KR20150105891A - The underground facilities for offshore airfield of semi land reclamation type - Google Patents
The underground facilities for offshore airfield of semi land reclamation type Download PDFInfo
- Publication number
- KR20150105891A KR20150105891A KR1020140028366A KR20140028366A KR20150105891A KR 20150105891 A KR20150105891 A KR 20150105891A KR 1020140028366 A KR1020140028366 A KR 1020140028366A KR 20140028366 A KR20140028366 A KR 20140028366A KR 20150105891 A KR20150105891 A KR 20150105891A
- Authority
- KR
- South Korea
- Prior art keywords
- pile
- piles
- prefabricated
- cast
- panel
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Mechanical Engineering (AREA)
- Revetment (AREA)
Abstract
Description
The present invention relates to an underground facility of a semi-landing maritime aerodrome using a cast-in-place pile method of a prefabricated caisson, more specifically, to secure stability by installing a cast-in-place pile in a sea floor facing method, The pile of the casting pile of the prefabricated pile can be integrated by carrying out the landfill by the unit volume, and the continuous beam, the box type structure and the cap beam on the sea surface can be installed to secure the stability of the whole structure. This paper deals with a runway underground facilities of an independent float foundation support on the sea floor using the
Deep foundations of soil and foundation fields are divided into foundation of pile foundation, cast-in-place pile and caisson foundation in file construction of civil engineering structure construction. The pile foundation is divided into steel pipe, PHC and RC pile depending on the material. And it is classified into type (hoe) pile and embedded pile according to the construction method in the pile foundation.
Generally, the bearing capacity of the structure is economical in terms of construction costs and the bearing capacity is large in the case of the pile, but the construction condition is not easy due to the noise vibration. And, when there is a gravel or a hard layer on the stratum, the piling is broken in case of hitting, so the application condition is not easy.
Therefore, when the above conditions are not met, the pile is buried or buried in the field, and the method of application such as SIP, SDA and PRD is developed in order to insert the pile after the excavation of the ground. many. Since the above-mentioned cast-in-place pile is installed at the site instead of the ready-made product, there are many difficulties in construction management and quality control, and in general, the bridge is widely used as a large diameter.
On the other hand, due to various factors such as the civil complaints caused by the noise generated during the construction of the airfield, the securing and compensation of the land due to the extension of the runway due to the enlargement of the aircraft, and the restriction of the altitude due to obstacles in the adjacent area, This is an unavoidable phenomenon.
The aerodrome construction method is divided into three types such as landfill type, semi-submerged type and floating type. Firstly, the floating type has the advantage of being environment friendly which is simple in structure type and freedom in site selection. However, There is a problem that it is susceptible to fluctuation due to wave, and a large cross-sectional force is generated.
Since the semi-submerged type is stable to blue but requires a high cross-sectional area and can be applied only in the deep sea, the construction of marine infrastructure such as a traffic route connected to the land is suitable for a place falling adequately on the shoreline and the site selection is extremely limited. Construction must follow.
Therefore, the reclamation method is suitable for water depths of about 20 m in consideration of economical efficiency and constructability. However, reclamation favoring land reclamation has recently been highly valued, and the value of utility for tidal flats in terms of national image and environmental protection due to stock development (Ramses Wetlands) inventory is superior to recreational economic creation And has caused many civil complaints such as the destruction of ecosystem due to large landfill.
Therefore, the advantages of the reclamation type excellent in the ability to cope with environmental external force among the above-described three construction methods are exaggerated and complementary so that the reclamation is not carried out completely, The combination of the independent float method with the piling method is used to secure the site stability and to prevent the rapid change of the ecosystem and the damage to the nearby fisheries by partially communicating the flow of the algae in the landfill The present inventors have considered various aspects in underground facilities to realize this.
In the existing landfill method, a caisson is installed in the landfill area, and the landfill is landfilled. As a result, the uplift phenomenon and liquefaction phenomenon in adjacent areas due to landfill and soil erosion from landfill are a part to be tolerated.
For example, when the input cargo quantity is detected, it is calculated that, in the case of direct reclaim, crushed stone and soil, the landfill will be buried in a region with a width of 100 m, a length of 3.000 m and a depth of 20 m. 3.000m × 20m × 1.25 = 7,500.000 m 3 , even if it takes only 50% of this figure, it is 3,750,000 m 3 , which is saved by about 400,000 units with a 25-ton dump truck (9.5 m 3 ). Therefore, it is enough to recognize the traffic congestion caused by the quarrying and transportation process, and the indirect cost for the air.
In order to reduce the natural settlement period due to this, it is indispensable to carry out the deep ground treatment mixer (DCM) or sand drain, sand paper, jet grouting, etc. as soft ground replacement and reinforcement.
In addition, the size of the caisson has been gradually enlarged to a minimum of 1.000 to 15,000 tons. From this land-based production to the landing, the hoisting equipment is also becoming larger and at least 2,000 tons of operating equipment is essential.
Therefore, it is inevitable that the construction period should be fixed according to the idle schedule of the extremely limited equipment. Even when the caisson is mounted, the caisson is seated only when the entire undersurface of the leading end is subjected to a smoothing operation at a time.
Accordingly, the present inventor intends to make use of the piling method of a cast-in-place pile using a prefabricated caisson, which can be operated as a 300-ton crane, and to combine the additional piles to make it easier to arrange, procure and operate the equipment.
That is, in the invention patent 10-1256274 of the present invention, the assembly caissons are connected by dragging and connecting the assembly caissons to each other to form a square-shaped structure on the undersurface, and the inside thereof is dredged up to the top of weathered rock (sandstone) The steel jacket with induction steel pipe is installed and the underwater concrete is put together to integrate it. This not only increases the footing role and function of the pier but also reduces the error range when entering the steel pipe, Which can be used for pile driving.
In addition, in the invention 10-1211811, it is possible to offset the support force, bending moment and eccentric load in the vertical or horizontal direction by providing a float on the bottom or bottom of the sea, which is used as an extension base of the direct- (RCD) method using an assembled caisson and a jacket which can reduce the resistivity against differential settlement to a pile base and increase the responsiveness according to the reduction of the overhead load of the upper bridge.
The inventor of the present invention has found that the application of the underground facility is efficient in completing the semi-landing marine aerodrome which is used wholly or in part for landing and landing of aircraft by utilizing the inventions of the invention.
In view of the above circumstances, the present invention is an invention of an underground facility of a runway. In the present invention, a bottom float is installed on a sea floor so as to apply a pre-cast pile method of a prefabricated caisson to a stand- To the bedrock by using the RCD (Reverse Circulation Drill) equipment, and by socking the landfill, the prefabricated panel is stacked by the landfill area and the inside is crushed and the soil is filled to increase the load. The bending moments of the vertical and horizontal bending moments and eccentric loads are increased by increasing the response force to the waves and increasing the response force against the stress due to the soil reaction force and the unbalanced settlement. Provide underground facilities of the maritime aerodrome that can offset and reduce the space for differential settlement with pile foundation Wish as it is an object.
Another object of the present invention is to provide a pile-in-place pile method of a prefabricated caisson in order to achieve the air delay due to the sinking of the pile and the efficiency of the pile file settlement during the pile installation, It is possible to set the area between each pile, to stack the prefabricated panels and to maintain the volume, to fill the inside with crushed stones and soil and to fill the per unit area to maximize the advantage of the buried type construction method, It is possible to provide an underground structure of a semi-landing maritime aerodrome that aims to reduce the difficulty in purchasing the related facilities by using the underground space by uniformly transferring the overhead load to the bedrock and the seabed surface and securing the structural stability .
In order to accomplish the above object, the present invention provides a method of installing a first concrete on a seabed surface by applying a ground piling method of a prefabricated caisson to an independent float basis method of a direct basic method, And a plurality of piles are poured into the concrete on the lower hut, and a second concrete is poured on the lower hut. The piles are then poured into a secondary concrete, And a plurality of unit structures, each of which is provided with a plurality of unit structures.
As described above, according to the present invention, it is possible to overcome various constraint requirements of the seabed topography and conditions by adopting the cast-in-place pile method of the prefabricated caisson, and to select a wider area, It is possible to reduce the damages on the adjacent areas caused by landfill and reduce the abrupt change of ecosystem by distributing seawater according to the interval and to reduce the cutting and input amount of the soil, It is possible to perform simultaneous operation in the direction of the air, thereby greatly shortening the air, thereby greatly contributing to the reduction in time and cost.
FIG. 1 is a view showing an installation state of a maritime aerodrome using the cast-in-place pile method of the prefabricated caisson of the present invention,
2 is a front view and an installation perspective view of a structure in an underground facility of a marine airfield according to an embodiment of the present invention,
Fig. 3 is a flow chart for installation of a prefabricated caisson and a jacket,
FIG. 4 is a detail view of the assembled casings shown in FIG. 3,
Fig. 5 is an installation view of the reinforcing steel net and the jacket shown in Fig.
6 is a flow chart of the steel pipe insertion and RCD,
FIG. 7 is a schematic view showing the lower grouting, the assembled panel installation,
FIG. 8 is a detailed view of the bottom assembled panel, the connecting portion of the steel tube support, and the bottom of FIG. 7,
9 is a detailed view of a steel pipe support,
10 is a view showing a continuous beam installation, the formation of a box-like structure, and the installation of a top plate.
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
FIG. 1 is a view showing a maritime aerodrome using the cast-in-place pile method of the prefabricated caisson according to the present invention. In the present invention, a marine aerodrome is constructed by constructing a marine airfield, , And it is applied by applying the cast-in-place pile method of the prefabricated caisson to the independent supporting foundation supporting method.
Therefore, it will expand the choice of location selection by marine airfield, reduce temporal, spatial and economic saving such as reduction of damages to construction area and surrounding ecosystem, reduction of civil incidence, drastic reduction of input trade volume, It is possible to respond positively to the environmental external force that can be generated at the time of construction.
(See FIG. 7) is added to the underside footing method using the invention patent of the inventor of the present invention to secure stability on the bedrock, and a prefabricated panel (see FIG. 9) It is necessary to secure the stability of the whole structure by integrating the ties between each pile and to establish a place where the various facilities can be attracted, We will respond positively to prevention of damage to natural environment.
At marine airfields, all of the passenger facilities, customs facilities, and aircraft support facilities can utilize a wide space underground, except for the necessary control facilities, security facilities, maintenance and hangar, etc.,
A security facility and a
The structure of the semi-buried maritime aerodrome of the present invention is such that the bottom flooding is installed on the bottom surface (see FIG. 3) so that the cast-in-place pile method of the prefabricated caisson can be applied to the independent float- (See FIG. 6), and a built-up type panel is stacked for each zone to fill crushed stone and gravel (see FIG. 7) to increase the load (See Fig. 10), the bending moment in the vertical or horizontal direction, the bending moment in the eccentricity The load can be reduced and the pile foundation can dampen the space of differential settlement.
FIG. 2 is a front view and a perspective view of a facility in an underground facility of a maritime airfield according to an embodiment of the present invention. It shows the procedure for installing the prefabricated caisson, jacket and primary concrete in FIG. 3, The lower grouting assembled panel of FIG. 7, the crushing of the crushed stone, and the continuous beam installation of FIG. 10 and the box-type structure installation.
In other words, a large number of on-shredding
The
In order to improve the air delay and the settlement of the steel pipe due to the sinking of the cave during the construction of the support pile, the marine aerodrome structure and the ground facilities of the present invention are designed to introduce the cast- It is possible to maximize the advantages of the landfill construction method by ensuring the basal point and setting the area between each pile, accumulating prefabricated panels to keep the volume, filling the interior with crushed stones and soil, The structure is unified to uniformly load the overhead load on the bedrock and seabed, ensuring structural stability.
FIG. 3 is a view showing a construction procedure for installing a prefabricated caisson, a jacket, and a primary concrete, FIG. 4 is a view showing a connection method of the prefabricated caisson shown in FIG. 3, And jacket. The construction of the offshore airfield structure of the present invention is not limited to the case where pile operation is performed while the tidal area is worsened or weather condition deteriorates or inevitably occurs, In order to reduce the time and economic loss required for in-situ re-settlement, a
As shown in Fig. 3 (a), the
As shown in FIG. 3 (b), the
The prefabricated caisson shown in Fig. 4 (a) is composed of a male-assembled
At this time, the size of the square of the
In the male-assembled
When the assembly of the
Then, the
5 (a) is a reinforcing bar net made of reinforcing
A plurality of
5 (c), the
Thereafter, as shown in FIG. 3 (d), the underwater concrete can be firstly laid by using the
As described above, by applying the ground piling method of the prefabricated caisson to the independent floating method of the direct basic method and installing the
6 is a flowchart of steel pipe insertion and RCD (Reverse Circulation Drill). The vibrohammer 212 (shown in FIG. 3 (d)) in the
The diameter of the mainstream steel pipe (211) is 2,000 to 2,500 mm in diameter, which is good in land transportation and general purpose, and a steel pipe having a thickness of 12 mm or more is used.
At this time, as shown in FIG. 4 (f), the
Therefore, as shown in Fig. 6 (a), the near-
Here,
The reinforcing
5 (a) is mounted on the
As shown in FIG. 6 (d), the reinforcing
Thereafter, the secondary concrete is poured into the void space between the entrained
Therefore, the four
Figure 7 is a bottom grouting, prefabricated panel installation, and crush fill diagram. 7 (a) is a cross-sectional view of the
That is, as shown in FIG. 6, the four concrete ducts shown in FIG. 6 and the in-situ concrete piles of the adjacent steel pipe are stacked on the
The
At this time, the grouting in the
Fig. 7 (b) is a flow chart showing the operation sequence of the assembled
8 (b) is a detailed view of the
First of all, it is preferable to use the steam-cured reinforced concrete, and the size of the
The
8A, the lower assembled
The lower assembled
The lower end of the
The connecting
9 (a): 425) and the bottom part of the joint part (Fig. 8 (b): 424) is assembled as shown in Fig. 9,
The connection
The
A non-toxic foam sponge (EVA sponge) is mounted on each of the assembled panel
As shown in FIG. 9, when the loading and unloading of the pile support to one side is completed, the wire is inserted into the connecting
The
The dropping
The assembly of the
When the dropping is completed, as shown in FIG. 7 (d), a smoothing operation is performed with the
9 (a) to Fig. 8 (c) are sequentially stacked to divide the buried region into zones and complete the steel pipe support shown in Fig. 9 as a built-up structure, And the soil can be filled and the load can be increased to secure stability by self weight.
9 is a detailed view of a steel pipe support, and includes a lower assembled
A pile
10 is a view showing a continuous beam installation, the formation of a box-like structure, and the installation of a top plate.
As shown in FIG. 10 (a), a plurality of field drilled
By installing a continuous reinforced
In addition, the underground clearance space can cope with the vibration and noise generated when taking off and landing airplanes, and can be usefully used as a ventilation hole and various piping facility passages.
Specifically, the reinforced concrete
10 (c), the cap beams 310 are installed on the ground drilled
A
The present invention adopts the field piling method of the prefabricated caisson to overcome various constraints of the seabed topography and conditions and to select a wider area. It is possible to reduce the damage of adjacent areas and to distribute seawater by sections. By reducing abrupt change of ecosystem and securing and utilizing underground space, it is possible to solve the difficulties by securing the site of related facilities, At the same time with the installation, it is possible to concurrently work in all directions by abolishing the existing landfill method and greatly shortening the air, thereby contributing to the saving in time and economy.
INDUSTRIAL APPLICABILITY As described above, the present invention is advantageous in that it is easy to form a quadrangular runway capable of taking off and landing even in a side direction of the wind speed (in the direction perpendicular to take-off and landing) In addition, since the foundation part of the landfill is connected to the bedrock by applying the cast-in-place pile method of the prefabricated caisson, the formation of the soft ground such as liquefaction due to the landfill, consolidation settlement and reinforcement treatment and replacement work are not necessary.
In the present invention, a grating is provided in a section of a river when it is heavy or heavy, so that drainage and drainage are extremely short, thereby reducing the operation management facility and cost. For example, it is possible to work up to 80 m depth (depth to which industrial diver can be put) so that the range of site selection can be expanded. Due to the development of future unmanned submersible (R, O, V) Depth can be deeper.
In addition, if the width and height of the waterway section are adjusted, it is possible to install anchoring facilities suitable for the scale at low cost, so that it is possible to use a submarine base, which is difficult to observe a certain area, at the same time.
It is to be understood that the underground facilities of the anti-landing maritime aerodrome of the present invention are not limited to the described embodiments, and that various modifications and variations can be made without departing from the spirit and scope of the present invention. It is self-evident.
It is therefore intended that such variations and modifications fall within the scope of the appended claims.
101: Control facility
102: Security Facilities and Terminals
103: boarding, maintenance shelter, security facilities
104: runway
105: aircraft
106: Sea level
107: Maintenance workshop
108: and the base
109: Shoulder
110: induction furnace
111: Underground entrance
112: Underground space
113: underground space
114: Lower Footing
201: Crane
202: Barge
203: Sea floor
204: Subsea sediment
205: Kramshell bucket
206: Prefabricated caisson
207: Jacket
208: Induction steel pipe
209: Treme Pipe
210: Marine concrete working line
211: Inserted steel pipe
212: Vibrohammer
213: RCD equipment
314: excavation surface
215: RCD Powerpack
216: RCD equipment
217: Reinforcing mesh (cast-in-place pile)
218: Excavated soil carrier
219: Concrete pouring part
220: Perforator (for grouting)
221: Cement injector
222: injection pressure
223: Grouting section section
224: injection direction
225: Concrete injection hose
226: Bushing roller
227: Wire connection ring
228: Circular hole
229: Primary concrete casting surface
230: Oyster tank
231: Induction Steel Pipe Protector
232: Grouting pipe protector
301: Prefabricated panel
302: Prefabricated panel circular portion
303: Pile reinforcement support
304: Crushing concentrate
305: Excavator
306: Crushed stone
307: Pipe for discharge
308: Rock-solidifying device
309: Tofu arrangement surface
310: Cap Beam
311: Top plate (runway)
312: Remicon vehicle
313: Box type structure
314:
315: Continuous beam
316: Prefabricated panel
317: Buffer space
401: H-beam
402: Rebar
403: Pipes for grouting
404: Angle
405: connection support
406: Nut
407: Bolt
408: Washer
409:
410: Pile support connection hole
411: Circular section linkage
412: Upper and lower connecting links
413: Upper key (key)
414: connection part (home)
415: Circular portion
416: Field casting piles
417: Pile support linkage mounting part
418: pile support vertical connection plate
419: Pile support circular part (outside)
420: pile support circular part (inner part)
421: Pile support transverse links
422: Pile support connection
423: Top panel of connection
424: connection panel bottom panel
425: bottom panel
426: Jacket connection support
427: Prefabricated panel top
428: Lower part of the assembled panel
501: landfill portion
502:
503: Flow of algae
504:
505: Lower Footing
601: Male-built cable
602: Arm-assembled cable
603: Circular hole
604: Sand pump
605: air pressure inlet
606: Towing and Connecting Hooks
607: Connection ring
608: Air pressure
609: Male caisson connection
610: Bushing roller
611: Wire
612: Edge caisson
613: Piping hose
Claims (6)
The support piles are connected to the bedrock by using RCD equipment to connect a plurality of piles to the second finishing concrete,
Wherein the piles are divided into a plurality of landfill areas and piles are stacked on a pile reinforcing support block so as to fill the crushed stones and the soil to fill up the piles.
Underground facilities of anti - landing marine airfields.
Wherein each of the sub-seabed sediments is divided into a plurality of submerged piles on the corresponding lower backing, and a prefabricated panel between the submerged piles and a prefabricated panel circular portion.
Characterized in that a plurality of pile reinforcing supports are installed between the piling piles of the cast structure and the continuous pile is provided on the sea surface
Underground facilities of anti - landing marine airfields.
Wherein the slab is placed on the reinforced concrete continuous beam using the upper part of the assembled panel and the upper part of the pile support to form a box-like structure on the side and the upper part in the same manner.
Characterized in that a cap beam is installed on the ground drilled pile between the respective structures on the sea level.
Wherein the cabin is provided with a top plate of a runway using a ready-made vehicle, and a bottom end stop of the cap non-clinical runway top plate is provided to prevent the bottom of the underwater landing aerodrome.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020140028366A KR20150105891A (en) | 2014-03-10 | 2014-03-10 | The underground facilities for offshore airfield of semi land reclamation type |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020140028366A KR20150105891A (en) | 2014-03-10 | 2014-03-10 | The underground facilities for offshore airfield of semi land reclamation type |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20150105891A true KR20150105891A (en) | 2015-09-18 |
Family
ID=54244971
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020140028366A KR20150105891A (en) | 2014-03-10 | 2014-03-10 | The underground facilities for offshore airfield of semi land reclamation type |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20150105891A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106351257A (en) * | 2016-10-14 | 2017-01-25 | 北京工业大学 | Built-in separation plate prefabricated separate post for underground structure |
CN111455959A (en) * | 2019-01-21 | 2020-07-28 | 中国电建集团华东勘测设计研究院有限公司 | Shallow pile type jacket structure for offshore booster station |
-
2014
- 2014-03-10 KR KR1020140028366A patent/KR20150105891A/en active Search and Examination
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106351257A (en) * | 2016-10-14 | 2017-01-25 | 北京工业大学 | Built-in separation plate prefabricated separate post for underground structure |
CN111455959A (en) * | 2019-01-21 | 2020-07-28 | 中国电建集团华东勘测设计研究院有限公司 | Shallow pile type jacket structure for offshore booster station |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102720140B (en) | Large-span prestress concrete continuous beam deepwater pier construction process | |
CN100564700C (en) | The job practices of lattice type steel column tower crane pedestal | |
CN103321241B (en) | Deep water open type combination foundation harbour and construction method thereof | |
KR101211811B1 (en) | Cast in concrete pile With precast type Caisson | |
CN210104758U (en) | Foundation pit supporting system of soil nail bored concrete pile anchor cable combination | |
CN104452829A (en) | Piled raft foundation anti-floating structure and construction method | |
KR20160080028A (en) | Multipurpose artifical island | |
CN106988334A (en) | A kind of open caisson supporting construction and open caisson construction method | |
KR20150110238A (en) | Semipermeable breakwater of combined power generation facility | |
Abdrabbo et al. | Challenges and uncertainties relating to open caissons | |
CN103711056A (en) | Steel tool type temporary construction road and construction method thereof | |
KR101256274B1 (en) | Reverse Drill Method With precast type Caisson and Jacket | |
CN113931211A (en) | Fabricated foundation and foundation of ground firmware and installation method thereof | |
CN102561379A (en) | Novel bridge installation foundation and construction method thereof | |
CN108999142A (en) | The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater | |
KR101650231B1 (en) | Construction structures with wave power generator of semipermeable breakwater | |
CN103572770B (en) | A kind of stake case hydraulic structures and construction method thereof | |
CN102733407A (en) | Two-ring grouted single pile foundation | |
KR102294871B1 (en) | Core wall structure method of the independent cassion for offshore runway | |
KR20150137725A (en) | Construction structures of semipermeable breakwater with wind power generator | |
KR20150105891A (en) | The underground facilities for offshore airfield of semi land reclamation type | |
CN204326119U (en) | A kind of pile-raft foundation float Structure | |
KR102294870B1 (en) | Core wall structure of composite cassion for offshore runway | |
KR20110046209A (en) | Method Of Construction For Scour Prevension And Reinforcement Of Bridge Pier, And Structure Of The Same | |
CN106049516A (en) | Corrugated steel cofferdam hollow digging pile and manufacturing technique thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
AMND | Amendment | ||
E601 | Decision to refuse application | ||
AMND | Amendment | ||
J301 | Trial decision |
Free format text: TRIAL NUMBER: 2016101003423; TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20160607 Effective date: 20171110 |