트 87 ; 변곡점 86; Lower casing concrete 87; Inflection point

90 ; 연결부90; Connection

Claims (42)

양측면에 전단홈(16)이 형성되고, 부모멘트가 발생되어 거더에는 압축력이 발생되는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부 (25)를 설치하고, 상기 프리스트레스미도입부 이외의 부분에 프리스트레스도입부 (20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더. Shear grooves 16 are formed on both sides, and a parent moment is generated, and pre-stressed non-introduced portions 25 are selectively provided on steel wires or steel rods 11 installed on upper and lower surfaces where compressive forces are generated in girders. The prestress introduction part 20 is provided in the part, and the prestress is selectively applied only to the upper and lower parts to which the compressive force which is characterized by providing the exposed steel wire 12 which exposed the steel wire or the steel rod 11 to the both ends of the said girder 10 is provided. Prestressed concrete composite girder with introduction section. 수평부(13)의 양측단부에 경사부(14)를 설치하고, 상기 경사부(14)의 하부에 수직부(15)를 형성하고, 상기 수평부(13)의 양측면에 전단홈(16)을 형성하고, 부모멘트가 발생되어 거더에는 압축력이 작용하는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 도입하고, 상기 프리스트레스미도입부 이외의 부분에 프리스트레스도입부(20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.Inclined portions 14 are provided at both end portions of the horizontal portion 13, vertical portions 15 are formed below the inclined portion 14, and shear grooves 16 are formed at both side surfaces of the horizontal portion 13. The pre-stress non-introduction part 25 is selectively introduced into the steel wire or the steel bar 11 installed on the upper and lower surfaces to which the compressive force acts on the girder, and the parent moment is generated. Prestressed concrete provided with a pre-stressed non-introduction portion only in the upper and lower portions of the compressive force acting characterized in that the exposed steel wire 12 is exposed to the steel wire or the steel bar 11 on both ends of the girder 10 Synthetic girder. 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.Shear grooves 16 are formed on both side surfaces in the longitudinal direction, and a plurality of steel wires or steel bars are provided at regular intervals on the longitudinal direction of the longitudinal direction, and prestressed non-introduction portions 25 are installed on the steel wires or steel bars provided at both ends of the girder. The prestress non-introduction part is selectively provided only in the upper and lower parts where the compressive force is applied, and the prestress introduction part 20 is provided in the other parts, and the exposed steel wire 12 which exposes the steel wire or the steel bar is provided at both ends of the girder. Prestressed concrete composite girder installed. 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.The inclined portion 14 is provided at both ends of the horizontal portion 13, and the vertical portion 15 is formed at the lower portion of the inclined portion 14, and the shear grooves 16 are formed at both side surfaces of the horizontal portion 13. And a plurality of steel wires or steel rods 11 are formed on the front end surface of the horizontal portion 13 at regular intervals, and the prestress non-introduction portion 25 is selectively attached to the steel wires or steel rods 11 provided at both ends of the girder. Compression force characterized in that the prestress introduction portion 20 is provided in the other portions, and the exposed steel wire 12 in which steel wires or steel bars 11 are exposed at both ends of the girder 10 is provided. Prestressed concrete composite girders with optional prestressed non-introduced parts on top and bottom only. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 강봉 또는 강선(11)에 선택적으로 프리스트레스미도입부(25)를 설치하는 범위는 거더(10)의 상부면에 설치된 강선 또는 강봉의 경우, 중앙부에는 프리스트레스미도입부(25)를 설치하고, 양단부에는 프리스트레스도입부(20)를 설치하고, The pre-stress non-introduction portion 25 is selectively installed in the steel rod or steel wire 11 in the case of the steel wire or the steel rod installed on the upper surface of the girder 10, and the pre-stress non-induction portion 25 is installed in the center portion, and at both ends. Install the prestressed introduction section 20, 하부면에 설치된 강선 또는 강봉의 경우, 중앙부에는 프리스트레스도입부(20)를 설치하고, 양단부에는 프리스트레스미도입부(25)를 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.  In the case of steel wires or steel rods provided on the lower surface, the prestress introduction portion 20 is installed in the center portion, and the prestress non-induction portion is selectively installed only on the upper and lower portions to which the compressive force acting is characterized in that the prestress non-induction portion 25 is provided at both ends. Prestressed concrete composite girder. 제1항 또는 제2항에 있어서,The method according to claim 1 or 2, 상기 프리스트레스미도입부(25)의 범위는 상부면에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.75L ~ 0.9L이며, 하부면에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.1L ~ 0.25L인 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더. The prestressed non-introduction portion 25 is in the range of 0.75L to 0.9L of the girder length (L) in the case of the steel wire or steel rod installed on the upper surface, 0.1 of the girder length (L) in the case of the steel wire or steel rod installed on the lower surface A prestressed concrete girder with a prestressed non-introduced section selectively installed only on the upper and lower parts where the compressive force characterized by L to 0.25L is applied. 제 3항 또는 제4항에 있어서,The method according to claim 3 or 4, 상기 프리스트레스미도입부(25)의 범위는 양단부에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.1L ~ 0.25L인 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.The range of the prestress non-introduction section 25 is a prestress which selectively installs the pre-stress non-introduction section only in the upper and lower portions where the compressive force is characterized in that, in the case of the steel wire or the steel rods installed at both ends, it is 0.1L to 0.25L of the girder length L. Rest concrete composite girder. 제1항 내지 제4항 중 어느 한 항에 있어서,The method according to any one of claims 1 to 4, 상기 프리스트레스미도입부(25)는 강선 또는 강봉(11)에 응고시간지연수지접착제를 도포한 도포부(21)인 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더. The prestressed non-introduced portion 25 is a prestressed concrete that selectively installs the prestressed non-introduced portion only on the upper and lower portions to which the compressive force is applied, characterized in that the coating portion 21 is applied to the steel wire or steel rod 11 and the coagulation time delay resin adhesive is applied. Synthetic girder. 제1항 내지 제4항 중 어느 한 항에 있어서,The method according to any one of claims 1 to 4, 상기 거더(10)의 상부에 다수개의 전단연결재(18)를 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.A prestressed concrete composite girder having a prestressed non-introduction section selectively installed only on the upper and lower portions of the girder 10 provided with a plurality of shear connecting members 18 on top of the girder 10. 지반(31) 위에 일정한 간격을 두고 지지대(40)를 마주보게 설치하고, 상기 지지대(40)의 수직지지부(41)에 관통공(43)을 다수개 설치하면서 상기 관통공(43)내에 관(44)을 설치하고,The support base 40 is installed to face the ground 31 at regular intervals, and a plurality of through holes 43 are installed in the vertical support part 41 of the support 40 while the pipes in the through holes 43 44) install it, 상기 수직지지부(41)의 양면에 관통공(51)이 다수개 형성된 단부지압강판(50)을 설치하고,Install the end pressure-bearing steel plate 50 is formed with a plurality of through holes 51 on both sides of the vertical support portion 41, 상기 수직지지부(41)의 외측에 다수개의 관통공(61)이 형성된 가동지압강판(60)을 설치하고,A movable acupressure steel plate 60 having a plurality of through holes 61 formed outside the vertical support part 41 is provided. 상기 수직지지부(41)의 내측에 다수개의 관통공(71)과 강선체결공(72)이 동시에 형성된 강선체결지압강판(70)을 설치하고,On the inner side of the vertical support portion 41 is provided with a steel wire fastening pressure steel plate 70 in which a plurality of through holes 71 and steel wire fastening holes 72 are formed at the same time, 상기 수직지지부(41)에 형성된 관통공(43)을 관통하여 내외면에 각각 설치된 가동지압강판(60)과 강선체결지압강판(70)의 관통공(61,71)을 관통하여 강봉(32)으 로 상호연결하여 너트(36)로 각각 고정설치하고,Steel bars 32 through the through holes 43 formed in the vertical support portion 41 and through the through-holes 61 and 71 of the movable pressure-bearing steel plate 60 and the steel wire fastening pressure-steel plate 70 respectively installed on the inner and outer surfaces thereof. Interconnected with each other and fixed with nuts 36, 상기 강선체결지압강판(70)에 형성된 다수개의 강선체결공(72)에 강선 또는 강봉(11)의 단부가 체결되도록 하고,The end of the steel wire or steel bar 11 is fastened to a plurality of steel wire fastening holes 72 formed in the steel wire fastening pressure plate 70, 상기 수직지지부(41)와 가동지압강판(60)과의 사이에 유압잭(34)을 설치한 거더제작대(30)를 설치하고,A girder production table 30 having a hydraulic jack 34 is installed between the vertical support portion 41 and the movable acupressure steel sheet 60, 상기 설치된 강선 또는 강봉에, 중앙에 수평부(13)를 설치하고, 양측의 경사부(14)와 수직부(15)를 설치하고, 상기 강선 또는 강봉(11)이 수평부(13)의 전단면과 경사부(14) 일부를 관통하도록 한 다수개의 거더(10)를 설치하고, 상기 거더(10)의 상하부에 설치된 강선 또는 강봉(11)에 일정범위에 걸쳐 선택적으로 응고시간지연접착수지재를 도포한 응고시간지연접착수지재도포부(21)를 형성하거나,On the provided steel wire or steel bar, a horizontal portion 13 is provided at the center, and inclined portions 14 and vertical portions 15 on both sides are provided, and the steel wire or steel rod 11 is placed before the horizontal portion 13. A plurality of girders 10 are installed so as to penetrate the cross section and a part of the inclined portion 14, and the solidification time delay adhesive resin selectively over a certain range on the steel wire or steel rods 11 installed on the upper and lower portions of the girder 10. Forming a coagulation time delay adhesive resin coating portion (21) 상기 설치된 강선 또는 강봉에, 전체적으로 직육면체를 형성하면서, 상기 강선 또는 강봉(11)이 전단면에 설치되도록 한 다수개의 거더를 설치하고, 상기 거더의 상하면에 설치된 강선 또는 강봉(11)에 일정범위에 걸쳐 선택적으로 응고시간지연접착수지재를 도포한 응고시간지연접착수지재도포부(21)를 형성하고,While forming the rectangular parallelepiped on the installed steel wire or steel bar as a whole, install a plurality of girders so that the steel wire or steel rod 11 is installed on the shear surface, and in a certain range on the steel wire or steel rod 11 provided on the upper and lower surfaces of the girder. Forming a solidification time delay adhesive resin coating portion 21 to which the solidification time delay adhesive resin material is selectively coated over, 상기 유압잭(34)에 스트로크를 발생시켜 가동지압강판(60)을 외측으로 밀면 강봉(32)에 의하여 상호 연결된 강선체결지압강판(70)이 지지대(40)쪽으로 이동하게되어, 상기 강선체결지압강판(70)의 강선체결공(72)에 체결연결된 강선 또는 강봉(11)도 당겨지게되어 강선 또는 강봉에 긴장력이 도입되도록 하면서 체결너트(35)로 강봉(32)과 수직지지대의 외측면에 매입된 단부지압강판(50)을 체결고정하고,When the movable jack steel plate 60 is pushed outward by generating a stroke in the hydraulic jack 34, the steel wire fastening pressure steel plate 70 interconnected by the steel bar 32 moves toward the support 40, and the steel wire fastening pressure steel sheet The steel wire or steel rod 11 fastened and connected to the steel fastening hole 72 of the 70 is also pulled so that the tension force is introduced into the steel wire or steel rod, and is embedded in the outer surface of the steel rod 32 and the vertical support with the fastening nut 35. Fasten the fixed end pressure plate (50), 상기 양측에 설치된 지지대(40)와의 사이에 설치된 긴장력이 도입된 상태의 다수개의 강선 또는 강봉(11)을 포함하면서 다수개의 거더를 제작할 수 있는 콘크리트를 타설양생하고,Placing concrete to manufacture a plurality of girders, including a plurality of steel wires or steel rods 11 in a state in which the tension force installed between the support 40 installed on both sides is introduced, 상기 콘크리트의 양생이 완료된 후에 거더와 거더 사이에 설치된 강선 또는 강봉(11)을 절단하되, 노출강선(12)이 설치되도록 하고, After the curing of the concrete is completed to cut the steel wire or steel rod 11 installed between the girder and the girder, so that the exposed steel wire 12 is installed, 상기 강선체결지압강판(70)에 설치된 강선체결공(72)에 체결된 강선 또는 강봉(11)을 이탈시켜 원하는 부분에만 선별적으로 프리스트레스가 도입되도록 한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. Selecting only the upper and lower parts of the compressive force, which is characterized in that the prestress is selectively introduced only in a desired portion by leaving the steel wire or the steel rod 11 fastened to the steel wire fastening hole 72 installed in the steel wire fastening pressure plate 70. Method for manufacturing prestressed concrete composite girder with prestressed non-introduction section 제 10항에 있어서,The method of claim 10, 상기 프리스트레스미도입부를 설치하기 위하여 양측면에는 전단홈(16)이 형성되고, 거더의 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 응고시간지연수지접착제를 도포한 도포부를 설치하거나,Shear grooves 16 are formed on both sides to install the prestressed non-introduction portion, and a plurality of steel wires or steel bars are provided at regular intervals on the front end surface of the girder at regular intervals, and on the steel wires or steel bars installed at both ends of the girder. Install a coating unit coated with a coagulation time delay resin adhesive, 수평부의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 응고시간지연수지접착제를 도포한 도포부를 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The inclined portion 14 is provided at both ends of the horizontal portion, and the vertical portion 15 is formed at the lower portion of the inclined portion 14, and the shear grooves 16 are formed at both side surfaces of the horizontal portion 13, A plurality of steel wires or steel rods 11 are provided on the front end surface of the horizontal portion 13 at regular intervals, and a coating portion coated with a solidification time delay resin adhesive is installed on the steel wires or steel rods 11 provided at both ends of the girder. A method of manufacturing a prestressed concrete composite girder, in which a prestressed non-introduced section is selectively installed only on the upper and lower portions where a compressive force characterized by 제 10항에 있어서,The method of claim 10, 상기 응고시간지연접착수지재도포부(21)의 범위는 상부면에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.75L ~ 0.9L이며, 하부면에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.1L ~ 0.25L이며, 상기 응고시간지연접착수지재의 경화시작 시간은 24 ~ 36시간이 경과된 후인 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The range of the solidification time delay adhesive resin coating portion 21 is 0.75L ~ 0.9L of the girder length (L) in the case of the steel wire or steel rod installed on the upper surface, the length of the girder (for steel wire or steel rod installed on the lower surface) L) of 0.1L to 0.25L, the curing time of the solidified time delay adhesive resin material is prestressed concrete in which the pre-stress non-introduction section is selectively installed only on the upper and lower parts of the compressive force is characterized in that after 24 to 36 hours have elapsed How to make a compound girder. 제 11항에 있어서,12. The method of claim 11, 상기 프리스트레스미도입부(25)의 범위는 양단부에 설치된 강선 또는 강봉의 경우, 거더길이(L)의 0.1L ~ 0.25L인 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The range of the prestress non-introduction section 25 is a prestress which selectively installs the pre-stress non-introduction section only in the upper and lower portions where the compressive force is characterized in that, in the case of the steel wire or the steel rods installed at both ends, it is 0.1L to 0.25L of the girder length (L). Manufacturing method of rest concrete composite girder. 제10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 지지대(40)는 철근콘크리트로 수직지지부(41)와 수평지지부(42)의 ㄴ자형으로 설치하되, 수평지지부(42)를 지반(31)내에 매입설치하되, 상기 수평지지 부(42)가 내측으로 설치되도록 한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The support 40 is installed in a B-shaped shape of the vertical support portion 41 and the horizontal support portion 42 with reinforced concrete, but the horizontal support portion 42 is embedded in the ground 31, the horizontal support portion 42 is A method of manufacturing a prestressed concrete composite girder, in which a prestressed non-introduced portion is selectively installed only on the upper and lower portions to which the compressive force which is characterized by being installed inward is applied. 제 10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 수직지지부(41)에는 다수개의 관통공(43)이 형성되고, 상기 관통공(43)내에는 관(44)을 삽입한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.A plurality of through holes 43 are formed in the vertical support part 41, and pre-stress non-introduction parts are selectively installed only on the upper and lower parts of the upper and lower parts in which the compression force is characterized in that the pipe 44 is inserted into the through holes 43. How to make a prestressed concrete composite girder. 제 10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 단부지압강판(50)은 수직지지부(41)의 내외면에 매입되어 설치되는 것으로서, 직각사각형의 강판으로 다수개의 관통공(51)이 형성된 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The end pressure-bearing steel plate 50 is embedded and installed on the inner and outer surfaces of the vertical support portion 41, and selectively prestressed only in the upper and lower portions that the compressive force is characterized by a plurality of through holes 51 formed of a rectangular steel sheet Manufacturing method of prestressed concrete composite girder with no inlet. 제 10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 가동지압강판(60)은 수직지지부(41)의 외측면에서 일정거리 떨어져 설치되는 것으로서, 직사각형의 강판으로 다수개의 관통공(61)이 설치된 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The movable acupressure steel sheet 60 is installed at a predetermined distance away from the outer surface of the vertical support portion 41, and is selectively prestressed only on the upper and lower portions of the rectangular steel sheet having a plurality of through holes 61 installed thereon. Manufacturing method of prestressed concrete composite girder with no inlet. 제 10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 강선체결지압강판(70)은 수직지지부(41)의 내측면에서 일정거리 간격을 두고 설치되는 것으로서, 직사각형의 강판에 다수개의 관통공(71)과 강선체결공(72)이 동시에 형성된 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The wire fastening pressure steel plate 70 is installed at a predetermined distance from the inner surface of the vertical support portion 41, characterized in that a plurality of through holes 71 and the steel wire fastening holes 72 are formed at the same time in a rectangular steel sheet Method of manufacturing a prestressed concrete composite girder, in which the prestressed non-introduced portion is selectively installed only on the upper and lower portions to which the compressive force is applied. 제 10항 또는 제11항에 있어서, The method according to claim 10 or 11, wherein 상기 강선체결공(72)은 열쇠구멍의 형태로서, 상부는 원형구멍(73)이 형성되고 이와 접하여 하부에는 상기 원형구멍(73)보다 폭은 작으나 수직구멍(74)의 길이는 길게 형성된 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The steel wire fastening hole 72 is in the form of a key hole, the upper portion is formed with a circular hole 73 is in contact with the lower portion is smaller than the circular hole 73, but the length of the vertical hole 74 is characterized in that formed long Method of manufacturing a prestressed concrete composite girder, in which the prestressed non-introduced portion is selectively installed only on the upper and lower portions to which the compressive force is applied. 제 10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 강선체결공(72)에 체결된 강선(11)의 단부는 강선의 직경보다 크게 설치된 확대두부(24)가 형성된 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The end portion of the steel wire 11 fastened to the wire fastening hole 72 is prestressed to selectively install the pre-stress non-introduction only in the upper and lower portions of the compression head is characterized in that the enlarged head 24 is formed larger than the diameter of the steel wire Manufacturing method of concrete composite girder. 삭제delete 삭제delete 삭제delete 삭제delete 제 10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 지지대(40)가 안정성이 있게 지반에 설치되는 조건은 지지대(40)의 전도 및 활동 및 단면파괴를 모두 만족할 수 있도록 설치되어야 하는 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The pre-stress non-introduction part is selectively provided only on the upper and lower portions of the support 40 having a compressive force, which is characterized in that the support 40 is stably installed on the ground so as to satisfy both the conduction and the activity of the support 40 and cross-sectional destruction. Manufacturing method of installed prestressed concrete composite girder. 제 10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 강선체결공(72)에 강선을 체결하는 방법은 강선체결공(72)의 원형구멍(73)내에 강선(11)의 단부에 설치된 확대두부(24)를 밀어넣은 다음, 상기 원형구멍(73)의 하부에 연접하여 설치된 수직구멍(74)으로 밀어내려 체결하는 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The method for fastening the steel wire to the steel fastening hole 72 is to push the expansion head 24 provided at the end of the steel wire 11 in the circular hole 73 of the steel fastening hole 72, and then the circular hole 73 A method of manufacturing prestressed concrete girder, in which a prestressed non-introduced section is selectively installed only on the upper and lower portions where the compressive force is characterized by being pushed down and fastened to a vertical hole 74 which is connected to a lower portion of the bottom). 제 10항 또는 제11항에 있어서,The method according to claim 10 or 11, wherein 상기 강선(11)을 강선체결구멍(72)으로부터 이탈시키는 방법은 상기 강선체결공(72)의 수직구멍(74)에 체결된 강선(11)을 위로 올리면 수직구멍(74)보다 직경이 넓은 원형구멍(73)으로 강선의 확대두부(24)가 올라오면서 원형구멍(73)을 통하여 외부로 빠지게 되도록 한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The method of detaching the steel wire 11 from the steel wire fastening hole 72 is to raise the steel wire 11 fastened to the vertical hole 74 of the steel wire fastening hole 72 upwards and have a larger diameter than the vertical hole 74. Prestressed concrete girder with a prestressed non-introduced section selectively installed only on the upper and lower portions where the compressive force acts as the expansion head 24 of the steel wire rises through the hole 73 and falls outward through the circular hole 73. How to make. 건축물의 기둥 또는 교량의 교대와 교각(미도시)에 다수개 설치된 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하고, Both ends of the prestressed concrete composite girder 10 are installed on the beam 81 installed in a plurality of pillars or bridges and bridges (not shown) of the building, 상기 빔(81) 위에 상기 거더(10)의 단부가 마주보게 설치된 부분에 설치된 노출강선(12)이 겹치도록 겹침부(74)를 설치하고 상기 겹침부를 감싸도록 루프철근(75)을 교차설치하고, 상기 노출강선에 정착클립(83)을 설치한 연결부(90)를 형성하고,The overlap portion 74 is installed to overlap the exposed steel wire 12 installed at the end portion of the girder 10 facing the beam 81 and the roof reinforcement 75 is cross-installed to surround the overlap portion. Forming a connection portion 90, the fixing clip 83 is installed in the exposed steel wire, 상기 연결부(90)에 콘크리트(37)를 타설하여 프리스트레스트콘크리트합성거더(10) 자체를 슬래브(84)로 사용한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체. Prestressed concrete with the pre-stressed non-introduction part selectively installed only in the upper and lower parts of the concrete portion 37 to the connecting portion 90 by using the prestressed concrete composite girder 10 itself as a slab 84 Slab structure using composite girder. 건축물의 기둥 또는 교량의 교대와 교각(미도시)에 다수개 빔(81)을 설치하고, A plurality of beams 81 are installed in alternating and pier (not shown) of pillars or bridges of buildings, 상기 설치된 빔의 하부플랜지에 하부케이싱콘크리트(86)를 설치하고, Install the lower casing concrete 86 on the lower flange of the installed beam, 상기 하부케이싱콘크리트(86)의 상부에 프리스트레스트콘크리트합성거더(10)의 단부가 걸쳐지게 설치하고,An end portion of the prestressed concrete composite girder 10 is installed on the upper portion of the lower casing concrete 86, 상기 하부케이싱콘크리트(86) 상부에 설치된 거더(10)의 단부에 설치된 노출강선(12)에 정착클립(83)을 설치한 연결부(90)를 형성하고, A connection portion 90 having a fixing clip 83 installed on an exposed steel wire 12 provided at an end of the girder 10 installed on the lower casing concrete 86, 상기 연결부(90)와 거더의 상부에 설치된 전단연결재(18)와 빔(81)의 상부플랜지(85)를 포함하는 콘크리트(37)를 타설하여 슬래브(84)를 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체.  Compression force, characterized in that the slab 84 is installed by pouring concrete 37 including the shear connector 18 and the upper flange 85 of the beam 81 installed on the connecting portion 90 and the girder Slab structure using prestressed concrete composite girder with prestressed non-introduced section selectively installed on the upper and lower parts. 제 28항에 있어서,The method of claim 28, 상기 프리스트레스트콘크리트합성거더(10)는 양측면에는 전단홈(16)이 형성되고, 부모멘트가 발생되어 거더에는 압축력이 발생되는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체.The prestressed concrete composite girder 10 is a pre-stressed non-introduction portion 25 to the steel wire or steel rod 11 is installed on the upper and lower surfaces formed on both sides, the shear grooves 16 are formed on both sides, the parent is generated and the compressive force is generated in the girder Compression force, characterized in that the prestress introduction portion 20 is provided in the other parts, and the exposed steel wire 12 exposed the steel wire or steel bar 11 on both ends of the girder 10 is provided. A slab structure using prestressed concrete composite girders, in which the prestressed non-introduced portion is selectively installed only on the upper and lower parts of the pipe. 제 28항에 있어서,The method of claim 28, 상기 프리스트레스트콘크리트합성거더(10)는 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 상기 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 부모멘트가 발생되어 거더에는 압축력이 작용하는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체.  The prestressed concrete composite girder 10 is provided with an inclined portion 14 at both ends of the horizontal portion 13, and a vertical portion 15 formed at the lower portion of the inclined portion 14. 13) is formed on both sides of the shear grooves 16, the parent moment is generated, the pre-stress non-introduction 25 is selectively provided on the steel wire or steel bar 11 provided on the upper and lower surfaces to the compressive force acting on the girder, The prestress introduction part 20 is provided in the part, and the prestress is selectively applied only to the upper and lower parts to which the compressive force which is characterized by providing the exposed steel wire 12 which exposed the steel wire or the steel rod 11 to the both ends of the said girder 10 is provided. Slab structure using prestressed concrete composite girder with introduction section. 제 29항에 있어서,The method of claim 29, 상기 프리스트레스트콘크리트합성거더(10)는 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체.The prestressed concrete composite girder 10 has shear grooves 16 formed on both side surfaces of the longitudinal direction, and a plurality of steel wires or steel bars are installed at regular intervals at regular intervals, and the steel wires installed at both ends of the girder. Alternatively, the prestressed non-introduction portion 25 is provided in the steel bar, and the prestressed introduction portion 20 is provided in the other parts, and the exposed steel wire 12 having the steel wire or the steel bar exposed at both ends of the girder is provided. Slab structure using prestressed concrete girder with prestressed non-introduced section only on the upper and lower parts where compressive force is applied. 제 29항에 있어서,The method of claim 29, 상기 프리스트레스트콘크리트합성거더(10)는 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체.The prestressed concrete composite girder 10 is provided with an inclined portion 14 at both ends of the horizontal portion 13, and a vertical portion 15 formed at the lower portion of the inclined portion 14, and the horizontal portion 13. Shear grooves 16 are formed on both sides of the), and a plurality of steel wires or steel bars 11 are provided at regular intervals on the front face of the horizontal portion 13, and the steel wires or steel rods 11 are provided at both ends of the girder. The pre-stressed non-introduction portion 25 is optionally provided in the above), and the prestressed introduction portion 20 is provided in the other portions, and the exposed steel wire 12 in which steel wires or steel rods 11 are exposed at both ends of the girder 10. A slab structure using prestressed concrete composite girders, in which the prestressed non-introduced portion is selectively installed only on the upper and lower portions of the compressive force, which is characterized in that it is installed. 제28항 또는 제29항에 있어서,The method of claim 28 or 29, 상기 빔(81)은 강재빔이거나 프리스트레스가 도입된 콘크리트빔인 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체. The beam 81 is a slab structure using a pre-stressed concrete girder selectively installed the pre-stress non-introduction only in the upper and lower portions that the compressive force is characterized in that the steel beam or pre-stressed concrete beam. 기둥 또는 교대 및 교각(미도시) 위에 다수개 빔(81)을 설치하고, Install a plurality of beams 81 on a pillar or alternating and piers (not shown), 상기 빔(81) 위에 프리스트레스트콘크리트합성거더(10)의 양단부가 걸쳐지게 설치하면서 측면이 접하도록 설치하고, On both sides of the prestressed concrete composite girder 10 is installed on the beam 81 so as to contact the side, 상기 빔(81) 위에 마주보고 설치된 상기 프리스트레스트콘크리트합성거더(10)의 단부에 설치된 노출강선(12)이 겹치도록 겹침부(74)를 설치하고, 상기 겹침부를 감싸도록 루프철근(75)을 교차설치하고, 상기 노출강선에 정착클립(83)을 설치하여 연결부(90)를 설치하고, The overlap reinforcement part 74 is installed to overlap the exposed steel wire 12 installed at the end of the prestressed concrete composite girder 10 facing the beam 81 and the loop reinforcement 75 is wrapped to surround the overlap part. Cross install, install the fixing clip (83) in the exposed steel wire to install the connection portion 90, 상기 연결부(90)에 콘크리트(37)를 타설하여 슬래브(84)를 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체의 시공방법. Construction method of the slab structure using prestressed concrete girder selectively installed in the upper and lower parts of the compressive force is characterized in that the slab 84 is installed by placing the concrete 37 on the connecting portion 90 . 기둥 또는 교각 및 교대(미도시) 위에 다수개 빔(81)을 설치하고, Install a plurality of beams 81 on a column or pier and alternating (not shown), 상기 빔(81)의 하부플랜지(82)에 하부케이싱콘크리트(86)를 설치하고,The lower casing concrete 86 is installed on the lower flange 82 of the beam 81, 프리스트레스트콘크리트합성거더(10)의 단부가 상기 하부케이싱콘크리트(86) 상부에 걸쳐지게 설치하면서 측면이 접하도록 설치하고, The end of the prestressed concrete composite girder 10 is installed so as to contact the side while being installed over the lower casing concrete 86, 상기 하부케이싱콘크리트(86) 상부에 설치된 상기 프리스트레스트콘크리트합성거더(10)의 단부에 설치된 노출강선(12)에 정착클립(83)을 설치하여 연결부(90)를 설치하고, Install the connection part 90 by installing a fixing clip 83 on the exposed steel wire 12 installed at the end of the prestressed concrete composite girder 10 installed on the lower casing concrete 86, 상기 연결부(90)와 상기 거더(10)의 상부에 설치된 전단연결재(18) 및 빔(81)의 상부플랜지(85)를 포함한 콘크리트(37)를 타설하여 슬래브(84)를 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체의 시공방법.It characterized in that the slab 84 is installed by pouring concrete 37 including the shear connector 18 and the upper flange 85 of the beam 81 installed on the connecting portion 90 and the girder 10. A method of constructing a slab structure using prestressed concrete girder, in which the prestressed non-introduced portion is selectively installed only on the upper and lower parts to which the compressive force is applied. 제35항 또는 제36항에 있어서,The method of claim 35 or 36, 상기 빔(81)은 강재빔이거나 프리스트레스가 도입된 콘크리트빔인 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체의 시공방법. The beam 81 is a steel beam or a pre-stressed concrete beam, the method of constructing a slab structure using a pre-stressed concrete girder selectively installed in the upper and lower portions of the pre-stress non-introduction only the compressive force is characterized by the action. 제 35항에 있어서,36. The method of claim 35, 상기 프리스트레스트콘크리트합성거더(10)는 양측면에는 전단홈(16)이 형성되고, 부모멘트가 발생되어 거더에는 압축력이 발생되는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체의 시공방법. The prestressed concrete composite girder 10 is a pre-stressed non-introduction portion 25 to the steel wire or steel rod 11 is installed on the upper and lower surfaces formed on both sides, the shear grooves 16 are formed on both sides, the parent is generated, the compression force is generated in the girder Compression force, characterized in that the prestress introduction portion 20 is provided in the other parts, and the exposed steel wire 12 exposed the steel wire or steel bar 11 on both ends of the girder 10 is provided. A method of constructing a slab structure using prestressed concrete composite girders, in which a prestressed non-introduced portion is selectively installed only on the upper and lower parts of the slab. 제35항에 있어서,36. The method of claim 35 wherein 상기 프리스트레스트콘크리트합성거더(10)는 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 상기 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 부모멘트가 발생되어 거더에는 압축력이 작용하는 상하면에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체의 시공방법. The prestressed concrete composite girder 10 is provided with an inclined portion 14 at both ends of the horizontal portion 13, and a vertical portion 15 formed at the lower portion of the inclined portion 14. 13) is formed on both sides of the shear grooves 16, the parent moment is generated, the pre-stress non-introduction 25 is selectively provided on the steel wire or steel bar 11 provided on the upper and lower surfaces to the compressive force acting on the girder, The prestress introduction part 20 is provided in the part, and the prestress is selectively applied only to the upper and lower parts to which the compressive force which is characterized by providing the exposed steel wire 12 which exposed the steel wire or the steel rod 11 to the both ends of the said girder 10 is provided. Construction method of slab structure using prestressed concrete composite girder with introduction part. 제 36항에 있어서,The method of claim 36, 상기 프리스트레스트콘크리트합성거더(10)는 길이방향의 양측면에는 전단홈(16)이 형성되고, 길이방향의 전단면에 강선 또는 강봉을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉에 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더의 양단부에 강선 또는 강봉을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체의 시공방법.The prestressed concrete composite girder 10 has shear grooves 16 formed on both side surfaces of the longitudinal direction, and a plurality of steel wires or steel bars are installed at regular intervals at regular intervals, and the steel wires installed at both ends of the girder. Alternatively, the prestressed non-introduction portion 25 is provided in the steel bar, and the prestressed introduction portion 20 is provided in the other parts, and the exposed steel wire 12 having the steel wire or the steel bar exposed at both ends of the girder is provided. Construction method of slab structure using prestressed concrete girder with prestressed non-introduced part selectively installed only on the upper and lower parts where compressive force is applied. 제 36항에 있어서,The method of claim 36, 상기 프리스트레스트콘크리트합성거더(10)는 수평부(13)의 양측단부에는 경사부(14)가 설치되고, 상기 경사부(14)의 하부에는 수직부(15)가 형성된 것으로서, 수평부(13)의 양측면에는 전단홈(16)이 형성되고, 상기 수평부(13)의 전단면에 강선 또는 강봉(11)을 일정한 간격을 두고 다수개 설치하고, 상기 거더의 양단부에 설치된 강선 또는 강봉(11)에 선택적으로 프리스트레스미도입부(25)를 설치하고, 그 이외의 부분에는 프리스트레스도입부(20)를 설치하고, 상기 거더(10)의 양단부에 강선 또는 강봉(11)을 노출시킨 노출강선(12)을 설치한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체의 시공방법.The prestressed concrete composite girder 10 is provided with an inclined portion 14 at both ends of the horizontal portion 13, and a vertical portion 15 formed at the lower portion of the inclined portion 14, and the horizontal portion 13. Shear grooves 16 are formed on both sides of the), and a plurality of steel wires or steel bars 11 are provided at regular intervals on the front face of the horizontal portion 13, and the steel wires or steel rods 11 are provided at both ends of the girder. The pre-stressed non-introduction portion 25 is optionally provided in the above), and the prestressed introduction portion 20 is provided in the other portions, and the exposed steel wire 12 in which steel wires or steel rods 11 are exposed at both ends of the girder 10. Construction method of the slab structure using prestressed concrete composite girders selectively installed in the pre-stress non-introduction only on the upper and lower portions that the compression force is characterized by the installation. 제 39항 또는 제41항에 있어서,42. The method of claim 39 or 41, 상기 경사부(14)는 우각부의 보강을 위하여 헌치부로 설치되도록 한 것에 특징이 있는 압축력이 작용하는 상하부에만 선택적으로 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 슬래브구조체의 시공방법. The inclined portion 14 is a method of constructing a slab structure using a pre-stressed concrete girder selectively installed the pre-stressed non-introduction only in the upper and lower portions that the compressive force is characterized by being installed as a haunch for reinforcing the right angle.
KR1020090044257A 2009-05-21 2009-05-21 Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same KR101170077B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090044257A KR101170077B1 (en) 2009-05-21 2009-05-21 Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090044257A KR101170077B1 (en) 2009-05-21 2009-05-21 Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same

Publications (2)

Publication Number Publication Date
KR20100125504A KR20100125504A (en) 2010-12-01
KR101170077B1 true KR101170077B1 (en) 2012-07-31

Family

ID=43503592

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090044257A KR101170077B1 (en) 2009-05-21 2009-05-21 Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same

Country Status (1)

Country Link
KR (1) KR101170077B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101710567B1 (en) * 2013-10-22 2017-03-13 주식회사 대산시빌테크날러지 Prestressing method using non-composite parts of tendon and concrete structure therewith
KR101939132B1 (en) * 2018-04-16 2019-01-16 한녹희 Girder, modular rahmen structure and construction method thereof
KR102203149B1 (en) * 2019-01-10 2021-01-13 김태균 Precast Prestressed Concrete Slab Using Unbonded Strand Area And Cutting Pocket And the Manufacturing Method Therefor

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002013196A (en) 2000-06-28 2002-01-18 Takenaka Komuten Co Ltd Self-base isolation method and self-base isolation structure for rc structure
JP2003205514A (en) 2002-01-11 2003-07-22 Kurimoto Ltd Apparatus for manufacturing prestressed concrete panel
KR100754789B1 (en) 2006-06-30 2007-09-03 박재만 Prestressed composition girder and method of constructing continuous girder used by the composition unit girder

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002013196A (en) 2000-06-28 2002-01-18 Takenaka Komuten Co Ltd Self-base isolation method and self-base isolation structure for rc structure
JP2003205514A (en) 2002-01-11 2003-07-22 Kurimoto Ltd Apparatus for manufacturing prestressed concrete panel
KR100754789B1 (en) 2006-06-30 2007-09-03 박재만 Prestressed composition girder and method of constructing continuous girder used by the composition unit girder

Also Published As

Publication number Publication date
KR20100125504A (en) 2010-12-01

Similar Documents

Publication Publication Date Title
US9657494B2 (en) Method for producing a tower construction from reinforced concrete
KR101170922B1 (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
KR101086646B1 (en) Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same
KR101240409B1 (en) Prestressed precast concrete Composite Beam and manufacture methode for there of and construction methode for there of
KR101045929B1 (en) Pro-environment prestressed long span light-weight precast concrete panel and this construction technique
KR101084993B1 (en) Prestress steel composite panel with prestress non-introducing portions provided at both ends and manufacturing method thereof
JP2005097946A (en) Construction method of bridge pier
KR101170077B1 (en) Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same
KR100343960B1 (en) Steel concrete structure
KR102440832B1 (en) Precat girder-column structure with large depth truss and construction method for the same
KR101086643B1 (en) Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
KR101157607B1 (en) Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof
KR101650431B1 (en) Precast wide composite girder with built up steel beam and prestressed concrete
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR101151773B1 (en) Prestress steel composite girder with prestress non-introducing portions respectively provided at both ends thereof and manufacturing method thereof
JP5439016B2 (en) Buried formwork
JP6817589B1 (en) How to build pile support structure
KR100860592B1 (en) Temporary system for vertical structure using precast concreat block
KR101131631B1 (en) Assembling bridge construction method using Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
WO2002092935A1 (en) Buried material unit, precast concrete panel and method of manufacturing the concrete panel, and slab and method of constructing the slab
KR20120030206A (en) A precast concrete deck and construction method for slab structure by using it
KR101084994B1 (en) Rahmen slab structure and construction method thereof
KR101131630B1 (en) Prestressed concrete panel with prestress non-introducing portions provided in both slope ends, manufacturing method thereof, precasted Rahmen and construction method thereof using the same
KR101127804B1 (en) Prestressed concrete panel with prestress non-introducing portions provided in both slope ends, manufacturing method
KR102625479B1 (en) Construction method using precast module with prestressing force

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150720

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170628

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190701

Year of fee payment: 8