JPH10121463A - Steel pipe concrete well foundation set on slant land and its construction method - Google Patents

Steel pipe concrete well foundation set on slant land and its construction method

Info

Publication number
JPH10121463A
JPH10121463A JP29787296A JP29787296A JPH10121463A JP H10121463 A JPH10121463 A JP H10121463A JP 29787296 A JP29787296 A JP 29787296A JP 29787296 A JP29787296 A JP 29787296A JP H10121463 A JPH10121463 A JP H10121463A
Authority
JP
Japan
Prior art keywords
well
foundation
excavated
joint
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP29787296A
Other languages
Japanese (ja)
Other versions
JP3635167B2 (en
Inventor
Takuya Saito
拓也 斎藤
Hisashi Hasegawa
久 長谷川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP29787296A priority Critical patent/JP3635167B2/en
Publication of JPH10121463A publication Critical patent/JPH10121463A/en
Application granted granted Critical
Publication of JP3635167B2 publication Critical patent/JP3635167B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a well foundation set on a slant land where a proportion of temporary work quantity to occupy to occupy in overall work is reduced and its construction method by narrowing a working space, eliminating retaining construction and reducing excavated sediment quantity, etc. SOLUTION: This steel pipe concrete well foundation and its construction method are about a pier foundation to be set on a slant land 17, and a steel made well 24 is constructed as a wall body by inserting steel pipes 20 with couplers in a large number of excavated vertical holes 18 arranged and excavated in a circular or square shape, filling a mortar or concrete grout material 30 in their periphery and connecting the couplers of the steel pipes 20 with the couplers with each other by intermediate coupler members. A top end height 23 of this well body is made a retaining wall 36 by making a valley side of the slant land a foundation top end height 33b and making a crest side of the sland land a height stop top end height 33a against slant earth pressure. Top plate concrete 26a making a foundation top plate 26 is filled in an excavated part where sediment in the upper pier is excavated from a lower end 37 of the foundation top plate 26 to be constituted in the well body, and this top plate concrete 26a and a combined reinforcement 38 are firmly combined.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、例えば橋脚基礎等
のため斜面地に設置される井筒基礎とその築造方法に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a well foundation installed on a slope for a pier foundation, for example, and a method of constructing the same.

【0002】[0002]

【従来の技術】従来の斜面地に設置される大径の基礎を
構築する方法としては、一般に孔壁を土留め材で保護し
ながら、人力または機械による竪孔掘削を行ない、この
竪孔にコンクリートを打設する深礎工法が挙げられる。
この深礎工法の長所としては、大径の杭を設置するにも
拘わらず、大きな掘削設備や、打ち込み設備が不要なこ
とから、山岳地等の斜面地での施工も可能である。
2. Description of the Related Art Conventionally, as a method of constructing a large-diameter foundation installed on a slope, a hole is generally excavated by manpower or a machine while protecting a hole wall with earth retaining material. There is a deep foundation method of placing concrete.
As an advantage of the deep foundation method, large drilling equipment and driving equipment are not required in spite of installing large-diameter piles, so construction on slopes such as mountainous areas is also possible.

【0003】図15と図16には、従来の深礎工の縦断
面図と平面図が示されている。各図に示されるように斜
面に深礎工を施工する場合は、斜面地1を平坦に整地し
て作業スペース2を確保し、次に、山側3及び、側面4
に鋼矢板5等による土留め壁6を設置する。その後、前
記土留め壁6の内側において基礎を築造するための竪孔
7の口径分(約3〜15m)の全断面の掘削を所定の深
さ(約10〜30m)まで人力又は掘削機8で行ない、
竪孔7の孔壁には掘削に伴ってその上部側にセグメント
10による土留め覆工がなされる。
FIGS. 15 and 16 show a vertical sectional view and a plan view of a conventional deep foundation. As shown in each figure, when the deep foundation work is performed on the slope, the slope ground 1 is leveled to secure the work space 2, and then the mountain side 3 and the side 4
An earth retaining wall 6 made of a steel sheet pile 5 or the like is installed in the vehicle. Thereafter, excavation of the entire cross section of the diameter of the vertical hole 7 (about 3 to 15 m) for constructing a foundation inside the earth retaining wall 6 is performed by a human power or an excavator 8 to a predetermined depth (about 10 to 30 m). Do
An earth retaining lining by a segment 10 is formed on an upper side of the hole wall of the vertical hole 7 with excavation.

【0004】[0004]

【発明が解決しようとする課題】従来の深礎工による竪
孔掘削施工法によると、前述のように、所定口径の竪孔
7を所定深さまで一度に掘削するため、図16に示すよ
うに孔壁保護用のセグメント10の置き場11、深
礎工用鉄筋の置き場12、資機材置き場15、クロ
ーラクレーン13の設置等の作業スペース14等を掘削
する竪孔7の周りに配置することになる。なお、9はダ
ンプトラック、16は仮設ハウスである。
According to the conventional method of excavating a pit by a deep foundation work, as described above, a pit 7 having a predetermined diameter is excavated to a predetermined depth at a time, as shown in FIG. The storage space 11 for the hole wall protection segment 10, the storage space 12 for the rebar for the deep foundation work, the equipment storage space 15, the work space 14 for installing the crawler crane 13 and the like are arranged around the pit 7 for excavating. . 9 is a dump truck, and 16 is a temporary house.

【0005】前記〜の理由から、竪孔7内の掘削土
砂や、孔外の作業スペース確保のための整地土砂の量が
極めて多くなり、かつ斜面地を平坦に整地し作業スペー
スを確保するためには、前述の土留め壁6を設置する必
要や、竪坑7の周辺部分を含む広い範囲に亘り45°以
下の緩やかな斜面に切り土にする必要があって、これら
により、仮設工事量の全体工事量に占める割合が大きく
なるという問題があった。
[0005] For the reasons described above, the amount of excavated earth and sand in the vertical hole 7 and the amount of earth and sand for leveling to secure a work space outside the hole are extremely large, and the work is required to level the slope land to secure the work space. It is necessary to install the retaining wall 6 described above, and to cut the slope into a gentle slope of 45 ° or less over a wide area including the periphery of the shaft 7, thereby reducing the amount of temporary construction work. There was a problem that the proportion of the total construction volume was large.

【0006】本発明は前述の課題を解決したもので、仮
設工事量を極力少なくした斜面地に設置される井筒基礎
およびその築造方法を提供することを目的とする。
An object of the present invention is to solve the above-mentioned problems, and an object of the present invention is to provide a well base and a method for constructing the same which are installed on a slope with a minimum amount of temporary construction work.

【0007】[0007]

【課題を解決するための手段】前記の課題を解決するた
め、本発明に係る斜面地に設置される鋼管コンクリート
井筒基礎は、斜面地に設置される井筒基礎であって、円
形又は方形に並べて掘削した多数の掘削孔内に継手付き
鋼管を挿入し、その周りにモルタル又はコンクリートの
グラウト材を充填し、前記継手付き鋼管の継手同士を継
手材で連結することで壁体として井筒体を構築し、この
井筒体の天端高を、斜面の下手側を基礎天端高とし、斜
面の上手側を斜面土圧に対抗する高止まり天端高として
これを土留め壁とし、前記井筒体内に構成すべき基礎頂
板の下端から上方の井筒内の土砂を掘削してその掘削部
分に前記基礎頂板をなす頂板コンクリートを充填して、
この頂板コンクリートと、井筒体に設けられた結合材と
を強固に結合されている構成を特徴とする。
SUMMARY OF THE INVENTION In order to solve the above-mentioned problems, a steel pipe concrete well pipe foundation installed on a slope according to the present invention is a well pipe foundation installed on a slope, and is arranged in a circle or a square. Insert a steel pipe with a joint into a number of excavated holes, fill grout material of mortar or concrete around it, and connect the joints of the steel pipe with a joint with a joint material to construct a well body as a wall body Then, the top end height of the well body, the lower side of the slope as the base top height, the upper side of the slope as a high stop ceiling against the slope earth pressure, and this as a retaining wall, in the well body Excavating the earth and sand in the well above the bottom from the lower end of the foundation top plate to be constructed and filling the excavated part with top plate concrete forming the foundation top plate,
It is characterized in that the top plate concrete and the binder provided on the well body are firmly connected.

【0008】また、本発明に係る鋼管コンクリート井筒
基礎の築造方法は、斜面地を整地して平坦地とした作業
スペースにクレーンを配設し、前記作業スペースの上手
側の平坦地に、前記クレーンで吊下げた掘削機を設置
し、この掘削機で前記斜面地の上手側を貫通して円形又
は方形の井筒体山側部を形成する複数の竪孔を掘削し、
前記上手側の各竪孔内に高止まり天端高を形成するよう
継手付き鋼管を建込み、その周囲をグラウトして土留め
壁を構成し、その後、前記斜面地の下手側を貫通して前
記円形又は方形の井筒体谷側部分を形成する複数の竪孔
を掘削し、前記下手側の各竪孔内に継手付き鋼管を建込
み、その周囲をグラウトし、継手付き鋼管の継手部内側
の掘削を行なって継手部間を中間継手材で連結し、かつ
中間継手材をグラウトすることで鋼製井筒を構成し、こ
の井筒内の上部を掘削して基礎頂板を構築することを特
徴とする。
Further, in the method for constructing a steel tubular concrete well tube foundation according to the present invention, a crane is arranged in a work space in which a slope is leveled to make it flat, and the crane is placed on a flat ground on the upper side of the work space. The excavator suspended by installing in, excavating a plurality of pits to form a circular or square well cylinder side by penetrating the upper side of the slope with this excavator,
A steel pipe with a joint is erected in each of the well-side pits to form a high ceiling height, and the surrounding area is grouted to form an earth retaining wall, and then penetrate the lower side of the slope ground. Excavating a plurality of pits forming the circular or square well tube side valley side, building a steel pipe with a joint in each of the lower side pits, grouting the periphery thereof, and inside the joint part of the steel pipe with a joint. By excavating the joints and connecting the joints with intermediate joints, and grouting the intermediate joints to form a steel well, and excavating the upper part of the well to construct a foundation top plate I do.

【0009】本発明によると、斜面地において円形又は
方形に並べて掘削される多数の竪孔に挿入された継手付
き鋼管のうち、山側の竪孔に挿入される継手付き鋼管の
天端高を高止まり天端高とし、これを土留め壁として井
筒体を構築し、井筒体内の上部を掘削して基礎頂板を構
築するので、掘削機吊下げ用のクレーンは井筒体の内側
に配設されることで作業スペースを狭くできる。
According to the present invention, among the steel pipes with joints inserted into a large number of pits excavated side by side in a circular or square shape on a slope, the height of the steel pipe with joints inserted into the pit on the mountain side is increased. The top of the well is used as the retaining wall, and the well is used as a retaining wall to construct a well body.The upper part of the well body is excavated to construct the foundation top plate, so the crane for hanging the excavator is placed inside the well body. By doing so, the working space can be narrowed.

【0010】つまり、本発明では、斜面地掘削におい
て、全旋回式掘削機設置用スペースや、クローラクレー
ン設置用のスペースが確保されればよく、各々のスペー
スは同じ高さ位置にある必要がないとの新しい着目点に
立脚してなされており、したがって、一番低い高さに合
わせた井筒基礎全ての平坦地を作る必要がなく、土留め
工を必要としなくても段切り等により整地土量を少なく
して井筒基礎の構築に必要な作業スペースが確保され
る。
In other words, according to the present invention, in excavation on a slope, a space for installing a full-rotation type excavator and a space for installing a crawler crane only need to be secured, and each space does not need to be at the same height position. Therefore, it is not necessary to make the flat ground of all the Izutsu foundations that are adjusted to the lowest height. The work space required for the construction of the Izutsu foundation is reduced by reducing the volume.

【0011】また本発明は、斜面地の山側に設置された
天止まり天端高を有する継手付き鋼管連続壁を土留め壁
として、斜面地の谷側の造成が可能とされているので、
例えば、図1〜図14に示される本発明は、図15、図
16に示される従来例よりも作業スペース確保のための
整地に動かす土量が低減される。すなわち、同じ傾斜の
斜面地に、同じ外径の井筒基礎を構築する場合、図1
5、図16の従来例では、作業スペースの傾斜方向の寸
法Lが35m、横方向の寸法Wが30m必要であるのに
対し、本発明では、その代表として図10に示すとお
り、作業スペースの傾斜方向の寸法L1 が18m、横方
向の寸法W1 が20mである。前記両者を比較換算して
数式で示すと、 20/30×18/35×(18 tan30/35 tan3
0)=18% で、本発明では従来の整地の移動量の18%ですみ、さ
らに、作業スペース面積は、約50%減となる。加え
て、掘削土量も、従来の35%程度に減ずることができ
る。
Further, according to the present invention, the valley side of the slope can be created by using the continuous wall of the steel pipe with the joint having the ceiling top installed on the mountain side of the slope as the earth retaining wall.
For example, in the present invention shown in FIGS. 1 to 14, the amount of soil to be moved to leveling to secure a work space is reduced as compared with the conventional example shown in FIGS. 15 and 16. In other words, when constructing an Izutsu foundation with the same outer diameter on a slope with the same slope, FIG.
In the conventional example shown in FIG. 16 and FIG. 16, the dimension L in the inclined direction of the working space is 35 m and the dimension W in the lateral direction is 30 m. On the other hand, in the present invention, as shown in FIG. dimension L 1 of the inclined direction 18m, dimension W 1 in the transverse direction is 20 m. The two are compared and expressed by a mathematical formula: 20/30 × 18/35 × (18 tan30 / 35 tan3
0) = 18%, and the present invention requires only 18% of the movement amount of the conventional leveling, and furthermore, the work space area is reduced by about 50%. In addition, the amount of excavated soil can be reduced to about 35% of the conventional amount.

【0012】さらに、前記土留め壁は根入れが深く鋼管
の断面剛性も大きいことから、十分土圧に対し耐力があ
り、支保工、腹起こし、控え材などが不要である。
Further, since the earth retaining wall is deeply embedded and has a large sectional rigidity of the steel pipe, the earth retaining wall has a sufficient resistance against earth pressure, and does not require a support work, an upset, a stay, and the like.

【0013】[0013]

【発明の実施の形態】以下本発明の実施の形態を図を参
照して説明する。図1〜図4は本発明の方法によって斜
面地17に設置された鋼管コンクリート井筒基礎の設置
状態を示すもので、井筒基礎を構成する鋼製井筒24
は、斜面地17を貫通して地盤25内の所定の根入れ深
さまで挿入され、その根入れ深さは、鋼製井筒24の設
置位置の上部、つまり山側35にある上方地盤がすべる
際に作用する水平力によって井筒がすべり方向に傾斜し
ないように、十分な根固め力を発揮する深さに設定され
る。また、鋼製井筒24内の上部に打設された基礎頂板
26にコンクリート橋脚27の下端部が一体に構築され
ている。コンクリート橋脚27の上部には、複数のH形
鋼からなる橋梁28を介して例えば道路橋29が架設さ
れている。
Embodiments of the present invention will be described below with reference to the drawings. 1 to 4 show an installation state of a steel pipe concrete well pipe foundation installed on a slope 17 by the method of the present invention, and a steel well pipe 24 constituting the well pipe foundation.
Is inserted through the slope ground 17 to a predetermined depth of the ground in the ground 25, and the depth of the deep ground is determined when the upper ground on the upper side of the installation position of the steel well tube 24, that is, the mountain side 35 slides. The depth is set to a sufficient rooting force so that the well tube does not tilt in the sliding direction due to the acting horizontal force. Further, a lower end portion of a concrete pier 27 is integrally formed with a foundation top plate 26 cast at an upper portion in a steel well tube 24. For example, a road bridge 29 is erected above the concrete pier 27 via a plurality of bridges 28 made of H-shaped steel.

【0014】前記鋼製井筒24の構造についてさらに説
明すると、多数の竪孔18が一定間隔で円形に並ぶよう
に斜面地17を貫通して掘削され、各竪孔18に継手付
き鋼管20が挿入されると共に、その継手付き鋼管20
におけるスリットパイプ製継手22が井筒築造予定位置
の円周方向に位置するように配置され、かつ竪孔18の
孔壁と継手付き鋼管20との間に、モルタルまたはコン
クリート等の硬化性グラウト材30が充填されている。
また、図3に拡大図示するように隣り合う竪孔18は掘
削竪孔の曲がりを防ぐため、先行建込みとして1エレメ
ントとばしで行い、その後中間部にオーバーラップ掘削
して連続する柱体31を築造したのち、隣り合う継手付
き鋼管20における対向するスリットパイプ製継手22
の間に、中間孔32を穿設して空間を形成し、かつ前記
スリットパイプ製継手22内のグラウト材を掘削して排
除し、またはスリット部にあらかじめ蓋を取り付けてお
き、スリットパイプ製継手22内へのグラウトを阻止す
るようにしておき、中間孔32を穿設する時にその蓋を
排除する。次に各スリットパイプ製継手22にわたって
中間継手部材23を挿入したのち、前記中間孔32内お
よびスリットパイプ製継手22内に硬化性グラウト材を
注入充填する。
The structure of the steel well 24 will be further described. A large number of pits 18 are excavated through the slope 17 so as to be arranged in a circle at regular intervals, and a steel pipe 20 with a joint is inserted into each pit 18. And the jointed steel pipe 20
Is disposed so as to be located in the circumferential direction of the planned construction position of the well pipe, and a hardening grout material 30 such as mortar or concrete is provided between the hole wall of the vertical hole 18 and the steel pipe 20 with the joint. Is filled.
In addition, as shown in an enlarged view in FIG. 3, the adjacent pits 18 are skipped by one element as a preliminary erection to prevent the excavation pits from bending, and then the overlapped excavation is performed at the intermediate portion to form a continuous column 31. After being built, opposed slit pipe joints 22 in adjacent jointed steel pipes 20
In the meantime, an intermediate hole 32 is formed to form a space, and the grout material in the slit pipe joint 22 is excavated and removed, or a lid is previously attached to the slit portion, and the slit pipe joint is formed. The grout into the interior 22 is prevented and the lid is removed when the intermediate hole 32 is drilled. Next, after inserting the intermediate joint member 23 over each slit pipe joint 22, a hardening grout material is injected and filled into the intermediate hole 32 and the slit pipe joint 22.

【0015】また、本発明の実施形態の特徴的構成とし
て、鋼製井筒24の天端高33は、斜面地17の谷側3
4を基礎天端高33bとし、斜面地17の山側35を斜
面土圧に対抗する高止まり天端高33aとして高低差を
設けてあり、この高止まり天端高33aのある継手付き
鋼管20の上部を土留め壁36としてある。さらに、鋼
製井筒24内に構築すべき基礎頂板26の下端37から
上方の井筒内の土砂が掘削されていて、この掘削部分に
頂板コンクリート26aが充填打設され、かつ継手付き
鋼管20の鋼管本体21から突出させた結合筋(ジベ
ル)38と強固に結合されて前記基礎頂板26を構成し
ている。
Further, as a characteristic configuration of the embodiment of the present invention, the top height 33 of the steel well tube 24 is set to the valley side 3 of the slope ground 17.
4 is defined as a base crown height 33b, and the mountain side 35 of the slope ground 17 is defined as a high stop crown height 33a against slope earth pressure. The upper part is a retaining wall 36. Further, the earth and sand in the well above the base plate 26 to be constructed in the steel well 24 is excavated from the lower end 37 of the base well 26, and the excavated portion is filled with the top plate concrete 26a and cast. The base top plate 26 is firmly connected to a connecting bar (dive) 38 protruding from the main body 21.

【0016】次に、本発明方法を実施して斜面地に鋼管
コンクリート井筒基礎を築造する例を説明する。まず、
図5,図6に示すように斜面地17における山側35施
工のために後述の全旋回式掘削機19を設置するため、
および、後述のクローラクレーン13の設置のために、
斜面地17の山側35と谷側34に第1と第2の作業ス
ペース39,40を段切り等により階段状に設け、な
お、必要により水平造成地41を設ける。つまり、第1
と第2の作業スペース39,40は、各々全旋回式掘削
機19設置のための作業スペースと、クローラクレーン
16設置のための作業スペースであるから、それぞれの
スペースが確保されればよく、それぞれの作業スペース
は同じ高さにある必要がない。
Next, an example of carrying out the method of the present invention to build a steel tube concrete well foundation on a slope will be described. First,
As shown in FIGS. 5 and 6, in order to install a below-described all-turn type excavator 19 for the construction of the mountain side 35 on the slope ground 17,
And, for installation of the crawler crane 13 described below,
First and second work spaces 39 and 40 are provided in the mountain side 35 and the valley side 34 of the sloped land 17 in a stepwise manner by step cutting, and a horizontal land 41 is provided as necessary. That is, the first
And the second work spaces 39 and 40 are a work space for installing the full-rotation type excavator 19 and a work space for installing the crawler crane 16, respectively. Work spaces need not be at the same height.

【0017】したがって、斜面地17の井筒基礎を築造
すべき部位のうち、一番低い高さ位置に合わせて井筒基
礎全体を築造する地盤を平坦地に作る必要がなく、この
ため、図に示すように段切り等により上下2段に第1,
第2の作業スペース39,40を造成することで十分に
対応でき、井筒基礎全体のために広いスペースの平坦地
を作る場合におけるような土留め工を必要とせず、かつ
整地土量を少なくすることができる(掘削土量の低減に
ついての具体的な数字については前述した)。
Therefore, it is not necessary to make the ground on which the entire well of the well is to be built on a flat ground in accordance with the lowest height position among the portions of the slope ground 17 where the well is to be built. The first, upper and lower two steps such as step cutting
The second working spaces 39 and 40 can be sufficiently prepared by forming the second working spaces 39 and 40, and do not require earth retaining work as in the case of making a flat space with a large space for the entire well tube foundation, and reduce the amount of soil leveled. (The specific figures for reduction of excavated soil volume are described above).

【0018】次に、図7,図8に示すように、第2作業
スペース40にクローラクレーン13を設置し、第1作
業スペース39に全旋回式掘削機19を設置する。この
全旋回式掘削機19はクラウン42を介してクローラク
レーン13の吊下げロープ41に吊下げられている。そ
して前記掘削機19により、竪孔18を掘削する。図
中、44はクラブハンマーである。このときの竪孔18
の掘削は、図8に示すように平面円形の井筒体を構成す
る円周線(C)上で、かつ山側35の所定角度範囲に亘
り複数掘削されている。
Next, as shown in FIGS. 7 and 8, the crawler crane 13 is installed in the second work space 40, and the full-rotation type excavator 19 is installed in the first work space 39. The full-turn type excavator 19 is suspended by a suspension rope 41 of the crawler crane 13 via a crown 42. The excavator 19 excavates the pit 18. In the figure, reference numeral 44 denotes a club hammer. The pit 18 at this time
As shown in FIG. 8, a plurality of excavations are made on the circumferential line (C) constituting the plane circular well cylinder and over a predetermined angle range of the mountain side 35.

【0019】このときの竪孔18の構築順序は、図8に
示す通りで、記号イで示す図形が竪孔18に継手付き鋼
管20を建込み完了した図を示し、記号ロで示す図形が
先行建込み予定位置を示し、記号ハで示す図形がラップ
建込予定位置を示す。
At this time, the construction order of the vertical hole 18 is as shown in FIG. 8, and the figure shown by the symbol a shows the figure in which the steel pipe 20 with the joint is completely installed in the vertical hole 18, and the figure shown by the symbol B is The preceding laying planned position is shown, and the figure indicated by the symbol C indicates the lap laying planned position.

【0020】前記竪孔18の掘削に際しては、泥水を用
いない掘削方式例えばケーシング併用掘削機を使用し
て、斜面地17の地盤に竪孔2を穿設する。地盤が脆い
斜面地17では泥水を用いた掘削方式を採用すると、孔
内から逸出した水が斜面に滞溜して地すべりを誘発する
恐れがあるから、泥水を使用しない掘削方式を採用する
のが好ましい。
When excavating the vertical hole 18, the vertical hole 2 is formed in the ground of the slope ground 17 by using an excavation method that does not use muddy water, for example, an excavator with a casing. If the excavation method using muddy water is adopted in the sloping ground 17 where the ground is fragile, the water that escapes from the hole may accumulate on the slope and induce a landslide. Is preferred.

【0021】そして、図9、図10に示すように井筒築
造予定位置の山側35の所定の角度範囲に亘って竪孔1
本分の間隔をあけて先行建込み予定の竪孔18を掘削
し、この竪孔18内に継手付き鋼管20を挿入し、次い
で竪孔18の孔壁と継手付き鋼管20との間に硬化性グ
ラウト材30を注入充填する。次に、前記先行建込み予
定の竪孔18の中間にラップ建込み予定の竪孔18を掘
削し、前記と同様にこの竪孔18内に継手付き鋼管20
を挿入し、次いで竪孔18の孔壁と継手付き鋼管20と
の間に硬化性グラウト材30を注入充填する。
Then, as shown in FIGS. 9 and 10, the pit 1 extends over a predetermined angular range on the mountain side 35 at the position where the well is to be constructed.
A vertical hole 18 to be erected in advance is excavated at intervals corresponding to this, and a steel pipe 20 with a joint is inserted into the vertical hole 18 and then hardened between the hole wall of the vertical hole 18 and the steel pipe 20 with a joint. The grout material 30 is injected and filled. Next, a pit 18 to be wrapped is excavated in the middle of the pit 18 to be preceded, and a steel pipe 20 with a joint is inserted into the pit 18 in the same manner as described above.
Then, the hardening grout material 30 is injected and filled between the hole wall of the vertical hole 18 and the steel pipe 20 with the joint.

【0022】次に隣り合う継手付き鋼管20における対
向する側のスリットパイプ製継手22内の硬化性グラウ
ト材30を、クロスビットを有する回転衝撃工具(図1
1に示すパーカッションドリル45)により掘削して、
そのスリットパイプ製継手22内を空間とする。(ま
た、前述の様にスリットに沿って蓋を取り付けておき、
硬化性グラウト材30の浸入を防ぐ方法もある。)その
後、その蓋をガイド部材により破壊するようにしてもよ
い。次いで隣り合う継手付き鋼管20の対向する側のス
リットパイプ製継手22内に嵌挿されるガイド部材を有
する掘削機により、隣り合うスリットパイプ製継手22
に近接すると共に隣り合う竪孔18にオーバラップする
中間孔32を穿設して空間を形成し、次にこの継手22
内に各スリットパイプ製継手22にわたってI形鋼から
なる中間継手部材23のフランジ側部分を挿入したの
ち、前記中間孔32内およびスリットパイプ製継手22
内の硬化性グラウト材を注入充填する(図3参照)。前
述の施工作業を経て図10に示すとおり井筒築造予定位
置の山側35の所定の角度範囲に亘ってその天端高33
が高止まり天端高33bである継手付き鋼管連続壁を築
造し、その上部を土留め壁36とし、この土留め壁36
の内側に、谷側井筒体施工用の作業スペースを確保す
る。
Next, the hardening grout material 30 in the slit pipe joint 22 on the opposite side of the adjacent steel pipe 20 with a joint is connected to a rotary impact tool having a cross bit (FIG. 1).
Drilling with the percussion drill 45) shown in 1
The inside of the slit pipe joint 22 is defined as a space. (Also, as described above, attach the lid along the slit,
There is also a method of preventing penetration of the curable grout material 30. Then, the lid may be broken by the guide member. Next, an adjacent slit pipe joint 22 is inserted by an excavator having a guide member inserted into the slit pipe joint 22 on the opposite side of the adjacent jointed steel pipe 20.
A space is formed by drilling an intermediate hole 32 that is close to and adjacent to the vertical hole 18 and forms a space.
After the flange-side portion of the intermediate joint member 23 made of I-shaped steel is inserted into each of the slit pipe joints 22, the inside of the intermediate hole 32 and the slit pipe joint 22 are inserted.
The curable grout material inside is filled and filled (see FIG. 3). Through the above-mentioned construction work, as shown in FIG.
Of the steel pipe continuous wall with a joint having a high end and a top end height of 33b, and the upper part thereof is used as a retaining wall 36.
A work space for the construction of the valley-side well body will be secured inside the building.

【0023】次に、図11,図12に示すように、前記
の掘削作業と同じ作業手順で井筒築造予定位置の谷側3
4の所定角度に亘る、谷側の鋼製井筒築造を行なう。こ
の谷側鋼製井筒の天端高33は基礎天端高33aとされ
て、土留め壁36を構成する高止まり天端高33bより
も低い位置に設けられる。
Next, as shown in FIG. 11 and FIG.
Construction of a steel well tube on the valley side over the predetermined angle of 4 is performed. The crown height 33 of the valley-side steel well is a base crown height 33a, and is provided at a position lower than the high stop crown height 33b constituting the retaining wall 36.

【0024】こうして、図11、図12に示されるよう
に斜面地17にクローラクレーン13と、これに吊下げ
られる全旋回式掘削機19とにより、基礎天端高33a
と高止まり天端高33bを有した継手付き鋼管20から
なる鋼製井筒24を築造する。なお、1本の継手付き鋼
管20の長さが築造する井筒の長さよりも短かい場合
は、継手付き鋼管20を溶接により継ぎ足しながら竪孔
内に挿入し、次いで竪孔18の孔壁と継手付き鋼管20
との間に硬化性グラウト材30を注入充填して柱体31
を築造する。
In this manner, as shown in FIGS. 11 and 12, the crawler crane 13 and the full-rotation type excavator 19 suspended from the crawler crane 13 on the sloped land 17 allow the base crown height 33a to be increased.
Then, a steel well 24 made of a steel pipe 20 with a joint having a high stop 33b is built. If the length of the steel pipe 20 with one joint is shorter than the length of the well tube to be built, the steel pipe 20 with the joint is inserted into the pit while being welded together, and then the wall of the pit 18 and the joint are connected. Steel pipe 20
Is filled with a curable grout material 30 to fill the column 31
To build.

【0025】次に、図13,図14に示すように、掘削
機43を用いて鋼製井筒24内の上部を所定深さL掘削
し、掘削後の井筒内空間に露出した継手付き鋼管20の
表面に複数の結合筋38を溶接し(図4参照)、その
後、前記掘削部の下端37から基礎天端高33bの間に
頂板コンクリート26aを打設充填し、前記結合筋38
を介して継手付き鋼管20と一体化して基礎頂板26を
構築する。その後、基礎頂板26に植設した鉄筋(図示
省略)を介して、基礎頂板26の上にコンクリート橋脚
27を構築するものである。なお、井筒基礎築造の後、
鋼製井筒24のうちの土留め壁36として用いた継手付
き鋼管20は切断しても構わない。また、継手付き鋼管
20同士の連結構造も公知の他の方法を用いてもよい。
Next, as shown in FIGS. 13 and 14, the upper part of the steel well 24 is excavated to a predetermined depth L using the excavator 43, and the steel pipe 20 with the joint exposed to the inside of the well after excavation is excavated. Then, a plurality of connecting bars 38 are welded to the surface of the excavated portion (see FIG. 4).
To form a base top plate 26 by integrating with the steel pipe 20 with a joint. Thereafter, a concrete pier 27 is constructed on the foundation top plate 26 via a reinforcing bar (not shown) planted on the foundation top plate 26. In addition, after Izutsu foundation construction,
The jointed steel pipe 20 used as the earth retaining wall 36 of the steel well tube 24 may be cut. Moreover, the connection structure between the steel pipes 20 with joints may use another known method.

【0026】[0026]

【発明の効果】以上説明したように本発明によると次の
効果がある。本発明では、小径の鋼管杭を竪孔に順次建
込み、1エレメント毎に井筒を構築するもので、構築
される井筒内上部は利用可能な面積であり、この井筒内
頂部を、井筒体構築終了までは掘削を行なうことなく利
用でき、そこにクレーン等の設置が可能である。それに
伴ない、小径の鋼管杭を建て込み作業するための狭い
平面スペースを確保するのみでよく、井筒基礎外径の全
体を平坦に整地する必要がないので、斜面の整地は段切
りでよく、掘削土砂量が少ない。よって、前記,が
相俟って狭い作業スペースで、掘削土量が少なく、周辺
環境を損なわず、山間部での自然環境への影響が少ない
という効果がある。また、山側に設置された継手付き鋼
管を自立式土留め壁として谷側を造成するので、新たな
土留め壁を必要とせず、仮設工事量の全体工事量に占め
る割合を小さくできて、井筒基礎の築造を迅速に行なえ
る効果がある。
As described above, according to the present invention, the following effects can be obtained. In the present invention, small-diameter steel pipe piles are sequentially built in a pit, and a well is constructed for each element. The upper part in the constructed well is an available area. Until the end, it can be used without excavation, and cranes can be installed there. Along with this, it is only necessary to secure a narrow plane space for installing small diameter steel pipe piles, and it is not necessary to level the entire outer diameter of the well base, so leveling of slopes may be stepped, Excavation volume is small. Therefore, in combination with the above, there is an effect that the excavated soil amount is small, the surrounding environment is not impaired, and the influence on the natural environment in the mountainous area is small in a narrow work space. In addition, since the valley side is constructed with steel pipes with joints installed on the mountain side as self-supporting retaining walls, new retaining walls are not required, and the ratio of temporary construction work to the total work volume can be reduced. This has the effect of quickly building the foundation.

【図面の簡単な説明】[Brief description of the drawings]

【図1】斜面地に設置される鋼管井筒基礎の設置状態を
示す縦断側面図である。
FIG. 1 is a vertical sectional side view showing an installation state of a steel pipe well foundation installed on a slope.

【図2】図1のA−A断面図である。FIG. 2 is a sectional view taken along line AA of FIG.

【図3】図2の部分拡大図である。FIG. 3 is a partially enlarged view of FIG. 2;

【図4】図1のB−B断面図である。FIG. 4 is a sectional view taken along line BB of FIG. 1;

【図5】本発明に係る鋼管井筒基礎の築造方法を斜面地
に実施する第1作業工程の側面説明図である。
FIG. 5 is an explanatory side view of a first operation step for implementing the method for constructing a steel pipe well foundation according to the present invention on a slope.

【図6】図5の平面図である。FIG. 6 is a plan view of FIG. 5;

【図7】同じく第2作業工程の側面説明図である。FIG. 7 is an explanatory side view of the second operation step.

【図8】図7の平面図である。FIG. 8 is a plan view of FIG. 7;

【図9】同じく第3作業工程の側面説明図である。FIG. 9 is an explanatory side view of the third operation step.

【図10】図9の平面図である。FIG. 10 is a plan view of FIG. 9;

【図11】同じく第4作業工程の側面説明図である。FIG. 11 is an explanatory side view of the fourth operation step.

【図12】図11の平面図である。FIG. 12 is a plan view of FIG.

【図13】同じく第5作業工程の側面説明図である。FIG. 13 is an explanatory side view of the fifth working step.

【図14】図13の平面図である。FIG. 14 is a plan view of FIG.

【図15】従来の深礎工法による斜面の竪孔掘削状況を
示す縦断面図である。
FIG. 15 is a vertical cross-sectional view showing a state of excavation of a pit on a slope by a conventional deep foundation method.

【図16】図15の平面図である。FIG. 16 is a plan view of FIG.

【符号の説明】[Explanation of symbols]

1 斜面地 2 作業スペース 3 山側 4 側面 5 鋼矢板 6 土留め壁 7 竪孔 8 掘削機 9 ダンプトラック 10 セグメント 11 セグメント置き場 12 鉄筋置き場 13 クローラクレーン 14 作業スペース 15 資機材置き場 16 仮設ハウス 17 斜面地 18 竪孔 19 全旋回掘削機 20 継手付き鋼管 21 鋼管本体 22 スリットパイプ製継手 23 中間継手部材 24 鋼製井筒 25 地盤 26 基礎頂板 26a 頂板コンクリート 27 橋脚 28 橋梁 29 道路橋 30 グラウト材 31 柱体 32 中間孔 33 天端高 33a 高止まり天端高 33b 基礎天端高 34 谷側 35 山側 36 土留め壁 37 下端 38 結合筋 39 第1作業スペース 40 第2作業スペース 41 吊下げロープ 42 クラウン 43 掘削機 44 クラブハンマー 45 パーカッションドリル DESCRIPTION OF SYMBOLS 1 Slope 2 Work space 3 Mountain side 4 Side 5 Steel sheet pile 6 Retaining wall 7 Vertical hole 8 Excavator 9 Dump truck 10 Segment 11 Segment storage 12 Reinforcement storage 13 Crawler crane 14 Work space 15 Equipment storage 16 Temporary house 17 Slope Reference Signs List 18 vertical hole 19 full-turn excavator 20 steel pipe with joint 21 steel pipe main body 22 slit pipe joint 23 intermediate joint member 24 steel well tube 25 ground 26 foundation top plate 26a top plate concrete 27 bridge pier 28 bridge 29 road bridge 30 grout material 31 pillar body 32 Intermediate hole 33 Top end height 33a High stop top end height 33b Base top end height 34 Valley side 35 Mountain side 36 Earth retaining wall 37 Lower end 38 Joining bar 39 First work space 40 Second work space 41 Hanging rope 42 Crown 43 Excavator 44 Club Hammer 45 Over cut Deployment drill

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 斜面地に設置される井筒基礎であって、
円形又は方形に並べて掘削した多数の掘削孔内に継手付
き鋼管を挿入し、その周りにモルタル又はコンクリート
のグラウト材を充填し、前記継手付き鋼管の継手同士を
継手材で連結することで壁体として井筒体を構築し、こ
の井筒体の天端高を、斜面の下手側を基礎天端高とし、
斜面の上手側を斜面土圧に対抗する高止まり天端高とし
てこれを土留め壁とし、前記井筒体内に構成すべき基礎
頂板の下端から上方の井筒内の土砂を掘削してその掘削
部分に前記基礎頂板をなす頂板コンクリートを充填し
て、この頂板コンクリートと、井筒体に設けられた結合
材とを強固に結合している構成を特徴とする斜面地に設
置される井筒基礎。
Claims: 1. A well foundation installed on a slope,
A steel pipe with a joint is inserted into a large number of drilled holes drilled side by side in a circle or a square, grout material of mortar or concrete is filled around the pipe, and the joints of the steel pipe with a joint are connected to each other with a joint material. The top of this well is set as the top of the well, and the lower side of the slope is taken as the base height.
The upper side of the slope is a high stop ceiling against the earth pressure of the slope and this is used as a retaining wall, and the earth and sand in the well above the bottom is excavated from the lower end of the foundation top plate to be formed in the well and the excavated portion is formed. A well foundation installed on a slope, characterized in that the top concrete forming the foundation top plate is filled and the top concrete is firmly bonded to a binder provided on the well body.
【請求項2】 斜面地を整地して平坦地とした作業スペ
ースにクレーンを配設し、前記作業スペースの上手側の
平坦地に、前記クレーンで吊下げた掘削機を設置し、こ
の掘削機で前記斜面地の上手側を貫通して円形又は方形
の井筒体山側部を形成する複数の竪孔を掘削し、前記上
手側の各竪孔内に高止まり天端高を形成するよう継手付
き鋼管を建込み、その周囲をグラウトして土留め壁を構
成し、その後、前記斜面地の下手側を貫通して前記円形
又は方形の井筒体谷側部分を形成する複数の竪孔を掘削
し、前記下手側の各竪孔内に継手付き鋼管を建込み、そ
の周囲をグラウトし、継手付き鋼管の継手部内側の掘削
を行なって継手部間を中間継手材で連結し、かつ中間継
手材をグラウトすることで井筒を構成し、この鋼製井筒
内の上部を掘削して基礎頂板を構築することを特徴とす
る斜面地に設置される井筒基礎の築造方法。
2. A crane is provided in a work space where the slope is leveled to be flat, and an excavator suspended by the crane is installed on a flat ground on the upper side of the work space. Excavating a plurality of pits that form a circular or square well cylinder side by penetrating the upper side of the sloped land with a joint so as to remain high in each of the pits on the upper side and form a top end height A steel pipe is erected, grouted around it to form a retaining wall, and then excavated a plurality of pits that penetrate the lower side of the sloped land and form the circular or square well tube valley side portion. A steel pipe with a joint is erected in each of the lower pits, the periphery thereof is grouted, the inside of the joint part of the steel pipe with the joint is excavated, the joint parts are connected with an intermediate joint material, and the intermediate joint material is formed. The well is constructed by grouting, and the upper part of this steel well is excavated. A method of constructing a well foundation installed on a slope characterized by constructing a foundation top plate.
JP29787296A 1996-10-23 1996-10-23 Steel pipe concrete well foundation installed on slope and its construction method Expired - Fee Related JP3635167B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29787296A JP3635167B2 (en) 1996-10-23 1996-10-23 Steel pipe concrete well foundation installed on slope and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29787296A JP3635167B2 (en) 1996-10-23 1996-10-23 Steel pipe concrete well foundation installed on slope and its construction method

Publications (2)

Publication Number Publication Date
JPH10121463A true JPH10121463A (en) 1998-05-12
JP3635167B2 JP3635167B2 (en) 2005-04-06

Family

ID=17852224

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29787296A Expired - Fee Related JP3635167B2 (en) 1996-10-23 1996-10-23 Steel pipe concrete well foundation installed on slope and its construction method

Country Status (1)

Country Link
JP (1) JP3635167B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100939916B1 (en) * 2009-07-14 2010-02-03 나석주 Construction method of train platform base pile
JP2010159601A (en) * 2009-01-09 2010-07-22 Railway Technical Res Inst Construction method of structure
JP2020097820A (en) * 2018-12-17 2020-06-25 鹿島建設株式会社 Construction method of earth retaining wall on slope and construction method of waste disposal site on slope
JP2020169467A (en) * 2019-04-02 2020-10-15 鹿島建設株式会社 Shear force transmission mechanism and construction method of steel pipe sheet pile foundation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010159601A (en) * 2009-01-09 2010-07-22 Railway Technical Res Inst Construction method of structure
KR100939916B1 (en) * 2009-07-14 2010-02-03 나석주 Construction method of train platform base pile
JP2020097820A (en) * 2018-12-17 2020-06-25 鹿島建設株式会社 Construction method of earth retaining wall on slope and construction method of waste disposal site on slope
JP2020169467A (en) * 2019-04-02 2020-10-15 鹿島建設株式会社 Shear force transmission mechanism and construction method of steel pipe sheet pile foundation

Also Published As

Publication number Publication date
JP3635167B2 (en) 2005-04-06

Similar Documents

Publication Publication Date Title
JP3211673B2 (en) Simple temporary bridge temporary pier construction method
KR20130081971A (en) Precast concrete wall and method for constructing underground permanent wall using the precast concrete wall
KR102195504B1 (en) Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method
KR101011169B1 (en) Precast Concrete Wall and Construction Method using the same
CN112127900A (en) Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
KR102195510B1 (en) Construction method for earth self-retaining wall using reinforcing member and PHC pile
Gil-Martín et al. Developments in excavation bracing systems
CN112726627B (en) Bored pile structure in karst region and construction method
JP2000352296A (en) Method o constructing passage just under underground structure
JP3635167B2 (en) Steel pipe concrete well foundation installed on slope and its construction method
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
CN214169107U (en) Cast-in-situ bored pile structure in area with intense karst
JPH02200917A (en) Landslide suppressing well cylinder and its building method
KR102194381B1 (en) Pile for Earth self-retaining wall using double I beam
KR102195496B1 (en) Pile for earth self-retaining wall using cast in place concrete pile with double I beam
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
EP0724066A1 (en) Method for underground excavation
KR100429283B1 (en) Construction Method using Precast Concrete for Diaphragm Wall
Kordahi Underpinning strategies for buildings with deep foundations
JP3681883B2 (en) Long-cut soil slope reduction method
KR101285987B1 (en) Improved Compound Roof Tunnel Method
KR102194388B1 (en) Construction method for earth self-retaining wall using reinforcing member and Soil retaining plate construction method
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
KR102194394B1 (en) Construction method for earth self-retaining wall using reinforcing member and SCW construction method
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041214

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Effective date: 20041221

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20041228

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 4

Free format text: PAYMENT UNTIL: 20090107

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 5

Free format text: PAYMENT UNTIL: 20100107

LAPS Cancellation because of no payment of annual fees