KR100819379B1 - Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction - Google Patents

Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction Download PDF

Info

Publication number
KR100819379B1
KR100819379B1 KR1020070082650A KR20070082650A KR100819379B1 KR 100819379 B1 KR100819379 B1 KR 100819379B1 KR 1020070082650 A KR1020070082650 A KR 1020070082650A KR 20070082650 A KR20070082650 A KR 20070082650A KR 100819379 B1 KR100819379 B1 KR 100819379B1
Authority
KR
South Korea
Prior art keywords
concrete structure
ground
hydraulic
foundation
concrete
Prior art date
Application number
KR1020070082650A
Other languages
Korean (ko)
Inventor
이학곤
이용혁
Original Assignee
이학곤
이용혁
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이학곤, 이용혁 filed Critical 이학곤
Priority to KR1020070082650A priority Critical patent/KR100819379B1/en
Application granted granted Critical
Publication of KR100819379B1 publication Critical patent/KR100819379B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/06Constructions, or methods of constructing, in water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A concrete structure using a hydraulic system and a no-noise and no-vibration construction method of a structure using the concrete structure are provided to minimize accidents by preventing breakdown, overturn and ground subsidence in a narrow and poor construction site above the ground, under the ground or under the water, to shorten working hours, to minimize noise and vibration caused at work, and to reduce working expense by performing construction work without installing a temporary sheeting or a cofferdam. A concrete structure using a hydraulic system comprises a cubic concrete structure(10) manufactured above the ground to be mounted on the top of foundation piles(20) constructed above the ground, under the ground and under the water, many hydraulic cylinders(15) coupled to the bottom or the side of the concrete structure to robotize the concrete structure and provided with a cylinder rod supported to the top of the foundation piles, and a controller controlling the operation of the hydraulic cylinder according to the operation of the hydraulic pump and operating the hydraulic cylinders individually or simultaneously. A no-noise and no-vibration construction method of a structure using the concrete structure comprises the steps of: manufacturing a robotized concrete structure by manufacturing a concrete structure above the ground and mounting many hydraulic cylinders on the bottom or the side; constructing many foundation piles on the bottom where the concrete structure is installed and arranging heads of the piles horizontally; mounting the hydraulic cylinders on the top of the head and supporting the concrete structure, and excavating the ground under the concrete structure; operating one of the hydraulic cylinders not to support the foundation piles, and cutting off the unsupported foundation pile as much as the maximum drawing distance of the cylinder, and drawing and supporting the cylinder to the cut foundation pile; operating other hydraulic cylinders mounted to the concrete structure individually and cutting off each foundation pile in order; operating the hydraulic cylinders simultaneously to approach to the horizontally arranged foundation piles, and descending the concrete structure and repeating the excavating step and the cutting step for foundation piles, and then descending the concrete structure to the target spot under the ground; and placing and curing bottom concrete on the bottom of the concrete structure reached the target spot.

Description

유압시스템을 이용한 콘크리트구조체 및 이를 이용한 구조물의 무소음 무진동 시공방법{CONCRETE CONSTRUCTION USING HYDRAULIC SYSTEM AND ANTI-NOISE NON-VIBRATION MANUFACTURING METHOD OF CONCRETE CONSTRUCTION}Concrete Structure Using Hydraulic System and Noise-Free Vibration Construction Method of Structures Using the System {CONCRETE CONSTRUCTION USING HYDRAULIC SYSTEM AND ANTI-NOISE NON-VIBRATION MANUFACTURING METHOD OF CONCRETE CONSTRUCTION}

본 발명은 유압시스템을 이용한 콘크리트구조체 및 이를 이용한 구조물의 무소음 무진동 시공방법에 관한 것으로, 더욱 상세하게는 작업환경이 협소하고 열악한 지상, 지하 또는 수중의 건설현장에서 시공의 공정 및 시간과 비용을 줄이고 안전사고등 위험성을 대폭 감소시킴과 더불어 시공중 발생되는 소음과 진동을 최소화하도록 한 유압시스템을 이용한 콘크리트구조체 및 이를 이용한 구조물의 무소음 무진동 시공방법에 관한 것이다.The present invention relates to a concrete structure using a hydraulic system and a noise-free vibration-free construction method of the structure using the same, and more particularly, to reduce the process, time and cost of construction in the construction site of a narrow and poor working environment, poor ground, underground or underwater The present invention relates to a concrete structure using a hydraulic system and a noiseless vibration-free construction method of the structure using the hydraulic system to greatly reduce risks such as safety accidents and to minimize noise and vibration generated during construction.

일반적으로 지상, 지하 및 수중 등 건설현장에서의 건축물이나 구조물의 시공시에는 건물지하층 가시설흙막이공사, 지하박스나 지하저수조설치공사, 기타 지하구조물설치 및 초연약지반등에서의 하천교량기초판설치공사, 수중기초시설물설치 및 우물통공법 등의 작업공정을 통해 구조물을 시공하고 있다.In general, when constructing buildings or structures in construction sites such as ground, underground, and underwater, construction of temporary foundation muds, construction of underground boxes or underground reservoirs, installation of other underground structures and foundation of river bridges in ultra soft ground, The construction of the structure is carried out through work processes such as the installation of underwater foundation facilities and the well drilling method.

기초공사시 일반적으로 사용되는 씨트파일이나 토류판공법 등을 이용한 상기 가시설흙막이공사는 공사비가 저렴한 방면 지반 침하나 붕괴, 가시설흙막이시설물의 전도 등 안전사고의 발생이 빈번하며, 특히 씨트파일공법의 경우 연약지반에서의 시공시 철강제의 기본신축성 때문에 인접경계지 크렉발생 및 인발시 시트파일이 인발된 자리의 공극과 진동으로 인하여 지반 침하가 필연적으로 발생된다. 토류판작업 등과 씨트파일 공법 모두 크레인과 같은 대형 중장비에서 전달되는 작업하중으로부터 가해지는 충격과 바이브레이다 등 진동을 이용함으로써 시공시 공통적으로 연약지반에서 안정된 기초지반을 교란하고 유동시키는 큰 단점을 가지고 있다.In the temporary construction work using sheet pile or earth plate method, which are generally used in basic construction, the occurrence of safety accidents such as ground subsidence or collapse, and conduction of temporary construction facilities are inexpensive, especially in the case of the sheet pile method. Due to the basic elasticity of steel during construction in the ground, ground settlement is inevitable due to the generation of adjacent boundary cracks and the voids and vibrations of the seat where the pile pile is drawn. Both soil plate work and sheet pile method have the big disadvantage of disturbing and flowing stable foundation ground in soft ground by using vibrations such as shock and vibrator from working load delivered from large heavy equipment such as crane.

또한, 수중이나 초연약지반에서 가물막이 공법과 병행 시공되는 우물통공법의 경우에는 우물통의 하부를 굴착하여 우물통의 자중에 의해 자연하강 침하되도록 시공되고 있으며, 이 공법의 경우 편심에 의한 부동침하시 바로잡는데 많은 시간이 소요되는 단점이 있다.In addition, in the case of the well-hole construction method, which is constructed in parallel with the temporary film construction method in the water or ultra soft ground, the bottom of the well is excavated to be settled to fall naturally due to the weight of the well. The disadvantage is that it takes a lot of time to correct the settlement.

종래의 SCW(Soil Cement Wall)공법, CIP(CAST-IN PLACED PILE)공법 등은 안전성은 높은 반면 대형 중장비 및 대형 부속장비 등이 필요하고, 시공과정에서 슬러지 등 산업폐기물이 발생하며, 공사비가 고가라는 단점이 있다.Conventional SCW (Soil Cement Wall) and CIP (CAST-IN PLACED PILE) methods are high in safety but require large heavy equipment and large accessories.In the process of construction, industrial waste such as sludge is generated and construction costs are high. There is a disadvantage.

또한 하천 등 초연약지반에서 교량의 기초나 펌프장설치 등 수변지역에서 시설되는 기초공사는 배수를 우회시킨 후 가물막이를 시공하고 공사 지점을 성토 매립하는 등 본 공사보다 준비공정이 더 많음에 따라 비용과 시간을 소요하는 단점이 있다.In addition, the foundation work in waterfront areas, such as the foundation of bridges and pumping stations in super soft grounds such as rivers, is more costly due to more preparatory processes than the construction work, such as construction of barriers and construction of construction sites. There is a disadvantage in that it takes time and time.

본 발명은 상기한 문제점을 해결하기 위하여 창안된 것으로, 본 발명의 목적은 작업환경이 협소하고 열악한 지상, 지하 또는 수중 등의 건설현장에서의 시공작업시 붕괴, 전도, 지반 침하 등을 방지하여 안전사고의 발생을 최소화함과 아울러 작업시간을 대폭 감소시키고, 작업시 불가피하게 발생되는 소음 및 진동을 최소화할 수 있으며, 별도의 가시설흙막이나 가물막이의 설치공정없이 시공할 수 있어 작업비용을 현저하게 감소시키도록 한 유압시스템을 이용한 콘크리트구조체 및 이를 이용한 구조물의 무소음 무진동 시공방법을 제공하는 데 있다.The present invention was devised to solve the above problems, and the object of the present invention is to prevent the collapse, fall, ground subsidence, etc. during construction work in construction sites, such as the ground, underground or underwater, where the working environment is narrow and poor It minimizes the occurrence of accidents, greatly reduces work time, minimizes the noise and vibration that is inevitably generated during work, and can be installed without the installation process of a separate soil film or temporary film, thereby significantly reducing work costs. It is to provide a concrete structure using a hydraulic system to reduce the noise, and a noise-free vibration-free construction method of the structure using the same.

또한, 본 발명은 상가나 아파트단지등 도심밀집지역, 진동에 민감한 문화재보호구역, 정밀기기를 사용하는 공단지역 및 연구시설, 군사시설보호구역, 댐,고속철도,고속도로등의 안전성이 요구되는 시설물의 인접공사 및 소음에 민감한 학교,도서관등 교육시설, 병원이나 대형 중장비의 운반 및 접근이 불가한 섬 등 도서지역, 해양수중시설공사 등이나 도로미개설 오지와 연약지반이나 초연약지반 등 현장여건이 진동이나 소음에 민감하고, 대형 중장비 사용이 불가한 열악한 환경의 건설현장에서 대형 중장비를 사용하지 않은 상태로 경량의 유압시스템이 결합되어 일체화된 콘크리트구조물과 기초파일을 이용하여 무진동 무소음으로 시공하도록 한 유압시스템을 이용한 콘크리트구조체 및 이를 이용한 구조물의 무소음 무진동 시공방법을 제공하는 데 있다.In addition, the present invention is the center of the city, such as shopping malls and apartment complexes, cultural property protection zones sensitive to vibration, industrial zones and research facilities using precision equipment, military facility protection zones, dams, high-speed railway, highways, etc. Educational facilities such as adjacent construction and noise-sensitive schools and libraries, islands such as hospitals and islands where large heavy equipment is not accessible and accessible, marine underwater facilities construction, unopened roads, soft ground or soft ground In a harsh construction site where it is sensitive to vibration or noise and cannot use large heavy equipment, lightweight hydraulic system is combined without using large heavy equipment, so it can be constructed without vibration by using integrated concrete structure and foundation pile. Concrete structure using hydraulic system and noise-free vibration-free construction method of the structure using the same There is.

상기의 목적을 달성하기 위한 본 발명의 콘크리트구조체는 지상, 지하, 수중에 시공되는 기초파일(20)의 상부에 안착되도록 지상에서 제작되는 입체형상의 콘크리트구조물(10)과; 상기 콘크리트구조물(10)의 저면 또는 측면에 상기 콘크리트구조물(10)을 로봇화하도록 결합되고, 실린더로드가 상기 기초파일(20)의 상부면에 지지되는 다수개의 유압실린더(15)와; 상기 유압실린더(15)의 구동을 제어하여 상기 유압실린더(15)를 단독 또는 동시 작동시키는 컨트롤러(30)로 이루어진 것을 특징으로 한다.Concrete structure of the present invention for achieving the above object is a three-dimensional concrete structure (10) manufactured on the ground to be seated on the top of the foundation pile 20 to be installed in the ground, underground, water; A plurality of hydraulic cylinders 15 coupled to the bottom or side surface of the concrete structure 10 to robotize the concrete structure 10 and having a cylinder rod supported on an upper surface of the foundation pile 20; It characterized in that it consists of a controller 30 for controlling the driving of the hydraulic cylinder 15 to operate the hydraulic cylinder 15 alone or simultaneously.

또한, 본 발명은 지중 또는 수중에 설치되는 콘크리트구조물의 시공방법에 있어서, 시공하고자 하는 콘크리트구조물을 지상에서 제작한 후 저면 또는 측면에 유압실린더를 다수개 장착하여 유압장치에 의한 로봇화된 콘크리트구조체로 제작하는 구조체 제작단계와; 상기 콘크리트구조체가 설치되는 지면에 기초파일을 다수개 선시공한 후 파일의 두부를 수평하게 정리하는 파일설치단계와; 상기 두부의 상부에 상기 유압실린더를 안착시켜 상기 콘크리트구조물을 지지시킨 후 콘크리트구조물의 아래쪽 지면을 굴착하는 굴착단계와; 상기 단계 후 상기 유압실린더 중 하나의 유압실린더를 작동시켜 기초파일을 지지하지 않도록 한 상태에서 지지되지 않은 기초파일을 실린더의 최대인출거리만큼 절단시킨 후 절단된 기초파일에 실린더를 인출시켜 지지시키는 과정과, 콘크리트구조물에 장착된 다른 유압실린더를 상기 과정과 같이 각각 개별적으로 작동시키면서 각각의 기초파일을 순차적으로 절단하는 과정으로 이루어진 기초파일 절단단계와; 상기 단계 후 개별적으로 각각 절단되어 수평하게 정리된 기초파일에 근접하도록 유압실린더를 동시구동하여 상기 콘크리트구조물을 하강시킨 후 상기 굴착단계 및 기초파일 절단단계를 반복수행하고, 상기 콘크리트구조물을 지중의 목표지점으로 하강시키는 구조물 하강단계와; 상기 단계 후 목표지점에 도달한 콘크리트구조물의 저부에 바닥콘크리트를 타설하여 양생하는 마무리단계로 이루어진 것을 특징으로 한다.In addition, the present invention in the construction method of concrete structures to be installed in the ground or underwater, after manufacturing the concrete structure to be installed on the ground and equipped with a plurality of hydraulic cylinders on the bottom or side of the robotized concrete structure by the hydraulic device A structure manufacturing step of manufacturing; A pile installation step of horizontally arranging the head of the pile after preliminary construction of a plurality of foundation piles on the ground on which the concrete structure is installed; An excavating step of mounting the hydraulic cylinder on the top of the head to support the concrete structure and then excavating the lower surface of the concrete structure; After the step of operating the one of the hydraulic cylinder of the hydraulic cylinder to the base pile in a state that does not support the base pile, the process of cutting the unsupported base pile by the maximum drawing distance of the cylinder and then withdrawing the cylinder to the cut base pile And, Foundation pile cutting step consisting of a step of sequentially cutting each of the foundation pile while operating each of the hydraulic cylinders mounted on the concrete structure individually as described above; After the step, the hydraulic cylinders are simultaneously driven to approach the foundation piles, which are individually cut and horizontally arranged, and then the concrete structures are lowered, and the excavation and cutting of the foundation piles are repeatedly performed. A structure descending step of descending to a point; After the step is characterized in that the finishing step of curing by pouring the bottom concrete to the bottom of the concrete structure reaching the target point.

상기와 같은 본 발명에 따르면, 작업환경이 협소하고 열악한 지상, 지하 또는 수중 등의 건설현장에서의 시공작업시 붕괴, 전도, 지반 침하 등을 방지하여 안전사고의 발생을 최소화함과 아울러 작업시간을 대폭 감소시키고, 작업시 불가피하게 발생되는 소음 및 진동을 최소화할 수 있으며, 별도의 가시설흙막이나 가물막이의 설치공정없이 시공할 수 있어 작업비용을 현저하게 감소시킬 수 있게 된다.According to the present invention as described above, to minimize the occurrence of safety accidents and to minimize the occurrence of safety accidents by preventing collapse, fall, ground subsidence during construction work in the construction site, such as the ground, underground or underwater, poor working environment It can greatly reduce, minimize the noise and vibration inevitably generated during the operation, and can be installed without a separate installation process of the soil film or temporary film can significantly reduce the work cost.

또한, 대형 중장비의 사용 없이 유압시스템을 갖는 콘크리트구조물과 기초파을만을 이용하여 무진동, 무소음으로 간편하게 시공할 수 있게 된다.In addition, by using only concrete structures and foundation waves having a hydraulic system without the use of large heavy equipment, it can be easily installed without vibration and noise.

이하, 첨부된 도면을 참조하여 본 발명의 유압시스템을 이용한 콘크리트구조체 및 이를 이용한 구조물의 무소음 무진동 시공방법을 상세히 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail a concrete structure using the hydraulic system of the present invention and a noise-free vibration-free construction method of the structure using the same.

도 1은 본 발명에 의한 기초파일의 상부에 구비되는 콘크리트구조물을 보인 상태도이고, 도 2는 본 발명에 의한 유압장치를 보인 블럭도이며, 도 3은 본 발명에 의한 유압시스템을 이용한 콘크리트구조물의 시공방법을 보인 순서도이고, 도 4a 내지 도 4f는 본 발명에 의한 기초파일 절단단계에서의 파일절단과정을 보인 순서도이다.1 is a state diagram showing a concrete structure provided on the upper portion of the foundation pile according to the present invention, Figure 2 is a block diagram showing a hydraulic apparatus according to the present invention, Figure 3 is a concrete structure using a hydraulic system according to the present invention 4A to 4F are flowcharts showing a file cutting process in the basic file cutting step according to the present invention.

상기 도 1 내지 도 4f에 도시된 바와 같이, 본 발명에 의한 유압시스템을 이용한 콘크리트구조체는 지상, 지하, 수중에 시공되는 기초파일(20)의 상부에 안착되도록 지상에서 제작되는 입체형상의 콘크리트구조물(10)과; 상기 콘크리트구조물(10)의 저면 또는 측면에 상기 콘크리트구조물(10)을 로봇화하도록 결합되고, 실린더로드가 상기 기초파일(20)의 상부면에 지지되는 다수개의 유압실린더(15)와; 유압펌프(25)의 동작에 따른 상기 유압실린더(15)의 구동을 제어하여 상기 유압실린더(15)를 단독 또는 동시 작동시키는 컨트롤러(30)로 이루어진다.As shown in FIG. 1 to FIG. 4F, the concrete structure using the hydraulic system according to the present invention is a three-dimensional concrete structure manufactured on the ground so as to be seated on the upper portion of the foundation pile 20 constructed in the ground, underground, and water ( 10); A plurality of hydraulic cylinders 15 coupled to the bottom or side surface of the concrete structure 10 to robotize the concrete structure 10 and having a cylinder rod supported on an upper surface of the foundation pile 20; The controller 30 is configured to control the driving of the hydraulic cylinder 15 according to the operation of the hydraulic pump 25 to operate the hydraulic cylinder 15 alone or simultaneously.

또한, 본 발명에 의한 상기 콘크리트구조체를 이용한 콘크리트구조물의 시공방법은 건축물의 지하층공사, 지하매설용 대형박스공사, 교량교각용 우물통공사, 송전탑기초공사, 하천 지하 구조물공사등, 토목 및 건축, 수중공사 등의 기초공사에서 가시설이나 가물막이 없이 시설물을 시공할 수 있도록 한 것으로, 시공하고자 하는 콘크리트구조물(10)을 지상에서 제작한 후 저면 또는 측면에 유압실린더(15)를 다수개 장착하여 유압장치에 의한 로봇화된 콘크리트구조체로 제작하는 구조체 제작단계와, 상기 콘크리트구조체가 설치되는 지면에 기초파일(20)을 다수개 시공한 후 파일의 두부를 수평하게 정리하는 파일설치단계와, 상기 두부의 상부에 상기 유압실린더(15)를 안착시켜 상기 콘크리트구조물(10)을 지지시킨 후 콘크리트구조물(10)의 아래쪽 지면을 굴착하는 굴착단계와, 상기 단계 후 상기 유압실린더 중 하나의 유압실린더를 작동시켜 기초파일을 지지하지 않도록 한 상태에서 지지되지 않은 기초파일을 실린더의 최대인출거리만큼 절단시킨 후 절단된 기초파일에 실린더를 인출시켜 지지시키는 과정과, 콘크리트구조물에 장착된 다른 유압실린더를 상기 과정과 같이 각각 개별적으로 작동시키면서 각각의 기초파일을 순차적으로 절단하는 과정으로 이루어진 기초파일 절단단계를 거치고, 그 후 개별적으로 각각 절단되어 수평하게 정리된 기초파일에 근접하도록 유압실린더를 동시구동하여 상기 콘크리트구조물을 하강시킨 후 상기 굴착단계 및 기초파일 절단단계를 반복수행하고, 상기 콘크리트구조물을 지중의 목표지점으로 하강시키는 구조물 하강단계를 거치게 되며, 상기 단계 후 목표지점에 도달한 콘크리트구조물(10)의 저부에 바닥콘크리트를 타설하여 양생하는 마무리단계를 통해 이루어진다.
상기 기초파일 절단단계를 도 4a 내지 도 4f를 통해 더욱 상세히 설명하면, 유압실린더(15)를 기초파일(20)의 두부에 안착시켜 콘크리트구조물(10)을 지지시킨 상태에서 구조물의 아래쪽 지면을 굴착하고(도 4a와 도 4b 참고), 기초파일(20)의 두부에 안착된 유압실린더(15) 중 하나의 유압실린더의 실린더를 구동시켜 기초파일을 지지시키지 않도록 하고(도 4c 참고), 이 상태에서 지지되지 않은 기초파일을 실린더의 최대하강거리만큼 절단하며(도 4d 참고), 기초파일의 절단 후 다시 실린더를 하강시켜 지지시키도록 하고, 이 상태에서 다른 유압실린더의 실린더를 구동시켜 기초파일을 지지시키지 않도록 하여 절단하는 과정(도 4e와 도 4f 참고)통해 개개의 기초파일(20)을 모두 절단한다.
즉, 상기와 같은 과정으로 다른 유압실린더도 동일하게 작동시키면서 기초파일을 절단시킨 후 다시 지지시키고, 모든 구간의 기초파일의 절단이 완료되면 유압실린더(15)를 동시구동하여 콘크리트구조물(10)을 조금씩 하강시키게 되는 것입니다.
In addition, the construction method of the concrete structure using the concrete structure according to the present invention is the basement construction of buildings, large box construction for underground laying, wells construction for bridge pier, transmission tower foundation construction, river underground structure construction, civil engineering and construction, It is to allow the installation of facilities without temporary facilities or temporary curtains in basic construction such as underwater construction. After manufacturing the concrete structure 10 to be installed on the ground, the hydraulic cylinders 15 are installed on the bottom or side of the hydraulic structure. Structural manufacturing step of manufacturing a robotized concrete structure by the device, File installation step of arranging the head of the pile horizontally after constructing a plurality of foundation piles 20 on the ground on which the concrete structure is installed, and the head The hydraulic cylinder 15 is seated on an upper portion of the lower surface of the concrete structure 10 after supporting the concrete structure 10. The excavation step of excavating and cutting the unsupported base pile by the maximum drawing distance of the cylinder after operating the hydraulic cylinder of one of the hydraulic cylinder after the step so as not to support the foundation pile to the cut foundation pile After the base pile cutting step consisting of the process of drawing out and supporting the cylinder, and cutting each foundation pile sequentially while operating the hydraulic cylinders mounted on the concrete structure individually as in the above process, and then individually Simultaneously drive the hydraulic cylinder so as to approach the foundation piles cut and arranged horizontally, the concrete structure is lowered, and the excavation step and the foundation pile cutting step are repeatedly performed, and the concrete structure is lowered to the target point of the ground. Will go through a descent step, and then Is made in a bottom portion of a concrete structure 10 reaches the point through a finishing step of curing by pouring the concrete floor.
4A to 4F, the cutting of the foundation pile is described in more detail. The hydraulic cylinder 15 is mounted on the head of the foundation pile 20 to excavate the lower surface of the structure while supporting the concrete structure 10. 4a and 4b, the cylinder of one of the hydraulic cylinders 15 mounted on the head of the foundation pile 20 is driven so as not to support the foundation pile (see FIG. 4c). The base pile which is not supported by the cutting machine is cut by the maximum descending distance of the cylinder (refer to FIG. 4D), and after the cutting of the foundation pile, the cylinder is lowered and supported again. In this state, the cylinder of another hydraulic cylinder is driven to The individual foundation piles 20 are cut through the cutting process (see FIGS. 4E and 4F) so as not to support them.
That is, while the other hydraulic cylinder is operated in the same manner as described above, the foundation pile is cut and supported again, and when the cutting of the foundation pile of all sections is completed, the hydraulic cylinder 15 is simultaneously driven to operate the concrete structure 10. It will be descended little by little.

상기 유압실린더(15)는 외부에 고인장력 내성을 갖는 하이텐강(EH강)계열의 소재를 사용한 원통형의 외부구조체가 구비되고, 상기 콘크리트구조물(10)에 일체로 결합된다.The hydraulic cylinder 15 is provided with a cylindrical outer structure using a high-tensile steel (EH steel) -based material having a high tensile resistance to the outside, it is integrally coupled to the concrete structure (10).

상기 유압실린더(15)의 실린더용량(CYLINDER CAPACITY)은 구조물의 중량과 토질, 작업의 난이도, 작업자의 안정성확보 등 작업환경에 따라 적정용량을 사용하도록 결정하고, 중량물 미끄럼 방지용 그루브 새들(GROOVED SADDLE)을 장착한 단동식이나, 복동,유압리턴식 대용량 유압실린더를 내장하여 일체화한 형태로 구성된다.CYLINDER CAPACITY of the hydraulic cylinder 15 is determined to use the appropriate capacity according to the working environment, such as the weight and soil quality of the structure, the difficulty of the work, the safety of the worker, and grooving saddle (GROOVED SADDLE) Single-acting, double-acting, hydraulic return type large-capacity hydraulic cylinders are built-in.

여기서, 상기 유압실린더(15)의 구동은 사용압력 중량물의 하중에 따라 17BAR에서 700BAR이내의 유압펌프와, 유량과 유압의 상태나 작업하중에 의한 부하도 및 시공압력 등 작업 중 시공 상태를 상시 확인할 수 있는 계측장치와, 상기 계측장치와 유압펌프에 연결되어 상기 유압실린더(15)의 구동을 통제하는 컨트롤러에 의해 행해진다.Here, the operation of the hydraulic cylinder 15 is always checked the construction state during the operation, such as the hydraulic pump within 17BAR to 700BAR, the flow rate and hydraulic pressure or the load diagram and construction pressure due to the working load according to the load of the working pressure heavy weight. And a controller connected to the measuring device and the hydraulic pump to control the driving of the hydraulic cylinder 15.

상기한 유압실린더(15)는 시공시 유압실린더(15)가 콘크리트구조물의 전체 자중에 의해 콘크리트구조물에서 이탈되지 않고, 지지력과 반력에 작용할 수 있도록 플렌지볼트 결속체나 후크타입의 결속체, 벽체볼트 체결식, 실린더상하지지판 설치법 등 합체베이스를 제작하여 구조물기초바닥이나 벽체하단부에 고정되도록 고장력너트 배열판이나, 후크 고리를 철근 등과 결속처리하는 플렌지나 고장력너트 배열판을 선시공하고 삽입하여 양생시켜 콘크리트구조물(판형,박스형,원통형,다각형등 어떤 형태든지 가능하다)의 구조체를 완성시킨다. 이때, 높은 압입력을 요구 하는 공정(파일 압입시)에서는 고장력볼트를 이용하여 플렌지방식이나 벽체고정판에 고장력볼트로 결합하고, 기동성이 요구되는 공정(경량구조물 안착시)에서는 후크타입으로 유압실린더(15)를 콘크리트구조물과 결합시키면 된다.The hydraulic cylinder 15 is a flange bolt binding member or a hook-type binding member, wall bolt fastening so that the hydraulic cylinder 15 when the construction does not deviate from the concrete structure by the total weight of the concrete structure, acting on the bearing force and reaction force Concrete structure by preparing and integrating high strength nut arrangement plate or flange or high tension nut arrangement plate that binds hook loop with reinforcing bar to be fixed at base of structure or bottom of wall by making coalescence base such as installation method of cylinder upper and lower fingerboard. Complete the structure of any plate, box, cylinder, polygon, etc. At this time, in the process requiring high pressing force (when pile press-in), the high-strength bolt is used to couple the flange type or wall fixing plate with the high-strength bolt. 15) can be combined with the concrete structure.

상기 콘크리트구조물(10)과 일체화된 유압실린더(15)를 유압펌프와, 계측장치와, 컨트롤러를 이용하여 구동시키게 되면, 작업자가 필요에 따라 임의대로 콘크리트구조물(10)을 기동시킬 수 있는 콘크리트구조체{이하에서는, 콘크리트구조물의 원격기동이 가능함에 따라 '콘크리트구조물로봇'이라 명하기로 한다}가 된다.When the hydraulic cylinder 15 integrated with the concrete structure 10 is driven using a hydraulic pump, a measuring device, and a controller, a concrete structure in which an operator can start the concrete structure 10 as needed. {Hereinafter, it will be referred to as 'concrete structure robot' as the remote operation of the concrete structure is possible}.

즉, 상기 콘크리트구조물(10)에 유압실린더(15)를 이용한 구동장치를 부착하여 작업자의 이용 목적에 따라 상하 구동되도록 조정이 가능한 콘크리트구조물로봇을 만든 것으로, 상기 유압실린더(15)를 콘크리트구조물(10)의 중량과 작업하중, 현장여건, 토질, 시공의 난이도 등에 따라 안정적으로 부양력을 확보하고 유지되도록 유압실린더(15)의 설치개소를 결정하여 제작하면 된다.That is, by attaching a drive device using the hydraulic cylinder 15 to the concrete structure 10 to make a concrete structure robot that can be adjusted to be driven up and down according to the purpose of the operator, the hydraulic cylinder 15 to the concrete structure ( The installation location of the hydraulic cylinder 15 may be determined and manufactured so as to secure and maintain the flotation force stably according to the weight of 10), work load, site condition, soil quality, and construction difficulty.

즉, 상기 콘크리트구조물(10)의 중량과 작업하중을 계측장치를 통해 계측하여 산출하고, 산출된 값과 현장여건을 기준으로 상기 콘크리트구조물(10)에 장착되는 상기 유압실린더(15)의 설치개소 및 설치간격을 결정하게 되는 것이다.That is, the weight and working load of the concrete structure 10 is measured and calculated through a measuring device, and the installation location of the hydraulic cylinder 15 mounted to the concrete structure 10 based on the calculated value and the site conditions. And the installation interval will be determined.

상기 유압실린더(15)는 작업자의 필요에 의한 조작으로 독립구동과 동시구동하여 발생되는 운동에너지를 발생시키게 되는데, 이러한 운동에너지가 상기 콘크리트구조물(10)을 상하 운동되게 하고, 이러한 운동량과 속도는 컨트롤러에 의해 제어되도록 함으로써 로봇화된 것이다.The hydraulic cylinder 15 generates the kinetic energy generated by simultaneous driving and independent driving by the operation of the operator, the kinetic energy causes the concrete structure 10 to move up and down, and the amount and speed of the It is robotized by being controlled by a controller.

한편, 상기 유압실린더의 결합방법은 상기한 방식 이외에도 여러 방식이 있 을 수 있으며, 콘크리트구조물(10)에 결합시켜 운동성을 제공할 수 있을 정도의 결합방식이면 충분하다.On the other hand, the coupling method of the hydraulic cylinder may have a number of methods in addition to the above-described method, it is sufficient if the coupling method is enough to provide mobility by coupling to the concrete structure (10).

본 발명의 콘크리트구조물로봇은 여러형태로 구조물화되어 양생된 부동의 콘크리트구조물을 유압실린더에 의해 유동화되게 한 것으로, 종래에서와 같은 건설현장에서 지면과 지하 기초파일이나 형틀속 등에 고정된 상태 즉, 부동의 상태로 시공된 방법에 비해 시공시 안전성과 신속성 및 경제성을 갖게 된다.The concrete structure robot according to the present invention is structured in various forms to allow the floating concrete structure to be cured by a hydraulic cylinder, which is fixed to the ground, underground foundation piles, molds, etc. Compared to the method of construction in a fixed state, construction has safety, speed and economics.

예로서, 지하공사의 경우 작업여건이 열악한 협소하고 붕괴, 전도 등 위험성이 높은 환경보다는 지상에서 지하 구조물을 형성하여 본 공법을 적용 시공할 수 있으며, 특히 초연약지반, 수변지역, 해양등 작업환경이 대형 중장비나 성토, 치환, 가시설흙막이, 가물막이 등이 필요한 현장에서 본 공법의 적용은 유용하다. 더욱이 상기 열거된 현장에서 주요공정을 위해 선행되는 부대공정 중 대형 중장비사용을 위한 성토작업 및 치환작업과, 공사비의 많은 부분을 차지하는 가시설흙막이 및 가물막이 같은 작업공정을 생략함으로써 공사기간단축 및 공사비 절감 등의 장점을 가지며, 가시설공사 중 발생되는 지반침하, 붕괴, 전도 등의 안전사고를 방지할 수 있는 공법이라 할 수 있다.For example, in the case of underground construction, this method can be applied by forming an underground structure on the ground rather than in a narrow environment with poor working conditions and high risk of collapse, fall, etc. In particular, the work environment such as ultra soft ground, waterfront area, ocean, etc. It is useful to apply this method in the field where large heavy equipment, fill, substitution, temporary soil wall, temporary barrier, etc. are needed. Furthermore, the construction period and reduction of construction costs are omitted by omitting the filling work and replacement work for the use of large heavy equipment and the work processes such as temporary wall and clogging, which occupy a large part of the construction cost, among the auxiliary processes that are preceded for the main processes at the sites listed above. It can be said to be a construction method that can prevent safety accidents such as ground subsidence, collapse, and fall generated during temporary construction work.

이하에서는 본 발명의 콘크리트구조물의 시공방법에 대해 단계적으로 설명하기로 한다.Hereinafter will be described step by step for the construction method of the concrete structure of the present invention.

지상에서 먼저 콘크리트구조물(10)을 제작하되, 건축의 지하실공정이면 지하실 박스를 지상에서 제작하고, 우물통공법인 경우에는 우물통을 지상에서 먼저 제작한다,In the ground first to produce a concrete structure (10), if the basement process of construction to produce a basement box on the ground, in the case of the well-hole method, the well bucket is produced on the ground first,

이후, 유압실린더(15)가 장착된 다수의 구동장치를 구조물의 중량과 용도에 따라 바닥에 고정시에는 플렌치형태의 고장력볼트를 체결하여 고정하고, 기동성이 요구되는 공정에서는 바닥에 후크식으로 설치하고, 바닥이 없는 관통형 구조물에서는 내측벽체하단부에 벽체제작시 고장력너트를 일정한 간격으로 다중수직배열한 후 미리 삽입타설하여 유압장치를 볼트 식으로 고정하면 작업자가 임의로 콘크리트구조물의 유동방향과 속도등의 움직임을 콘트롤 할수 있는 콘크리트구조물로봇이 완성된다.Then, when fixing a plurality of driving devices equipped with a hydraulic cylinder (15) on the floor according to the weight and use of the structure by tightening the high-strength bolt in the form of a flange, in the process requiring maneuverability hook-type on the floor In the bottomless through-hole structure, multi-vertical arrangement of high-tension nuts at regular intervals in the bottom wall of the inner wall is inserted in advance, and the hydraulic system is fixed by bolt type. The concrete structure robot that can control the movement of the back is completed.

이 상태에서 상기 유압실린더(15)를 임의로 조작하여 독립구동과 동시구동되게 함으로써 발생되는 운동에너지로 콘크리트구조물이 운동되게 하고, 이 운동량과 속도를 컨트롤러를 이용하여 필요에 따라 제어하여 구조물을 유압실린더의 실린더행정길이만큼 부양시키고, 구조물의 부피와 유압실린더의 행정길이만큼 하부를 굴착한다.In this state, the hydraulic cylinder 15 is arbitrarily manipulated to allow the concrete structure to move with the kinetic energy generated by simultaneous driving with independent driving, and the movement amount and speed are controlled by using a controller to control the structure as needed. Support the cylinder stroke length of, and excavate the lower part by the volume of the structure and the stroke length of the hydraulic cylinder.

굴착 후에는 한곳씩 유압실린더(15)를 단독 구동하여 상승시킨 상태에서 기초파일(20)을 유압실린더(15)의 최대하강길이만큼 절단하고, 절단된 곳의 유압실린더(15)는 다시 하강시켜 기초파일(20) 위에 지지시킨다. 다른 유압실린더도 동일한 방법으로 기초파일 절단 후 지지시킨다.After the excavation, the hydraulic piles 15 are driven and driven up one by one, and the foundation pile 20 is cut by the maximum descending length of the hydraulic cylinders 15, and the hydraulic cylinders 15 of the cut portions are lowered again. Support on the foundation pile (20). Other hydraulic cylinders are supported after cutting the foundation pile in the same way.

이와 같은 과정으로 동일한 길이를 갖도록 전구간의 기초파일이 절단 완료되면 유압실린더(15)를 동시구동하여 콘크리트구조물(10)을 하강시키고, 하강이 완료되면 상기 기초파일의 절단공정을 동일한 방법으로 반복 시공한 다음 계획된 목표지점에 안착되면 바닥콘크리트를 타설하여 양생시키면 된다.In this process, when the foundation piles are cut to have the same length, the hydraulic cylinder 15 is driven simultaneously to lower the concrete structure 10, and when the construction is completed, repeat the cutting process of the foundation piles in the same manner. Then, when it is settled at the planned target point, the concrete is poured and cured.

이와 같이, 본 발명은 지상에서 제작한 콘크리트구조물(10)이 선 시공된 기초파일(20) 위에서 유압실린더(15)의 행정길이만큼 허공에 부양할 수 있으므로, 이를 이용해 시설물의 하부를 유압실린더(15)의 행정길이 만큼 단계별로 굴착하고, 기초파일(20)의 위에 구비된 유압실린더(15)를 일개소씩 개별 구동시켜 파일을 절단하는 작업을 반복 실시한 후, 상기 유압실린더(15)를 동시 구동시켜 콘크리트구조물(10)을 하강시키고 이를 여러 단계로 반복적으로 실시하여 목표지점에 콘크리트구조물(10)을 안착시키는 공법으로서, 구조물의 외벽과 터파기되는 공간의 접점간극이 미세하여 토사의 유실이나 붕괴, 전도될 공간을 허용하지 않은 상태로 하강됨으로써 근본적으로 가설흙막이나 가설물막이공사와 되메우기 공정을 별도로 시공할 필요가 없으며, 이에 따라 공사비절감과 공사기간의 단축, 지반붕괴 등으로 인한 안전사고예방 등의 안전성, 경제성, 신속성을 갖춘 공법이라 할 수 있다.As described above, the present invention can support the air in the air as long as the stroke length of the hydraulic cylinder 15 on the foundation pile 20, the concrete structure 10 manufactured on the ground, using the hydraulic cylinder ( After excavating stepwise by the stroke length of 15), and repeatedly cutting the pile by individually driving the hydraulic cylinder 15 provided on the foundation pile 20, the hydraulic cylinder 15 is simultaneously operated. Drive down the concrete structure 10 and repeatedly carry out it in several steps to settle the concrete structure 10 at the target point. The contact gap between the outer wall of the structure and the space that is destroyed is minute, By not allowing the space to collapse or fall down, there is no need to separately install the temporary soil wall, temporary wall construction and backfilling process. The cost savings and accident prevention due to the shortening of the construction period, the ground collapsed, including safety, cost-effectiveness, can be called with the process speed.

앞에서 설명되고, 도면에 도시된 본 발명의 일 실시예는 본 발명의 기술적사상을 한정하는 것으로 해석되어서는 안 되는 것으로, 본 발명의 기술분야에서 통상의 지식을 가진 자가 유압실린더에 의해 기동되는 콘크리트구조물을 이용하여 시설물을 제작하고 시공하는 등 당업자에게 있어 자명한 것인 한 본 발명의 보호범위에 속하게 될 것이다.One embodiment of the present invention described above and shown in the drawings should not be construed as limiting the technical spirit of the present invention, concrete that is maneuvered by a self-hydraulic cylinder of ordinary skill in the art It will fall within the protection scope of the present invention as long as it will be apparent to those skilled in the art, such as manufacturing and constructing facilities using the structure.

도 1은 본 발명에 의한 기초파일의 상부에 구비되는 콘크리트구조물을 보인 상태도,1 is a state diagram showing a concrete structure provided on the upper portion of the foundation pile according to the present invention,

도 2는 본 발명에 의한 유압장치를 보인 블럭도,2 is a block diagram showing a hydraulic apparatus according to the present invention;

도 3은 본 발명에 의한 유압시스템을 이용한 콘크리트구조물의 시공방법을 보인 순서도,
도 4a 내지 도 4f는 본 발명에 의한 기초파일 절단단계에서의 파일절단과정을 보인 순서도.
3 is a flow chart showing a construction method of a concrete structure using a hydraulic system according to the present invention,
4a to 4f is a flow chart showing a file cutting process in the basic file cutting step according to the present invention.

< 도면의 주요 부분에 대한 부호의 설명 ><Description of Symbols for Main Parts of Drawings>

10: 콘크리트구조물 15: 유압실린더10: concrete structure 15: hydraulic cylinder

20: 기초파일 25: 유압펌프20: Foundation pile 25: Hydraulic pump

30: 컨트롤러30: controller

Claims (2)

삭제delete 지중 또는 수중에 설치되는 콘크리트구조물의 시공방법에 있어서,In the construction method of concrete structures installed underground or underwater, 시공하고자 하는 콘크리트구조물을 지상에서 제작한 후 저면 또는 측면에 유압실린더를 다수개 장착하여 유압장치에 의한 로봇화된 콘크리트구조체로 제작하는 구조체 제작단계와;A structure manufacturing step of manufacturing a concrete structure to be constructed on the ground and then mounting a plurality of hydraulic cylinders on the bottom or side to produce a robotized concrete structure by a hydraulic device; 상기 콘크리트구조체가 설치되는 지면에 기초파일을 다수개 선시공한 후 파일의 두부를 수평하게 정리하는 파일설치단계와;A pile installation step of horizontally arranging the head of the pile after preliminary construction of a plurality of foundation piles on the ground on which the concrete structure is installed; 상기 두부의 상부에 상기 유압실린더를 안착시켜 상기 콘크리트구조물을 지지시킨 후 콘크리트구조물의 아래쪽 지면을 굴착하는 굴착단계와;An excavating step of mounting the hydraulic cylinder on the top of the head to support the concrete structure and then excavating the lower surface of the concrete structure; 상기 단계 후 상기 유압실린더 중 하나의 유압실린더의 실린더를 상승시켜 기초파일을 지지하지 않도록 한 상태에서 지지되지 않은 기초파일을 실린더의 최대인출거리만큼 절단시킨 후 절단된 기초파일에 실린더를 하강시켜 지지시키는 과정과, 콘크리트구조물에 장착된 다른 유압실린더의 실린더를 상기 과정과 같이 각각 개별적으로 상승과 하강을 반복하여 작동시키면서 각각의 기초파일을 순차적으로 절단하는 과정으로 이루어진 기초파일 절단단계와;After the step, the cylinder of one hydraulic cylinder of the hydraulic cylinder is raised so as not to support the foundation pile, the unsupported foundation pile is cut by the maximum drawing distance of the cylinder, and then the cylinder is lowered to the cut foundation pile. A basic pile cutting step of sequentially cutting the respective basic piles while repeatedly operating the cylinders of the other hydraulic cylinders mounted on the concrete structure as described above; 상기 단계 후 개별적으로 각각 절단되어 수평하게 정리된 기초파일에 근접하도록 유압실린더를 동시구동하여 상기 콘크리트구조물을 하강시킨 후 상기 굴착단계 및 기초파일 절단단계를 반복수행하고, 상기 콘크리트구조물을 지중의 목표지점으로 하강시키는 구조물 하강단계와;After the step, the hydraulic cylinders are simultaneously driven to approach the foundation piles, which are individually cut and horizontally arranged, and then the concrete structures are lowered, and the excavation and cutting of the foundation piles are repeatedly performed. A structure descending step of descending to a point; 상기 단계 후 목표지점에 도달한 콘크리트구조물의 저부에 바닥콘크리트를 타설하여 양생하는 마무리단계로 이루어진 것을 특징으로 하는 콘크리트구조체를 이용한 구조물의 무소음 무진동 시공방법.Noise-free vibration-free construction method of a structure using a concrete structure, characterized in that the finishing step of curing by placing the bottom concrete on the bottom of the concrete structure reaches the target point after the step.
KR1020070082650A 2007-08-17 2007-08-17 Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction KR100819379B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070082650A KR100819379B1 (en) 2007-08-17 2007-08-17 Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070082650A KR100819379B1 (en) 2007-08-17 2007-08-17 Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction

Publications (1)

Publication Number Publication Date
KR100819379B1 true KR100819379B1 (en) 2008-04-04

Family

ID=39533748

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070082650A KR100819379B1 (en) 2007-08-17 2007-08-17 Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction

Country Status (1)

Country Link
KR (1) KR100819379B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010002076A1 (en) * 2008-07-01 2010-01-07 Dongjin Construction Co., Ltd. Caisson structures for underground soil blocking and manufacturing method of anti-noise non-vibration caisson structures using thereof
CN114481849A (en) * 2022-02-21 2022-05-13 北京好运达智创科技有限公司 Vibration system for capping beam construction
CN116068969A (en) * 2022-11-18 2023-05-05 熙恒科技(常熟)有限公司 Intelligent production management and control system of asphalt concrete

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03202510A (en) * 1989-12-28 1991-09-04 Nippon Concrete Ind Co Ltd Constructing method for underground structure
JP2000240088A (en) * 1999-02-19 2000-09-05 Taisei Corp Construction method for footing

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03202510A (en) * 1989-12-28 1991-09-04 Nippon Concrete Ind Co Ltd Constructing method for underground structure
JP2000240088A (en) * 1999-02-19 2000-09-05 Taisei Corp Construction method for footing

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010002076A1 (en) * 2008-07-01 2010-01-07 Dongjin Construction Co., Ltd. Caisson structures for underground soil blocking and manufacturing method of anti-noise non-vibration caisson structures using thereof
CN114481849A (en) * 2022-02-21 2022-05-13 北京好运达智创科技有限公司 Vibration system for capping beam construction
CN114481849B (en) * 2022-02-21 2024-06-07 北京好运达智创科技有限公司 Vibrating system for bent cap construction
CN116068969A (en) * 2022-11-18 2023-05-05 熙恒科技(常熟)有限公司 Intelligent production management and control system of asphalt concrete
CN116068969B (en) * 2022-11-18 2024-01-05 中亿丰(苏州)材料科技有限公司 Intelligent production management and control system of asphalt concrete

Similar Documents

Publication Publication Date Title
JP6166264B2 (en) How to build a retaining wall
KR101111594B1 (en) Method for constructing underground structure
CN114319396A (en) Construction method of bottomless box cofferdam suitable for underwater complex geological conditions
CN103711056A (en) Steel tool type temporary construction road and construction method thereof
KR100819379B1 (en) Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction
CN108118689B (en) Prefabricated underground diaphragm wall capable of being partially recycled, lifting appliance and construction method
CN108612049B (en) Construction method for shore protection engineering construction by adopting integral steel slip form structure
CN108221955B (en) Prefabricated underground diaphragm wall capable of being recycled integrally, lifting appliance and construction method
CN108221954B (en) Easy-to-detach prefabricated underground diaphragm wall, lifting appliance and construction method
CN109972644A (en) Pushing tow open caisson device and its construction method
CN206753488U (en) A kind of artificial digging pile reaming auxiliary equipment
CN109208623A (en) A kind of steel tube-concrete pile foundation and its construction method as temporary base
CN113279373B (en) Concrete warehousing complete method and hydropower station open channel repairing method
CN115387207A (en) Shallow covering layer steel-concrete composite pile pier structure and construction method
KR102294870B1 (en) Core wall structure of composite cassion for offshore runway
CN114411721A (en) Replacement construction method for steel trestle with steel pipe piles anchored after first forming bridge
CN114411761A (en) Advanced pre-support system for planned subway tunnel during construction of newly-built building and pre-support construction method
KR100891980B1 (en) Caisson structures for underground soil blocking and manufacturing method of anti-noise non-vibration caisson structures using thereof
Gispert Prefabricated foundations for housing applied to room modules
KR20150105891A (en) The underground facilities for offshore airfield of semi land reclamation type
CN209260744U (en) A kind of steel tube-concrete pile foundation as temporary base
CN114687356B (en) Construction method for deep foundation pit excavation of building
CN109469080A (en) A kind of embedding rock steel sheet pile cofferdam structure and its construction method under water
CN209066470U (en) A kind of steel tube-concrete series connection stake combination multi-column pier foundation
CN113006010B (en) Method for reinforcing concrete guide wall foundation

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130321

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20140129

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20160303

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20170425

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180326

Year of fee payment: 11

LAPS Lapse due to unpaid annual fee