KR100443809B1 - Fabricated arch tunnel and construction method thereof - Google Patents

Fabricated arch tunnel and construction method thereof Download PDF

Info

Publication number
KR100443809B1
KR100443809B1 KR10-2002-0050278A KR20020050278A KR100443809B1 KR 100443809 B1 KR100443809 B1 KR 100443809B1 KR 20020050278 A KR20020050278 A KR 20020050278A KR 100443809 B1 KR100443809 B1 KR 100443809B1
Authority
KR
South Korea
Prior art keywords
unit
wall members
bolt
tunnel
right wall
Prior art date
Application number
KR10-2002-0050278A
Other languages
Korean (ko)
Other versions
KR20040018002A (en
Inventor
김달환
Original Assignee
주식회사 우일 이알에스
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 우일 이알에스 filed Critical 주식회사 우일 이알에스
Priority to KR10-2002-0050278A priority Critical patent/KR100443809B1/en
Publication of KR20040018002A publication Critical patent/KR20040018002A/en
Application granted granted Critical
Publication of KR100443809B1 publication Critical patent/KR100443809B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2450/00Gaskets
    • E02D2450/10Membranes
    • E02D2450/105Membranes impermeable
    • E02D2450/106Membranes impermeable for liquids
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명의 단위 부재를 이용한 조립식 아치 터널의 시공방법은, 미리 분할하여 성형제작된 것으로서, 밑면부(11a,120a)와 곡면부(110b,120b)로 구성된 단위 좌,우측벽부재(110, 120)와, 그 단위 좌,우측벽부재의 곡면에 연장되어 전체적으로 하나의 아치면을 형성할 수 있는 곡면 몸체로 구성된 단위 천정부재(130)를 이용하여 조립식 아치 터널을 시공함에 있어서, 터널 시공 대상의 현장의 지면을 다짐하고 정리한 후 기초 콘크리트층(100)을 형성하는 단계; 기초 콘크리트층의 상면 에 상기 단위 좌,우측벽부재(110,120)의 안착을 위한 고정대(220)를 설치하는 단계; 고정대 위에 상기 단위 좌,우측벽부재를 안착, 설치하는 단계; 단위 좌,우측벽부재 위에 상기 단위 천정부재를 설치하면서 종방향 결합수단을 이용하여 고정시켜 단위 아치터널을 형성시키는 단계; 단위 좌,우측벽부재와 단위 천정부재로 구성된 단위 아치터널의 일측 또는 양측에 연결설치되는 또 다른 단위 아치 터널간에 횡방향 결합수단을 이용하여 고정설치하는 단계; 및 단위 좌,우측벽부재와 단위 천정부재로 이루어지는 단위 아치 터널 구조체를 동일한 방식으로 반복 조립하여 터널의 길이방향으로 연장하여 축조하는 단계를 포함한다.The construction method of the prefabricated arch tunnel using the unit member of the present invention is formed by dividing in advance, the unit left and right side wall member 110, 120 consisting of the bottom portion (11a, 120a) and the curved portion (110b, 120b) In the construction of the prefabricated arch tunnel using the unit ceiling member 130 composed of a curved body which extends to the curved surfaces of the unit left and right wall members and can form an arch surface as a whole, Forming a foundation concrete layer 100 after pruning and arranging the ground of the site; Installing a fixing unit 220 for mounting the unit left and right wall members 110 and 120 on an upper surface of the foundation concrete layer; Mounting and installing the unit left and right wall members on a fixture; Installing the unit ceiling members on the unit left and right wall members to fix the unit arch tunnel by using a longitudinal coupling means; Fixing by using a transverse coupling means between another unit arch tunnel connected to one side or both sides of the unit arch tunnel including the unit left and right wall members and the unit ceiling member; And repeating assembling the unit arch tunnel structure including the unit left and right wall members and the unit ceiling member in the same manner to extend the longitudinal direction of the tunnel.

이와 같은 본 발명에 의하면, 아치 형상을 갖는 몇 개의 부품으로 분할 제작된 각 콘크리트 구조물을 현장에 이송하여 조립한 후, 각 결합수단에 의하여 형성된 체결부에는 발포 우레탄(200) 또는 무수축 몰탈(223)등으로 채우고 모든 이음부를 방수시트(240)로 외벽 마감처리함으로써 하나의 조립식 아치 터널이 완성되므로, 터널 시공에 소요되는 기간을 대폭 감축할 수 있고, 분할 제작된 각 콘크리트 구조물은 이미 제작 단계에서 공장내의 철저한 품질검사를 거치게 되므로, 완성된 콘크리트 구조물의 품질면에서 우수한 신뢰도를 얻을 수 있으며 갱구부 경관이 수려한 터널을 축조할 수 있다.According to the present invention, after transporting and assembling each concrete structure divided into several parts having an arch shape in the field, the fastening portion formed by each coupling means is urethane foam 200 or non-shrink mortar 223 By filling the outer wall with the waterproof sheet 240 and finishing all the prefabricated arch tunnels, it is possible to drastically reduce the time required for the construction of the tunnel. Since the factory undergoes a thorough quality inspection, it is possible to obtain excellent reliability in terms of the quality of the finished concrete structure and to build a tunnel with a beautiful view of the shaft.

Description

단위 부재를 이용한 조립식 아치 터널 및 그 시공방법{Fabricated arch tunnel and construction method thereof}Fabricated arch tunnel and construction method using unit member

본 발명은 단위 부재를 이용한 조립식 아치 터널 및 그 시공방법에 관한 것으로서, 특히 아치 터널 구축을 위한 특정 형태의 콘크리트 구조물을 미리 공장에서 몇 개의 분할 구조물로 제작하고 현장에 이송하여 조립한 후 이음부위를 마감처리함으로써 신속한 시공이 가능하고, 경제적이며, 경관이 미려한 조립식 아치 터널 및 그 시공방법에 관한 것이다.The present invention relates to a prefabricated arch tunnel using a unit member and a construction method thereof, and in particular, a concrete structure of a specific type for building an arch tunnel is manufactured in advance in a few divided structures in a factory and transported to a site before assembling a joint part. The present invention relates to a prefabricated arch tunnel and its construction method which can be quickly constructed by finishing, economical and beautiful in landscape.

일반적으로, 아치 구조는 오래전서부터 토목 구조물이나 건축물 등에 많이사용 되어오던 하나의 구조 양식으로서 소규모의 교량이나 성곽, 기타 주거 공간 등에 폭넓게 활용되고 있다.In general, arch structure is a structural form that has been widely used in civil engineering structures and buildings for a long time, and is widely used in small bridges, castles, and other residential spaces.

이와 같은 아치 구조는 외부 토압이나 통과 하중에 대해 응력분산이 용이한 구조이기 때문에 동일 응력 조건하에서는 여타 단면 형상일 때보다 콘크리트 단면을 얇게 할 수 있다. 따라서, 경제적이며, 특히 주변 경관과 조화를 이룰 수 있어 심리적으로 편안한 정서를 제공함에도 불구하고 공사현장에서는 여전히 구형(박스형) 구조를 현장 타설 콘크리트 방식으로 하는 재래식 공법에 의존하는 경우가 많다.Since the arch structure is easy to distribute stress against external earth pressure or through load, the concrete cross section can be made thinner than other cross-sectional shapes under the same stress condition. Therefore, in spite of being economical, especially in harmony with the surrounding landscape, and providing psychologically comfortable emotions, construction sites still rely on conventional construction methods using spherical (box-type) structures in the form of cast-in-place concrete.

재래식 공법에 의하면, 건설 현장에서 동바리, 거푸집을 설치하고, 철근을 가공 조립한 후, 콘크리트를 타설하여 양생하고, 거푸집을 해체하는 방식이므로, 현장에서 공사의 종류별로 많은 인원이 투입되고, 콘크리트를 바닥, 벽체, 슬래브 등 3단계로 구분하여 타설하므로 장기간이 소요되며, 슬래브의 침강 균열을 방지하기 어렵고, 구조적으로 동일 응력이 가해지는 조건하에서는 콘크리트의 두께가 두꺼워지므로 구체중량이 증가되어 지반 침하에 대해 안전성이 떨어질 뿐 아니라, 콘크리트의 세심한 품질관리가 요구된다. 또한, 지보공 설치에 충분한 주의가 필요하고, 많은 숙련공이 요구되며, 갱구부(터널 출입구)에는 삼각형 모양의 날개벽이 설치되므로, 경관을 훼손하는 문제가 있다.According to the conventional construction method, since the construction site installs round bars and formwork, processes and assembles reinforcing bars, pours concrete, cures it, and dismantles the form, a large number of people are added to the construction site. Since it is divided into three stages such as floor, wall, and slab, it takes a long time, and it is difficult to prevent sedimentation cracking of the slab, and the concrete thickness becomes thick under the condition that structurally equal stress is applied. In addition to poor safety, careful quality control of concrete is required. In addition, sufficient support is required for the installation of the jibo, many skilled workers are required, and since the triangular wing wall is installed in the shaft portion (tunnel entrance), there is a problem of damaging the landscape.

특히, 대단면 콘크리트 타설시의 수화열에 의한 균열, 침강균열 등은 불량 시공의 대표적인 사례로 지적되어 그 균열보수에 많은 비용이 추가로 투입되고, 지보공 설치시 부주의로 인한 구조물의 붕괴로 인명사고가 종종 발생되며, 콘트리트의 양생 완료까지는 구조물 주변의 성토다짐 작업을 할 수가 없어 공사기간이 장기화되고, 차량 통행 제한 등 통행상의 불편을 야기하여 민원의 대상이 되는 등 많은 문제점이 대두되고 있다.In particular, cracks due to heat of hydration and sedimentation cracks during large section concrete casting are pointed out as a representative case of poor construction, and a lot of cost is added to repairing cracks. It often occurs, and the construction of the concrete can not be done until the completion of curing of the concrete, and the construction period is prolonged, causing inconveniences in traffic, such as restriction of traffic, and becoming a target of civil complaints.

본 발명은 이상과 같은 사항을 감안하여 창출된 것으로서, 아치 터널 구축을 위한 특정 형태의 콘크리트 구조물을 미리 공장에서 몇 개의 분할 구조물로 제작하고 현장에 이송하여 조립한 후 이음부위를 마감처리함으로써 신속한 시공이 가능하고, 경제적이며, 경관이 미려한 단위 부재를 이용한 조립식 아치 터널 및 그 시공방법을 제공함에 그 목적이 있다.The present invention has been made in view of the above-mentioned matters, the concrete structure of a specific form for the construction of the arch tunnel in advance in the factory to produce a few divided structures and transported to the site after assembling the joint construction to finish quickly It is an object of the present invention to provide a prefabricated arch tunnel and a construction method using a unit member capable of economical and beautiful landscape.

도 1은 본 발명에 따른 조립식 아치 터널의 정면 사시도.1 is a front perspective view of a prefabricated arch tunnel according to the present invention.

도 2는 본 발명에 따른 조립식 아치 터널의 정단면도.Figure 2 is a front sectional view of the prefabricated arch tunnel according to the present invention.

도 3은 본 발명에 따른 조립식 아치 터널에 있어서, 단위 좌,우측벽부재와 단위 천정부재들간의 연결 이음부 및 방수 마감처리 상태를 보여주는 도면.FIG. 3 is a view illustrating a connection seam between a unit left and a right wall member and a unit ceiling member and a waterproof finish in a prefabricated arch tunnel according to the present invention.

도 4는 본 발명에 따른 조립식 아치 터널의 단위 좌,우측벽부재와 단위 천정부재간의 맞이음부에 마련되어 있는 요철결합부의 구조를 보여주는 도면.Figure 4 is a view showing the structure of the concave-convex coupling portion provided in the fitting portion between the unit left, right wall member and the unit ceiling member of the prefabricated arch tunnel according to the present invention.

도 5는 본 발명에 따른 조립식 아치 터널의 단위 좌,우측벽부재와 단위 천정부재간의 종방향 체결부에만 마련되어 있는 볼트/너트 체결부의 구조를 보여주는 도면.5 is a view showing the structure of the bolt / nut fastening portion provided only in the longitudinal fastening portion between the unit left, right wall member and the unit ceiling member of the prefabricated arch tunnel according to the present invention.

도 6은 본 발명에 따른 조립식 아치 터널의 측면도.6 is a side view of a prefabricated arch tunnel according to the present invention.

도 7은 본 발명에 따른 조립식 아치 터널에 있어서, 단위 아치 터널간의 횡방향 체결부에 만 마련되어 있는 결합수단을 보여주는 평면도.7 is a plan view showing a coupling means provided only in the transverse fastening portion between the unit arch tunnel in the prefabricated arch tunnel according to the present invention.

도 8은 도 7의 결합수단을 보여주는 단면도.8 is a cross-sectional view showing a coupling means of FIG.

도 9는 본 발명에 따른 조립식 아치 터널의 시공방법에 따라 기초 콘크리트층 위에 단위 좌,우측벽부재의 안착을 위한 고정대를 설치한 상태를 보여주는 도면.Figure 9 is a view showing a state in which the mounting bracket for the mounting of the unit left, right wall member on the foundation concrete layer according to the construction method of the prefabricated arch tunnel according to the present invention.

도 10은 본 발명에 따른 조립식 아치 터널의 시공방법에 따라 단위 좌,우측벽부재를 인양수단에 의해 인양하여 기초 콘크리트층에 설치된 고정대 위의 정해진 위치에 설치하는 과정을 보여주는 도면.10 is a view showing a process of installing the left and right side wall member by the lifting means in accordance with the construction method of the prefabricated arch tunnel according to the present invention installed in a predetermined position on the fixed base installed in the foundation concrete layer.

도 11은 본 발명에 따른 조립식 아치 터널의 시공방법에 따라 단위 천정부재를 인양수단에 의해 인양하여 단위 좌,우측벽부재 위에 거치하는 과정을 보여주는 도면.FIG. 11 is a view showing a process of mounting a unit ceiling member on a unit left and right side wall member by a lifting means according to a construction method of a prefabricated arch tunnel according to the present invention. FIG.

도 12는 본 발명에 따른 조립식 아치 터널의 시공방법에 따라 단위 좌,우측벽부재와 단위 천정부재를 조립 완성한 상태를 보여주는 도면.12 is a view showing a state of assembling the unit left, right wall member and the unit ceiling member according to the construction method of the prefabricated arch tunnel according to the present invention.

도 13은 본 발명에 따른 좌우측벽 부재와 바닥콘크리트층과의 철근 이음을 보여주는 도면.13 is a view showing a reinforcing bar between the left and right side wall member and the bottom concrete layer according to the present invention.

도 14는 본 발명에 따른 조립식 아치 터널의 시공방법에 따라 조립 완성된 아치 터널의 양측면에 채움토에 의한 성토 다짐작업을 보여주는 도면.14 is a view showing the filling compaction by the filling soil on both sides of the assembled arch tunnel according to the construction method of the prefabricated arch tunnel according to the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

100...기초 콘크리트층 102...바닥 콘크리트층100 ... Foundation Concrete Floor 102 ... Floor Concrete Floor

104...아스팔트층 110...단위 좌측벽부재104 ... asphalt layer 110 ... unit left wall member

120...단위 우측벽부재 130...단위 천정부재120 ... unit right wall member 130 ... unit ceiling member

110a,120a...밑면부 110b,120b...곡면부110a, 120a ... Bottom section 110b, 120b ... Curved section

110c...종방향 볼트/너트 체결부 120c...맞이음 요철결합부110c ... longitudinal bolt / nut coupling 120c ...

120d...볼트/너트 체결홈 120e...탄성와샤120d ... bolt / nut tightening groove 120e ... elastic washer

120f...볼트너트 체결구 140...연결금구120f ... Bolt nut fastener 140 ... Connection bracket

150...볼트/너트 체결구 151...횡방향 볼트/너트 체결부150 ... Bolt / Nut Fasteners 151 ... Horizontal Bolt / Nut Fasteners

160...철근 연결구 170...볼트/너트 체결홈160 ... rebar connector 170 ... bolt / nut tightening groove

200...발포우레탄 210...탄성씰링재200 ... Polyurethane 210 ... Elastic sealing material

220...고정대 221...앵커 볼트220 ... fixture 221 ... anchor bolt

222...H형강(또는 I형강) 223...무수축 몰탈222 ... H section steel (or I section steel) 223 ... non-shrink mortar

225...부몰탈 224...앵커볼트 삽입구225 ... Boot mortar 224 ... Anchor bolt insertion hole

230...인양수단 231...경사지반230 ... lifting means 231 ... sloped ground

240...방수시트240 ... waterproof sheet

상기의 목적을 달성하기 위하여 본 발명에 따른 단위 부재를 이용한 조립식 아치 터널은, 사전에 각각 분할 제작되어 현장으로 이송된 후, 조립에 의해 하나의 아치 터널을 구축하게 되는 것으로서,In order to achieve the above object, the prefabricated arch tunnel using the unit member according to the present invention is to be divided into pre-fabricated and transported to the site, and then to build an arch tunnel by assembly,

터널 시공 현장의 기초 콘크리트층(100)의 좌,우측 단부에 설치된 고정대의 상면에 설치되는 것으로, 고정대 위에 안착될 수 있는 밑면부(110a, 120a)와 그 밑면부에 대해 대략 L자 형의 일체로 형성되되, 내향으로의 소정 곡률을 가지는 곡면부(110b,120b)와 그 상단부 및 측단부에는 이웃하는 타부재와의 조립식 결합을 위한 결합수단(110c,151)이 각각 마련되어 있으며, 그 상단부에는 단위천정부재(130)와의 결합을 위한 맞물림 요철결합부(120c)가 형성되어 있는 단위 좌,우측벽부재(110,120); 및It is installed on the upper surface of the fixing stand installed at the left and right ends of the foundation concrete layer 100 of the tunnel construction site, and has an approximately L shape with respect to the bottom parts 110a and 120a that can be seated on the fixing stand and the bottom part thereof. Is formed in, but the curved portion (110b, 120b) having a predetermined curvature inward and the coupling means (110c, 151) for the prefabricated coupling with other neighboring members are provided at the upper end and the side end, respectively, the upper end Unit left and right wall members 110 and 120 having an engagement concave-convex coupling part 120c for coupling with the unit ceiling member 130; And

상기 단위 좌,우측벽부재의 각 상단부에 그 양측 하단부가 각각 얹히어 조립식으로 결합되는 것으로, 상기 단위 좌,우측벽부재의 곡면에 연장되어 전체적으로 하나의 아치면을 형성할 수 있는 곡면 몸체로 구성되며, 그 몸체의 하단부에는 상기 단위 좌,우측벽부재(110,120)의 각 상단부에 마련되어 있는 볼트/너트 체결수단(110c) 및 맞물림 요철결합부(120c)에 대응하는 조립식 결합수단과 맞물림 요철결합부가 각각 마련되고, 몸체의 측면부에는 이웃하는 타부재와의 조립식 결합을 위한 결합수단(151)이 마련되어 있는 단위 천정부재(130)를 포함하여 구성된 점에 그 특징이 있다.The upper and lower ends of both sides of the unit left and right wall members are respectively assembled on the upper ends of the unit, and the curved body may extend to the curved surfaces of the unit left and right wall members to form a single arch surface as a whole. At the lower end of the body, prefabricated coupling means and engagement coupling parts corresponding to the bolt / nut fastening means 110c and the engagement concave-convex coupling part 120c provided at each upper end of the unit left and right wall members 110 and 120 are provided. Each side is provided, and the side portion of the body is characterized in that it comprises a unit ceiling member 130 is provided with a coupling means 151 for prefabricated coupling with other neighboring members.

또한, 상기의 목적을 달성하기 위하여 본 발명에 따른 조립식 아치 터널의 시공방법은, 기초 콘크리트(100) 타설면 위에 설치되어 그 상부에 단위 좌,우측벽부재(110,120)를 정위치에 고정설치하기 위한 고정대(220)와, 미리 분할하여 성형제작된 것으로서, 콘크리트 바닥면에 안착될 수 있는 밑면부(110a,120a)와 그 밑면부에 대해 대략 L자 형의 일체로 형성되되, 내향으로의 소정 곡률을 가지는 곡면부(110b,120b)와 그 상단부 및 측단부에는 이웃하는 타부재와의 조립식 결합을 위한 결합수단(110c,151)과 맞물림 요철결합부(120c)가 각각 마련되어 있는 단위 좌,우측벽부재(110,120)와, 그 단위 좌,우측벽부재의 곡면에 연장되어 전체적으로 하나의 아치면을 형성할 수 있는 곡면 몸체로 구성되며, 그 몸체의 양측 하단부에는 상기 단위 좌,우측벽부재의 각 상단부에 마련되어 있는 결합수단(110c)에 대응하는 조립식 결합수단과 맞물림 요철결합부(120c)가 각각 마련되고, 몸체의 측면부에는 이웃하는 타부재와의 조립식 결합을 위한 결합수단(151)이 마련되어 있는 단위 천정부재(130)를 이용하여 조립식 아치 터널을 시공함에 있어서,In addition, the construction method of the prefabricated arch tunnel according to the present invention in order to achieve the above object, is installed on the foundation concrete 100, the placing surface fixed to the unit left, right side wall members (110, 120) installed in the upper position For the fixing portion 220, and pre-divided and molded, the bottom portion (110a, 120a) that can be seated on the concrete floor and the bottom portion is formed integrally of approximately L-shaped, inwardly predetermined Units left and right having curvatures 110b and 120b, and coupling means 110c and 151 and engagement concave and convex coupling portions 120c for prefabricated coupling with neighboring other members, respectively, on upper and side ends thereof. It consists of a wall member (110, 120) and a curved body extending to the curved surface of the unit left, right wall member to form a single arch surface as a whole, the lower end of the body on each side of the unit left, right wall member At the top Unit prefabricated coupling means corresponding to the coupling means (110c) and the engagement concave-convex coupling portion (120c) is provided, respectively, the unit ceiling is provided with a coupling means (151) for the prefabricated coupling with the neighboring other members on the side of the body In constructing the prefabricated arch tunnel using the member 130,

(a) 터널 시공 대상의 현장의 지면을 다지고 정리한 후 기초 콘크리트층(100)을 형성하는 단계;(a) forming a foundation concrete layer 100 after compacting and arranging the ground of the site of the tunnel construction target;

(b) 상기 기초 콘크리트층(100)의 상면 양단에, 상기 단위 좌,우측벽부재(110,120)의 안착을 위한 고정대(220)를 설치하는 단계;(b) installing fixing rods 220 for mounting the left and right wall members 110 and 120 at both ends of the upper surface of the foundation concrete layer 100;

(c) 상기 고정대 위에 상기 단위 좌,우측벽부재를 안착, 설치하는 단계;(c) mounting and installing the unit left and right wall members on the fixing base;

(d) 상기 단위 좌,우측벽부재 위에 상기 단위 천정부재(130)를 설치하는 단계; 및(d) installing the unit ceiling member 130 on the unit left and right wall members; And

(e) 상기 단위 좌,우측벽부재(110,120)와 단위 천정부재(130)로 이루어지는 단위 아치 터널 구조체를 동일한 방식으로 반복 조립하여 터널의 길이방향으로 연장하여 축조하는 단계를 포함하는 점에 그 특징이 있다.(e) repeating assembling the unit arch tunnel structure consisting of the unit left and right wall members 110 and 120 and the unit ceiling member 130 in the same manner to extend and build in the longitudinal direction of the tunnel. There is this.

더 나아가, 상기 기초 콘크리트층(100) 위에 바닥 콘크리트층(102)을 형성하고, 그 위에 아스팔트(104)를 포장하는 단계를 더 포함한다.Furthermore, the method further includes forming a bottom concrete layer 102 on the foundation concrete layer 100 and paving the asphalt 104 thereon.

또한, 상기 아치 터널 구조체의 길이방향으로의 연장 축조가 완료된 후, 터널 구조체의 좌우측 공간에 토사를 메꾸어 넣고 성토 다짐하는 단계를 더 포함한다.In addition, after completion of the extension in the longitudinal direction of the arch tunnel structure, and filling the soil in the left and right spaces of the tunnel structure further comprising the step of filling.

이하 첨부된 도면을 참조하면서 본 발명의 실시예를 상세히 설명한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 도 3은 본 발명에 따른 조립식 아치 터널을 나타낸 것으로서, 도1은 정면 사시도이고, 도 2는 정단면도이며, 도 3은 연결 이음부 및 방수마감처리 상세도이다.1 to 3 show a prefabricated arch tunnel according to the present invention, Figure 1 is a front perspective view, Figure 2 is a front sectional view, Figure 3 is a connection seam and waterproof finish detail.

도 1 내지 도 3을 참조하면, 본 발명에 따른 조립식 아치 터널은 사전에 각각 분할 제작되어 현장으로 이송된 후, 조립에 의해 하나의 아치 터널을 구축하게 되는 것으로서, 크게 단위 좌,우측벽부재(110,120)와 단위 천정부재(130)로 구성된다.1 to 3, the prefabricated arch tunnel according to the present invention is to be divided into a pre-fabricated and transported to the site, and then to build a single arch tunnel by assembly, largely unit left, right wall member ( 110, 120 and the unit ceiling member 130.

상기 단위 좌,우측벽부재(110,120)는 터널 시공 현장의 기초 콘크리트층 (100)의 좌,우측 단부의 상면에 설치되는 것으로, 기초 콘크리트층에 설치된 고정대위에 안착될 수 있는 밑면부(110a,120a)와 그 밑면부(110a,120a)에 대해 대략 L자형의 일체로 형성되되, 내향으로의 소정 곡률을 가지는 곡면부(110b, 120b)로 구성된다. 이 곡면부(110b,120b)의 상단부 및 측단부에는 이웃하는 타부재와의 조립식 결합을 위한 결합수단이 각각 마련된다.The unit left and right wall members 110 and 120 are installed on the upper surfaces of the left and right ends of the foundation concrete layer 100 at the tunnel construction site, and bottom portions 110a and 120a that can be seated on a fixed base installed on the foundation concrete layer. ) And its bottom portions 110a and 120a are formed integrally in a substantially L-shape, and have curved portions 110b and 120b having a predetermined curvature inwardly. Coupling means for prefabricated coupling with other neighboring members are provided at the upper end and the side end of the curved portions 110b and 120b, respectively.

여기서, 상기 단위 좌,우측벽부재(110,120)의 상단부와 단위 천정부재(130)의 좌우측 하단부에 마련되는 결합수단으로서 도 4 및 도 5에 도시된 바와 같이, 좌,우측벽부재(110,120)의 상단부와 단위 천정부재(130)의 하단부가 결속되는 맞이음부의 단면형상은 대략 "S"자 형태로 제작하여 이들이 견고히 결합될 수 있도록한 요철결합부(120c)가 마련되고, 요철결합부 구간내에는 단위 천정부재(130)와 좌우측벽부재(110.120)간의 이동이나 변위를 방지하기 위해 볼트너트 체결홈(120d), 탄성와샤(120e), 볼트너트(120f)등으로 구성되어 있는 종방향 볼트너트 체결부(110c)가 좌우측에 적정 위치에 적정수로 마련되어 상호간에 긴밀히 결합된다.Here, as shown in Figures 4 and 5 as the coupling means provided in the upper end of the left and right wall members (110, 120) and the lower left and right sides of the unit ceiling member 130, the left and right wall members (110, 120) The cross-sectional shape of the fitting portion where the upper end portion and the lower end portion of the unit ceiling member 130 are bound is formed in a substantially “S” shape, and an uneven coupling portion 120c is provided to allow them to be firmly coupled thereto. In order to prevent movement or displacement between the unit ceiling member 130 and the left and right side wall members (110.120) is a longitudinal bolt nut consisting of a bolt nut fastening groove (120d), elastic washer (120e), bolt nut (120f) Fastening portion 110c is provided in the appropriate number at the right position on the left and right are closely coupled to each other.

도 4에서 참조번호 200은 볼트/너트 체결홈(120d)의 공간에 충전된 발포우레탄(200)을 나타낸다. 이에 대해서는 뒤에서 다시 설명된다.In FIG. 4, reference numeral 200 denotes a foam urethane 200 filled in the space of the bolt / nut fastening groove 120d. This is described again later.

이상과 같이 상기 좌,우측벽부재(110,120)의 상단부와 천정부재(130)의 하단부에는 종방향 결합수단이 마련되는 한편, 도 6 내지 도 8에 도시된 바와 같이, 좌,우측벽부재(110,120)의 측단부와 천정부재(130)의 측단부에는 횡방향 결합수단(151)이 마련된다. 즉, 이 측단부의 결합수단은 단위 아치터널간의 횡방향 연결 결합 수단으로서 "ㄷ"자 형태의 연결금구(140)와 볼트/너트 체결구(150) 및 볼트/너트 체결홈(170)으로 구성되는데, 연결금구(140)는 맞이음부를 제외한 몸체의 다른 부위는 좌,우측벽부재(110,120) 또는 천정부재(130)의 콘크리트 몸체 내에 매설되며 볼트/너트 체결구(150)의 양측에는 체결작업을 용이하게 하기 위한 볼트/너트 체결홈(170)이 형성된다. 도 8에서 참조 번호 223은 무수축 몰탈채움을 나타낸다. 이에 대해서는 뒤에서 다시 설명한다.As described above, longitudinal coupling means are provided at the upper end of the left and right wall members 110 and 120 and the lower end of the ceiling member 130, and as shown in FIGS. 6 to 8, the left and right wall members 110 and 120. Lateral coupling means 151 is provided at the side end of the side and the side end of the ceiling member 130. That is, the coupling means of the side end portion is composed of a coupling tool 140, bolt / nut fastener 150 and bolt / nut fastening groove 170 of the "c" shape as a lateral connection coupling means between the unit arch tunnel. The connection bracket 140 is embedded in the concrete body of the left and right wall members 110 and 120 or the ceiling member 130 except for the fitting portion, and fastening work on both sides of the bolt / nut fastener 150. Bolt / nut fastening groove 170 is formed to facilitate the. In FIG. 8, reference numeral 223 denotes non-contraction mortar filling. This will be described later.

그러면, 이상과 같은 구성을 갖는 본 발명에 따른 단위 부재를 이용한 조립식 아치 터널의 시공방법에 대하여 설명해 보기로 한다.Then, the construction method of the prefabricated arch tunnel using the unit member according to the present invention having the above configuration will be described.

본 발명에 따른 단위 부재를 이용한 조립식 아치 터널의 시공방법은, 상기에서와 같은 단위 좌,우측벽부재(110,120)와 단위 천정부재(130)를 이용하여 조립식 아치 터널을 시공함에 있어서, 상기 도 2에서와 같이, 먼저 터널 시공 대상의 현장의 지면을 정리한 후 기초 콘크리트층(100)을 형성하게 된다. 이때, 필요에 따라서는 터널을 조립설치 완료한 후에 그 기초 콘크리트층(100) 위에 바닥 콘크리트층(102)과 아스팔트층(104)을 더 형성할 수도 있다.In the construction method of the prefabricated arch tunnel using the unit member according to the present invention, in the construction of the prefabricated arch tunnel using the unit left and right wall members 110 and 120 and the unit ceiling member 130 as described above, FIG. As in, first, after cleaning the ground of the site of the tunnel construction target is to form a foundation concrete layer (100). At this time, if necessary, after assembling and installing the tunnel, the bottom concrete layer 102 and the asphalt layer 104 may be further formed on the foundation concrete layer 100.

기초 콘크리트층(100)의 형성이 완료되면, 도 9에 도시된 바와 같이, 그 기초 콘크리트층(100)의 상면 양단에, 상기 단위 좌,우측벽부재(110,120)의 정밀한 안착을 위한 고정대(220)가 설치된다. 여기서, 이 고정대(220)는 기초 콘크리트층(100)에 삽입설치된 앵커볼트 삽입구(224)에 체결된 앵커 볼트(221)와, 그 앵커 볼트(221)의 상부에 용접에 의해 수평고정 설치되는 H형강 또는 I형강으로 구성된다. 고정대(220)의 설치가 완료되면, H형강 또는 I형강의 상단부를 제외한 아래의 모든 부분은 부몰탈(225)로 마감 처리한다.When the formation of the foundation concrete layer 100 is completed, as shown in Figure 9, on both ends of the upper surface of the foundation concrete layer 100, the fixing table for precise mounting of the left and right wall members (110, 120) ) Is installed. Here, the fixture 220 is anchor bolt 221 fastened to the anchor bolt insertion hole 224 inserted into the foundation concrete layer 100, and H is fixed to the horizontal installation of the anchor bolt 221 by welding It consists of section steel or section I steel. When the installation of the fixture 220 is completed, all parts of the lower portion except the upper end of the H-beam or I-beam is finished with a mortar 225.

이때 고정대(220)는 단위 좌,우측벽부재의 위치와 높이(LEVEL)를 정확히 하고 설치를 신속하게 진행하기 위하여 설치하는 것으로서, 그 위에 단위 좌,우측벽부재를 설치고정하기만 하면 된다.At this time, the fixing table 220 is to be installed to accurately position and height (LEVEL) of the unit left, right wall member and to proceed with the installation, it is only necessary to fix the unit left, right wall member installed thereon.

고정대 설치 및 부몰탈(225)의 마감 처리가 완료되면, 도 10에 도시된 바와 같이, 크레인 등의 인양수단(230)에 의해 상기 단위 좌,우측벽부재(110,120)를 인양하여 상기 고정대(220) 위의 정해진 위치에 각각 안착, 설치한다. 그런 후, 도 11 및 도 12에 도시된 바와 같이, 단위 천정부재(130)를 인양하여, 상기 단위 좌,우측벽부재(110,120) 위에 거치한다. 이때, 단위 좌,우측벽부재(110,120)의 상단부와 단위 천정부재(130)의 하단부에 각각 마련되어 있는 결합수단, 즉 종방향 요철결합부(120c)의 단면형상 특성상 천정부재(130)는 좌우측벽부재(110,120)들의 상단부에 안전하게 거치된다. 거치작업이 완료되면 요철결합부(120C) 구간내에 적정위치에 매입되어 있는 종방향 볼트/너트 체결부(110c)를 체결함으로써 단위 좌,우측벽부재(110,120)와 단위 천정부재(130)를 간단히 조립할 수 있게 된다. 특히,볼트/너트 체결부(110c)의 볼트/너트 결합 후의 주변의 공간에는 상기 도 5에 도시된 바와 같이, 발포우레탄(200)을 충전하여 마감 처리한다.When the holder is installed and the finishing treatment of the mortar 225 is completed, as shown in FIG. 10, the lifting unit 220 is lifted by the lifting means 230 such as a crane to lift the unit left and right wall members 110 and 120. ) Settle and install at each of the above positions. Thereafter, as shown in FIGS. 11 and 12, the unit ceiling member 130 is lifted and mounted on the unit left and right wall members 110 and 120. At this time, the ceiling member 130 is a left and right side wall due to the cross-sectional shape of the coupling means, that is, the longitudinal concave-convex coupling portion 120c provided at the upper end of the unit left and right wall members 110 and 120 and the lower end of the unit ceiling member 130, respectively. It is securely mounted on the upper end of the members (110, 120). When the mounting work is completed, the unit left and right wall members 110 and 120 and the unit ceiling member 130 are simply fastened by tightening the longitudinal bolt / nut fastening portion 110c which is embedded at an appropriate position within the uneven coupling portion 120C. I can assemble it. In particular, the space after the bolt / nut coupling of the bolt / nut fastening portion (110c) as shown in FIG.

이상에 의해 단위 좌,우측벽부재(110,120)와 단위 천정부재(130)로 이루어지는 단위 아치 터널 구조체의 축조가 완성되면, 위에서와 동일한 방식으로 단위 좌,우측벽부재(110,120)와 단위 천정부재(130)를 터널의 길이방향으로 반복 조립하여 전체적으로 완성된 하나의 아치 터널 구조체를 축조한다. 이때, 단위 아치터널간의 횡방향 연결이음부는 도 6내지 도 8에 도시된 바와 같이, 인접하는 부재들에 매입되어 있는 연결금구(140)를 볼트너트(150)로 체결하고, 볼트너트체결홈(170)을 무수축 몰탈(223)로 충진하여 마감처리한 후 각 이음부를 외부는 방수시트(240)로 방수처리하고, 내부는 탄성씰링재(210)(도 8 참조)로 마감 처리한다. 또한, 상기 아치터널의 갱구부(출입구)는 도 3에 도시된바와 같이 상부 경사지반(231)의 경사각도에 따라 단위 천정부재(130)를 부분적으로만 형성하거나 좌우측벽부재(110,120)로만 갱구부(출입구)를 조립 축조하여 아치터널의 출입구를 터널 상부의 경사지반의 경사각도에 따라 자연스럽게 입구를 마감처리하여 터널입구의 경관을 자연스럽게 처리할 수도 있다.When the construction of the unit arch tunnel structure consisting of the unit left and right wall members 110 and 120 and the unit ceiling member 130 is completed, the unit left and right wall members 110 and 120 and the unit ceiling member ( 130 is repeatedly assembled in the longitudinal direction of the tunnel to construct one completed arch tunnel structure. At this time, as shown in Figs. 6 to 8, the lateral connection joint between the unit arch tunnel, fastening the connecting bracket 140, which is embedded in the adjacent members with the bolt nut 150, bolt fastening groove After filling the 170 with the non-shrink mortar 223, each joint is waterproofed with a waterproof sheet 240, the inside is finished with an elastic sealing material 210 (see Fig. 8). In addition, the shaft portion (entrance) of the arch tunnel, as shown in FIG. 3, may form the unit ceiling member 130 only partially or according to the inclination angle of the upper inclined ground 231 or the shaft only as the left and right side wall members 110 and 120. The entrance and exit of the arch tunnel can be naturally finished according to the inclination angle of the inclined ground at the upper part of the tunnel, so that the landscape of the tunnel entrance can be naturally processed.

이렇게 하여 전체적인 아치 터널 구조체의 축조가 완성되면, 도 12,도13에 도시한 바와 같이 좌우측벽부재의 밑면부(110a,120a)의 내측에 매입되어 있는 철근 연결구(160)에 철근을 연결시키고 바닥 콘크리트층(102)을 시공한 후 도 14에 도시된 바와 같이 터널 구조체의 좌우측 공간에 토사를 메꾸어 넣고 성토 다짐한다.In this way, when the construction of the entire arch tunnel structure is completed, as shown in FIGS. 12 and 13, the reinforcing bar is connected to the reinforcing bar connector 160 embedded in the bottoms 110a and 120a of the left and right side wall members. After constructing the concrete layer 102, as shown in Figure 14 to fill the soil in the left and right spaces of the tunnel structure to fill the fill.

이상의 설명에서와 같이, 본 발명에 따른 조립식 아치 터널 및 그 시공방법은 아치 형상을 갖는 몇 개의 부품으로 분할 제작된 각 콘크리트 구조물을 현장에 이송하여 조립한 후 볼트너트 체결홈을 충진마감하고 각 이음부를 방수시트 등으로 마감처리함으로써 하나의 조립식 아치 터널이 완성되므로, 터널 시공에 소요되는 기간을 대폭 감축할 수 있고, 분할 제작된 각 콘크리트 구조물은 이미 제작 단계에서 공장내의 철저한 품질검사를 거치게 되므로, 완성된 콘크리트 구조물의 품질면에서 우수한 신뢰도를 얻을 수 있다.As described above, the prefabricated arch tunnel and the construction method according to the present invention after transporting and assembling each concrete structure divided into a few parts having an arch shape to the field filling and closing the bolt nut fastening groove and each joint By finishing the part with waterproof sheet, etc., one prefabricated arch tunnel is completed, so that the time required for the construction of the tunnel can be greatly reduced, and each of the concrete structures manufactured separately is subjected to thorough quality inspection in the factory at the manufacturing stage. Excellent reliability can be obtained in terms of the quality of the finished concrete structure.

Claims (6)

기초 콘크리트층(100)위에 단위 좌,우측벽 부재(110,120)의 정밀하고 신속한 설치를 위해 설치되는 고정대(220);Fixture 220 is installed for precise and rapid installation of the unit left, right wall member (110, 120) on the base concrete layer (100); 터널 시공 현장의 기초 콘크리트(100)면의 좌,우측 단부의 상면에 설치되는 고정대 위에서 안착될 수 있는 밑면부(110a,120a)와 그 밑면부에 대해 대략 L자 형의 일체로 형성되되, 내향으로의 소정 곡률을 가지는 곡면부(110b,120b)와 그 상단부에는 이웃하는 천정부재(130)와의 볼트너트체결을 위한 종방향 결합수단(110c)과 맞이음 요철결합부(120c)가, 측단부에는 측면에 설치되는 인접부재와 결합을 위한 횡방향 결합수단(151)이 각각 마련되어 있는 단위 좌,우측벽부재(110,120);It is formed integrally in an approximately L shape with respect to the bottom portions 110a and 120a and its bottom portion which can be seated on the fixing rods installed on the upper left and right ends of the foundation concrete 100 surface of the tunnel construction site. Curved portions 110b and 120b having a predetermined curvature and upper end portions thereof are fitted with longitudinal coupling means 110c for fastening bolt nuts with neighboring ceiling members 130, and concave-convex coupling portions 120c have side ends. The unit has left and right side wall members 110 and 120 provided with lateral coupling means 151 for coupling with adjacent members installed on the side; 상기 단위 좌,우측벽부재의 각 상단부에 그 양측 하단부가 각각 얹히어 조립식으로 결합되는 것으로, 상기 단위 좌,우측벽부재의 곡면에 연장되어 전체적으로 하나의 아치면을 형성할 수 있는 곡면 몸체로 구성되며, 그 몸체의 양측 하단부에는 상기 단위 좌,우측벽부재의 각 상단부에 마련되어 있는 결합수단에 대응하는 조립식 종방향 결합수단(110c)과 맞이음 요철결합부(120c)가 각각 마련되고, 몸체의 측면부에는 이웃하는 타부재와의 조립식 결합을 위한 횡방향 결합수단(151)이 마련되어 있는 단위 천정부재(130); 및The upper and lower ends of both sides of the unit left and right wall members are respectively assembled on the upper ends of the unit, and the curved body may extend to the curved surfaces of the unit left and right wall members to form a single arch surface as a whole. On both lower ends of the body, prefabricated longitudinal coupling means (110c) and the fitting concave-convex coupling portion (120c) corresponding to the coupling means provided on each upper end of the left and right wall members of the unit are provided, respectively, A side ceiling unit (130) having a transverse coupling means (151) for prefabricated coupling with other neighboring members; And 상기 단위 좌,우측벽 부재와 단위 천정부재를 상하로 연결하여 단위 아치터널 조립을 위한 종방향 볼트너트 체결부(110c)와 인접하는 단위 좌,우측벽부재 또는 인접하는 단위 천정부재와의 좌우연결을 위한 횡방향 볼트/너트 체결부(151)가각각 설치되어 볼트너트 체결한 후 볼트/너트 체결홈(120d,170)에 채움재인 발포 우레탄(200)과 무수축 몰탈(223)을 채우고 각각의 부재가 연결되어 발생되는 연결부의 외부는 방수시트(240)로 방수처리를 하고 내부는 탄성씰링재(210)로 마감하는 것을 특징으로 하는 단위 부재를 이용한 조립식 아치 터널.The left and right wall members and the unit ceiling member are vertically connected to each other so that the longitudinal bolt nut fastening unit 110c for assembling the unit arch tunnel and the unit left and right wall members or adjacent unit ceiling members are connected to each other. The lateral bolt / nut fastening part 151 for each is installed, and after tightening the bolt nut, filling the foamed urethane 200 and the non-shrink mortar 223 filling the bolt / nut fastening groove (120d, 170) and each Prefabricated arch tunnel using a unit member characterized in that the outside of the connection portion generated by the member is waterproofed with a waterproof sheet 240 and the inside is finished with an elastic sealing material (210). 제 1항에 있어서,The method of claim 1, 상기 단위 좌,우측벽부재(110, 120)의 상단부에는 대략 "S"자 형태의 단면 형상을 갖는 맞이음 요철결합부(120C)가 마련되고 상기 요철결합구간내에는 상하부재간 볼트너트 체결을 위한 볼트너트 체결홈(120d), 탄성와샤(120e), 볼트너트(120f)로 구성된 종방향 볼트너트 체결부(110c)가 적정위치에 적정수량 설치되며 또한 단위 좌,우측벽부재(110,120)의 측단부에는 단위아치터널간의 횡방향 결합을 위해 적정위치에 맞이음부를 제외한 몸체의 다른 부위가 좌,우측벽부재(110,120)의 콘크리트 몸체 내에 매설되는 "ㄷ"자 형태의 연결금구(140)와 볼트/너트 체결홈(170)내에 위치한 볼트/너트 체결구(150)로 이루어진 단위아치터널간의 횡방향 결합수단(151)이 마련되는 단위 좌,우측벽부재인 것을 특징으로 하는 단위 부재를 이용한 조립식 아치 터널.The upper and lower end portions of the unit left and right wall members 110 and 120 are provided with a fitting concave-convex coupling part 120C having a cross-sectional shape of approximately “S” shape, and fastening bolt nuts between upper and lower members in the concave-convex coupling section. Longitudinal bolt nut fastening portion 110c consisting of a bolt nut fastening groove 120d, an elastic washer 120e, and a bolt nut 120f is installed in an appropriate amount at the proper position, and the sides of the unit left and right wall members 110 and 120 are provided. At the end, other parts of the body except for the fitting portion at the proper position for the lateral coupling between the unit arch tunnel, the "c" shaped connection bracket 140 and bolts are embedded in the concrete body of the left and right wall members (110, 120) Prefabricated arch using unit members, characterized in that the unit left, right wall member is provided with the lateral coupling means 151 between the unit arch tunnel made of bolt / nut fastener 150 located in the / nut fastening groove 170 tunnel. 제 1항에 있어서,The method of claim 1, 상기 단위 천정부재(130)의 하단부에는 단위천정부재(130)가 좌우측벽부재(110,120)의 상단부에 마련되는 요철결합부에 대응하여 긴밀히 거치될 수 있도록 대략 "S"자 형태의 단면형상을 갖는 요철결합부가 마련되고 좌우측벽부재(110,120)와의 상하간 결합을 위해 좌우측벽부재(110,120) 상단에 마련되는 볼트너트 체결홈(120d)과 대응하는 볼트너트 체결홈이 적정 위치에 적정개소 설치되며 단위 천정부재(130)의 측단부에는 인접하는 천정부재와의 횡방향 결합을 위해 맞이음부를 제외한 몸체의 다른 부위는 단위 천정부재(130)의 콘크리트 몸체 내에 매설되는 "ㄷ"자 형태의 연결금구(140)와 볼트너트 체결홈(170)에 위치된 볼트/너트 체결구(150)로 이루어진 횡방향 결합수단이 마련된 천정부재인 것을 특징으로 하는 단위 부재를 이용한 조립식 아치 터널.The lower end of the unit ceiling member 130 has a cross-sectional shape of approximately "S" shape so that the unit ceiling member 130 can be closely mounted corresponding to the concave-convex coupling portion provided on the upper end of the left and right side wall members (110, 120). Concave-convex coupling part is provided and the bolt nut fastening groove corresponding to the bolt nut fastening groove (120d) provided on the upper left and right side wall members (110, 120) for the upper and lower coupling with the left and right side wall members (110, 120) is installed in the proper position and the unit On the side end of the ceiling member 130, the other portion of the body except for the fitting portion for the lateral coupling with the adjacent ceiling member is a "c" shaped connection bracket embedded in the concrete body of the unit ceiling member 130 ( 140) and the prefabricated arch tunnel using a unit member, characterized in that the ceiling member is provided with a transverse coupling means consisting of bolt / nut fasteners 150 located in the bolt nut fastening groove (170). 제 1항에 있어서The method of claim 1 상기 고정대(220)는 좌우측벽부재(110,120)의 설치 위치를 조정하기 위하여 기초 콘크리트층(100)에 삽입설치된 앵커볼트 삽입구(224)와 좌우측벽부재(110,120)의 설치높이를 조정하기 위한 앵커 볼트(221) 및 좌우측벽부재로부터 전달되는 하중에 대응하기 위해 앙카볼트(221)의 상부에 용접에 의해 고정 설치되는 H형강 또는 I형강과 H형강 또는 I형강의 상단부를 제외한 아래 부분은 부 몰탈(225)로 마감 처리한 고정대인 것을 특징으로 하는 단위 부재를 이용한 조립식 아치 터널.The anchor 220 is an anchor bolt for adjusting the installation height of the anchor bolt insertion hole 224 and the left and right side wall members 110 and 120 inserted into the foundation concrete layer 100 to adjust the installation position of the left and right side wall members 110 and 120. 221 and the lower portion except for the upper end of the H-beam or I-beam and H-beam or I-beam, which are fixed by welding on the upper part of the anchor bolt 221 to correspond to the load transmitted from the left and right side wall members, 225) prefabricated arch tunnel using a unit member, characterized in that the fixing stand. (a) 터널 시공 대상의 현장의 지면을 정리 다짐한 후 기초 콘크리트층(100)을 형성하는 단계;(A) forming a foundation concrete layer 100 after pruning the ground of the site of the tunnel construction target; (b) 상기 기초 콘크리트층(100)의 상면 양단에 삽입설치된 앵커볼트 삽입구(224)에 체결된 앵커 볼트(221)의 상부에 용접에 의해 고정 설치되는 H형강 또는 I형강으로서 H형강 또는 I형강의 상단부를 제외한 아래 부분은 부 몰탈(225)로 마감 처리한 고정대(220)를 설치하는 단계;(b) H-shaped steel or I-shaped steel as H-shaped steel or I-shaped steel fixedly installed by welding on the upper part of the anchor bolt 221 fastened to the anchor bolt insertion hole 224 inserted into both ends of the upper surface of the foundation concrete layer 100 The lower part of the lower part except for the upper part of the installation mortar 225, the fixing step 220 is installed; (c) 상기 고정대(220) 위에 콘크리트 바닥면에 안착될 수 있는 밑면부(110a,120a)와 그 밑면부에 대해 대략 L자 형의 일체로 형성되되, 내향으로의 소정 곡률을 가지는 곡면부(110b,120b)로 이루어진 단위 좌,우측벽부재를 정위치에 안착, 설치하는 단계;(C) the bottom portion 110a, 120a which can be seated on the concrete floor surface and the bottom portion is formed integrally of approximately L-shaped with respect to the bottom portion, the curved portion having a predetermined curvature inwardly ( Mounting and installing unit left and right wall members 110b and 120b at a proper position; (d) 상기 단위 좌,우측벽부재 위에 상기 단위 천정부재(130)를 인양하여 거치하는 단계;(d) lifting and mounting the unit ceiling member 130 on the unit left and right wall members; (e) 상기 단위 좌,우측벽부재(110,120)의 상단부와 상기 단위 천정부재(130)의 하단부를 "s"자 형상을 한 요철결합부(120c)와 지정위치에 마련되는 볼트/너트 체결부/구(110c)를 이용하여 연결시키되 볼트/너트는 볼트/너트 체결홈(120d)내에 위치하는 탄성와샤(120e)와 볼트/너트 체결부/구(120f)로 이루어진 결합수단(110c)을 이용하여 상기 단위 좌,우측벽부재와 상기 단위 천정부재를 상하로 각각 체결하고 볼트/너트 체결홈(120d)에는 발포우레탄(200)을 채움을 하는 단계;(e) Bolts / nuts fastening portions provided at the designated positions with the uneven coupling portion 120c having an “s” shape at the upper end of the unit left and right wall members 110 and 120 and the lower end of the unit ceiling member 130. Using the / 110 (c) is connected to the bolt / nut using a coupling means (110c) consisting of an elastic washer 120e and the bolt / nut fastening portion / sphere (120f) located in the bolt / nut fastening groove (120d). Fastening the unit left and right side wall members and the unit ceiling member up and down, respectively, and filling the foamed urethane 200 into the bolt / nut fastening groove 120d; (f)상기 좌,우측벽부재(110,120)와 상기 단위 천정부재의 측단부에 마련되는"ㄷ"자 형태의 연결금구(140)는 맞이음부를 제외한 몸체의 다른 부위는 좌,우측벽부재(110,120)의 콘크리트 몸체 내의 지정위치에 매설되며 볼트/너트 체결홈(170)에 위치된 볼트/너트 체결부/구(150)를 이용하여 인접한 상기 단위 좌,우측벽 부재와 상기 단위 천정부재끼리 서로 연결하고 볼트/너트 체결홈(170)에는 무수축 몰탈(223)로 채움을 하는 단계;(f) The left and right wall members 110 and 120 and the “c” shaped connecting bracket 140 provided at the side ends of the unit ceiling member are other parts of the body except for the fitting portion of the left and right wall members ( The unit left and right wall members and the unit ceiling members are buried at a predetermined position in the concrete body of the 110 and 120 and adjacent to each other by using the bolt / nut fastening part / sphere 150 located in the bolt / nut fastening groove 170. Connecting and filling the bolt / nut fastening groove 170 with the non-shrink mortar 223; (g) 상기 단위 좌,우측벽부재(110,120)와 단위 천정부재(130)로 이루어지는 단위 아치 터널 구조체를 상기의 각 단계를 거쳐 동일한 방식으로 반복 조립하여 터널의 길이방향으로 연장하여 축조하는 단계;(g) repeating assembling the unit arch tunnel structure including the unit left and right wall members 110 and 120 and the unit ceiling member 130 in the same manner through each of the above steps to extend and build in the longitudinal direction of the tunnel; (h) 좌우측벽부재(110,120)의 밑면부(110a,120a)의 내측에 매입되어 있는 철근 연결구(160)에 철근을 연결시킨 후 바닥콘크리트(102)를 타설하여 좌우측벽 부재를 일체화시키고 콘크리트 포장층을 축조시키는 단계;(h) After connecting the reinforcing bar to the reinforcing bar connector 160, which is embedded in the bottom portion (110a, 120a) of the left and right side wall members (110, 120), the bottom concrete 102 is poured to integrate the left and right wall members and concrete pavement Building a layer; (i)상기 (g)단계에서 각각의 단위부재를 서로 연결하여 발생된 연결부의 외부는 방수시트(240)로 방수처리하고 내부는 탄성실링재(210)로 마감을 하는 단계; 및(i) the outside of the connection portion generated by connecting each unit member in step (g) is waterproofed with a waterproof sheet 240 and the inside is finished with an elastic sealing material 210; And (j) 상기 (h)단계의 바닥 콘크리트(102)의 축조가 완료된 후, 터널 구조체의 좌우측 공간에 토사를 메꾸어 넣고 성토 다짐하여 터널공사의 마무리를 하는 단계를 더 포함하는 것을 특징으로 하는 단위 부재를 이용한 조립식 아치 터널의 시공방법.(j) after the construction of the bottom concrete 102 of the step (h) is completed, filling the soil in the left and right spaces of the tunnel structure and compacting the fillet further comprises the step of finishing the tunnel construction Construction method of prefabricated arch tunnel using. 제 5항에 있어서,The method of claim 5, 상기 터널의 갱구부(출입구) 상부 경사지반(231)의 경사각도에 따라 천정부재(130)가 부분적으로만 형성되거나, 또는 천정부재(130)가 없이 좌우측벽부재(110,120)로만 갱구부가 축조되어 터널의 출입구에 자연스러운 경관을 제공하는 것을 특징으로 하는 단위 부재를 이용한 조립식 아치 터널의 시공방법.According to the inclination angle of the shaft (entrance) upper inclined ground 231 of the tunnel, the ceiling member 130 is only partially formed, or the shaft portion is constructed only by the left and right side wall members 110 and 120 without the ceiling member 130. A method of constructing a prefabricated arch tunnel using a unit member, characterized by providing a natural view to the entrance and exit of the tunnel.
KR10-2002-0050278A 2002-08-24 2002-08-24 Fabricated arch tunnel and construction method thereof KR100443809B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0050278A KR100443809B1 (en) 2002-08-24 2002-08-24 Fabricated arch tunnel and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0050278A KR100443809B1 (en) 2002-08-24 2002-08-24 Fabricated arch tunnel and construction method thereof

Publications (2)

Publication Number Publication Date
KR20040018002A KR20040018002A (en) 2004-03-02
KR100443809B1 true KR100443809B1 (en) 2004-08-11

Family

ID=37323673

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0050278A KR100443809B1 (en) 2002-08-24 2002-08-24 Fabricated arch tunnel and construction method thereof

Country Status (1)

Country Link
KR (1) KR100443809B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100605559B1 (en) * 2006-01-20 2006-08-02 주식회사 도화종합기술공사 Assembling structure of tunnel lining using concrete panel
KR100605560B1 (en) * 2006-01-20 2006-08-02 주식회사 도화종합기술공사 Assembling structure of tunnel lining using anchor pipe
KR100605561B1 (en) * 2006-01-20 2006-08-02 주식회사 도화종합기술공사 Assembling structure of tunnel lining block
KR100717390B1 (en) * 2005-09-14 2007-05-11 박창순 Assembly precasted panel for excavation tunnel

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100732622B1 (en) * 2006-09-28 2007-06-27 주식회사 우일 이알에스 The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method
PT104312A (en) 2008-12-31 2010-06-30 Univ Aveiro METHOD AND NON-ASSEMBLY CONCRETE BLOCKS FOR CONTRACTION OF ARC ART WORKS
KR101040437B1 (en) * 2011-04-07 2011-06-09 주식회사 인터컨스텍 Construction method of a segmental precast concrete arched tunnel with hinges
KR101851557B1 (en) * 2016-06-16 2018-04-25 하미정 Arch structure with reinforced arch rib segment and arch structure construction method therefor
CN110486040B (en) * 2019-07-08 2024-03-08 重庆交通大学 Assembled lining structure for highway tunnel
CN115354693B (en) * 2022-10-19 2023-03-17 中国铁路设计集团有限公司 Open trench tunnel assembly type U-shaped groove structure and construction method
KR102690686B1 (en) * 2023-03-31 2024-08-05 한국콘크리트산업 주식회사 Precast arch-type structure (hci arch) with a crown part (top part) rigid joint structure

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57133698U (en) * 1981-02-09 1982-08-20
JPS6255697U (en) * 1985-09-25 1987-04-07
JPH03260296A (en) * 1990-03-09 1991-11-20 Kyoritsu Kagaku Sangyo Kk Filling up method of hole of connection box for segment
JPH084486A (en) * 1994-06-21 1996-01-09 Nippon Concrete Ind Co Ltd Tunnel lining construction method
JPH0874496A (en) * 1994-09-08 1996-03-19 Kyoritsu Kagaku Sangyo Kk Segment-connecting bolt box closing method
JPH11107695A (en) * 1997-10-01 1999-04-20 Ohbayashi Corp Joint structure of concrete structural member treated with corrosion preventive coating
JP2000186331A (en) * 1998-12-18 2000-07-04 Ishikawajima Constr Materials Co Ltd Large-section tunnel and method for constructing the same
JP2001011928A (en) * 1999-06-30 2001-01-16 Geostr Corp Hollow structure with height adjusting means
JP2001012188A (en) * 1999-06-30 2001-01-16 Geostr Corp Joint structure for hollow structure
JP2001012195A (en) * 1999-06-30 2001-01-16 Geostr Corp Support structure for hollow structure
JP2001012190A (en) * 1999-06-30 2001-01-16 Geostr Corp Joint structure for hollow structure
JP2002089194A (en) * 2000-09-19 2002-03-27 Ishikawajima Constr Materials Co Ltd Installation structure for curved slab for arched tunnel
JP2002088788A (en) * 2000-09-19 2002-03-27 Ishikawajima Constr Materials Co Ltd Installation method for curved slab for arch tunnel
KR200285552Y1 (en) * 2002-05-17 2002-08-13 주식회사 한구엔지니어링 Assembly tunnel mounting structure of site with practicable open cutting

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57133698U (en) * 1981-02-09 1982-08-20
JPS6255697U (en) * 1985-09-25 1987-04-07
JPH03260296A (en) * 1990-03-09 1991-11-20 Kyoritsu Kagaku Sangyo Kk Filling up method of hole of connection box for segment
JPH084486A (en) * 1994-06-21 1996-01-09 Nippon Concrete Ind Co Ltd Tunnel lining construction method
JPH0874496A (en) * 1994-09-08 1996-03-19 Kyoritsu Kagaku Sangyo Kk Segment-connecting bolt box closing method
JPH11107695A (en) * 1997-10-01 1999-04-20 Ohbayashi Corp Joint structure of concrete structural member treated with corrosion preventive coating
JP2000186331A (en) * 1998-12-18 2000-07-04 Ishikawajima Constr Materials Co Ltd Large-section tunnel and method for constructing the same
JP2001011928A (en) * 1999-06-30 2001-01-16 Geostr Corp Hollow structure with height adjusting means
JP2001012188A (en) * 1999-06-30 2001-01-16 Geostr Corp Joint structure for hollow structure
JP2001012195A (en) * 1999-06-30 2001-01-16 Geostr Corp Support structure for hollow structure
JP2001012190A (en) * 1999-06-30 2001-01-16 Geostr Corp Joint structure for hollow structure
JP2002089194A (en) * 2000-09-19 2002-03-27 Ishikawajima Constr Materials Co Ltd Installation structure for curved slab for arched tunnel
JP2002088788A (en) * 2000-09-19 2002-03-27 Ishikawajima Constr Materials Co Ltd Installation method for curved slab for arch tunnel
KR200285552Y1 (en) * 2002-05-17 2002-08-13 주식회사 한구엔지니어링 Assembly tunnel mounting structure of site with practicable open cutting

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100717390B1 (en) * 2005-09-14 2007-05-11 박창순 Assembly precasted panel for excavation tunnel
KR100605559B1 (en) * 2006-01-20 2006-08-02 주식회사 도화종합기술공사 Assembling structure of tunnel lining using concrete panel
KR100605560B1 (en) * 2006-01-20 2006-08-02 주식회사 도화종합기술공사 Assembling structure of tunnel lining using anchor pipe
KR100605561B1 (en) * 2006-01-20 2006-08-02 주식회사 도화종합기술공사 Assembling structure of tunnel lining block

Also Published As

Publication number Publication date
KR20040018002A (en) 2004-03-02

Similar Documents

Publication Publication Date Title
EP0912804B1 (en) A foundation element, methods for the construction of prefabricated structures including these elements, particularly prefabricated tunnels, and prefabricated structures made by these methods
JP5576207B2 (en) Installation foundation and its construction method
KR101077821B1 (en) Tunnel conctruction method using arch pre-cast segmental structural body
US20170022726A1 (en) Prefabricated, deconstructable, multistory building construction
CN111550262B (en) Tunnel assembly type prestress lining design method
KR100443809B1 (en) Fabricated arch tunnel and construction method thereof
US20240125120A1 (en) Modular Slab, Slab System, Piles and Methods of Use Thereof
US10988910B2 (en) Pre-cast concrete wall structures, and methods for manufacturing and installing the same
US20030033773A1 (en) Foundation construction
KR100712354B1 (en) PC Integrating Construction Method of an Underground Parking Lot and PC Column-Beam Joint System for Long Span PC Beam therein
JP2022175669A (en) Construction method of mat foundation
EP1561874A1 (en) Connecting device and node for buildings with prefabricated elements
KR101036177B1 (en) Method for constructing building using PRC integrating method
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
JPH08135087A (en) Precast concrete column member and joint method thereof
KR100653865B1 (en) Coupler tension type fabricated retaining wall built by connecting high intensity reinforcing bars installed in the retaining wall panel unit by coupler and prestressing those bars, and constructing method thereof
KR101482523B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
JPH0475322B2 (en)
KR100732622B1 (en) The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method
JP2515227B2 (en) Installation method of cast-in-place concrete foundation and precast concrete wall slab
JP4010388B2 (en) High-strength reinforced concrete precast plate
RU2291935C1 (en) Structural combined member for composite diaphragm wall and composite diaphragm wall
JPH084343A (en) Garage
JP2002138408A (en) Foundation block for sidewalk and road-way boundary block
JP2555837B2 (en) Construction method of underground structure by upside down construction method

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120830

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20140203

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20140730

Year of fee payment: 11

LAPS Lapse due to unpaid annual fee