JPS61191725A - Stress material drawing work - Google Patents

Stress material drawing work

Info

Publication number
JPS61191725A
JPS61191725A JP3236285A JP3236285A JPS61191725A JP S61191725 A JPS61191725 A JP S61191725A JP 3236285 A JP3236285 A JP 3236285A JP 3236285 A JP3236285 A JP 3236285A JP S61191725 A JPS61191725 A JP S61191725A
Authority
JP
Japan
Prior art keywords
steel sheet
sheet pile
piles
ground
stress material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3236285A
Other languages
Japanese (ja)
Inventor
Kazuo Hayashi
一夫 林
Tsukasa Hashimoto
司 橋本
Hitoshi Nishimaki
西牧 均
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP3236285A priority Critical patent/JPS61191725A/en
Publication of JPS61191725A publication Critical patent/JPS61191725A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To simply and quickly remove out steel sheet piles by a method in which a steel sheet pile consisting of an upper steel sheet pile and a lower steel sheet pile is driven, and the upper steel sheet pile is drawn out when embedding the ground after an underground structure is constructed. CONSTITUTION:The lower end of an upper steel sheet pile 5 is fitted into a plate 2 provided to the upper end of a lower steel sheet pile 1 and the piles 1 and 5 are integrated with bolts 7 and nuts 4. The sheet piles so integrated are driven into the ground 9 to form a sheathing wall, and the ground within the sheathing wall is excavated and an underground structure 11 is constructed. The ground is embedded to the connected portion 12 of the sheet piles, the bolts 7 are removed out, the area to the ground's surface is embedded, and the upper steel sheet pile 5 is pulled out. The stress material consisting of the piles 1 and 5 can thus be easily and quickly removed out, and the piles can also be used as sheathing wall until construction work is completed.

Description

【発明の詳細な説明】 開削工事における土留工法において応力材の鋼材として
鋼矢板、H鋼杭が使用され、且つ応力材が20m以上に
なると工事終了後不要となるにもかかわらず埋殺しとな
っているのが現状で、これは応力材を経済的に引き抜く
方法が見い出されていないためであるが、現在では工事
完了後においては引き抜き撤去が要求されてきた。
[Detailed description of the invention] In the earth retaining method for excavation construction, steel sheet piles and H steel piles are used as stressed steel materials, and when the stressed materials exceed 20 m, they are buried even though they are no longer needed after the construction is completed. Currently, this is because no economical method has been found to pull out stressed materials, but it is now required to pull them out and remove them after construction is completed.

これは省資源を計り、コストダウンを目的とする事の他
、公有地及び私有地の地下の永久占有が困難釦なって来
たことが上げられる。
This is done not only to conserve resources and cut costs, but also because it has become difficult to permanently occupy underground areas of public and private land.

例えば地下鉄工事等の場合、応力材により土留を施し地
盤を掘削し地下構築物の構築を完了した後、上部で作業
或は通行ができるように地面まで一旦埋戻し、作業等を
続行し、全べての去し再び埋め戻すという二重三重の手
数をかけているものである。
For example, in the case of subway construction, etc., after completing the construction of an underground structure by applying earth retention with stress materials and excavating the ground, it is temporarily backfilled to the ground so that work or passage can be carried out on the upper part, and work is continued until the entire structure is completed. This involves the double and triple effort of removing and reburying.

本願はこのような手数をかけずに簡巣且っ迅速に撤去で
き、しかも応力材を土留壁として作業完了まで使用する
ことができるようにすることを目的とした応力材引抜き
方法に関する発明である。
The present application is an invention relating to a method for pulling out stressed materials, which is intended to enable easy and quick removal of nests without such trouble, and to allow the stressed materials to be used as earth retaining walls until the work is completed. .

今その実施例を説明すれば二本の応力材の内一本の応力
材(以後下部鋼矢板と呼ぶ)(11の上端内外面にプレ
ート(2)を溶接によって固定し、下部鋼矢板(11の
上部に延長されているプレート外面でボルト挿通孔(3
)に合致させてナラ) (411!:溶接し、ナツト(
4)の雌ネジ孔とボルト挿通孔(3)とが一致するよう
にさせる。
To explain the example now, a plate (2) is fixed to the inner and outer surfaces of the upper end of one of the two stress members (hereinafter referred to as the lower steel sheet pile) (11) by welding, and the lower steel sheet pile (11 Bolt insertion holes (3
) (411!: Weld, nut (
Make sure that the female screw hole (4) and the bolt insertion hole (3) match.

他の一本の応力材(以後上部鋼矢板と呼ぶ)(5)の下
部に前記プレート(2)に穿りたボルト挿通孔(3)と
合致するボルト挿通孔(6)を穿つものである。
A bolt insertion hole (6) that matches the bolt insertion hole (3) drilled in the plate (2) is bored in the lower part of another stress member (hereinafter referred to as the upper steel sheet pile) (5). .

即ち下部鋼矢板(1)の上部に上部鋼矢板(5)を突き
合せて継ぎ足した時プレート(2)のボルト挿通孔(3
)と合致する箇所にボルト挿通孔(6)を穿つものであ
る。
That is, when the upper steel sheet pile (5) is butted against the upper part of the lower steel sheet pile (1) and added, the bolt insertion hole (3) of the plate (2)
) A bolt insertion hole (6) is drilled at a location that matches the hole.

本願は前記構成の下部鋼矢板(1)の上端に設けたプレ
ート(2)内に上部鋼矢板(5)の下端を嵌合しボルト
挿通孔(3) (6)を一致させてボルト(7)を挿通
し、ナツト(4)にボルト(7)を螺合する。このよう
して地下構築物u1)を構築した後、地上部での作業及
び通行をなるべく早く可能くするため上下部鋼矢板(8
)の連結部住りまで埋戻し、ボルト(7)をはずし、そ
の後地表面q3まで完全に埋戻すものである。
In the present application, the lower end of the upper steel sheet pile (5) is fitted into the plate (2) provided at the upper end of the lower steel sheet pile (1) having the above structure, and the bolt insertion holes (3) and (6) are aligned so that the bolts (7) ) and screw the bolt (7) onto the nut (4). After constructing the underground structure u1) in this way, the upper and lower steel sheet piles (8
), remove the bolts (7), and then completely backfill to the ground surface q3.

完全に埋戻した後クレーンにて上部鋼矢板(5)を引抜
くことにより所定深さまでの鋼矢板を取り除くことがで
きるので以後の上部の構築物の構築、ガス管或は水道管
の配役に支障をきたさないものである。
After it is completely backfilled, the steel sheet pile (5) can be removed to a specified depth by pulling out the upper steel sheet pile (5) using a crane, so there will be no hindrance to the subsequent construction of the upper structure or the installation of gas or water pipes. It does not cause any damage.

本願は叙上のように長手方向の中間に″′Cボルトナツ
トで連結一体化した応力材を用いて土留壁を形成し、土
留壁内に地下構築物を構築して応力材の連結部まで埋戻
した後、上部応力材を固定しているボルトを撤去し再び
地表面まで土留壁内を皿戻し、その後上部の応力材を引
抜くことを特徴とするので良く所期の目的を達すること
ができるものである。
As described above, in this application, an earth retaining wall is formed using stressed materials that are connected and integrated with "'C bolts and nuts" in the middle of the longitudinal direction, and an underground structure is constructed within the earth retaining wall and backfilled up to the connecting part of the stressed materials. After that, the bolts fixing the upper stressed material are removed and the inside of the earth retaining wall is returned to the ground surface again, and then the upper stressed material is pulled out, so the desired purpose can be achieved well. It is something.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は上下部鋼矢板の斜視図、第2図は同要部の正面
図、第3図及び第4図は第2図の縦断面図及び横断面図
、第5図は土留壁を建込んだ地盤の平面図、第6図は地
盤の縦断面図である。
Figure 1 is a perspective view of the upper and lower steel sheet piles, Figure 2 is a front view of the main parts, Figures 3 and 4 are vertical and cross-sectional views of Figure 2, and Figure 5 is a view of the retaining wall. A plan view of the ground on which the construction was built, and Figure 6 is a vertical cross-sectional view of the ground.

Claims (1)

【特許請求の範囲】[Claims] (1)、長手方向の中間にてボルトナットで連結一体化
した応力材を用いて土留壁を形成し、土留壁内に地下構
築物を構築して応力材の連結部まで埋戻した後、上部応
力材を固定しているボルトを撤去し再び地表面まで土留
壁内を埋戻し、その後上部の応力材を引抜くことを特徴
とする応力材引抜き方法。
(1) Form an earth retaining wall using stressed materials connected and integrated with bolts and nuts in the middle of the longitudinal direction, construct an underground structure within the earth retaining wall and backfill up to the joint of the stressed materials, and then A stress material extraction method characterized by removing the bolts fixing the stress material, backfilling the inside of the earth retaining wall to the ground surface, and then pulling out the stress material at the top.
JP3236285A 1985-02-20 1985-02-20 Stress material drawing work Pending JPS61191725A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3236285A JPS61191725A (en) 1985-02-20 1985-02-20 Stress material drawing work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3236285A JPS61191725A (en) 1985-02-20 1985-02-20 Stress material drawing work

Publications (1)

Publication Number Publication Date
JPS61191725A true JPS61191725A (en) 1986-08-26

Family

ID=12356841

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3236285A Pending JPS61191725A (en) 1985-02-20 1985-02-20 Stress material drawing work

Country Status (1)

Country Link
JP (1) JPS61191725A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07102564A (en) * 1993-10-05 1995-04-18 Yamashitagumi:Kk Driving method when sheet pile member is driven in water bottom by distance shorter than water depth and driving member used for the method
WO2005121458A1 (en) * 2004-06-05 2005-12-22 Seong-U Park Apparatus for pile connecting and piling method using auxiliary pile
JP2011038288A (en) * 2009-08-10 2011-02-24 Nippon Steel Corp Joint structure of steel sheet pile and steel sheet pile wall structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5858327A (en) * 1981-10-05 1983-04-06 Taisei Corp Driving of underground pile

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5858327A (en) * 1981-10-05 1983-04-06 Taisei Corp Driving of underground pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07102564A (en) * 1993-10-05 1995-04-18 Yamashitagumi:Kk Driving method when sheet pile member is driven in water bottom by distance shorter than water depth and driving member used for the method
WO2005121458A1 (en) * 2004-06-05 2005-12-22 Seong-U Park Apparatus for pile connecting and piling method using auxiliary pile
JP2011038288A (en) * 2009-08-10 2011-02-24 Nippon Steel Corp Joint structure of steel sheet pile and steel sheet pile wall structure

Similar Documents

Publication Publication Date Title
JP5268732B2 (en) Wall member for underground continuous wall, underground continuous wall construction method, and underground continuous wall
JPS61191725A (en) Stress material drawing work
JPH0510596U (en) Concrete box for underground structure
JPH1136296A (en) Pc hollow pile and construction method for underground structure
JP3404315B2 (en) Removal method and device for wall core pile
JPS6224673B2 (en)
KR20020085104A (en) A method of construction for earth-protection walls of building
JP2876266B2 (en) Sheet pile for underground continuous wall and underground continuous wall method
JP2807587B2 (en) Water sheet for steel sheet pile and ground excavation method
JPS60246918A (en) Method of removing negative friction force of cast-in-place concrete pile
JP2544159Y2 (en) Temporary retaining wall
JP3009845B2 (en) Protective material for underground diaphragm wall method
JPH06240670A (en) Method and device for pulling pile
JP2844157B2 (en) Open shield method and concrete box used for it
JPH09317374A (en) Method of construction of subsurface structure
JPS61257529A (en) Underground continuous wall construction work
JPH0310199Y2 (en)
KR20220012119A (en) Tunnel Structure Construction Method by Steel Pipe Installed Lead Steel Pipe
JP2002013144A (en) Device for removal of continuous wall core pile
JPH1113062A (en) Simplified pneumatic caisson earth retaining construction method
JP2556415B2 (en) Construction method of self-supporting retaining wall
JPS62228525A (en) Removal work of sheathing stressing material by drawing
JPS60175628A (en) Burying method for pipe
JPH0266220A (en) Prevention method of damage at cross-section in concrete part of cast-in-place pile
JPH10168917A (en) Caisson prefabricated manhole and execution method thereof