CN205502340U - Peripheral coincide unit -installment floor - Google Patents

Peripheral coincide unit -installment floor Download PDF

Info

Publication number
CN205502340U
CN205502340U CN201521136783.2U CN201521136783U CN205502340U CN 205502340 U CN205502340 U CN 205502340U CN 201521136783 U CN201521136783 U CN 201521136783U CN 205502340 U CN205502340 U CN 205502340U
Authority
CN
China
Prior art keywords
floor
periphery
overlapping
coincide
overall assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201521136783.2U
Other languages
Chinese (zh)
Inventor
龚永智
余志武
丁发兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN201521136783.2U priority Critical patent/CN205502340U/en
Application granted granted Critical
Publication of CN205502340U publication Critical patent/CN205502340U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a peripheral coincide unit -installment floor, the floor system for prefabricated prestressing force or non prestressed floor, in peripheral L5~L4 cast in situs coincide area of (L is floor calculation span) of reserving of floor. It is used for being connected with the cast in situs of prefabricated wallboard, precast beam to water the coincide area after. Apply the pre -compaction load to the floor in watering the construction of coincide area after, water the congruent region fracture after preventing in the later stage use. The assembled floor, the assembly rate can reach more than 85%, the site operation process is simple to can realize the fitment, the pipeline is pre -buried and the structure integration prefabricating production of mill. The floor system for current superimposed sheet system, the stiffness is big in the installation, applicablely constructs in the big standard width of a room in an old -style house. And the wholeness in this floor system coincide district can be good to the general precast floor plank of solution that can be fine through prestressing force distinguishes the easy shortcoming that ftractures at coincide department hogging moment.

Description

A kind of overall assembled floor of periphery overlapping
Technical field
This utility model relates to a kind of overall assembled floor of building industry, and specifically a kind of periphery overlapping is whole Body assembled floor and construction method thereof.
Background technology
Building floor typically uses on-the-spot integral cast-in-situ floor, prefabricated hollow floor or superimposed sheet at present, its Middle cast-in-situ floor has an advantage that globality is strong, stress performance is good, but due to its steel bar meter, colligation, Template construct completes with maintenance molding the most at the construction field (site) with support, concreting, needs bigger material Stack and materials processing place and substantial amounts of artificial input, therefore, often result in each operation in construction the most dry Disturbing, construction quality is difficult to ensure, and situ wet workload is big, and building waste is piled up, and has a strong impact on construction field Ground and surrounding enviroment, cause environmental pollution.Although and prefabricated hollow floor easy construction, but large area building Plate due to temperature, shrink the crack that may produce in overlapping district, floor cracking phenomena is more universal and globality Poor.The most conventional laminated floor slab is generally divided into two-layer, bottom band bar-mat reinforcement prefabrication, and top layer is on-the-spot Pour.Its situ wet work operations amount is big, and assembly rate is low, and when floor is installed, rigidity is little, inapplicable opens greatly Between building.
Utility model content
This utility model solves the technical problem that and is: for existing on-the-spot integral cast-in-situ floor, precast hollow building The drawbacks described above that plate or superimposed sheet exist, it is provided that one is capable of that good integrity, crack resistance be strong, assembly rate High overall assembled floor, to meet the demand of house building industry modernization.
This utility model adopts the following technical scheme that realization:
This utility model includes a kind of overall assembled floor of periphery overlapping, and described floor is prefabricated prestressing force Or non-prestressed floor, after the upper strata periphery of floor construction layer 1 is reserved, water overlapping band 14, described after water folded Crossed belt 14 is the shaped as frame empty portions being positioned at floor upper strata periphery, waters for carrying out scene with body of wall, beam Build.
Further, the hogging moment area steel bar stress that described floor slab back casting overlaps with 14 uses prefabricated and on-the-spot peace Pretending combination, bar splicing position is crisscross arranged in nearly zero moment of flexure position, or interval set up negative reinforcement with Neighbouring floor connects.
Further, it is spaced or is abound with between the levels bar-mat reinforcement of described floor construction layer 1 continuously erection is set Muscle, described bearing rod forms space bar-mat reinforcement together with steel bar stress, distribution bar.
Preferably, watering the width overlapped with 14 after described is L/5~L/4 (L is floor effective span).
Further, vertically integrated pre-buried installation suspension ring of described floor construction layer 1 periphery, for floor Lift and plate periphery concrete is applied precompression.
Further, water the overlapping slab surfaces with 14 places after described and make coarse process.
In this utility model, described floor construction layer 1 is unidirectional or bidirectional hollow precast floor slab, in floor Portion's preheating embedding line.
Further, overall assembled floor of the present utility model also includes being arranged on floor construction layer 1 Floor decorative layer 2, described floor decorative layer 2 and floor construction layer 1 together prefabricated construction, or at floor construction Shop is carried out again after layer 1 construction.
This utility model additionally includes the construction method of the overall assembled floor of a kind of above-mentioned periphery overlapping, bag Include following steps:
The first step, above-mentioned prefabricated periphery is overlapped overall assembled floor on-site hoisting put in place, be placed on and take On the wallboard built;
Second step, longitudinal reserved steel bar of the reinforcing bar and wallboard that will water overlapping region after floor are installed and are combined;
3rd step, by prestressed cable by floor periphery to install the drag-line placed in the middle of suspension ring and wallboard solid Determine device to connect, then by jack by the installation suspension ring of drag-line fixing device tension floor periphery, to floor Overall Shi Hanzhang;
4th step, carry out concreting to watering overlapping region after floor periphery, floor and wallboard are tied It is combined;
5th step, unclamp prestressed cable, to watering overlapping band Shi Hanzhang after pouring;
6th step, to after water the flooring of overlapping region and fit up, and to non-precast floor slab decorative layer Floor carries out the construction of decorative layer.
Wherein, the concrete poured described floor slab back casting overlapping region in the 4th step is that microdilatancy is from close Real concrete.
Floor system in this utility model uses major part prefabrication to produce, and can realize finishing, pipeline Pre-buried and structure-integrated, it is greatly improved assembly rate, after reserved, water overlapping district, strengthen floor and wall The globality that body connects.At the scene in work progress can to assembled floor Shi Hanzhang of the present utility model, Strengthen the position, overlapping district of weakness, be greatly improved the cracking resistance in floor overlapping district, to overcome existing skill Floor and wallboard that art exists overlap the defect that district is easy to crack.
Compared with prior art, this utility model has the advantages that
(1) sound insulation of floor, decoration, pipe built-in produce with structure-integrated prefabrication, and assembly rate can Reach more than 85%.
(2) after reserved, water overlapping band, the globality that floor is connected with wall, beam can be strengthened.
(3) Shi Hanzhang can be passed through, the cracking resistance in floor overlapping district can be improved.
Thus visible, the overall assembled floor of the periphery that the utility model proposes overlapping, compare traditional prefabricated Floor, the integrated precast floor construction of the high assembly rate of the periphery overlapping of this utility model patent, can realize The standardized production of factory and effective mass control, the precast floor slab installed according to this utility model and wall, beam The globality connected and the crack resistance in overlapping district are more preferable, and the higher feature of assembly rate can be generally applicable to assembling In formula building.
Below in conjunction with the drawings and specific embodiments, this utility model is described further.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of the overall assembled solid floor of periphery overlapping in embodiment 1.
Fig. 2 is the schematic diagram of the overall unidirectional cassette ceiling of assembled of periphery overlapping in embodiment 2.
Fig. 3 is the schematic diagram of the overall assembled bidirectional hollow floor of periphery overlapping in embodiment 3.
Fig. 4 is the overall assembled floor scheme of installation on wallboard of periphery overlapping in embodiment 4.
Fig. 5 is the prestress application schematic diagram of the overall assembled floor of periphery overlapping in embodiment 4.
Fig. 6 is the prestress application schematic diagram of the overall assembled floor of periphery overlapping in embodiment 5.
Fig. 7 is the prestress application schematic diagram of the overall assembled floor of periphery overlapping in embodiment 6.
Label in figure: 1-floor construction layer, 2-floor decorative layer, 3-soffit reinforcing bar, 4-bearing rod, 5-installs suspension ring, 6-distribution bar, 7-zip fixing device, 8-jack, 9-prestressed cable, 10-wall Body longitudinal reinforcement, 11-sleeper, 12-body of wall, 13-plate face is born muscle, is watered overlapping band after 14-.
Detailed description of the invention
Embodiment 1
Seeing Fig. 1, a kind of overall assembled floor of periphery overlapping, described floor is prefabricated solid floor, Water overlapping band 14 after the periphery hogging moment area, upper strata of floor construction layer 1 is reserved, described after to water overlapping band 14 be position In the empty portions of floor construction layer periphery, described after to water the width overlapped with 14 be that (L is building to L/5-L/4 Plate effective span), this region is after laying with wallboard, for carrying out cast in situs with body of wall, beam, its The reserved steel bar knot of the overlapping hogging moment area steel bar stress with 14 places and floor construction layer periphery is watered after described in Close.In floor installation process can by can directly rest on wallboard, by rear pouring concrete realize wall/ Integrated connection between plate, beam/plate and plate/plate, waters overlapping band and is positioned near floor hogging moment area after floor, Reasonable stress, and avoid the anchoring original position of floor slab tops reinforcing bar, easy construction, the entirety of floor is just Degree is big, and more traditional laminated floor slab is applicable to large bay building.
Wherein, described floor construction layer 1 uses that levels bar-mat reinforcement is prefabricated to be poured, floor levels reinforcing bar 3 The bearing rod 4 arranged by interval or be abound with is bundled into bar-mat reinforcement, carries out floorslab concrete the most in a template Pouring, described bar-mat reinforcement periphery extends vertically integrated of floor construction layer 1 periphery, and length in reserve meets Bar Anchorage requirement, carries out Bar Anchorage in time building with body of wall.Water folded after described floor construction layer Crossed belt 14 arranges distribution bar 6, is crisscross arranged by distribution bar 6 in nearly zero moment of flexure position of floor, with building The bar-mat reinforcement that plate structure layer stretches out is by being welded and fixed.Bearing rod is formed together with steel bar stress, distribution bar Space bar-mat reinforcement, reaches the service behaviour of tradition cast-in-situ floor, strengthens the globality of flooring.
In the prefabrication process of floor, floor can be carried out prestressing force pressure, i.e. after concrete floor slab placement completes, The prestressed slab of floor is put tension prestress reinforcing bar with Shi Hanzhang, after making floor, water overlapping band preloading Stress, is greatly improved the cracking resistance in floor overlapping district.
The pre-buried installation suspension ring 5, Ke Yiyong of vertically integrated of rear overlapping crossed belt at described floor construction layer 1 periphery Carry out construction in lifting floor to build, can be additionally used in simultaneously and plate periphery concrete is applied precompression.
Water the overlapping slab surfaces with 14 places after described and make coarse process, in work progress to after water overlapping When band pours, the beneficially adhesion between casting concrete and floor, strengthen the knot of New-old concrete joint surface Close performance.
Embodiment 2
Seeing Fig. 2, in the present embodiment, described floor construction layer 1 is unidirectional hollowcore precast floor, in prefabricated building During plate, can realize sound insulation, decoration, pipe built-in and structural integrity at the internal preheating embedding line of floor Chemical plant Prefabrication, assembly rate is up to more than 85%, and follow-up finishing carries out stringing without chiseling floor again.
Embodiment 3
Seeing Fig. 3, in the present embodiment, described floor construction layer 1 is bidirectional hollow precast floor slab, laterally and Longitudinally it is respectively provided with hollow hole.
Pre-stress floor manufacturing process in embodiment 1 to embodiment 3 is as follows:
A. arrange bar-mat reinforcement, as presstressed reinforcing steel, then utilize pedestal tension reinforcing steel bar;
B., unidirectional drawing core pipe, or pre-buried bidirectional hollow plate magazine are installed;
C. installation plate periphery bears muscle, triangle seriality bearing rod and pre-buried suspension ring;
D. prop up double-deck lateral template, after reserving, water the region of overlapping band;
E. casting concrete, steam curing, form removal;
F. extract drawing core pipe, prestressed slab is put tension prestress reinforcing bar with Shi Hanzhang;
G. construction bottom surface and end face decorative layer, makees coarse place to watering the overlapping slab surfaces with 14 places after described Reason;
H. warehouse-in is stacked.
In the above-described embodiments, prefabricated on floor construction layer 1 build floor decorative layer 2 can be watered, it is possible at floor After-pouring molding is built in structure sheaf 1 construction.
Embodiment 4
See Fig. 4 and Fig. 5, the periphery in above-described embodiment is overlapped overall assembled floor to monolithic floor Work progress illustrates:
The first step, prefabricated periphery is overlapped overall assembled floor on-site hoisting put in place, floor construction layer 1 Periphery be placed on the body of wall 12 and sleeper 11 built, as shown in Figure 4;
Second step, longitudinal reserved steel bar of the reinforcing bar and wallboard that will water overlapping region after floor are installed and are combined, Specifically include the soffit reinforcing bar 3 that floor periphery is exposed and after the distribution bar 6 that waters in overlapping band weld Fixing;
3rd step, by prestressed cable 9, pre-buried for floor periphery installation suspension ring 5 are placed in the middle of wallboard Drag-line fixing device 7 connect, drag-line fixing device 7 is a rigid member, by all peaces of floor periphery The prestressed cable 9 that dress suspension ring connect links together, then by jack 8 by outside for drag-line fixing device Expansion, as it is shown in figure 5, jack 8 can be directly placed on floor, by jacking drag-line fixing device, The installation suspension ring of tension floor periphery are to floor entirety Shi Hanzhang;
4th step, in the case of keeping the prestress application in the 3rd step, water overlapping to after floor periphery Region carries out concreting, floor and wallboard is combined, and pours employing microdilatancy self-compaction and mixes Solidifying soil, is conducive to improving the switching performance of congruent region;
5th step, the prestress application of releasing floor, unclamp prestressed cable, and release floor is prestressed same Time, to watering overlapping band Shi Hanzhang after pouring;
6th step, to after water the flooring of overlapping region and fit up, and to non-precast floor slab decorative layer Floor carries out the construction of decorative layer.
Embodiment 5
Seeing Fig. 6, the present embodiment is the signal using two pieces of floorslab in series constructions to build, executing of embodiment 4 On the basis of work, water the hogging moment area steel bar stress of overlapping band after floor periphery and use and prefabricated tie mutually with in-site installation Closing, the plate face between floor and floor is born muscle and is used dislocation lap joint form.
Embodiment 6
See Fig. 7, the present embodiment on the basis of embodiment 5, can be between the floor building construction continuously between Every setting up plate face and bear the space bar-mat reinforcement overlap joint of muscle 13 and floor construction layer, improve the bonding strength between floor.
Embodiment above describes ultimate principle of the present utility model and principal character and of the present utility model excellent Point, skilled person will appreciate that of the industry, this utility model is not restricted to the described embodiments, above-mentioned reality Execute and specific works principle of the present utility model is simply described, without departing from this practicality described in example and description On the premise of novel spirit and scope, this utility model also has various changes and modifications, and these change and change Entering in the range of both falling within claimed this utility model, this utility model claims scope by appended power Profit claim and equivalent thereof define.

Claims (8)

1. the overall assembled floor of periphery overlapping, it is characterized in that: described floor is prefabricated prestressing force or non-prestressed floor, overlapping band (14) is watered after the upper strata periphery of floor construction layer (1) is reserved, watering overlapping band (14) after described is the shaped as frame empty portions being positioned at floor upper strata periphery, for carrying out cast in situs with body of wall, beam.
A kind of overall assembled floor of periphery overlapping the most according to claim 1, the hogging moment area steel bar stress employing of described floor slab back casting overlapping band (14) is prefabricated to combine with in-site installation, bar splicing position is crisscross arranged in nearly zero moment of flexure position, or interval is set up negative reinforcement and is connected with neighbouring floor.
A kind of overall assembled floor of periphery overlapping the most according to claim 2, being spaced or be abound with between the levels bar-mat reinforcement of described floor construction layer (1) and arrange continuous beam stud, described bearing rod forms space bar-mat reinforcement together with steel bar stress, distribution bar.
A kind of overall assembled floor of periphery overlapping the most according to claim 1, described after to water the width of overlapping band (14) be L/5~L/4, wherein L is floor effective span.
A kind of overall assembled floor of periphery overlapping the most according to claim 1, vertically integrated pre-buried installation suspension ring of described floor construction layer (1) periphery, for floor lifting and plate periphery concrete is applied precompression.
A kind of overall assembled floor of periphery overlapping the most according to claim 1, described after water the slab surfaces at overlapping band (14) place and make coarse process.
7. overlapping overall assembled floor according to a kind of periphery according to any one of claim 1-6, described floor is unidirectional or bidirectional hollow precast floor slab, the internal preheating embedding line of floor.
A kind of overall assembled floor of periphery overlapping the most according to claim 7, also include the floor decorative layer (2) being arranged on floor construction layer (1), described floor decorative layer (2) and floor construction layer (1) together prefabricated construction, or carry out shop again after floor construction layer (1) is constructed.
CN201521136783.2U 2015-12-31 2015-12-31 Peripheral coincide unit -installment floor Active CN205502340U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521136783.2U CN205502340U (en) 2015-12-31 2015-12-31 Peripheral coincide unit -installment floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521136783.2U CN205502340U (en) 2015-12-31 2015-12-31 Peripheral coincide unit -installment floor

Publications (1)

Publication Number Publication Date
CN205502340U true CN205502340U (en) 2016-08-24

Family

ID=56721077

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521136783.2U Active CN205502340U (en) 2015-12-31 2015-12-31 Peripheral coincide unit -installment floor

Country Status (1)

Country Link
CN (1) CN205502340U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507470A (en) * 2015-12-31 2016-04-20 中南大学 Periphery-overlapped integral fabricated floor and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507470A (en) * 2015-12-31 2016-04-20 中南大学 Periphery-overlapped integral fabricated floor and construction method thereof

Similar Documents

Publication Publication Date Title
CN105507470B (en) A kind of periphery overlapping overall assembled floor and its construction method
CN100416010C (en) Joint construction method of prefabricated composite bearing wall structure
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN106968381B (en) Assembled prefabricated shear wall and superimposed sheet node connected by combined grouting sleeve
CN106013432B (en) A kind of high ductility prefabricated integral frame interior joint connection structure and construction method
CN206707124U (en) Prefabricated assembling type reinforced concrete component with joint of steel structure
CN105970803B (en) The shearing resistance energy-dissipating device and construction method of assembled bridge pier
CN212026779U (en) Building node structure of assembled full-prefabricated floor slab and supporting member
CN114108917B (en) Height-adjustable assembly type composite floor slab construction method
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN108643429B (en) But height-adjusting's assembled coincide floor
CN110670770A (en) Solid shear wall and laminated plate type edge member combined structure and construction method
CN110644662A (en) Prefabricated flat slab composite slab based on stress and splitting method thereof
CN110439291A (en) A kind of assembled production and construction method suitable for low-rise building
CN106639101A (en) Assembled type cavity composite floor slab construction method
CN205502340U (en) Peripheral coincide unit -installment floor
CN208618627U (en) A kind of precast floor slab and its connection structure
CN101082241B (en) Formwork for reinforced bar concrete solid load-carrying structural storied building cover
CN203603542U (en) Fabricated electronic workshop
CN216108007U (en) Concrete beam type bridge and cast-in-situ hidden cover beam thereof
CN105951984B (en) A kind of high ductility prefabricated integral frame mid-side node connection structure and construction method
CN112900949A (en) Assembled reinforced concrete one-way multi-ribbed laminated slab floor and construction method thereof
CN203113581U (en) Ribbed steel bar truss concrete laminated slab
CN217053953U (en) Building node structure with notch assembled full-prefabricated floor slab and supporting members
CN211850334U (en) Prefabricated superimposed sheet type edge member combined structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Zhuyou Zhizao Construction Technology Group Co.,Ltd.

Assignor: CENTRAL SOUTH University

Contract record no.: X2023980037426

Denomination of utility model: A type of peripheral stacked integrated prefabricated floor slab

Granted publication date: 20160824

License type: Common License

Record date: 20230704

EE01 Entry into force of recordation of patent licensing contract