KR100813664B1 - Method for constructing land-side protection wall - Google Patents

Method for constructing land-side protection wall Download PDF

Info

Publication number
KR100813664B1
KR100813664B1 KR1020070054454A KR20070054454A KR100813664B1 KR 100813664 B1 KR100813664 B1 KR 100813664B1 KR 1020070054454 A KR1020070054454 A KR 1020070054454A KR 20070054454 A KR20070054454 A KR 20070054454A KR 100813664 B1 KR100813664 B1 KR 100813664B1
Authority
KR
South Korea
Prior art keywords
bulletin
excavation
main
reinforcement
excavated
Prior art date
Application number
KR1020070054454A
Other languages
Korean (ko)
Inventor
장지건
Original Assignee
장지건
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 장지건 filed Critical 장지건
Application granted granted Critical
Publication of KR100813664B1 publication Critical patent/KR100813664B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A method for constructing a retaining wall having reinforced sectional second moment is provided to construct the land-side prevention wall having deep depth easily by inclining rakers in lower parts of the second main beams and excavating main excavated parts. Multiple first main beams(120) are installed along edges of surfaces to be excavated, and multiple second main beams(130) are placed in the first main beams. Excavated parts(220) of reinforcing members are excavated, and first and second main beams are connected by reinforcing members. A main excavated part(210), which is between the second main beams, is excavated. Rakers are installed to be inclined and removed to support the second main beams. Ground continuous walls(110) are formed between the first main beams along the edges of the surfaces to be excavated.

Description

단면 2차 모멘트가 강화된 흙막이 시공 방법{METHOD FOR CONSTRUCTING LAND-SIDE PROTECTION WALL}Construction method of earthen board with reinforced second-side moment {METHOD FOR CONSTRUCTING LAND-SIDE PROTECTION WALL}

도 1은 본 발명에 의한 일 실시례에 따라 주보설치단계를 거친 굴착지반의 평면도, 1 is a plan view of the excavated ground through the jumbo installation step according to an embodiment of the present invention,

도 2a 내지 도 2h는 도 1의 굴착지반이 굴착되는 방법을 순서적으로 도시한 것, 2a to 2h sequentially illustrate how the excavation ground of FIG. 1 is excavated,

도 3은 동일 깊이에 위치한 보강재용 굴착부를 굴착하고 제1보강재를 설치하는 방법을 순서적으로 도시한 것, 3 is a view showing a method of excavating the excavation for the reinforcement located in the same depth and installing the first reinforcement in order,

도 4a 내지 도 4c는 제1주보, 제2주보, 및 이들 사이에 연결되는 제1보강재의 여러가지 연결상태를 도시한 것,4A to 4C illustrate various connection states of the first reinforcement, the second reinforcement, and the first reinforcing material connected therebetween,

도 5a 내지 도 5e는 도 1의 굴착지반이 본 발명에 의한 다른 실시례에 따라 굴착되는 방법을 순서적으로 도시한 것,Figures 5a to 5e sequentially illustrates how the excavation ground of Figure 1 according to another embodiment according to the present invention,

도 6은 본 발명의 실시례에 따라 시공된 흙막이의 여러가지 종단면도,Figure 6 is a longitudinal cross-sectional view of the construction of the earthenware constructed in accordance with an embodiment of the present invention,

도 7은 본 발명의 다른 실시례에 따라 시공된 흙막이의 종단면도,Figure 7 is a longitudinal cross-sectional view of the earthenware constructed in accordance with another embodiment of the present invention,

도 8은 본 발명의 다른 실시례에 따라 시공된 흙막이의 평면도 및 종단면도,8 is a plan view and a longitudinal sectional view of an earthquake constructed in accordance with another embodiment of the present invention;

도 9는 본 발명의 다른 실시례에 따라 시공된 흙막이의 평면도 및 종단면도,9 is a plan view and a longitudinal sectional view of the earthenware constructed in accordance with another embodiment of the present invention;

도 10 및 도 11은 도 8 및 도 9에 대응하여 지중연속벽 대신 흙막이판을 사용한 실시례,10 and 11 are embodiments using a retaining plate instead of the continuous wall in correspondence with FIGS. 8 and 9,

도 12 내지 도 19는 본 발명이 적용될 수 있는 여러가지 사례들의 시공 순서도,12 to 19 is a construction flowchart of various cases to which the present invention can be applied,

도 20은 본 발명이 적용된 다른 실시례의 평면도 및 종단면도,20 is a plan view and a longitudinal sectional view of another embodiment to which the present invention is applied;

도 21은 본 발명이 적용된 다른 실시례의 종단면도,21 is a longitudinal sectional view of another embodiment to which the present invention is applied;

도 22는 본 발명이 적용된 다른 실시례의 종단면도.Figure 22 is a longitudinal sectional view of another embodiment to which the present invention is applied.

< 도면의 주요 부분에 대한 부호의 설명 ><Description of Symbols for Main Parts of Drawings>

110 : 지중연속벽 120 : 제1주보110: continuous underground wall 120: first bulletin

130 : 제2주보 140 : 흙막이판130: second note 140: earthen board

210 : 본굴착부 220 : 보강재용 굴착부210: the main excavation portion 220: excavation portion for the reinforcement

310 : 제1보강재 320 : 제2보강재310: first reinforcing material 320: second reinforcing material

410 : 버팀대 701 : 레이커410: Prop 701: Raker

대한민국 공개특허공보 제10-2006-0032823호 "2열 파일을 이용한 흙막이 공법", Republic of Korea Patent Publication No. 10-2006-0032823 "soil barrier construction method using a two-row pile",

대한민국 공개특허공보 제10-2005-0010616호 "건축용 흙막이 횡트러스 버팀 공법 및 구조", Republic of Korea Patent Application Publication No. 10-2005-0010616 "Building earth fence transverse truss support method and structure",

대한민국 공개특허공보 제10-2003-0030868호 "흙막이벽 구축용 트러스식 지보구조체"Republic of Korea Patent Publication No. 10-2003-0030868 "Truss-type support structure for the construction of earthen wall"

본 발명은 흙막이 시공 방법에 관한 것으로, 구체적으로는 제1주보와 제1주보의 내측에 마련되는 제2주보를 미리 지중에 설치한 후 지반을 굴착함에 따라서 제1주보와 제2주보 사이를 연결하는 제1보강재를 설치하여 굴착 깊이에 따라서 주보의 단면 2차 모멘트가 확장되어 주보의 물량 대비 극대화된 굴착 깊이를 구현할 수 있는 새로운 흙막이 시공 방법에 관한 것이다.The present invention relates to a construction method for earthenware, and in particular, the first bulletin and the second bulletin provided on the inner side of the first bulletin are installed in the ground in advance, and then the ground is connected between the first bulletin and the second bulletin. By installing the first reinforcing material to the cross section secondary moment of the main beam in accordance with the depth of excavation and relates to a new construction method for the construction of the excavation to realize the maximum excavation depth compared to the volume of the main beam.

일반적으로 흙막이는 지하 구조물을 건설할 때, 지반이 붕괴되는 것을 방지하기 위하여 굴착된 지하 공간에 설치되는 임시 구조물 또는 영구 구조물로서, 토목의 경우에는 지하철 건설 등에 많이 사용되고 있으며, 건축의 경우에는 빌딩의 지하층 건설에 많이 사용되고 있다.In general, when the construction of the underground structure is a temporary structure or permanent structure installed in the excavated underground space in order to prevent the ground collapse, civil engineering is used for the construction of subways, and in the case of construction It is widely used for underground construction.

그러나 현재의 흙막이 공법은 많은 수의 버팀대(STRUT)가 사용되어 비경제적이며, 버팀대(STRUT)로 인하여 작업 공간 확보가 어려울 뿐만 아니라, 구조적으로도 비효율적이다.However, the current retaining method is uneconomical because a large number of struts are used, and it is difficult to secure a working space due to the struts and structurally inefficient.

한편, 본 명세서에 일체화된 종래의 기술로서 대한민국 공개특허공보 제10- 2006-0032823호 "2열 파일을 이용한 흙막이 공법", 대한민국 공개특허공보 제10-2005-0010616호 "건축용 흙막이 횡트러스 버팀 공법 및 구조", 대한민국 공개특허공보 제10-2003-0030868호 "흙막이벽 구축용 트러스식 지보구조체" 등이 공개되어 있다.On the other hand, as a conventional technology integrated in the present specification, the Republic of Korea Patent Publication No. 10-2006-0032823 "pigment construction method using a two-row file", Republic of Korea Patent Publication No. 10-2005-0010616 "Building mudguard transverse truss support method And structure, "Korean Unexamined Patent Publication No. 10-2003-0030868," a truss-type support structure for constructing an earthquake wall "and the like are disclosed.

상기의 종래 기술들은 기본적으로 굴착예정면의 굴착과 흙막이의 주보(post)의 시공이 독립적으로 이루어진다.The prior art is basically the construction of the excavation of the excavation expected surface and the construction of the post (post) of the retaining wall.

즉, 굴착예정면의 굴착이 완료된 후 흙막이 주보의 시공이 완료되거나, 혹은 흙막이 주보의 시공이 완료된 후 굴착예정면이 굴착된다.That is, after the excavation of the excavation prospecting surface is completed, construction of the retainer jumbo is completed, or after the construction of the retainer jumbo is completed, the excavation expectation surface is excavated.

이러한 종래 기술에 의하여 흙막이를 시공하면 동일한 주보에 의할 경우에는 굴착 깊이에 한계가 있을 수 밖에 없으며, 굴착 깊이를 깊게 하고자 할 경우에는 주보의 지지력을 확대하기 위하여 수많은 보강재가 필요하게 된다.If the construction of the earthenware according to the prior art, there is no limit to the excavation depth in the case of the same bulletin, if you want to deepen the excavation depth is required a number of reinforcement to expand the bearing capacity of the bulletin.

본 발명은 상기와 같은 종래 기술의 문제점을 해결하기 위하여 안출된 것으로서, 제1주보와 제1주보의 내측에 마련되는 제2주보를 미리 지중에 설치한 후 지반을 굴착함에 따라서 제1주보와 제2주보 사이를 연결하는 제1보강재를 설치하여 굴착 깊이에 따라서 제1주보, 제2주보 및 제1보강재로 이루어지는 주보의 단면 2차 모멘트가 확장되어 주보의 물량 대비 극대화된 굴착 깊이를 구현할 수 있는 새로운 흙막이 시공 방법에 관한 것이다.The present invention has been made to solve the problems of the prior art as described above, the first bulletin and the second bulletin provided in the interior of the first bulletin in advance in the ground after the first bulletin and ground excavation By installing the first reinforcing material connecting the two beams, the second moment of the cross section of the beam consisting of the first beam, the second beam and the first reinforcement can be expanded according to the excavation depth to realize the maximum excavation depth compared to the quantity of the beam. It is about new construction method.

상기의 과제를 해결하기 위하여 본 발명은, 굴착예정면의 가장자리를 따라 다수의 제1주보를 설치하고, 상기 제1주보 내측에 다수의 제2주보를 설치하는 주보설치단계(S10);
상기 제1주보와 제2주보의 사이인 보강재용 굴착부를 굴착하면서 상기 제1주보와 제2주보가 연결되도록 보강재를 연결하는 보강재용 굴착부 굴착 및 보강재 연결단계(S20);
상기 제2주보와 서로 대향되어지는 또 다른 제2주보 사이인 본굴착부를 굴착하는 본굴착부 굴착단계(S30);
상기 보강재용 굴착부 굴착 및 보강재 연결단계(S20)와 본굴착부 굴착단계(S30)가 2회이상 반복되어지는 굴착반복단계(S40);
상기 굴착반복단계(S40)의 본굴착 굴착단계(S30)에서 본굴착부(210)의 제2주보(130) 하부 내측에 상기 제2주보9130)가 버티어지도록 레이커(701)를 경사지게 설치 및 해체하는 레이커 설치 및 해체단계(S50)로 이루어짐을 특징으로 한다.
In order to solve the above problems, the present invention, the installation of a plurality of first bullets along the edge of the prospecting excavation surface, and installing a plurality of second bulletin inside the first bulletin (S10);
Digging excavation and reinforcing material connecting step (S20) for connecting the reinforcing material to be connected to the first and second bulletin while excavating the reinforcing material excavation portion between the first and second bulletin;
A main excavation part excavating step (S30) for excavating the main excavation part between the second jog and another second jog facing each other;
Excavation repetition step (S40) is repeated two or more times the excavation part excavation and reinforcing material connection step (S20) and the main excavation part excavation step (S30) for the reinforcement;
Installing and dismantling the raker 701 inclined so that the second bulletin 9130 is supported on the lower inner side of the second bulletin 130 of the main excavator 210 in the main drilling excavation step (S30) of the excavation repeating step (S40). It characterized by consisting of a raker installation and dismantling step (S50).

상기에 있어서, 상기 주보설치단계에서 굴착예정면의 가장자리를 따라 지중연속벽을 형성하는 것일 수 있다. 혹은 상기에 있어서, 상기 굴착단계에서 굴착예정면의 가장자리에 위치한 상기 제1주보를 따라 흙막이판을 설치할 수 있다.In the above, it may be to form a continuous wall along the edge of the surface to be excavated in the installation step. Or in the above, it may be installed in the excavation step along the first bulletin located on the edge of the excavation surface.

상기에 있어서, 상기 제1보강재는 상기 제1주보 및 상기 제2주보에 볼팅 또는 용접되어 연결될 수 있다.In the above, the first reinforcing material may be bolted or welded to the first bulletin and the second bulletin.

상기에 있어서, 상기 주보설치단계에서, 상기 제1주보 및 상기 제2주보의 근입부의 강성을 증가시키기 위하여 제1주보 및 상기 제2주보 사이의 하부지반을 개량할 수 있다.In the above bulletin installation step, the lower ground between the first bulletin and the second bulletin can be improved to increase the rigidity of the indentation of the first bulletin and the second bulletin.

상기에 있어서, 상기 굴착단계는, 본굴착된 지반의 하부에 지반의 굴착면을 가로지르면서 상기 제2주보사이를 연결하는 버팀대를 설치하는 단계와, 본굴착의 진행에 따라 본굴착된 지반의 중간부에 위치하게 되는 상기 버팀대를 철거하는 단 계를 더 포함할 수 있다.In the above, the excavation step, the step of installing a brace connecting the second jovo while crossing the excavation surface of the ground at the bottom of the main excavated ground, and the main excavation of the ground according to the progress of the main excavation It may further comprise the step of removing the brace is located in the middle portion.

상기에 있어서, 상기 주보설치단계에서 상기 굴착예정면의 가장자리로부터 굴착배면을 향하여 이격되게 보조지중연속벽을 형성하는 한편 상기 보조지중연속벽을 따라 복수의 제1보조주보를 서로 간격을 가지도록 설치하며, 상기 시공된 흙막이는 제2보강재(320)에 의하여 상기 제1주보의 상부가 상기 제1보조주보의 상부와 연결된 것일 수 있다. 제2보강재는 주보설치단계에서 설치되거나 혹은 굴착단계에서 설치될 수 있다.In the above-described information installation step, the auxiliary underground continuous wall is formed to be spaced apart from the edge of the expected excavation surface toward the excavation back surface, and the plurality of first auxiliary information along the auxiliary continuous wall is installed to be spaced apart from each other. In addition, the constructed soil block may be the upper portion of the first bulletin by the second reinforcing material 320 is connected to the upper portion of the first secondary beam. The second reinforcement may be installed in the main installation step or in the excavation step.

상기에 있어서, 상기 주보설치단계에서 상기 제1주보로부터 굴착배면을 향하여 이격되게 복수의 제1보조주보를 서로 간격을 가지도록 설치하며, 상기 시공된 흙막이는 제2보강재에 의하여 상기 제1주보의 상부가 상기 제1보조주보의 상부와 연결된 것일 수 있다.In the above-mentioned information, in the step of installing the first bulletin from the first to the excavation back spaced apart from each other to install a plurality of first auxiliary beams to be spaced from each other, the constructed earth block is the second reinforcement of the first An upper portion may be connected to an upper portion of the first auxiliary bulletin.

상기에 있어서, 상기 굴착단계를 거친 후 상기 제1주보와 상기 제2주보 사이의 공간에 영구벽체인 구조물벽체를 시공할 수 있다.In the above, after the excavation step, it is possible to construct a structural wall which is a permanent wall in the space between the first bulletin and the second bulletin.

상기에 있어서, 상기 제1주보는 강널말뚝일 수 있다. 즉, 이 경우에 강널말뚝은 제1주보로서 기능하는 동시에 지중연속벽으로 기능하게 된다.In the above, the first bullet may be a steel sheet pile. That is, in this case, the steel sheet pile serves as the first bulletin and also functions as a continuous underground wall.

먼저 본 발명의 설명 이전에 본 발명에서 강화하고자 하는 단면의 2차 모멘트(area moment of inertia)에 대하여 먼저 설명한다.First, the second moment (area moment of inertia) of the cross section to be strengthened in the present invention before the description of the present invention will be described first.

흙막이에서 주보(post)는 지지하는 지반으로부터 측방의 힘을 받고 이는 주보에게 굽힘응력을 일으키는 요인이 된다.In the retaining wall, the post receives lateral force from the supporting ground, which causes bending stress on the beam.

주보가 받게 되는 굽힘응력은 단면의 2차 모멘트에 반비례하며, 단면의 2차 모멘트는 중심축으로부터의 거리를 제곱한 값을 단위면적에 대하여 적분한 값이다.The bending stress received by the main beam is inversely proportional to the secondary moment of the cross section, and the secondary moment of the cross section is the integral of the unit area with the squared distance from the central axis.

따라서 주보의 단면 2차 모멘트가 클수록 동일 중량의 주보가 지지할 수 있는 힘은 커지게 된다.Therefore, the larger the cross-section secondary moment of the beam, the larger the force that can be supported by the same weight of the beam.

통상적으로 주보(Post)로서 사용되는 H-Beam의 형태 또한 이러한 단면 2차 모멘트를 향상시킬 수 있는 구조이다.The shape of H-Beam, which is usually used as a post, is also a structure capable of improving such cross section secondary moment.

그러나 본 발명에서 구현하고자 하는 형태는 두개의 주보(제1주보 및 제2주보)를 이격되게 마련한 후 그 주보이 제1보강재에 의하여 연결됨으로써 완성된 주보를 이루게 함으로써, 각 주보이 굽힘의 중심축으로부터의 거리가 훨씬 멀어지게 되어, 동일 면적을 가진 주보 2개가 연속되어 있는 것보다 훨씬 더 큰 단면 2차 모멘트를 가지게 되며, 따라서 동일한 중량에 의한 주보일 경우에도 보다 큰 지지력을 가질 수 있으므로 보다 깊이 흙막이를 시공할 수 있도록 하는 것이다.However, the form to be implemented in the present invention is to prepare the two bulletin (first bulletin and second bulletin) spaced apart by the main beam is connected by the first reinforcing material to achieve a completed bulletin, from the central axis of each main beam bending The distance is much greater, so that the two sections with the same area have a much larger cross-section secondary moment than they are contiguous. It is to allow construction.

이하 본 발명에 의한 제1실시례에 따라 그 구성과 작용을 상세히 설명한다.Hereinafter, the configuration and operation of the first embodiment according to the present invention will be described in detail.

도 1은 본 발명에 의한 일 실시례에 따라 주보설치단계를 거친 굴착지반의 평면도이며, 도 2a 내지 도 2h는 도 1의 굴착지반이 굴착되는 방법을 순서적으로 도시한 것이며, 도 3은 동일 깊이에 위치한 보강재용 굴착부를 굴착하고 제1보강재를 연결하는 방법을 순서적으로 도시한 것이며, 도 4a 내지 도 4c는 제1주보, 제2주보, 및 이들 사이에 연결되는 제1보강재의 여러가지 연결상태를 도시한 것이다.1 is a plan view of an excavation ground that went through the main installation step according to an embodiment of the present invention, Figures 2a to 2h is a view showing a method of excavating the excavation ground of Figure 1 in sequence, Figure 3 is the same Figure 1a to 4c shows a method of excavating the excavation for the reinforcing reinforcement located in depth and connecting the first reinforcement in order, the first reinforcement, the second reinforcement, and the various connections of the first reinforcement connected between them The state is shown.

삭제delete

본 발명에 의한 흙막이를 시공하기 위하여 먼저, 굴착예정면의 가장자리를 따라 다수의 제1주보(120)를 설치하고 상기 제1주보의 내측에 다수의 제2주보를 설치한다.(S10 ; 주보설치단계) 상기 재1주보(120)와 또다른 제1주보(120) 사이에는 지중연속벽(110)을 형성한다.In order to construct the earthenware according to the present invention, first, a plurality of first bulletin 120 is installed along the edge of the excavation prospecting surface and a plurality of second bulletin is installed inside the first bulletin. Step) The continuous continuous wall 110 is formed between the first bulletin 120 and the other first bulletin 120.

상기 지중연속벽(110)은 굴착예정면의 가장자리를 따라 지반에 설치되는 것으로, 지중연속벽(110)으로는 대표적으로 주열식 지중연속벽 혹은 벽식 지중연속벽 공법이 일반적으로 알려져 있다. 그러나 경우에 따라서는 콘크리트말뚝뿐만이 아니라 강널말뚝 등으로도 사용될 수 있다.The underground continuous wall 110 is installed on the ground along the edge of the excavation prospective surface, the underground continuous wall 110 is typically known as the main column type continuous wall or wall continuous wall method. However, in some cases, it can be used not only for concrete piles but also for steel sheet piles.

즉 지중에 미리 연속적으로 시공되어 벽으로서 기능한다면 본 발명의 지중연속벽으로 해석될 수 있다.In other words, it can be interpreted as the underground continuous wall of the present invention if it is continuously constructed in advance and functions as a wall.

제1주보(120)들은 지중연속벽(110)을 따라 마련되며, 즉 굴착예정면의 가장자리를 따라 마련되며, 서로간에 간격을 가지도록 지반에 타입된다. 본 실시례에서는 지중연속벽(110)이 주열식 지중연속벽으로 이루어지며, 또한 제1주보(120)들은 지중연속벽(110) 내부에 타입되는 것으로 상정하였다. 그러나 이는 실시례에 따라 변경될 수 있는 것으로서, 제1주보(120)들은 직접적으로 지중연속벽(110)을 지지할 수 있는 구조를 갖추고, 굴착단계 이전에 미리 지중에 마련되는 것으로 충분하다.The first bulletin 120 is provided along the underground continuous wall 110, that is, is provided along the edge of the excavation prospective surface, and is typed on the ground to have a gap therebetween. In the present embodiment, it is assumed that the underground continuous wall 110 is composed of a main row type underground continuous wall, and the first bulletin 120 is typed in the underground continuous wall 110. However, this can be changed according to the embodiment, the first bulletin 120 has a structure that can directly support the underground continuous wall 110, it is sufficient to be provided in the ground before the excavation step.

제2주보(130)들은 제1주보(120)들의 내측, 즉 제1주보(120)로부터 굴착예정면을 향하여 이격되게 마련되며, 또한 제2주보(130)들은 서로 일정한 간격을 가지도록 지반에 타입된다.The second bulletin 130 is provided to be spaced apart from the inside of the first bulletin 120, that is, toward the excavation prospective surface from the first bulletin 120, and the second bulletin 130 is on the ground to have a predetermined distance from each other Type.

이렇게 하여 도 1과 같은 주보설치단계가 완료된 흙막이의 평면상태가 시공된다.In this way, the flat state of the earthquake block is completed as shown in FIG.

이때 굴착예정면은 제2주보(130)들에 의하여 둘러싸인 본굴착부(210)와 제2주보(130)들과 제1주보(120)들에 의하여 둘러싸인 보강재용 굴착부(220)로 구분하여 생각될 수 있다. At this time, the excavation expected surface is divided into the main excavation portion 210 surrounded by the second bulletin 130 and the excavation portion 220 for the reinforcement surrounded by the second bulletin 130 and the first bulletin 120 It can be thought of.

삭제delete

주보설치단계를 거친 후 굴착부지의 굴착예정면을 굴착하게 된다.After the main installation step, the excavation expected surface of the excavation site will be excavated.

이때 굴착단계는 도 2a 내지 도 2h로 설명될 수 있다.In this case, the excavation step may be described with reference to FIGS. 2A to 2H.

먼저 도 2a에 도시된 바와 같이 본굴착부(210)와 보강재용 굴착부(220)를 소정의 깊이로 굴착한 후 제1주보(120)와 제2주보(130)를 연결하도록 제1보강재(310-1)를 설치한다.First, as shown in FIG. 2A, the main excavation part 210 and the reinforcing material excavation part 220 are excavated to a predetermined depth, and then the first reinforcing material ( 310-1).

동일한 깊이에 마련되는 제1보강재(310)의 설치방법은 도 3a ~ 도 3f에 의하여 보다 상세히 설명될 수 있다.The installation method of the first reinforcing material 310 provided at the same depth may be described in more detail with reference to FIGS. 3A to 3F.

도 3a에서 도시된 바와 같이 1,4,7 구간을 먼저 굴착한 후, 도 3b에 도시된 바와 같이 1,4,7 구간에 제1보강재(310)를 설치하며, 이후 도 3c에 도시된 바와 같이 2,5구간을 굴착한 후, 도 3d에 도시된 바와 같이 2, 5 구간에 제1보강재(310)를 설치하며, 이후 도 3e에 도시된 바와 같이 3,6구간을 굴착한 후 도 3f에 도시된 바와 같이 3,6구간에 제1보강재(310)를 설치한다.
즉, 제1주보(120)와 제2주보(130)의 사이인 보강재용 굴착부(220)를 굴착하면서 상기 제1주보(120)와 제2주보(130)가 연결되도록 보강재(310)를 설치한다(S20 ; 보강재용 굴착부 굴착 및 보강재 연결단계)
As shown in FIG. 3A, the first, fourth, and seventh sections are first excavated, and then, as shown in FIG. 3B, the first reinforcement 310 is installed in the first, fourth, and seventh sections, and as shown in FIG. 3C. After excavating sections 2 and 5, the first reinforcing material 310 is installed in sections 2 and 5, as shown in FIG. 3D, and after excavating sections 3 and 6, as shown in FIG. 3E, FIG. 3F. As shown in the first reinforcing material 310 is installed in sections 3 and 6.
That is, while reinforcing the excavation portion 220 for the reinforcing material between the first bulletin 120 and the second bulletin 130, the reinforcing material 310 to connect the first bulletin 120 and the second bulletin 130 Install (S20; excavation section for the reinforcement and connecting the reinforcement)

이와 같이 부분적으로 굴착한 후 부분적으로 제1보강재를 설치하는 것은 동시에 모든 부분을 굴착한 후 다음으로 제1보강재를 설치하는 것에 비하여, 점진적으로 제1주보(120)와 제2주보(130)에 의한 단면 2차 모멘트가 향상되면서 굴착이 진행되므로 지반이 붕괴될 수 있는 위험을 차단하는 것이다.As described above, the first reinforcement is partially installed after the excavation, and the first reinforcement is gradually installed in the first bulletin 120 and the second bulletin 130, compared to the installation of the first reinforcement after the excavation of all the portions at the same time. The excavation proceeds as the secondary moment of the cross section is improved, thereby preventing the ground from collapsing.

이와 같이 동일한 깊이에 마련되는 제1보강재(310)의 설치방법은 다른 깊이 에 마련되는 제1보강재(310)의 설치 방법에 그대로 적용될 수 있다.As such, the installation method of the first reinforcement 310 provided at the same depth may be applied to the installation method of the first reinforcement 310 provided at different depths.

또한 제1보강재(310)를 제1주보(120)와 제2주보(130) 사이에 설치하는 방법으로서는 볼팅 또는 용접이 적용될 수 있다.In addition, as a method of installing the first reinforcing material 310 between the first bulletin 120 and the second bulletin 130, bolting or welding may be applied.

도 4a 내지 도 4c는 여러 형태의 제1주보(120)와 제2주보(130) 사이에 설치되는 여러 가지 형태의 제1보강재(310)를 도시한 것으로서 볼팅에 의하여 제1주보(120)와 제2주보(130)에 연결되는 상태를 도시한 것이다.4A to 4C illustrate various forms of the first reinforcement material 310 installed between the first and second bulletin 120 and the second and second bulletin 130. As shown in FIG. The state connected to the second bulletin 130 is shown.

특히 도 4b 및 도 4c는 제1주보(120)와 제2주보(130)로 H-Beam으로 이용하고 있는 것이다.In particular, FIGS. 4B and 4C are used for the first bullet 120 and the second bullet 130 as H-Beam.

상기와 같이 도 2a상태로 시공한 후, 도 2b와 같이 보강재용 굴착부(220)를 굴착한 후 그 굴착된 공간에 제1보강재(310-2)를 시공한다. 이러한 보강재용 굴착부(220)의 굴착과 제1보강재(310-2)의 시공은 도 3a 내지 도 3f의 시공 방법이 그대로 적용될 수 있다.After the construction in the state of FIG. 2A as described above, the excavating portion 220 for the reinforcing material is excavated as shown in FIG. 2B and then the first reinforcing material 310-2 is constructed in the excavated space. Excavation of the excavation portion 220 for the reinforcing material and the construction of the first reinforcing material 310-2 may be applied as it is the construction method of Figures 3a to 3f.

도 2b와 같이 제1보강재(310-2)가 제1주보(120)와 제2주보(130) 사이에 연결되면, 도 2c와 같이 상기 제2주보(130)와 서로 대항되어지는 또다른 제2주보(130) 사이인 본굴착부(210)를 일정 깊이까지 굴착한다.(S30 ; 본굴착부 굴착단계)When the first reinforcing material 310-2 is connected between the first bulletin 120 and the second bulletin 130, as shown in FIG. 2B, another second material opposed to the second bulletin 130 as shown in FIG. 2C. Excavation of the main excavation portion 210 between the two jumbo 130 to a certain depth. (S30; main excavation excavation step)

이후 도 2d 및 도 2e와 같이 보강재용 굴착부(220)를 굴착하고 제1보강재(310-3)를 연결하는 보강재용 굴착단계와, 본굴착부(210)를 굴착하는 본굴착 단계가 반복된다.Then, as shown in FIGS. 2d and 2e, the excavation step 220 for excavating the reinforcing material and connecting the first reinforcing material 310-3 and the main excavation step for excavating the main excavation part 210 are repeated. .

이후 도 2f 및 도 2g와 같이 보강재용 굴착부(220)를 굴착하고 제1보강재(310)를 연결하는 보강재용 굴착단계(S20)와, 본굴착부 굴착단계(S30)가 2회이상반복된다.(S40 ; 굴착반복단계) Then, as shown in FIGS. 2F and 2G, the reinforcing material excavation part 220 is excavated and the first reinforcing material excavation step S20 for connecting the first reinforcing material 310 and the main excavation part excavation step S30 are repeated two or more times. (S40; Excavation Repeat Step)

이러한 단계가 반복된 후, 보강재용 굴착부(220)는 도 2h와 같이 되메움되어, 최하단의 제1보강재(310-4)는 지반에 매립되어 전체적인 주보의 지지력을 더욱 향상시킨다.After this step is repeated, the reinforcing material excavation portion 220 is backfilled as shown in Figure 2h, the bottom of the first reinforcing material 310-4 is embedded in the ground to further improve the overall support capacity.

이와 같이 흙막이를 시공하면 제1주보(120) 및 제2주보(130)가 단독적으로 혹은 단순 연결하여 사용하는 것보다, 제1주보(120)와 제2주보(130)가 제1보강재(310)에 의하여 서로 연결되어 그 굽힘중심축으로부터의 거리가 증가하게 됨으로써 제1주보, 제2주보, 및 제1보강재로 이루어지는 주보의 단면 2차 모멘트가 상승하게 되며, 또한 제1보강재(310)가 그 굴착 깊이의 증가에 따라 단계적으로 설치됨으로써 굴착 깊이에 따라 주보가 필요한 지지력을 충분히 가질 수 있다.In this way, when constructing the retainer, the first bulletin 120 and the second bulletin 130 are the first reinforcing materials 310 rather than using the first bulletin 120 and the second bulletin 130 alone or simply connected. The second moment of cross section of the first beam, the second beam, and the first reinforcement is increased, and the first reinforcement 310 is increased. Step by step installation in accordance with the increase in the excavation depth can be enough to have the necessary supporting force according to the excavation depth.

따라서 이러한 시공방법에 의하여 매우 깊은 굴착부를 가지는 흙막이를 매우 적은 중량의 주보 및 제1보강재에 의하여 구현할 수 있다.Therefore, by this construction method it can be implemented by a very small weight of the main beam and the first reinforcement having a very deep excavation.

이하 본 발명에 의한 제2실시례에 따라 그 구성과 작용을 상세히 설명한다.Hereinafter, the configuration and operation according to the second embodiment of the present invention will be described in detail.

도 1은 본 발명에 의한 일 실시례에 따라 주보설치단계를 거친 굴착지반의 평면도이며, 도 5a 내지 도 5e는 도 1의 굴착지반이 굴착되는 방법을 순서적으로 도시한 것이다.1 is a plan view of an excavation ground that has undergone a bulletin installation step according to an exemplary embodiment of the present invention, and FIGS. 5A to 5E sequentially illustrate a method of excavating the excavating ground of FIG. 1.

삭제delete

삭제delete

주보설치단계(S10)를 제1실시예와 동일하게 거친 후 굴착부지의 굴착예정면을 굴착하게 된다.After the main installation step (S10) in the same manner as in the first embodiment is to excavate the excavation of the excavation site.

이때 굴착단계는 도 5a 내지 도 5e로 설명될 수 있다.In this case, the excavation step may be described with reference to FIGS. 5A to 5E.

먼저 도 5a에 도시된 바와 같이 본굴착부(210)와 보강재용 굴착부(220)를 소정의 깊이로 굴착한 후 제1주보(120)와 제2주보(130)를 연결하도록 제1보강재(310-1)를 설치한다.First, as shown in FIG. 5A, the main excavation part 210 and the reinforcing material excavation part 220 are excavated to a predetermined depth, and then the first reinforcing material ( 310-1).

동일한 깊이에 마련되는 제1보강재(310-1)의 설치방법은 도 3a ~ 도 3f에 의한 과정이 그대로 적용될 수 있을 것이다.In the installation method of the first reinforcing material 310-1 provided at the same depth, the process of FIGS. 3A to 3F may be applied as it is.

상기와 같이 도 5a상태로 시공한 후, 도 5b와 같이 보강재용 굴착부(220)와 본굴착부(210)를 굴착한 후, 보강재용 굴착부(220)에는 제1보강재(310-2)를 시공하며, 본굴착부(210)에는 버팀대(410-1)를 시공한다. 제1보강재(310-2)의 시공방법은 앞서 설명한 것과 동일하며, 버팀대(410)는 본굴착된 지반의 하부에 굴착면을 가로지르면서 제2주보(130) 사이가 서로 버티어지도록 설치한다.After the construction in the state of FIG. 5A as described above, after excavating the excavation portion 220 and the main excavation portion 210 for the reinforcement, as shown in FIG. 5B, the first reinforcement 310-2 to the excavation portion 220 for the reinforcement To construct, the main excavation 210 is constructed with a brace 410-1. The construction method of the first reinforcing material (310-2) is the same as described above, the support 410 is installed so that the second jujube 130 endure each other while crossing the excavation surface on the bottom of the main excavated ground.

또한 도 5b와 같은 시공 또한 본굴착 단계와, 보강재용 굴착단계가 이루어짐을 확인할 수 있다. 다만 이때 굴착 자체는 본굴착부(210)와 보강재용 굴착부(220)의 구분없이 전체적으로 굴착될 수 있지만, 최종적으로는 보강재용 굴착부(220)에 제1보강재(310-2)를 설치하게 되어, 결과적으로는 보강재용 굴착단계가 이루어진다는 것을 확인할 수 있다.In addition, the construction as shown in Figure 5b can also be seen that the excavation step, the excavation step for the reinforcement is made. However, at this time, the excavation itself may be excavated as a whole without distinguishing the main excavation portion 210 and the reinforcement excavation portion 220, but finally install the first reinforcement 310-2 in the excavation portion 220 for the reinforcement. As a result, it can be confirmed that the excavation step for the reinforcement is made.

이때 버팀대(410-1)는 본 흙막이의 시공에 있어서, 굴착되는 지반의 최하부가 가장 취약하다는 점을 감안하여, 굴착된 지반의 하부에 더욱 큰 지지력을 부여하기 위한 것이다.At this time, the brace 410-1 is to give a greater support force to the lower portion of the excavated ground in view of the fact that the bottom of the ground to be excavated is the most vulnerable in the construction of the earth retaining.

도 5b와 같이 제1보강재(310-2)가 제1주보(120)와 제2주보(130) 사이에 연결되며 또한 버팀대(410)가 제2주보(130) 사이에 연결되면, 도 5c와 같이 도 5b의 작 업을 반복한다.When the first reinforcing material 310-2 is connected between the first bulletin 120 and the second bulletin 130, and the brace 410 is connected between the second bulletin 130, as shown in FIG. Repeat the operation of Figure 5b.

즉, 본굴착부(210)와 보강재용 굴착부(220)가 굴착되며, 또한 보강재용 굴착부(220)에는 제1보강재(310-3)가 추가로 설치되며, 본굴착부(210)에는 버팀대(410-2)가 추가로 설치된다.That is, the main excavation portion 210 and the excavation portion 220 for the reinforcement are excavated, and the first reinforcement 310-3 is additionally installed in the excavation portion 220 for the reinforcement and the main excavation portion 210. A brace 410-2 is additionally installed.

도 5c와 같이 제1보강재(310-3)가 제1주보(120)와 제2주보(130) 사이에 연결되며 또한 버팀대(410-2)가 본굴착부(210)의 제2주보(130) 사이에 설치되면, 도 5d와 같이 도 5c의 작업을 반복한다.As shown in FIG. 5C, the first reinforcement 310-3 is connected between the first bulletin 120 and the second bulletin 130, and the brace 410-2 is the second bullet 130 of the main excavation portion 210. If installed between), the operation of FIG. 5C is repeated as shown in FIG. 5D.

이때 본굴착부(210)와 보강재용 굴착부(220)의 굴착과, 제1보강재(310-4)의 추가 작업은 종전과 동일하지만, 버팀대(410)의 설치는 종전에 이미 설치되어 지반의 굴착에 따라 지반의 중간부에 위치하게 되는 버팀대(410-1)을 이용한다.At this time, the excavation of the main excavation portion 210 and the reinforcement excavation portion 220, and the additional work of the first reinforcing material 310-4 is the same as before, but the installation of the brace 410 is already installed before As the excavation uses a brace 410-1 which is located in the middle of the ground.

즉 굴착 지반의 중간부에 위치하게 되는 버팀대(410-1)을 해체하고, 이 해체된 버팀대(410-1)를 굴착된 지반의 최하부에 다시 설치하는 것으로 한다.That is, it is assumed that the prop 410-1 located at the middle of the excavated ground is dismantled, and the disassembled prop 410-1 is installed again at the bottom of the excavated ground.

굴착 지반의 중간부에 위치하게 되는 버팀대(410-1)는, 이미 제1주보(120)와 제2주보(130) 사이에 마련되는 제1보강재(310)에 의하여 그 단면 2차 모멘트가 증가하여 충분한 지지력을 발휘하므로, 재료의 절감 및 후속 공정 등을 위하여 철거하는 것이다.The brace 410-1 positioned at the middle of the excavation ground has a second moment of cross section increased by the first reinforcing material 310 provided between the first bullet 120 and the second bullet 130. It is to be demolished for the reduction of materials and subsequent processes, so as to demonstrate sufficient bearing capacity.

도 5d와 같이 제1보강재(310-4)가 제1주보(120)와 제2주보(130) 사이에 연결되며 또한 버팀대(410-1)가 제2주보(130) 사이에 연결되면, 도 5e와 같이 도 5d의 작업을 반복한다.When the first reinforcing material 310-4 is connected between the first bulletin 120 and the second bulletin 130 as shown in FIG. 5D and the brace 410-1 is connected between the second bulletin 130, FIG. The operation of FIG. 5D is repeated as in 5e.

이 공정 또한 본굴착부(210)와 보강재용 굴착부(220)의 굴착과, 제1보강재(310-5)의 추가 작업은 종전과 동일하며, 버팀대(410-2)의 설치는 도 5d의 버팀대(410-1)의 해체 및 설치와 마찬가지로, 본 굴착의 진행에 따라 지반의 중간부에 위치하게 되는 버팀대(410-2)을 이용한다.This process is also the excavation of the main excavation portion 210 and the reinforcement excavation portion 220, and the additional work of the first reinforcing material 310-5 is the same as before, the installation of the brace 410-2 is shown in FIG. As with the disassembly and installation of the brace 410-1, the brace 410-2 which is located in the middle of the ground according to the progress of the excavation is used.

즉 굴착 지반의 중간부에 위치하게 되는 버팀대(410-2)를 해체하고, 이 해체된 버팀대(410-2)를 굴착된 지반의 최하부에 다시 설치하는 것으로 한다.
상기와 같이 본굴착부(210)에 버팀대(410)를 설치함으로써 매우 깊은 깊이를 가지는 흙막이를 매우 용이하게 시공할 수 있다.
That is, it is assumed that the brace 410-2 positioned at the middle of the excavated ground is dismantled, and the disassembled brace 410-2 is installed again at the bottom of the excavated ground.
By installing the brace 410 in the main excavation portion 210 as described above, it is possible to easily construct a soil barrier having a very deep depth.

삭제delete

도 6은 본 발명의 실시례에 따라 시공된 흙막이의 여러가지 종단면도로서, 제1주보(120)과 제2주보(130) 사이에 설치되는 제1보강재(310)의 여러가지 형태들을 그 종단면상에서 도시한 것이다.6 is various longitudinal cross-sectional views of the soil barrier constructed in accordance with an embodiment of the present invention, showing the various forms of the first reinforcing material 310 installed between the first bullet 120 and the second bullet 130 on the longitudinal cross-section It is.

제1보강재(310)는 수평보로서 설치될 수 있을 뿐만 아니라, 경사보로서 설치되어 트러스형 구조를 이룰 수도 있다.The first reinforcement 310 may not only be installed as a horizontal beam, but may also be installed as a slanted beam to form a truss structure.

도 7은 본 발명의 실시례에 따라 시공된 흙막이의 종단면도로서, 제1주보(120) 및 제2주보(130)의 근입부의 강성을 증가시키기 위하여 제1주보(120) 및 제2주보(130)의 하부지반(A)이 개량된 것을 도시한 것이다.7 is a longitudinal cross-sectional view of the soil barrier constructed in accordance with an embodiment of the present invention, the first bulletin 120 and the second bulletin (in order to increase the stiffness of the inlet of the first bulletin 120 and the second bulletin 130 ( It shows that the lower ground (A) of 130 is improved.

이와 같은 하부지반(A)의 개량은 주보설치단계에서 미리 시공된 것이다.The improvement of the lower ground (A) is constructed in advance in the main installation step.

도 8은 본 발명의 다른 실시례에 따라 시공된 흙막이의 평면도 및 종단면도 이다.8 is a plan view and a longitudinal cross-sectional view of a retainer constructed in accordance with another embodiment of the present invention.

본 실시례에서는 주보설치단계(S10)에서 상기 제1주보(120)의 외측에 다수의 제1보조주보(120a)를 설치하는 것으로, 상기 실시례에서는 제1주보(120)간에는 지중연속벽(110)이 형성될 뿐만 아니라 상기 지중연속벽(110)으로부터 굴착배면을 향하여 이격되게 보조지중연속벽(110a)를 형성하여 실질적으로 2중의 다중연속벽을 형성하며, 또한 보조지중연속벽(110a)을 따라 복수의 제1보조주보(120a)가 서로 간격을 가지도록 마련된다. In the present embodiment, a plurality of first auxiliary bullets 120a are installed on the outside of the first bulletin 120 in the main bulletin installation step (S10), and in the embodiment, a continuous continuous wall (between the first bulletin 120) Not only 110 is formed, but also the secondary continuous wall 110a is formed to be spaced apart from the underground continuous wall 110 toward the excavation rear surface to form a substantially double multi-continuous wall, and also the secondary continuous wall 110a Accordingly, the plurality of first auxiliary bullets 120a are provided to be spaced apart from each other.

이와 같이 주보설치단계에서 지중연속벽(110), 보조지중연속벽(110a), 제1주보(120), 제1보조주보(120a), 제2주보(130)가 미리 지중에 마련된 후 앞서와 동일한 공정으로 굴착예정면을 굴착할 수 있다.As described above, the underground continuous wall 110, the secondary continuous wall 110a, the first bulletin 120, the first auxiliary bulletin 120a, and the second bulletin 130 are prepared in the ground in the main bulletin installation step. Excavation expected surface can be excavated by the same process.

또한 굴착전 혹은 굴착을 시작하면서 제1주보(120)와 제1보조주보(120a)의 상부를 연결하는 제2보강재(320)가 설치된다.In addition, a second reinforcing material 320 for connecting the upper portion of the first auxiliary line 120 and the first auxiliary line 120a before the excavation or starting excavation is installed.

한편, 제2보강재(320)는 제1주보(120)와 제1보조주보(120a)와 제2주보(130)의 상부를 모두 연결하도록 마련될 수도 있을 것이다.On the other hand, the second reinforcing material 320 may be provided to connect both the first bulletin 120, the first auxiliary bulletin 120a and the second bulletin 130.

이러한 구조는 지중연속벽(110)과 보조지중연속벽(110a) 사이의 지반이 중력식 옹벽으로 작용하는 소일 탱크(Soil Tank)의 구조를 가지게 되어 흙막이 벽의 강성을 더욱 높일 수 있다.This structure has a structure of a soil tank in which the ground between the underground continuous wall 110 and the auxiliary underground continuous wall 110a acts as a gravity retaining wall, thereby further increasing the rigidity of the retaining wall.

도 9는 본 발명의 다른 실시례에 따라 시공된 흙막이의 평면도 및 종단면도이다.9 is a plan view and a longitudinal cross-sectional view of a retainer constructed in accordance with another embodiment of the present invention.

도 9에서는 도 8과 달리 보조지중연속벽(110a)을 형성하지 않은 상태로 제1보조주보(120a)를 사용한 점만이 도 8과 상이할 뿐이다.In FIG. 9, unlike FIG. 8, only the point of using the first auxiliary bullet 120a without the auxiliary underground continuous wall 110a is different from FIG. 8.

이와 같이 제1보조주보(120a)만을 이용하는 경우에도 전도에 대한 저항력을 상당히 높일 수 있을 것이라 예상된다.As such, even when only the first auxiliary bullet 120a is used, it is expected that the resistance to conduction can be considerably increased.

한편, 앞서 설명들은 주보설치단계에서 지중연속벽(110)이 미리 형성된다는 전제하에 설명하였다.On the other hand, the above description has been described under the premise that the underground continuous wall 110 is formed in advance in the installation step.

그러나 일반적인 흙막이 시공의 경우 지중연속벽은 물론이며, 엄지말뚝 사이에 연결되는 흙막이판(혹은 토류판이라고도 함.)을 이용하는 사례가 매우 흔하다.However, in the case of general earthquake construction, as well as underground continuous wall, it is very common to use the earthquake plate (or earth plate) connected between the thumb piles.

따라서 본 발명에도 흙막이판을 이용하여 흙막이를 시공하는 방법이 매우 용이하게 적용될 수 있다.Therefore, the method of constructing the earthen board using the earthen board can also be very easily applied to the present invention.

다만 흙막이판은 지중연속벽과는 달리 본 발명의 주보설치단계에서는 설치될 수 없으며, 본 발명의 굴착단계에서 시공될 수 있다. 보다 엄밀히는 본 발명의 보강재용 굴착단계가 진행되는 정도에 따라 흙막이판도 점차적으로 설치될 수 있다. However, the earthen board may not be installed in the bulletin installation step of the present invention, unlike the underground continuous wall, it may be constructed in the excavation step of the present invention. More strictly according to the degree of progress of the excavation step for the reinforcement of the present invention can also be installed gradually.

도 10 내지 도 11은 도 8 내지 도 9에 대응하면서 또한 도 8 내지 도 9의 지중연속벽 대신 흙막이판을 채택한 실시례의 평면도 및 종단면도이다.10 to 11 are plan and longitudinal cross-sectional views of an embodiment corresponding to FIGS. 8 to 9 and employing an earth retaining plate instead of the underground continuous wall of FIGS. 8 to 9.

도 10에서는 흙막이판(140)과 보조지중연속벽(110a) 사이의 지반이 중력식 옹벽으로 기능하는 소일 탱크(Soil Tank)의 구조를 가지게 되어 흙막이 벽의 강성을 더욱 높일 수 있다.In FIG. 10, the soil between the retaining plate 140 and the auxiliary underground continuous wall 110a has a structure of a soil tank that functions as a gravity retaining wall, thereby further increasing the rigidity of the retaining wall.

도 11에서는 제1보조주보(120a)만을 이용하는 경우에도 전도에 대한 저항력을 상당히 높일 수 있을 것이라 예상된다.In FIG. 11, even when only the first auxiliary bullet 120a is used, the resistance to conduction can be considerably increased.

이와 같이 흙막이판(140)을 이용하여 흙막이를 시공하는 여러가지 사례들을 설명한다. 물론 이하의 여러가지 사례들은 지중연속벽을 적용하는 경우에도 대부분 그대로 적용될 수 있는 것이다.As described above, various examples of constructing a retainer using the retainer plate 140 will be described. Of course, the following examples can be applied to most cases even when applying the continuous wall.

도 12a 내지 도 12f는 지하구조물 설치시에 본 발명을 실시하는 사례이다.12A to 12F are examples of implementing the present invention when installing underground structures.

도 12a와 같이, 제1주보(120) 및 제2주보(130)을 설치한 후 본굴착부(210)를 굴착하고 또한 보강재용 굴착부(220)를 굴착하여, 제1주보(120)와 제2주보(130) 사이에는 제1보강재(310)을, 제2주보(130) 사이에는 버팀대(410)를 설치한다. 이때 최상부의 상기 버팀대(410)는 도 12a와 같이 트러스구조물로 할 수도 있다. 이때 제1주보(120)를 따라 흙막이판(미도시)이 시공된다.As shown in FIG. 12A, after the first bulletin 120 and the second bulletin 130 are installed, the main excavation portion 210 is excavated and the excavation portion 220 for the reinforcing material is excavated. The first reinforcing material 310 is installed between the second jumbo 130, and the brace 410 is installed between the second jumbo 130. At this time, the upper brace 410 may be a truss structure as shown in Figure 12a. At this time, a retaining plate (not shown) is constructed along the first bulletin 120.

도 12a 공정 후 도 12b와 같이 본굴착부(210) 및 보강재용 굴착부(220)를 추가 굴착하고, 본굴착부(210)에는 버팀대(410)를 설치하며, 보강재용 굴착부(220)에는 제1보강재(310)와 흙막이판(미도시)이 시공된다. After the process of FIG. 12A, the main excavation portion 210 and the excavation portion 220 for the reinforcement are further excavated as shown in FIG. 12B, and the prop excavation portion 210 is provided with the support 410 and the excavation portion 220 for the reinforcement. The first reinforcement 310 and the earth plate (not shown) is constructed.

도 12b 공정 후 도 12c와 같이 추가 굴착한 후, 굴착된 부위에 제1보강재(310)와 흙막이판(미도시)을 시공하며, 또한 하부에 측방변위 억제용 콘크리트(501)를 타설한다.After further drilling as shown in FIG. 12c after FIG. 12b process, the first reinforcement 310 and the earthen board (not shown) are constructed on the excavated portion, and further, the lateral displacement inhibiting concrete 501 is poured.

도 12c 공정 후 도 12d와 같이 제1주보(120)와 제2주보(130) 사이에 구조물 벽체(502)를 시공한 후 하부구조물(503)을 설치한다.After the process of FIG. 12C, the substructure 503 is installed after constructing the structure wall 502 between the first bulletin 120 and the second bulletin 130 as shown in FIG. 12D.

도 12d 이후 도 12e와 같이 버팀대(410)를 해체하며, 이후 도 12f와 같이 상부 구조물(504)를 설치한 후 최상부의 버팀대(410)를 해체하고 되메움한다.12D and after disassembling the brace 410 as shown in FIG. 12E, and after installing the upper structure 504, as shown in Figure 12f dismantle and backfill the top brace 410.

도 13a 내지 도 13e는 지하구조물 설치시에 본 발명을 이용한 다른 사례이 다.13a to 13e is another example of using the present invention when installing the underground structure.

도 13a와 같이, 제1주보(120) 및 제2주보(130)을 설치한 후 본굴착부(210)를 굴착하고 또한 보강재용 굴착부(220)를 굴착하여, 제1주보(120)와 제2주보(130) 사이에는 제1보강재(310)을, 제2주보(130) 사이에는 트러스(또는 박스형) 지지대(420)를 설치한다. 이때 제1주보(120)를 따라 흙막이판(미도시)이 시공된다.As shown in FIG. 13A, after the first bulletin 120 and the second bulletin 130 are installed, the main excavation unit 210 is excavated, and the excavation unit 220 for the reinforcement is excavated, and the first bulletin 120 and the first bulletin 120 are installed. A first reinforcing material 310 is provided between the second bulletin 130, and a truss (or box-shaped) support 420 is installed between the second bulletin 130. At this time, a retaining plate (not shown) is constructed along the first bulletin 120.

도 13a 공정 후 도 13b와 같이 본굴착부(210) 및 보강재용 굴착부(220)를 추가 굴착하고, 본굴착부(210)에는 상부 슬라브(510-1)를 시공하며, 보강재용 굴착부(220)에는 제1보강재(310)와 흙막이판(미도시)이 시공된다. After the process of FIG. 13A, the main excavation portion 210 and the excavation portion 220 for the reinforcement are further excavated as shown in FIG. 13B. 220, the first reinforcing material 310 and the earth plate (not shown) is constructed.

도 13b 공정 후 도 13c와 같이 본굴착부(210) 및 보강재용 굴착부(220)를 추가 굴착하고, 본굴착부(210)에는 중간 슬라브(510-2)를 시공하며, 보강재용 굴착부(220)에는 제1보강재(310)와 흙막이판(미도시)이 시공된다. After the process of FIG. 13B, the main excavation part 210 and the excavation part 220 for the reinforcement material are further excavated as shown in FIG. 13C, and the main excavation part 210 is constructed with an intermediate slab 510-2, and the excavation part for the reinforcement material ( 220, the first reinforcing material 310 and the earth plate (not shown) is constructed.

도 13c 공정 후 도 13d와 같이 본굴착부(210) 및 보강재용 굴착부(220)를 추가 굴착하고, 본굴착부(210)에는 최종 슬라브(510-3)를 시공하며, 보강재용 굴착부(220)에는 제1보강재(310)와 흙막이판(미도시)이 시공되며, 이후 제1주보(120)와 제2주보(130) 사이에 구조물 벽체(또는 영구벽체, 502)를 시공한다.After the process of FIG. 13C, the main excavation portion 210 and the excavation portion 220 for the reinforcement are further excavated as shown in FIG. 13D, and the final excavation portion 210 is constructed with the final slab 510-3, and the excavation portion for the reinforcement ( 220, the first reinforcing material 310 and the retaining plate (not shown) is constructed, and then a structure wall (or permanent wall, 502) is constructed between the first bulletin 120 and the second bulletin 130.

도 13d 이후 도 13e와 같이 상부의 버팀대(410)를 해체하고 되메움한다.After FIG. 13D, as shown in FIG. 13E, the upper brace 410 is dismantled and backfilled.

도 14a 내지 도 14e는 지하구조물 설치시에 본 발명을 이용한 다른 사례이다.14a to 14e is another example using the present invention when installing the underground structure.

도 14a와 같이, 제1주보(120) 및 제2주보(130)을 설치한 후 본굴착부(210)를 굴착하고 또한 보강재용 굴착부(220)를 굴착하여, 제1주보(120)와 제2주보(130) 사이에는 제1보강재(310)를 연결하고, 제2주보(130)오 대향되는 또다른 제2주보(130) 사이에 설치되는 버팀대(410)는 상기 도 14a에서와 같이 트러스구조물로 설치할 수도 있다. 이때 제1주보(120)를 따라 흙막이판(미도시)이 시공된다.As shown in FIG. 14A, after the first bulletin 120 and the second bulletin 130 are installed, the main excavation unit 210 is excavated and the excavation unit 220 for the reinforcing material is excavated, and the first bulletin 120 and the first bulletin 120 are installed. The first reinforcing material 310 is connected between the second bulletin 130, and the brace 410 installed between another second bulletin 130 opposite to the second bulletin 130 is as shown in FIG. 14A. It can also be installed as a truss structure. At this time, a retaining plate (not shown) is constructed along the first bulletin 120.

도 14a 공정 후 도 14b와 같이 본굴착부(210) 및 보강재용 굴착부(220)를 추가 굴착하고, 본굴착부(210)에는 상부 슬라브(510-1)를 시공하며, 보강재용 굴착부(220)에는 제1보강재(310)와 흙막이판(미도시)이 시공된다. After the process of FIG. 14A, the main excavation portion 210 and the excavation portion 220 for the reinforcement are further excavated as shown in FIG. 14B, and the main excavation portion 210 is constructed with the upper slab 510-1, and the excavation portion for the reinforcement ( 220, the first reinforcing material 310 and the earth plate (not shown) is constructed.

도 14b 공정 후 도 14c와 같이 본굴착부(210) 및 보강재용 굴착부(220)를 추가 굴착하고, 본굴착부(210)에는 중간 슬라브(510-2) 및 슬라브 상간 벽체(510-4)를 시공하며, 보강재용 굴착부(220)에는 제1보강재(310)와 흙막이판(미도시)이 시공된다. After the process of FIG. 14B, the main excavation part 210 and the excavation part 220 for the reinforcing material are further excavated as shown in FIG. 14C, and the main excavation part 210 includes the intermediate slab 510-2 and the slab inter-wall 510-4. The construction, the first reinforcement 310 and the earth plate (not shown) is installed in the excavation portion 220 for the reinforcement.

도 14c 공정 후 도 14d와 같이 본굴착부(210) 및 보강재용 굴착부(220)를 추가 굴착하고, 본굴착부(210)에는 최종 슬라브(510-3)를 시공하며, 보강재용 굴착부(220)에는 제1보강재(310)와 흙막이판(미도시)이 시공되며, 이후 제1주보(120)와 제2주보(130) 사이에 구조물 벽체(또는 영구벽체, 502)를 시공한다.After the process of FIG. 14C, the main excavation portion 210 and the excavation portion 220 for the reinforcement are further excavated as shown in FIG. 14D, and the final excavation portion 210 is constructed with the final slab 510-3, and the excavation portion for the reinforcement ( 220, the first reinforcing material 310 and the retaining plate (not shown) is constructed, and then a structure wall (or permanent wall, 502) is constructed between the first bulletin 120 and the second bulletin 130.

도 14d 이후 도 14e와 같이 상부의 버팀대(410)인 트러스구조물을 해체하고 되메움한다.After FIG. 14D, the truss structure, which is the upper brace 410 as shown in FIG. 14E, is dismantled and backfilled.

실시례에 따라서는 도 14e 대신에 도 14d 이후 도 14f로 진행하여, 상부의 버팀대(410)를 해체한 후 지상 구조물을 시공할 수도 있다.According to an embodiment, instead of FIG. 14E, the process proceeds to FIG. 14D and FIG. 14F, and then, after dismantling the upper brace 410, the ground structure may be constructed.

도 15a 내지 도 15d는 본 발명을 이용하는 다른 사례이다.15A to 15D are another example of using the present invention.

도 15a는, 제1주보(120) 및 제2주보(130)를 설치한 후 본굴착과 보강재용 굴착을 반복(제1보강재와 흙막이판의 시공도 함께 이루어짐)하여 도 15a와 같이 범(berm, 601)을 이용하여 자립 굴착을 이룬 상태의 종단면도 및 사시도이다.15a, after the first bulletin 120 and the second bulletin 130 is installed, the main excavation and the excavation for the reinforcement are repeated (the construction of the first reinforcement and the retaining plate is also carried out), and a berm as shown in FIG. , 601 is a longitudinal sectional view and a perspective view of the self-excavated excavation state.

이후 도 15b(종단면도 및 사시도)와 같이 제2주보(130)에 레이커(701)를 설치한다.
상기의 레이커(raker; 경사버팀대)는 본굴착부(210)의 제2주보(130) 하부 내측에 경사지게 설치되는 것으로 상기 제2주보를 직접 지지해주는 압축부재이다.
Thereafter, the raker 701 is installed in the second bulletin 130 as shown in FIG. 15B (a longitudinal section and a perspective view).
The raker (inclined brace) is a compression member that directly supports the second bullet to be installed inclined in the lower inside of the second bullet 130 of the main excavation portion (210).

다음으로 도 15c와 같이 범(berm, 601)을 제거하여 트렌치를 형성한다.Next, as shown in FIG. 15C, a berm 601 is removed to form a trench.

다음으로 도 15d와 같이 트렌치에 전단키(501a)를 타입하고 측방변위 억제용 콘크리트(501)를 타설하여 수평저항력을 확보한 후 레이커(701)를 해체한다. 즉 상기 굴착반복단계(S40)으 본굴착부 굴착단계(S30)에서 본굴착부(210)의 제2주보(130) 하부 내측에 상기 제2주보(130)가 버티어지도록 레이커(701)를 경사지게 설치 및 해체하는 레이커 설치 및 해체단계가 추가되어질 수도 있다.(S50 : 레이커 설치 및 해체단계)Next, as shown in FIG. 15D, the shear key 501a is typed into the trench, and the concrete 501 for lateral displacement is placed to secure horizontal resistance, and then the raker 701 is dismantled. That is, in the excavation repeating step (S40), the inclined excavation unit (S30) to incline the raker 701 so that the second bulletin 130 is held on the lower inner side of the second bulletin 130 of the main excavation unit 210. Raker installation and dismantling step to install and dismantle may be added (S50: Raker installation and dismantling step).

이에 의하여 전단키(501a)가 부착된 역 L형 부벽식 옹벽의 구조가 형성될 수 있다. 물론 실시례에 따라서는 전단키(501a)를 생략할 수도 있다.Thereby, the structure of the inverted L-shaped subwall retaining wall to which the shear key 501a is attached can be formed. Of course, in some embodiments, the shear key 501a may be omitted.

도 16a 내지 도 16f는 본 발명을 이용하는 다른 사례이다.16A-16F are another example of using the present invention.

도 16a는, 제1주보(120) 및 제2주보(130)를 설치한 후 본굴착과 보강재용 굴착을 반복(제1보강재와 흙막이판의 시공도 함께 이루어짐)한 상태이다.FIG. 16a shows a state in which the main excavation and the excavation for reinforcement are repeated after the first bulletin 120 and the second bulletin 130 are installed (along with the construction of the first reinforcement and the retaining plate).

이후 도 16b와 같이 트렌치를 굴착한 후 제2주보(130)에 1단 레이커(701-1)를 설치한다.Then, after digging the trench as shown in FIG. 16B, the first stage raker 701-1 is installed in the second bulletin 130.

다음으로 도 16c와 같이 트렌치를 추가 굴착한 후 제2주보(130)에 2단 레이커(701-2)를 설치한다.Next, after the trench is additionally excavated as shown in FIG. 16C, a second stage raker 701-2 is installed in the second bulletin 130.

다음으로 도 16d와 같이 트렌치를 추가 굴착한 후 트렌치에 측방변위 억제용 콘크리트(501)를 타설한다.Next, after the trench is additionally excavated as shown in FIG. 16d, the lateral displacement inhibiting concrete 501 is poured into the trench.

다음으로 도 16e와 같이 보강재용 굴착부(220)의 공간인 제1주보(120)와 제2주보(130) 사이에 콘크리트(501)를 타설하여 구조물 벽체(502)를 형성하는 구조물 벽체 형성단계를 포함할 수도 있다.Next, as shown in FIG. 16e, the structure wall forming step of forming the structure wall 502 by pouring concrete 501 between the first bullet 120 and the second bullet 130, which is a space of the excavation portion 220 for the reinforcement, is formed. It may also include.

다음으로 도 16f와 같이 굴착을 마무리하고 마지막으로 포장(801)을 한다.Next, the excavation is finished as shown in FIG. 16F, and finally, the packing 801 is performed.

도 17a 내지 도 17e는 본 발명을 이용하는 다른 사례로서, 도 16의 변형 형태이다.17A to 17E illustrate another example of using the present invention.

도 17a는, 제1주보(120) 및 제2주보(130)를 설치한 후 본굴착과 보강재용 굴착을 반복(제1보강재와 흙막이판의 시공도 함께 이루어짐)한 상태이다.Figure 17a, after the first bulletin 120 and the second bulletin 130 is installed, the main excavation and excavation for the reinforcement is repeated (construction of the first reinforcement and the earthen plate is also made).

이후 도 17b와 같이 트렌치를 굴착한 후 제2주보(130)에 레이커(701)를 설치한다.After the excavation of the trench as shown in FIG. 17B, a raker 701 is installed in the second bulletin 130.

다음으로 도 17c와 같이 트렌치에 측방변위 억제용 콘크리트(501)를 타설한다.Next, as shown in FIG. 17c, the lateral displacement inhibiting concrete 501 is poured into the trench.

다음으로 도 17d와 같이 제1주보(120)와 제2주보(130) 사이에 구조물 벽체(502)를 시공한다.Next, a structure wall 502 is constructed between the first bulletin 120 and the second bulletin 130 as shown in FIG. 17D.

다음으로 도 17e와 같이 굴착을 마무리하고 마지막으로 포장(801)을 한다.Next, the excavation is finished as shown in FIG. 17E, and finally, the packing 801 is performed.

도 18a 내지 도 18c는 본 발명을 이용하는 다른 사례로서, 수평저항력이 부족한 경우에 대처하는 방법에 관한 것이다.18A to 18C illustrate another example of using the present invention, and a method for coping with a case where the horizontal resistance force is insufficient.

먼저 도 18a를 설명한다. 제1주보(120) 및 제2주보(130)가 설치된 후 본 발명에 의한 공법에 따라 굴착이 진행되어 상부에는 버팀대(410)로서 트러스구조물이 마련되어 있으며, 제1주보(120)와 제2주보(130) 사이의 보강재용 굴착부(220)에는 제1보강재(310)가 마련되며, 제1주보(120)를 따라 흙막이판(미도시)이 마련되어 있다. 즉 상기 다른 실시예에서는 버팀대(410)로 트러스구조물을 이용하고 본굴착부(210)에 다수의 슬라브(510)를 탑다운공법으로 시공하는 슬라브시공단계를 포함할 수도 있다. 도 18a는 탑다운 공법으로 슬라브(510-1), 슬라브(510-2)가 시공되어 있는 상태이다. 이 경우 먼저 제2주보(130)를 레이커(701)에 의하여 아일랜드 공법을 적용하여 지지한다.First, FIG. 18A will be described. After the first bulletin 120 and the second bulletin 130 are installed, the excavation proceeds according to the construction method according to the present invention, and a truss structure is provided as a brace 410 on the upper side, the first bulletin 120 and the second bulletin The first reinforcing material 310 is provided in the excavation portion 220 for the reinforcing material between the 130, and the retaining plate (not shown) is provided along the first jumbo 120. That is, in another embodiment, the truss structure may be used as the brace 410, and the slab construction step may be performed by constructing a plurality of slabs 510 on the main excavation portion 210 by a top-down method. 18A illustrates a state in which the slabs 510-1 and the slabs 510-2 are constructed by a top-down method. In this case, the second bulletin 130 is first supported by the raker 701 by applying the island method.

다음으로 도 18b와 같이 하부에 측방변위 억제용 콘크리트(501)를 타설한다.Next, as shown in FIG. 18b, the lateral displacement inhibiting concrete 501 is poured.

다음으로 도 18c와 같이 최종 슬라브(510-3)을 시공하며, 또한 제1주보(120)와 제2주보(130) 사이에 구조물 벽체(502)를 시공하여 합벽식 영구벽체가 형성된다.Next, as shown in FIG. 18C, the final slab 510-3 is constructed, and a structural wall 502 is constructed between the first bullet 120 and the second bullet 130 to form a laminated wall.

도 19a 내지 도 19f는 본 발명을 이용하는 다른 사례이다.19A-19F are another example of using the present invention.

도 19a는, 제1주보(120) 및 제2주보(130)를 설치한 후 본굴착과 보강재용 굴착을 반복(제1보강재와 흙막이판의 시공도 함께 이루어짐)하여 도 15a와 같이 범(berm, 601)을 이용하여 자립 굴착을 이룬 상태이다.19a, after the first bulletin 120 and the second bulletin 130 is installed, the main excavation and the excavation for the reinforcement are repeated (the construction of the first reinforcement and the retaining plate is also carried out), and a berm is obtained as shown in FIG. 15A. , 601) is a self-supporting excavation.

다음으로 도 19b와 같이 레이커(701)를 설치하며, 도 19c와 같이 범(601) 부위을 굴착하고 제1주보(120)와 제2주보(130) 사이를 굴착한 후 제1보강재(310)를 설치하고 다시 되메움한다.Next, the raker 701 is installed as shown in FIG. 19B, and the first reinforcement 310 is excavated after excavating the 601 rim and digging between the first bulletin 120 and the second bulletin 130 as shown in FIG. 19C. Install and refill.

다음으로 도 19d와 같이 제1주보(120)와 제2주보(130) 사이의 하부에 제1보강재(310)를 시공한 후 측방변위 억제용 콘크리트(501)를 시공한다.Next, as shown in FIG. 19d, the first reinforcing material 310 is installed in the lower portion between the first and second bulletin 120 and the second bulletin 130, and then the lateral displacement suppressing concrete 501 is constructed.

다음으로 도 19e와 같이 바닥에 콘크리트를 타설함으로써 기초바닥을 시공한 후 도 19f와 같이 레이커를 해체한다. 이때 레이커의 하부는 매몰처리하거나 또는 해체될 수 있다.Next, after laying the foundation by pouring concrete on the floor as shown in FIG. 19e, the raker is dismantled as shown in FIG. 19f. At this time, the lower part of the raker may be buried or dismantled.

도 20은 본 발명이 적용된 다른 실시례의 평면도 및 종단면도이다.20 is a plan view and a longitudinal sectional view of another embodiment to which the present invention is applied.

본 실시례에서는 본 발명의 제1주보로서 H 빔 대신에 강널말뚝(910)을 이용하였다. 또한 강널말뚝(910)은 서로 연결되면서 마련되어 일종의 지중연속벽으로서 기능한다.In the present embodiment, the steel sheet pile 910 was used as the first bullet of the present invention instead of the H beam. In addition, the steel sheet pile 910 is provided while being connected to each other to function as a kind of underground continuous wall.

따라서 제2주보(130)는 강널말뚝(910)으로부터 이격되어 설치되며, 또한 강널말뚝(910)과 제2주보(130) 사이에 제1보강재(310)가 설치된다. 설치 방법은 강널말뚝(910)을 제1주보로서 고려하면 앞서의 방법들이 그대로 적용될 수 있다.Therefore, the second bulletin 130 is installed spaced apart from the steel sheet pile 910, and the first reinforcing material 310 is installed between the steel sheet pile 910 and the second bulletin 130. If the installation method considering the steel sheet pile 910 as the first bulletin, the above methods can be applied as it is.

도 21은 본 발명이 적용된 다른 실시례의 종단면도이다.21 is a longitudinal sectional view of another embodiment to which the present invention is applied.

본 실시례에서는 제1주보(120) 및 제2주보(130)의 중앙 부위를 상부나 하부에 비하여 단면강성을 증가시켜 사용하고 있는 형태를 보여주고 있다.In this embodiment, the center portion of the first bulletin 120 and the second bulletin 130 is shown to increase the cross-sectional stiffness than the upper or lower portion.

도 22는 본 발명이 적용된 다른 실시례의 종단면도이다.22 is a longitudinal sectional view of another embodiment to which the present invention is applied.

본 실시례는 언덕 등의 경사면에 본 발명의 개념을 적용한 경우로서, 초기 굴착에서는 제1주보(120)와 제2주보(130)에 본 발명의 개념이 적용되고, 다음 굴착에서는 이미 설치된 제2주보(130)를 제1주보(120a)로 하고 상기 제1주보(120a) 내측에 다수의 제2주보(130a)를 설치하여, 본 발명의 개념이 적용되고, 다음 굴착에서는 이미 설치된 제2주보(130a)를 제1주보(120b)로하고 상기 제1주보(120b)의 내측에 다수의 제2주보(130b)를 설치하여 본 발명의 개념이 적용됨으로써, 본굴착부(210)의 내측으로 경사지게 되어지는 흙막이 시공방법을 도시한 것이다.The present embodiment is a case where the concept of the present invention is applied to an inclined surface such as a hill. In the initial drilling, the concept of the present invention is applied to the first bulletin 120 and the second bulletin 130. With the first bulletin 120a as the first bulletin 120a and installing a plurality of second bulletin 130a inside the first bulletin 120a, the concept of the present invention is applied, and the second bulletin is already installed in the next excavation. 130a is the first bulletin 120b and a plurality of second bulletin 130b is installed inside the first bulletin 120b so that the concept of the present invention is applied. It shows the construction method of the soil wall is to be inclined.

상기의 실시례들은 본 발명의 바람직한 실시례일 뿐이며, 본 발명의 기술적 사상은 당업자에 의하여 다양하게 변형 내지 조정되어 실시될 수 있다. 이러한 변형 내지 조정이 본 발명의 기술적 사상을 이용한다면 이는 본 발명의 범위에 속하는 것이다.The above embodiments are merely preferred embodiments of the present invention, and the technical spirit of the present invention may be variously modified or adjusted by those skilled in the art. Such modifications and adjustments fall within the scope of the present invention if they use the technical idea of the present invention.

상기와 같이 본 발명은 제1주보와 제1주보의 내측에 마련되는 제2주보를 미리 지중에 설치한 후 지반을 굴착함에 따라서 제1주보와 제2주보 사이를 연결하는 제1보강재를 설치하여 굴착 깊이에 따라서 제1주보, 제2주보 및 제1보강재로 이루어지는 주보의 단면 2차 모멘트가 확장되어 주보의 물량 대비 극대화된 굴착 깊이를 구현할 수 있을 뿐만 아니라 본굴착부의 제2주보 하부 내측에 압축부재인 레이커를 경사지게 설치하면서 본굴착부를 굴착함으로써 매우 깊은 깊이를 갖는 흙막이를 용이하게 시공할 수 있는 새로운 흙막이 시공 방법을 제공할 수 있다.As described above, according to the present invention, after the first bulletin and the second bulletin provided inside the first bulletin are installed in the ground in advance, the first reinforcement is connected between the first and second bulletin as the ground is excavated. According to the excavation depth, the cross section second moment of the beam consisting of the first bullet, the second bullet and the first reinforcement can be expanded to realize the excavation depth that is maximized compared to the volume of the bullet, and is also compressed inside the lower part of the second bullet. By excavating the main excavation part while installing the raker which is a member inclinedly, it is possible to provide a new construction method for constructing an earthquake having a very deep depth.

Claims (12)

굴착예정면의 가장자리를 따라 다수의 제1주보(120)를 설치하고, 상기 제1주보(120) 내측에 다수의 제2주보(130)를 설치하는 주보설치단계(S10);Installing a plurality of first bulletin 120 along the edge of the excavation surface, and installing a plurality of second bulletin 130 inside the first bulletin 120 (S10); 상기 제1주보(120)와 제2주보(130)의 사이인 보강재용 굴착부(220)를 굴착하면서 상기 제1주보(120)와 제2주보(130)가 연결되도록 보강재(310)를 연결하는 보강재용 굴착부 굴착 및 보강재 연결단계(S20);While reinforcing the excavation portion 220 for the reinforcement between the first bulletin 120 and the second bulletin 130 is connected to the reinforcement 310 so that the first bulletin 120 and the second bulletin 130 is connected. To excavation for the reinforcement excavation and connecting the reinforcement (S20); 상기 제2주보(130)와 서로 대항되어지는 또다른 제2주보(130) 사이인 본굴착부(210)를 굴착하는 본굴착부 굴착단계(S30);A main excavation part excavating step (S30) for excavating the main excavation part 210 between the second jumbo 130 and another second jog 130 opposed to each other; 상기 보강재용 굴착부 굴착 및 보강재 연결단계(S20)와 본굴착부 굴착단계(S30)가 2회이상 반복되어지는 굴착반복단계(S40);Excavation repetition step (S40) is repeated two or more times the excavation part excavation and reinforcing material connection step (S20) and the main excavation part excavation step (S30) for the reinforcement; 상기 굴착반복단계(S40)의 본굴착 굴착단계(S30)에서 본굴착부(210)의 제2주보(130) 하부 내측에 상기 제2주보(130)가 버티어지도록 레이커(701)를 경사지게 설치 및 해체하는 레이커 설치 및 해체단계(S50)로 이루어짐을 특징으로 하는 단면2차모텐트가 강화된 흙막이 싱공방법.In the main excavation excavation step (S30) of the excavation repetition step (S40), the raker 701 is installed to be inclined so that the second bulletin 130 is held in the lower inner side of the second bulletin 130 of the main excavation part 210. Reclamation raker installation and dismantling step (S50), characterized in that the cross-section secondary motent reinforced earthing gasket method. 제 1 항에 있어서,The method of claim 1, 상기 주보설치단계(S10)에서 굴착예정면의 가장자리를 따라 상기 제1주보(120)와 또다른 제1주보(120) 사이에 지중연속벽(110)을 형성하는 것을 특징으로 하는 단면 2차 모멘트가 강화된 흙막이 시공 방법.Cross section secondary moment, characterized in that for forming the underground continuous wall (110) between the first bulletin 120 and another first bulletin 120 along the edge of the prospecting surface in the bulletin installation step (S10) Reinforced earth block construction method. 제 1 항에 있어서,The method of claim 1, 상기 보강재용 굴착부(220)를 굴착하는 진행에 따라 상기 제1주보(120)와 또다른 제1주보(120) 사이에 흙막이판(140)을 설치하는 것을 특징으로 하는 단면 2차 모멘트가 강화된 흙막이 시공 방법.As the excavation part 220 for the reinforcing material is excavated, the second moment of cross section is characterized in that the earth plate 140 is installed between the first bullet 120 and another first bullet 120. Construction method 삭제delete 삭제delete 제 1 항에 있어서,The method of claim 1, 상기 굴착반복단계(S40)의 본굴착부 굴착단계(S30)에서 본굴착부(210)의 제2주보(130)와 서로 대향되는 또 다른 제2주보(130)가 서로 버티어지도록 본굴착의 진행에 따라 버팀대(410)를 설치 및 해체하는 것을 특징으로 하는 단면2차모멘트가 강화된 흙막이 시공 방법.In the excavation repeating step (S40) of the main excavation unit excavation step (S30) of the second excavation 130 of the main excavation unit 210 and another second bulletin 130 facing each other so that the propagation of the main excavation According to the brace construction method of the reinforced secondary section reinforced moment, characterized in that the mounting and disassembly 410. 삭제delete 제 1 항에 있어서,The method of claim 1, 상기 주보설치단계(S10)에서 상기 제1주보(120)의 외측에 다수의 제1보조주보(120a)를 설치하는 것을 특징으로 하는 단면2차모멘트가 강화된 흙막이 시공 방법.In the step of installing the main bulletin step (S10), the first section of the first jujube 120, a plurality of secondary secondary beams 120a, characterized in that the secondary moment reinforced reinforced earthquake construction method. 제 1 항 내지 제 3 항 중 어느 한항에 있어서,The method according to any one of claims 1 to 3, 상기 보강재용 굴착부(220)를 굴착하는 진행에 따라 상기 제1주보(120)와 제2주보 사이에 콘크리트(501)를 타설하여 구조물벽체(502)를 형성하는 것을 특징으로 하는 단면2차모멘트가 강화된 흙막이 시공 방법.As the excavation part 220 for the reinforcing material is excavated, the secondary moment of cross section is formed by placing concrete 501 between the first bullet 120 and the second bullet to form the structure wall 502. Reinforced earth block construction method. 제 1 항에 있어서,The method of claim 1, 상기 제1주보(120)는 강널말뚝인 것을 특징으로 하는 단면2차모멘트가 강화된 흙막이 시공방법.The first jujube 120 is a steel sheet construction method reinforced section second moment, characterized in that the steel sheet pile. 제 6 항에 있어서,The method of claim 6, 상기 버팀대(410)를 트러스구조물로 하고 상기 본굴착부(210)에 다수의 슬라브(510)를 탑다운공법으로 시공하는 특징으로 하는 단면2차모멘트가 강화된 흙막이 시공방법.Reinforced earth wall construction method characterized in that the braces 410 as a truss structure and a plurality of slabs 510 to the main excavation portion 210 by the top-down method. 제 1 항에 있어서,The method of claim 1, 상기 제1주보(120)와 제2주보(130)에서 상기 제2주보(130)를 제1주보(120a)로 하고, 상기 제1주보(120a)의 내측에 다수의 제2주보(130a)를 설치하며, 다시 상기 제2주보(130a)를 또다른 제1주보(120b)로 하고, 상기 제1주보(120b)의 내측에 다수의 제2주보(130b)를 설치하는 것을 특징으로 하는 단면2차모멘트가 강화된 흙막이 시공방법.In the first bulletin 120 and the second bulletin 130, the second bulletin 130 is the first bulletin 120a, and a plurality of second bulletin 130a is formed inside the first bulletin 120a. Cross section characterized in that the second bulletin (130a) to another first bulletin (120b), and to install a plurality of second bulletin (130b) inside the first bulletin (120b) Secondary moment reinforced earth block construction method.
KR1020070054454A 2006-12-12 2007-06-04 Method for constructing land-side protection wall KR100813664B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020060125948 2006-12-12
KR20060125948 2006-12-12

Publications (1)

Publication Number Publication Date
KR100813664B1 true KR100813664B1 (en) 2008-03-14

Family

ID=39398815

Family Applications (2)

Application Number Title Priority Date Filing Date
KR1020070054454A KR100813664B1 (en) 2006-12-12 2007-06-04 Method for constructing land-side protection wall
KR1020070064077A KR100886445B1 (en) 2006-12-12 2007-06-28 Soil tank type land-side protection wall

Family Applications After (1)

Application Number Title Priority Date Filing Date
KR1020070064077A KR100886445B1 (en) 2006-12-12 2007-06-28 Soil tank type land-side protection wall

Country Status (1)

Country Link
KR (2) KR100813664B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804089A (en) * 2016-03-30 2016-07-27 广东华固工程有限公司 Locally-deepened supporting and protecting system used after original deep foundation pit is constructed and construction method of system
CN105887891A (en) * 2016-04-16 2016-08-24 朱奎 Deep basement supporting construction method
CN106193048A (en) * 2016-07-14 2016-12-07 上海岩土工程勘察设计研究院有限公司 H profile steel construction method in powder, sandy soil is gone along with sb. to guard him in a kind of indoor
KR101695715B1 (en) * 2016-06-09 2017-01-13 이기환 Construction method for underground structure

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101105676B1 (en) 2011-05-23 2012-01-18 최정석 Earth retaining wall consrtuction method using two rows pile
KR101105677B1 (en) 2011-05-23 2012-01-18 최정석 Liner screw assembly and earth retainning wall structure using thereof
KR101311422B1 (en) * 2012-04-18 2013-09-25 주식회사 힐 엔지니어링 Connection structure of before and after pile connection for two rows pile construction
CN105908748B (en) * 2016-05-31 2019-01-22 中国建筑第八工程局有限公司 To the Brace in Deep Footing Groove method for being used to control foundation pit deformation under supporting system
KR101913493B1 (en) * 2017-02-06 2018-10-30 김영길 Cast in place pile used self-retaining construction method
KR101947119B1 (en) * 2017-03-10 2019-02-13 이기환 Soil retaining wall using two rows pile

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000058238A (en) * 1999-10-30 2000-10-05 홍원기 Underground construction method using permanent reinforced concrete girders as temporary struts
JP2002227204A (en) * 2001-01-29 2002-08-14 Maeda Corp Earth retaining method of excavation section
KR20030030868A (en) * 2002-10-01 2003-04-18 (주)신성엔지니어링 Trusstype support structures for building landslide protection wall
KR20050010616A (en) * 2003-07-21 2005-01-28 김정균 transverse truss strutting method for construction and structure thereof
KR20060032823A (en) * 2004-10-13 2006-04-18 코오롱건설주식회사 Soil retaining method using two rows pile

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56135608A (en) * 1980-03-24 1981-10-23 Kawasaki Steel Corp Method for mitigating destructive shearing forge exerting on double walled structure
JPS57155421A (en) * 1981-03-18 1982-09-25 Kajima Corp Method of construction of underground double coffering sheathing
JP2757208B2 (en) * 1989-06-13 1998-05-25 大成建設株式会社 Continuous underground wall construction method
JPH0617416A (en) * 1992-06-30 1994-01-25 Kajima Corp Earth retaining wall
JP3036295B2 (en) * 1993-04-20 2000-04-24 株式会社大林組 Construction method of retaining wall
JP4318460B2 (en) * 2003-01-07 2009-08-26 株式会社竹中工務店 Earth retaining structure
JP4914062B2 (en) * 2005-12-12 2012-04-11 株式会社竹中工務店 Two-tiered retaining wall and its construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000058238A (en) * 1999-10-30 2000-10-05 홍원기 Underground construction method using permanent reinforced concrete girders as temporary struts
JP2002227204A (en) * 2001-01-29 2002-08-14 Maeda Corp Earth retaining method of excavation section
KR20030030868A (en) * 2002-10-01 2003-04-18 (주)신성엔지니어링 Trusstype support structures for building landslide protection wall
KR20050010616A (en) * 2003-07-21 2005-01-28 김정균 transverse truss strutting method for construction and structure thereof
KR20060032823A (en) * 2004-10-13 2006-04-18 코오롱건설주식회사 Soil retaining method using two rows pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804089A (en) * 2016-03-30 2016-07-27 广东华固工程有限公司 Locally-deepened supporting and protecting system used after original deep foundation pit is constructed and construction method of system
CN105887891A (en) * 2016-04-16 2016-08-24 朱奎 Deep basement supporting construction method
KR101695715B1 (en) * 2016-06-09 2017-01-13 이기환 Construction method for underground structure
CN106193048A (en) * 2016-07-14 2016-12-07 上海岩土工程勘察设计研究院有限公司 H profile steel construction method in powder, sandy soil is gone along with sb. to guard him in a kind of indoor

Also Published As

Publication number Publication date
KR100886445B1 (en) 2009-03-04
KR20080054332A (en) 2008-06-17

Similar Documents

Publication Publication Date Title
KR100813664B1 (en) Method for constructing land-side protection wall
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
KR102162467B1 (en) Thrust pile with prestress and self-supporting type pile construction using it
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
KR100967497B1 (en) Method for constructing an underground structure
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
KR20080005109A (en) Structure for supporting retaining wall of earth with arch material and method constructing the arch structure
KR20200029079A (en) Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method
KR20120115704A (en) Soil retaining method using two rows pile
KR20080007483A (en) Underground retaining wall for public works and method for constructing the same
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR101262357B1 (en) Inclined Earth Retaining Structure Method
KR101190739B1 (en) Method of Constructing Underground Composite Outer Wall Structure and Underground Composite Outer Wall Structure Constructed by the Same
JP2012026250A (en) Reinforcement structure and reinforcement method of existing retaining wall
KR20080025219A (en) Underground outer wall construction method using deck-plate and deck-plate for constructing underground outer wall
KR100376590B1 (en) Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts
JP6768477B2 (en) How to build an underground structure
KR20190002845U (en) Braced wall
KR102195496B1 (en) Pile for earth self-retaining wall using cast in place concrete pile with double I beam
KR102194381B1 (en) Pile for Earth self-retaining wall using double I beam
JP2003268770A (en) Earth retaining construction method and reinforcing structure of sheet pile used for this construction method
KR200369479Y1 (en) The land-side protection wall panel
KR101218825B1 (en) Method of land-side protection wall using bracing
KR100515971B1 (en) Soil retaining method using H-pile having large section
JP3228199U (en) Construction structure of earth retaining support

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120314

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee