JPS62228525A - Removal work of sheathing stressing material by drawing - Google Patents
Removal work of sheathing stressing material by drawingInfo
- Publication number
- JPS62228525A JPS62228525A JP7400986A JP7400986A JPS62228525A JP S62228525 A JPS62228525 A JP S62228525A JP 7400986 A JP7400986 A JP 7400986A JP 7400986 A JP7400986 A JP 7400986A JP S62228525 A JPS62228525 A JP S62228525A
- Authority
- JP
- Japan
- Prior art keywords
- ground
- sheet piles
- adhesive
- excavated
- pulled out
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000463 material Substances 0.000 title claims abstract description 26
- 239000000853 adhesive Substances 0.000 claims abstract description 18
- 230000001070 adhesive effect Effects 0.000 claims abstract description 18
- 238000010276 construction Methods 0.000 claims abstract description 15
- 238000000034 method Methods 0.000 claims abstract description 12
- 239000007788 liquid Substances 0.000 claims abstract description 9
- 229920003002 synthetic resin Polymers 0.000 claims abstract description 9
- 239000000057 synthetic resin Substances 0.000 claims abstract description 9
- 238000007711 solidification Methods 0.000 claims description 9
- 230000008023 solidification Effects 0.000 claims description 9
- 238000009412 basement excavation Methods 0.000 claims description 6
- 229910000831 Steel Inorganic materials 0.000 abstract description 18
- 239000010959 steel Substances 0.000 abstract description 18
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 8
- 239000012466 permeate Substances 0.000 abstract description 2
- 230000008878 coupling Effects 0.000 abstract 1
- 238000010168 coupling process Methods 0.000 abstract 1
- 238000005859 coupling reaction Methods 0.000 abstract 1
- 239000002002 slurry Substances 0.000 description 3
- 239000002689 soil Substances 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- QNRATNLHPGXHMA-XZHTYLCXSA-N (r)-(6-ethoxyquinolin-4-yl)-[(2s,4s,5r)-5-ethyl-1-azabicyclo[2.2.2]octan-2-yl]methanol;hydrochloride Chemical compound Cl.C([C@H]([C@H](C1)CC)C2)CN1[C@@H]2[C@H](O)C1=CC=NC2=CC=C(OCC)C=C21 QNRATNLHPGXHMA-XZHTYLCXSA-N 0.000 description 1
- 229910052802 copper Inorganic materials 0.000 description 1
- 239000010949 copper Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 238000005286 illumination Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 210000000056 organ Anatomy 0.000 description 1
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【発明の詳細な説明】
産業上の利用分野
開削工事における土留応力材を土留壁内を掘削し構築物
の構築あるいは埋戻しが完了後簡単且つ低引張力で引き
抜くことができるようにした発明である。[Detailed description of the invention] This invention enables the earth retaining stress material used in excavation work to be easily pulled out with low tensile force after excavating the inside of the earth retaining wall and completing the construction or backfilling of the structure. .
従来の技術
開削工事における土留工法には多くの種類があるが、古
くは鋼矢板工法、H銅損矢板工法が行なわれ、この10
年程度以前からPIF工法、連続地中壁工法が山留壁工
法として広く使用され、比較的深い掘削では剛性の大き
い地下連続壁が盛んに施工されている。Conventional technology There are many types of earth retaining methods used in excavation construction, but the steel sheet pile method and the H-copper loss sheet pile method were used in the past.
The PIF construction method and the continuous underground wall construction method have been widely used as mountain retaining wall construction methods since about 2000, and continuous underground walls with high rigidity are frequently constructed in relatively deep excavations.
最近、大都市市街地での開削工事においては工事周辺の
住民生活を妨げる騒音、振動、地下水低下、地盤法下等
を極力低減する工法として泥水固化工法、オーガーソイ
ルミキシング工法が採用されている。Recently, mud water solidification method and auger soil mixing method have been adopted for cut-and-cover construction in large urban areas as construction methods to minimize noise, vibration, groundwater drop, subgrade ground law, etc. that disturb the lives of residents around the construction site.
しかも、これらの土留工法においても応力材の鋼材とし
て鋼矢板、H鋼杭工型鋼が使用され、且つ応力材が20
m以上になると工事終了後、不要となるにもかかわら
ず埋殺しとなっているのが現状で、これは応力材を経済
的に引き抜く方法が見い出されていないためであるが、
現在では工事完了後においては引抜き撤去が要求されて
きた。Moreover, even in these earth retaining methods, steel sheet piles and H-steel pile type steel are used as stress materials, and the stress materials are
At present, when the stress exceeds 500 m, it is buried even though it is no longer needed after construction is completed.This is because no method has been found to economically extract the stressed material.
Nowadays, it is required to pull it out and remove it after construction is completed.
これは省資源を計シ、コストダウンを目的とする事の他
、公有地及び私有地の地下の永久占有が困難になってき
たことがあげられる。This is not only to save resources and reduce costs, but also because it has become difficult to permanently occupy underground areas of public and private land.
そのだめに長い場合は地表よシ地下3m位いまで応力材
の両側を土留を施して掘削し応力材を切断し、再び埋め
戻すという二重三重の手数をかけているものである。If the length is too long, it takes a double or triple effort to excavate with earth retaining on both sides of the stressed material from the ground surface to about 3 meters underground, cut the stressed material, and then fill it back in again.
従って現在泥水固化工法の応力材として鋼矢板が、二連
オーガーンイルミキシング工法の応力材としてH鋼杭の
使用が主であるが、長さは20m以下でジヨイント無し
の一本物に限定されている。Therefore, currently, steel sheet piles are mainly used as the stress material in the mud water solidification method, and H steel piles are used as the stress material in the double organ illumination method, but the length is limited to 20 m or less and a single pile without a joint. There is.
発明が解決しようとする問題点
20m以上の応力材を簡単且つ低引張力で引き抜くこと
ができないという問題点を解決しようとする発明である
。Problems to be Solved by the Invention This invention attempts to solve the problem that a stressed material of 20 m or more cannot be easily pulled out with a low tensile force.
問題点を解決するだめの手段
地盤を掘削して形成した掘削孔に泥水固化液を充填した
のち、応力材の表面に合成樹脂フィルムを特殊な粘着剤
、接着剤の塗布、あるいはそれ等の粘着剤、接着剤をコ
ーティングしたテープにて装着又は被覆した応力材を互
いの係合部を係合連設しながら前記掘削孔内に建込み、
′全周の土留壁を形成した後、少なくとも地表面までの
地下構築物の溝築完了後或は埋戻し後、応力材を引抜く
ことにより20m以上の応力材を埋殺しすることなく省
資源化を図ることができ、騒音、振動が少くなくしかも
低引張力で簡単且つ容易に引抜くことができるようにし
た発明である。Measures to solve the problem: After excavating the ground and filling the hole formed with slurry solidification liquid, apply a synthetic resin film to the surface of the stressed material with a special adhesive, adhesive, or other adhesive. erecting a stress material attached or covered with a tape coated with an adhesive into the excavation hole while engaging and connecting each other's engaging portions;
'After forming an earth retaining wall around the entire circumference, and after completing the trench construction of the underground structure to at least the ground surface or after backfilling, we can save resources by pulling out the stressed material without burying more than 20 m of stressed material. This invention allows for simple and easy pulling out with low tensile force, with less noise and vibration.
作用及び実施例
本願は未だ試みられていない20 m以上の長大物でも
引抜き及び砂礫地盤条件下での引抜き工法を発明したも
のである。Effects and Examples The present application has invented a method for pulling out even long objects of 20 m or more, which has not been tried yet, and for pulling out under sandy and gravel ground conditions.
今その実施の一例を説明すれば、鋼矢板(1)の係合部
(2)を除く全面に合成樹脂フィルム(3)を水溶性粘
着剤の塗布又は水溶性粘着剤をコーティングしたテープ
にて装着又は被覆して準備する。To explain one example of its implementation, a synthetic resin film (3) is applied to the entire surface of the steel sheet pile (1) except for the engaging part (2) by applying a water-soluble adhesive or by using a tape coated with a water-soluble adhesive. Prepare by attaching or covering.
これと平行して地盤の所定箇所に掘削機によシ一定間隔
毎に掘削孔(4)を掘削し残土を処理し掘削孔(4)に
泥水固化液を封入した後、クレーンにて鋼矢板(1)を
吊シ上げ建込み、数本の鋼矢板(1)を互いの保合部(
2ンを係合させながら順次建込み、所定数の建込みが終
了したならば、鋼矢板(1)の垂直精度及び通り芯等を
確認して泥水固化壁の強度発現までの間吊り金具にて保
持固定する。In parallel with this, an excavator drills holes (4) at regular intervals in a predetermined location in the ground, and after disposing of the remaining soil and filling the holes (4) with slurry solidification liquid, a crane is used to drill the steel sheet piles. (1) is hoisted up and erected, and several steel sheet piles (1) are attached to each other at the joints (
After the predetermined number of erections have been completed, the vertical accuracy and alignment of the steel sheet piles (1) are checked, and the hanging metal fittings are installed until the muddy water solidification wall develops its strength. Hold and secure.
泥水固化壁の強度発現後一定間隔毎に掘削された掘削孔
(4)間を掘削(5)シ泥水固化液を封入し、鋼矢板(
1)を建込み連続した土留壁を形成するものである。After the mud solidification wall developed its strength, the holes (4) were drilled at regular intervals (5), and the mud water solidification liquid was filled in and the steel sheet piles (
1) to form a continuous retaining wall.
鋼矢板(1)には水溶性粘着剤にて合成樹脂フィルム(
3)が被覆されていることによシ、建込んだ時泥水固化
物の水分が鋼矢板(1)と合成樹脂フィルム(3)間に
浸透し泥水固化物の水分と粘着剤が流動状態を保ち抵抗
が非常に減じられているため数10)ンの引張力で簡単
に合成樹脂フィルムを泥水固化物内に残したまま抜くこ
とができるものである。A synthetic resin film (
3), when the building is built, the moisture from the solidified mud permeates between the steel sheet pile (1) and the synthetic resin film (3), causing the moisture from the solidified mud and the adhesive to become fluid. Since the holding resistance is extremely reduced, the synthetic resin film can be easily removed with a tensile force of several tens of tons while leaving it in the solidified muddy material.
その後土留壁内を掘削し構築物の構築或は埋戻しが完了
したならば油圧ジヤツキクレーンにて鋼矢板(6)を引
き抜くものである。After that, the inside of the earth retaining wall is excavated, and once the construction or backfilling of the structure is completed, the steel sheet pile (6) is pulled out using a hydraulic jack crane.
鋼矢板は道交法等の規則から25mもの長い応力材は運
搬することができないので現場にて溶接して長大物を形
成するものであるが、溶接に当っては応力材同志を突合
せ溶接するか、応力材同志を突合せた箇所の片面或は両
面にプレートを重ね合せて溶接するものである。Due to regulations such as the Road Traffic Act, steel sheet piles cannot be transported as long as 25 meters, so they are welded on-site to form a long sheet pile. When welding, we either butt-weld the stressed materials together, or weld them together. A plate is overlapped and welded to one or both sides of the area where the stressed materials are butted together.
又、プレートは長方形でもよいが引抜き抵抗を考慮して
縦長の菱形プレートにするときはよシいっそう引抜き抵
抗を少くすることができるものである。Further, the plate may be rectangular, but if the plate is made into a vertically long rhombic plate in consideration of the pull-out resistance, the pull-out resistance can be further reduced.
本願における現場引抜実験結果を表にして現すと
本願は叙上のように地盤を掘削して形成した掘削孔に泥
水固化液を充填したのち、応力材の表面に合成樹脂フィ
ルムを特殊な粘着剤、接着剤の塗布、あるいはそれ等の
粘着剤、接着剤をコーティングしたテープにて被覆した
応力材を互いの保合部を係合連設しながら前記掘削孔内
に建込み、全周の土留壁を形成した後、少なくとも地表
面までの地下構築物の構築完了後或は埋戻し後、応力材
を引抜くことを特徴とするので良く所期の目的を達する
ことができるものである。The results of the on-site pull-out experiments in this application are expressed in a table as follows: After filling the excavated hole formed by excavating the ground with slurry solidification liquid as described above, a synthetic resin film is applied to the surface of the stress material using a special adhesive. , apply adhesive, or apply adhesive or tape coated with such adhesive or adhesive, and build it into the excavation hole while engaging and connecting each other's retaining parts, and install earth retaining around the entire circumference. After the wall is formed, the stressed material is pulled out after the construction of the underground structure up to at least the ground surface is completed, or after it is backfilled, so that the intended purpose can be well achieved.
第1図は鋼矢板の斜視図、第2図は掘削部の地盤の平面
図、第3図は鋼矢板引抜実験によるグラフ図、第4図及
び第5図は鋼矢板の継手タイプの側面図、第6図は突合
せ溶接の場合の断面、第7図はプレートを重ね合せて溶
接した場合の平面図、第8図は同一部の正面図である。
第1図
第2図
第7図Figure 1 is a perspective view of the steel sheet pile, Figure 2 is a plan view of the ground in the excavated area, Figure 3 is a graph from the steel sheet pile pulling experiment, and Figures 4 and 5 are side views of the joint type of the steel sheet pile. , FIG. 6 is a cross section in the case of butt welding, FIG. 7 is a plan view when the plates are overlapped and welded, and FIG. 8 is a front view of the same part. Figure 1 Figure 2 Figure 7
Claims (1)
填したのち、応力材の表面に合成樹脂フィルムを特殊な
粘着剤、接着剤の塗布、あるいはそれ等の粘着剤、接着
剤をコーティングしたテープにて装着又は被覆した応力
材を互いの係合部を係合連設しながら前記掘削孔内に建
込み、全周の土留壁を形成した後、少なくとも地表面ま
での地下構築物の構築完了後或は埋戻し後、応力材を引
抜くことを特徴とする土留応力材の引抜き撤去工法。(1) After excavating the ground and filling the mud solidification liquid into the hole formed, apply a synthetic resin film to the surface of the stress material with a special adhesive or adhesive, or apply other adhesives or adhesives. Stressed materials attached or covered with coated tape are built into the excavation hole while engaging and connecting their engaging parts to form an earth retaining wall around the entire circumference, and then the underground structure is constructed at least up to the ground surface. A method for pulling out and removing stress-retaining earth retaining materials, which is characterized by pulling out the stress-retaining materials after construction is completed or after backfilling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7400986A JPS62228525A (en) | 1986-03-31 | 1986-03-31 | Removal work of sheathing stressing material by drawing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7400986A JPS62228525A (en) | 1986-03-31 | 1986-03-31 | Removal work of sheathing stressing material by drawing |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS62228525A true JPS62228525A (en) | 1987-10-07 |
Family
ID=13534653
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP7400986A Pending JPS62228525A (en) | 1986-03-31 | 1986-03-31 | Removal work of sheathing stressing material by drawing |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS62228525A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012237166A (en) * | 2011-05-13 | 2012-12-06 | Taisei Corp | Coated core member, end-bearing pile provided with coated core member and method of manufacturing coated core member |
-
1986
- 1986-03-31 JP JP7400986A patent/JPS62228525A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012237166A (en) * | 2011-05-13 | 2012-12-06 | Taisei Corp | Coated core member, end-bearing pile provided with coated core member and method of manufacturing coated core member |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108360543A (en) | A kind of big pre-cast sink well structure of depth and its installation method | |
CN112064751A (en) | Deep groove construction method for drainage pipeline | |
CN108071122A (en) | Assembled underground pipe gallery and its construction method | |
GB2102866A (en) | Constructing retaining walls | |
KR100834920B1 (en) | Sheathing of tapetum sheet and construction method to use the above sheet | |
CN215715515U (en) | Municipal pipe network construction supporting integrated structure under unfavorable geological conditions | |
CN108797609A (en) | Environmentally protective steel pipe steel plate combination construction method for supporting | |
JPS62228525A (en) | Removal work of sheathing stressing material by drawing | |
CN206204928U (en) | Constitute the diaphram wall of piping lane side wall | |
CN205857212U (en) | Corrugated steel cofferdam borehole hollow pile | |
JPS61191722A (en) | Drawing and removing work for steel sheet pile | |
JPH0813495A (en) | Earth retaining wall and method thereof | |
JP7566235B1 (en) | Ground improvement methods | |
JP2000240075A (en) | Penetration type retaining wall | |
JPH10121463A (en) | Steel pipe concrete well foundation set on slant land and its construction method | |
JP2985063B2 (en) | Caisson prefabricated manhole and its construction method | |
JPH10252080A (en) | Method for reinforcing foundation of pier for high level road | |
JPH0447734B2 (en) | ||
JPS60246918A (en) | Method of removing negative friction force of cast-in-place concrete pile | |
JPH07300845A (en) | Preventive method against liquefaction of underground linear structure | |
JPH045101B2 (en) | ||
JP3352951B2 (en) | Installation method of invert and underground drainage in mountain tunnel | |
JPS61191725A (en) | Stress material drawing work | |
JPS63304821A (en) | Construction work of underground continuous cut-off wall | |
JPS6192235A (en) | Fixing of embedded pipe |