JPS5858327A - Driving of underground pile - Google Patents
Driving of underground pileInfo
- Publication number
- JPS5858327A JPS5858327A JP15755681A JP15755681A JPS5858327A JP S5858327 A JPS5858327 A JP S5858327A JP 15755681 A JP15755681 A JP 15755681A JP 15755681 A JP15755681 A JP 15755681A JP S5858327 A JPS5858327 A JP S5858327A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- temporary
- driving
- piles
- main
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/28—Prefabricated piles made of steel or other metals
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【発明の詳細な説明】 本発明は地中杭の打設方法に関するものである。[Detailed description of the invention] The present invention relates to a method for driving underground piles.
土留用の杭は地上から匣接打ち込むものであるが、地下
構造物の周囲にのみ設ける地中杭(構内杭)は構造物上
部から地itでの間は不要である。Earth retaining piles are driven into the box from the ground, but underground piles (premium piles), which are installed only around underground structures, are not required between the top of the structure and the ground.
しかしいきなり地中の深部に杭だけを位置させることは
できないから従来は次のような方法を採用しているが各
々欠点を有する。However, since it is not possible to suddenly place only the piles deep underground, the following methods have been used in the past, but each method has its own drawbacks.
〈1〉 排土部分の掘削終了の後、掘削された構内よ
り打込みをする方法。<1> A method in which after the excavation of the earth removal area is completed, the earth is driven into the excavated premises.
しかしこの方法の場合、構内で打設するためだけに種々
の機械を構内に搬入しまたは搬出する必要があり、その
うえ打設作業に従事する作業人員も必要となる。However, in the case of this method, it is necessary to carry various machines into and out of the premises just for pouring on the premises, and in addition, workers who are engaged in the pouring work are also required.
その結果作業工程にロスが発生し、工期が長くなり、打
込み費月ゴが高く付く等の欠点が生じる。As a result, there are disadvantages such as losses in the work process, lengthening of the construction period, and high monthly driving costs.
〈2〉 最初にCiLから土留杭と土留杭より相尚長
さの構内杭を打込み一11削を並行して構内杭の不要が
分を順次切断していく方法。〈2〉 First, from CiL, drive the earth retaining pile and the yard pile of the same length as the earth retaining pile, and then cut the unnecessary yard piles one by one in parallel.
この方法の場合(/Cは杭の露出部分が、掘削作業の能
率を低下させ、または切断費用が高くつく等の欠点を有
するものであった。In the case of this method (/C), the exposed portion of the pile had disadvantages such as lowering the efficiency of excavation work and increasing cutting costs.
またその他の構内杭として2本の杭をワイヤや磁石を使
った継手装置Wを用いて連結する構内杭も在任するが、
いずれも−11¥4作性や信頼1ノrに問題があった。There are also other types of on-site piles that connect two piles using a joint device W that uses wire or magnets.
Both had problems with -11 yen 4 performance and reliability.
本発明は以上のような点の改簀についでなされたもので
作業能率の向上を促進し、作業経費の節減が可能で打込
みの正確な地中杭の打設方法を提供することを目的とす
る。The present invention was made in response to the above-mentioned problems, and aims to provide a method for driving underground piles that can improve work efficiency, reduce work costs, and ensure accurate driving. do.
次に実施例について説明する。Next, an example will be described.
(1)構内杭(第1図) 本発明の構内杭は仮杭(1)と本杭(2)で構成する。(1) Piles within the premises (Fig. 1) The in-plant pile of the present invention is composed of a temporary pile (1) and a real pile (2).
仮t(1)は例えばIIH型鋼あり下端には水平面(1
1)を形成する。Temporary t(1) is, for example, a type IIH steel with a horizontal surface (1
1) Form.
本杭(2)は例えばH型鋼であり上端には水平面(21
)を形成する。This pile (2) is made of, for example, H-shaped steel, and has a horizontal surface (21
) to form.
そして水平面(21)下方には?ルト孔(6)を複数個
開設する。And below the horizontal plane (21)? Open multiple route holes (6).
仮杭(])は本杭(2)の打設終了時せでの短時間だけ
必要とされる杭であり、一方本杭(2)は打設後長期間
にわたって地中に位置し、荷重の支持その他の役割を果
す杭である。The temporary pile (]) is a pile that is needed only for a short period of time when the driving of the main pile (2) is completed, whereas the main pile (2) is located in the ground for a long period of time after driving, and is under load. This is a pile that serves as a support and other functions.
そして仮杭(1)と本杭(2)を仮杭(1)を上に、本
杭(2)を下にして同軸線上に配置1〜、両統間に間隔
(L)を介して後述する連結板(3)によって連結し構
内杭を形成する。Then, the temporary pile (1) and the main pile (2) are arranged on the same axis with the temporary pile (1) on top and the main pile (2) on the bottom. They are connected by a connecting plate (3) to form a yard pile.
(2)連結部
連結板(3)は両統(1) (2)を形成するI(型鋼
の板幅より多少狭い板幅で形成する鉄板片であり、下方
にはボルト孔(5)を開設する。(2) The connecting plate (3) is an iron plate piece formed with a plate width slightly narrower than the plate width of the I (shaped steel) that forms both sides (1) and (2), and has bolt holes (5) at the bottom. do.
この連結板(3)の上部を仮杭(1)の下端に溶接する
。The upper part of this connecting plate (3) is welded to the lower end of the temporary pile (1).
溶接個所は例えばF(型鋼のフランジ外面、及びリブの
両面とし、連結板(3)の下半分は仮杭(1)下端より
も突出させておく。The welding points are, for example, the outer surface of the flange of the F (shaped steel) and both sides of the rib, and the lower half of the connecting plate (3) is made to protrude beyond the lower end of the temporary pile (1).
連結板(3)により両統(1) (2)を連結するには
、両デルト(4)を貫通させて固定する。In order to connect the two mains (1) and (2) with the connecting plate (3), both delts (4) are passed through and fixed.
このボルト(4)は後述するように杭の打ち込みの打撃
によって剪断する程度の径、強度の物を一3−
用いる。As will be described later, this bolt (4) has a diameter and strength enough to be sheared by the impact of driving the pile.
次に構内杭の打込み作業について説明する。Next, we will explain the work of driving in-plant piles.
(1) オーガ削孔
あらかじめ打込み予だ論所に削孔機で予定深さのオーガ
孔(7)を削孔する。(第31ml )オーガ孔(7)
は惰内抗、が容易に進入可能な径に開孔する、。(1) Drill an auger hole (7) at the planned depth using a drilling machine in advance. (No. 31ml) Auger hole (7)
The hole is drilled to a diameter that allows easy entry.
削孔深さは、(仮杭(1)の長さ十本杭(2)の長さ)
より1.0 Om〜2.0 (] +1Ql)短かく設
定する。The drilling depth is (the length of temporary pile (1) and the length of ten piles (2))
Set 1.0 Om to 2.0 (] +1Ql) shorter.
(2)杭の建込み
あらかじめ仮杭(1)と本杭(2)を前述のように連結
板(3)で接続し構内杭を形成する。(2) Erecting piles In advance, connect temporary piles (1) and regular piles (2) with connecting plates (3) as described above to form on-site piles.
この構内杭をクレーン等で吊り上げオーガ孔(7)内へ
建込む。This on-site pile is lifted up by a crane or the like and placed into the auger hole (7).
(3)打込み(第4図)
地上より打込距離QO突出している仮杭(1)の上端面
をモンケク尋の打撃装置にで打込む。(3) Driving (Figure 4) Drive the upper end of the temporary pile (1), which protrudes a driving distance QO above the ground, into the striking device of Monkekuhiro.
すると本杭(2)と連結板(3)がボルト(4)のみで
連結しであるため71?ルト(4)にせん断を起こし連
結−5〜
4−
オ喧3)と本杭(2)の接合が解除される。Then, since the main pile (2) and the connecting plate (3) are connected only with bolts (4), 71? This causes a shear in the bolt (4), and the connection between the connection -5~4- 3) and the main pile (2) is released.
その結果両統(1) (2)の水平面(11)(21)
は直接に接触し本杭(2)は軸線上で打撃力を受は距離
11だけ地中に打ち込廿れる。As a result, the horizontal plane (11) (21) of Ryoto (1) (2)
are in direct contact and the main pile (2) receives the impact force on the axis and is driven into the ground by a distance of 11.
(4)仮杭の撤去。掘削(第5図1)
予定本数の打込み終了後、杭抜槓によす仮杭(1)群を
引抜く。(4) Removal of temporary piles. Excavation (Fig. 5 1) After driving the scheduled number of piles, pull out the group of temporary piles (1) that will be used for pile extraction.
ボルト(4)が切断しているため本杭(2)群は地中の
予定位置に残り、仮杭(1)群のみ撤去されることにな
る。Since the bolts (4) have been cut, the main pile (2) group will remain in the planned position underground, and only the temporary pile (1) group will be removed.
次に通常の方法VCよって構内を掘削する。The premises are then excavated by conventional VC methods.
以上のようになるから本発明は次のような効果を期待す
ることができる。As described above, the following effects can be expected from the present invention.
〈イ〉 本発明の構内杭は地上から打込むことができる
ため構内への打込様の搬入搬出の必要がなく作業能率が
向上する。<B> Since the yard pile of the present invention can be driven from the ground, there is no need to carry it in and out like driving it into the yard, improving work efficiency.
〈口〉 構内の掘削と同時に杭を順次切断する必要が全
くなく、仮杭を引抜くことによりM両杭である本杭を形
成でき経済的である。<Exposure> There is no need to cut the piles one after another at the same time as the excavation of the premises, and the actual pile, which is an M double pile, can be formed by pulling out the temporary pile, which is economical.
〈ノ) 上杭と下枝の両統間に一定間隔(■・)を介
(〜、連結g7で一方の杭のみを仮固定し両枝を連結す
るので、打込時には上杭と下枝の分団が容易であり、同
軸線上で打撃力を伝達することができる。〈〈〉) Interpose a certain interval (■・) between the upper pile and the lower branch (~, since only one stake is temporarily fixed with connection g7 and both branches are connected, the division of the upper pile and lower branch will be separated when driving. It is easy and the impact force can be transmitted coaxially.
〈今 連結板の取付けは簡単な作業で行うことができか
つ硅込時には十分な連結力を得ることができる。(Now) Attaching the connecting plate is a simple task, and sufficient connecting force can be obtained when screwing in.
ぐ) 上杭はオーガ孔内に位置するため杭引抜きの場合
比較的低能力の引抜機を1ψ月1することができる。(g) Since the upper pile is located inside the auger hole, a relatively low-capacity extractor can be used once a month to pull out the pile.
4.1g1面の1111巣な能、間 第1図:打撃前の継手部分の斜視図、 第2図:杓撃後の継手部分の斜視図、 第3ド41〜第5図:施工順序の説明図。4.1g 1 side of 1111 nests, between Figure 1: Perspective view of the joint part before impact. Figure 2: Perspective view of the joint part after being rammed, 3rd do 41 to 5: Explanatory diagram of construction order.
1:仮杭、2:本杭、3:)1ド結板、4ニア」ンルト
。1: Temporary pile, 2: Main pile, 3:) 1 hardboard, 4 near bolt.
特許出願人 大成建設株式会社 代理人 弁理士 山 口 朔 生=7= 第1図Patent applicant: Taisei Corporation Agent Patent Attorney Yamaguchi Saku = 7 = Figure 1
Claims (1)
本杭上端とは一定の間隔を介して位置せしめ、 オーガ一孔内に仮杭と本杭とを一体で吊り下ろし、 仮杭上端を打撃してボルトを切断した後、仮杭下端と本
杭上端とを接触させて打撃全本杭下端に伝達して本杭を
オーガ一孔下底に打ち込み、仮杭を引き上げることを特
徴とする 地中杭の打設方法[Claims] A connecting plate is welded and fixed to the lower part of the temporary pile, the connecting plate and the upper part of the actual pile are fixed with bolts, the lower end of the temporary pile and the upper end of the actual pile are positioned with a certain distance between them, and the auger The temporary pile and the main pile are hung together in one hole, the upper end of the temporary pile is struck to break the bolt, the lower end of the temporary pile and the upper end of the main pile are brought into contact, and the entire blow is transmitted to the lower end of the main pile. An underground pile driving method characterized by driving the main pile into the bottom of the auger hole and pulling up the temporary pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15755681A JPS5858327A (en) | 1981-10-05 | 1981-10-05 | Driving of underground pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15755681A JPS5858327A (en) | 1981-10-05 | 1981-10-05 | Driving of underground pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS5858327A true JPS5858327A (en) | 1983-04-06 |
Family
ID=15652258
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP15755681A Pending JPS5858327A (en) | 1981-10-05 | 1981-10-05 | Driving of underground pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5858327A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6153915A (en) * | 1984-08-22 | 1986-03-18 | Marufuji Shiitopairu Kk | Method of driving down sheathing material |
JPS61191725A (en) * | 1985-02-20 | 1986-08-26 | Toda Constr Co Ltd | Stress material drawing work |
JPH01178610A (en) * | 1988-01-05 | 1989-07-14 | Kajima Corp | Setting method for stress member |
JP2010222943A (en) * | 2009-03-25 | 2010-10-07 | Nippon Steel Corp | Connection fitting for wall member and continuous underground wall construction method |
US20110308197A1 (en) * | 2009-02-11 | 2011-12-22 | Rob Wallace | Structural member |
-
1981
- 1981-10-05 JP JP15755681A patent/JPS5858327A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6153915A (en) * | 1984-08-22 | 1986-03-18 | Marufuji Shiitopairu Kk | Method of driving down sheathing material |
JPH0458526B2 (en) * | 1984-08-22 | 1992-09-17 | Marufuji Sheet Piling | |
JPS61191725A (en) * | 1985-02-20 | 1986-08-26 | Toda Constr Co Ltd | Stress material drawing work |
JPH01178610A (en) * | 1988-01-05 | 1989-07-14 | Kajima Corp | Setting method for stress member |
US20110308197A1 (en) * | 2009-02-11 | 2011-12-22 | Rob Wallace | Structural member |
JP2010222943A (en) * | 2009-03-25 | 2010-10-07 | Nippon Steel Corp | Connection fitting for wall member and continuous underground wall construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6681148B2 (en) | Bridge construction method, pillars and guide means used in the bridge construction method | |
CN214883827U (en) | Construction elevator foundation support system device that encorbelments | |
JPS5858327A (en) | Driving of underground pile | |
US5199824A (en) | Excavation shoring system | |
CN206071096U (en) | The underpinning device of load bearing wall in brick mix structure | |
CN219410877U (en) | Foundation pit supporting pile | |
JPS584094A (en) | Method of constructing low road cross | |
CN208668453U (en) | Electric power pylon earthing pole piling bar fastener driving device | |
JPS63280153A (en) | Underground inverted lining method | |
CN208792340U (en) | PC goes along with sb. to guard him the attachment device of steel-pipe pile | |
JPS57193622A (en) | Driving method of composite pile and used composite pile therefor | |
JPS61250222A (en) | Method and apparatus for connection of pile | |
CN108661067A (en) | Electric power pylon earthing pole piling bar fastener driving device and squeeze into method | |
CN211596749U (en) | Combined concrete precast pile | |
JPH10252080A (en) | Method for reinforcing foundation of pier for high level road | |
CN210621726U (en) | Construction device for hammering barbed anchor rod into high and steep blast furnace slag slope | |
JPS6153915A (en) | Method of driving down sheathing material | |
JP2650539B2 (en) | Construction method of underground diaphragm wall | |
CN217054226U (en) | Manual hole digging pile operating platform | |
CN210857189U (en) | Butt joint device for I-shaped steel in SMW construction method pile | |
JP2521795Y2 (en) | Retaining material | |
JPS61250229A (en) | Method and apparatus for penetration of steel sheet pile | |
RU2023811C1 (en) | Method of constructing wall in ground for protecting foundation of building | |
JP3325550B2 (en) | Pile construction equipment and pile construction method | |
JPH06173284A (en) | Construction method for self-standing continuous wall |