KR100732622B1 - The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method - Google Patents

The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method Download PDF

Info

Publication number
KR100732622B1
KR100732622B1 KR1020060100123A KR20060100123A KR100732622B1 KR 100732622 B1 KR100732622 B1 KR 100732622B1 KR 1020060100123 A KR1020060100123 A KR 1020060100123A KR 20060100123 A KR20060100123 A KR 20060100123A KR 100732622 B1 KR100732622 B1 KR 100732622B1
Authority
KR
South Korea
Prior art keywords
tunnel
longitudinal
unit
reinforcing rib
wall members
Prior art date
Application number
KR1020060100123A
Other languages
Korean (ko)
Inventor
김달환
Original Assignee
주식회사 우일 이알에스
김달환
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 우일 이알에스, 김달환 filed Critical 주식회사 우일 이알에스
Application granted granted Critical
Publication of KR100732622B1 publication Critical patent/KR100732622B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/086Methods of making concrete lining segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall

Abstract

A prefabricated arch tunnel using a tunnel member having a reinforcement rib is provided to be constructed quickly and economically by manufacturing a concrete structure in many unit members in a factory and assembling the unit members in a construction site. The prefabricated arch tunnel using a tunnel member having a reinforcement rib comprises a foundation concrete layer formed by placing and curing concrete, a fixture installed on the foundation concrete layer, right and left side wall members(110,120) placed on the fixture and provided with base planes, curved planes formed in the L-shape against the base planes and having the appointed curvature inward, a vertical bolt-and-nut joint(110c), a butt-type rugged joint(120c) and a horizontal bolt-and-nut joint(151), a ceiling member(130) extended to the curved surfaces of the right and left side wall members, formed in one arch shape as a whole and provided with a vertical bolt-and-nut-joint, a butt-type rugged joint and a horizontal bolt-and-nut joint, expanded urethane and non-shrinkage mortar filled in the bolt-and-nut joint of the right and left side wall members and the bolt-and-nut joint of the ceiling member, and a waterproof sheet and an elastic seal installed to the inside and outside of a connection of the right, left side wall members and the ceiling member, wherein the tunnel member is formed by assembling at least two or more unit members(400) having the appointed size sectionally or integrally, and the unit member is integrated with a tunnel arch member and provided with many vertical ribs(310) and horizontal ribs(320) to reduce the cross-section of the unit member and the tunnel arch member and to increase resistance to external force.

Description

보강리브를 갖는 터널부재를 이용한 조립식 아치터널 및 그 시공방법{The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method}The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method

도 1은 본 발명에 따른 3분할 터널부재의 외부 표면에 종, 횡방향 리브가 형성된 상태를 도시한 예시도,1 is an exemplary view showing a state in which longitudinal, transverse ribs are formed on an outer surface of a three-part tunnel member according to the present invention;

도 2는 본 발명에 따른 2분할 터널부재의 내부 표면에 종, 횡방향 리브가 형성된 상태를 도시한 예시도,Figure 2 is an exemplary view showing a state in which longitudinal, transverse ribs are formed on the inner surface of the two-split tunnel member according to the present invention,

도 3은 본 발명에 따른 터널아치부재의 내외부 표면에 종, 횡방향 리브가 형성된 상태를 도시한 예시도,3 is an exemplary view showing a state in which longitudinal, transverse ribs are formed on the inner and outer surfaces of the tunnel arch member according to the present invention;

도 4는 본 발명에 따른 2분할 터널부재의 내외부 표면에 상하로 엇갈린 상태로 종, 횡방향 리브가 형성된 상태를 도시한 예시도,Figure 4 is an exemplary view showing a state in which the longitudinal, transverse ribs are formed in the up and down staggered state on the inner and outer surfaces of the two-split tunnel member according to the present invention,

도 5(a) 및 5(b)는 본 발명에 따른 터널부재간 볼트 체결 상태를 도시한 예시도,5 (a) and 5 (b) is an exemplary view showing a bolt fastening state between tunnel members according to the present invention,

도 6(a) 내지 6(e)는 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널을 시공하는 상태를 도시한 공정도.6 (a) to 6 (e) is a process diagram showing a state of constructing a prefabricated arch tunnel using a tunnel member having a reinforcing rib according to the present invention.

-도면의 주요부분에 대한 부호의 설명-Explanation of symbols on the main parts of the drawing

100: 기초콘크리트층 102: 바닥콘크리트층100: foundation concrete layer 102: floor concrete layer

104: 포장층 110: 좌측벽부재104: paving layer 110: left wall member

110a: 밑면부 110b: 곡면부110a: bottom portion 110b: curved portion

110c: 종방향 볼트너트 체결부 120: 우측벽부재110c: longitudinal bolt nut fastening part 120: right wall member

120a: 밑면부 120b: 곡면부120a: bottom portion 120b: curved portion

120c: 맞이음 요철결합부 130: 천정부재120c: Butt uneven coupling 130: Ceiling member

140: 연결금구 150: 볼트너트 체결구140: connection bracket 150: bolt nut fastener

151: 횡방향 볼트너트 체결구 160: 철근연결구151: transverse bolt nut fastener 160: rebar connector

170: 볼트너트 체결홈 210: 탄성실링재170: bolt nut coupling groove 210: elastic sealing material

220: 고정대 221: 앵커볼트220: holder 221: anchor bolt

222: H형강 223: 무수축몰탈222: H-beam 223: non-shrink mortar

224: 앵커볼트삽입구 225: 부몰탈224: anchor bolt insertion hole 225: mortar

230: 양중수단 310: 종방향리브230: lifting means 310: longitudinal rib

320: 횡방향리브 330: 종방향 연결공 320: transverse rib 330: longitudinal connection hole

400: 단위부재 A: 터널아치부재400: unit member A: tunnel arch member

U: 터널단위부재U: tunnel unit member

본 발명은 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 및 그 시공방법에 관한 것으로, 특히 아치터널 구축을 위한 특정 형태의 콘크리트구조물을 미리 공장에서 몇 개의 단위부재로 제작하고, 현장에 이송하여 단위부재를 조립한 후, 이음부위를 마감 처리함으로써, 신속한 터널 시공이 가능하고, 경제적이며, 경관이 수려한 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 및 그 시공방법에 관한 것이다.The present invention relates to a prefabricated arch tunnel using a tunnel member having a reinforcing rib and a construction method thereof, and in particular, a concrete structure of a specific type for building an arch tunnel is manufactured in advance in a factory using several unit members, and transported to a site by a unit. By assembling the member, and then finishing the joint portion, the present invention relates to a prefabricated arch tunnel using a tunnel member having a reinforcing rib capable of rapid tunnel construction, economical and beautiful scenery, and a construction method thereof.

일반적으로 아치구조는 오래전서부터 토목 구조물이나 건축물 등에 많이 사용되던 하나의 구조 양식이다.In general, arch structure is a structural form that has been used in civil engineering structures and buildings for a long time.

이와 같은 아치구조는 외부 토압이나 통과하중에 대해 응력분산이 용이한 구조이기 때문에 동일 응력 조건하에서는 여타 단면 형상일 때보다 부재단면을 얇게 할 수 있으므로 경제적이며, 특히 아치 구조물이 주변 경관과 조화를 이룰 수 있음에도 공사현장에서는 재래식 현장 타설 콘크리트 방식으로 박스 구조로 시공하였다.Since the arch structure is easy to dissipate stress against external earth pressure or through load, it is economical because the member section can be made thinner than other cross-sectional shapes under the same stress condition, and in particular, the arch structure is in harmony with the surrounding landscape. Although possible, the construction site was constructed in a box structure using conventional cast-in-place concrete.

이러한 재래식 공법에 의하면, 건설현장에서 동바리 및 거푸집을 설치하고, 철근을 배근한 후, 콘크리트를 타설 및 양생하고, 거푸집을 해체하는 방식이므로, 공종에 따라 많은 인원이 투입되고, 콘크리트를 바닥, 벽체, 슬래브 등 3단계로 구분하여 시공하므로, 공사에 장기간이 소요되며, 특히 슬래브의 침하균열을 방지하기 어렵고, 구조적으로 동일 응력이 가해지는 조건하에서는 콘크리트의 두께가 두꺼워지므로 구조체 중량이 증가되어 지반침하에 대한 안정성이 떨어질 뿐만 아니라 콘크리트의 세심한 품질관리가 요구되고 있는 실정이다.According to this conventional construction method, since the construction site installs copper bars and formwork, reinforces steel bars, reinforces and cures concrete, and dismantles formwork, a large number of people are added to the construction site. As it is divided into three stages of construction, slab, etc., it takes a long time to construct, and it is difficult to prevent the settling crack of the slab.In particular, under the condition that the same stress is applied to the structure, the thickness of the concrete increases, so the weight of the structure increases and the ground subsidence is increased. In addition to poor stability, concrete quality control is required.

또한, 박스 구조 시공시 지보공 설치에 세심한 주의가 필요하고, 많은 숙련공이 필요하며, 또한 터널 갱구에는 삼각형 형상의 날개벽이 별도로 형성되므로 터널 경관을 훼손하는 문제가 있다.In addition, when constructing the box structure, careful installation is required for the support, many skilled workers are required, and the tunnel shaft has a problem that damages the tunnel landscape because a triangular wing wall is separately formed.

특히, 대단면 콘크리트 타설시 수화열에 의한 균열, 침하균열 등의 발생으로 인하여 균열 보수에 많은 비용이 별도로 소요되고, 지보공 설치시 작업자의 부주의로 인한 구조물의 붕괴로 인명사고가 빈번하며, 콘크리트 양생시까지는 구조물 주변을 성토다짐 작업을 할 수 없어, 공사기간이 장기화되고, 차량 통행 제한 등 통행상의 불편을 야기하여 민원의 대상이 되는 등 많은 문제점이 있다.Particularly, large-sided concrete is costly due to cracks and settlement cracks due to hydration heat during concrete casting, and life-saving accidents occur frequently due to the collapse of the structure due to carelessness of workers during the installation of jibo. There is a lot of problems, such as not being able to fill the area around the structure until the construction period is prolonged, causing inconveniences in the traffic, such as restricting the passage of vehicles, to be the subject of a complaint.

이에, 본 발명은 상기한 바와 같은 제문제점을 해결하기 위해 안출된 것으로서, 아치터널 구축을 위한 특정 형태의 콘크리트구조물을 미리 공장에서 몇 개의 단위부재로 제작하고, 제작된 단위부재를 현장으로 이송한 후, 단위부재들을 조립하고 이음부위를 마감 처리함으로써 신속한 아치터널 시공이 가능하고, 경제적이며, 경관이 수려한 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 및 그 시공방법을 제공하는데 그 목적이 있다.Therefore, the present invention has been made to solve the problems as described above, to produce a concrete structure of a specific form for the construction of the arch tunnel in advance in the factory of several unit members, and to transfer the manufactured unit member to the site After that, by assembling the unit members and finishing the joint portion, it is possible to provide a fast arch tunnel construction, economical, and prefabricated arch tunnel using a tunnel member having a beautiful landscape reinforcing rib and its construction method.

상기한 목적을 달성하기 위한 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널은 콘크리트가 타설 및 양생된 기초콘크리트층과; 상기 기초콘크리트층상에 설치되는 고정대와; 상기 고정대상에 안착되며, 밑면부와, 그 밑면부에 대해 L자형으로 일체로 형성되되, 내향으로 소정 곡률을 갖는 곡면부와, 그 상단부에는 종방향 볼트너트체결부와, 맞이음 요철결합부가, 측면부에는 횡방향 볼트너트체결부가 각각 구비된 좌, 우측벽부재와; 상기 좌, 우측벽부재의 곡면에 연장되며 전체적으로 하나의 아치형상으로 곡면 몸체가 구성되며, 그 몸체의 양측 하단부에는 상기 좌, 우측벽부재의 각 상단부에 구비된 종방향 볼트너트체결부에 대응되는 조립식 종방향 볼트너트체결부와 맞이음 요철결합부가 구비되고, 몸체의 측면부에는 횡방향 볼트너트체결부가 구비된 천정부재와; 상기 좌, 우측벽부재의 볼트너트체결부와 천정부재의 볼트너트체결부에 충전되는 발포우레탄 및 무수축몰탈과; 상기 좌, 우측벽부재와 천정부재의 연결부 내부 및 외부에 설치되는 방수시트 및 탄성실링재로 구성되는 터널부재를 이용한 조립식 아치터널에 있어서, 상기 터널부재는 적어도 2 이상의 일정한 크기를 갖는 단위부재가 분할된 상태로 조립 설치됨을 특징으로 한다.Prefabricated arch tunnel using a tunnel member having a reinforcing rib according to the present invention for achieving the above object and the concrete concrete is placed and cured; A fixing stand installed on the foundation concrete layer; It is seated on the fixed object, the bottom portion, and formed integrally in an L-shape with respect to the bottom portion, the curved portion having a predetermined curvature inward, the upper end of the longitudinal bolt nut fastening portion, the fitting concave-convex coupling portion The left and right side wall members are provided with side bolt nuts, respectively; The curved body extends to the curved surfaces of the left and right wall members, and has a curved shape as a whole, and both lower ends of the body correspond to longitudinal bolt nut fastening parts provided at each upper end of the left and right wall members. A prefabricated longitudinal bolt nut fastening portion and an uneven coupling portion, and a ceiling member having a transverse bolt nut fastening portion at a side portion of the body; Foamed urethane and non-condensation mortar filled in the bolt nut fastening portions of the left and right wall members and the bolt nut fastening portions of the ceiling members; In the prefabricated arch tunnel using a tunnel member consisting of a waterproof sheet and an elastic sealing material installed inside and outside the connecting portion of the left and right wall member and the ceiling member, the tunnel member is divided into unit members having at least two constant sizes It is characterized in that the assembly is installed in the state.

또한, 상기한 목적을 달성하기 위한 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법은 터널을 시공할 지면을 정리한 후, 콘크리트를 타설 및 양생시켜 기초콘크리트층을 형성하는 단계(Ⅰ); 상기 기초콘크리트층상에 고정대를 설치하는 단계(Ⅱ); 상기 고정대상에 좌, 우측벽부재를 설치하는 단계(Ⅲ); 상기 좌, 우측벽부재간에 천정부재를 거치하는 단계(Ⅳ); 상기 좌, 우측벽부재와 천정부재를 볼트너트로 체결하여 결합하는 단계(Ⅴ); 상기 좌, 우측벽부재와 천정부재를 볼트너트로 체결한 부위에 발포우레탄 및 무수축몰탈을 충전하여 터널구조체를 형성하는 단계(Ⅵ); 상기 단계(Ⅰ)로부터 단계(Ⅵ)를 반복하여 터널구조체를 형성하며, 각 터널구조체를 길이방향으로 연속적으로 연장 형성하는 단계(Ⅶ); 상기 좌, 우측벽부재와 천정부재 사이와 기초콘크리트층상에 콘크리트를 타설하여 바닥콘크리트층을 형성하는 단계(Ⅷ); 상기 바닥콘크리트층상에 일정한 두께 및 길이로 아스팔트를 포설하여 포장층을 형성하는 단계(Ⅸ); 상기 좌, 우측벽부재와 천정부재의 연결부 외부는 방수시트를 부착하고, 내부는 탄성실링재를 실링하여 터널구조체를 마감하는 단계(Ⅹ); 상기 터널구조체를 시공한 후, 터널구조체의 주위를 성토 및 다짐하는 단계(ⅩⅠ)를 순차적으로 시행하여 터널을 시공하는 터널부재를 이용한 조립식 아치터널 시공방법에 있어서, 상기 터널부재는 적어도 2 이상의 일정한 크기를 갖는 단위부재가 분할된 상태로 조립 설치함을 특징으로 한다.In addition, the prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib according to the present invention for achieving the above object is to clean up the ground to be constructed in the tunnel, then placing and curing concrete to form a foundation concrete layer (I); Installing a fixture on the foundation concrete layer (II); Installing left and right wall members on the fixed object (III); Mounting a ceiling member between the left and right wall members (IV); (V) fastening the left and right wall members and the ceiling member by bolt nuts; Forming a tunnel structure by filling the urethane foam and the non-shrink mortar to a portion where the left and right wall members and the ceiling member are fastened with bolt nuts (VI); (Iii) repeating step (VI) from step (I) to form tunnel structures, and continuously extending each tunnel structure in the longitudinal direction; Placing concrete between the left and right wall members and the ceiling member and on the foundation concrete layer to form a floor concrete layer; (Ⅸ) forming a paving layer by laying asphalt with a predetermined thickness and length on the bottom concrete layer; (Iii) attaching the waterproof sheet to the outside of the left and right wall members and the ceiling member to attach the waterproof sheet, and sealing the elastic sealing material to finish the tunnel structure; In the prefabricated arch tunnel construction method using a tunnel member for constructing a tunnel by sequentially performing the step (Ⅹ I) of the tunnel structure after the construction of the tunnel structure, the tunnel member is at least two constant Characterized in that the unit member having a size is assembled and installed in a divided state.

이하, 본 발명을 첨부한 예시도면을 참조하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, the present invention will be described in detail.

도 1은 본 발명에 따른 3분할 터널부재의 외부 표면에 종, 횡방향 리브가 형성된 상태를 도시한 예시도이며, 도 2는 본 발명에 따른 2분할 터널부재의 내부 표면에 종, 횡방향 리브가 형성된 상태를 도시한 예시도이며, 도 3은 본 발명에 따른 단일 터널아치부재의 내외부 표면에 종, 횡방향 리브가 형성된 상태를 도시한 예시도이며, 도 4는 본 발명에 따른 2분할 터널부재의 내외부 표면에 상하로 엇갈린 상태로 종, 횡방향 리브가 형성된 상태를 도시한 예시도이며, 도 5(a) 및 5(b)는 본 발명에 따른 터널부재간 볼트 체결 상태를 도시한 예시도이다.1 is an exemplary view showing a state in which the longitudinal, transverse ribs are formed on the outer surface of the three-split tunnel member according to the present invention, Figure 2 is a longitudinal, transverse ribs are formed on the inner surface of the two-split tunnel member according to the present invention Figure 3 is an exemplary view showing a state, Figure 3 is an exemplary view showing a longitudinal, transverse rib formed on the inner and outer surfaces of the single tunnel arch member according to the present invention, Figure 4 is an inner and outer parts of the two-split tunnel member according to the present invention Exemplary views showing a state in which longitudinal and lateral ribs are formed in a state where the surface is staggered up and down, and FIGS. 5 (a) and 5 (b) are exemplary views illustrating a bolt fastening state between tunnel members according to the present invention.

이들 도면에 도시된 바와 같이, 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널은 소정의 폭과 높이를 가지며, 콘크리트가 타설 및 양생된 기초콘크리트층(100)과; 상기 기초콘크리트층(100)상에 설치되는 고정대(220)와; 상기 고정대(220)상에 안착되며, 밑면부(110a, 120a)와, 그 밑면부(110a, 120a)에 대해 대략 L자형의 일체로 형성되되, 내향으로 소정곡률을 갖는 곡면부(110b, 120b)와, 그 상단부에는 종방향 볼트너트체결부(110c)와, 맞이음 요철결합부(120c)가, 측면부에는 횡방향 볼트너트체결부(151)이 각각 구비된 좌, 우측벽부재(110, 120)와; 상기 좌, 우측벽부재(110, 120)의 곡면에 연장되며 전체적으로 하나의 아치형상으로 곡면 몸체가 구성되며, 그 몸체의 양측 하단부에는 상기 좌, 우측벽부재(110, 120)의 각 상단부에 구비된 종방향 볼트너트체결부(110c)에 대응되는 조립식 종방향 볼트너트체결부(110c)와 맞이음 요철결합부(120c)가 구비되고, 몸체의 측면부에는 횡방향 볼트너트체결부(151)가 구비된 천정부재(130)와; 상기 좌,우측벽부재(110, 120)의 볼트너트체결부(110c)와 천정부재(130)의 볼트너트체결부(110c)에 충전되는 발포우레탄 및 무수축몰탈(223)과; 상기 좌, 우측벽부재(110, 120)와 천정부재(130)의 연결부 내부 및 외부에 설치되는 방수시트 및 탄성실링재(210)로 구성되는 터널부재를 이용한 조립식 아치터널에 있어서는 종래와 기술적 사상이 동일함을 밝혀둔다.As shown in these figures, the prefabricated arch tunnel using the tunnel member having a reinforcing rib according to the present invention has a predetermined width and height, and the concrete concrete layer 100 is cast and cured; A fixed base 220 installed on the basic concrete layer 100; Seated on the fixture 220, the bottom portion (110a, 120a) and the bottom portion (110a, 120a) of approximately L-shaped integrally formed, the curved portion 110b, 120b having a predetermined curvature inwardly ), The left and right side wall members 110, which are provided with a longitudinal bolt nut fastening part 110c, a fitting convex and concave coupling part 120c, and a lateral bolt nut fastening part 151 at a side part thereof, respectively. 120); The curved body extends to the curved surfaces of the left and right wall members 110 and 120 and has a curved body as a whole, and is provided at each upper end of the left and right wall members 110 and 120 at both lower ends of the body. The assembled longitudinal bolt nut fastening part 110c corresponding to the longitudinal bolt nut fastening part 110c is provided, and the concave-convex coupling part 120c is provided, and the lateral bolt nut fastening part 151 is provided on the side part of the body. A ceiling member 130 provided; Polyurethane foam and non-condensation mortar (223) is filled in the bolt nut fastening portion (110c) of the left and right wall members (110, 120) and the bolt nut fastening portion (110c) of the ceiling member 130; In the prefabricated arch tunnel using a tunnel member composed of a waterproof sheet and an elastic sealing member 210 installed inside and outside the connection parts of the left and right wall members 110 and 120 and the ceiling member 130, the technical idea Note the same.

다만, 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널에 있어서는 상기 터널부재는 적어도 2 이상의 일정한 크기를 갖는 단위부재(400)가 분할된 상태로 조립 설치되거나,However, in the prefabricated arch tunnel using a tunnel member having a reinforcing rib according to the present invention, the tunnel member is assembled or installed in a state in which the unit member 400 having a predetermined size of at least two or more is divided,

또는 상기 터널부재는 일정한 크기를 갖는 단위부재(400)가 일체로 형성됨을 특징으로 한다.Alternatively, the tunnel member may be integrally formed with a unit member 400 having a predetermined size.

즉, 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널은 크게 단위부재(400)와 터널아치부재(A)로 구성된다.That is, the prefabricated arch tunnel using the tunnel member having a reinforcing rib according to the present invention is largely composed of the unit member 400 and the tunnel arch member (A).

여기서, 상기 단위부재(400)는 적어도 2 이상의 일정한 크기를 갖고, 분할된 상태로 조립 설치되어 구조물을 형성함을 밝혀둔다.Here, the unit member 400 has a predetermined size of at least two or more, and is assembled to form a divided state to form a structure.

즉, 좌, 우측에 단위부재(400)가 대칭으로 설치되어, 2분할의 단위부재(400)로 구성된다.That is, the unit member 400 is installed symmetrically on the left and right sides, and is composed of a two-part unit member 400.

또한, 상기 단위부재(400)는 좌, 우측에 대칭으로 형성되고, 상기 좌, 우측 단위부재(400) 사이에 좌, 우측 단위부재(400)와 동일한 곡률을 갖는 단위부재(400)가 고정 설치되어, 3분할로 구성됨을 밝혀두는 바이다.In addition, the unit member 400 is formed symmetrically on the left and right, the unit member 400 having the same curvature as the left and right unit member 400 is fixedly installed between the left and right unit member 400 It is to be understood that it consists of three divisions.

그리고 상기 터널아치부재(A)는 일정한 크기를 갖는 단위부재(400)가 일체로 형성되어 구조물을 형성함을 밝혀둔다.And the tunnel arch member (A) is a unit member 400 having a certain size is formed integrally to form a structure.

한편, 상기 단위부재(400)와 터널아치부재(A)에는 표면에 다수의 종방향리브(310)들과 횡방향리브(320)들이 형성되며, 이 종방향리브(310)들과 횡방향리브(320)들에 의해서 단위부재(400)와 터널아치부재(A)의 단면적이 감소됨과 동시에 외력에 대한 저항력이 대폭 증가됨을 특징으로 한다.Meanwhile, a plurality of longitudinal ribs 310 and transverse ribs 320 are formed on the surface of the unit member 400 and the tunnel arch member A, and the longitudinal ribs 310 and the transverse ribs are formed on the surface thereof. The cross-sectional area of the unit member 400 and the tunnel arch member A is reduced by the 320 and at the same time, the resistance to external force is greatly increased.

여기서, 상기 종, 횡방향리브(310, 320)들의 위치와 수량은 재하조건, 지질조건에 따라 단위부재(400)와 터널아치부재(A)의 내측면 또는 외측면 또는 내외측면에 선택적으로 형성된 구조이다.Here, the position and quantity of the longitudinal, transverse ribs (310, 320) is selectively formed on the inner side or the outer side or the inner and outer side of the unit member 400 and the tunnel arch member (A) according to the loading conditions, geological conditions Structure.

또한, 상기 종방향리브(310)는 단위부재(400) 또는 터널아치부재(A)의 내측면 또는 외측면 또는 내외측면 또는 내외측면에 설치위치가 교호적으로 엇갈린 상태로 선택적으로 형성된 구조이다.In addition, the longitudinal rib 310 is a structure selectively formed in the alternate position alternately on the inner side or the outer side or the inner and outer side or the inner and outer side of the unit member 400 or tunnel arch member (A).

그리고 상기 단위부재(400) 또는 터널아치부재(A)간의 상하 결합은 볼트체결방식을 적용하고, 상기 단위부재(400) 또는 터널아치부재(A)간의 종방향 연결은 볼트체결방식 또는 종방향리브(310) 내에 형성되는 종방향 연결공(330)을 관통하는 PC강선(강봉)체결방식을 선택적으로 사용함을 밝혀둔다.The vertical coupling between the unit member 400 or the tunnel arch member A applies a bolting method, and the longitudinal connection between the unit member 400 or the tunnel arch member A is a bolting method or a longitudinal rib. It turns out that the PC steel wire (steel rod) fastening method that selectively penetrates the longitudinal connection hole 330 formed in the 310.

즉, 단위부재(400) 또는 터널아치부재(A)의 내측면 또는 외측면 또는 내외측면에 종방향 및 횡방향 리브(310, 320)가 형성됨으로써, 평활면을 갖는 터널부재에 비하여 단면 2차 모멘트가 많이 증가함에 따라 재하조건, 지질조건 등의 동일한 설계조건하에서 단위부재(400) 또는 터널아치부재(A)들의 단면적을 많이 감소시킬 수 있고, 동일한 중량일 경우에는 단위부재(400) 또는 터널아치부재(A)들의 종방향 길이를 증가시킬 수 있으며, 또한 상기 종, 횡방향 리브(310, 320)는 체결부위의 구조적 안정성을 확보할 수 있음과 동시에 외력에 대한 저항력이 많이 증가하는 작용효과가 있다.That is, longitudinal and transverse ribs 310 and 320 are formed on the inner side, the outer side, or the inner and outer side surfaces of the unit member 400 or the tunnel arch member A, so that the cross section is secondary to the tunnel member having the smooth surface. As the moment increases a lot, the cross-sectional area of the unit member 400 or the tunnel arch members A may be greatly reduced under the same design conditions such as loading conditions and geological conditions, and in the case of the same weight, the unit member 400 or the tunnel The longitudinal length of the arch members (A) can be increased, and the longitudinal and lateral ribs (310, 320) can ensure the structural stability of the fastening portion and at the same time the effect of increasing the resistance to external forces much There is.

또한, 상기 종, 횡방향 리브(310, 320)를 단위부재(400) 또는 터널아치부재(A)의 내부 표면에 형성할 경우에는 터널 내부 조명, 전기통신 배선 등의 부속 시설물의 안전과 점검대로 활용할 수 있을 뿐만 아니라 터널 내부의 경관을 수려하게 조성할 수 있고, 터널 내부의 소음을 분산시키는 작용효과가 있다.In addition, when the longitudinal and transverse ribs 310 and 320 are formed on the inner surface of the unit member 400 or the tunnel arch member A, the safety and inspection of the accessory facilities such as tunnel interior lighting, telecommunication wiring, etc. Not only can it be utilized, the scenery inside the tunnel can be created beautifully, and there is an effect of dispersing the noise inside the tunnel.

그리고 상기 종, 횡방향 리브(310, 320)는 외력에 대한 저항성이 크게 향상됨으로써, 단위부재(400) 또는 터널아치부재(A)의 조립 설치 후 인접부위 성토 다짐 작업시 층다짐두께를 크게 할 수 있으므로 시공성이 크게 향상되고, 중장비 사용으로 인한 다짐작업시의 하중이나 진동 및 충격으로 인한 균열을 예방할 수 있어 안정성 향상에 기여하는 작용효과가 있다.In addition, the longitudinal and horizontal ribs 310 and 320 have greatly improved resistance to external force, thereby increasing the compaction thickness during the compaction work of adjacent parts after assembling and installing the unit member 400 or the tunnel arch member A. Since the workability can be greatly improved, and cracks due to the load, vibration and impact during compaction work due to the use of heavy equipment can be prevented, which contributes to the improvement of stability.

이하, 상기한 바와 같은 구성으로 이루어진 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공에 대해서 설명한다.Hereinafter, the construction of the prefabricated arch tunnel using the tunnel member having a reinforcing rib according to the present invention having the configuration as described above.

도 6(a) 내지 6(e)는 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널을 시공하는 상태를 도시한 공정도이다.6 (a) to 6 (e) is a process diagram showing a state of constructing a prefabricated arch tunnel using a tunnel member having a reinforcing rib according to the present invention.

이들 도면에 도시된 바와 같이, 본 발명에 따른 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법은 터널을 시공할 지면을 정리한 후, 콘크리트를 타설 및 양생시켜 기초콘크리트층(100)을 형성하는 단계(Ⅰ); 상기 기초콘크리트층(100)상에 고정대(220)를 설치하는 단계(Ⅱ); 상기 고정대(220)상에 좌, 우측벽부재(110, 120)를 설치하는 단계(Ⅲ); 상기 좌, 우측벽부재(110, 120)간에 천정부재(130)를 거치하는 단계(Ⅳ); 상기 좌, 우측벽부재(110, 120)와 천정부재(130)를 볼트너트로 체결하여 결합하는 단계(Ⅴ); 상기 좌, 우측벽부재(110, 120)와 천정부재(130)를 볼트너트로 체결한 부위에 발포우레탄 및 무수축몰탈(223)을 충전하여 터널구조체를 형성하는 단계(Ⅵ); 상기 단계(Ⅰ)로부터 단계(Ⅵ)를 반복하여 터널구조체를 형성하며, 각 터널구조체를 길이방향으로 연속적으로 연장 형성하는 단계(Ⅶ); 상기 좌, 우측벽부재(110, 120)와 천정부재(130) 사이와 기초콘크리트층(100)상에 콘크리트를 타설하여 바닥콘크리트층(102)을 형성하는 단계(Ⅷ); 상기 바닥콘크리트층(102)상에 일정한 두께 및 길이로 아스팔트를 포설하여 포장층(104)을 형성하는 단계(Ⅸ); 상기 좌, 우측벽부재(110, 120)와 천정부재(130)의 연결부 외부는 방수시트를 부착하고, 내부는 탄성실링재(210)를 실링하여 터널구조체를 마감하는 단계(Ⅹ); 상기 터널구조체를 시공한 후, 터널구조체의 주위를 성토 및 다짐하는 단계(ⅩⅠ)를 순차적으로 시행하여 터널을 시공하는 터널부재를 이용한 조립식 아치터널 시공방법에 있어서, As shown in these drawings, the prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib according to the present invention after cleaning the ground on which the tunnel is to be constructed, placing and curing concrete to form the foundation concrete layer 100 Step (I); Installing a fixture 220 on the foundation concrete layer (100); Installing left and right wall members (110, 120) on the holder (220) (III); Mounting a ceiling member (130) between the left and right wall members (110, 120) (IV); (V) fastening the left and right wall members (110, 120) and the ceiling member (130) by bolt nuts; Forming a tunnel structure by filling the urethane foam and the non-shrink mortar 223 at a portion where the left and right wall members 110 and 120 and the ceiling member 130 are fastened with bolt nuts; (Iii) repeating step (VI) from step (I) to form tunnel structures, and continuously extending each tunnel structure in the longitudinal direction; Placing concrete between the left and right wall members (110, 120) and the ceiling member (130) and on the foundation concrete layer (100) to form a bottom concrete layer (102); Laying asphalt on the bottom concrete layer (102) in a predetermined thickness and length to form a pavement layer (104); A step of attaching a waterproof sheet to the outside of the left and right wall members 110 and 120 and the ceiling member 130 to attach a waterproof sheet, and sealing the elastic sealing material 210 to finish the tunnel structure; In the prefabricated arch tunnel construction method using the tunnel member for constructing the tunnel by sequentially performing the step (Ⅹ I) to build and compact around the tunnel structure after the construction of the tunnel structure,

상기 터널부재는 적어도 2 이상의 일정한 크기를 갖는 단위부재(400)가 분할된 상태로 조립 설치하거나, The tunnel member is assembled or installed in a state in which the unit member 400 having a predetermined size of at least two or more is divided,

또는, 터널부재는 일정한 크기를 갖는 단위부재(400)가 일체로 형성함을 특징으로 한다.Alternatively, the tunnel member is characterized in that the unit member 400 having a predetermined size is formed integrally.

즉, 상기 단위부재(400)는 좌, 우측에 대칭으로 설치되어, 2분할로 구성된다.That is, the unit member 400 is installed symmetrically on the left and right, it is composed of two divisions.

또한, 상기 단위부재(400)는 좌, 우측에 대칭으로 형성되고, 상기 좌, 우측 단위부재(400) 사이에 좌우측 단위부재(400)와 동일한 곡률을 갖는 단위부재(400)가 고정 설치되어, 3분할 단위부재(400)로 구성됨을 밝혀두는 바이다.In addition, the unit member 400 is formed symmetrically to the left and right, the unit member 400 having the same curvature as the left and right unit member 400 is fixedly installed between the left and right unit member 400, It is to be understood that it consists of a three-division unit member (400).

그리고 상기 터널아치부재(A)는 일정한 크기를 갖는 단위부재(400)가 일체로 형성되어 구조물을 형성함을 밝혀둔다.And the tunnel arch member (A) is a unit member 400 having a certain size is formed integrally to form a structure.

여기서, 상기 단위부재(400)나 터널아치부재(A)의 표면에는 다수의 종방향리브(310)들과 횡방향리브(320)들이 형성되며, 이 종방향리브(310)들과 횡방향리브(320)들에 의해서 단위부재(400)와 터널아치부재(A)의 단면적이 감소됨과 동시에 외력에 대한 저항력이 대폭 증가됨을 특징으로 한다.Here, a plurality of longitudinal ribs 310 and transverse ribs 320 are formed on the surface of the unit member 400 or the tunnel arch member A, and the longitudinal ribs 310 and the transverse ribs are formed. The cross-sectional area of the unit member 400 and the tunnel arch member A is reduced by the 320 and at the same time, the resistance to external force is greatly increased.

그리고 상기 종, 횡방향리브(310, 320)들의 위치와 수량은 재하조건, 지질조건에 따라 단위부재(400) 또는 터널아치부재(A)들의 내측면 또는 외측면 또는 내외측면에 선택적으로 형성한다.And the position and the number of the longitudinal ribs (310, 320) is selectively formed on the inner surface or the outer surface or the inner and outer surface of the unit member 400 or tunnel arch members (A) according to the loading conditions, geological conditions .

또한, 상기 종방향리브(310)는 단위부재(400) 또는 터널아치부재(A)의 내측면 또는 외측면 또는 내외측면 또는 내외측면에 설치위치가 교호적으로 엇갈린 상태로 선택적으로 형성한다.In addition, the longitudinal rib 310 is selectively formed on the inner side or the outer side or the inner and outer side or the inner and outer side of the unit member 400 or the tunnel arch member (A) alternately staggered.

그리고 상기 단위부재(400) 또는 터널아치부재(A)간의 상하 결합은 볼트체결방식을 적용하고, 상기 단위부재(400) 또는 터널아치부재(A)간의 종방향 연결은 볼트체결방식 또는 종방향리브(310)내에 형성되는 종방향연결공(330)을 관통하는 PC강선(강봉)체결방식을 선택적으로 사용하여 시공함을 밝혀두는 바이다.The vertical coupling between the unit member 400 or the tunnel arch member A applies a bolting method, and the longitudinal connection between the unit member 400 or the tunnel arch member A is a bolting method or a longitudinal rib. It is to be understood that the construction by selectively using a PC steel wire (steel rod) fastening method penetrating the longitudinal connection hole 330 formed in (310).

이상에서 설명한 바와 같이, 본 발명에 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 및 그 시공방법은 다음과 같은 효과가 있다.As described above, the prefabricated arch tunnel and the construction method using the tunnel member having a reinforcing rib in the present invention has the following effects.

첫째, 본 발명은 보강리브를 갖는 단면으로, 평활면을 갖는 단면에 비하여 단면 2차 모멘트가 많이 증가하므로 재하조건, 지질조건 등의 동일한 설계조건하에서는 단위부재의 단면적을 많이 감소시킬 수 있고, 중량이 감소되므로 운반 및 취급이 용이하며, 시공성도 대폭향상되며, 경제성을 확보할 수 있는 이점이 있다.First, the present invention is a cross section having a reinforcing rib, the cross-sectional secondary moment is increased much compared to the cross section having a smooth surface, it is possible to reduce the cross-sectional area of the unit member much under the same design conditions, such as loading conditions, geological conditions, weight Since it is reduced, it is easy to transport and handle, greatly improves the workability, there is an advantage that can be secured economical.

둘째, 본 발명은 보강리브를 갖는 단면으로, 평활면을 갖는 단면에 비하여 동일한 중량일 경우에는 단위부재들의 종방향 길이를 증가시킬 수 있으므로, 전체적인 소요부재의 수량을 축소할 수 있어 경제성이 향상되는 이점이 있다.Second, the present invention is a cross section having a reinforcing rib, when the same weight as compared to the cross section having a smooth surface can increase the longitudinal length of the unit member, it is possible to reduce the total number of required member to improve the economic efficiency There is an advantage.

셋째, 본 발명은 보강리브를 갖는 단면으로, 보강리브는 체결부위의 구조적 안정성을 확보함과 동시에 외력에 대한 저항력이 많이 증가하는 장점이 있다.Third, the present invention is a cross section having a reinforcing rib, the reinforcing rib has the advantage of increasing the resistance to external forces while ensuring the structural stability of the fastening portion.

넷째, 본 발명은 보강리브를 갖는 단면으로, 터널 내측에 보강리브를 설치할 경우에는 내부 조명, 전기통신 배선 등의 부속 시설물의 안전과 점검대로 활용하여 터널 내부의 경과를 조성할 수 있을 뿐만 아니라 소음을 분산시키는 이점이 있다.Fourth, the present invention is a cross-section having a reinforcing rib, when installing the reinforcing rib inside the tunnel can utilize the safety and inspection of the auxiliary facilities, such as internal lighting, telecommunication wiring, etc. as well as create the passage of the interior of the tunnel noise There is an advantage to disperse.

다섯째, 본 발명은 보강리브를 갖는 단면으로, 외력에 대한 저항성이 크게 향상됨으로써, 아치부재의 조립 설치 후 인접부위 성토 다짐 작업시 층다짐두께를 크게 할 수 있으므로 시공성이 크게 향상되고, 중장비 사용으로 인한 다짐작업시의 하중이나 진동 및 충격으로 인한 균열을 예방할 수 있어 안정성 향상에 기여하는 이점이 있다. Fifth, the present invention is a cross section having a reinforcing rib, the resistance to external force is greatly improved, so that the compaction thickness can be increased during the compaction work of the adjacent site after assembling and installing the arch member, the construction performance is greatly improved, and the use of heavy equipment It is possible to prevent cracks due to load or vibration and impact during compaction work, which has the advantage of improving stability.

Claims (32)

콘크리트가 타설 및 양생된 기초콘크리트층과; 상기 기초콘크리트층상에 설치되는 고정대와; 상기 고정대상에 안착되며, 밑면부와, 그 밑면부에 대해 L자형으로 일체로 형성되되, 내향으로 곡률을 갖는 곡면부와, 그 상단부에는 종방향 볼트너트체결부와, 맞이음 요철결합부가, 측면부에는 횡방향 볼트너트체결부가 각각 구비된 좌, 우측벽부재와; 상기 좌, 우측벽부재의 곡면에 연장되며 전체적으로 하나의 아치형상으로 곡면 몸체가 구성되며, 그 몸체의 양측 하단부에는 상기 좌, 우측벽부재의 각 상단부에 구비된 종방향 볼트너트체결부에 대응되는 조립식 종방향 볼트너트체결부와 맞이음 요철결합부가 구비되고, 몸체의 측면부에는 횡방향 볼트너트체결부가 구비된 천정부재와; 상기 좌, 우측벽부재의 볼트너트체결부와 천정부재의 볼트너트체결부에 충전되는 발포우레탄 및 무수축몰탈과; 상기 좌, 우측벽부재와 천정부재의 연결부 내부 및 외부에 설치되는 방수시트 및 탄성실링재로 구성되는 터널부재를 이용한 조립식 아치터널에 있어서,A base concrete layer in which concrete is poured and cured; A fixing stand installed on the foundation concrete layer; Seated on the fixed object, the bottom portion, and integrally formed in the L-shape with respect to the bottom portion, the curved portion having a curvature inward, the upper end of the longitudinal bolt nut fastening portion, the fitting concave-convex coupling portion, The left side and the right side wall member each provided with a lateral bolt nut fastening part in the side part; The curved body extends to the curved surfaces of the left and right wall members, and has a curved shape as a whole, and both lower ends of the body correspond to longitudinal bolt nut fastening parts provided at each upper end of the left and right wall members. A prefabricated longitudinal bolt nut fastening portion and an uneven coupling portion, and a ceiling member having a transverse bolt nut fastening portion at a side portion of the body; Foamed urethane and non-condensation mortar filled in the bolt nut fastening portions of the left and right wall members and the bolt nut fastening portions of the ceiling members; In the prefabricated arch tunnel using a tunnel member consisting of a waterproof sheet and an elastic sealing material installed inside and outside the connecting portion of the left and right wall members and the ceiling member, 상기 터널부재는 적어도 2 이상의 일정한 크기를 갖는 단위부재가 분할된 상태로 조립 설치되며, 상기 단위부재의 표면에는 다수의 종방향리브들과 횡방향리브들이 형성되며, 이 종방향리브들과 횡방향리브들에 의해서 터널부재의 단면적이 감소됨과 동시에 외력에 대한 저항력이 증가됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널. The tunnel member is assembled and installed in a state in which unit members having at least two predetermined sizes are divided, and a plurality of longitudinal ribs and transverse ribs are formed on a surface of the unit member, and the longitudinal ribs and the transverse direction are formed. Prefabricated arch tunnel using a tunnel member having a reinforcing rib characterized in that the cross-sectional area of the tunnel member is reduced by the ribs and the resistance to external force is increased. 삭제delete 삭제delete 삭제delete 제 1항에 있어서,The method of claim 1, 상기 종방향리브는 단위부재의 내측면에 형성됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널.The longitudinal rib is a prefabricated arch tunnel using a tunnel member having a reinforcing rib, characterized in that formed on the inner surface of the unit member. 제 1항에 있어서,The method of claim 1, 상기 종방향리브는 단위부재의 외측면에 형성됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널.The longitudinal rib is a prefabricated arch tunnel using a tunnel member having a reinforcing rib, characterized in that formed on the outer surface of the unit member. 제 1항에 있어서,The method of claim 1, 상기 종방향리브는 단위부재의 내측면과 외측면에 형성됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널.The longitudinal rib is a prefabricated arch tunnel using a tunnel member having a reinforcing rib, characterized in that formed on the inner surface and the outer surface of the unit member. 제 1항에 있어서,The method of claim 1, 상기 종방향리브는 단위부재의 내측면과 외측면에 엇갈린 상태로 교호적으로 형성됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널.The longitudinal rib is prefabricated arch tunnel using a tunnel member having a reinforcing rib, characterized in that alternately formed on the inner side and the outer side of the unit member. 제 1항에 있어서,The method of claim 1, 상기 단위부재간의 상하 결합은 볼트체결방식을 적용하고, 상기 단위부재간의 종방향 연결은 볼트체결방식 또는 종방향리브내에 형성되는 종방향연결공을 관통하는 PC강선 체결방식을 선택적으로 사용함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널. The vertical coupling between the unit members is applied by the bolt fastening method, and the longitudinal connection between the unit members is selectively used by the bolt fastening method or the PC steel wire fastening method penetrating the longitudinal connection hole formed in the longitudinal rib. Prefabricated arch tunnel using a tunnel member having a reinforcing rib. 콘크리트가 타설 및 양생된 기초콘크리트층과; 상기 기초콘크리트층상에 설치되는 고정대와; 상기 고정대상에 안착되며, 밑면부와, 그 밑면부에 대해 L자형으로 일체로 형성되되, 내향으로 곡률을 갖는 곡면부와, 그 상단부에는 종방향 볼트너트체결부와, 맞이음 요철결합부가, 측면부에는 횡방향 볼트너트체결부가 각각 구비된 좌,우측벽부재와; 상기 좌,우측벽부재의 곡면에 연장되며 전체적으로 하나의 아치형상으로 곡면 몸체가 구성되며, 그 몸체의 양측 하단부에는 상기 좌,우측벽부재의 각 상단부에 구비된 종방향 볼트너트체결부에 대응되는 조립식 종방향 볼트너트체결부와 맞이음 요철결합부가 구비되고, 몸체의 측면부에는 횡방향 볼트너트체결부가 구비된 천정부재와; 상기 좌,우측벽부재의 볼트너트체결부와 천정부재의 볼트너트체결부에 충전되는 발포우레탄 및 무수축몰탈과; 상기 좌,우측벽부재와 천정부재의 연결부 내부 및 외부에 설치되는 방수시트 및 탄성실링재로 구성되는 터널부재를 이용한 조립식 아치터널에 있어서,A base concrete layer in which concrete is poured and cured; A fixing stand installed on the foundation concrete layer; Seated on the fixed object, the bottom portion, and integrally formed in the L-shape with respect to the bottom portion, the curved portion having a curvature inward, the upper end of the longitudinal bolt nut fastening portion, the fitting concave-convex coupling portion, The left side and the right side wall member each provided with a transverse bolt nut fastening part; The curved body extends to the curved surfaces of the left and right wall members and has a curved shape as a whole, and both lower ends of the body correspond to longitudinal bolt nut fastening parts provided at each upper end of the left and right wall members. A prefabricated longitudinal bolt nut fastening portion and an uneven coupling portion, and a ceiling member having a transverse bolt nut fastening portion at a side portion of the body; Foamed urethane and non-contraction mortar filled in the bolt nut fastening portions of the left and right wall members and the bolt nut fastening portions of the ceiling member; In the prefabricated arch tunnel using a tunnel member consisting of a waterproof sheet and an elastic sealing member installed inside and outside the connecting portion of the left and right wall members and the ceiling member, 상기 터널부재는 일정한 크기를 갖는 단위부재가 일체로 형성되며, 상기 단위부재의 표면에는 다수의 종방향리브들과 횡방향리브들이 형성되며, 이 종방향리브들과 횡방향리브들에 의해서 터널부재의 단면적이 감소됨과 동시에 외력에 대한 저항력이 증가됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널. The tunnel member is integrally formed with a unit member having a predetermined size, and a plurality of longitudinal ribs and transverse ribs are formed on the surface of the unit member, and the tunnel member is formed by the longitudinal ribs and the transverse ribs. Prefabricated arch tunnel using a tunnel member having a reinforcing rib characterized in that the cross-sectional area of the cross section is reduced and resistance to external force is increased. 삭제delete 제 10항에 있어서,The method of claim 10, 상기 종방향리브는 단위부재의 내측면에 형성됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널.The longitudinal rib is a prefabricated arch tunnel using a tunnel member having a reinforcing rib, characterized in that formed on the inner surface of the unit member. 제 10항에 있어서,The method of claim 10, 상기 종방향리브는 단위부재의 외측면에 형성됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널.The longitudinal rib is a prefabricated arch tunnel using a tunnel member having a reinforcing rib, characterized in that formed on the outer surface of the unit member. 제 10항에 있어서,The method of claim 10, 상기 종방향리브는 단위부재의 내측면과 외측면에 형성됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널.The longitudinal rib is a prefabricated arch tunnel using a tunnel member having a reinforcing rib, characterized in that formed on the inner surface and the outer surface of the unit member. 제 10항에 있어서,The method of claim 10, 상기 종방향리브는 단위부재의 내측면과 외측면에 엇갈린 상태로 교호적으로 형성됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널.The longitudinal rib is prefabricated arch tunnel using a tunnel member having a reinforcing rib, characterized in that alternately formed on the inner side and the outer side of the unit member. 제 10항에 있어서,The method of claim 10, 상기 단위부재간의 상하 결합은 볼트체결방식을 적용하고, 상기 단위부재간의 종방향 연결은 볼트체결방식 또는 종방향리브내에 형성되는 종방향연결공을 관통하는 PC강선 체결방식을 선택적으로 사용함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널. The vertical coupling between the unit members is applied by the bolt fastening method, and the longitudinal connection between the unit members is selectively used by the bolt fastening method or the PC steel wire fastening method penetrating the longitudinal connection hole formed in the longitudinal rib. Prefabricated arch tunnel using a tunnel member having a reinforcing rib. 터널을 시공할 지면을 정리한 후, 콘크리트를 타설 및 양생시켜 기초콘크리트층을 형성하는 단계(Ⅰ); 상기 기초콘크리트층상에 고정대를 설치하는 단계(Ⅱ); 상기 고정대상에 좌,우측벽부재를 설치하는 단계(Ⅲ); 상기 좌,우측벽부재간에 천정부재를 거치하는 단계(Ⅳ); 상기 좌, 우측벽부재와 천정부재를 볼트너트로 체결하여 결합하는 단계(Ⅴ); 상기 좌, 우측벽부재와 천정부재를 볼트너트로 체결한 부위에 발포우레탄 및 무수축몰탈을 충전하여 터널구조체를 형성하는 단계(Ⅵ); 상기 단계(Ⅰ)로부터 단계(Ⅵ)를 반복하여 터널구조체를 형성하며, 각 터널구조체를 길이방향으로 연속적으로 연장 형성하는 단계(Ⅶ); 상기 좌, 우측벽부재와 천정부재 사이와 기초콘크리트층상에 콘크리트를 타설하여 바닥콘크리트층을 형성하는 단계(Ⅷ); 상기 바닥콘크리트층상에 일정한 두께 및 길이로 아스팔트를 포설하여 포장층을 형성하는 단계(Ⅸ); 상기 좌, 우측벽부재와 천정부재의 연결부 외부는 방수시트를 부착하고, 내부는 탄성실링재를 실링하여 터널구조체를 마감하는 단계(Ⅹ); 상기 터널구조체를 시공한 후, 터널구조체의 주위를 성토 및 다짐하는 단계(ⅩⅠ)를 순차적으로 시행하여 터널을 시공하는 터널부재를 이용한 조립식 아치터널 시공방법에 있어서,After arranging the ground to be constructed in the tunnel, placing and curing concrete to form a foundation concrete layer (I); Installing a fixture on the foundation concrete layer (II); Installing left and right wall members to the fixed object (III); Mounting a ceiling member between the left and right wall members (IV); (V) fastening the left and right wall members and the ceiling member by bolt nuts; Forming a tunnel structure by filling the urethane foam and the non-shrink mortar to a portion where the left and right wall members and the ceiling member are fastened with bolt nuts (VI); (Iii) repeating step (VI) from step (I) to form tunnel structures, and continuously extending each tunnel structure in the longitudinal direction; Placing concrete between the left and right wall members and the ceiling member and on the foundation concrete layer to form a floor concrete layer; (Ⅸ) forming a paving layer by laying asphalt with a predetermined thickness and length on the bottom concrete layer; (Iii) attaching the waterproof sheet to the outside of the left and right wall members and the ceiling member to attach the waterproof sheet, and sealing the elastic sealing material to finish the tunnel structure; In the prefabricated arch tunnel construction method using the tunnel member for constructing the tunnel by sequentially performing the step (Ⅹ I) to build and compact around the tunnel structure after the construction of the tunnel structure, 상기 터널부재는 적어도 2 이상의 일정한 크기를 갖는 단위부재가 분할된 상태로 조립 설치하며, 상기 단위부재의 표면에는 다수의 종방향리브들과 횡방향리브들을 형성하며, 이 종방향리브들과 횡방향리브들에 의해서 터널부재의 단면적이 감소됨과 동시에 외력에 대한 저항력이 증가됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법. The tunnel member is assembled and installed in a state in which at least two unit members having a predetermined size are divided, and a plurality of longitudinal ribs and transverse ribs are formed on the surface of the unit member, and the longitudinal ribs and the transverse direction are formed. Prefabricated arch tunnel construction method using a tunnel member having a reinforced rib characterized in that the cross-sectional area of the tunnel member is reduced by the ribs at the same time the resistance to external forces increases. 삭제delete 삭제delete 삭제delete 제 17항에 있어서,The method of claim 17, 상기 종방향리브를 단위부재의 내측면에 형성함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법.Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib characterized in that the longitudinal rib is formed on the inner surface of the unit member. 제 17항에 있어서,The method of claim 17, 상기 종방향리브를 단위부재의 외측면에 형성함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법.Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib characterized in that the longitudinal rib is formed on the outer surface of the unit member. 제 17항에 있어서,The method of claim 17, 상기 종방향리브를 단위부재의 내측면과 외측면에 형성함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법.Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib characterized in that the longitudinal ribs are formed on the inner and outer surfaces of the unit member. 제 17항에 있어서,The method of claim 17, 상기 종방향리브를 단위부재의 내측면과 외측면에 엇갈린 상태로 교호적으로 형성함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법.The longitudinal arch is prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib alternately formed on the inner surface and the outer surface of the unit member alternately. 제 17항에 있어서,The method of claim 17, 상기 단위부재간의 상하 결합은 볼트체결방식을 적용하고, 상기 단위부재간의 종방향 연결은 볼트체결방식 또는 종방향리브내에 형성되는 종방향연결공을 관통하는 PC강선 체결방식을 선택적으로 사용함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법. The vertical coupling between the unit members is applied by the bolt fastening method, and the longitudinal connection between the unit members is selectively used by the bolt fastening method or the PC steel wire fastening method penetrating the longitudinal connection hole formed in the longitudinal rib. Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib. 터널을 시공할 지면을 정리한 후, 콘크리트를 타설 및 양생시켜 기초콘크리트층을 형성하는 단계(Ⅰ); 상기 기초콘크리트층상에 고정대를 설치하는 단계(Ⅱ); 상기 고정대상에 좌,우측벽부재를 설치하는 단계(Ⅲ); 상기 좌,우측벽부재간에 천정부재를 거치하는 단계(Ⅳ); 상기 좌, 우측벽부재와 천정부재를 볼트너트로 체결하여 결합하는 단계(Ⅴ); 상기 좌, 우측벽부재와 천정부재를 볼트너트로 체결한 부위에 발포우레탄 및 무수축몰탈을 충전하여 터널구조체를 형성하는 단계(Ⅵ); 상기 단계(Ⅰ)로부터 단계(Ⅵ)를 반복하여 터널구조체를 형성하며, 각 터널구조체를 길이방향으로 연속적으로 연장 형성하는 단계(Ⅶ); 상기 좌, 우측벽부재와 천정부재 사이와 기초콘크리트층상에 콘크리트를 타설하여 바닥콘크리트층을 형성하는 단계(Ⅷ); 상기 바닥콘크리트층상에 일정한 두께 및 길이로 아스팔트를 포설하여 포장층을 형성하는 단계(Ⅸ); 상기 좌, 우측벽부재와 천정부재의 연결부 외부는 방수시트를 부착하고, 내부는 탄성실링재를 실링하여 터널구조체를 마감하는 단계(Ⅹ); 상기 터널구조체를 시공한 후, 터널구조체의 주위를 성토 및 다짐하는 단계(ⅩⅠ)를 순차적으로 시행하여 터널을 시공하는 터널부재를 이용한 조립식 아치터널 시공방법에 있어서,After arranging the ground to be constructed in the tunnel, placing and curing concrete to form a foundation concrete layer (I); Installing a fixture on the foundation concrete layer (II); Installing left and right wall members to the fixed object (III); Mounting a ceiling member between the left and right wall members (IV); (V) fastening the left and right wall members and the ceiling member by bolt nuts; Forming a tunnel structure by filling the urethane foam and the non-shrink mortar to a portion where the left and right wall members and the ceiling member are fastened with bolt nuts (VI); (Iii) repeating step (VI) from step (I) to form tunnel structures, and continuously extending each tunnel structure in the longitudinal direction; Placing concrete between the left and right wall members and the ceiling member and on the foundation concrete layer to form a floor concrete layer; (Ⅸ) forming a paving layer by laying asphalt with a predetermined thickness and length on the bottom concrete layer; (Iii) attaching the waterproof sheet to the outside of the left and right wall members and the ceiling member to attach the waterproof sheet, and sealing the elastic sealing material to finish the tunnel structure; In the prefabricated arch tunnel construction method using the tunnel member for constructing the tunnel by sequentially performing the step (Ⅹ I) to build and compact around the tunnel structure after the construction of the tunnel structure, 상기 터널부재는 일정한 크기를 갖는 단위부재를 일체로 형성하며, 상기 단위부재의 표면에는 다수의 종방향리브들과 횡방향리브들을 형성하며, 이 종방향리브들과 횡방향리브들에 의해서 터널부재의 단면적이 감소됨과 동시에 외력에 대한 저항력이 증가됨을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법. The tunnel member integrally forms a unit member having a predetermined size, and a plurality of longitudinal ribs and transverse ribs are formed on the surface of the unit member, and the tunnel member is formed by the longitudinal ribs and the transverse ribs. Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib characterized in that the cross-sectional area of the reduction and at the same time increased resistance to external forces. 삭제delete 제 26항에 있어서,The method of claim 26, 상기 종방향리브를 단위부재의 내측면에 형성함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법.Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib characterized in that the longitudinal rib is formed on the inner surface of the unit member. 제 26항에 있어서,The method of claim 26, 상기 종방향리브를 단위부재의 외측면에 형성함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법.Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib characterized in that the longitudinal rib is formed on the outer surface of the unit member. 제 26항에 있어서,The method of claim 26, 상기 종방향리브를 단위부재의 내측면과 외측면에 형성함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법.Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib characterized in that the longitudinal ribs are formed on the inner and outer surfaces of the unit member. 제 26항에 있어서,The method of claim 26, 상기 종방향리브를 단위부재의 내측면과 외측면에 엇갈린 상태로 교호적으로 형성함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법.The longitudinal arch is prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib alternately formed on the inner surface and the outer surface of the unit member alternately. 제 26항에 있어서,The method of claim 26, 상기 단위부재간의 상하 결합은 볼트체결방식을 적용하고, 상기 단위부재간의 종방향 연결은 볼트체결방식 또는 종방향리브내에 형성되는 종방향연결공을 관통하는 PC강선 체결방식을 선택적으로 사용함을 특징으로 하는 보강리브를 갖는 터널부재를 이용한 조립식 아치터널 시공방법. The vertical coupling between the unit members is applied by the bolt fastening method, and the longitudinal connection between the unit members is selectively used by the bolt fastening method or the PC steel wire fastening method penetrating the longitudinal connection hole formed in the longitudinal rib. Prefabricated arch tunnel construction method using a tunnel member having a reinforcing rib.
KR1020060100123A 2006-09-28 2006-10-16 The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method KR100732622B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR20060094473 2006-09-28
KR1020060094473 2006-09-28

Publications (1)

Publication Number Publication Date
KR100732622B1 true KR100732622B1 (en) 2007-06-27

Family

ID=38373506

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060100123A KR100732622B1 (en) 2006-09-28 2006-10-16 The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method

Country Status (1)

Country Link
KR (1) KR100732622B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101750987B1 (en) * 2016-09-29 2017-06-26 전종환 Precast segment arch structure and method for constructing this same
CN110486040A (en) * 2019-07-08 2019-11-22 重庆交通大学 A kind of prefbricated tunnel lining structure for vcehicular tunnel

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040018002A (en) * 2002-08-24 2004-03-02 주식회사 우일 이알에스 Fabricated arch tunnel and construction method thereof
KR200417221Y1 (en) 2006-03-09 2006-05-25 조남준 Precast Arch Panel having Corrugated Multi Plate

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040018002A (en) * 2002-08-24 2004-03-02 주식회사 우일 이알에스 Fabricated arch tunnel and construction method thereof
KR200417221Y1 (en) 2006-03-09 2006-05-25 조남준 Precast Arch Panel having Corrugated Multi Plate

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101750987B1 (en) * 2016-09-29 2017-06-26 전종환 Precast segment arch structure and method for constructing this same
CN110486040A (en) * 2019-07-08 2019-11-22 重庆交通大学 A kind of prefbricated tunnel lining structure for vcehicular tunnel
CN110486040B (en) * 2019-07-08 2024-03-08 重庆交通大学 Assembled lining structure for highway tunnel

Similar Documents

Publication Publication Date Title
KR101630235B1 (en) Precast truss wall structure and construction method of underground structure using thereof
KR101588593B1 (en) Temporary bridge construction method
KR20090047575A (en) Slip form for concrete lining of shaft tunnel and method constructing concrete lining of shaft tunnel
KR100775767B1 (en) Top-down method using the vertical steel bar for the src column
KR101277751B1 (en) Precast Concrete Blocks and Remodeling Reinforcing Construction Methods for Low and Middle-rise Beam-column Buildings by Using that Blocks
KR101127923B1 (en) Pylon of cable-stayed bridge having composite combination structure and construction method thereof
KR20160039855A (en) Construction methods of precast concrete slab having its connection part being concealed by coupled ribs and, precast concrete slab used therefor
KR100579440B1 (en) Mold-Reinforcing Rod One Body Type Precast Concrete Pannel and Fabrication Structure of The Same
KR100650411B1 (en) Tunnel cover plate
CN108547209B (en) Single-hole prefabricated hollow slab bridge without expansion joint and construction method thereof
KR100732622B1 (en) The sectional arch tunnel using the tunnel member with a reinforcement rib, and its construction method
KR100443809B1 (en) Fabricated arch tunnel and construction method thereof
KR20030096697A (en) A tunnel lining structure system using curved corrugated steel plates and consrution method therof
KR101054450B1 (en) Precasting structure
KR101045629B1 (en) High durability shotcrete composite for concrete structure, and retaining wall structure using the same and construction method thereof
CN111364520A (en) Prefabricated multi-way cable well and construction method thereof
KR101036177B1 (en) Method for constructing building using PRC integrating method
KR200391986Y1 (en) Carbon-glass fiber composite concrete mold
KR101103680B1 (en) Pc slab with arch type rib for underground parking lot
KR20110135046A (en) Prestressed assembly block structure applying external ps force to strongly connected assembly block and construction method thereof
KR101056395B1 (en) The water-storage tank of assembly type and method for constructing thereof
KR102026112B1 (en) Pre-cast concrete segment blocks for vertical structures with various bracket connection means
IT202000016588A1 (en) SYSTEM AND METHOD OF FOUNDATION WITH SEISMIC ISOLATION OF BUILDINGS
KR100664965B1 (en) Carbon-glass fiber composite concrete mold, its manufacturing method and construction method
KR200348534Y1 (en) Wing type of footpath block

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
G170 Publication of correction
FPAY Annual fee payment

Payment date: 20120620

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee