JPS6059210A - Replacing method of bridge reinforced concrete floor panel - Google Patents

Replacing method of bridge reinforced concrete floor panel

Info

Publication number
JPS6059210A
JPS6059210A JP16801583A JP16801583A JPS6059210A JP S6059210 A JPS6059210 A JP S6059210A JP 16801583 A JP16801583 A JP 16801583A JP 16801583 A JP16801583 A JP 16801583A JP S6059210 A JPS6059210 A JP S6059210A
Authority
JP
Japan
Prior art keywords
reinforced concrete
concrete
steel deck
slab
main girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP16801583A
Other languages
Japanese (ja)
Other versions
JPH0115647B2 (en
Inventor
成瀬 輝男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP16801583A priority Critical patent/JPS6059210A/en
Publication of JPS6059210A publication Critical patent/JPS6059210A/en
Publication of JPH0115647B2 publication Critical patent/JPH0115647B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は補修が必要となった橋梁鉄筋コンクリート床版
の張替え工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for resurfacing reinforced concrete deck slabs of bridges that require repair.

近年、■車両の増加等により橋梁鉄筋コンクリート床版
の老朽化が一段と進み、近い将来大岳の鉄筋コンクリー
ト床版の張替えが必要とされている。
In recent years, the reinforced concrete deck slabs of bridges have deteriorated further due to the increase in the number of vehicles, and it is expected that the reinforced concrete deck slabs at Mt. Otake will need to be replaced in the near future.

将来−ころ17た張′aンの必萼1式牛1:た思合は一
第1図に示す如く、主桁aのフランジa′上にジベルb
を介して一体に固定され且つ上面にアスファルトCを敷
設された鉄筋コンクリ−1〜床版dにおいて、まず、前
記アスファルトC及び鉄筋コンクリート床版dをエアー
ガウジング或いはコアブレーカにより解体除去した後、
従来の鉄筋コンクリート橋梁の建設と同様に配筋し型枠
を組んでコンクリートを打設することにより第1図の状
態に復旧させるようにしている。
In the future, the calyx 1 of the roller 17 should be placed on the flange a' of the main girder a, as shown in Figure 1.
In the reinforced concrete 1 to floor slab d which are fixed together via the asphalt C and have asphalt C laid on the upper surface, first, after dismantling and removing the asphalt C and the reinforced concrete floor slab d by air gouging or a core breaker,
Similar to the construction of conventional reinforced concrete bridges, the structure was restored to the state shown in Figure 1 by arranging reinforcement, building forms, and pouring concrete.

しかし上記従来方式においては、鉄筋コンクリート床版
を張替える際、再び鉄筋コンクリート床版を構成するよ
うにしているため、配筋、型枠の設置、足場の建設等多
大の現場作業が生じると共に、多大の」ンクリートt1
 flu 呈どその養生とにより非常に長い■−期を要
してしまう。
However, in the conventional method described above, when replacing the reinforced concrete slab, the reinforced concrete slab is constructed again, which requires a large amount of on-site work such as reinforcing, installing formwork, and constructing scaffolding. "Increet t1
Flu It takes a very long ■- period due to its development and curing.

このように鉄筋コンクリ−1・床版の張替えに長時間を
要することは、その間交通を遮断してしまうことになる
ので、近年の交通事情から重要な問題となっている。
In this way, the long time it takes to replace the reinforced concrete 1/floor slab means that traffic is blocked during that time, which has become an important problem in light of recent traffic conditions.

このため、前記したように、鉄筋コンクリ−ト床版dを
解体除去した後、主桁aのフランジa′上に、第2図に
示すように鋼床版eを溶接f固定したり、或いは第3図
に示すように鋼床版eをポル[〜Q等にて固定すること
により、主桁a上に直接連結して鋼床版eにより張替え
を行うことが考えられている。
For this reason, as mentioned above, after the reinforced concrete deck slab d is dismantled and removed, the steel deck slab e is fixed by welding f on the flange a' of the main girder a as shown in Fig. 2, or As shown in FIG. 3, it is considered that the steel deck slab e is fixed with poles [--Q, etc., so that it is directly connected to the main girder a, and the steel deck slab e is used for recladding.

しかしこの両方式にJ3い′Cも、作業の邪魔になるフ
ランジa′上の既存ジベルb (第1図参照)を除去す
る必要があり、しかも主桁aのフランジa′と新規鋼床
版eとを精密に位置合わせし現場調整することが大変で
あり(溶接の場合は開先精度の保持、ボルトの場合は孔
の位置ずれ及び孔数の問題)、更に上記操作に起因して
工期が延長されるといった問題を有していた。
However, for both types of J3'C, it is necessary to remove the existing dowel b (see Figure 1) on flange a', which obstructs the work, and to remove flange a' of main girder a and new steel deck slabs. It is difficult to precisely align and make on-site adjustments (in the case of welding, maintaining the groove accuracy, and in the case of bolts, there are problems with hole position misalignment and number of holes), and the above operations also cause problems with the construction time. The problem was that the period was extended.

本発明は、こうした実情に鑑みてなしたもので、補修に
際し、主桁のフランジ上の既存のジベルをそのまま残し
た状態で鉄筋コンクリート床版を解体除去し、続いて前
記フランジ上に矩・形空間を形成する連結リブを有した
鋼床版を予め工場等で製作しておきそれを前記フランジ
上に載置した後、前記矩形空間内にコンクリートを注入
して前記主桁と鋼床版を一体化させることにより、容易
にしかも短期間に張替えを行わしめることを目的とする
The present invention has been made in view of these circumstances. During repair, the reinforced concrete slab is dismantled and removed while the existing dowel on the flange of the main girder remains intact, and then a rectangular or shaped space is created on the flange. A steel deck slab having connecting ribs forming the main girder is manufactured in advance in a factory, etc., and is placed on the flange. Then, concrete is poured into the rectangular space to integrate the main girder and the steel deck slab. The purpose of this is to make it easier and faster to reupholster.

以下本発明の実施例を図面を参照しつつ説明する。Embodiments of the present invention will be described below with reference to the drawings.

第4図中1は主桁を示しており、主桁1のフランジ1′
上に既存のジベル2が残された状態で、鉄筋コンクリー
ト床版が解体除去されている。
1 in Figure 4 indicates the main girder, and the flange 1' of the main girder 1
The reinforced concrete slab was dismantled and removed, leaving the existing dowel 2 on top.

上記主桁1のフランジ1′上に鋼床版3を載置する。鋼
床版3は、前記主桁1の間隔位置において、フランジ1
′の幅方向両端部上に位置するようにした連結リブ4,
5を下面に取付けてなる上面板6、及び上面板6の下面
に所要の間隔で取付けた補強リブ7、更に前記連結リブ
4,5の内側面に取付けた側部ジベル8を備えた構成を
有しており、工場等において予め製作される。
A steel deck slab 3 is placed on the flange 1' of the main girder 1. The steel deck slab 3 is located between the flanges 1 at the spacing positions of the main girder 1.
connecting ribs 4 positioned on both ends in the width direction of ';
5 attached to the lower surface, reinforcing ribs 7 attached at required intervals to the lower surface of the upper plate 6, and side dowels 8 attached to the inner surfaces of the connecting ribs 4 and 5. It is manufactured in advance at a factory or the like.

上記鋼床版3を主桁1上に載置するに際し、主桁1のフ
ランジ1′上面と連結リブ4,5の下端との間に、第5
.6図に示すように例えばネオプレンゴム等の弾性材か
らなるノ\ツキング9を配して載置することにより、鋼
床版3の据付高の調整と止水効果を図る。また止水の補
完のため、要すればバッキング9部を外部力\らコーキ
ングづるJ:うにしても良い。
When placing the steel deck slab 3 on the main girder 1, a fifth
.. As shown in FIG. 6, the installation height of the steel deck 3 can be adjusted and the water-stopping effect can be achieved by arranging and placing a knot 9 made of an elastic material such as neoprene rubber. In order to supplement the waterproofing, if necessary, the backing section 9 may be applied with external force or caulking.

上記鋼床版3の載置によりフランジ1′と連結リブ4,
5と上面板6にて構成される矩形空fiill。
By placing the above-mentioned steel deck 3, the flange 1' and the connecting rib 4,
5 and a top plate 6.

内に、主桁1の端部側及び上面板6に形成した間口11
から早強コンクリート12を注入し、該コンクリ−1・
12の固化により、主桁1と調法1返3をジベル2,8
を介して一体化する。
Inside, a frontage 11 formed on the end side of the main girder 1 and on the top plate 6.
Pour early strength concrete 12 from the concrete 1.
By solidification of 12, the main girder 1 and adjustment method 1 return 3 are converted to dowels 2 and 8.
Unify through.

また、幅広の橋梁が必要な場合には、第7図に示すよう
に、鋼床版3.3相互の1妾合☆罎13を溶接或いはポ
ル]〜等で閉じ合わせ連結する。
In addition, if a wide bridge is required, as shown in FIG. 7, the steel deck plates 3, 3 and 13 are closed and connected by welding or bonding.

上記しt、sように、既存のジベル2をそのまま残して
鋼床版3の固定に利用するようにして(するので、解体
除去作業の容易化、既存1旧1勿の有効利用が図れ、且
つ鋼床版3は工場等に予め製作しておくことができ、し
かも主桁1のフラーi ”31’トへの固定をコンクリ
ート12にて(テうようにしているので、かなりの誤差
をコンクリートで吸収させることができ、更にコンクリ
−1〜の打設量も少ない等により、現地作業を少なくし
て張替え作業全体の工期を著しく短縮することができる
。また、アスファルトの敷設は、工場等において予め上
面板6上に施工しておいても、或は鋼床版3の載置終了
後に現地にてIIするようにしても良い。
As shown in t and s above, the existing dowel 2 is left as is and used for fixing the steel deck slab 3 (this makes the disassembly and removal work easier and makes effective use of the existing dowel 1 and old 1 dowel, In addition, the steel deck slab 3 can be manufactured in advance at a factory, etc., and since the main girder 1 is fixed to the flat plate 12 with concrete 12, a considerable amount of error can be avoided. Since the amount of asphalt can be absorbed by concrete and the amount of concrete to be placed is small, the on-site work can be reduced and the overall period of re-padding work can be significantly shortened.In addition, asphalt can be laid at factories, etc. It may be installed on the top plate 6 in advance, or it may be installed on site after the steel deck slab 3 is placed.

尚、本発明は上記実施例にのみ限定されるものではなく
、矩形空間内に注入するコンクリートとして超早強コン
クリ−1〜或は無収縮コンクリートを使用しても良いこ
と、鋼床版の構成は種々変更し得ること、その信奉発明
の要旨を逸脱しない範囲内において種々変更を加え得る
こと、等は勿論である。
It should be noted that the present invention is not limited to the above embodiments, and that ultra-early strength concrete 1 or non-shrinkage concrete may be used as the concrete poured into the rectangular space, and that the structure of the steel deck It goes without saying that various changes may be made to the invention, and that various changes may be made without departing from the gist of the claimed invention.

上述した本発明の橋梁鉄筋コンクリート床版の張替え工
法によれば、次のにうな優れた効果を奏し得る。
According to the above-mentioned bridge reinforced concrete deck resurfacing method of the present invention, the following excellent effects can be achieved.

(+) 主桁上の既存のジベルをそのまま残して鋼床版
の固定に利用するようにしているので、解体除去作業の
容易化、既存構造物の有効利用が図れる。
(+) Existing dowels on the main girder are left as is and used to secure the steel deck slab, making dismantling and removal work easier and making effective use of the existing structure.

(i) 既存の主桁と新規の鋼床版とをコンクリートを
介して一体的に結合するようにしているので、かなりの
誤差をコンクリートで吸収させることができ、よって高
度の連結精度を必要としない。
(i) Since the existing main girder and the new steel deck are integrally connected via concrete, a considerable amount of error can be absorbed by the concrete, which eliminates the need for a high degree of connection accuracy. do not.

(ロ) 注入するコンクリートのmが少ないので、注入
に要する時間は短く、しかも超早強コンクリート或は無
収縮コンクリートを使用してもコストを低くおさえるこ
とができる。
(b) Since the amount of concrete to be poured is small, the time required for pouring is short, and even if ultra-early strength concrete or non-shrinkage concrete is used, costs can be kept low.

(へ) 上記(+) (ii)(ト)により、現地作業
が容易、簡略化され、全工期の大幅な短縮が図れる。
(f) The above (+) (ii) (g) will make on-site work easier and simpler, and the overall construction period will be significantly shortened.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の張替え工法の一般的な例を説明するため
の概略図、第2図及び第3図は鋼床版により従来の張替
え工法の例を示す説明図、第4図は本発明の一実施例を
示す説明図、第5図は第4図の部分拡大図、第6図は第
5図の斜視図、第7図、は幅広の橋梁に適用した場合の
説明図である。 1は主桁、1′はフランジ、2はジベル、3は鋼床版、
4,5は連結リブ、8は側部ジベル、9はバッキング、
10は矩形空間、11は間口、12【よコンクリートを
示す。 特 許 出 願 人 石川島播磨重工業株式会社
Fig. 1 is a schematic diagram for explaining a general example of the conventional re-covering method, Figs. 2 and 3 are explanatory diagrams showing an example of the conventional re-covering method using steel deck slabs, and Fig. 4 is a diagram of the present invention. 5 is a partially enlarged view of FIG. 4, FIG. 6 is a perspective view of FIG. 5, and FIG. 7 is an explanatory view of the case where the present invention is applied to a wide bridge. 1 is the main girder, 1' is the flange, 2 is the dowel, 3 is the steel deck,
4 and 5 are connecting ribs, 8 is a side dowel, 9 is a backing,
10 indicates a rectangular space, 11 indicates a frontage, and 12 indicates concrete. Patent application Hitoshi Kawajima Harima Heavy Industries Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 1) 補修が必要となった橋梁の鉄筋コンクリ−1・床
版を主桁のフランジ上のジベルを残した状態で解体除去
し、続いて前記フランジ上に矩形空間を形成し得る連結
リブを有した鋼床−版を載置し、前記矩形空間内にコン
クリートを注入、固化させて前記1桁と鋼床版を一体化
することを特徴とづ“る橋梁鉄筋コンクリート床版の張
替え工法。
1) The reinforced concrete 1/deck slab of the bridge that required repair was dismantled and removed with the dowels on the flanges of the main girders remaining, and then a connecting rib that could form a rectangular space was installed on the flanges. A bridge reinforced concrete deck resurfacing method comprising: placing a steel deck slab, and then pouring concrete into the rectangular space and solidifying it to integrate the single girder and the steel deck slab.
JP16801583A 1983-09-12 1983-09-12 Replacing method of bridge reinforced concrete floor panel Granted JPS6059210A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16801583A JPS6059210A (en) 1983-09-12 1983-09-12 Replacing method of bridge reinforced concrete floor panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16801583A JPS6059210A (en) 1983-09-12 1983-09-12 Replacing method of bridge reinforced concrete floor panel

Publications (2)

Publication Number Publication Date
JPS6059210A true JPS6059210A (en) 1985-04-05
JPH0115647B2 JPH0115647B2 (en) 1989-03-20

Family

ID=15860220

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16801583A Granted JPS6059210A (en) 1983-09-12 1983-09-12 Replacing method of bridge reinforced concrete floor panel

Country Status (1)

Country Link
JP (1) JPS6059210A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017122356A (en) * 2016-01-08 2017-07-13 Jfeスチール株式会社 Replacement steel plate deck of concrete slab and replacement method of concrete slab
JP2017122353A (en) * 2016-01-08 2017-07-13 Jfeスチール株式会社 Replacement method of concrete slab and replacement structure
JP2018091062A (en) * 2016-12-05 2018-06-14 鹿島建設株式会社 Concrete floor slab removal method and concrete floor slab construction method
JP2021025228A (en) * 2019-07-31 2021-02-22 日本製鉄株式会社 Floor slab structure and floor slab replacement method
JP2021025229A (en) * 2019-07-31 2021-02-22 日本製鉄株式会社 Floor slab structure and floor slab replacement method
JP2023161604A (en) * 2022-04-26 2023-11-08 三井住友建設鉄構エンジニアリング株式会社 Floor slab replacement method
JP2023162651A (en) * 2022-04-27 2023-11-09 三井住友建設鉄構エンジニアリング株式会社 Floor slab replacement method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017122356A (en) * 2016-01-08 2017-07-13 Jfeスチール株式会社 Replacement steel plate deck of concrete slab and replacement method of concrete slab
JP2017122353A (en) * 2016-01-08 2017-07-13 Jfeスチール株式会社 Replacement method of concrete slab and replacement structure
JP2018091062A (en) * 2016-12-05 2018-06-14 鹿島建設株式会社 Concrete floor slab removal method and concrete floor slab construction method
JP2021025228A (en) * 2019-07-31 2021-02-22 日本製鉄株式会社 Floor slab structure and floor slab replacement method
JP2021025229A (en) * 2019-07-31 2021-02-22 日本製鉄株式会社 Floor slab structure and floor slab replacement method
JP2023161604A (en) * 2022-04-26 2023-11-08 三井住友建設鉄構エンジニアリング株式会社 Floor slab replacement method
JP2023162651A (en) * 2022-04-27 2023-11-09 三井住友建設鉄構エンジニアリング株式会社 Floor slab replacement method

Also Published As

Publication number Publication date
JPH0115647B2 (en) 1989-03-20

Similar Documents

Publication Publication Date Title
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
JP2872346B2 (en) Prefab slab installation method
JPS6059210A (en) Replacing method of bridge reinforced concrete floor panel
CN113152663A (en) Assembled building frame system
JPH0449210Y2 (en)
JPH022738Y2 (en)
CN214784697U (en) Assembled building frame system
JP3579167B2 (en) Deck for road surface and its laying method
KR100324704B1 (en) Formwork method using no prop for the floor concrete of the bridge
JP2861219B2 (en) Bridge deck repair steel slab and its mounting method
JP3065931B2 (en) Expansion joint support for steel road bridge and construction method of expansion joint for steel road bridge
JPS6245804A (en) Re-covering of bridge reinforced concrete
JPH108429A (en) Structure of concrete protection fence and construction method therefor
JPS6059209A (en) Replacing method of bridge reinforced concrete floor panel
KR100334257B1 (en) Formwork method using no prop for the floor concrete of the bridge
KR100339440B1 (en) Construction method using mold equipped with shape steel and plywood
JPS5980809A (en) Construction of prestressed concrete floor panel in road bridge
JPH0820915A (en) Precast floor slab
KR20040034970A (en) Prestressed reinforced concrete using prestressed concrete wire and T-shaped steel plate and method for constructing bridge using the same
KR100395590B1 (en) The Method of Lane Extension by Beam Support to Wayside and Structure Thereof
JPS6314906A (en) Construction method for re-covering bridge concrete floor panel
KR200240457Y1 (en) Frame for substitu ting steel girder of a railway bridge for concrete slab
KR200302134Y1 (en) Prestressed reinforced concrete using prestressed concrete wire and T-shaped steel plate
JPH035442B2 (en)
JPS597365Y2 (en) Edge structure of concrete slab at road joint