JPS63144707A - Method and apparatus for paying off messemger rope for laying cable in cable rack - Google Patents

Method and apparatus for paying off messemger rope for laying cable in cable rack

Info

Publication number
JPS63144707A
JPS63144707A JP61292154A JP29215486A JPS63144707A JP S63144707 A JPS63144707 A JP S63144707A JP 61292154 A JP61292154 A JP 61292154A JP 29215486 A JP29215486 A JP 29215486A JP S63144707 A JPS63144707 A JP S63144707A
Authority
JP
Japan
Prior art keywords
cable
support
wire
cable rack
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP61292154A
Other languages
Japanese (ja)
Other versions
JPH0787660B2 (en
Inventor
神永 康
岩重 哲志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kandenko Co Ltd
Original Assignee
Kandenko Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kandenko Co Ltd filed Critical Kandenko Co Ltd
Priority to JP29215486A priority Critical patent/JPH0787660B2/en
Publication of JPS63144707A publication Critical patent/JPS63144707A/en
Publication of JPH0787660B2 publication Critical patent/JPH0787660B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 [発 明 の 目 的] (産業上の利用分野) 本発明はケーブルラックのケーブル延線用メツセンジャ
ーロープの繰り出し方法及びその装置に係り、ケーブル
ラック内に各種のケーブルを延線させるに際してのメツ
センジャーロープをケーブルラック内に簡単に繰り出す
ことができ、メツセンジャーロープによるケーブルの延
線作業の能率を向上させるものである。
[Detailed Description of the Invention] [Object of the Invention] (Industrial Application Field) The present invention relates to a method and device for feeding out a metsenger rope for cable extension in a cable rack, and relates to a method and device for feeding out a metsenger rope for extending cables in a cable rack. When extending the cable, the metsenger rope can be easily fed out into the cable rack, and the efficiency of the cable extension work using the metsenger rope is improved.

(従来の技術) 従来から、ビル、工場その他の建築構造物に各種ケーブ
ルを纏めて配線する場合、棚状となるケーブルラックを
敷設し、このケーブルラック内にケーブルを通線収納す
ることが多い。
(Conventional technology) Traditionally, when wiring various cables together in buildings, factories, and other architectural structures, a shelf-like cable rack is often laid and the cables are routed and stored within this cable rack. .

通線させる延線作業に際し、ケーブル径が大きく、比較
的重量があるものの場合には、ケーブル端にメツセンジ
ャーロープを連結し、そのメツセンジーロープを延線が
わ前方から牽引して行なう。
When running a wire, if the cable has a large diameter and is relatively heavy, a Messenger rope is connected to the end of the cable and the Messenger rope is pulled from the front of the wire.

すなわち、第9図に示すように、先ず、通線すべきケー
ブルラックLにおける延線繰り出しがわにケーブルCを
用意し、またケーブルラックLにおける延線引き取りが
わにウィンチ等の牽引機Wを配置しておき、纏め上げら
れているメツセンジャーロープRを作業員が引き取りが
わから繰り出しがわへ運搬する(同図(I)参照)。次
いで、ケーブルC先端にメツセンジャーロープRを連結
し、ケーブルラックL内にメツセンジャーロープRを順
次伸ばし出し、引き取りがわの牽引機Wに連結する(同
図(n)参照)。然る後、牽引機Wを起動し、メツセン
ジャーロープRを牽引することでケーブルCをケーブル
ラックL内に引き込み通線する(同図(m)参照)。延
線作業の終了後は牽引機WからメツセンジャーロープR
を取外し、メツセンジャーロープRを再び繰り出しがわ
へ運搬し、これを繰り返す。
That is, as shown in FIG. 9, first, a cable C is prepared on the side of the cable rack L to be wired, and a traction machine W such as a winch is placed on the side of the cable rack L to take out the line. A worker transports the Messenger rope R that has been arranged and gathered up to the unwinding side after knowing where to take it (see (I) in the same figure). Next, the Messenger rope R is connected to the tip of the cable C, and the Messenger rope R is sequentially extended into the cable rack L and connected to the pulling machine W at the receiving end (see (n) in the same figure). Thereafter, the traction machine W is started and the cable C is drawn into the cable rack L by pulling the messenger rope R (see (m) in the same figure). After the line extension work is completed, the Metsusenger rope R is transferred from the traction machine W.
Remove it, transport the Metzenger rope R to the payout side again, and repeat this process.

(発明が解決しようとする問題点) このような従来の作業方法によると、夫々ケーブルの延
線終了毎に、メツセンジャーロープを運搬すべく作業員
が往復しなければならず、極めて面倒であり、しかも、
それが長大な距離になると、作業員の疲労度も大きくな
り、多数の作業員を必要とする。
(Problems to be Solved by the Invention) According to such a conventional work method, a worker has to go back and forth to transport the Messenger rope every time the cable has been extended, which is extremely troublesome. ,Moreover,
If the distance is long, the fatigue level of the workers will increase, and a large number of workers will be required.

こうした現状に鑑み、本発明者等は、メツセンジャーロ
ープを運搬、往復させることなく簡易に作業をなし得る
よう考察、検討し、本発明を完成させるに至った。
In view of the current situation, the inventors of the present invention have considered and investigated ways to easily carry out the work without transporting or reciprocating the Messenger rope, and have completed the present invention.

すなわち、本発明は、従来の延線作業上のネッ夕となっ
ていたメツセンジャーロープの運搬、往復作業を不要な
ものとして延線作業の能率向上を図ることにあり、特に
、ケーブルの繰り出しかわあるいは引き取りがわでの操
作のみによってメツセンジャーロープを繰り出しがわか
ら引き取りがわへ簡単に繰り出しできるようにすること
にある。
That is, the present invention aims to improve the efficiency of wire extension work by eliminating the need for transporting and reciprocating the metsenger rope, which was a nuisance in conventional wire extension work. Alternatively, the purpose is to enable the metsenger rope to be easily fed out to the receiving side without knowing how to pay it out, only by operating it at the receiving side.

[発明の構成] (問題点を解決するための手段) 上述した目的を達成するため、本発明にあって、その方
法は、ケーブルを延線すべきケーブルラックに沿って、
ループ状にしたガイドワイヤーを挿通状態で配置し、巻
回部の一方はケーブルの繰り出しがわに、他方は引き取
りがわに夫々位置させ、ガイドワイヤーの任位置に、ケ
ーブルラック内に通線すべきケーブルに後端が連繋され
ているメツセンジャーロープの先端を連繋紐を介して連
繋しておき、次いで、ガイドワイヤーを強制的に牽引、
巡環させてメツセンジャーロープをケーブルラック内に
引き込み、メツセンジャーロープ先端を引き取りがわま
で移動させることにあり、この方法を実施するのに直接
使用する装置は、ケーブルを延線すべきケーブルラック
の繰り出しがわ、引き取りがわの末端路に配される末端
路支持金具と、配線路態様によっての直線路に配される
直線路支持金具、水平曲がり路に配される水平曲がり路
支持金具、アップダウン路に配されるアップダウン路支
持金具との組合せにて成り、末端路支持金具、直線路支
持金具、水平曲がり路支持金具、アップダウン路支持金
具に支持、挿通させたガイドワイヤーをケーブルラック
に沿ったループ状に配装したことにある。
[Structure of the Invention] (Means for Solving the Problems) In order to achieve the above-mentioned object, the present invention provides a method that includes:
A looped guide wire is inserted into the cable rack, one winding section is placed on the cable's feeding side, and the other is placed on the cable receiving side. The tip of the Metsenger rope, whose rear end is connected to the cable to be used, is connected via a connecting string, and then the guide wire is forcibly pulled.
The purpose of this method is to pull the Metsenger rope into the cable rack by circulating it, and move the end of the Metsenger rope to the receiving side. An end path support fitting placed on the end path of the delivery side and a take-up side, a straight path support fitting placed on a straight path depending on the wiring route mode, a horizontal bending path support fitting placed on a horizontal curved path, It consists of a combination of up-down path support fittings arranged on up-down paths, and the guide wire supported and inserted through the end path support fittings, straight path support fittings, horizontal bending path support fittings, and up-down path support fittings is connected to the cable. This is because they are arranged in a loop along the rack.

(作用) 叙上のように構成された本発明において、先ず、ケーブ
ルを通線すべく適宜敷設されているケーブルラックにお
いてのケーブルの繰り出しがわ、引き取りがわ夫々に末
端路支持金具を配設する。
(Function) In the present invention configured as described above, firstly, terminal path support fittings are provided on each of the cable delivery side and the cable take-off side in the cable rack which is appropriately laid to pass the cable. do.

その間での配線路態様によって選択組合せることで、ケ
ーブルラックの直線路では直線路支持金具を、水平曲が
り路では水平曲がり路支持金具を、アップダウン路では
アップダウン路支持金具を夫々配設する。
By selecting and combining them depending on the wiring path mode between them, straight path support fittings are installed for straight paths of cable racks, horizontal bending path support fittings are installed for horizontal curved paths, and up-down path support fittings are installed for up-down paths. .

配設後では、夫々の金具にガイドワイヤーを挿通、支持
することにより、ケーブルラック側方でガイドワイヤー
をループ状に掃通させておく。
After installation, the guide wire is passed through and supported by each metal fitting, so that the guide wire sweeps in a loop shape on the side of the cable rack.

そこで、繰り出しがわで用意されているケーブルに後端
を連結したメツセンジャーロープ先端の連繋紐をガイド
ワイヤーに連繋し、ガイ下ワイヤーを手動あるいは機械
的作動によって牽引巡環させる。
Therefore, the connecting string at the tip of the Messenger rope, whose rear end is connected to the cable prepared at the feeder, is connected to the guide wire, and the wire under the guide is pulled around by manual or mechanical operation.

すると、メツセンジャーロープはケーブルラック内に繰
り出され、引き取りがわに至る。このようにして引き取
りがわまでメツセンジャーロープ先端が繰り出されると
、適当な牽引機にメツセンジャーロープを連結して、牽
引機を起動することによってケーブルはメツセンジャー
ロープを介してケーブルラック内に引き込み延線される
The metsenger rope is then fed out into the cable rack and delivered to the receiving end. When the tip of the metsenger rope is unwound as far as it can be taken in, the cable is pulled into the cable rack via the metsenger rope by connecting the rope to an appropriate traction machine and starting the traction machine. The line will be extended.

引き込み延線後は、ケーブルからメツセンジャーロープ
を取り外し、ケーブル毎に延線作業を繰り返えせばよい
After pulling in and extending the cable, the Metsenger rope can be removed from the cable and the extension work can be repeated for each cable.

(実施例) 以下、第1図乃至第8図を参照して本発明の一実施例を
説明する。
(Embodiment) An embodiment of the present invention will be described below with reference to FIGS. 1 to 8.

第1図において、本発明の概略が示されている。In FIG. 1, an overview of the invention is shown.

すなわち、ケーブルCを延線すべきケーブルラックLに
沿って、ループ状にしたガイドワイヤー1を挿通状態で
配置し、巻回部の一方はケーブルCの繰り出しがわに、
他方は牽引機Wが配置される引き取りがわに夫々位置さ
せる。ガイドワイヤ−1自体は、作業員の手動あるいは
機械的操作によって牽引され、その掛違径路に沿って巡
環されるようになっている。
That is, a looped guide wire 1 is inserted along the cable rack L where the cable C is to be extended, and one of the winding portions is placed on the side where the cable C is fed out.
The other one is located on the receiving side where the towing machine W is arranged. The guide wire 1 itself is pulled by a worker manually or mechanically, and is looped along its interlocking path.

このガイドワイヤー1の任位置に、ケーブルラックL内
に通線すべきケーブルCに後端が連繋されているメツセ
ンジャーロープRの先端を連繋紐2を介して連繋する(
第1図(I)参照)。メツセンジャーロープR自体の長
さは、繰り出しがゎと引き取りがわとの間でのそれにほ
ぼ対応しており、ケーブルCを牽引するに足る耐荷重性
を備えるも、可能な限り軽量であることが望ましい。
The tip of the messenger rope R, whose rear end is connected to the cable C to be routed inside the cable rack L, is connected to the position of the guide wire 1 via the connecting string 2 (
(See Figure 1 (I)). The length of the Metsusenger rope R itself roughly corresponds to the length between the point at which it is fed out and the point at which it is picked up, and it must be as light as possible while having sufficient load capacity to tow the cable C. is desirable.

メツセンジャーロープRが連結されたガイドヮイヤー1
は、例えば繰り出しがわにいる作業員の操作によって強
制的に牽引、巡環される。これに伴ないメツセンジャー
ロープRはケーブルラックL内に引き込まれ、メツセン
ジャーロープR先端は牽引機Wが配置されている引き取
りがわに至る(第1図(II)参照)。
Guide wire 1 to which Metsenger rope R is connected
For example, the robot is forcibly towed and circulated by a worker on the delivery side. Along with this, the messenger rope R is drawn into the cable rack L, and the tip of the messenger rope R reaches the receiving side where the traction machine W is arranged (see FIG. 1 (II)).

引き取りがわでは、メツセンジャーロープRの先端をガ
イドワイヤー1から取外して牽引機Wに連結し、次いで
牽引機Wを起動させることで、メツセンジャーロープR
を介してケーブルCをケーブルラックL内に引き込み延
線する(第1図(■)参照)。
At the pick-up point, the tip of the Messenger rope R is removed from the guide wire 1 and connected to the traction machine W, and then the Messenger rope R is started by starting the traction machine W.
The cable C is drawn into the cable rack L through the cable (see Fig. 1 (■)).

ケーブルCの延線終了後では、牽引機Wからメツセンジ
ャーロープRを取外し、再び同様に繰り返すことで、複
数のケーブルCの延線作業が行なわれる。
After the cables C have been stretched, the messenger rope R is removed from the traction machine W, and the same process is repeated to complete the work of stretching a plurality of cables C.

なお、牽引機Wの牽引によってケーブルCが引き込まれ
るとき、その延線荷重の軽減のために各種の延線ローラ
ーの使用が予定される(図示せず)−11= しかして、ケーブルラックLに沿ってのループ状のガイ
ドワイヤー1の掛違配置は、第2図に示すように、繰り
出しがわ、引き取りがわの末端路に配される末端路支持
金具10と、配線路態様によっての直線路に配される直
線路支持金具20、水平曲がり路に配される水平曲がり
路支持金具30、アップダウン路に配されるアップダウ
ン路支持金具40との組合せによって行なわれる。
In addition, when the cable C is pulled by the traction machine W, various types of wire stretching rollers are planned to be used to reduce the wire stretching load (not shown). As shown in FIG. 2, the loop-shaped guide wire 1 is arranged along the wire path by a terminal path support fitting 10 arranged at the terminal path of the feeding side and the receiving side, and a straight line depending on the wiring path mode. This is achieved by a combination of straight road support fittings 20 arranged on roads, horizontal curved road support fittings 30 arranged on horizontal curved roads, and up-down road support fittings 40 arranged on up-down roads.

末端路支持金具10は、第3図、第4図に示すように、
ケーブルラックLの親桁L1に固着される支持片11の
上部に」二部片12を、側部に側部片13を夫々折曲連
設する。上部片12には、ガイドワイヤー1を挿通させ
るループが形成されているワイヤー支持ボルト14を連
結し、側部片13には、同じくガイドワイヤー1を挿通
させるループが形成されているワイヤーテンションボル
ト15を、弾撥的な牽引作用にて摺動自在にさせて貫挿
支持して成る。
As shown in FIGS. 3 and 4, the distal tract support fitting 10 includes:
Two pieces 12 are bent and connected to the upper part of the support piece 11 fixed to the main girder L1 of the cable rack L, and side pieces 13 are bent and connected to the sides thereof. A wire support bolt 14 having a loop formed therein through which the guide wire 1 is inserted is connected to the upper piece 12, and a wire tension bolt 15 having a loop formed therein through which the guide wire 1 is inserted is connected to the side piece 13. are slidably inserted and supported by an elastic traction action.

支持片11の親桁L1への固着は、親桁L11画面に支
持片11下部を当接し、親桁L1内がわから当てかった
コ字形のセットボルト16を支持片11下部に貫挿し、
ねじ止めする。ワイヤー支持ボルト14、ワイヤーテン
ションボルト15のループは、ループ自由端がループ基
部に重ねられていて、その間隙にガイドワイヤー1が強
制挿入されるものとして、ガイドワイヤー1のループへ
の挿通円滑性を図る。ワイヤー支持ボルト14の上部片
12への連結は、上部片12に形成したネジ孔にねじ込
むと同時にナツト止めしてワイヤー支持ボルト14自体
の空転、がたつきを防止する。
To fix the support piece 11 to the main girder L1, the lower part of the support piece 11 is brought into contact with the screen of the main girder L11, and the U-shaped set bolt 16, which has been placed inside the main girder L1, is inserted through the lower part of the support piece 11.
Fasten with screws. The loops of the wire support bolts 14 and wire tension bolts 15 have their free ends overlapped with the loop bases, and the guide wire 1 is forcibly inserted into the gap, so that smooth insertion of the guide wire 1 into the loops is ensured. Plan. The wire support bolt 14 is connected to the upper piece 12 by screwing it into a screw hole formed in the upper piece 12 and at the same time tightening it with a nut to prevent the wire support bolt 14 itself from spinning or rattling.

また、ワイヤーテンションボルト15は、側部片13に
穿設された透孔にネジ部を貫挿し、このネジ部にコイル
スプリング17を嵌め込んでナツト止めしてあり、コイ
ルスプリング17に対しての弾撥圧縮の調整によって、
ループに挿通させたガイドワイヤー1を適宜に緊張させ
る。なお、このワイヤーテンションボルト15は、繰り
出しがわ、引き取りがわでの末端路支持金具10のいず
れか一方のみに設けられることでも足りる。
The wire tension bolt 15 has a threaded portion inserted into a through hole drilled in the side piece 13, and a coil spring 17 is fitted into the threaded portion and secured with a nut. By adjusting the elastic compression,
The guide wire 1 inserted through the loop is tensioned appropriately. It is also sufficient to provide the wire tension bolt 15 only on either one of the end path support fittings 10 at the feeding side and the pulling side.

直線路での直線路支持金具20は、第5図に示−13= すように、ケーブルラックLの親桁L1に固着される支
持片21の上部に上部片22を折曲連設し、この上部片
22には、ガイドワイヤー1を挿通させるループが形成
されているワイヤー支持ボルト23を連結する。また、
支持片21自体には支持アーム24を連結し、この支持
アーム24に取付けたワイヤー受筒25の周壁には、前
記連繋紐2を挿通させる挿通スリット26を切設して成
る。
The straight path support fitting 20 for a straight path has an upper piece 22 bent and connected to the upper part of a support piece 21 fixed to the main girder L1 of the cable rack L, as shown in FIG. A wire support bolt 23 having a loop formed therein through which the guide wire 1 is inserted is connected to the upper piece 22 . Also,
A support arm 24 is connected to the support piece 21 itself, and an insertion slit 26 is cut in the peripheral wall of a wire receiver 25 attached to the support arm 24, through which the connecting cord 2 is inserted.

支持片21の親桁L1への固着構造、ワイヤー支持ボル
ト23の上部片22への連結構造夫々は、末端路支持金
具10での支持片11、ワイヤー支持ボルト14と同様
であるため、その説明は省略される。図示の支持アーム
24は、適宜肉厚、幅員の帯状版材を側面はぼL字形に
折曲したもので、その垂直部分にて支持片21にねじ止
めされ、水平部分先端下面にワイヤー受筒25をねじ止
め支持している。ワイヤー受筒25の挿通スリット26
は、筒状のワイヤー受筒25の一端から他端に至るよう
に設けられ、両端においては端部に至るに伴ない次第に
広幅となし、中央においては前記連繋紐2のみが挿通さ
れるに足る狭幅なものとされる(第7図参照)。
The fixing structure of the support piece 21 to the main girder L1 and the connection structure of the wire support bolt 23 to the upper piece 22 are the same as those of the support piece 11 and the wire support bolt 14 in the terminal path support fitting 10, so the explanation thereof will be omitted. is omitted. The illustrated support arm 24 is made by bending a strip-shaped plate material of appropriate thickness and width into an L-shape on the side. The support arm 24 is screwed to the support piece 21 at the vertical part, and has a wire receiver on the lower surface of the tip of the horizontal part. 25 is supported by screws. Insertion slit 26 of wire receiver 25
is provided from one end of the cylindrical wire receiver 25 to the other end, and the width becomes gradually wider at both ends, and the width is wide enough at the center to allow only the connecting string 2 to be inserted. It is considered to be narrow (see Figure 7).

しかして、ワイヤー受筒25内に挿通されているガイド
ワイヤー1に連繋紐2を介してメツセンジャーロープR
を連繋させるとき、第7図に示すように、メツセンジャ
ーロープR先端には、頂部が丸味を帯びた円錐形のロー
プ取付はキャップ3を冠せておく。すると、牽引巡環さ
れるガイドワイヤー1に伴ない牽引されたメツセンジャ
ーロープRがワイヤー受筒25位置に至ると、連繋紐2
はワイヤー受筒25内を挿通し、一方、ロープ取付はキ
ャップ3は挿通スリット26縁外面に摺接しながらワイ
ヤー受筒25外方でこれに沿って移動する。このとき、
ロープ取付はキャップ3の円錐形の頂部はワイヤー受筒
25との円滑な摺接作用を発揮し、移動を阻害しない。
The guide wire 1 inserted into the wire receiver 25 is connected to the mesh rope R via the connecting string 2.
When connecting the ropes, as shown in FIG. 7, a conical cap 3 with a rounded top is attached to the tip of the Messenger rope R. Then, when the metsenger rope R pulled along with the guide wire 1 being towed and circulated reaches the wire receiver 25 position, the connecting cord 2
is inserted into the wire receiver 25, while the cap 3 moves along the outer side of the wire receiver 25 while slidingly contacting the outer surface of the edge of the insertion slit 26 when attaching the rope. At this time,
When attaching the rope, the conical top of the cap 3 makes smooth sliding contact with the wire receiver 25 and does not hinder movement.

また、水平曲がり路での水平曲がり路支持金具30は、
第6図に示すように、曲がり路での水平面での曲がり角
度に対応して、直線路支持金具20と同様な構造のもの
として構成された幾つかのものが曲がり路での前後で親
桁L1に取付けられる。すなわち、親桁L1に固着され
る支持片31、支持片31上部に折曲連設した上部片3
2、上部片32に連結したワイヤー支持ボルト33、支
持片31自体に連結した支持アーム片34、挿通スリッ
ト36を有して支持アーム片34に取付けられるワイヤ
ー受筒35を備えて成り、ただ、ワイヤー受筒35は支
持アーム片34に対し、曲がり角度に対応して水平面で
揺動自在なものとしてある。
In addition, the horizontal curved road support fittings 30 for horizontal curved roads are
As shown in FIG. 6, in response to the bending angle in the horizontal plane on a curved road, several pieces of structure similar to the straight road support bracket 20 are installed at the front and rear of the curved road. Attached to L1. That is, the support piece 31 fixed to the main girder L1, the upper piece 3 bent and connected above the support piece 31
2. It comprises a wire support bolt 33 connected to the upper piece 32, a support arm piece 34 connected to the support piece 31 itself, and a wire receiver 35 that has an insertion slit 36 and is attached to the support arm piece 34. The wire receiver 35 is designed to be able to swing freely in a horizontal plane relative to the support arm piece 34 in accordance with the bending angle.

なお、直線路支持金具20におけるワイヤー受筒25の
挿通スリット26、及び水平曲がり路支持金具30にお
けるワイヤー受筒35の挿通スリット36は、いずれも
ケーブルラックLへの配設状態において側方に、特に、
水平曲がり路においては外側方に向けられており、牽引
巡環されるガイドワイヤー1がワイヤー受筒25.35
から抜脱されないように配慮されている。
In addition, the insertion slit 26 of the wire receiver 25 in the straight path support fitting 20 and the insertion slit 36 of the wire receiver 35 in the horizontal curved path support fitting 30 are both located laterally when installed in the cable rack L. especially,
In a horizontal curve, the guide wire 1 is directed outward and is towed around the wire receiver 25.35.
Care has been taken to ensure that it does not fall out.

更に、アップダウン路でのアップダウン路支持金具40
は、例えば第8図に示すように、親桁し1に固着したほ
ぼL字形の丸棒製のガイド杆41にて成り、その水平部
分の下面でガイドワイヤー1を摺接案内させるようにな
っている。ガイド杆41自体の親桁L1への固着は、親
桁L1内がわから当てかったコ字形のセット支持片42
の両側部分にガイド杆41の垂直ネジ部を貫挿し、ナツ
ト止めする。
Furthermore, up-down road support fittings 40 for up-down roads
As shown in FIG. 8, for example, the guide rod 41 is made of an approximately L-shaped round bar fixed to the main beam 1, and the guide wire 1 is slidably guided on the lower surface of the horizontal portion thereof. ing. The guide rod 41 itself is fixed to the main girder L1 by using the U-shaped set support piece 42, which is not properly fixed inside the main girder L1.
The vertical threaded portions of the guide rod 41 are inserted through both sides of the guide rod 41 and fixed with nuts.

このアップダウン路支持金具40は、第2図に示すよう
に、傾斜敷設されるケーブルラックLに連続させた下方
位のケーブルラックLにおける親桁L1に取付けられ、
上下方向での曲がり部位に位置される。
As shown in FIG. 2, this up-down path support fitting 40 is attached to the main girder L1 of the lower cable rack L that is continuous with the cable rack L installed at an angle.
It is located at the bend in the vertical direction.

一方、アップダウン路でのガイドワイヤー1の掃通糸路
の形成のため、第2図に示すように、アップダウン路支
持金具40によるガイドワイヤー1の案内位置上方でガ
イドワイヤー1を案内支持するアップダウン路補助支持
金具45が配されている。このアップダウン路補助支持
金具45は、親桁L1に固着される支持片46の上部に
折曲連設した上部片47に、ガイドワイヤー1を挿通さ
せるループが形成されているワイヤー支持ボルト48を
連結して成るものである。なお、図示を省略したが、直
線路支持金具20の支持片21あるいは水平曲がり路支
持金具30の支持片31と同様にして親桁L1に固着さ
れる支持片21に、ガイド杆41を連結することでガイ
ドワイヤー1の摺動案内と、また、上部に折曲連設した
上部片12にワイヤー支持ボルト14を連結することで
ガイドワイヤー1の掃通糸路の形成とを図るようにして
もよい(図示せず)。
On the other hand, in order to form a sweeping path for the guide wire 1 in the up-down path, the guide wire 1 is guided and supported above the guiding position of the guide wire 1 by the up-down path support fitting 40, as shown in FIG. Up-down path auxiliary support metal fittings 45 are arranged. This up-down path auxiliary support metal fitting 45 has a wire support bolt 48 in which a loop through which the guide wire 1 is inserted is formed in an upper piece 47 that is bent and connected to the upper part of a support piece 46 fixed to the main girder L1. It is made up of connected parts. Although not shown, the guide rod 41 is connected to the support piece 21 fixed to the main girder L1 in the same manner as the support piece 21 of the straight road support fitting 20 or the support piece 31 of the horizontal curved road support fitting 30. In this way, the guide wire 1 can be guided slidingly, and the wire support bolt 14 can be connected to the upper piece 12 which is bent and connected to the upper part to form a sweeping thread path for the guide wire 1. Good (not shown).

次に、第2図を参照して本発明装置の使用を説明する。Next, the use of the apparatus of the present invention will be explained with reference to FIG.

ケーブルCを通線すべく適宜敷設されているケーブルラ
ックLにおいて、ケーブルCの繰り出しがわ、引き取り
がわ夫々に末端路支持金具10を配設する。その間での
配線路態様によって選択組合せることで、ケーブルラッ
クLの直線路では直線路支持金具20を、水平曲がり路
では水平曲がり路支持金具30を、アップダウン路では
アップダウン路支持金具40更にはアップダウン路補助
支持金具45を夫々配設する。配設後では、夫々の金具
10.20.30,40.45でのワイヤー支持ボルト
14.23.33のループ内、ワイヤー受筒25.35
内にガイドワイヤー1を挿通し、また、ワイヤーテンシ
ョンボルト15のループ内に挿通して適宜のテンション
を与えることにより、ケーブルラックL側方でガイドワ
イヤー1をループ状に掛巡させておく。
In a cable rack L which is suitably laid down to pass the cable C, terminal path support fittings 10 are arranged on each of the cable C feeding side and the receiving side. By selecting and combining them depending on the wiring route mode between them, the straight path support metal fitting 20 is used for the straight path of the cable rack L, the horizontal curve support metal fitting 30 is used for the horizontal curved path, and the up-down path support metal fitting 40 is used for the up-down path. Up-down path auxiliary support metal fittings 45 are respectively provided. After installation, in the loops of the wire support bolts 14, 23, 33 in the respective fittings 10, 20, 30, 40, 45, the wire receivers 25, 35
The guide wire 1 is looped around the side of the cable rack L by passing the guide wire 1 through the cable rack L and applying appropriate tension by inserting the guide wire 1 into the loop of the wire tension bolt 15.

そこで、繰り出しがわで用意されているケーブルCに連
結したメツセンジャーロープR先端の連繋紐2をガイド
ワイヤー1に連繋し、ガイドワイヤー1を手動あるいは
機械的作動によって牽引巡環させる。すると、メツセン
ジャーロープRはケーブルラックL内に繰り出され、引
き取りがわで設置されている牽引機Wに至る。このよう
にして引き取りがわまでメツセンジャーロープR先端が
繰り出されると、牽引機WにメツセンジャーロープRを
連結して、牽引機Wを起動することによってケーブルC
はメツセンジャーロープRを介してケーブルラックL内
に引き込み延線される。引き込み延線後は、ケーブルC
からメツセンジャーロープRを取り外し、ケーブルC毎
に延線作業を繰り返えせばよい。
Therefore, the connecting string 2 at the tip of the metsenger rope R connected to the cable C prepared at the feeding end is connected to the guide wire 1, and the guide wire 1 is pulled around by manual or mechanical operation. Then, the metsenger rope R is let out into the cable rack L and reaches the traction machine W installed on the receiving side. In this way, when the tip of the metsenger rope R is paid out as far as it can be taken, the cable C is connected by connecting the metsenger rope R to the traction machine W and starting the traction machine W.
is drawn into the cable rack L via the metsenger rope R and extended. After pulling in and extending cable C.
It is sufficient to remove the metsenger rope R from the cable C and repeat the wire extension work for each cable C.

[発明の効果] 本発明は叙上のように構成されており、そのため、繰り
出しかわあるいは引き取りがわでのガイドワイヤー1の
牽引巡環によって、ケーブルラックL内にメツセンジャ
ーロープRを繰り出すことができ、従来のように、作業
員がメツセンジャーロープRを運搬する必要がないから
、作業員の負担を軽減させ、作業能率を向上できる。
[Effects of the Invention] The present invention is configured as described above, and therefore, it is possible to pay out the Messenger rope R into the cable rack L by pulling the guide wire 1 at the feeding or receiving side. Since there is no need for the worker to carry the Messenger rope R as in the past, the burden on the worker can be reduced and work efficiency can be improved.

また、ケーブルラックの末端路では末端路支持金具10
を配し、その間での配線路ではその態様によって適宜組
合せることで、直線路支持金具20、水平曲がり炉支持
金具30、アップダウン路支持金具40を配するから、
それらの金具10゜20.30.40に挿通支持された
ガイドワイヤー1は、ケーブルラックの配線路に沿った
ものとなる。
In addition, at the end of the cable rack, there is a terminal support fitting 10.
, and in the wiring paths between them, straight path support fittings 20, horizontal bending furnace support fittings 30, and up-down path support fittings 40 are arranged by appropriately combining them depending on the mode.
The guide wire 1 inserted and supported by these metal fittings 10°20.30.40 follows the wiring path of the cable rack.

しかも、ガイドワイヤー1は、繰り出しがわと引き取り
がわとの間でループ状に掛巡され、ケーブルラックL内
でのケーブルCの通線系路に沿って配されているから、
メツセンジャーロープR自体はケーブルラックL内に繰
り出され、通線されるケーブルCを確実にケーブルラッ
クL内に案内する。
Moreover, since the guide wire 1 is looped between the feeding end and the receiving end, and is arranged along the route of the cable C within the cable rack L,
The messenger rope R itself is let out into the cable rack L, and reliably guides the cable C being routed into the cable rack L.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第8図は本発明の一実施例を示すもので、第
1図(I)乃至(III)は本発明方法の概略を表わす
概略図、第2図は本発明装置の全体斜視図、第3図は末
端路支持金具を表わす斜視図、第4図はその正面図、第
5図は直線路支持金具を表わす斜視図、第6図は水平曲
がり路支持金具を表わす斜視図、第7図はワイヤー受筒
部位でロープ取付はキャップが移動されるときでの斜視
図、第8図はアップダウン路支持金具を表わす斜視図で
あり、第9図(I)乃至(m)は従来方法の概略を表わ
す概略図である。 L・・・ケーブルラック、Ll・・・親桁、C・・・ケ
ーブル、R・・・メツセンジャーロープ、W・・・牽引
機、1・・・ガイドワイヤー、2・・・連繋紐、3・・
・ロープ取付はキャップ、10・・・末端路支持金具、
11・・・支持片、12・・・上部片、13・・・側部
片、14・・・ワイヤー支持ポルl−115・・・ワイ
ヤーテンションボルト、16・・・セットボルト、17
・・・コイルスプリング、20・・・直線路支持金具、
21・・・支持片、22・・・上部片、23・・・ワイ
ヤー支持ボルト、24・・・支持アーム、25・・・ワ
イヤー受筒、26・・・挿通スリット、30・・・水平
曲がり路支持金具、31・・・支持片、32・・・上部
片、33・・・ワイヤー支持ボルト、34・・・支持ア
ーム片、35・・・ワイヤー受筒、36・・・挿通スリ
ット、40・・・アップダウン路支持金具、41・・・
ガイド杆、42・・・セット支持片、45・・・アップ
ラン路補助支持金具、46・・・支持片、47・・・上
部片、48・・・ワイヤー支持ボルト。 ≧
Figures 1 to 8 show an embodiment of the present invention, Figures 1 (I) to (III) are schematic diagrams showing the outline of the method of the present invention, and Figure 2 is a perspective view of the entire device of the present invention. FIG. 3 is a perspective view showing the terminal path support fitting, FIG. 4 is a front view thereof, FIG. 5 is a perspective view showing the straight path support fitting, and FIG. 6 is a perspective view showing the horizontal curved path support fitting. Fig. 7 is a perspective view of the wire receiver section and the rope attachment when the cap is moved, Fig. 8 is a perspective view showing the up-down path support fittings, and Figs. 9 (I) to (m) are 1 is a schematic diagram showing an outline of a conventional method. L... Cable rack, Ll... Main girder, C... Cable, R... Metsenger rope, W... Traction machine, 1... Guide wire, 2... Connecting string, 3・・・
・Rope installation is done with a cap, 10...terminal path support fittings,
DESCRIPTION OF SYMBOLS 11... Support piece, 12... Top piece, 13... Side piece, 14... Wire support pole l-115... Wire tension bolt, 16... Set bolt, 17
...Coil spring, 20...Straight path support fitting,
21... Support piece, 22... Upper piece, 23... Wire support bolt, 24... Support arm, 25... Wire receiver, 26... Insertion slit, 30... Horizontal bending Road support fitting, 31... Support piece, 32... Upper piece, 33... Wire support bolt, 34... Support arm piece, 35... Wire receiver, 36... Insertion slit, 40 ...Up-down road support fitting, 41...
Guide rod, 42...Set support piece, 45...Uprun path auxiliary support fitting, 46...Support piece, 47...Upper piece, 48...Wire support bolt. ≧

Claims (1)

【特許請求の範囲】 1、ケーブルを延線すべきケーブルラックに沿って、ル
ープ状にしたガイドワイヤーを掛巡状態で配置し、巻回
部の一方はケーブルの繰り出しがわに、他方は引き取り
がわに夫々位置させ、ガイドワイヤーの任位置に、ケー
ブルラック内に通線すべきケーブルに後端が連繋されて
いるメッセンジャーロープの先端を連繋紐を介して連繋
しておき、次いで、ガイドワイヤーを強制的に牽引、巡
環させてメッセンジャーロープをケーブルラック内に引
き込み、メッセンジャーロープ先端を引き取りがわまで
移動させることを特徴としたケーブルラックのケーブル
延線用メッセンジャーロープの繰り出し方法。 2、ケーブルを延線すべきケーブルラックの繰り出しが
わ、引き取りがわの末端路に配される末端路支持金具と
、配線路態様によっての直線路に配される直線路支持金
具、水平曲がり路に配される水平曲がり路支持金具、ア
ップダウン路に配されるアップダウン路支持金具との組
合せにて成り、末端路支持金具、直線路支持金具、水平
曲がり路支持金具、アップダウン路支持金具に支持、挿
通させたガイドワイヤーをケーブルラックに沿ったルー
プ状に配装したことを特徴とするケーブルラックのケー
ブル延線用メッセンジャーロープの繰り出し装置。 3、末端路支持金具は、ケーブルラックの親桁に固着さ
れる支持片の上部に上部片を、側部に側部片を夫々連設
し、上部片には、ガイドワイヤーを挿通させるループが
形成されているワイヤー支持ボルトを連結し、側部片に
は、同じくガイドワイヤーを挿通させるループが形成さ
れているワイヤーテンションボルトを弾撥的な牽引作用
にて摺動自在にさせて貫挿支持して成る特許請求の範囲
第2項記載のケーブルラックのケーブル延線用メッセン
ジャーロープの繰り出し装置。 4、直線路支持金具は、ケーブルラックの親桁に固着さ
れる支持片の上部に上部片を連設し、この上部片には、
ガイドワイヤーを挿通させるループが形成されているワ
イヤー支持ボルトを連結し、また、支持片自体には支持
アームを連結し、この支持アームに取付けたワイヤー受
筒の周壁には、前記連繋紐を挿通させる挿通スリットを
切設して成る特許請求の範囲第2項または第3項記載の
ケーブルラックのケーブル延線用メッセンジャーロープ
の繰り出し装置。 5、水平曲がり路支持金具は、ケーブルラックの親桁に
固着される支持片の上部に上部片を連設し、この上部片
には、ガイドワイヤーを挿通させるループが形成されて
いるワイヤー支持ボルトを連結し、また、支持片自体に
は支持アームを連結し、この支持アームに取付けたワイ
ヤー受筒の周壁には、前記連繋紐を挿通させる挿通スリ
ットを切設して成り、ワイヤー受筒は支持アーム片に対
し、曲がり角度に対応して水平面で揺動自在なものとし
てある特許請求の範囲第2項乃至第4項のいずれか記載
のケーブルラックのケーブル延線用メッセンジャーロー
プの繰り出し装置。 6、アップダウン路支持金具は、親桁に固着したほぼL
字形の丸棒製のガイド杆にて成り、その水平部分の下面
でガイドワイヤーを摺接案内させるようになっている特
許請求の範囲第2項乃至第5項のいずれか記載のケーブ
ルラックのケーブル延線用メッセンジャーロープの繰り
出し装置。
[Claims] 1. A looped guide wire is arranged in a looped manner along the cable rack where the cable is to be extended, and one of the winding parts is used to feed out the cable, and the other part is used to take it back. The tip of the messenger rope, whose rear end is connected to the cable to be routed inside the cable rack, is connected to the designated position of the guide wire via a connecting cord, and then the guide wire is A method for feeding out a messenger rope for cable extension of a cable rack, characterized by forcibly towing and circulating the messenger rope to draw the messenger rope into the cable rack, and moving the tip of the messenger rope to the receiving side. 2. End path support fittings placed on the end path of the cable rack where the cable is to be extended and the cable take-off side, straight path support fittings placed on the straight path depending on the type of wiring path, and horizontal curved paths. It consists of a combination of horizontal curved road support fittings placed on the up-down road, and up-down road support fittings placed on the up-down road. A device for feeding out a messenger rope for cable extension of a cable rack, characterized in that a guide wire supported and inserted through the cable rack is arranged in a loop shape along the cable rack. 3. The terminal path support fitting has an upper piece connected to the upper part of the support piece fixed to the main girder of the cable rack, and a side piece connected to the side part, and the upper piece has a loop through which the guide wire is inserted. The formed wire support bolts are connected, and the wire tension bolt, which also has a loop formed in the side piece through which the guide wire is inserted, is slidably supported by an elastic traction action. A messenger rope feeding device for cable extension of a cable rack according to claim 2, comprising: 4. The straight path support fitting has an upper piece connected to the upper part of the support piece fixed to the main girder of the cable rack, and this upper piece has the following:
A wire support bolt having a loop formed therein through which the guide wire is inserted is connected, a support arm is connected to the support piece itself, and the connecting cord is inserted into the peripheral wall of a wire receiver attached to this support arm. A device for feeding out a messenger rope for cable extension of a cable rack according to claim 2 or 3, wherein an insertion slit is cut to allow the messenger rope to extend. 5. The horizontal curve support fitting has an upper piece connected to the upper part of the support piece fixed to the main girder of the cable rack, and this upper piece has a wire support bolt formed with a loop through which the guide wire is inserted. In addition, a support arm is connected to the support piece itself, and an insertion slit is cut in the peripheral wall of the wire receiver attached to the support arm, through which the connecting string is inserted. The device for feeding out a messenger rope for cable extension of a cable rack according to any one of claims 2 to 4, wherein the device is capable of swinging in a horizontal plane according to the bending angle with respect to the support arm piece. 6. The up-down road support fittings are approximately L fixed to the main girder.
The cable of the cable rack according to any one of claims 2 to 5, which comprises a guide rod made of a round bar in the shape of a letter, and a guide wire is slidably guided on the lower surface of the horizontal portion thereof. Messenger rope feeding device for wire extension.
JP29215486A 1986-12-08 1986-12-08 A messenger rope feeding device for extending the wire of a cable rack Expired - Lifetime JPH0787660B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29215486A JPH0787660B2 (en) 1986-12-08 1986-12-08 A messenger rope feeding device for extending the wire of a cable rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29215486A JPH0787660B2 (en) 1986-12-08 1986-12-08 A messenger rope feeding device for extending the wire of a cable rack

Publications (2)

Publication Number Publication Date
JPS63144707A true JPS63144707A (en) 1988-06-16
JPH0787660B2 JPH0787660B2 (en) 1995-09-20

Family

ID=17778239

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29215486A Expired - Lifetime JPH0787660B2 (en) 1986-12-08 1986-12-08 A messenger rope feeding device for extending the wire of a cable rack

Country Status (1)

Country Link
JP (1) JPH0787660B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4042159A1 (en) * 1989-12-30 1991-07-11 Mirai Ind U=shaped ducting cable laying method
JPH0497417U (en) * 1991-01-17 1992-08-24
DE4315750A1 (en) * 1992-05-12 1993-11-18 Mirai Ind Co Laying appts. for cables and flexible pipes - has tractor on girder above cable path inside conduit and cable suspended below it with quick-release hook
WO2012051655A1 (en) * 2010-10-20 2012-04-26 Leigh Klugh Cable laying device and cable installation system
US9810021B2 (en) 2014-05-30 2017-11-07 Panduit Corp. Thermal expansion and contraction system
CN108736380A (en) * 2018-06-02 2018-11-02 徐盼盼 A kind of power cable automatic placement equipment
CN108736379A (en) * 2018-06-02 2018-11-02 徐盼盼 A kind of Electrical construction guidance frame

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57186116U (en) * 1981-05-18 1982-11-26
JPS59148508A (en) * 1983-02-14 1984-08-25 日立プラント建設株式会社 Guide for extending cable

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57186116U (en) * 1981-05-18 1982-11-26
JPS59148508A (en) * 1983-02-14 1984-08-25 日立プラント建設株式会社 Guide for extending cable

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4042159A1 (en) * 1989-12-30 1991-07-11 Mirai Ind U=shaped ducting cable laying method
JPH0497417U (en) * 1991-01-17 1992-08-24
DE4315750A1 (en) * 1992-05-12 1993-11-18 Mirai Ind Co Laying appts. for cables and flexible pipes - has tractor on girder above cable path inside conduit and cable suspended below it with quick-release hook
FR2691297A1 (en) * 1992-05-12 1993-11-19 Mirai Ind Device for hanging cables or pipes and apparatus for laying.
WO2012051655A1 (en) * 2010-10-20 2012-04-26 Leigh Klugh Cable laying device and cable installation system
US9810021B2 (en) 2014-05-30 2017-11-07 Panduit Corp. Thermal expansion and contraction system
US10240393B2 (en) 2014-05-30 2019-03-26 Panduit Corp. Thermal expansion and contraction system
CN108736380A (en) * 2018-06-02 2018-11-02 徐盼盼 A kind of power cable automatic placement equipment
CN108736379A (en) * 2018-06-02 2018-11-02 徐盼盼 A kind of Electrical construction guidance frame
CN108736380B (en) * 2018-06-02 2020-05-05 扬州市工二电力机具有限公司 Automatic laying equipment for power cables
CN108736379B (en) * 2018-06-02 2020-05-29 国网山东省电力公司禹城市供电公司 Electric power construction leading truck

Also Published As

Publication number Publication date
JPH0787660B2 (en) 1995-09-20

Similar Documents

Publication Publication Date Title
JPS63144707A (en) Method and apparatus for paying off messemger rope for laying cable in cable rack
US4475715A (en) Aerial cable installation block
JP3044343B2 (en) Cable catch with shooter
JP2879667B2 (en) Cable guide device
JP2001327016A (en) Stringing construction method for cable and corner guide for cable stringing
JP2755332B2 (en) Drum movable manipulator cable trolley
JP3484635B2 (en) Route construction method and obstacle traversing tool
JP3581854B2 (en) Corner guide for cable overhead line
JPH09271125A (en) Method of multiple cable stringing and switchboard for extending cable
JP3350663B2 (en) Moving gold car
JPH05215923A (en) Method for laying wiring cable and traction jig to be used therein
JPH07118854B2 (en) Tip traction type manipulator cable
JP3165945B2 (en) Cable catch with shooter
US20050127237A1 (en) Alignment tool
JP3326452B2 (en) Continuous shooter and cable laying device for cable laying
JP2000295726A (en) Overhead cable installation method and spiral wire pay- off device used for the method
JP3514433B2 (en) Cable erection method and cable erection device
JP3517732B2 (en) Cable laying fixture
JPH02241303A (en) Line extension technique and device therefor
EP0653892B1 (en) Method for pulling a wire by means of a pilot wire
JP2000295727A (en) Overhead cable installation method
JPH0978525A (en) Suspending method and suspending device for diagonal member cable
JP3198437B2 (en) Cable catch with shooter
JPH10313514A (en) Cable stringing device
JPS6295910A (en) Systematically mechanized method of stretching and hanging coaxial cable