KR102065507B1 - Realtime construction work management apparatus - Google Patents

Realtime construction work management apparatus Download PDF

Info

Publication number
KR102065507B1
KR102065507B1 KR1020190016943A KR20190016943A KR102065507B1 KR 102065507 B1 KR102065507 B1 KR 102065507B1 KR 1020190016943 A KR1020190016943 A KR 1020190016943A KR 20190016943 A KR20190016943 A KR 20190016943A KR 102065507 B1 KR102065507 B1 KR 102065507B1
Authority
KR
South Korea
Prior art keywords
construction
submission
submitted
documents
evaluation
Prior art date
Application number
KR1020190016943A
Other languages
Korean (ko)
Inventor
이지연
Original Assignee
이지연
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이지연 filed Critical 이지연
Application granted granted Critical
Publication of KR102065507B1 publication Critical patent/KR102065507B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/18Legal services

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Technology Law (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a realtime construction work integrated management device. More specifically, the realtime construction work integrated management device provides a function that a technician may manage official business, construction, and quality right time according to related regulations by providing submissions to be submitted according to related statute and contract, construction confirmation performed for each construction step and work, and lists such quality standard to be checked for each user and shortens working hours by shortening access time for relative standards and simplifying unnecessary administrative power and task while performing evaluation according to the related statute in real time for completed task.

Description

실시간 건설 공사 통합 관리 장치{REALTIME CONSTRUCTION WORK MANAGEMENT APPARATUS}REALTIME CONSTRUCTION WORK MANAGEMENT APPARATUS}

본 발명은 실시간 건설 공사 통합 관리 장치에 관한 것으로, 보다 상세하게는 관련법령 및 계약서에 의거 제출되어야 할 제출 서류 및 성적서와, 시공단계 및 공사별로 수행되어야 하는 시공진행 및 상태확인, 사용자 별 확인하여야 할 품질기준 등의 목록을 제공하여 기술자가 관련규정에 따라 적기에 공무관리, 시공관리 및 품질관리가 이루어질 수 있도록 기능을 제공하고, 공사 관련 법령, 관리 방법에 대한 접근시간을 단축함으로써 불필요한 행정력 및 업무를 간소화시킴으로써 근로시간을 단축함과 더불어 완료된 업무에 대하여 실시간으로 관련법령에 따른 평가가 수행될 수 있도록 하는 실시간 건설 공사 통합 관리 장치에 관한 것이다.The present invention relates to a real-time construction integrated management device, more specifically, the submission documents and test reports to be submitted in accordance with the relevant laws and contracts, and the construction progress and status to be performed by construction stage and construction, and must be confirmed by user By providing a list of quality standards to be performed, technicians can provide timely management, construction, and quality management according to related regulations, and reduce unnecessary administrative power by reducing access time to construction laws and management methods. The present invention relates to a real-time construction integrated management device that reduces work hours by simplifying work and enables evaluation of completed work in real time according to related laws.

건설관리란 건설공사의 기초단계인 기획 단계부터 설계, 시공, 감리 및 사후 관리 단계에 관하여 관리를 하는 것이고, 각 분야의 관리업무들은 고유의 업무를 가지고 있어, 각 분야의 업무들이 계획되고 실행되는 과정에서 후발업무가 생성되므로, 공사작업의 진행되는 건설관리에 있다고 할 수 있다.Construction management is the management of the design, construction, supervision and after-sales management stages from the planning stage, which is the basic stage of construction work. The management tasks in each field have their own tasks, so that the tasks in each field are planned and executed. Since late work is created in the process, it can be said that construction work is in progress.

건설공사의 공무, 시공, 품질, 안전, 환경, 자재, 하도급 등의 각 관리업무들은 고유의 업무영역을 가지고 있어 서로 다른 업무를 수행하지만 각 관리업무의 선발(先發) 업무의 진행정도가 다른 관리업무의 후발(後發)업무의 진행에 영향을 끼치게 된다.Each management task such as public works, construction, quality, safety, environment, materials, subcontracting, etc., has its own work area and performs different tasks, but the progress of the selection tasks of each management task is different. It affects the progress of late work of management work.

한편, 건설관리 업무는 공사의 단계별, 종류별, 공법 별, 업무 유형별로 처리해야 할 업무에 대해 각각의 법령과 지침 등에 규정되어 있다. 대표적으로는 건설행정과 공사관리가 있는데, 공사의 단계별, 종류별, 공법 별, 업무유형별로 제출하여야 할 서류 및 중점적으로 검토 및 확인해야 할 점이 모두 달라 관련규정을 준수하며 적기에 이행하기란 쉽지 않다.On the other hand, construction management work is prescribed in each law and guideline about the work to be handled by construction stage, type, construction method, and work type. Representative examples are construction administration and construction management. The documents to be submitted by stage, type, construction method, and type of construction are different, and the points to be reviewed and checked are different.

또한, 공사의 단계, 종류, 공법, 업무유형별로 제출해야 하는 서류의 서류제출 기준일과 마감기한이 달라, 서류를 제출하지 못하거나 제출이 지연되는 경우가 종종 발생하고 있고, 공사 착수 전 공사에 사용되는 자재의 품질을 확인하여야 하나 적기에 확인하지 아니하고 우선시공한 경우, 자재의 품질기준이 미달되어 시공된 물량에 대한 전체 또는 부분적으로 재시공이나 보완 시공하는 경우도 종종 발생되어 공사 진행에 공정지연 및 추가비용 등이 발생되고 있다.In addition, due to different stages, types, construction methods, and types of work, the filing dates and deadlines for documents to be submitted differ, which often results in documents failing to be submitted or delayed. If the quality of the material to be used must be checked, but not prior to the timely construction, the quality standards of the material may not be met. Additional costs are incurred.

앞서 각 관리업무의 선발업무의 진행정도가 다른 관리업무의 후발업무의 진행에 영향을 끼치는 것에서 하나의 선발업무가 지연되었을 때 후속 업무에 미치는 영향(공정, 품질, 안전, 원가 등)은 실로 작지 않다고 할 수 있다.As the progress of the selection tasks of each management task affects the progress of the late tasks of other management tasks, the impact on the subsequent tasks when one selection task is delayed (process, quality, safety, cost, etc.) is very small. I can say no.

이러한 문제를 해결하기 위해, 최근에는 공사관리의 일정관리를 쉽게 할 수 있도록 지원해주는 프로그램, 시스템이 보급되고 있다. 하지만, 이러한 프로그램은 각 작업들 간의 관계정보 및 공사수행을 위해 계획된 자원의 수량 및 일정을 관리하여 공사가 지연된 경우 공사일정을 자동으로 재설정해주는 기능을 포함하고 있으나, 건설공사와 관련되어 제출되어야 할 서류를 리스트 화하여 캘린더에 표시하고, 제출물별 검토되어야 할 사항(법령, 시공방법, 평가방법, 작성방법, 예시자료)을 표기해주며, 제출 서류 별 관련규정에 따라 적기에 제출할 수 있도록 날짜를 계산하여 일정계획을 수립해주고, 제출기한을 초과한 경우 강조 표시되어 관리자에게 알려주며, 처리된 업무에 대하여 스스로 평가를 하는 기능 등이 없어 관련법령을 준수하며 효율적으로 공사관리 및 건설사업관리(공사감독 및 감리 등)가 가능하도록 하는 장치가 없어 공사현장을 효율적으로 관리하기 어렵다는 문제점이 있다.In order to solve this problem, recently, programs and systems that support easy schedule management of construction management have been spreading. However, such a program includes a function to manage the relationship information between each work and the quantity and schedule of planned resources for construction, and to automatically reset the construction schedule when construction is delayed. List the documents, mark them on the calendar, indicate the matters to be reviewed (statutes, construction methods, evaluation methods, preparation methods, and example materials) for each submission, and set the date so that they can be submitted in a timely manner according to the relevant regulations for each submission. Calculate the schedule plan, highlight the case when the deadline is exceeded, notify the manager, and do not have the function of self-evaluating the processed work, and comply with related laws and efficiently manage the construction and construction project (construction supervision) And supervision, etc.), it is difficult to efficiently manage construction sites There is a point.

한국공개특허공보 제 10-2007-0004162 호Korean Laid-Open Patent Publication No. 10-2007-0004162 일본공개특허공보 제 2006-113940 호Japanese Laid-Open Patent Publication No. 2006-113940 한국등록특허공보 제 10-1618775 호Korea Patent Publication No. 10-1618775

본 발명은 공사 단계별, 종류별 및 유형별로 제출하여야 하는 서류의 목록을 제공하여 서류의 누락을 방지하도록 하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다.An object of the present invention is to provide a real-time construction integrated management device to provide a list of documents to be submitted by stage, type and type of construction to prevent the omission of documents.

또한, 본 발명은 위의 제출서류에 대한 제출 일을 관련법령 및 기준 등에 의해 자동 계산하여 달력에 표기해주며, 이를 사전에 알려주어 제출이 지연되거나 누락되는 것을 방지하여 기술자가 관련규정을 준수 할 수 있도록 하는 것을 목적으로 한다.In addition, the present invention automatically calculates the submission date for the above submitted documents according to the related laws and standards, etc., and displays them on the calendar.Inform them in advance to prevent delays or omissions of the submission so that technicians can comply with the relevant regulations. The purpose is to make it possible.

또한, 본 발명은 각 공사 단계에 해당하는 관련 법령을 제공하여 공사단계 별로 위법 여부를 사전에 판단 할 수 있도록 하고, 관련 법령에서 규정된 업무인 경우 각 업무별로 관련법령의 해당 조항까지 제공하여 관련법령에 대한 접근성을 단축하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다.In addition, the present invention provides a related law corresponding to each construction step to determine in advance whether or not an offense per construction step, and in the case of the work prescribed in the relevant law provides up to the relevant provisions of the relevant law for each task An object of the present invention is to provide a real-time construction integrated management device that shortens the access to the law.

또한, 본 발명은 각 공사 단계의 평가항목, 방법, 점수 및 기준 등을 제공하여 업무수행과 동시에 공사현장의 사전평가를 수행할 수 있도록 사전 평가기능을 제공하여 본 평가에서 지적받는 항목 없이 원활한 평가가 이루어지도록 하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다.In addition, the present invention provides a pre-evaluation function to perform the pre-evaluation of the construction site at the same time to perform the work by providing the evaluation items, methods, scores and criteria of each construction stage, smooth evaluation without items pointed out in this evaluation An object of the present invention is to provide a real-time construction work integrated management device to be made.

또한, 본 발명은 공사의 단계별, 종류별 및 유형별로 업무 담당자를 지정하고, 업무 담당자에게 배분된 업무를 파악하는 업무분장 기능을 부여하여 업무의 형평성 있는 배분 및 원활한 인수인계를 제공하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다. In addition, the present invention designates the person in charge of work by stage, type and type of construction, and gives the work division function to grasp the work assigned to the person in charge of the work to provide a fair distribution of work and smooth handover construction integration It is an object to provide a management device.

또한, 본 발명은 공사 일정계획의 자동 수립 및 업무일정관리를 제공하고, 업무별 기준정보, 법령정보, 공법 정보에 대한 접근시간을 단축하여 원하는 정보에 대한 정확하고 신속하게 제공하여 근로자의 삶의 질을 향상 시킬 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다.In addition, the present invention provides automatic establishment of work schedule planning and work schedule management, and by reducing the access time for the standard information, law information, public law information by task to provide accurate and promptly to the desired information of workers' lives The purpose is to provide a real-time construction integrated management device that can improve the quality.

또한, 본 발명은 효율적인 장치의 사용으로 근로시간 단축으로 실제 현장 투입시간을 증대하여 건설공사의 품질향상과 안전사고 예방으로 현행의 탁상행정 체계를 현장실무 방식으로 구조개선하여 기업 및 국가의 경쟁력 제고에 기여할 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다.In addition, the present invention improves the competitiveness of the company and the country by improving the current table administration system in the field working method by improving the quality of construction work and preventing safety accidents by increasing the actual site input time by reducing the working time by using an efficient device. To provide a real-time construction integrated management device that can contribute to.

또한, 본 발명은 공사현장의 변화(설계변경 및 공사기간 조정 등)시 간단한 일정의 입력만으로 후발 업무의 일정계획을 자동 변경해주는 기능을 부여하여, 수시로 변경되는 현장여건 변화에도 공사일정의 즉각 대응 및 수정할 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다.In addition, the present invention provides a function that automatically changes the schedule of late work by simply inputting a simple schedule when the construction site changes (design change and adjustment of construction period, etc.), and immediately responds to construction schedule changes even if site conditions change from time to time. And it aims to provide a real-time construction work integrated management device that can be modified.

또한, 본 발명은 시스템을 연계하여 현장의 거리 및 개수와 상관없이 현장을 방문하지 않고도 제출되어야하는 서류의 상태(지연, 누락, 미흡)와 또는 불량 업무와 평가항목별 점수상태를 즉시 확인할 수 있도록 하여 현행 기술지원 방식 대비 기술지원에 소요되는 비용 및 시간을 획기적으로 절감할 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다.In addition, the present invention is linked to the system so that you can immediately check the status of the documents (delay, missing, insufficient) to be submitted without visiting the site irrespective of the distance and number of the site, or poor work and score status for each evaluation item It aims to provide a real-time construction integrated management device that can significantly reduce the cost and time required for technical support compared to the current technical support method.

또한, 본 발명은 관련규정에서 책임(형사 또는 민사)을 지도록 규정된 검토 또는 확인 업무에 대하여 단계별, 종류별, 유형별로 목록을 제공하고, 책임을 분명히 명확화 함으로써 기술자들이 관련규정을 우선적으로 준수할 수 있도록 하여 기술자를 형사 또는 민사책임으로부터 보호 할 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공하는 것을 목적으로 한다.In addition, the present invention provides a list by stage, type, and type for the review or verification task prescribed by the relevant regulations to be held accountable (criminal or civil), and clearly clarifies the responsibilities so that technicians can preferentially comply with the relevant regulations. It aims to provide a real-time construction integrated management device that protects technicians from criminal or civil liability.

본 발명의 목적들은 이상에서 언급한 목적으로 제한되지 않으며, 언급되지 않은 본 발명의 다른 목적 및 장점들은 하기의 설명에 의해서 이해될 수 있고, 본 발명의 실시예에 의해 보다 분명하게 이해될 것이다. 또한, 본 발명의 목적 및 장점들은 특허 청구 범위에 나타낸 수단 및 그 조합에 의해 실현될 수 있음을 쉽게 알 수 있을 것이다.The objects of the present invention are not limited to the above-mentioned objects, and other objects and advantages of the present invention, which are not mentioned above, can be understood by the following description, and more clearly by the embodiments of the present invention. Also, it will be readily appreciated that the objects and advantages of the present invention may be realized by the means and combinations thereof indicated in the claims.

본 발명의 바람직한 일실시예에 따르면, 공사의 단계 및 공법별로 제출해야 하는 항목별 제출 서류의 목록과 상기 항목별 제출 서류에서 주요하게 확인해야 하는 주요 확인 내용을 제공하는 공무 관리부; 공사별 공사관계자가 시공방법 등 시공 시 관리하여야 할 항목을 시공단계별로 제공하는 시공 관리부; 공사의 종류 및 시공단계별로 공사의 품질기준과 자재의 시험기준 및 참고기준을 제공하는 품질 관리부; 상기 공사의 종류 및 시공단계별로 시공 감독 또는 시공 감리자의 확인 항목을 제공하는 시공 검측부; 공사 및 제출된 서류를 대상으로 평가에 대비할 수 있는 점검 내용 리스트 및 평가 정보를 제공하는 점검 평가부; 및 기술자 별 업무현황 및 업무분장을 제공하고 상기 업무현황 및 업무분장을 통합관리가 가능한 본사 관리부를 포함하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, a public service management unit for providing a list of items to be submitted by each step and construction method of the construction and the main confirmation details to be confirmed in the main submission documents; A construction management unit that provides construction-specific items for each construction stage, such as construction methods, by construction personnel; A quality control department that provides construction quality standards, material testing standards, and reference standards for each type of construction and construction stage; A construction detection unit providing a construction supervision or construction supervisor's confirmation item for each type and construction stage of the construction; An inspection and evaluation unit for providing a list of inspection contents and evaluation information for the evaluation of the construction and submitted documents; And a head office management unit capable of providing a work status and work division for each technician and capable of integrated management of the work status and work division.

본 발명의 바람직한 일실시예에 따르면, 상기 공무, 시공 및 품질 관리부는 공사의 항목별 제출 서류, 주요 확인 내용, 제출 상태 및 참조 데이터가 대응되어 저장되어 있는 제출 서류 데이터베이스와 상기 제출 서류 데이터베이스에 저장된 항목별 제출 서류를 제출 일자 별로 분류하여 표시하는 스케쥴 모듈; 상기 공사의 항목별 제출 서류 각각의 제출 상태를 관리하여 상기 제출 서류 데이터베이스의 제출 상태를 갱신하는 서류 관리 모듈; 및 공사의 시공 각각의 단계에 대한 확인 항목을 제공하는 시공 관리 모듈 및 품질 관리 모듈을 포함하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the public service, construction and quality control unit stored in the submission document database and the submission document database, which is stored in correspondence with the submission documents, main confirmation details, submission status and reference data for each construction item A schedule module for classifying itemized submission documents by submission dates; A document management module for managing the submission status of each submission document for each item of the construction to update the submission status of the submission document database; And it characterized in that it comprises a construction management module and a quality management module for providing a check item for each stage of construction of the construction.

본 발명의 바람직한 일실시예에 따르면, 상기 서류 관리 모듈은 공사의 착수일과 종료일을 이용하여 항목별 제출 서류의 제출 날짜를 결정하고, 현재 날짜 및 항목별 제출 서류의 제출 날짜를 비교하여 항목별 제출 서류 각각의 제출 상태를 결정한 후, 상기 제출 서류 데이터베이스를 갱신하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the document management module determines the submission date of the item submission documents by using the start date and the end date of the construction, and submits by item by comparing the submission date of the current date and item submission documents After determining the submission status of each document, characterized in that for updating the submission document database.

본 발명의 바람직한 일실시예에 따르면, 상기 서류 관리 모듈은 공사의 항목별 서류 업로드 또는 확인 절차를 제공하여 해당 항목 각각의 제출 서류를 수신하고, 상기 항목별 서류 업로드 또는 확인 절차를 통해 항목 별 제출 서류가 업로드 또는 확인되면 해당 항목의 제출 서류의 제출 상태를 제출 완료로 결정한 후 상기 제출 서류 데이터베이스를 갱신하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the document management module provides a document upload or confirmation procedure for each item of construction to receive the submission documents of each item, and submit by item through the document upload or confirmation procedure for each item When the documents are uploaded or confirmed, the submission status of the submitted documents of the corresponding item is determined to be completed, and then the submitted documents database is updated.

본 발명의 바람직한 일실시예에 따르면, 상기 서류 관리 모듈은 공사의 항목별로 제출해야 하는 항목별 제출 서류에 대한 참조 요청에 따라 상기 제출 서류 데이터베이스에서 항목별 제출 서류에 해당하는 법령정보 데이터, 샘플양식 데이터 및 제출된 서류의 우수/미비 예시사례 데이터 및 평가 기준/방법 데이터를 독출하여 제공하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the document management module according to the request for reference to the item-specific submission documents to be submitted for each item of construction, the statutory information data, sample form corresponding to the submission documents by item in the submission document database It is characterized in that the reading and providing excellent / inferior example data and evaluation criteria / method data of the data and submitted documents.

본 발명의 바람직한 일실시예에 따르면, 상기 스케쥴 모듈은 공사의 항목별 제출 서류 각각의 제출 상태 별 표시 색상 설정 절차를 제공하고, 상기 표시 색상 설정 절차를 통해 제출 상태 별 표시 색상이 설정되면 공사의 항목별 제출 서류 각각의 제출 상태에 따라 해당 표시 색상을 이용하여 표시하고 제출당일 알림을 제공하며, 제출기한이 초과된 경우 지연된 서류의 목록을 제공하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the schedule module provides a display color setting procedure for each submission state of each of the submission documents for each item of construction, and if the display color for each submission state is set through the display color setting procedure, According to the submission status of each item of submission, it is displayed using the corresponding display color and provides notification on the day of submission, and if the submission deadline is exceeded, a list of delayed documents is provided.

본 발명의 바람직한 일실시예에 따르면, 상기 시공 관리 모듈은 공사 또는 공법별로 제출물과 함께 시공 전 단계, 시공 단계 및 시공 후 단계로 구분하여 각각의 단계에서 확인해야 하는 항목을 더 포함하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the construction management module is characterized in that it further comprises an item to be checked at each step by dividing into the pre-construction stage, the construction stage and the post-construction stage with the submission by construction or construction method do.

본 발명의 바람직한 일실시예에 따르면, 상기 품질 관리 모듈은 건설공사 및 공종 별 적용되는 법령, KS 및 시방서 등 참고기준을 제공하고, 상기 공종에 사용되는 자재의 품질기준, 허용오차, 합격 및 불합격 판정기준, 공사기록 기준 등 품질관리 기준을 제공하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the quality control module provides reference standards, such as laws, KS and specifications that are applied to construction work and type of work, and the quality standards, tolerances, passing and rejection of materials used in the work type It is characterized by providing quality control standards such as judgment criteria and construction record standards.

본 발명의 바람직한 일실시예에 따르면, 상기 점검 평가부는 공사의 단계 및 공법별로 제출된 항목 별 제출 서류를 대상으로 각종 점검에 대비할 수 있도록 점검 내용 리스트를 제공하는 점검 모듈; 및 공사 및 제출된 항목 별 제출 서류를 대상으로 평가가 진행되도록 배점 및 평가 방법을 제공하는 평가 모듈을 포함하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the inspection evaluation unit check module for providing a list of inspection contents to prepare for a variety of inspection for the submitted documents for each item submitted by the construction stage and construction method; And an evaluation module for providing a distribution and evaluation method so that the evaluation can be performed on the submitted documents for each construction and submitted items.

본 발명의 바람직한 일실시예에 따르면, 상기 평가 모듈은 항목 별 배점 변경 절차를 제공하고, 상기 배점 변경 절차를 통해 특정 항목의 배점이 변경되면 평가 그룹 각각의 그룹 배점 및 평가 그룹에 있는 항목 각각의 배점을 고려하여 상기 특정 항목의 배점이 변경되는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the evaluation module provides a point change procedure for each item, and if a point change of a specific item is changed through the point change procedure, each group in the evaluation group and each item in the evaluation group In consideration of the scoring, the distribution of the specific item is characterized in that it is changed.

본 발명의 바람직한 일실시예에 따르면, 상기 공무 관리부, 시공 검측부 및 점검 평가부에서 제공되는 정보를 기초로 사용자가 입력한 정보를 시뮬레이션하여 그 결과를 출력하는 시뮬레이션부를 더 포함하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, a simulation unit for simulating the information input by the user based on the information provided from the official management, construction detection and inspection evaluation unit and outputs the result of the characterized in that it further comprises: .

본 발명의 바람직한 일실시예에 따르면, 상기 시뮬레이션부는 상기 공무 관리부에서 제공되는 정보를 기초로 사용자가 입력한 자료 생성 참조 정보를 시뮬레이션하여 각 항목별 제출 서류를 자동으로 생성하는 것을 특징으로 한다.According to a preferred embodiment of the present invention, the simulation unit is characterized by automatically generating the submission documents for each item by simulating the data generation reference information input by the user based on the information provided from the official management unit.

전술한 바와 같은 본 발명에 의하면, 공사 단계별, 종류별 및 유형별로 제출하여야 하는 서류의 목록을 제공하여 서류의 누락을 방지하도록 하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.According to the present invention as described above, it is possible to provide a real-time construction work integrated management device to provide a list of documents to be submitted by stage, type and type of construction to prevent the omission of documents.

또한 본 발명에 의하면, 위의 제출서류에 대한 제출 일을 관련법령 및 기준 등에 의해 자동 계산하여 달력에 표기해주며, 이를 사전에 알려주어 제출이 지연되거나 누락되는 것을 방지하여 기술자가 관련규정을 준수할 수 있도록 하는 장점이 있다.In addition, according to the present invention, the date of submission of the above submitted documents is automatically calculated according to relevant laws and standards and marked on the calendar, and the technician complies with the related regulations by informing them in advance to prevent the delay or omission of the submission. There is an advantage to doing this.

또한 본 발명에 의하면, 각 공사 단계에 해당하는 관련 법령을 제공하여 공사단계 별로 위법 여부를 사전에 판단 할 수 있도록 하고, 관련 법령에서 규정된 업무인 경우 각 업무별로 관련법령의 해당 조항까지 제공하여 관련법령에 대한 접근성을 단축하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, by providing the relevant laws corresponding to each construction step to determine in advance whether there is an offense for each construction stage, and in the case of the work prescribed in the relevant laws and regulations to provide the relevant provisions of the relevant laws for each task It can provide a real-time construction integrated management device that shortens the access to the relevant laws.

또한 본 발명에 의하면, 각 공사 단계에 해당하는 관련 법령을 제공하여 공사단계 별로 위법 여부를 사전에 판단 할 수 있도록 하고, 관련 법령에서 규정된 업무인 경우 각 업무별로 관련법령의 해당 조항까지 제공하여 관련법령에 대한 접근성을 단축하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, by providing the relevant laws corresponding to each construction step to determine in advance whether there is an offense for each construction stage, and in the case of the work prescribed in the relevant laws and regulations to provide the relevant provisions of the relevant laws for each task It can provide a real-time construction integrated management device that shortens the access to the relevant laws.

또한 본 발명에 의하면, 각 공사 단계의 평가항목, 방법, 점수 및 기준 등을 제공하여 업무수행과 동시에 공사현장의 사전평가를 수행할 수 있도록 사전 평가기능을 제공하여 본 평가에서 지적받는 항목 없이 원활한 평가가 이루어지도록 하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, by providing the evaluation items, methods, scores and criteria of each construction step, and provides a pre-evaluation function to perform a pre-evaluation of the construction site at the same time to perform the work smoothly without items pointed out in this evaluation It is possible to provide a real-time construction integrated management device for evaluation.

또한 본 발명에 의하면, 공사의 단계별, 종류별 및 유형별로 업무 담당자를 지정하고, 업무 담당자에게 배분된 업무를 파악하는 업무분장 기능을 부여하여 업무의 형평성 및 원활한 인수인계를 제공하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, real-time construction construction integrated management to provide work fairness and smooth takeover by assigning a work person by step, type and type of work, and assigning a work division function to grasp the work allocated to the work person A device can be provided.

또한 본 발명에 의하면, 공사 일정계획의 자동 수립 및 업무일정관리를 제공하고, 업무별 기준정보, 법령정보, 공법 정보에 대한 접근시간을 단축하여 원하는 정보에 대한 정확하고 신속하게 제공하여 근로자의 삶의 질을 향상 시킬 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, it provides automatic establishment of work schedule planning and work schedule management, and provides accurate and promptly to the desired information by shortening the access time for the standard information, law information, public law information by work, workers' lives Real-time construction work integrated management device to improve the quality can be provided.

또한 본 발명에 의하면, 효율적인 장치의 사용으로 근로시간 단축 및 실제 현장 투입시간을 증대하여 건설공사의 품질향상과 안전사고 예방으로 현행의 탁상행정 체계를 현장실무 방식으로 구조개선하여 기업 및 국가의 경쟁력 제고에 기여할 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, by reducing the working hours and increasing the actual site input time by the use of efficient equipment to improve the quality of the construction work and to prevent safety accidents, the current table administration system is structurally improved in the field working manner to improve the competitiveness of the company and the country. Real-time construction integrated management device can be provided to contribute to the improvement.

또한 본 발명에 의하면, 공사현장의 변화(설계변경 및 공사기간 조정 등)시 간단한 일정의 입력만으로 후발 업무의 일정계획을 자동 변경해주는 기능을 부여하여, 수시로 변경되는 현장여건 변화에도 공사일정의 즉각 대응 및 수정할 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, when the construction site changes (design changes and adjustment of the construction period, etc.) by giving a function to automatically change the schedule of late work by simply inputting a simple schedule, the construction schedule immediately changes even on site conditions that are changed from time to time It is possible to provide a real-time construction integrated management device that can respond and correct.

또한 본 발명에 의하면, 시스템을 연계하여 현장의 거리 및 개수와 상관없이 현장을 방문하지 않고도 제출되어야하는 서류의 상태(지연, 누락, 미흡)와 또는 불량 업무와 평가항목별 점수상태를 즉시 확인할 수 있도록 하여 현행 기술지원 방식 대비 기술지원에 소요되는 비용 및 시간을 획기적으로 절감할 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, regardless of the distance and the number of sites in conjunction with the system, you can immediately check the status of the documents (delay, omission, insufficient) to be submitted without visiting the site or the status of the poor work and scores by evaluation items It can provide a real-time construction integrated management device that can significantly reduce the cost and time required for technical support compared to the current technical support method.

또한 본 발명에 의하면, 관련규정에서 책임(형사 또는 민사)을 지도록 규정된 검토 또는 확인 업무에 대하여 단계별, 종류별, 유형별로 목록을 제공하고, 책임을 분명히 명확화 함으로써 기술자들이 관련규정을 우선적으로 준수할 수 있도록 하여 기술자를 형사 또는 민사책임으로부터 보호 할 수 있도록 하는 실시간 건설 공사 통합 관리 장치를 제공할 수 있다.In addition, according to the present invention, by providing a list by step, type, and type for the review or verification task prescribed by the relevant regulations to have responsibility (criminal or civil), and clearly clarifying the responsibilities, technicians can preferentially comply with the relevant regulations. It is possible to provide a real-time construction integrated management device to protect technicians from criminal or civil liability.

도 1은 본 발명의 일 실시예에 따른 실시간 건설 공사 통합관리 시스템의 실행 과정을 설명하기 위한 네트워크 구성도.
도 2는 본 발명의 일 실시예에 따른 실시간 건설 공사 통합 관리 장치의 내부 구조를 설명하기 위한 블록도.
도 3 내지 도 7은 본 발명의 일 실시예에 따른 공사관리 과정을 설명하기 위한 예시도.
도 8 및 도 9는 본 발명의 일 실시예에 따른 시공 과정을 설명하기 위한 예시도.
도 10은 본 발명의 일 실시예에 따른 점검 과정을 설명하기 위한 예시도.
도 11및 도 12는 본 발명의 일 실시예에 따른 평가 과정을 설명하기 위한 예시도.
도 13 내지 도 16은 본 발명의 일 실시예에 따른 본사 관리 과정을 설명하기 위한 예시도.
1 is a network diagram illustrating an execution process of a real-time construction work integrated management system according to an embodiment of the present invention.
Figure 2 is a block diagram for explaining the internal structure of the integrated real-time construction construction management apparatus according to an embodiment of the present invention.
3 to 7 is an exemplary view for explaining a construction management process according to an embodiment of the present invention.
8 and 9 are exemplary views for explaining the construction process according to an embodiment of the present invention.
10 is an exemplary view for explaining a checking process according to an embodiment of the present invention.
11 and 12 are exemplary diagrams for explaining an evaluation process according to an embodiment of the present invention.
13 to 16 is an exemplary view for explaining a head office management process according to an embodiment of the present invention.

전술한 목적, 특징 및 장점은 첨부된 도면을 참조하여 상세하게 후술되며, 이에 따라 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 본 발명의 기술적 사상을 용이하게 실시할 수 있을 것이다. 본 발명을 설명함에 있어서 본 발명과 관련된 공지 기술에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 상세한 설명을 생략한다. 이하, 첨부된 도면을 참조하여 본 발명에 따른 바람직한 실시예를 상세히 설명하기로 한다. 도면에서 동일한 참조부호는 동일 또는 유사한 구성요소를 가리키는 것으로 사용된다.The above objects, features, and advantages will be described in detail with reference to the accompanying drawings, whereby those skilled in the art to which the present invention pertains may easily implement the technical idea of the present invention. In describing the present invention, when it is determined that the detailed description of the known technology related to the present invention may unnecessarily obscure the gist of the present invention, the detailed description will be omitted. Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the drawings, the same reference numerals are used to indicate the same or similar components.

이하에서는 첨부된 도면을 참조하여 본 발명의 실시예들을 상세히 설명하기로 한다.Hereinafter, with reference to the accompanying drawings will be described embodiments of the present invention;

도 1은 본 발명의 일 실시예에 따른 실시간 건설 공사 통합관리 시스템의 실행 과정을 설명하기 위한 네트워크 구성도이다.1 is a network diagram illustrating an execution process of a real-time construction work integrated management system according to an embodiment of the present invention.

도 1을 참조하면, 실시간 건설 공사 통합관리 시스템은 시공자 단말(100), 실시간 건설 공사 통합 관리 장치(200), 공사 감독자 단말(300), 관리자 단말(400) 및 정보 제공 서버(500)를 포함한다.Referring to FIG. 1, the real-time construction integrated management system includes a constructor terminal 100, a real-time construction integrated management apparatus 200, a construction supervisor terminal 300, a manager terminal 400, and an information providing server 500. do.

시공자 단말(100)은 공사를 시공하는 사용자가 보유하는 단말이다. 이러한 시공자 단말(100)은 스마트폰, 테블릿 PC, 노트북, 데스크 탑 등으로 구현될 수 있다.The builder terminal 100 is a terminal possessed by the user constructing the construction. The builder terminal 100 may be implemented as a smartphone, a tablet PC, a notebook, a desktop, and the like.

시공자 단말(100)은 실시간 건설 공사 통합 관리 장치(200)에서 제공하는 데이터를 사용하기 위한 어플리케이션이 설치될 수 있다. 따라서 시공자 단말(100)은 실시간 건설 공사 통합 관리 장치(200)에 접속한 후 실시간 건설 공사 통합 관리 장치(200)로부터 데이터를 수신하여 표시한다.The builder terminal 100 may be installed with an application for using the data provided by the real-time construction integrated management device 200. Therefore, the builder terminal 100 receives and displays data from the real-time construction integrated management device 200 after accessing the real-time construction integrated management device 200.

먼저, 시공자 단말(100)은 실시간 건설 공사 통합 관리 장치(200)로부터 공사의 종류, 공법, 업무유형별로 처리해야 할 업무 데이터를 수신하여 표시한다. 이때, 업무 데이터는 진행 중인 공사의 항목별로 제출해야 하는 항목별 제출 서류와 상기 항목별 제출 서류에서 주요하게 확인해야 하는 주요 확인 내용을 포함한다. First, the builder terminal 100 receives and displays work data to be processed for each type of construction, construction method, and work type from the real-time construction work integrated management device 200. At this time, the work data includes the item-specific submission documents to be submitted for each item of the ongoing construction and the main confirmation contents to be checked in the item submission documents.

즉, 시공자 단말(100)은 실시간 건설 공사 통합 관리 장치(200)로부터 진행 중인 공사의 항목별로 제출해야 하는 항목별 제출 서류 및 주요 확인 내용을 수신하여 표시한다. That is, the builder terminal 100 receives and displays the item-specific submission documents and the main confirmation contents to be submitted for each item of the ongoing construction from the real-time construction work integrated management device 200.

이때, 시공자 단말(100)은 실시간 건설 공사 통합 관리 장치(200)로부터 수신된 진행 중인 공사의 항목별로 제출해야 하는 항목별 제출 서류 업로드 절차를 수신하고, 항목별 제출 서류 업로드 절차를 통해 항목 별 제출 서류를 업로드 할 수 있다.At this time, the builder terminal 100 receives the item-by-item submission document upload procedure to be submitted for each item of the ongoing construction received from the real-time construction work integrated management device 200, and submitted by item through the item-specific submission document upload procedure You can upload documents.

시공자 단말(100)은 실시간 건설 공사 통합 관리 장치(200)로부터 항목별 제출 서류가 제출 일자 별로 분류되어 표시된 스케쥴표를 수신하여 표시한다. 시공자 단말(100)은 항목별 제출 서류 각각의 제출 상태(예를 들어, 제출완료, 제출 기한 임박, 제출 지연 등)에 따라 서로 다른 색으로 표시할 수 있도록 제출 상태 별 표시 색상 설정 절차를 통해 표시 색상을 설정할 수 있다.The builder terminal 100 receives and displays a schedule table displayed by classifying submission documents by item from the real-time construction integrated management device 200. The builder terminal 100 is displayed through the display color setting procedure for each submission state so that the builder terminal 100 can display in different colors according to the submission status (for example, submission completion, deadline for submission, delay of submission, etc.) for each item of submission. You can set the color.

또한, 시공자 단말(100)은 스케쥴표 상에 새로운 스케쥴을 추가할 수 있다.In addition, the builder terminal 100 may add a new schedule on the schedule table.

시공자 단말(100)은 실시간 건설 공사 통합 관리 장치(200)로부터 공사의 종류 및 공법 별로 주요하게 확인해야 할 내용을 수신하여 표시한다.The builder terminal 100 receives and displays the main contents to be checked for each type of construction and construction method from the real-time construction work integrated management device 200.

이때, 시공자 단말(100)은 완료된 공사 항목을 선택한 후 해당 공사 항목에 대한 검토 요청 메시지를 실시간 건설 공사 통합 관리 장치(200)를 통해 공사 감독자 단말(300)에 제공한다. At this time, the builder terminal 100 selects the completed construction item and provides a review request message for the construction item to the construction supervisor terminal 300 through the real-time construction construction integrated management device 200.

이에 따라, 공사 감독자 단말(300)은 실시간 건설 공사 통합 관리 장치(200)를 통해 공사 항목에 대한 검토 요청 사항을 확인한 후 승인할 수 있다. 그러면, 실시간 건설 공사 통합 관리 장치(200)는 승인된 항목이 건설관리대장으로 관리되어 공사 별, 위치 별로 분류하여 관리한다. Accordingly, the construction supervisor terminal 300 may confirm and approve a request for review of a construction item through the real-time construction construction integrated management device 200. Then, the real-time construction work integrated management device 200 is managed by the construction management ledger approved items are classified and managed by construction, location.

실시간 건설 공사 통합 관리 장치(200)는 정보 제공 서버(500)로부터 수신된 정보를 기초로 건설공사의 종류, 공법 및 업무유형으로 분류되어 건설공사에 대한 규정, 수행해야할 공무 및 행정업무에 대한 규정에 대한 데이터를 제공하는 장치이다.The real-time construction integrated management device 200 is classified into the type of construction work, construction method and type of work based on the information received from the information providing server 500, the regulations for construction work, public service and administrative work to be performed Device that provides data for.

이러한 실시간 건설 공사 통합 관리 장치(200)는 컴퓨터 입력장치에 의해 반응하는 웹페이지 및 어플리케이션으로 제작될 수 있으며, 휴대용 디바이스로 접속하는 웹 페이지 및 어플리케이션으로도 제작 될 수 있다. 본 발명에서는 그 어느 하나에 한정하여 설명하지 아니한다.Such a real-time construction integrated management device 200 may be produced as a web page and application to respond to the computer input device, it may also be produced as a web page and application to access to a portable device. In the present invention, the description is not limited to any one.

실시간 건설 공사 통합 관리 장치(200)는 건설공사의 종류, 공법 및 업무유형으로 분류되어 건설공사에 대한 규정, 수행해야 할 공무 및 행정업무에 대한 규정에 대한 데이터를 시공자 단말(100)에 제공하고, 시공자 단말(100)로부터 수신된 데이터를 저장하거나 공사 감독자 단말(300)에 제공할 수 있다. 이러한 실시간 건설 공사 통합 관리 장치(200)는 이하의 도 2를 참조하여 보다 구체적으로 설명하기로 한다. Real-time construction integrated management device 200 is classified into the type of construction work, construction method and type of work to provide the construction terminal 100 with data on the regulations for construction work, the regulations for public service and administrative work to be performed The data received from the builder terminal 100 may be stored or provided to the construction supervisor terminal 300. This real-time construction integrated management device 200 will be described in more detail with reference to FIG. 2 below.

공사 감독자 단말(300)은 실시간 건설 공사 통합 관리 장치(200)을 통해 시공사에 의해 요청된 사항을 확인하고 승인하는 공사 감독자가 보유하는 단말이다.The construction supervisor terminal 300 is a terminal possessed by the construction supervisor for confirming and approving the request requested by the construction company through the real-time construction construction integrated management device 200.

공사 감독자 단말(300)은 실시간 건설 공사 통합 관리 장치(200)을 통해 완료된 공사 항목에 대한 검토 요청 메시지를 수신하면, 해당 공사 항목의 내용을 확인한 후 승인 메시지를 실시간 건설 공사 통합 관리 장치(200)에 제공한다. 따라서 실시간 건설 공사 통합 관리 장치(200)는 승인된 항목이 건설관리대장으로 관리되어 공사 별, 위치 별로 분류하여 관리한다. When the construction supervisor terminal 300 receives a review request message for a completed construction item through the real-time construction work integrated management device 200, after confirming the contents of the construction item, the approval message is sent to the real-time construction work integrated management device 200. To provide. Therefore, the real-time construction work integrated management device 200 is managed by the construction management book approved items are classified and managed by construction, location.

관리자 단말(400)은 실시간 건설 공사 통합 관리 장치(200)을 통해 전체 현장을 관리하는 관리자가 보유하는 단말이다.The manager terminal 400 is a terminal held by a manager who manages the entire site through the real-time construction integrated management device 200.

이러한 관리자 단말(400)은 실시간 건설 공사 통합 관리 장치(200)을 통해 현장 정보(예를 들어, 사업자정보, 회사명)을 입력하여 해당 현장에 대한 항목별 제출 서류의 제출 상태, 제출 지연 여부, 제출 지연 일수 및 평균 제출 지연 일 수를 확인할 수 있다.The manager terminal 400 inputs site information (for example, company information and company name) through the real-time construction integrated management device 200, and the state of submission of submission documents for each site, whether to delay the submission, You can see the number of submission delays and average submission delays.

관리자 단말(400)은 실시간 건설 공사 통합 관리 장치(200)을 통해 제출 상태가 제출 지연인 제출 서류를 선택하여 해당 공사의 항목별 제출 서류 중 제출 지연된 제출 서류의 목록을 확인할 수 있다. The manager terminal 400 may select a submission document whose submission status is a submission delay through the real-time construction integrated management device 200 to check a list of submission submission delayed items among submission documents for each construction item.

또한, 관리자 단말(400)은 실시간 건설 공사 통합 관리 장치(200)을 통해 공사 별 평가 유형 및 평가 항목 별로 점수를 비교하여 관리할 수 있다. In addition, the manager terminal 400 may compare and manage scores by evaluation type and evaluation item for each construction through the real-time construction construction integrated management device 200.

정보 제공 서버(500)는 실시간 건설 공사 통합 관리 장치(200)에 정보를 제공하는 서버이다. 예를 들어, 정보 제공 서버(500)는 국가 법령 정보 및 기타 정보를 제공하는 서버에 위치할 수 있다. The information providing server 500 is a server that provides information to the real-time construction work integrated management device 200. For example, the information providing server 500 may be located in a server providing national legal information and other information.

도 2는 본 발명의 일 실시예에 따른 실시간 건설 공사 통합 관리 장치의 내부 구조를 설명하기 위한 블록도이다. 2 is a block diagram illustrating an internal structure of a real-time construction work integrated management device according to an embodiment of the present invention.

도 2를 참조하면, 실시간 건설 공사 통합 관리 장치(200)는 공무 관리부(210), 시공 관리부(220), 품질 관리부(230) 시공 검측부(240), 점검 평가부(250) 및 업무 관리부(260)를 포함한다.Referring to FIG. 2, the real-time construction integrated management device 200 includes a public service management unit 210, a construction management unit 220, a quality control unit 230, a construction detection unit 240, an inspection evaluation unit 250, and a task management unit ( 260).

공무 관리부(210)는 제출 서류 데이터베이스(211), 스케쥴 모듈(212), 서류 관리 모듈(213)을 포함하고, 시공 관리부(220)는 시공 관리 모듈(221)을 포함하며, 품질 관리부(230)는 품질 관리 모듈(231)을 포함한다.The official management unit 210 includes a submission document database 211, a schedule module 212, a document management module 213, the construction management unit 220 includes a construction management module 221, and a quality control unit 230. Includes a quality management module 231.

제출 서류 데이터베이스(211)에는 공사의 종류, 공법, 업무유형별로 처리해야 할 업무 데이터가 저장되어 있다. 이때, 업무 데이터는 진행 중인 공사의 항목별로 제출해야 하는 항목별 제출 서류와 상기 항목별 제출 서류에서 주요하게 확인해야 하는 주요 확인 내용을 포함한다. The submission document database 211 stores work data to be processed by construction type, construction method, and work type. At this time, the work data includes the item-specific submission documents to be submitted for each item of the ongoing construction and the main confirmation contents to be checked in the item submission documents.

제출 서류 데이터베이스(211)에는 서류 관리 모듈(213)에 의해 항목별 제출 서류가 업로드 되었는지 여부에 따라 결정되는 제출 상태(예를 들어, 제출완료, 제출 기한 임박, 제출 지연 등) 및 참조 데이터(예를 들어, 법령정보 데이터, 샘플양식 데이터, 우수/미비 사례 데이터 및 평가 기준 데이터 등)가 저장되어 있다. The submission document database 211 includes a submission status (e.g., submission completion, deadline for submission, delayed submission, etc.) and reference data (e.g., determined by whether the document submission by item is uploaded by the document management module 213). For example, statutory information data, sample form data, good / bad case data, evaluation criteria data, etc.) are stored.

스케쥴 모듈(212)은 제출 서류 데이터베이스(211)에 저장된 항목별 제출 서류를 제출 일자 별로 분류하여 표시한다. 이때, 스케쥴 모듈(212)은 항목별 제출 서류 각각의 제출 상태(예를 들어, 제출완료, 제출 기한 임박, 제출 지연 등)에 따라 서로 다른 색으로 표시한다. The schedule module 212 classifies and displays the submission documents for each item stored in the submission document database 211 by the submission date. At this time, the schedule module 212 displays in different colors according to the submission status (eg, submission completion, deadline, submission delay, etc.) of each item of the submitted documents.

이를 위해, 스케쥴 모듈(212)은 항목별 제출 서류 각각의 제출 상태 별 표시 색상 설정 절차를 제공하고, 표시 색상 설정 절차를 통해 표시 색상이 설정되면 해당 색상으로 제출 서류의 색을 표시한다. To this end, the schedule module 212 provides a display color setting procedure for each submission state of each item-submitted document, and displays the color of the submission document in the corresponding color when the display color is set through the display color setting procedure.

일 실시예에서, 스케쥴 모듈(212)은 항목별 제출 서류 각각의 제출 상태 별 표시 색상 설정 절차를 통해 제출 완료된 제출 서류의 표시 색상이 파란색으로 설정된 경우, 제출 완료된 제출 서류의 색을 파란색으로 표시할 수 있다.According to an embodiment, the schedule module 212 may display the color of the submitted submission documents in blue when the display color of the submitted submission documents is set to blue through the display color setting procedure for each submission status of each item of submission documents. Can be.

다른 일 실시예에서, 스케쥴 모듈(212)은 항목별 제출 서류 각각의 제출 상태 별 표시 색상 설정 절차를 통해 제출 지연된 제출 서류의 표시 색상이 빨간색으로 설정된 경우, 제출 서류의 색을 빨간색으로 표시할 수 있다.In another embodiment, the schedule module 212 may display the color of the submitted document in red when the display color of the submitted document that is delayed to submit is set to red through the procedure of setting the display color for each submission status of each item of submitted document. have.

만일, 스케쥴 모듈(212)은 제출 서류 데이터베이스(211)에 저장된 항목 별 제출 서류의 제출 상태가 제출 지연인 제출 서류의 경우, 표준 제출일로부터 지연된 일수 및 항목을 별도의 공간에 함께 표시한다. If the submission module 212 is a submission document whose submission status of the item-specific submission documents stored in the submission document database 211 is a submission delay, the schedule module 212 displays the number of days and items delayed from the standard submission date together in a separate space.

여기서, 스케쥴 모듈(212) 상에 표시된 제출 서류 데이터 각각의 제출 일자는 공사의 착수일과 종료일을 포함하며, 입력된 착수일과 종료일에 연계되어 법령에서 규정하고 있는 서류의 제출 날짜가 자동으로 계산되어 표시된다. Here, the submission date of each of the submitted document data displayed on the schedule module 212 includes the start date and the end date of the construction, and the submission date of the documents prescribed by the law is automatically calculated and displayed in connection with the entered start date and the end date. do.

스케쥴 모듈(212)은 제출 서류 데이터베이스(211)에 저장된 제출 서류 데이터에 대한 정보 이외의 추가 정보를 메모 영역을 통해 표시할 수 있다. The schedule module 212 may display additional information other than the information on the submission document data stored in the submission document database 211 through the memo area.

서류 관리 모듈(213)은 진행 중인 공사의 항목별로 제출해야 하는 항목별 제출 서류 및 주요 확인 내용을 제공한다. 예를 들어, 서류 관리 모듈(213)은 공제품자료, 자재승인, 자재신고, 견본제품, 시공계획서, 시공상세도, 시험성적서 및 보고서 등의 항목에 대한 항목별 제출 서류 및 주요 확인 내용을 제공한다. The document management module 213 provides the item-specific submission documents and the main confirmation contents to be submitted by the items of the ongoing construction. For example, the document management module 213 provides item-specific submission documents and major confirmations on items such as manufactured product data, material approval, material declaration, sample product, construction plan, construction detail, test report and report. do.

또한, 서류 관리 모듈(213)은 진행 중인 공사의 업무 종류 각각의 항목별로 항목별 제출 서류의 제출 상태를 관리하여 제출 서류 데이터베이스(211)를 갱신한다. In addition, the document management module 213 updates the submission document database 211 by managing the submission status of the item-specific submission documents for each item of the work type of construction in progress.

이를 위해, 서류 관리 모듈(213)은 공사의 착수일과 종료일을 이용하여 연계되어 법령에서 규정하고 있는 항목별 제출 서류의 제출 날짜를 결정한다. 그런 다음, 서류 관리 모듈(213)은 현재 날짜 및 항목별 제출 서류의 제출 날짜를 비교하여 항목별 제출 서류 각각의 제출 상태를 결정한 후 제출 서류 데이터베이스(211)를 갱신한다.To this end, the document management module 213 is linked by using the start date and the end date of the construction to determine the submission date of the item-specific submission documents prescribed by law. Then, the document management module 213 compares the current date and the submission date of the item-by-item submission documents, determines the submission status of each item-by-item submission document, and updates the submission document database 211.

즉, 서류 관리 모듈(213)은 현재 날짜가 항목별 제출 서류의 제출 날짜 이전인지 또는 이후인지 여부에 따라 제출 기한 임박 및 제출 지연을 결정한 후 제출 서류 데이터베이스(211)를 갱신한다. That is, the document management module 213 updates the submission document database 211 after determining the submission deadline imminent and the submission delay according to whether the current date is before or after the submission date of the item-specific submission documents.

일 실시예에서, 서류 관리 모듈(213)은 현재 날짜가 항목별 제출 서류의 제출 날짜 이전이면, 현재 날짜 및 항목별 제출 서류의 제출 날짜 사이의 차이일에 따라 제출 기한 임박 여부를 결정한다.In one embodiment, the document management module 213 determines whether the submission deadline is imminent according to a difference date between the current date and the date of submission of the itemized submission if the current date is before the date of submission of the itemized submission.

상기의 실시예에서, 서류 관리 모듈(213)은 현재 날짜 및 항목별 제출 서류의 제출 날짜 사이의 차이일이 특정일 이하이면 제출 상태를 제출 기한 임박이라고 결정한 후 제출 서류 데이터베이스(211)를 갱신한다. In the above embodiment, the document management module 213 updates the submission document database 211 after determining that the submission status is due to be due when the difference date between the current date and the submission date of the item-specific submission documents is less than or equal to a specific date. .

다른 일 실시예에서, 서류 관리 모듈(213)은 현재 날짜가 항목별 제출 서류의 제출 날짜 이후이면, 제출 상태를 제출 지연으로 결정한 후 제출 서류 데이터베이스(211)를 갱신한다. In another embodiment, the document management module 213 updates the submission document database 211 after determining the submission status as the submission delay if the current date is after the submission date of the itemized submission document.

상기의 실시예에서, 서류 관리 모듈(213)은 항목별 제출 서류의 제출 날짜를 초과한 날짜를 지연일로 산출한 후 제출 서류 데이터베이스(211)를 갱신한다. In the above embodiment, the document management module 213 updates the submission document database 211 after calculating the date exceeding the submission date of the item-specific submission documents as the delay date.

또한, 서류 관리 모듈(213)은 진행 중인 공사의 항목별로 제출해야 하는 항목별 제출 서류 업로드 및 업로드 된 서류의 확인 절차를 제공하여 해당 항목 각각의 제출 서류를 수신한다. 이때, 서류 관리 모듈(213)은 항목별 서류 업로드 및 업로드 된 서류의 확인 절차를 통해 항목 별 제출 서류가 업로드 및 서류의 업로드가 확인 되면 해당 항목의 제출 서류의 제출 상태를 제출 완료로 결정한 후 제출 서류 데이터베이스(211)를 갱신한다. In addition, the document management module 213 provides a procedure for uploading the submitted documents for each item to be submitted for each item of the construction in progress and checking the uploaded documents to receive the submitted documents for each of the corresponding items. At this time, the document management module 213, after the document upload by item and the verification of the uploaded document is confirmed by the upload document and the upload of the document is confirmed, the submission status of the document submission of the item is determined to be submitted and submitted The document database 211 is updated.

또한, 서류 관리 모듈(213)은 진행 중인 공사의 항목별 주요 확인 내용의 진행 상태를 결정한다. In addition, the document management module 213 determines the progress status of the main confirmation content for each item of the ongoing construction.

일 실시예에서, 서류 관리 모듈(213)은 특정 항목의 주요 확인 내용에 대한 확인 신호를 수신하면 해당 항목의 진행 상태를 확인 상태로 변경할 수 있다.In one embodiment, when the document management module 213 receives a confirmation signal for the main confirmation content of a specific item, the document management module 213 may change the progress state of the corresponding item to the confirmation state.

또한, 서류 관리 모듈(213)은 진행 중인 공사의 항목별로 제출해야 하는 항목별 제출 서류에 대한 참조 요청에 따라 제출 서류 데이터베이스(211)에서 항목별 제출 서류에 해당하는 참조 데이터(예를 들어, 법령정보 데이터, 샘플양식 데이터 및 제출된 서류의 우수/미비 예시사례 데이터 및 평가 기준 데이터 등)를 독출하여 제공한다. In addition, the document management module 213 according to the reference request for the item-specific submission documents to be submitted for each item of the construction in progress, the reference data corresponding to the item-specific submission documents in the submission document database 211 (for example, laws and regulations Read and provide information data, sample form data, and case data of good or incomplete examples of submitted documents and evaluation criteria data.

이와 같이, 본 발명은 항목별 제출 서류에 해당하는 참조 데이터를 제공함으로써 시스템이 없는 업체도 샘플 양식 데이터 등을 다운로드받아 사용할 수 있도록 한다. As such, the present invention provides reference data corresponding to the item-specific submission documents so that companies without a system can download and use sample form data.

한편, 시공 관리 모듈(221)은 시공 각각의 단계를 시공 전 단계, 시공 단계 및 시공 후 단계로 구분하여 각각의 시공단계에서 확인해야 하는 확인 항목을 제공한다.On the other hand, the construction management module 221 divides each stage of construction into a pre-construction stage, a construction stage and a post-construction stage to provide a check item to be confirmed at each construction stage.

시공 전 단계에 대한 확인 항목은 시공을 진행하기 위해 준비, 검토 및 사전에 확인되어야 하는 항목을 포함한다. 예를 들어, 콘크리트 공사의 경우 시공 전 단계에 대한 확인 항목은 공사 전 협의사항, 견본시공, 타설 예정 보고, 바탕준비, 환경조건 등 각각에 대한 주요 확인 내용을 포함한다.Confirmation items for the pre-construction phase include items that must be prepared, reviewed and confirmed in advance in order to proceed with the construction. For example, in the case of concrete construction, the confirmation items for the pre-construction stage include the main confirmations for each of the pre-construction discussions, sample construction, placement planning reports, ground preparation, and environmental conditions.

시공 단계에 대한 확인 항목은 공사의 순서 및 주요하게 확인하여야 할 각각의 항목을 포함한다. 예를 들어, 콘크리트 공사의 경우시공 단계에 대한 확인 항목은 타설 전 검사항목, 운반, 타설, 다짐, 마감, 양생 등 콘크리트 공사 단계별 각각에 대한 주요 확인 내용을 포함한다.Confirmation items for the construction stage include the order of construction and each item to be checked. For example, in the case of concrete construction, the confirmation items for the construction stage include the main confirmation contents for each concrete construction stage, such as inspection items before transportation, transportation, casting, compaction, finishing, and curing.

시공 후 단계에 대한 확인 항목은 청소, 양생, 보양 및 관리 방법 등에 대한 각각의 항목을 포함한다. Confirmation items for the post-construction step include respective items for cleaning, curing, maintenance and management methods.

또한, 시공 관리 모듈(221)은 공사 종류 및 유형 별 시공 감독 또는 시공 감리자의 확인 항목을 제공한다. 따라서 공사가 완료된 후 시공자는 시공 감독 또는 공사 감리자시공 감리자에게 시공 내용에 대하여 확인을 받을 때 시공 관리 모듈(221)에서 제공되는 시공 감독 또는 시공 감리자의 확인 항목을 통해 시공 내용을 확인 받을 수 있어 공사의 감독 및 감리가 효율적으로 이루어질 수 있도록 한다. In addition, the construction management module 221 provides a check item of construction supervision or construction supervisor by construction type and type. Therefore, after the construction is completed, the construction contractor can check the construction contents through the construction supervision or construction supervisor's confirmation items provided by the construction management module 221 when the construction supervisor or construction supervisor confirms the construction contents. Ensure that supervision and supervision are conducted efficiently.

품질 관리 모듈(231)은 건설공사 및 공종 별 적용되는 법령, KS 및 시방서 등 참고기준을 제공하고, 해당 공종에 사용되는 자재의 품질기준, 허용오차, 합격 및 불합격 판정기준, 공사기록 기준 등 품질관리 기준을 제공한다. The quality management module 231 provides reference standards such as laws, KS and specifications that are applied to construction works and types of work, and includes quality standards, tolerances, acceptance and rejection criteria, construction record standards, etc. Provide management standards.

시공 검측부(240)는 시공 감독 또는 시공 감리자가 공사의 종류 및 공법 별로 확인해야 할 사항을 제공한다. 시공자는 공사감독 또는 공사 감리자시공 감리자에게 시공이 완료된 항목에 대하여 확인을 받고 후속공사를 진행하도록 규정되어 있으며, 시공 감독 또는 시공 감리자는 공사종류 및 공법 별로 주요하게 확인해야할 기준, 재료, 순서와 같은 사항을 확인한다. The construction detection unit 240 provides the construction supervisor or construction supervisor to check the matter by construction type and construction method. The contractor is required to confirm the construction completed by the construction supervisor or the construction supervisor, and to carry out the subsequent construction.The construction supervisor or the construction supervisor must check the criteria, materials, order, etc. Check the details.

따라서 시공 검측부(240)는 시공 감독 또는 시공 감리자가 공사의 종류 및 공법 별로 확인해야 할 기준, 재료, 순서 등의 사항을 포함하여, 공사의 감리가 효율적으로 이루어지도록 한다.Therefore, the construction detection unit 240, including the matters, such as standards, materials, order to be confirmed by the construction supervisor or construction supervisor by the type and construction method of the construction, to ensure that the construction of the construction is efficient.

일 실시예에서, 시공 검측부(240)는 공사의 종류 및 공법 별로 주요하게 확인해야 할 내용을 분류하여 제공한다. 여기서, 시공 검측부(240)는 공사의 진행 단계별로 주요하게 확인해야 할 내용은 확인방법, 확인기준, 샘플을 참고자료로 제공하여, 정확하고 효율적으로 감리가 이루어지도록 한다.In one embodiment, the construction detection unit 240 provides a categorized content to be checked by the type and construction method of the construction. Here, the construction detection unit 240 provides the verification method, confirmation criteria, and samples as a reference material for the main contents of the construction step by step, so that the supervision can be made accurately and efficiently.

또한, 시공 검측부(240)는 시공자가 완료된 공사항목을 선택하여 감리자에게 요청하면, 감리자는 요청한 내용을 확인하고 승인할 수 있도록 하여, 상기 승인된 항목이 시공확인관리대장으로 관리되어 공사별, 위치별로 분류되어 확인내용을 확인할 수 있다.In addition, when the construction detection unit 240 selects the completed construction items and asks the supervisor, the supervisor can confirm and approve the requested contents, so that the approved items are managed by the construction confirmation management ledger for each construction, You can check the confirmation contents classified by location.

점검 평가부(250)는 점검 모듈(251) 및 평가 모듈(252)을 포함한다. The check evaluator 250 includes a check module 251 and an evaluation module 252.

점검 모듈(251)은 공사 및 제출된 서류를 대상으로 평가에 대비할 수 있도록 점검 내용 리스트를 제공한다. 이와 같이, 점검 모듈(251)이 점검 내용을 리스트로 제공함으로써 시공자는 스스로 위법행위의 여부와 미비된 서류의 평가가 이루어지기 전에 확인하여, 미비된 부분을 보완할 수 있다. 특히, 용역점검의 경우, 용역업체의 기술자에게 법령상 책임이 주어진 항목에 대해 검토가 가능하여, 공사 전반에 걸쳐 완전한 평가가 이루어질 수 있다.The inspection module 251 provides a list of inspection contents for the evaluation of the construction and submitted documents. As such, the inspection module 251 provides the inspection contents as a list, so that the contractor can check whether the illegal act and the evaluation of the incomplete document are made before the supplement is completed. In particular, in case of service inspection, it is possible to review the items that the technicians of the contractor are legally responsible for, so that a complete evaluation can be made throughout the construction.

평가 모듈(252)은 공사 및 제출된 서류를 대상으로 평가가 진행될 수 있도록 배점을 선정하고, 그 평가방법, 평가기준 및 평가요령을 제공한다. The evaluation module 252 selects a distribution point so that the evaluation can be performed on the construction and submitted documents, and provides the evaluation method, evaluation criteria, and evaluation method.

일 실시예에서, 평가 모듈(252)은 국가, 지자체 및 발주청별로 다른 배점을 변경하여 새롭게 산정할 수 있다. In one embodiment, the evaluation module 252 may be newly calculated by changing the different points for each country, municipality and ordering agency.

이를 위해, 평가 모듈(252)은 항목 별 배점 변경 절차를 제공하고, 배점 변경 절차를 통해 특정 항목의 배점이 변경되면 해당 항목의 배점을 변경 처리한다. To this end, the evaluation module 252 provides a point change procedure for each item, and if a point of a specific item is changed through the point change procedure, the point of change of the corresponding item is processed.

이때, 평가 모듈(252)은 평가 그룹 각각의 그룹 배점 및 평가 그룹에 있는 항목 각각의 배점을 고려하여 특정 항목의 배점이 변경되도록 한다. 즉, 평가 모듈(252)은 평가 그룹에 있는 항목 중 특정 항목의 배점이 변경될 때 특정 항목의 변경된 배점 및 나머지 항목의 배점을 모두 합한 점수가 해당 평가 그룹의 그룹 배점과 동일하도록 한다.In this case, the evaluation module 252 allows the distribution of specific items to be changed in consideration of the group distribution of each evaluation group and the distribution of each item in the evaluation group. That is, the evaluation module 252 when the distribution of the specific item among the items in the evaluation group is changed so that the score of the sum of the changed distribution of the specific item and the distribution of the remaining items is equal to the group distribution of the evaluation group.

또한, 평가 모듈(252)은 평가의 기준과 평가의 요령을 제공하여 평가기준을 명확하게 확인하여 평가가 이루어 질 수 있도록 한다.In addition, the evaluation module 252 provides a criterion of evaluation and a method of evaluation so that the evaluation can be clearly confirmed.

업무 관리부(260)는 기술자 별로 업무현황, 업무분장, 인수인계가 이루어질 수 있도록 한다.The task management unit 260 enables the work status, division of duties, and take over for each technician.

시뮬레이션부(270)는 공무 관리부(210), 시공 관리부(220), 품질 관리부(230), 시공 검측부(240) 및 점검 평가부(250)에서 제공되는 정보를 기초로 사용자가 입력한 정보를 시뮬레이션하여 그 결과를 출력한다.The simulation unit 270 uses the information input by the user based on information provided by the official management unit 210, the construction management unit 220, the quality control unit 230, the construction detection unit 240, and the inspection evaluation unit 250. Simulate and output the results.

먼저, 시뮬레이션부(270)는 공무, 시공, 품질 관리부(210)(220)(230)에서 제공되는 정보를 기초로 사용자가 입력한 정보를 시뮬레이션하여 각 항목 별 제출 서류를 자동으로 생성하여 제공한다.First, the simulation unit 270 simulates the information input by the user based on the information provided by the official, construction, quality control unit 210, 220, 230, automatically generates and provides the submission documents for each item. .

이를 위해, 시뮬레이션부(270)는 각 항목 별 제출 서류를 자동으로 생성하기 위한 자료 생성 참조 정보(예를 들어, 제품 자료, 제품 제조업자, 레미콘 정보, 배합 정보, 보수 재료 정보, 콘크리트 시공 계획 정보)를 입력받는다. To this end, the simulation unit 270 is the data generation reference information (eg, product data, product manufacturer, ready-mixed concrete information, formulation information, repair material information, concrete construction plan information for automatically generating the submission documents for each item) ) Is inputted.

그런 다음, 시뮬레이션부(270)는 공무, 시공, 품질 관리부(210)(220)(230)의 서류 관리 모듈(213)에 저장된 항목 별 우수 사례 데이터 중 자료 생성 참조 정보에 해당하는 우수 사례 데이터를 추출한 후 이들의 조합을 통해 항목 별 제출 서류를 자동으로 생성하여 제공할 수 있다. Then, the simulation unit 270 is to select the best case data corresponding to the data generation reference information among the best case data for each item stored in the document management module 213 of the public service, construction, quality control unit 210, 220, 230 After extraction, a combination of these can be automatically generated and provided for each item.

이때, 시뮬레이션부(270)는 자료 생성 참조 정보에 해당하는 우수 사례 데이터를 추출한 후 이들을 조합할 때 공통적인 내용들만 조합하고 공통적이지 않은 내용들이 제외한 후 항목 별 제출 서류를 자동으로 생성하여 제공할 수 있다. At this time, the simulation unit 270 extracts the best case data corresponding to the data generation reference information, and when combining them, only the common contents are combined and the non-common contents are excluded and the submission documents for each item can be automatically generated and provided. have.

또한, 시뮬레이션부(270)는 시공 검측부(240)에서 제공되는 정보를 기초로 사용자가 입력한 정보를 시뮬레이션하여 각 항목 별 제출 서류를 자동으로 생성하여 제공한다.In addition, the simulation unit 270 simulates the information input by the user based on the information provided from the construction detection unit 240 to automatically generate and provide the submission documents for each item.

이를 위해, 시뮬레이션부(270)는 시공 검측부(240)에서 제공되는 시공 감독 또는 시공 감리자가 공사의 종류 및 공법 별로 확인해야 할 사항 각각에 상태 정보 입력 절차를 제공하고, 상태 정보 입력 절차를 통해 공사의 종류 및 공법 별로 확인해야 할 사항 각각에 대한 상태 정보를 수신한다.To this end, the simulation unit 270 provides the state information input procedure to each of the construction supervision or construction supervisor provided by the construction detection unit 240 to check for each type of construction and construction method, and through the state information input procedure Receive status information on each item to be checked for each type of construction and construction method.

그런 다음, 시공 검측부(240)에서 제공되는 확인방법 및 확인기준을 기초로 상태 정보 입력 절차를 통해 입력된 상태 정보를 평가하여 시공자가 공사감독 또는 공사 감리자시공 감리자에게 시공 내용에 대한 확인을 받아보기 전에 자가 점검을 해볼 수 있도록 하였다. Then, the construction information is evaluated by the state information input procedure based on the verification method and the verification criteria provided by the construction detection unit 240, the construction manager receives the confirmation of the construction contents from the construction supervisor or construction supervisor construction supervisor You can do a self-test before you look.

또한, 시뮬레이션부(270)는 점검 평가부(250)에서 제공되는 정보를 기초로 사용자가 입력한 정보를 시뮬레이션하여 각 항목 별 제출 서류를 자동으로 생성하여 제공한다.In addition, the simulation unit 270 simulates the information input by the user based on the information provided from the check evaluation unit 250 to automatically generate and provide the submission documents for each item.

도 3 내지 도 7은 본 발명의 일 실시예에 따른 공사관리 과정을 설명하기 위한 예시도이다.3 to 7 is an exemplary view for explaining a construction management process according to an embodiment of the present invention.

도 3 내지 도 7을 참조하면, 실시간 건설 공사 통합 관리 장치(200)는 도 3을 통해 진행 중인 공사의 항목별로 제출해야 하는 항목별 제출 서류 각각의 제출 상태를 관리한다. 3 to 7, the real-time construction work integrated management device 200 manages the submission status of each of the submission documents for each item to be submitted for each item of the construction in progress through FIG. 3.

이를 위해, 실시간 건설 공사 통합 관리 장치(200)는 도 4의 참조번호(1)과 같이 공사의 착수일과 종료일을 입력받은 후 공사의 착수일과 종료일을 이용하여 연계되어 법령에서 규정하고 있는 도 4의 참조번호(5)과 같은 항목별 제출 서류의 제출 날짜를 결정한다. To this end, the real-time construction construction integrated management device 200 is inputted by the start date and end date of the construction as shown by reference number (1) of FIG. Determine the date of submission of the submission for each item, such as reference number (5).

그런 다음, 실시간 건설 공사 통합 관리 장치(200)는 현재 날짜 및 항목별 제출 서류의 제출 날짜를 비교하여 지연 여부를 결정한 후 지연 여부에 따라 지연 날짜를 함께 산출하여 도 4의 참조번호(6)과 같이 표시한다. 즉, 실시간 건설 공사 통합 관리 장치(200)는 현재 날짜 및 항목별 제출 서류의 제출 날짜를 비교하여 지연 여부에 따라 도 4의 참조번호(6)과 같이 + 또는 -를 통해 날짜를 표시한다. Then, the real-time construction integrated management device 200 compares the current date and the submission date of the item-by-item submission documents to determine whether there is a delay, calculate the delay date according to whether or not the reference number (6) of FIG. Mark it together. That is, the real-time construction integrated management device 200 displays the date through + or-as shown by reference number 6 of FIG.

또한, 실시간 건설 공사 통합 관리 장치(200)는 도 4의 참조번호(2)과 같이 진행 중인 공사의 항목별 주요 확인 내용을 제공하며, 특정 항목의 주요 확인 내용에 대한 확인 신호를 수신하면 도 4의 참조번호(4)와 같이 해당 항목의 진행 상태를 확인 상태로 변경할 수 있다.In addition, the real-time construction work integrated management device 200 provides the main confirmation for each item of the ongoing construction as shown by reference number (2) of Figure 4, when receiving the confirmation signal for the main confirmation of the specific item 4 As shown by reference number (4) of the progress of the item can be changed to the confirmed state.

또한, 실시간 건설 공사 통합 관리 장치(200)는 도 4의 참조번호(3)을 통해 참조 데이터를 제공한다. 만일, 실시간 건설 공사 통합 관리 장치(200)는 도 4의 참조번호(3)을 통해 항목별 제출 서류에 대한 참조 요청이 수신되면, 항목별 제출 서류에 해당하는 참조 데이터(예를 들어, 법령정보 데이터, 샘플양식 데이터, 우수/미비 사례 데이터 및 평가 기준 데이터 등)를 제공한다. In addition, the real-time construction integrated management device 200 provides the reference data through the reference number (3) of FIG. If the real-time construction work integrated management device 200 receives a reference request for item-specific submission documents through reference number 3 of FIG. 4, reference data corresponding to the item-specific submission documents (eg, legal information) Data, sample form data, good / negative case data and evaluation criteria data).

또한, 실시간 건설 공사 통합 관리 장치(200)는 항목별 제출 서류를 제출 일자 별로 분류하여 도 6 및 도 7과같이 표시한다. 이때, 실시간 건설 공사 통합 관리 장치(200)는 항목별 제출 서류 각각의 제출 상태(예를 들어, 제출완료, 제출 기한 임박, 제출 지연 등)에 따라 서로 다른 색으로 표시한다. In addition, the real-time construction work integrated management device 200 classifies the submitted documents for each item by submission date and display as shown in FIGS. 6 and 7. At this time, the real-time construction integrated management device 200 displays in different colors according to the submission status (for example, the completion of the submission, the deadline for submission, the submission delay, etc.) of each item of the submitted documents.

이때, 실시간 건설 공사 통합 관리 장치(200)는 도 6의 참조번호(1)과 같이 상단에 색상 별로 제출 상태가 어떠한지를 나타내는 범례를 표시한다. 예를 들어, 빨간색 = 제출지연, 노란색 = 제출 기한 임박, 파란색: 제출완료 등으로 표시할 수 있다. In this case, the real-time construction integrated management device 200 displays a legend indicating how the submission status for each color as shown in the reference number (1) of FIG. For example, red = delayed submission, yellow = deadline for submission, blue: submission complete.

이를 위해, 실시간 건설 공사 통합 관리 장치(200)는 항목별 제출 서류 각각의 제출 상태 별 표시 색상 설정 절차를 제공하고, 표시 색상 설정 절차를 통해 표시 색상이 설정되면 해당 색상으로 제출 서류의 색을 표시한다. To this end, the real-time construction integrated management device 200 provides a display color setting procedure for each submission status of each item of submission documents, and when the display color is set through the display color setting procedure, the color of the submission document is displayed in the corresponding color. do.

그런 다음, 실시간 건설 공사 통합 관리 장치(200)는 도 6의 참조번호(2)와 같이 스케줄 상에 있는 일정을 상세히 제공하고, 스케쥴 상에서 특정 일정이 선택되면 도 6의 참조번호(3)와 같이 특정 일정에 대한 상세한 정보를 제공한다.Then, the real-time construction work integrated management device 200 provides a schedule on the schedule in detail as shown by reference number (2) of FIG. 6, and when a specific schedule is selected on the schedule, as shown by reference number (3) of FIG. Provides detailed information about a specific schedule.

그리고 실시간 건설 공사 통합 관리 장치(200)는 도 7과 같이 항목별 제출 서류 중 제출 상태가 제출 지연인 제출 서류를 제공함으로써 사용자가 제출 지연인 제출 서류가 어떠한 것인지 한눈에 확인할 수 있도록 한다. In addition, the real-time construction integrated management device 200 allows the user to check at a glance what the submission documents are the delay in submission by providing a submission document whose submission status is a delay in submission as shown in FIG. 7.

도 8 및 도 9는 본 발명의 일 실시예에 따른 시공 과정을 설명하기 위한 예시도이다.8 and 9 are exemplary views for explaining the construction process according to an embodiment of the present invention.

도 8 및 도 9를 참조하면, 실시간 건설 공사 통합 관리 장치(200)는 도 8과 같이 시공 각각의 단계를 시공 전 단계, 시공 단계 및 시공 후 단계로 구분하여 각각의 단계에서 확인해야 하는 확인 항목을 제공한다.8 and 9, the real-time construction work integrated management device 200, as shown in Figure 8, each step of construction divided into pre-construction stage, construction stage and post-construction stage check items to check at each stage To provide.

시공 전 단계에 대한 확인 항목은 시공을 진행하기 위해 준비, 검토 및 사전에 확인되어야 하는 항목을 포함한다. 예를 들어, 시공 전 단계에 대한 확인 항목은 환경 조건, 견본 시공 및 바탕 준비 각각에 대한 주요 확인 내용 각각에 대한 주요 확인 내용을 포함한다.Confirmation items for the pre-construction phase include items that must be prepared, reviewed and confirmed in advance in order to proceed with the construction. For example, the verification items for the pre-construction phase include key verifications for each of the main verifications for each of the environmental conditions, sample construction, and ground preparation.

시공 단계에 대한 확인 항목은 공사의 순서 및 주요하게 확인하여야 할 각각의 항목을 포함한다. 예를 들어, 시공 단계에 대한 확인 항목은 바름 횟수, 초배 바르기, 정배지 바르기, 장판지 바르기 각각에 대한 주요 확인 내용 각각에 대한 주요 확인 내용을 포함한다.Confirmation items for the construction stage include the order of construction and each item to be checked. For example, the check items for the construction stage include the main checks for each of the main checks for each of the number of times of application, the number of times of initial application, the application of fixed media, and the loading of cardboard.

시공 후 단계에 대한 확인 항목은 청소, 양생, 보양 및 관리 방법에 대한 각각의 항목을 포함한다. Confirmation items for post-construction steps include respective items for cleaning, curing, maintenance and care methods.

또한, 실시간 건설 공사 통합 관리 장치(200)는 도 9와 같이 공사 및 공종 별 주요 확인 내용을 제공한다. 이때, 실시간 건설 공사 통합 관리 장치(200)는 공사 및 공종 별 주요 확인 항목에 대한 확인 요청 항목 선택 절차를 제공하여 시공자가 확인을 요청할 항목을 체크하도록 한다.In addition, the real-time construction work integrated management device 200 provides the main confirmation content for each construction and type, as shown in FIG. At this time, the real-time construction work integrated management device 200 provides a check request item selection procedure for the main confirmation items for each construction and construction to allow the contractor to check the item to request confirmation.

실시간 건설 공사 통합 관리 장치(200)는 확인 요청 항목 선택 절차를 통해 선택된 주요 확인 항목을 공사 감독자 단말(300)에 제공하여 공사 감독자가 승인할 수 있도록 한다. 실시간 건설 공사 통합 관리 장치(200)는 공사 감독자에 의해 주요 확인 항목의 승인이 완료되면 대장으로 관리하여 공사 별, 위치 별 시공 확인 내용을 저장하여 관리할 수 있다.The real-time construction work integrated management device 200 provides the construction supervisor terminal 300 by providing the main check items selected through the confirmation request item selection procedure so that the construction supervisor can approve. The real-time construction construction integrated management device 200 can be managed by the construction manager when the approval of the main confirmation item is completed by the construction supervisor to store and manage the construction confirmation content for each construction, location.

도 10은 본 발명의 일 실시예에 따른 점검 과정을 설명하기 위한 예시도이다.10 is an exemplary view for explaining a checking process according to an embodiment of the present invention.

도 10을 참조하면, 실시간 건설 공사 통합 관리 장치(200)는 공사 및 제출된 서류를 대상으로 평가에 대비할 수 있도록 점검 내용 리스트를 제공한다. Referring to FIG. 10, the real-time construction integrated management device 200 provides a list of check contents to prepare for the evaluation of the construction and the submitted documents.

이와 같이, 실시간 건설 공사 통합 관리 장치(200)가 점검 내용을 리스트로 제공함으로써 시공자는 스스로 위법행위의 여부와 미비된 서류의 평가가 이루어지기 전에 확인하여, 미비된 부분을 보완할 수 있다. 특히, 용역점검의 경우, 용역업체의 기술자에게 법령상 책임이 주어진 항목에 대해 검토가 가능하여, 공사 전반에 걸쳐 완전한 평가가 이루어질 수 있다.In this way, the real-time construction integrated management device 200 provides the check list as a list, the contractor can check whether the offenses themselves and the evaluation of the incomplete document before the evaluation is made, it is possible to supplement the incomplete. In particular, in case of service inspection, it is possible to review the items that the technicians of the contractor are legally responsible for, so that a complete evaluation can be made throughout the construction.

도 11및 도 12는 본 발명의 일 실시예에 따른 평가 과정을 설명하기 위한 예시도이다.11 and 12 are exemplary views for explaining an evaluation process according to an embodiment of the present invention.

도 11 및 도 12를 참조하면, 실시간 건설 공사 통합 관리 장치(200)는 도 11 및 도 12와 같이 공사 및 제출된 서류를 대상으로 평가가 진행될 수 있도록 한다. 이때, 실시간 건설 공사 통합 관리 장치(200)는 도 11의 참조번호(1)과 같이 배점을 선정하고, 도 11의 참조번호(2)를 통해 그 평가방법, 평가기준 및 평가요령을 제공한다. Referring to FIGS. 11 and 12, the real-time construction work integrated management device 200 may perform an evaluation on a construction and submitted documents as illustrated in FIGS. 11 and 12. At this time, the real-time construction integrated management device 200 selects a distribution point as shown by reference number (1) of Figure 11, and provides the evaluation method, evaluation criteria and evaluation tips through the reference number (2) of FIG.

이를 위해, 실시간 건설 공사 통합 관리 장치(200)는 도 11의 참조번호(3)를 통해 항목 별 배점 변경 절차를 제공하고, 배점 변경 절차를 통해 특정 항목의 배점이 변경되면 해당 항목의 배점을 변경 처리한다. To this end, the real-time construction integrated management device 200 provides a procedure for changing the points for each item through the reference number (3) of FIG. 11, and changes the distribution of the corresponding item when the distribution of a specific item is changed through the distribution change procedure. Process.

이때, 실시간 건설 공사 통합 관리 장치(200)는 평가 그룹 각각의 그룹 배점 및 평가 그룹에 있는 항목 각각의 배점을 고려하여 특정 항목의 배점이 변경되도록 한다. 즉, 실시간 건설 공사 통합 관리 장치(200)는 평가 그룹에 있는 항목 중 특정 항목의 배점이 변경될 때 특정 항목의 변경된 배점 및 나머지 항목의 배점을 모두 합한 점수가 해당 평가 그룹의 그룹 배점과 동일하도록 한다.At this time, the real-time construction integrated management device 200 allows the distribution of a specific item in consideration of the group distribution of each evaluation group and the distribution of each item in the evaluation group. That is, the real-time construction integrated management device 200 is such that when the distribution of a specific item among the items in the evaluation group is changed, the sum of the changed distribution of the specific item and the distribution of the remaining items is equal to the group distribution of the evaluation group. do.

도 13 내지 도 16은 본 발명의 일 실시예에 따른 본사 관리 과정을 설명하기 위한 예시도이다.13 to 16 are exemplary views for explaining a head office management process according to an embodiment of the present invention.

도 13 내지 도 16을 참조하면, 실시간 건설 공사 통합 관리 장치(200)는 기술자별로 업무현황, 업무분장, 인수인계가 이루어질 수 있도록 한다. Referring to Figures 13 to 16, the real-time construction work integrated management device 200 allows the work status, job division, takeover for each technician.

즉, 실시간 건설 공사 통합 관리 장치(200)는 도 13과 같이 현장 별로 공사 정보, 용역 정보 및 사용자 정보를 제공할 수 있다. That is, the real-time construction integrated management device 200 may provide construction information, service information and user information for each site as shown in FIG.

또한, 실시간 건설 공사 통합 관리 장치(200)는 도 14와 같이 공사 별로 제출 상태가 제출 지연인 공사장의 정보를 제공함으로써 한눈에 어느 공사의 제출 서류가 아직 제출되지 않았는지 확인할 수 있도록 한다. 즉, 본사 관리자는 제출 지연된 행정서류와 제출지연일수 및 평균제출지연 일수도 확인할 수 있으며, 제출지연건수 클릭시 해당현장으로 이동하여 누락 또는 제출 지연된 서류목록을 확인할 수 있다.In addition, the real-time construction work integrated management device 200 as shown in Figure 14 by providing the information of the construction site, the submission status is delayed for each construction so that at a glance it is possible to check whether the submitted documents of the construction is not yet submitted. In other words, the headquarters manager can check the administrative documents delayed in the submission, the number of days delayed in submission and the average number of days delayed in submission.

또한, 실시간 건설 공사 통합 관리 장치(200)는 도 15와 같이 공사 별 평가 점수를 제공함으로써 한눈에 공사 별 평가 점수를 확인할 수 있도록 한다. 이때, 실시간 건설 공사 통합 관리 장치(200)는 특정 기준으로 공사 별 평가 점수를 정렬하여 제공할 수 있다. 예를 들어, 실시간 건설 공사 통합 관리 장치(200)는 평가 점수를 내림차순 또는 오름차순으로 정렬하여 제공할 수 있다.In addition, the real-time construction work integrated management device 200 to check the evaluation score for each construction at a glance by providing a evaluation score for each construction as shown in FIG. At this time, the real-time construction integrated management device 200 may be provided by arranging the evaluation score for each construction on a specific basis. For example, the real-time construction integrated management device 200 may provide the evaluation scores sorted in descending or ascending order.

이때, 실시간 건설 공사 통합 관리 장치(200)는 회사의 년도 별 평가점수 및 년도 별 평균 점수를 제공하여 평가점수만으로 회사의 품질, 안전 및 공사관리 수준의 변화와, 외부 이미지 변화 등을 확인할 수 있도록 한다.At this time, the real-time construction integrated management device 200 provides the company's evaluation score and the average score for each year to determine the change in the company's quality, safety and construction management level and the external image change only by the evaluation score do.

또한, 실시간 건설 공사 통합 관리 장치(200)는 도 16과 같이 건설 사업 관리 용역 별 평가 점수를 제공함으로써 한눈에 건설 사업 관리 용역 별 평가 점수를 확인할 수 있도록 한다. In addition, the real-time construction work integrated management device 200 to check the evaluation score for each construction project management service at a glance by providing an evaluation score for each construction project management service as shown in FIG.

이상과 같이 본 발명은 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 발명은 상기의 실시예에 한정되는 것은 아니며, 이는 본 발명이 속하는 분야에서 통상의 지식을 가진 자라면 이러한 기재로부터 다양한 수정 및 변형이 가능하다. 따라서 본 발명 사상은 아래에 기재된 특허청구범위에 의해서만 파악되어야 하고, 이의 균등 또는 등가적 변형 모두는 본 발명 사상의 범주에 속한다고 할 것이다.As described above, although the present invention has been described by way of limited embodiments and drawings, the present invention is not limited to the above-described embodiments, which can be variously modified and modified by those skilled in the art. Modifications are possible. Therefore, the spirit of the present invention should be grasped only by the claims described below, and all equivalent or equivalent modifications thereof will belong to the scope of the present invention.

한편 본 명세서에 개시된 기술에 관한 설명은 단지 구조적 내지 기능적 설명을 위한 실시예에 불과하므로, 개시된 기술의 권리범위는 본문에 설명된 실시예에 의하여 제한되는 것으로 해석되어서는 아니 된다. 즉, 실시예는 다양한 변경이 가능하고 여러 가지 형태를 가질 수 있으므로 개시된 기술의 권리범위는 기술적 사상을 실현할 수 있는 균등물들을 포함하는 것으로 이해되어야 한다. 또한, 개시된 기술에서 제시된 목적 또는 효과는 특정 실시예가 이를 전부 포함하여야 한다거나 그러한 효과만을 포함하여야 한다는 의미는 아니므로, 개시된 기술의 권리범위는 이에 의하여 제한되는 것으로 이해되어서는 아니 될 것이다.On the other hand, the description of the technology disclosed herein is only an embodiment for structural or functional description, the scope of the disclosed technology is not to be construed as limited by the embodiments described in the text. That is, the embodiments may be variously modified and may have various forms, and thus the scope of the disclosed technology should be understood to include equivalents capable of realizing the technical idea. In addition, the objects or effects presented in the disclosed technology does not mean that a specific embodiment should include all or only such effects, and thus the scope of the disclosed technology should not be understood as being limited thereto.

또한 본 발명에서 서술되는 용어의 의미는 다음과 같이 이해되어야 할 것이다. “제1”, “제2” 등의 용어는 하나의 구성요소를 다른 구성요소로부터 구별하기 위한 것으로, 이들 용어들에 의해 권리범위가 한정되어서는 아니 된다. 예를 들어, 제1 구성요소는 제2 구성요소로 명명될 수 있고, 유사하게 제2 구성요소로 제1 구성요소로 명명될 수 있다.In addition, the meaning of the terms described in the present invention will be understood as follows. The terms “first” and “second” are used to distinguish one component from another component, and the scope of rights should not be limited by these terms. For example, a first component may be named a second component, and similarly may be named a first component as a second component.

나아가 어떤 구성요소가 다른 구성요소에 “연결되어”있다고 언급된 때에는, 그 다른 구성요소에 직접적으로 연결될 수도 있지만, 중간에 다른 구성요소가 존재할 수도 있다고 이해되어야 할 것이다. 반면에, 어떤 구성요소가 다른 구성요소에 “직접 연결되어”있다고 언급된 때에는 중간에 다른 구성요소가 존재하지 않는 것으로 이해되어야 할 것이다. 한편, 구성요소들 간의 관계를 설명하는 다른 표현들, 즉 “~사이에”와 “~사이에” 또는 “~에 이웃하는”과 “~에 직접 이웃하는” 등도 마찬가지로 해석되어야 한다.Further, when a component is referred to as being "connected" to another component, it should be understood that there may be another component in between, although it may be directly connected to the other component. On the other hand, when a component is referred to as being "directly connected" to another component, it should be understood that there is no other component in between. On the other hand, other expressions that describe the relationship between the components, such as "between" and "between," or "neighboring to," and "direct neighboring to" should be interpreted as well.

단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한 복수의 표현을 포함하는 것으로 이해되어야 하고, “포함하다”또는 “가지다” 등의 용어는 설시된 특징, 숫자, 단계, 동작, 구성요소, 부분품 또는 이들을 조합한 것이 존재함을 지정하려는 것이며, 하나 또는 그 이상의 다른 특징이나 숫자, 단계, 동작, 구성요소, 부분품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다.Singular expressions should be understood to include plural expressions unless the context clearly indicates otherwise, and terms such as “include” or “have” refer to features, numbers, steps, actions, components, parts, or parts thereof described. It is to be understood that the combination is intended to be present and does not exclude in advance the possibility of the presence or addition of one or more other features or numbers, steps, actions, components, parts or combinations thereof.

이상과 같이 본 발명은 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 발명은 상기의 실시예에 한정되는 것은 아니며, 이는 본 발명이 속하는 분야에서 통상의 지식을 가진 자라면 이러한 기재로부터 다양한 수정 및 변형이 가능하다. 따라서 본 발명 사상은 아래에 기재된 특허청구범위에 의해서만 파악되어야 하고, 이의 균등 또는 등가적 변형 모두는 본 발명 사상의 범주에 속한다고 할 것이다.As described above, although the present invention has been described by way of limited embodiments and drawings, the present invention is not limited to the above-described embodiments, which can be variously modified and modified by those skilled in the art. Modifications are possible. Therefore, the spirit of the present invention should be grasped only by the claims described below, and all equivalent or equivalent modifications thereof will belong to the scope of the present invention.

100: 시공자 단말
200: 실시간 건설 공사 통합 관리 장치
210: 공무 관리부 211: 제출 서류 데이터베이스
212: 스케쥴 모듈 213: 서류 관리 모듈
220: 시공 관리부 221: 시공 관리 모듈
230: 품질 관리부 231: 품질 관리 모듈
240: 시공 검측부 250: 점검 평가부
251: 점검 모듈 252: 평가 모듈
260: 업무 관리부 270: 시뮬레이션부
300: 공사 감독자 단말 400: 관리자 단말
500: 정보 제공 서버
100: constructor terminal
200: real-time construction integrated management device
210: Government Affairs Department 211: Submitted Documents Database
212: schedule module 213: document management module
220: construction management unit 221: construction management module
230: quality control unit 231: quality control module
240: construction detection unit 250: inspection evaluation unit
251: check module 252: evaluation module
260: business management unit 270: simulation unit
300: construction supervisor terminal 400: manager terminal
500: informational server

Claims (7)

건설공사 수행 시 관련법령 또는 계약내용에 따라 제출되어야 할 제출 서류와 서류 작성 시 포함되어야 하는 항목과 기준을 제공하여 제출 서류를 적기에 제출하고 적정성이 확보되어지도록 하고, 관련법령에서 규정된 사항에 대하여 실시간으로 법령을 확인할 수 있도록 하며, 관련법령 및 계약내용에서 규정한 시공 품질기준, 현장 관리기준 및 자재 품질기준 및 기준에 따른 확인방법을 제공하여, 적기에 업무수행이 이루어지도록 하는 실시간 건설 공사 통합 관리 장치에 있어서,
공사의 단계 및 공법별로 제출해야 하는 항목별 제출 서류의 목록과 상기 항목별 제출 서류에서 포함되어야 하는 내용 및 제출 서류에서 주요하게 확인되어야 하는 주요 확인 내용을 제공하는 공무 관리부(210)와,
시공 시 관리하여야 할 항목을 시공단계별로 구분하여 공사관계자에게 제공하는 시공 관리부(220);와
공사의 종류 및 시공단계별로 공사의 품질기준과 자재의 시험기준 및 참고기준을 제공하는 품질 관리부(230);와
상기 공사의 종류 및 시공단계별로 확인되어야 하는 항목을 시공 감독 또는 시공 감리자에게 제공하는 시공 검측부(240);와
공사의 단계 및 공법별로 제출된 항목 별 제출 서류와 시공관리 및 품질관리 기준을 대상으로 각종 점검에 대비할 수 있도록 점검 내용 리스트를 제공하는 점검 모듈(251)과, 공사관리, 품질관리 및 항목 별로 제출된 서류를 대상으로 평가가 진행되도록 배점 및 평가 방법을 제공하는 평가 모듈(252)을 포함하는 점검 평가부(250);와
기술자 별 업무 처리현황과 업무분장을 통합관리하고 기술자 간의 인수인계를 지원하는 업무 관리부(260);와
상기 공무, 시공, 품질 관리부(210,220,230)와 시공 검측부(240) 및 점검 평가부(250)에서 제공되는 정보를 기초로, 관리자에 의해 입력된 공사 정보를 시뮬레이션하여 항목 별 제출 서류 목록을 생성하는 시뮬레이션부(270);로 구성되되,
상기 공무 관리부(210)는 관련법령 및 계약내용에 따라 제출되어야 하는 제출 서류와 제출물별로 포함되어야 하는 항목을 결정하고, 공사 항목별 제출서류와 주요 확인 내용 및 참조 데이터가 저장된 제출 서류 데이터베이스(211);와,
상기 제출 서류 데이터베이스(211)에 저장된 항목별 제출 서류를 법령에 규정된 일자별로 분류하고 제출 서류의 내용을 표시하는 스케쥴 모듈(212);과,
상기 제출 서류 데이터베이스(211)에 저장되어 공사 항목별로 제출되어야 하는 제출 서류에 관련된 법령정보를 포함하는 법령정보 데이터와, 제출 서류의 작성 예시가 포함된 샘플 양식 데이터와, 공사현장의 우수/미비 사례가 포함된 예시사례 데이터와, 공사현장의 평가 기준/방법이 작성된 기준/평가 데이터를 제공하는 서류 관리 모듈(213);을 포함하고,
상기 시공 관리부(220)는 공사 또는 공법별로 제출되어야 하는 제출물과 함께 시공 전 단계, 시공 단계 및 시공 후 단계로 구분되어 각각의 단계에서 확인해야 하는 항목이 제공되며, 시공 내용에 대해 감리가 이루어 질 때 상기 시공 전 단계, 시공 단계 및 시공 후 단계에서 제공되는 확인해야 하는 항목을 통해 감리가 이루어지도록 하는 시공 관리 모듈(221);을 포함하고,
상기 품질 관리부(230)는 공종에 사용되는 자재의 품질기준, 허용오차, 합격 및 불합격 판정기준, 공사기록의 품질관리 기준과 법령, KS 및 시방서에 따른 참고기준을 제공하는 품질 관리 모듈(231);을 포함하는 것을 특징으로 하는 실시간 건설 공사 통합 관리장치.
Provide the documents to be submitted in accordance with the related laws or contracts and the items and criteria to be included in the preparation of the construction work in order to ensure that the documents are submitted in a timely manner and ensure appropriateness. Real-time construction work to check the laws and regulations in real time, and provide verification methods according to the construction quality standards, site management standards, and material quality standards and standards prescribed in the relevant laws and contract details, to ensure that timely work is performed. In the integrated management device,
The public service management unit 210 which provides a list of the documents to be submitted by the items to be submitted by the stage and construction method of the construction, the contents to be included in the documents to be submitted by the items, and the main confirmation contents to be mainly checked in the documents to be submitted.
Construction management unit 220 to provide to the construction personnel by classifying the items to be managed at construction stage by construction stage; and
Quality management unit 230 for providing the quality standards and materials testing standards and reference standards of construction by type and construction stage of the construction; and
A construction detection unit 240 for providing a construction supervisor or a construction supervisor with an item to be checked for each type and construction stage of the construction; and
Inspection module (251) that provides a list of inspection contents to prepare for various inspections for the submitted documents and construction management and quality control standards submitted by each stage and construction method, and submitted by construction management, quality control and items A check evaluator 250 including an evaluation module 252 for providing a scoring and evaluation method for the evaluation of the collected documents; and
A task management unit 260 that integrates and manages the work processing status and work division for each technician and supports the handover between technicians; and
On the basis of the information provided by the official, construction, quality control unit 210, 220, 230 and the construction detection unit 240 and the inspection evaluation unit 250, to simulate the construction information input by the manager to generate a list of submission documents for each item Simulation unit 270; consisting of,
The public service management unit 210 determines the documents to be submitted and items to be included in each submission according to the related laws and contracts, and the submission documents database 211 storing the submitted documents for each construction item, main confirmation contents, and reference data. ;Wow,
A schedule module 212 for classifying the submitted documents for each item stored in the submitted documents database 211 by the date defined in the law and displaying the contents of the submitted documents;
Statutory information data including statutory information related to the submitted document to be stored in the submitted document database 211 to be submitted for each construction item, sample form data including an example of preparation of the submitted document, and excellent / incomplete cases of the construction site. Includes; the document management module 213 that provides example case data and a standard / evaluation data is written, the evaluation criteria / method of the construction site, including,
The construction management unit 220 is divided into pre-construction stages, construction stages and post-construction stages with the submissions to be submitted by construction or construction method, and items to be checked at each stage are provided, and the construction contents are supervised. When the construction management module 221 to be supervised through the items to be provided in the pre-construction stage, construction stage and post-construction stage;
The quality control unit 230 provides a quality control module 231 providing reference standards according to quality standards, tolerances, acceptance and rejection criteria, construction records quality control standards and laws, KS and specifications of materials used in the work type. Real-time construction work integrated management device comprising a.
제 1 항에 있어서,
상기 서류 관리 모듈(213)은
항목별로 제출해야 하는 제출 서류 및 주요 확인 내용을 제공하며, 상기 제출 서류는 제출 될 때, 공사의 항목별로 제출되어야 하는 서류의 업로드 확인 절차를 제공하여 제출 서류 각각의 제출 여부가 수신되어 상기 제출 서류의 업로드 확인 절차를 통해 제출 서류의 업로드가 확인되면, 제출 서류의 상태를 제출 완료로 갱신하고,
상기 제출 서류는 현재 날짜와 제출 날짜를 비교하여 제출 상태를 결정하되, 제출 날짜의 전후 여부에 따라 제출 상태를 제출 기한 임박 또는 제출 지연으로 결정하고, 현재 날짜와 제출 서류의 제출 날짜 사이의 차이일이 특정일 이하이면, 제출 상태를 제출 기한 임박으로 결정하여 제출 서류 데이터베이스(211)를 갱신하는 것을 특징으로 하는 실시간 건설 공사 통합 관리 장치.
The method of claim 1,
The document management module 213 is
Provides the documents to be submitted by each item and the main confirmation contents.The documents to be submitted provide a confirmation procedure for uploading documents to be submitted for each item of the construction when submitted, and whether or not each submission is received. Once your upload has been confirmed by the upload verification process, your status of the submission will be updated to Submitted.
The submitted document shall determine the submission status by comparing the current date with the submission date, and the status of submission shall be determined as the due date or delay of submission, depending on whether the submission date is before or after the submission date, and the difference date between the current date and the submission date of the submission If it is less than this specific day, the real-time construction construction integrated management device characterized by updating a submission document database 211 by determining a submission state as the submission deadline imminent.
제 1 항에 있어서,
상기 스케쥴 모듈(212)은
관련규정 및 계약내용에 따라 제출되어야 하는 제출 서류 각각의 제출 일자가 관련규정에서 규정하고 있는 제출 날짜로 계산되고,
상기 제출 서류는 공무 관리부(210)에 입력된 착수일과 종료일에 연계되어 법령에서 규정하는 제출 날짜를 산출하고 캘린더에 일자별로 표시되어지되, 공사현장의 상황 및 공사여건에 따라 공사 일정이 변경되면 변경된 공사 일정에 맞게 후발 업무계획과 제출 서류의 제출 날짜가 자동으로 변경되어지도록 하며,
상기 제출 날짜가 결정된 제출 서류는 제출 여부 및 제출 날짜까지 남은 날짜에 따라, 제출 상태를 제출 완료, 제출 기한 임박, 제출 지연 및 미제출 중 하나로 설정되며,
상기 제출 상태가 결정된 제출 서류는 공무 관리부(210)에 입력된 제출 날짜까지 남은 날짜와 제출 서류의 제출 상태에 따라 지정된 색상 및 영역으로 구분되어 캘린더에 일자별로 표시되고, 상기 제출 서류 중 지연 제출 또는 미제출 된 서류는 별도의 공간에 추가로 기재되어 제출 지연대장으로 작성되어 공사별 또는 위치별로 분류되어 관리되어지고,
상기 캘린더에 표시된 제출 서류 중 하나가 선택되면, 상기 제출 서류는 제출 서류와 관련된 일정과 추가 정보의 기재가 가능한 메모 영역이 표시되어지는 것을 특징으로 하는 실시간 건설 공사 통합 관리 장치.
The method of claim 1,
The schedule module 212 is
The submission date of each submitted document to be submitted in accordance with the relevant regulations and contract details shall be calculated as the submission date specified in the relevant regulations.
The submitted documents are calculated in accordance with the laws and regulations in connection with the start date and the end date entered into the official management 210 and displayed on the calendar by date, if the construction schedule is changed according to the construction site conditions and construction conditions The date of submission of late work plan and submitted documents is automatically changed in accordance with the construction schedule.
The submitted documents for which the submission date has been determined are set to one of the submission status, the submission deadline, the submission delay, and the non-submission, depending on whether the submission date and the remaining date until the submission date,
The submitted documents in which the submission status is determined are classified by color and area designated according to the remaining date of the submission date entered into the official management unit 210 and the submission status of the submitted documents, and are displayed by date on a calendar. Unsubmitted documents are additionally listed in a separate space, prepared as a delayed submission book, and classified and managed by construction or location.
When one of the submission documents displayed in the calendar is selected, the submission document is a real-time construction work integrated management device, characterized in that the memo area that can be written of the schedule and additional information associated with the submission documents are displayed.
◈청구항 4은(는) 설정등록료 납부시 포기되었습니다.◈Claim 4 has been abandoned upon payment of a set-up fee. 제 1 항에 있어서,
상기 시공 관리 모듈(221)은
시공 각각의 단계를 시공 전 단계, 시공 단계 및 시공 후 단계로 구분하여 각각의 시공단계에서 확인해야 하는 항목을 제공하되,
상기 시공 전 단계에서는 시공을 진행하기 위한 작업준비, 검토사항, 협의사항, 견본시공, 환경조건의 데이터가 제공되며,
상기 시공 단계에서는 공사의 순서, 주의사항, 진행 중인 공사 항목 중 주요하게 확인되어야 하는 항목과 상기 항목의 준수 여부에 따른 우수/미흡 사례 자료가 제공되고,
상기 시공 후 단계에서는 청소, 관리 방법에 대한 데이터가 제공되며,
시공이 완료된 후, 시공감리자가 확인해야 할 항목이 공사의 종류와 유형별로 제공되어, 시공 내용의 감독과 감리가 이루어지도록 하는 것을 특징으로 하는 실시간 건설 공사 통합 관리장치.
The method of claim 1,
The construction management module 221 is
Each stage of construction is divided into pre-construction stage, construction stage and post-construction stage to provide the items to be checked at each construction stage.
In the pre-construction stage, data on work preparation, review matters, consultation matters, sample construction, and environmental conditions are provided.
In the construction phase, the main order of the construction, precautions, items that should be checked among the ongoing construction items, and excellent / poor case data according to compliance with the above items are provided.
In the post-construction step, data on cleaning and management methods is provided.
After the construction is completed, the construction supervisor is provided with the items to be checked by the type and type of construction, the supervision and supervision of the construction contents, real-time construction construction integrated management device characterized in that.
제 1 항에 있어서,
상기 시공 검측부(240)는
공사의 종류 및 공법별로 확인해야 할 내용을 공사의 단계별로 기준, 재료, 순서별로 분류하여 시공 검측기준을 제공하고,
상기 공사의 종류 및 공법에 따라 공사확인방법, 공사확인기준, 샘플 참고자료를 추가로 제공되며,
관련규정 및 공사계획에 따라 부분적으로 공사가 완료되거나 후속공사의 진행이 필요하게 되면, 공사가 완료된 공사항목을 선택하여 감리자에게 감리 요청이 발송하고, 감리자는 감리 요청된 항목이 수신되면 공사종류, 공법, 재료, 순서 및 각 공사 단계별로 주요하게 확인되어야 할 사항이 표시되어 상기 감리 요청된 항목의 후속공사 진행 여부의 결정이 가능하며,
상기 감리 요청된 항목 중 후속공사 진행이 승인된 항목은 공사별, 위치별로 분류되어 시공확인 관리대장으로 관리 되어지는 것을 특징으로 하는 실시간 건설 공사 통합 관리 장치.
The method of claim 1,
The construction detection unit 240 is
Provides construction inspection criteria by classifying contents to be checked by construction type and construction method by criteria, materials, and order of construction stages.
According to the type and construction method of the above construction, additional construction verification methods, construction verification standards, and sample reference materials are provided.
When the construction is partially completed or the follow-up construction is required according to the related regulations and the construction plan, the supervisor request is sent to the supervisor by selecting the completed construction item, and the supervisor receives the supervision request. The construction method, materials, order, and major items to be checked at each construction stage are displayed, and it is possible to determine whether to proceed with the subsequent construction of the requested item for supervision.
The real-time construction work integrated management device, characterized in that the items approved for the progress of the subsequent construction of the supervision requested items are classified by construction and location and managed by the construction confirmation management ledger.
◈청구항 6은(는) 설정등록료 납부시 포기되었습니다.◈Claim 6 has been abandoned upon payment of a setup registration fee. 제 1 항에 있어서,
상기 점검 모듈(251)은
평가가 진행되기 전에 공사항목 및 제출된 서류를 대상으로 서류의 제출이 미비 되거나, 위법행위가 발생 된 공사항목의 보완이 이루어지도록 점검 내용 리스트가 제공되어 법령상 책임이 있는 항목에 대해 사전검토가 가능하며,
상기 평가 모듈(252)은 공사항목 및 제출이 완료된 서류를 대상으로 관련법령에 규정된 배점을 산정하고, 평가방법, 평가기준 및 평가요령을 제공하여 평가가 진행되도록 하되, 상기 배점은 국가, 지자체 및 발주청별로 상이한 평가방법, 평가기준, 평가요령 및 배점을 적용하여 평가가 가능하며,
평가 그룹에 있는 항목 중 특정 항목의 배점이 변경되면 특정 항목의 변경된 배점 및 나머지 항목의 배점을 모두 합한 점수가 기존 그룹의 배점을 모두 합한 점수와 동일하도록 배점이 변경되어지며,
평가 모듈(252)에 의해 평가가 완료되어 점수 집계된 공사 및 제출 서류는 공사 현장별, 연도별로 분류되어 평가 점수 및 상기 평가 점수의 평균 점수가 제공되는 것을 특징으로 하는 실시간 건설 공사 통합 관리 장치.
The method of claim 1,
The check module 251 is
Before the evaluation is conducted, a list of checks is provided to supplement the construction items that have been submitted to the construction items and submitted documents, or to make up for the illegal items. Is possible,
The evaluation module 252 calculates the distribution point prescribed in the relevant laws and regulations for the construction items and the documents that have been submitted, and provides an evaluation method, evaluation criteria, and evaluation tips so that the evaluation can proceed, but the distribution point is a state or a local government. And can be evaluated by applying different evaluation methods, evaluation criteria, evaluation tips and points for each client.
If the distribution of a particular item among the items in an evaluation group is changed, the score is changed so that the sum of both the changed distribution of the specific item and the distribution of the remaining items is the same as the sum of the distributions of the existing group.
Real-time construction work integrated management device, characterized in that the evaluation is completed by the evaluation module 252, the construction and submission documents, the score is classified by construction site, year by year and the evaluation score and the average score of the evaluation score is provided.
◈청구항 7은(는) 설정등록료 납부시 포기되었습니다.◈Claim 7 was abandoned upon payment of a set-up fee. 제 1 항에 있어서,
상기 시뮬레이션부(270)는
공무 관리부(210), 시공 관리부(220), 품질 관리부(230), 시공 검측부(240) 및 점검 평가부(250)에서 제공되는 정보와 사용자에 의해 입력된 자료 생성 참조 정보를 시뮬레이션하여 각 항목별로 제출되어야 하는 제출 서류 목록을 생성하되,
상기 공무관리부(210)는 제출 서류 데이터베이스(211) 및 스케쥴 모듈(212)에서 추출된 제출 서류 및 제출 날짜 데이터와 상기 서류 관리 모듈(213)에 저장된 우수, 미흡, 기준 사례 데이터에서 추출된 자료 생성 참조 정보 중 공통으로 입력된 데이터를 비교 및 조합하여 항목별 제출 서류와 시공 기준 및 품질 기준 데이터를 시뮬레이션부(270)에 제공하고,
상기 시공 관리부(220)는 시공 각각의 단계를 시공 전 단계, 시공 단계, 시공 후 단계로 구분되어 각각의 시공단계에서 확인되어야 하는 항목을 시뮬레이션부(270)에 제공하며,
상기 품질 관리부(230)는 건설공사 및 공종 별 적용되는 법령, KS 및 시방서와, 상기 공종에서 사용되는 자재의 품질기준, 허용오차, 합격 및 불합격 판정기준, 공사기록 기준을 시뮬레이션부(270)에 제공하고,
상기 시공 검측부(240)는 공사의 종류 및 공법 별로 확인되어야 할 시공 기준, 시공 재료, 시공 순서별로 분류된 시공 검측기준과 상기 공사의 종류 및 공법에 따라 공사 확인방법, 공사 확인기준, 샘플 참고자료를 시뮬레이션부(270)에 제공하며,
상기 점검 평가부(250)는 공사의 진행상태 및 제출된 서류를 대상으로 평가에 대비할 수 있는 점검 내용 리스트와, 평가방법, 평가기준, 평가요령 및 배점 정보를 시뮬레이션부(270)에 제공되어 입력되어지도록 하고,
상기 자료 생성 참조 정보는 제품 자료, 제품 제조업자 정보, 견본 제품 정보, 시공 계획 정보, 시공 상세 정보, 공사 진행 상태를 시뮬레이션부(270)에 제공하여 입력되어지도록 하되,
상기 시뮬레이션부(270)는 공무 관리부(210), 시공 관리부(220), 품질 관리부(230), 시공 검측부(240)에서 제공되는 정보와 상기 자료 생성 참조 정보의 조합에서 공통적으로 포함되는 항목을 추출하고, 항목별로 제출 되어야 하는 서류가 시뮬레이션되어 생성 되어지며,
상기 시뮬레이션부(270)는 점검 평가부(250)에서 제공되는 점검 및 평가 자료와 시공 완료된 공사 및 제출된 서류의 조합에서 평가가 진행되기 전에 위법행위의 여부와 미비 된 서류의 확인 및 자가 점검이 가능하도록 시뮬레이션 되는 것을 특징으로 하는 실시간 건설 공사 통합 관리 장치.
The method of claim 1,
The simulation unit 270 is
Each item by simulating the information provided by the official management unit 210, the construction management unit 220, the quality control unit 230, the construction detection unit 240 and the inspection evaluation unit 250 and the data generation reference information input by the user Create a list of documents to be submitted
The official management unit 210 generates data extracted from the submitted documents and the submission date data extracted from the submission document database 211 and the schedule module 212 and the excellent, insufficient, reference case data stored in the document management module 213. Compare and combine the data commonly input among the reference information, and provide the simulation document 270 with the submission documents, construction standards and quality criteria data for each item,
The construction management unit 220 is provided to the simulation unit 270 to be identified at each construction stage by dividing each construction stage into a construction stage, a construction stage, and a construction stage.
The quality control unit 230 is a simulation of the construction and construction by law, KS and specifications, quality standards, tolerances, acceptance and rejection criteria, construction record criteria of the materials used in the construction to the simulation unit 270 Offering,
The construction detection unit 240 refers to the construction standard to be confirmed by construction type and construction method, construction materials, construction inspection criteria classified by construction order and construction verification method, construction verification standard, and sample according to the construction type and construction method. Provide the data to the simulation unit 270,
The inspection evaluation unit 250 is provided to the simulation unit 270 to provide a list of inspection contents and evaluation methods, evaluation criteria, evaluation methods and points information for the evaluation of the progress of the construction and submitted documents for the evaluation. To be done,
The data generation reference information is inputted by providing the product data, product manufacturer information, sample product information, construction plan information, construction detailed information, construction progress status to the simulation unit 270,
The simulation unit 270 is an item commonly included in the combination of the information provided from the official management unit 210, construction management unit 220, quality control unit 230, construction detection unit 240 and the data generation reference information. The documents to be extracted and submitted by item are simulated and generated.
The simulation unit 270 is to check whether the offenses and incomplete documents and self-inspection before the evaluation proceeds in the combination of the inspection and evaluation data provided by the inspection and evaluation unit 250 and the completed construction and submitted documents Real-time construction work integrated management device, characterized in that simulated to be possible.
KR1020190016943A 2018-12-28 2019-02-13 Realtime construction work management apparatus KR102065507B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR20180172841 2018-12-28
KR1020180172841 2018-12-28

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020190172344A Division KR102209809B1 (en) 2018-12-28 2019-12-20 Construction management system for real-time construction inspection and evaluation

Publications (1)

Publication Number Publication Date
KR102065507B1 true KR102065507B1 (en) 2020-01-13

Family

ID=69153096

Family Applications (2)

Application Number Title Priority Date Filing Date
KR1020190016943A KR102065507B1 (en) 2018-12-28 2019-02-13 Realtime construction work management apparatus
KR1020190172344A KR102209809B1 (en) 2018-12-28 2019-12-20 Construction management system for real-time construction inspection and evaluation

Family Applications After (1)

Application Number Title Priority Date Filing Date
KR1020190172344A KR102209809B1 (en) 2018-12-28 2019-12-20 Construction management system for real-time construction inspection and evaluation

Country Status (1)

Country Link
KR (2) KR102065507B1 (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111461675A (en) * 2020-04-20 2020-07-28 成都一智科技有限公司 Building construction measurement system based on mobile internet and relevant smart machine
CN112488329A (en) * 2020-11-26 2021-03-12 南通市市政工程设计院有限责任公司 Municipal works supervision information management system
CN112766818A (en) * 2021-02-07 2021-05-07 中建水务环保有限公司 Safety target management control examination system
CN112966880A (en) * 2021-04-08 2021-06-15 合肥信息工程监理咨询有限公司 GSFI point location information management platform
KR102322456B1 (en) 2020-06-05 2021-11-05 (주)오픈웍스 Apparatus for Handling Local Safety Management Situation and Driving Method Thereof
CN113657081A (en) * 2021-08-19 2021-11-16 机汇网(深圳)科技有限公司 Safety technology intersection management method, system and storage medium for building construction
CN113689088A (en) * 2021-08-04 2021-11-23 中国二十冶集团有限公司 Technical background management method based on engineering management and control platform
CN113837643A (en) * 2021-09-30 2021-12-24 上海豆家网络科技有限公司 Project task management system and method
CN115033640A (en) * 2022-04-26 2022-09-09 广东创成建设监理咨询有限公司 Electric power construction engineering supervision experience uploading and consulting system
CN115471105A (en) * 2022-09-26 2022-12-13 兰州石化职业技术大学 Green energy-saving construction system
CN116384837A (en) * 2023-04-25 2023-07-04 盐城市建设工程质量检测中心有限公司 Information processing method, system and inspector terminal for engineering quality inspection
CN116629696A (en) * 2023-06-06 2023-08-22 广东云下汇金科技有限公司 Data center engineering construction stage construction quality management system platform
KR102593368B1 (en) 2022-07-07 2023-10-25 주식회사 케플라비크 Apparatus for Intergrated Management of Thechnician and Driving Method Thereof
CN117035564A (en) * 2023-10-10 2023-11-10 江西恒信项目管理有限公司 Construction quality supervision system suitable for engineering supervision
CN116307554B (en) * 2023-03-06 2023-12-22 中核四川环保工程有限责任公司 Method and system for managing checking data of medium-low nuclear waste liquid cement solidified body
CN117575518A (en) * 2023-11-20 2024-02-20 浙江建友工程咨询有限公司 Method, device, equipment and medium for digital management of whole engineering construction process
CN117787800A (en) * 2023-12-29 2024-03-29 北京中水卓越认证有限公司 Authentication management system based on engineering construction
CN117808376A (en) * 2024-02-29 2024-04-02 杭州钱塘产城开发集团有限公司 Construction engineering quality detection supervision method and system
CN117852846A (en) * 2024-03-08 2024-04-09 济南城建集团有限公司 Intelligent and refined management and control system and method for engineering construction

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102513608B1 (en) * 2022-11-24 2023-03-22 방재웅 Smart inspection system for quality control of construction

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09256635A (en) * 1996-03-21 1997-09-30 Takenaka Komuten Co Ltd Construction work managing and supporting device, and system
JPH11149497A (en) * 1997-11-14 1999-06-02 Fujitsu Ltd Document management supporting system and storage medium storing program for computer to perform processing in the same system
JP2005108015A (en) * 2003-09-30 2005-04-21 Shimizu Corp Construction management support system
JP2006113940A (en) 2004-10-18 2006-04-27 Japan Home Kk Construction job supporting system and program
KR20070004162A (en) 2005-07-04 2007-01-09 심영호 Project management information system
KR20130130100A (en) * 2011-12-23 2013-12-02 엠피이코리아 주식회사 Construction management system and method thereof
KR101618775B1 (en) 2014-08-07 2016-05-18 주식회사 에코시안 Metadata input supporting system for laws and regulation, and method for processing of the same

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011134287A (en) * 2009-12-24 2011-07-07 Interwave Co Ltd Construction performance rating simulation system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09256635A (en) * 1996-03-21 1997-09-30 Takenaka Komuten Co Ltd Construction work managing and supporting device, and system
JPH11149497A (en) * 1997-11-14 1999-06-02 Fujitsu Ltd Document management supporting system and storage medium storing program for computer to perform processing in the same system
JP2005108015A (en) * 2003-09-30 2005-04-21 Shimizu Corp Construction management support system
JP2006113940A (en) 2004-10-18 2006-04-27 Japan Home Kk Construction job supporting system and program
KR20070004162A (en) 2005-07-04 2007-01-09 심영호 Project management information system
KR20130130100A (en) * 2011-12-23 2013-12-02 엠피이코리아 주식회사 Construction management system and method thereof
KR101618775B1 (en) 2014-08-07 2016-05-18 주식회사 에코시안 Metadata input supporting system for laws and regulation, and method for processing of the same

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111461675A (en) * 2020-04-20 2020-07-28 成都一智科技有限公司 Building construction measurement system based on mobile internet and relevant smart machine
KR102322456B1 (en) 2020-06-05 2021-11-05 (주)오픈웍스 Apparatus for Handling Local Safety Management Situation and Driving Method Thereof
CN112488329A (en) * 2020-11-26 2021-03-12 南通市市政工程设计院有限责任公司 Municipal works supervision information management system
CN112766818A (en) * 2021-02-07 2021-05-07 中建水务环保有限公司 Safety target management control examination system
CN112966880A (en) * 2021-04-08 2021-06-15 合肥信息工程监理咨询有限公司 GSFI point location information management platform
CN113689088A (en) * 2021-08-04 2021-11-23 中国二十冶集团有限公司 Technical background management method based on engineering management and control platform
CN113657081A (en) * 2021-08-19 2021-11-16 机汇网(深圳)科技有限公司 Safety technology intersection management method, system and storage medium for building construction
CN113837643A (en) * 2021-09-30 2021-12-24 上海豆家网络科技有限公司 Project task management system and method
CN113837643B (en) * 2021-09-30 2023-12-29 重庆云才企业孵化器有限公司 Project task management system and method
CN115033640A (en) * 2022-04-26 2022-09-09 广东创成建设监理咨询有限公司 Electric power construction engineering supervision experience uploading and consulting system
KR102593368B1 (en) 2022-07-07 2023-10-25 주식회사 케플라비크 Apparatus for Intergrated Management of Thechnician and Driving Method Thereof
CN115471105A (en) * 2022-09-26 2022-12-13 兰州石化职业技术大学 Green energy-saving construction system
CN116307554B (en) * 2023-03-06 2023-12-22 中核四川环保工程有限责任公司 Method and system for managing checking data of medium-low nuclear waste liquid cement solidified body
CN116384837B (en) * 2023-04-25 2023-10-31 盐城市建设工程质量检测中心有限公司 Information processing method, system and inspector terminal for engineering quality inspection
CN116384837A (en) * 2023-04-25 2023-07-04 盐城市建设工程质量检测中心有限公司 Information processing method, system and inspector terminal for engineering quality inspection
CN116629696A (en) * 2023-06-06 2023-08-22 广东云下汇金科技有限公司 Data center engineering construction stage construction quality management system platform
CN117035564A (en) * 2023-10-10 2023-11-10 江西恒信项目管理有限公司 Construction quality supervision system suitable for engineering supervision
CN117035564B (en) * 2023-10-10 2024-01-05 江西恒信项目管理有限公司 Construction quality supervision system suitable for engineering supervision
CN117575518A (en) * 2023-11-20 2024-02-20 浙江建友工程咨询有限公司 Method, device, equipment and medium for digital management of whole engineering construction process
CN117787800A (en) * 2023-12-29 2024-03-29 北京中水卓越认证有限公司 Authentication management system based on engineering construction
CN117808376A (en) * 2024-02-29 2024-04-02 杭州钱塘产城开发集团有限公司 Construction engineering quality detection supervision method and system
CN117852846A (en) * 2024-03-08 2024-04-09 济南城建集团有限公司 Intelligent and refined management and control system and method for engineering construction

Also Published As

Publication number Publication date
KR20200083256A (en) 2020-07-08
KR102209809B1 (en) 2021-01-29

Similar Documents

Publication Publication Date Title
KR102065507B1 (en) Realtime construction work management apparatus
CN111598379B (en) Project management method, platform, device, computer equipment and storage medium
US20210110347A1 (en) Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
Kassem et al. BIM in facilities management applications: a case study of a large university complex
US20190220936A1 (en) Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
US20170053244A1 (en) Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
US20190220796A1 (en) Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
US20220101235A1 (en) Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
MXPA04006428A (en) Method for compliance of standards registrar with accreditation agency requirements.
Karimidorabati et al. Evaluation of automation levels for construction change management
O'Brien Construction inspection handbook: Quality assurance/quality control
Gajaman et al. Conflict avoidance in construction stage through proper practice in pre contract stage
CN115511331A (en) Vehicle production management manufacturing system, method and storage medium
Bhonde et al. Review of project quality plan
Samuels Construction facilities audit: quality system-performance control
Greasley A redesign of a road traffic accident reporting system using business process simulation
O'Brien Construction inspection handbook: Total quality management
Cater et al. ISO 9000-a perspective on a global quality standard
Rojas Construction project management: A practical guide for building and electrical contractors
Flanagan et al. Code of quality management-guide to best practice construction quality management
Greasley Case study: A simulation of a road traffic accident process
Wotschke et al. Construction Auditing: Planning-Implementation-Use
Ebenezer IMPROVING CONSTRUCTION QUALITY: A COMPREHENSIVE ANALYSIS OFQUALITY ASSURANCE PRACTICES IN THE NIGERIAN BUILDING SECTOR
Lemer et al. Inspection and Other Strategies for Assuring Quality in Government Construction
Park et al. Reality-based construction project management: A constraint-based 4d simulation environment

Legal Events

Date Code Title Description
A107 Divisional application of patent
GRNT Written decision to grant
G170 Publication of correction