KR101218825B1 - Method of land-side protection wall using bracing - Google Patents

Method of land-side protection wall using bracing Download PDF

Info

Publication number
KR101218825B1
KR101218825B1 KR1020100050593A KR20100050593A KR101218825B1 KR 101218825 B1 KR101218825 B1 KR 101218825B1 KR 1020100050593 A KR1020100050593 A KR 1020100050593A KR 20100050593 A KR20100050593 A KR 20100050593A KR 101218825 B1 KR101218825 B1 KR 101218825B1
Authority
KR
South Korea
Prior art keywords
bracing
supporting
self
open cut
thumb
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020100050593A
Other languages
Korean (ko)
Other versions
KR20110131000A (en
Inventor
김종율
Original Assignee
나우이엔씨(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 나우이엔씨(주) filed Critical 나우이엔씨(주)
Priority to KR1020100050593A priority Critical patent/KR101218825B1/en
Publication of KR20110131000A publication Critical patent/KR20110131000A/en
Application granted granted Critical
Publication of KR101218825B1 publication Critical patent/KR101218825B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/223Details of top sections of foundation piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 브레이싱을 이용한 자립식 흙막이 공법에 관한 것으로, 더욱 상세하게는 굴착영역의 둘레를 굴착하여 오픈 컷을 형성하는 단계와, 상기 오픈 컷에 의하여 형성된 지반의 양측을 따라 복수의 엄지말뚝을 근입시키는 단계와, 상기 엄지말뚝에 수평 또는 경사브레이싱(bracing), 또는 이들 모두를 상호간에 연결하여 흙막이 구조를 형성하는 단계와, 상기 굴착영역을 굴착하여 기초부를 형성하는 단계를 포함하여 이루어져, 엄지말뚝과 수평 및 경사브레이싱이 상호 결합된 자립식 흙막이 구조를 도입하여 부재력과 변위를 기존 공법에 비하여 현저히 낮추어 줌으로써 동일한 지반 조건과 하중이 적용되는 경우에도 기본 공법보다 충분한 부재자체의 안정성을 확보할 수 있으며, 아울러 기존 공법에서 사용하던 지보재(스트럿, 어스앵커, 레이커 등)를 사용하지 않음으로써 충분한 작업공간을 확보할 수 있고, 또 지보재의 미사용으로 이의 설치를 위한 작업 시간을 줄여 전체적인 공기를 단축하는 것이 가능하며, 더 나아가 흙막이 구조의 안정성 보강을 위한 추가적인 부재의 도입 필요성이 없어 경제성을 도모할 수 있는 브레이싱을 이용한 자립식 흙막이 공법을 제안하고자 한다.The present invention relates to a self-supporting retaining method using bracing, and more specifically, excavating a circumference of an excavation area to form an open cut, and incorporating a plurality of thumb piles along both sides of the ground formed by the open cut. And forming a mud structure by connecting horizontal or inclined bracing, or both, to the thumb pile, and forming a foundation by excavating the excavation area. By introducing a self-supporting retaining structure in which horizontal and inclined bracing are mutually combined, the member force and displacement are significantly lowered compared to the existing method, so that even when the same ground conditions and loads are applied, sufficient stability of the member itself can be secured. In addition, it is possible to secure a sufficient working space by not using the supporting materials (struts, earth anchors, rakers, etc.) used in the existing construction method, and to shorten the overall air by reducing the working time for its installation by not using the supporting materials. It is possible, and furthermore, to propose a self-supporting mud-blocking method using bracing, which can promote economic efficiency since there is no need to introduce an additional member to reinforce the stability of the mud-guard structure.

Description

브레이싱을 이용한 자립식 흙막이 공법{METHOD OF LAND-SIDE PROTECTION WALL USING BRACING}METHOD OF LAND-SIDE PROTECTION WALL USING BRACING}

본 발명은 일정한 폭을 유지하면서 2열로 근입된 엄지말뚝과 말뚝 상부에 수평 및 경사 브레이싱이 상호 결합된 자립식 흙막이 구조를 도입하여 토압에 의한 흙막이벽체의 변위를 말뚝 상부 브레이싱의 축력으로 저항하게 하여, 부재력 및 변위를 기존 공법에 비하여 현저히 낮추어 줌으로써 부재 자체의 안정성을 확보할 수 있으며, 아울러 기존 공법에서 사용하던 지보재(스트럿, 어스앵커, 레이커 등)를 사용하지 않아 지하층 공사 시 충분한 작업공간을 확보할 수 있고, 또 지보재의 미사용으로 이의 설치를 위한 작업 시간을 줄여 전체적인 공기를 단축하는 것이 가능하며, 더 나아가 흙막이 구조의 안정성 보강을 위한 추가적인 부재의 도입 필요성이 없어 경제성을 도모할 수 있는 브레이싱을 이용한 자립식 흙막이 공법에 관한 것이다.
The present invention introduces a self-supporting retaining structure in which horizontal and inclined bracing are mutually coupled to the top of the pile and the thumb piles joined in two rows while maintaining a constant width to resist the displacement of the retaining wall by earth pressure with the axial force of the top bracing of the pile , By reducing the member force and displacement significantly compared to the existing construction method, it is possible to secure the stability of the member itself. In addition, it does not use the support materials (Strut, Earth Anchor, Raker, etc.) used in the existing construction method to secure sufficient working space for the basement construction. It is possible to shorten the overall air by reducing the working time for its installation by not using support materials, and furthermore, there is no need to introduce additional members to reinforce the stability of the mudguard structure. It relates to a self-supporting self-supporting mudguard method.

엄지말뚝 흙막이 공법이란 개착식 흙막이 공법의 일종으로서, 일정간격으로 엄지말뚝(H-Pile)을 항타하거나 천공 후 삽입하는 방식에 의해 근입하고, 터파기를 진행하면서 토류판 등의 흙막이 부재를 엄지말뚝 사이에 끼워 넣어 벽체를 형성하는 공법을 말하며, 엄지말뚝 토류판 공법, 시트파일 공법, SCW, CIP 등이 이에 해당한다.
The thumb pile mud construction method is a kind of an open-type mud construction method, which is inserted by inserting the thumb pile (H-Pile) at regular intervals or by inserting it after drilling. It refers to a method of inserting to form a wall, and the thumb pile earth plate method, sheet pile method, SCW, CIP, etc. are applicable.

또한 종래의 흙막이 공법 중 엄지말뚝 토류판 공법에 의한 흙막이 구조물의 구성은 상호 홈부가 마주 보도록 수직하게 설치된 복수개의 엄지말뚝(H 빔)과, 상기 홈부에 삽입 지지되어 후방의 흙더미 등이 전방을 향하여 무너지는 것을 방지하기 위한 토류판에 의해 구성된다.
In addition, among the conventional mud construction methods, the construction of the mud structure by the thumb pile earth plate construction method is a plurality of thumb piles (H beams) vertically installed to face each other and the groove portions inserted into the grooves, so that the rear soil piles collapsing toward the front. It is constituted by the earth plate to prevent it from losing.

그리고 토류판으로는 소정 규격의 목재판 또는 강재판이 사용되며, 이를 적층하여 벽체를 형성하고, 그 적층된 토류판을 고정하기 위하여 끼움목(쐐기)을 설치한 구조를 채용하는 것이 일반적이다.
In addition, a wood plate or a steel plate of a predetermined standard is used as the earth plate, and it is common to adopt a structure in which a wall is formed by laminating it and a fitting tree (wedge) is installed to fix the stacked earth plate.

이러한 종래의 흙막이 공법으로는 등록특허 제10-0831332호(2008.05.15. 등록. 이하 '선행기술 1'이라 함.) "토목공사용 지하 흙막이벽 및 그의 시공방법" 및 공개특허 제10-2009-0091473호(2009.08.28. 공개. 이하 '선행기술 2'라 함.) "스트럿을 이용한 2열 엄지말뚝 흙막이 공법"이 개시되어 있다.
Patent registration No. 10-0831332 (2008.05.15. registration, hereinafter referred to as "Prior Art 1") as such a conventional mud construction method "Underground mud wall for civil engineering works and construction method thereof" and published patent No. 10-2009- 0091473 (2009.08.28. Published, hereinafter referred to as "Prior Art 2") "The construction method of a two-column thumb pile using a strut" is disclosed.

그러나 이러한 종래의 흙막이 공법은 다음과 같은 점에서 문제점이 있다.
However, this conventional mudguard method has a problem in the following points.

첫째, 고심도의 터파기 공사를 수행하는 경우, H 빔만으로는 배후토사의 토압에 저항할 수 없으므로, 이를 보강하기 위하여 많은 수의 지보재(Strut, Earth Anchor, Raker 등)를 사용해야 하는데, 이러한 방식은 비경제적일 뿐만 아니라,First, in the case of performing a high-depth trenching construction, the H-beam alone cannot resist the earth pressure of the rear soil, so a large number of support materials (Strut, Earth Anchor, Raker, etc.) must be used to reinforce it. Not only is it not economical,

작업공간의 확보를 어렵게 하고, 구조적으로 비효율적이므로 주변지반 침하의 우려가 있다는 점이다.
It is difficult to secure a working space and is structurally inefficient, so there is a risk of subsidence.

둘째, 종래의 공법에 의한 흙막이 구조물은 강성체로서 토류벽 역할을 할 수는 있으나, 상부두부 변위가 상대적으로 크게 발생하므로 배면부 지반의 이완이 크게 발생한다는 점이다.
Second, the conventional structure of the earth retaining structure is a rigid body, which can serve as a earth wall, but the displacement of the upper head occurs relatively large, so that the relaxation of the back ground is large.

본 발명은 상기한 바와 같은 문제점을 해결하기 위해 안출된 것으로,The present invention has been made to solve the problems as described above,

엄지말뚝과 수평 및 경사브레이싱이 상호 결합된 자립식 흙막이 구조를 도입하여 부재력과 변위를 기존 공법에 비하여 현저히 낮추어 줌으로써 동일한 지반 조건과 하중이 적용되는 경우에도 부재자체의 안정성을 확보할 수 있으며,By introducing a self-supporting retaining structure in which thumb piles and horizontal and inclined bracing are mutually coupled, the member force and displacement are significantly reduced compared to the existing method, thereby ensuring the stability of the member itself even when the same ground conditions and loads are applied.

아울러 기존 공법에서 사용하던 지보재(스트럿, 어스앵커, 레이커 등)를 사용하지 않음으로써 충분한 작업공간을 확보할 수 있고,In addition, sufficient work space can be secured by not using the supporting materials (strut, earth anchor, raker, etc.) used in the existing construction method.

또 지보재의 미사용으로 이의 설치를 위한 작업 시간을 줄여 전체적인 공기를 단축하는 것이 가능하며,In addition, it is possible to shorten the overall air by reducing the working time for the installation of it without the use of supporting materials.

더 나아가 흙막이 구조의 안정성 보강을 위한 추가적인 부재의 도입 필요성이 없어 경제성을 도모할 수 있는 브레이싱을 이용한 자립식 흙막이 공법을 제공하는 것을 하나의 목적으로 한다.
Furthermore, it is an object of the present invention to provide a self-supporting self-supporting retaining method using bracing, which can promote economic efficiency because there is no need to introduce additional members for reinforcing the stability of the retaining structure.

그리고 본 발명에 따른 경사브레이싱을 트러스 구조로 배열함으로써 엄지말뚝이 수직 및 수평방향으로 힘의 반력을 받음과 동시에 대각선 방향으로도 반력을 발생하도록 하여 인접부근의 각 부재로 힘을 분산하여 지지하게 되고,And by arranging the inclined bracing according to the present invention in a truss structure, the thumb pile receives the reaction force of the force in the vertical and horizontal directions and simultaneously generates the reaction force in the diagonal direction, thereby dispersing and supporting the force to each member in the vicinity.

따라서 엄지말뚝으로 가해지는 반력을 인장 및 압축되게 분담하여 작용하므로 지지력을 더욱 보강할 수 있는 브레이싱을 이용한 자립식 흙막이 공법을 제공하는 것을 또 하나의 특징으로 한다.
Therefore, it is another feature to provide a self-supporting earth retaining method using bracing that can further reinforce the supporting force because the reaction force applied to the thumb pile is applied by tension and compression.

또 본 발명에 따른 흙막이 구조를 축조한 다음 오픈 컷의 경사면을 채워 지면과 수평을 이루도록 함으로써 굴착영역을 굴착 시 굴착 장비나 작업자 등의 접근성을 확보하여 작업 편의성 및 안정성을 보장할 수 있는 브레이싱을 이용한 자립식 흙막이 공법을 제공하는 것을 또 하나의 목적으로 한다.
In addition, by constructing the mudguard structure according to the present invention and filling the inclined surface of the open cut so as to be level with the ground, using a bracing that secures accessibility of excavation equipment or workers when excavating the excavation area to ensure work convenience and stability Another object is to provide a self-supporting retaining method.

본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법은The self-supporting earthenware construction method using bracing according to the present invention

(a) 굴착영역의 둘레를 굴착하여 오픈 컷을 형성하는 단계;(a) excavating the circumference of the excavation area to form an open cut;

(b) 상기 오픈 컷에 의하여 형성된 지반의 양측을 따라 복수의 엄지말뚝을 근입시키는 단계;(B) step of rooting a plurality of thumb piles along both sides of the ground formed by the open cut;

(c) 상기 엄지말뚝과 수평 또는 경사브레이싱(bracing), 또는 이들 모두를 상호간에 연결하여 흙막이 구조를 형성하는 단계; 및(c) forming a mudguard structure by connecting the thumb pile with horizontal or inclined bracing, or both of them; And

(d) 상기 굴착영역을 굴착하여 기초부를 형성하는 단계;를 포함하여 이루어진다.
(d) excavating the excavation area to form a foundation.

그리고 본 발명에 따른 상기 경사브레이싱은 상호 엇갈려 배열된 트러스(truss) 구조인 것을 특징으로 한다.
And the inclined bracing according to the present invention is characterized in that the truss (truss) structure arranged in a staggered mutually.

또 본 발명에 따른 상기 (c)단계에는 상기 오픈 컷의 굴착 시 흙막이 구조의 외측에 형성된 경사면에 흙채움을 하거나, 또는 상기 경사면의 상부를 복공판으로 덮어 경사면을 복구하는 (c′)단계가 더 포함되어 있는 것을 특징으로 한다.
In addition, in the step (c) according to the present invention, the step (c′) of repairing the inclined surface by filling the soil on the inclined surface formed on the outside of the mudguard structure when excavating the open cut or covering the upper part of the inclined surface with a perforated plate It is characterized by being included.

더 나아가 본 발명에 따른 상기 (c)단계에는 상호 인접한 엄지말뚝 사이에 토류판을 장착하는 (c″)단계가 더 포함되어 있는 것을 특징으로 한다.
Furthermore, the step (c) according to the present invention is characterized in that it further comprises a step (c″) of mounting the earth plate between adjacent thumb piles.

본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법은 엄지말뚝과 수평 및 경사브레이싱이 상호 결합된 자립식 흙막이 구조를 도입하여 부재력과 변위를 기존 공법에 비하여 현저히 낮추어 줌으로써 동일한 지반 조건과 하중이 적용되는 경우에도 부재자체의 안정성을 확보할 수 있으며,In the self-supporting earthing method using bracing according to the present invention, when the same ground condition and load are applied by significantly lowering the member force and displacement compared to the existing method by introducing a self-supporting earthing structure in which horizontal and inclined bracing are mutually coupled. Edo can secure the stability of the absent itself,

아울러 기존 공법에서 사용하던 지보재(스트럿, 어스앵커, 레이커 등)를 사용하지 않음으로써 충분한 작업공간을 확보할 수 있고,In addition, sufficient work space can be secured by not using the supporting materials (strut, earth anchor, raker, etc.) used in the existing construction method.

또 지보재의 미사용으로 이의 설치를 위한 작업 시간을 줄여 전체적인 공기를 단축하는 것이 가능하며,In addition, it is possible to shorten the overall air by reducing the working time for the installation of it without the use of supporting materials.

더 나아가 흙막이 구조의 안정성 보강을 위한 추가적인 부재의 도입 필요성이 없어 경제성을 도모할 수 있게 된다.
Furthermore, there is no need to introduce an additional member for reinforcing the stability of the retaining structure, and thus economic efficiency can be achieved.

그리고 본 발명에 따른 경사브레이싱을 트러스 구조로 배열함으로써 엄지말뚝이 수직 및 수평방향으로 힘의 반력을 받음과 동시에 대각선 방향으로도 반력을 발생하도록 하여 인접부근의 각 부재로 힘을 분산하여 지지하게 되고,And by arranging the inclined bracing according to the present invention in a truss structure, the thumb pile receives the reaction force of the force in the vertical and horizontal directions and simultaneously generates the reaction force in the diagonal direction, thereby dispersing and supporting the force to each member in the vicinity.

따라서 엄지말뚝으로 가해지는 반력을 인장 및 압축되게 분담하여 작용하므로 지지력을 더욱 보강할 수 있게 된다.
Therefore, the reaction force applied to the thumb pile is applied by tension and compression, so that the supporting force can be further reinforced.

또 본 발명에 따른 흙막이 구조를 축조한 다음 오픈 컷의 경사면을 채워 지면과 수평을 이루도록 함으로써 굴착영역을 굴착 시 굴착 장비나 작업자 등의 접근성을 확보하여 작업 편의성 및 안정성을 보장할 수 있게 된다.
In addition, by constructing the mudguard structure according to the present invention and filling the inclined surface of the open cut so as to be level with the ground, it is possible to secure workability and stability by securing accessibility of excavation equipment or workers when excavating the excavation area.

도 1은 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법을 나타내는 흐름도,
도 2a 내지 도 2f는 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법의 작업 공정을 나타내는 공정도,
도 3은 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 구조를 나타내는 평면도 및 정면도,
도 4는 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법의 경사브레이싱의 다양한 배열 형태를 나타내는 사시도.
1 is a flow chart showing a self-supporting method of mudguard using bracing according to the present invention,
Figures 2a to 2f is a process diagram showing the working process of the self-supporting earthing method using the bracing according to the present invention,
3 is a plan view and a front view showing a self-supporting retaining structure using bracing according to the present invention;
Figure 4 is a perspective view showing a variety of arrangement of the inclined bracing of the self-supporting soil retaining method using the bracing according to the present invention.

본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법을 첨부된 도면을 참조하여 상세하게 설명하기로 한다.
A self-supporting earthenware construction method using bracing according to the present invention will be described in detail with reference to the accompanying drawings.

우선 본 명세서상에서 사용되는 유사한 의미의 명칭을 편의상으로 정의하면,First of all, if the name of a similar meaning used in this specification is defined for convenience,

우선 '지면(地面)(G1)'은 굴착 작업 전의 땅 바닥면을 의미하고,First,'ground surface (G1)' means the ground surface before excavation,

다음으로 '지반(地盤)(G2)'은 지면을 굴착하여 건물이나 가설물 등과 같은 구조물의 기초나 근거가 되는 바닥면을 의미하는 것으로 한다.
Next,'ground (G2)' refers to the ground surface that is the basis or foundation of structures such as buildings and temporary objects by excavating the ground.

도 1 내지 도 2f에 도시된 바와 같이 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법은As shown in Figures 1 to 2f, a self-supporting soiling method using bracing according to the present invention

(a) 굴착영역의 둘레를 굴착하여 오픈 컷(10)을 형성하는 단계(S100);(a) excavating the circumference of the excavation area to form an open cut 10 (S100);

(b) 상기 오픈 컷(10)에 의하여 형성된 지반(G2)의 양측을 따라 복수의 엄지말뚝(20)을 근입시키는 단계(S200);(b) step of advancing a plurality of thumb piles (20) along both sides of the ground (G2) formed by the open cut (S200);

(c) 상기 엄지말뚝(20)과 수평 또는 경사브레이싱(bracing)(30)(40), 또는 이들 모두를 상호간에 연결하여 흙막이 구조를 형성하는 단계(S300); 및(c) forming a mudguard structure by connecting the thumb pile 20 and a horizontal or inclined bracing 30, 40, or both of them to each other (S300); And

(d) 상기 굴착영역(EA)을 굴착하여 기초부(BA)를 형성하는 단계(S400);를 포함하여 이루어진다.
(d) excavating the excavation area EA to form a base portion BA (S400).

도 1 내지 도 2f에 도시된 바와 같이 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법에서, 상기 (a)단계(S100)는As shown in Figures 1 to 2f, in the self-supporting earthing method using the bracing according to the present invention, the step (a) (S100) is

굴착영역(EA)의 둘레를 굴착하여 오픈 컷(10)을 형성하기 위한 단계이다.
This is a step for excavating the circumference of the excavation area EA to form the open cut 10.

즉 본 발명에 따른 (a)단계(S100)는 기초부(BA)를 형성하기 전에, 굴착영역(EA) 주변을 따라 지면(G1)을 굴착하여 형성된 경사면(11)과, 상기 경사면(11)과 이어지는 편평한 지반(G2)을 구성되는 굴착면에 오픈 컷(10)이 형성된다.
That is, in step (a) (S100) according to the present invention, before forming the base portion BA, the inclined surface 11 formed by excavating the ground G1 along the periphery of the excavation area EA and the inclined surface 11 And an open cut 10 is formed on the excavation surface constituting the flat ground G2.

이는 지면(G1)의 굴착 시 일정한 각도를 갖는 경사면(11)을 형성함으로서 별도의 흙막이 공법을 사용하지 않고 굴착작업 중 지면(G1)이나 토사의 침하나 붕괴를 방지할 수 있기 때문이다.
This is because by forming the inclined surface 11 having a certain angle when excavating the ground G1, it is possible to prevent settlement or collapse of the ground G1 or soil during excavation without using a separate earthing method.

이때 상기 오픈 컷(10)의 경사면(11)은 지반(G2)의 양측에 형성되거나,At this time, the inclined surface 11 of the open cut 10 is formed on both sides of the ground (G2),

또는 지반(G2)의 일측, 더욱 구체적으로는 굴착영역(EA)을 외측에서 감싸는 위치에 형성하는 가능하나,Or one side of the ground (G2), more specifically, it is possible to form in a position surrounding the excavation area (EA) from the outside,

후자의 경우에는 굴착영역(EA)과 인접한 내측 경사면(11)은 굴착영역(EA)을 굴착하여 기초부(BA)를 형성하는 경우 함께 굴착된다는 점을 고려한 것이다.
In the latter case, it is considered that the inner inclined surface 11 adjacent to the excavation area EA is excavated together when excavating the excavation area EA to form the base portion BA.

그리고 상기 오픈 컷(10)에 의하여 경사면(11)을 제외한 지반(G2)의 깊이와 폭은 상기 수평 및 경사브레이싱(30)(40)의 설치 높이와 설치 폭과 동일하게 굴착하는 것이 바람직하고,And it is preferable that the depth and width of the ground G2 excluding the inclined surface 11 by the open cut 10 are the same as the installation height and installation width of the horizontal and inclined bracing 30, 40.

따라서 지반(G2)에서 지면(G1)까지의 높이는 하부에 위치하는 수평브레이싱(30)과 상부에 위치하는 수평브레이싱(30)까지의 높이와 동일하며,Therefore, the height from the ground (G2) to the ground (G1) is the same as the height to the horizontal bracing (30) located at the bottom and the horizontal bracing (30) located at the top,

아울러 지반(G2)의 폭은 각 수평브레이싱(30)의 길이와 동일하게 형성된다.
In addition, the width of the ground (G2) is formed to be the same as the length of each horizontal bracing (30).

도 1, 도 2f에 도시된 바와 같이 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법에서, 상기 (b)단계(S200)는As shown in Figures 1 and 2f, in the self-supporting earthing method using the bracing according to the present invention, the step (b) (S200) is

상기 오픈 컷(10)에 의하여 형성된 지반(G2)의 양측을 따라 복수의 엄지말뚝(20)을 근입시키기 위한 단계이다.
This is a step for rooting a plurality of thumb piles 20 along both sides of the ground G2 formed by the open cut 10.

즉 본 발명에 따른 (b)단계(S200)는 상기 오픈 컷(10)에서 굴착영역(EA)과 인접한 내측 지반(G2)을 따라 복수의 엄지말뚝(20)을 항타(杭打)하여 근입시키고,That is, in step (b) (S200) according to the present invention, in the open cut 10, a plurality of thumb piles 20 are struck along the inner ground G2 adjacent to the excavation area EA, and then rooted. ,

아울러 굴착영역(EA)을 외측에서 감싸는 외측 지반(G2)을 따라 복수의 엄지말뚝(20)을 항타하여 근입시켜,In addition, by driving a plurality of thumb piles 20 along the outer ground G2 surrounding the excavation area EA from the outside,

상기 각 엄지말뚝(20)이 지반(G2)을 따라 2열로 배열되어 굴착영역(EA)을 둘러싸게 된다.
Each of the thumb piles 20 is arranged in two rows along the ground G2 to surround the excavation area EA.

이때 상기 각 엄지말뚝(20)의 근입깊이는 힘의 평형, 지지력, 히빙, 보일링, 파이핑, 팽상 등 굴착저면의 안정성에 대한 검토를 통하여 결정하고, 최소근입깊이는 1.5m 정도로 하며,At this time, the root depth of each of the thumb piles 20 is determined through a review of the stability of the excavation bottom, such as balance of force, support force, heaving, piping, and expansion, and the minimum root depth is about 1.5 m.

상기 각 엄지말뚝(20)이 지반(G2)으로부터 노출되는 길이는 지반(G2)으로부터 지면(G1)까지, 즉 지면(G1)과 수평을 이룰 수 있는 높이이고,The length at which each of the thumb piles 20 is exposed from the ground G2 is a height that can be leveled from the ground G2 to the ground G1, that is, level with the ground G1,

또한 상기 각 엄지말뚝(20)은 H-파일이나 I-파일을 사용하게 된다.
Also, each of the thumb piles 20 uses an H-file or an I-file.

도 1 내지 도 2c에 도시된 바와 같이 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법에서, 상기 (c)단계(S300)는As shown in Figures 1 to 2c, in the self-supporting earthing method using the bracing according to the present invention, the step (c) (S300) is

상기 엄지말뚝(20)과 수평 또는 경사브레이싱(30)(40), 또는 이들 모두를 상호 연결하여 자립식 흙막이 구조(PW)를 형성하기 위한 단계이다.
It is a step for forming a self-supporting mudguard structure PW by interconnecting the thumb pile 20 and the horizontal or inclined bracing 30, 40, or both.

즉 본 발명에 따른 (c)단계(S300)에서는 우선 상호 마주하는 위치에 배열된 엄지말뚝(20)의 상단부 및 하단부에 수평브레이싱(30)을 연결하고(도 2c 및 도 3 참조),That is, in step (c) (S300) according to the present invention, first, horizontal bracing 30 is connected to upper and lower ends of the thumb piles 20 arranged at mutually facing positions (see FIGS. 2C and 3),

다음으로 상호 마주하는 위치에 배열된 엄지말뚝(20) 또는 상기 수평브레이싱(30), 또는 이들 모두에 경사브레이싱(40)을 연결하게 된다.Next, the inclined bracing 40 is connected to the thumb pile 20 or the horizontal bracing 30 arranged at mutually facing positions, or both.

그리고 상기 엄지말뚝(20), 수평브레이싱(30) 및 경사브레이싱(40)은 용접이나 또는 고장력 볼트에 의한 볼트체결 방식으로 연결하여 상호간에 일체화된 거동을 유지할 수 있도록 하여 지지력을 보장할 수 있도록 하는 것이 바람직하다.
In addition, the thumb pile 20, the horizontal bracing 30, and the inclined bracing 40 are connected by a bolting method by welding or a high-strength bolt so as to maintain the unified behavior of each other, so as to ensure support force. It is preferred.

더 나아가 상기 경사브레이싱(40)은 상호 엇갈린 형태의 트러스 구조로 연결하게 되는데,Further, the inclined bracing 40 is connected to each other by a staggered truss structure.

이는 트러스의 구조적인 특징, 즉 엄지말뚝(20)이 수직 및 수평방향으로 힘의 반력을 받음과 동시에 대각선 방향으로도 반력을 발생하도록 함으로써 인접부근의 각 부재로 힘을 분산하여 지지하게 된다.
This is to support the structural characteristics of the truss, that is, the thumb pile 20 receives the reaction force of the force in the vertical and horizontal directions and simultaneously generates the reaction force in the diagonal direction.

또한 상기 경사브레이싱(40)이 트러스 구조로 이루어진 경우에는 엄지말뚝(20)으로 가해지는 반력을 분담하도록 인장 및 압축되게 작용하므로 더욱 지지력을 높이는 효과를 얻을 수 있게 된다.
In addition, when the inclined bracing 40 is made of a truss structure, it acts to be tensioned and compressed so as to share the reaction force applied to the thumb pile 20, so that an effect of increasing the support force can be obtained.

아울러 첨부된 도 4는 본 발명에 따른 경사브레이싱(40)의 또 다른 배열구조를 나타내는 변형례들로In addition, the attached Figure 4 is a modified example showing another arrangement structure of the inclined bracing 40 according to the present invention

우선, 도 4의 (a)에는 상기 경사브레이싱(40)이 인접한 네 지점의 엄지말뚝(20) 상단부에 수평한 형태로 엇갈려 배열되도록 연결되어 있고,First, in Fig. 4 (a), the inclined bracing 40 is connected to be staggered and arranged horizontally at the upper end of the thumb pile 20 at four adjacent points,

다음으로 도 4의 (b)에는 상기 경사브레이싱(40)이 상호 대각방향에 위치하는 엄지말뚝(20)에 상호 경사진 형태로 엇갈려 배열되도록 연결됨으로써Next, in Figure 4 (b), the inclined bracing 40 is connected to be arranged to be staggered in a mutually inclined shape to the thumb pile 20 positioned in the diagonal direction.

상호 나란히 배열된 엄지말뚝(20)이 좌우측 방향으로의 뒤틀림을 방지하여 구조적인 안정성을 보장할 수 있도록 하는 것도 또한 바람직하다.
It is also desirable that the thumb piles 20 arranged side by side prevent distortion in the left and right directions to ensure structural stability.

따라서 상기 수평브레이싱(30)과 경사브레이싱(40), 더 나아가 경사브레이싱(40)을 트러스 구조로 연결함으로써 엄지말뚝(20)의 유효좌굴길이를 줄여 줌으로써 엄지말뚝(20) 상단의 변위를 현격하게 줄이고,Therefore, by reducing the effective buckling length of the thumb pile 20 by connecting the horizontal bracing 30 and the inclined bracing 40, and furthermore, the inclined bracing 40 in a truss structure, the displacement of the upper end of the thumb pile 20 is significantly increased. Reduce,

또한 동일한 지반(G2) 및 하중조건 하에서 부재력, 즉 휨모멘트와 전단력을 감소시켜 경제적이면서도 안정성을 보장할 수 있어 안전율을 증대시킴으로써In addition, under the same ground (G2) and load conditions, the member force, that is, the bending moment and the shear force, can be reduced to ensure economical stability, thereby increasing the safety factor.

굴착영역(EA)의 굴착 시 더욱 깊은 심도로 굴착하는 것이 가능하게 된다.
When excavating the excavation area EA, it is possible to excavate to a deeper depth.

특히 본 발명에 따른 흙막이 구조의 상단부까지 높이는 지면의 높이와 동일하게 설치함으로써 흙막이 구조(PW)가 지면(G1)의 하부에 위치하도록 하여In particular, the height to the upper end of the mudguard structure according to the present invention is the same as the height of the ground, so that the mudguard structure (PW) is located at the bottom of the ground (G1)

유효좌굴길이를 감소시킴과 동시에 그 만큼 굴착 깊이를 깊게 할 수 있어 굴착 심도를 깊게 유지할 수 있게 된다.
At the same time as reducing the effective buckling length, it is possible to deepen the depth of excavation and maintain the depth of excavation.

다음으로 도 2d에 도시된 바와 같이 본 발명에 따른 흙막이 공법에는 상기 (c)단계를 통하여 브레이싱(30)(40)을 설치한 후,Next, as shown in Figure 2d, after installing the bracing (30) (40) through the step (c) in the earthing method according to the present invention,

상호 인접한 엄지말뚝(20) 사이에 토류판(23)을 장착하는 (c′)단계(S310)를 더 포함되어 이루어진다.
(C') step (S310) of mounting the earth plate 23 between the mutually adjacent thumb pile 20 is further made.

즉 상기 (c′)단계(S310)는 상기 토류판(23)은 상기 오픈 컷이 형성되는 굴착면을 따라 배열되어 상호 인접한 각 엄지말뚝(20)의 플랜지(21) 사이에 삽입하여 상기 각 엄지말뚝(20) 사이에 형성된 지반(G2) 쪽으로 토사가 붕괴하여 유입되는 것을 방지하게 되고,That is, in the step (c′) (S310), the earth plate 23 is arranged along the excavation surface on which the open cut is formed, and is inserted between the flanges 21 of each thumb pile 20 adjacent to each other to each thumb pile. (20) to prevent the soil from entering the soil (G2) formed between the collapse,

또한 상기 토류판(23)은 목재, 강재 시트, 또는 데크 플레이트 등과 같이 다양한 소재를 사용할 수 있으며,In addition, the earth plate 23 may use a variety of materials, such as wood, steel sheet, or deck plate,

이는 굴착 공사가 이루어지는 표토의 성질이나, 토사압 등과 같은 다양한 팩트를 고려하여 선택할 수 있다.
This can be selected in consideration of various factors such as the properties of the topsoil where the excavation work is performed or the soil pressure.

더 나아가 도 3 및 도 4에 도시된 바와 같이 상기 엄지말뚝(20)의 상단부와 하단부에는 상기 오픈 컷의 굴착면을 따라 배열된 각 엄지말뚝(20)과 직교하는 형태로 수평버팀목(25)이 나란히 배열되어 엄지말뚝(20)을 좌우측, 즉 수평방향으로 지지하게 된다.
Furthermore, as illustrated in FIGS. 3 and 4, horizontal shorings 25 are formed at upper and lower portions of the thumb pile 20 in a form orthogonal to each thumb pile 20 arranged along the excavation surface of the open cut. It is arranged side by side to support the thumb pile 20 in the left and right, that is, in the horizontal direction.

한편 도 2e에 도시된 바와 같이 상기 (c)단계(S300)에서 각 브레이싱(30)(40)을 설치하고, 상기(c′)단계(S310)에서 토류판(23)을 설치한 후,Meanwhile, as shown in FIG. 2E, after each bracing 30 and 40 are installed in step (c) (S300), and after installing the earth plate 23 in step (c′) (S310),

상기 오픈 컷(10)의 굴착 시 형성된 경사면(11), 즉 굴착영역(EA)을 외측에서 감싸는 경사면(11)을 복구하기 위한 (c″)단계(S320)가 더 구비된다.
A step (c″) (S320) for restoring the inclined surface 11 formed during excavation of the open cut 10, that is, the inclined surface 11 surrounding the excavation area EA from the outside, is further provided.

상기 (c″)단계(S320)에서 경사면을 복구하는 방식으로는In the (c″) step (S320) to recover the slope

첫째, 도 2e의 (a)에 도시된 바와 같이 경사면에 흙채움하는 방식과First, as shown in (a) of Figure 2e and the method of filling the soil on the slope

둘째, 도 2e의 (b)에 도시된 바와 같이 경사면 상부를 복공판(13)으로 덮어 경사면을 복구하는 방식이 있다.
Second, as shown in FIG. 2E (b), there is a method of restoring the inclined surface by covering the upper portion of the inclined surface with the perforated plate 13.

우선 흙채움을 통한 경사면 복구방식은 상기 오픈 컷(10)의 외측 경사면(11)과, 흙막이 구조(PW)의 외벽면 즉, 상기 각 엄지말뚝(20)에 토류판(23)이 장착된 벽면 사이에 토사를 채운 후,First, the method of restoring the inclined surface through the filling of the soil is between the outer inclined surface 11 of the open cut 10 and the outer wall surface of the mudguard structure PW, that is, the wall surface on which the earth plate 23 is mounted on each of the thumb piles 20. After filling the earth and sand,

채워진 토사를 일정한 압력으로 다져 지면(G1)과 흙막이 구조(PW)의 상단부와 수평을 이룰 수 있도록 복구영역(R)을 형성하게 된다.
The filled earth is compacted at a constant pressure to form a recovery area R so as to be level with the top of the ground G1 and the retaining structure PW.

다음으로 복공판에 의한 경사면 복구방식은 상기 엄지말뚝(20) 상면부와 경사면(11)이 시작되는 상단 부분에 복공판(13)을 설치하게 되며,Next, the method of restoring the inclined surface by the perforated plate is to install the perforated plate 13 in the upper portion where the upper surface of the thumb pile 20 and the inclined surface 11 are started.

이 경우 상기 복공판(13)은 지면(G1)과 수평하게 설치되어야 하는데,In this case, the perforated plate 13 should be installed horizontally with the ground (G1),

이는 굴착 작업을 위한 장비가 근접하여 작업을 하는 경우 복공판(13)에 의한 턱이 형성되지 않도록 하여 작업에 방해되는 요소를 미연에 제거하기 위함이다.
This is to remove the elements that interfere with the work by preventing the jaws formed by the perforated plate 13 when the equipment for excavation work in close proximity.

또한 흙막이 구조(PW) 내측의 굴착영역(EA)을 굴착하는 경우 상기 오픈 컷(10)의 경사면(11)이 복구되지 않는다면 흙막이 구조(PW) 둘레에 존재하는 경사면(11)이 굴착 작업을 위한 장비나 작업자 등의 근접 작업을 어렵게 하는 장애물이 될 수 있으며,In addition, when excavating the excavation area EA inside the retaining structure PW, if the inclined surface 11 of the open cut 10 is not restored, the inclined surface 11 around the retaining structure PW is used for excavation work. It can be an obstacle that makes it difficult to work close to equipment or workers.

이에 의하여 굴착 작업을 원활히 할 수 없다는 문제가 야기될 수 있다.
This may cause a problem that the excavation work cannot be smoothly performed.

따라서 상기 (c)단계(S300)에서 흙막이 구조(PW)를 축조하고, 상기 (c″)단계(S310)에서 토류판(23)을 설치한 다음Therefore, in the step (c) (S300) to construct the earth retaining structure (PW), the (c″) step (S310) to install the earth plate 23, and then

상기 (c″)단계에서 경사면(11)을 채워, 지면(G1)과 수평을 이루는 복구영역(R)을 형성하여 굴착 작업을 위한 장비나 작업자 등의 접근성을 확보하여 작업 편의성 및 안정성을 보장할 수 있도록 하는 것이 바람직하다.
In step (c″), filling the inclined surface 11, forming a recovery area (R) parallel to the ground (G1) to ensure accessibility of equipment or workers for excavation work to ensure work convenience and stability It is desirable to be able to.

그리고 상기 (c″)단계(S320)에서의 경사면 복구방식은 상기 경사면(11)의 상부, 즉 상기 복공판(13)이 상기 엄지말뚝(20)과 상기 경사면(11)의 최상부에 걸치어 얹히고,And in the (c″) step (S320), the recovery method of the inclined surface is placed on the upper portion of the inclined surface 11, that is, the perforated plate 13 is placed on the top of the thumb pile 20 and the inclined surface 11, ,

이 경우 상기 복공판(13)은 상기 지면(G1)과 수평하게 설치하여 굴착 작업을 위한 장비나 작업자들의 접근 용이성 및 작업 편의성을 보장하게 된다.
In this case, the perforated plate 13 is installed horizontally with the ground G1 to ensure accessibility and work convenience of equipment or workers for excavation work.

또한 상기 복공판(13)에 의하여 경사면(11)을 복구하는 경우에는 상부에 위치하는 수평브레이싱(30)을 설치하지 않고, 상기 복공판(13)이 수평브레이싱(30) 역할을 대신하거나,In addition, when the inclined surface 11 is restored by the perforated plate 13, the horizontal bracing 30 located at the upper portion is not installed, and the perforated plate 13 replaces the role of the horizontal bracing 30,

또는 첨부된 도면에는 도시되지 않았지만 상부에 위치하는 수평브레이싱을 설치한 상태에서 복구되어야할 경사면에 인접한 엄지말뚝에만 복공판을 설치하는 것이 가능하다.
Alternatively, although not shown in the accompanying drawings, it is possible to install the perforated plate only on the thumb pile adjacent to the inclined surface to be restored in a state where the horizontal bracing located at the top is installed.

도 1 내지 도 2f에 도시된 바와 같이 본 발명에 따른 브레이싱을 이용한 자립식 흙막이 공법에서, 상기 (d)단계(S400)는As shown in Figures 1 to 2f, in the self-supporting earthing method using the bracing according to the present invention, the step (d) (S400) is

상기 (a) 내지 (c)단계(S300)를 거쳐 자립식 흙막이 구조(PW)가 축조된 후, 흙막이 구조(PW) 내측에 위치하는 굴착영역(EA)을 굴착하여 기초부(BA)를 형성하기 위한 단계이다.
After the steps (a) to (c) (S300), after the self-supporting earth retaining structure (PW) is built, the excavation area (EA) located inside the earth retaining structure (PW) is excavated to form the base (BA). It is a step to do.

본 발명에 따른 (d)단계(S400)는 상기 엄지말뚝(20), 수평브레이싱(30) 및 경사브레이싱(40)에 의하여 형성된 흙막이 구조(PW)에 의하여 부재력과 변위를 종래의 공법에 비하여 현저히 낮추어 줌으로써 동일한 지반 조건과 하중을 적용하는 경우에도 부재 자체의 안전성과 경제성을 확보하는 것이 가능하고,In step (d) (S400) according to the present invention, the member force and displacement are significantly compared to the conventional method by the retaining structure (PW) formed by the thumb pile (20), horizontal bracing (30) and inclined bracing (40). By lowering it, it is possible to secure the safety and economy of the member itself even when applying the same ground conditions and loads,

아울러 굴착영역(EA)의 굴착하여 기초부(BA)를 형성하는 경우에도 기초부(BA)의 심도를 더욱 깊게 하는 것이 가능하게 된다.
In addition, even when the foundation portion BA is formed by excavation of the excavation region EA, it is possible to further deepen the depth of the foundation portion BA.

이상에서 첨부된 도면을 참조하여 본 발명인 브레이싱을 이용한 자립식 흙막이 공법을 설명함에 있어 특정 형상 및 방향을 위주로 설명하였으나, 본 발명은 당업자에 의하여 다양한 변형 및 변경이 가능하고, 이러한 변형 및 변경은 본 발명의 권리범위에 포함되는 것으로 해석되어야 한다.
In the above, specific shapes and directions have been mainly described in the description of the self-supporting retaining method using the inventor's bracing with reference to the accompanying drawings, but the present invention can be modified and changed in various ways by those skilled in the art. It should be interpreted as being included in the scope of the invention.

10 : 오픈 컷 11 : 경사면
13 : 복공판
20 : 엄지말뚝 21 : 플랜지
23 : 토류판 25 : 수평버팀목
30 : 수평브레이싱
40 : 경사브레이싱
EA : 굴착영역 BA : 기초부
PW : 흙막이 구조 G1 : 지면
G2 : 지반 R : 복구영역
S100 : (a)단계 S200 : (b)단계
S300 : (c)단계 S310 : (c′)단계
S320 : (c″)단계 S400 : (d)단계
10: open cut 11: slope
13: double-edged board
20: thumb pile 21: flange
23: earth plate 25: horizontal support
30: horizontal bracing
40: inclined bracing
EA: Excavation area BA: Foundation
PW: Earthing structure G1: Ground
G2: Ground R: Recovery area
S100: (a) step S200: (b) step
S300: (c) step S310: (c′) step
S320: (c″) step S400: (d) step

Claims (4)

(a) 굴착영역의 둘레를 굴착하여 경사면을 갖는 오픈 컷을 형성하는 단계;
(b) 상기 오픈 컷에 의하여 형성된 지반의 양측을 따라 복수의 엄지말뚝을 근입시키는 단계;
(c) 상기 엄지말뚝과 수평 또는 경사브레이싱(bracing), 또는 이들 모두를 상호간에 연결하는 단계; 및
(d) 상기 굴착영역을 굴착하여 기초부를 형성하는 단계;를 포함하여 이루어지고,

상기 (c)단계에는 상기 오픈 컷이 되어 있는 굴착면을 따라 상호 인접한 엄지말뚝 사이에 토류판을 장착하는 (c′)단계가 더 포함되며,

상기 (c)단계에는 상기 오픈 컷의 굴착 시, 흙막이 구조의 외측에 형성된 경사면에 흙채움을 하거나, 또는 상기 경사면의 상부를 복공판으로 덮어 경사면을 복구하는 (c″)단계가 더 포함되어 있는 것을 특징으로 하는 브레이싱을 이용한 자립식 흙막이 공법.
(a) excavating the circumference of the excavation area to form an open cut having an inclined surface;
(B) step of rooting a plurality of thumb piles along both sides of the ground formed by the open cut;
(c) connecting the thumb pile with horizontal or inclined bracing, or both of them; And
(d) excavating the excavation area to form a foundation;

The step (c) further includes the step (c′) of mounting the earth plate between the thumb piles adjacent to each other along the excavation surface which is the open cut,

In the step (c), when the open cut is excavated, the step (c″) of further filling the soil on an inclined surface formed on the outside of the mudguard structure or covering the upper portion of the inclined surface with a perforated plate to restore the inclined surface is further included. A self-supporting earth retaining method using bracing.
제 1 항에 있어서,
상기 경사브레이싱은 상호 엇갈려 배열된 트러스(truss)인 것을 특징으로 브레이싱을 이용한 자립식 흙막이 공법.
According to claim 1,
The inclined bracing is a self-supporting earth retaining method using bracing, characterized in that the truss (truss) arranged in a mutually staggered.
제 1 항에 있어서,
상기 오픈 컷이 되어 있는 굴착면을 따라 배열된 각 엄지말뚝에 직교하는 형태로 연결되는 수평버팀목이 더 구비되어 있는 것을 특징으로 하는 브레이싱을 이용한 자립식 흙막이 공법.
According to claim 1,
A self-supporting earthing method using bracing, characterized in that a horizontal support is connected to each thumb pile arranged along the excavation surface of the open cut orthogonally.
삭제delete
KR1020100050593A 2010-05-28 2010-05-28 Method of land-side protection wall using bracing Active KR101218825B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100050593A KR101218825B1 (en) 2010-05-28 2010-05-28 Method of land-side protection wall using bracing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100050593A KR101218825B1 (en) 2010-05-28 2010-05-28 Method of land-side protection wall using bracing

Publications (2)

Publication Number Publication Date
KR20110131000A KR20110131000A (en) 2011-12-06
KR101218825B1 true KR101218825B1 (en) 2013-01-07

Family

ID=45499600

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100050593A Active KR101218825B1 (en) 2010-05-28 2010-05-28 Method of land-side protection wall using bracing

Country Status (1)

Country Link
KR (1) KR101218825B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102260481B1 (en) 2020-05-27 2021-06-04 한국콘크리트산업 주식회사 Bracing structure for soil sheathing and wall construction method using the same

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105756068B (en) * 2016-04-06 2018-02-02 中国十七冶集团有限公司 A kind of Large Scale Deep Foundation Pit Support anchor tube beats pipe construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002227204A (en) * 2001-01-29 2002-08-14 Maeda Corp Earth retaining method of excavation section

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002227204A (en) * 2001-01-29 2002-08-14 Maeda Corp Earth retaining method of excavation section

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102260481B1 (en) 2020-05-27 2021-06-04 한국콘크리트산업 주식회사 Bracing structure for soil sheathing and wall construction method using the same

Also Published As

Publication number Publication date
KR20110131000A (en) 2011-12-06

Similar Documents

Publication Publication Date Title
CN100564700C (en) The job practices of lattice type steel column tower crane pedestal
KR100855098B1 (en) End vertical truss type brace structure and construction method using the same
KR102234513B1 (en) Block type reinforcement retaining wall structure and constructing method for the same
KR20120115705A (en) Soil retaining structure using two rows pile
KR101262357B1 (en) Inclined Earth Retaining Structure Method
KR100633796B1 (en) Central Reinforced Connection Structure of Temporary Temporary Construction
JP4979789B2 (en) Construction method of stair-permeable permeable retaining fence
JP2016528406A (en) Beam connection structure of temporary retaining works for earth retaining
KR100789209B1 (en) Block construction using synthetic piles and beams
KR101061516B1 (en) Temporary wall structure using arched steel pile
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
KR101218825B1 (en) Method of land-side protection wall using bracing
JP6826820B2 (en) Insertion pile type retaining wall
KR100831332B1 (en) Underground wall for civil engineering and construction method
JP2012026250A (en) Reinforcement structure and reinforcement method of existing retaining wall
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
JP4108456B2 (en) Civil engineering structure with planting part and its construction method
KR200492883Y1 (en) Braced wall
JP2003268770A (en) Earth retaining construction method and reinforcing structure of sheet pile used for this construction method
KR102194381B1 (en) Pile for Earth self-retaining wall using double I beam
KR102195496B1 (en) Pile for earth self-retaining wall using cast in place concrete pile with double I beam
JP4666674B2 (en) Wall structure with filling material
KR100995503B1 (en) Two-row thumb pile earth block structure with work path and earth block construction method
KR101256311B1 (en) Structual deepening method
KR102617795B1 (en) Retaining wall system combine H-piles with steel reinforcement structure

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20100528

PA0201 Request for examination
PG1501 Laying open of application
E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20120529

Patent event code: PE09021S01D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20121106

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20121228

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20121231

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
FPAY Annual fee payment

Payment date: 20151126

Year of fee payment: 4

PR1001 Payment of annual fee

Payment date: 20151126

Start annual number: 4

End annual number: 4

FPAY Annual fee payment

Payment date: 20161130

Year of fee payment: 5

PR1001 Payment of annual fee

Payment date: 20161130

Start annual number: 5

End annual number: 5

FPAY Annual fee payment

Payment date: 20171212

Year of fee payment: 6

PR1001 Payment of annual fee

Payment date: 20171212

Start annual number: 6

End annual number: 6

FPAY Annual fee payment

Payment date: 20191231

Year of fee payment: 8

PR1001 Payment of annual fee

Payment date: 20191231

Start annual number: 8

End annual number: 8

PR1001 Payment of annual fee

Payment date: 20201209

Start annual number: 9

End annual number: 9

PR1001 Payment of annual fee

Payment date: 20241021

Start annual number: 13

End annual number: 13