JPH035442B2 - - Google Patents

Info

Publication number
JPH035442B2
JPH035442B2 JP24336683A JP24336683A JPH035442B2 JP H035442 B2 JPH035442 B2 JP H035442B2 JP 24336683 A JP24336683 A JP 24336683A JP 24336683 A JP24336683 A JP 24336683A JP H035442 B2 JPH035442 B2 JP H035442B2
Authority
JP
Japan
Prior art keywords
girder
deck
steel wire
girders
replacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP24336683A
Other languages
Japanese (ja)
Other versions
JPS60138106A (en
Inventor
Saburo Tomizawa
Mitsuo Saito
Takeshi Takahashi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ishikawajima Kenzai Kogyo Co Ltd
Original Assignee
Ishikawajima Kenzai Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ishikawajima Kenzai Kogyo Co Ltd filed Critical Ishikawajima Kenzai Kogyo Co Ltd
Priority to JP24336683A priority Critical patent/JPS60138106A/en
Publication of JPS60138106A publication Critical patent/JPS60138106A/en
Publication of JPH035442B2 publication Critical patent/JPH035442B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 本発明は、道路橋等の路面を形成する合成桁床
版の打替工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for replacing composite girder slabs forming the road surface of road bridges and the like.

道路橋等の路面を形成するコンクリート製床版
には、合成桁床版および非合成桁床版がある。前
者の合成桁床版は、床版とこの床版を支える鋼製
の主桁とが一体で、走行する車輌等の荷重に抵抗
する構造となつたものであり、後者の非合成桁床
版は、主桁自体の強度のみでも前記の活荷重に耐
え得る構造のものである。
Concrete deck slabs that form the road surface of road bridges, etc. include composite girder deck slabs and non-synthetic girder deck slabs. The former composite girder deck consists of a deck and a steel main girder that supports the deck, and has a structure that resists the loads of moving vehicles, etc., while the latter non-synthetic girder deck The structure is such that the strength of the main girder itself can withstand the above-mentioned live load.

ところで、近年においては、このようなコンク
リート製床版の老朽化に伴ない床版の改修、すな
わち床版の打替工事が次第に多くなりつつある。
この打替工事を行なうにあたり、床版が前述の非
合成桁床版の場合は、その主桁自体が充分な強度
を備えているため片側通行などの方法で交通処理
しながら順次打替工事を行なうことも可能である
が、床版とこれを支える主桁とが一体構造となつ
て荷重に抵抗する合成桁床版の場合には、その合
成桁床版特有の構造から、床版打替時において主
桁の強度不足の問題が生じることが当然予想さ
れ、このため、交通開放下での床版打替工事を行
なうことは非常に困難なものとされている。した
がつて、従来においては、反覆施工するのに充分
な幅員がある現場以外は、その打替工事区間をま
たぐ、いわゆる応急橋の架設、あるいは迂回路の
確保およびこれに伴なう分岐路の仮設などの手段
で交通処理しながら床版の打替工事を行なつてい
た。
Incidentally, in recent years, as such concrete floor slabs become obsolete, renovation of the floor slabs, that is, work to replace the floor slabs, is gradually becoming more common.
When carrying out this replacement work, if the deck is the non-synthetic girder slab mentioned above, the main girder itself has sufficient strength, so the replacement work will be carried out one-way while managing traffic using methods such as one-way traffic. However, in the case of composite girder decks where the deck slab and the main girder supporting it are integrated to resist loads, it is not possible to replace the deck due to the unique structure of the composite girder deck. Naturally, it is expected that there will be problems with the strength of the main girder at times, and for this reason, it is extremely difficult to perform floor slab replacement work while the building is open to traffic. Therefore, in the past, unless the site had sufficient width for repeated construction, it was necessary to construct a so-called emergency bridge over the replacement work section, or to secure a detour and create a branch road accordingly. Work to replace the floor slabs was being carried out while dealing with traffic using temporary construction and other means.

しかしながら、このような従来の方法において
は、前記応急橋の架設にしても、打替工事区間を
またぐ相当大がかりな架設工事となつて多大な手
間と費用がかかり、また、打替工事区間によつて
は迂回路の確保すら困難な場合もしばしば生じる
などの問題点があり、いずれにしてもこれらの点
を解決できる対策が強く望まれていた。
However, in such conventional methods, even if the emergency bridge is constructed, it is a fairly large-scale construction work that straddles the replacement work section, which requires a great deal of effort and cost. However, there are problems such as it is often difficult to secure a detour, and in any case, there is a strong desire for measures that can solve these problems.

本発明は、以上のような点を考慮してなされた
もので、迂回路の確保や多大な手間と費用のかか
る応急橋の架設工事などの相当大がかりな交通処
理手段を根本的になくすことができる合成桁床版
の打替工法を提供しようとするものである。
The present invention has been made in consideration of the above points, and makes it possible to fundamentally eliminate fairly large-scale traffic management methods such as securing detours and constructing emergency bridges that require a great deal of effort and expense. The purpose of this project is to provide a method for replacing composite girder deck slabs.

以下、本発明を図面に示す一実施例に基づいて
詳述する。
Hereinafter, the present invention will be explained in detail based on an embodiment shown in the drawings.

まず、本発明による工法を実施する際の基本的
な考え方を第1図および第2図を参照して説明す
る。合成桁床版を打替える場合に問題となるのは
鋼桁の強度確保である。すなわち旧床版を除いた
あとの鋼桁は車両通行などの活荷重に対して強度
不足となる。そこで本発明では、片側半分ずつ打
替える工法を採用し、この際、第1図に示すよう
に橋軸方向に延在する両外桁1,2間の中桁3が
床版4と縁切となるためこの中桁3を非合成桁と
考え、その耐力不足を補う目的でワイヤー等の補
強用鋼線5を張り、かつ、鋼線支持および反力受
けを兼ねる支持装置6を中桁3に取り付けて、中
桁3に対し予め逆方向の荷重をかけ、これを合成
桁となつている外桁1と同程度の強度まで補強し
ておく点に特徴がある。
First, the basic concept when implementing the construction method according to the present invention will be explained with reference to FIGS. 1 and 2. When replacing composite girder decks, the problem is ensuring the strength of the steel girders. In other words, the steel girder after removing the old deck slab will not have enough strength to withstand live loads such as vehicle traffic. Therefore, in the present invention, a construction method is adopted in which half of each side is replaced, and in this case, as shown in FIG. Therefore, this middle girder 3 is considered to be a non-synthetic girder, and reinforcing steel wire 5 such as wire is stretched in order to compensate for the lack of strength, and a support device 6 that also serves as a steel wire support and a reaction force receiver is attached to the middle girder 3. The feature is that the inner girder 3 is attached to the inner girder 3 and a load is applied in the opposite direction in advance to reinforce it to the same level of strength as the outer girder 1, which is a composite girder.

次に、第3図〜第6図に示す具体例について述
べる。
Next, specific examples shown in FIGS. 3 to 6 will be described.

第3図a〜gは床版打替要領を示す工程図であ
り、まず同図aに示すように、打替えるべき旧床
版4と一体化している各鋼製桁(外桁1,2、中
桁3)の下側や側方に足場7を組立てた後、外桁
2と中桁3との間に、両桁2,3を連結する連結
桁8aおよびこの連結桁8aの上部において床版
を支持させる支持桁8b等の増設桁を取り付け
る。これらの増設桁は他の各桁と同様永久桁とし
て使用できるように取り付けておく。
Figures 3a to 3g are process diagrams showing the steps for replacing the deck slab. First, as shown in Figure a, each steel girder (outer girder 1, 2 After assembling the scaffolding 7 on the lower side and side of the inner girder 3), a connecting girder 8a connecting both girders 2 and 3 is installed between the outer girder 2 and the middle girder 3, and a connecting girder 8a on the upper part of this connecting girder 8a is installed. Install additional girders such as support girder 8b to support the floor slab. These additional girders will be installed so that they can be used as permanent girders like the other girders.

次に、中桁3の桁端近傍に、すなわち第4図
a,bに示すように中桁3の橋脚9の近傍にボル
ト挿通用の孔10をあけ、この孔10を利用して
後述する中桁の補強用鋼線5の端部を固定するた
めのアンカー金具11をボルト止めする。このア
ンカー金具11は中桁3の他方の桁端近傍にも同
様の要領でボルト止めしておく。この場合、両ア
ンカー金具11は互いに向き合う形態で取り付け
ることになる。このアンカー金具11の具体的構
造例は第5図a,bに示すように、中桁3の本体
部3aとこれに直交する下部フランジ3bとに沿
つて本体部3aを両側から挾み付ける如く形成さ
れた一対のL型板11a,11aと、下部フラン
ジ3bの下面に当てられる当板11bと、この当
板11bに溶接止めされ中央に鋼線挿通孔11c
を有する支圧板11dと、この支圧板11dおよ
び当板11bを互いに一体化して補強する補強リ
ブ11eとから構成され、図示のようにボルト1
2により中桁3に一体的に固定される。
Next, holes 10 for bolt insertion are drilled near the girder ends of the middle girder 3, that is, near the piers 9 of the middle girder 3 as shown in FIGS. 4a and 4b. Anchor fittings 11 for fixing the ends of reinforcing steel wires 5 of the middle girder are bolted. This anchor fitting 11 is also bolted to the vicinity of the other end of the middle girder 3 in the same manner. In this case, both anchor fittings 11 will be attached so as to face each other. As shown in FIGS. 5a and 5b, a specific example of the structure of this anchor fitting 11 is such that the main body 3a is sandwiched from both sides along the main body 3a of the middle girder 3 and the lower flange 3b perpendicular to the main body 3a. A pair of L-shaped plates 11a, 11a are formed, a contact plate 11b is applied to the lower surface of the lower flange 3b, and a steel wire insertion hole 11c is welded to the contact plate 11b in the center.
The bearing plate 11d and the reinforcement rib 11e are configured to integrate and reinforce the bearing plate 11d and the contact plate 11b.
2, it is integrally fixed to the middle girder 3.

上記のようにアンカー金具11を取り付けた
ら、次いで中桁3に支持装置6を取り付ける。こ
の支持装置6の取付位置およびその個数は、中桁
3の長さにもよるが、好ましくは第2図に示すよ
うに中桁3の長さlの4等分位置にそれぞれ1個
ずつ合計3個取り付ける程度が良い。第6図a,
bはこの支持装置6の具体的構成例を示すもの
で、中桁3の下部フランジ3bの下面に当接され
その下部フランジ3bの長手方向に延びる水平板
6aと、この水平板6aと直交する水平方向に配
されその下部フランジ3bの幅よりも十分に長尺
のチヤンネル材よりなる水平部材6bと、この水
平部材6bの両端上側に一端がそれぞれ取り付け
られ、他端が上部フランジ3cの下面に当板6
c′を介して当接すると共に本体部3aを挾み付け
る形態で配される一対の上側傾斜フレーム6c,
6cと、同じく水平部材6bの両端下側に一端が
それぞれ取り付けられ、他端が本体部3aの断面
に沿う垂直方向線分上で交差する如く1つに集束
された一対の下側傾斜フレーム6d,6dと、こ
の傾斜フレーム6dと90゜異なる位置において一
端が前記水平板6aの両端下面にそれぞれ取り付
けられ、他端が前記傾斜フレーム6dの集束位置
に溶接止めされた一対の補強傾斜フレーム6e,
6eと、この補強傾斜フレーム6e,6eおよび
下側傾斜フレーム6d,6dで形成された逆角錐
形の中心軸線方向となる鉛直方向に摺動可能に設
けられかつ先端に鋼線5に係合する係合溝6fを
有する可動支柱6gと、この可動支柱6gの基端
と水平板6aとの間に配される油圧ジヤツキ6h
と、前記下部フランジ6b上に設けられ支持装置
6の下部フランジ6bに対する位置決め材6i,
6jとを有する構成となつている。なお、可動支
柱6gには調整ナツト6kが螺合され、また、上
側傾斜フレーム6c,6cのうち一方の傾斜フレ
ーム6cは、支持装置6の中桁3に対する取り付
け取り外しを容易にするためボルト・ナツト6n
により着脱自在に取り付けられる。
After the anchor fittings 11 are attached as described above, the support device 6 is then attached to the middle girder 3. The mounting position and the number of support devices 6 depend on the length of the middle girder 3, but preferably one in each of the four equal parts of the length l of the middle girder 3, as shown in FIG. It is best to install 3 of them. Figure 6a,
b shows a specific configuration example of this support device 6, which includes a horizontal plate 6a that comes into contact with the lower surface of the lower flange 3b of the middle girder 3 and extends in the longitudinal direction of the lower flange 3b; A horizontal member 6b made of a channel material arranged in the horizontal direction and sufficiently longer than the width of the lower flange 3b; one end is attached to the upper side of both ends of this horizontal member 6b, and the other end is attached to the lower surface of the upper flange 3c. Toban 6
a pair of upper inclined frames 6c disposed in such a manner as to abut each other via c′ and sandwich the main body portion 3a;
6c, and a pair of lower inclined frames 6d, one end of which is attached to the lower side of both ends of the horizontal member 6b, and the other end of which is converged so as to intersect on a vertical line segment along the cross section of the main body portion 3a. , 6d, and a pair of reinforcing inclined frames 6e, one end of which is attached to the lower surface of both ends of the horizontal plate 6a at a position 90° different from the inclined frame 6d, and the other end is welded to the convergence position of the inclined frame 6d.
6e, the reinforcing inclined frames 6e, 6e, and the lower inclined frames 6d, 6d are provided so as to be slidable in the vertical direction, which is the central axis direction of the inverted pyramid, and engage the steel wire 5 at the tip. A movable strut 6g having an engagement groove 6f, and a hydraulic jack 6h disposed between the base end of the movable strut 6g and the horizontal plate 6a.
and a positioning member 6i provided on the lower flange 6b of the support device 6 with respect to the lower flange 6b,
6j. An adjustment nut 6k is screwed onto the movable column 6g, and one of the upper inclined frames 6c, 6c is fitted with bolts and nuts to facilitate attachment and removal of the support device 6 to the middle girder 3. 6n
It can be detachably attached.

このような構成の支持装置6を中桁3の所定箇
所に取り付けたら、鋼線5の一端を一方の桁端の
アンカー金具11に固定し、次いで鋼線5の他端
を他方の桁端のアンカー金具11の鋼線挿通孔1
1cに通してこれを引き込みながらその鋼線5を
可動支柱6g先端の係合溝6fに係合させ、さら
にこの鋼線5をたるみのない程度にまで引き込ん
だ上でその他端をアンカー金具11に固定してお
く。
Once the support device 6 with such a configuration is attached to a predetermined location on the middle girder 3, one end of the steel wire 5 is fixed to the anchor fitting 11 at one end of the girder, and then the other end of the steel wire 5 is fixed to the anchor fitting 11 at the end of the other girder. Steel wire insertion hole 1 of anchor fitting 11
1c, the steel wire 5 is engaged with the engagement groove 6f at the tip of the movable strut 6g, and the steel wire 5 is further pulled in to the extent that there is no slack, and the other end is connected to the anchor fitting 11. Keep it fixed.

そして、このようにして鋼線5の張設作業を終
えたら、次いで油圧ジヤツキ6hをセツトし、そ
のロツドを伸長させて可動支柱6gを押し下げて
鋼線5を緊張し、さらにこの状態でナツト6kを
回転させて可動支柱6gを固定し、これによつて
中桁3に予め逆方向の荷重をかけ、その中桁3を
実質的に補強しておく。ここで、鋼線5の張力管
埋は油圧力にて行なう。例えば、油圧ジヤツキ6
hと可動支柱6gとの間にロードセルなどを介在
させておけば良い。
After completing the work of tensioning the steel wire 5 in this way, the hydraulic jack 6h is then set, the rod is extended and the movable column 6g is pushed down to tension the steel wire 5, and in this state the nut 6k is tightened. is rotated to fix the movable support column 6g, thereby applying a load in the opposite direction to the middle girder 3 in advance, thereby substantially reinforcing the middle girder 3. Here, the tension pipe embedding of the steel wire 5 is performed using hydraulic pressure. For example, hydraulic jack 6
A load cell or the like may be interposed between h and the movable support 6g.

上記のようにして、中桁3の補強作業を終えた
ら、次に第3図bに示すように防護柵13をセツ
トし片側交通規制を行なつた上で、同図中鎖線で
示すように片側幅員床版を斫り出し、次いで必要
に応じてジベルの手直しや補強等を行ない、さら
に中桁3および外桁2の上部フランジに補強材1
4をそれぞれ設けてその上部フランジを補強す
る。
After completing the reinforcing work on the middle girder 3 as described above, next, as shown in Figure 3b, the protective fence 13 is set up to restrict traffic on one side, and then as shown by the chain line in the figure, One side of the width deck is scooped out, then the dowels are modified and reinforced as necessary, and reinforcing material 1 is installed on the upper flanges of the middle girder 3 and outer girder 2.
4 to reinforce its upper flange.

次に、第3図cに示すように予め工場等で生産
しておいた合成床版用のプレキヤスト床版15を
架設し、さらに現場鉄筋16をセツトすると共に
早強コンクリートを使用して目地コンクリート1
7を打設し、プレキヤスト床版15と外桁2とを
一体化させる。そしてさらに、同図dに示す如く
地覆部コンクリートを打設した後、アスフアルト
舗装18を施す。
Next, as shown in Fig. 3c, a precast deck slab 15 for a composite deck slab that has been produced in advance at a factory, etc. is erected, and on-site reinforcing bars 16 are set, and joint concrete is concreted using early-strengthening concrete. 1
7 is poured, and the precast deck slab 15 and the outer girder 2 are integrated. Further, as shown in Figure d, after concrete is placed for the ground cover, asphalt pavement 18 is applied.

こうして旧床版4の片側幅員床版を予め決めて
おいた長さだけ打替えたら、次は残りの片側幅員
床版を前述と同様の要領で打替える。すなわち、
同図dに示すように打替えた新床版側に防護柵1
3′をセツトした上で交通切り替え規制を行なつ
ておき、次いで同図eにおいて鎖線で示す如く残
りの片側幅員床版を斫り出した後、必要に応じて
ジベルの手直しや補強を行ない、さらに中桁3お
よび外桁1の上部フランジに補強材14′をそれ
ぞれ設けてその上部フランジを補強する。
After the one-side width floor slab of the old floor slab 4 is replaced by a predetermined length in this way, the remaining one-side width floor slab is replaced in the same manner as described above. That is,
As shown in Figure d, there is a protective fence 1 on the side of the new deck slab that has been replaced.
3', traffic switching regulations are carried out, and then the remaining one-side width floor slab is cleared out as shown by the chain line in Figure e, and the dowels are modified and reinforced as necessary. Further, reinforcing members 14' are provided on the upper flanges of the inner girder 3 and the outer girder 1, respectively, to reinforce the upper flanges.

次に同図fに示す如くプレキヤスト床版15′
を架設し、さらに現場鉄筋16′をセツトすると
共に目地コンクリート17′を打設し、プレキヤ
スト床版15′と外桁1とを一体化させる。そし
てさらに、同図gに示す如く中桁3上の目地コン
クリート19を超速硬性コンクリートを打設して
形成し、両プレキヤスト床版15,15′および
中桁3を互いに一体化させた後、中桁3の補強
材、すなわち鋼線5や支持装置6等を撤去し、次
いで、地覆部コンクリート打設後、アスフアルト
舗装18′を施して桁端間の打替作業工程を完了
とする。そして、以上のような作業工程を順次繰
り返し実施することにより、打替予定区間の全域
を打替える。
Next, as shown in Figure f, the precast floor slab 15'
Further, on-site reinforcing bars 16' are set, joint concrete 17' is poured, and the precast slab 15' and the outer girder 1 are integrated. Furthermore, as shown in Figure g, joint concrete 19 on the middle girder 3 is formed by pouring ultra-fast hardening concrete, and after both precast slabs 15, 15' and the middle girder 3 are integrated with each other, Reinforcing materials for the girder 3, ie, steel wires 5, support devices 6, etc., are removed, and after concrete is placed on the ground cover, asphalt pavement 18' is applied to complete the replacement work process between the ends of the girder. Then, by sequentially repeating the above-mentioned work steps, the entire area of the scheduled replacement section is replaced.

なお、実施例では中桁3を補強するための鋼線
5の支持装置6として、油圧ジヤツキにより駆動
される可動支柱を備えたものを示したが、要する
に鋼線5を下方へ押し下げて緊張させることがで
きる機能をもつ構成であればよく、実施例に限定
されるものではない。
In the embodiment, the support device 6 for the steel wire 5 for reinforcing the middle girder 3 is shown as having a movable column driven by a hydraulic jack, but in short, the steel wire 5 is pushed down and tensioned. Any configuration can be used as long as it has a function that allows the configuration to be performed, and is not limited to the embodiments.

以上詳述したように、本発明による合成桁床版
の打替工法にあつては、旧床版撤去後に縁切りと
なる中桁を鋼線や支持装置等により予め補強した
上で片側ずつ打替える工法としたので、従来工法
のように迂回路の確保や多大な手間と費用のかか
る応急橋の架設工事など相当大ががりな交通処理
手段を根本的になくすことができ、また、中桁の
実質的な補強手段も支持装置や鋼線など比較的簡
単でしかも繰り返し使用可能なものであるから、
作業性に優れかつ工費節減に寄与するなど、種々
の効果を奏する。
As detailed above, in the method of replacing composite girder decks according to the present invention, the middle girders that serve as edge cuts after the removal of the old deck are reinforced in advance with steel wires, support devices, etc., and then replaced one side at a time. This construction method fundamentally eliminates the need for fairly large-scale traffic management methods, such as securing detours and constructing emergency bridges that require a great deal of effort and expense, as required with conventional construction methods. The actual reinforcing means are relatively simple and reusable, such as support devices and steel wires, so
It has a variety of effects, including excellent workability and contributing to reduced construction costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第6図は本発明の一実施例を示すもの
で第1図および第2図は本発明による工法の基本
的な考え方を示すモデル図、第3図a〜gは床版
の打替要領を示す工程図、第4図aおよびbはそ
れぞれアンカー金具の取付位置を示す概略側面
図、第5図aおよびbはアンカー金具の構成を示
す正面図および側面図、第6図aおよびbは支持
装置の正面図および側面図である。 1,2……外桁、3……中桁、4……旧床版、
5……補強用鋼線、6……支持装置、11……ア
ンカー金具、15,15′……プレキヤスト床版、
17,17′……目地コンクリート、18,1
8′……アスフアルト舗装、19……目地コンク
リート。
Figures 1 to 6 show one embodiment of the present invention. Figures 1 and 2 are model diagrams showing the basic concept of the construction method according to the present invention, and Figures 3 a to g are floor slabs. Figures 4a and 4b are schematic side views showing the mounting position of the anchor fittings, Figures 5a and b are front and side views showing the structure of the anchor fittings, and Figure 6a is a process diagram showing the replacement procedure. and b are front and side views of the support device. 1, 2...External girder, 3...Medium girder, 4...Old floor slab,
5... Steel wire for reinforcement, 6... Support device, 11... Anchor fittings, 15, 15'... Precast floor slab,
17,17'...Joint concrete, 18,1
8'...Asphalt pavement, 19...Joint concrete.

Claims (1)

【特許請求の範囲】 1 橋軸方向に延在する外桁間に同じく橋軸方向
に延在する中桁を有し、かつ、これら各桁とその
上のコンクリート製床版とが一体で活荷重に抵抗
する構造である合成桁床版の打替工法であつて、 (イ) 前記中桁の下方に、該中桁の長手方向に沿つ
て延びる補強用鋼線を配するとともにその鋼線
の両端を中桁の桁端近傍にそれぞれ固定する工
程と、 (ロ) 前記鋼線の両固定点間における中桁に、該中
桁よりも下方に突出しかつ自身の軸方向に摺動
可能な可動支柱を備える支持装置を取り付ける
工程と、 (ハ) 前記支持装置の可動支柱に前記鋼線の両固定
点間の少なくとも1ケ所を係合させた状態で可
動支柱を押し下げて鋼線を緊張させる工程と、 (ニ) 前記各桁の桁端間における片側幅員床版を打
替えた後、残りの片側幅員床版を打替える工程
とを有する道路橋等における合成桁床版の打替
工法。
[Scope of Claims] 1. An intermediate girder that also extends in the bridge axis direction is provided between the outer girders that extend in the bridge axis direction, and each of these girders and the concrete deck slab thereon are integrally activated. A method for replacing a composite girder deck, which has a structure that resists loads, which includes: (a) arranging reinforcing steel wires extending along the longitudinal direction of the middle girders below the middle girders; (b) A step of fixing both ends of the steel wire near the girder ends of the middle girder; a step of attaching a support device having a movable strut; (c) tensing the steel wire by pushing down the movable strut while engaging the movable strut of the support device at at least one location between both fixing points of the steel wire; (d) A method for replacing composite girder decks in road bridges, etc., comprising the steps of: (d) replacing the one-side width deck between the girder ends of each girder, and then replacing the remaining one-side width deck.
JP24336683A 1983-12-23 1983-12-23 Casting replacement construction method of synthetic beam floor panel in road bridge Granted JPS60138106A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24336683A JPS60138106A (en) 1983-12-23 1983-12-23 Casting replacement construction method of synthetic beam floor panel in road bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24336683A JPS60138106A (en) 1983-12-23 1983-12-23 Casting replacement construction method of synthetic beam floor panel in road bridge

Publications (2)

Publication Number Publication Date
JPS60138106A JPS60138106A (en) 1985-07-22
JPH035442B2 true JPH035442B2 (en) 1991-01-25

Family

ID=17102766

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24336683A Granted JPS60138106A (en) 1983-12-23 1983-12-23 Casting replacement construction method of synthetic beam floor panel in road bridge

Country Status (1)

Country Link
JP (1) JPS60138106A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2510516B2 (en) * 1986-05-21 1996-06-26 キヤノン株式会社 Image processing device
JP6180376B2 (en) * 2014-06-23 2017-08-16 首都高速道路株式会社 Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method
JP6755172B2 (en) * 2016-12-26 2020-09-16 首都高速道路株式会社 Floor slab renewal method

Also Published As

Publication number Publication date
JPS60138106A (en) 1985-07-22

Similar Documents

Publication Publication Date Title
US7461427B2 (en) Bridge construction system and method
US8522381B1 (en) System and method for bridge pier replacement
US6588160B1 (en) Composite structural member with pre-compression assembly
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
JP3844743B2 (en) Box girder bridge structure and its construction method
JP2872346B2 (en) Prefab slab installation method
JP2004137686A (en) Composite panel structure, panel bridge structure and construction method for continuous composite girder bridge
KR101309004B1 (en) Rahmen bridge and constructing method thereof
JP2967876B1 (en) Method of forming concrete slab and method of constructing upper road suspension bridge
JP3737475B2 (en) Box girder bridge structure and construction method
JP2734987B2 (en) Existing bridge repair method
JPH0449210Y2 (en)
KR100842062B1 (en) The steel composite rahmen bridge construction technique for which preflexion steel girder was used
JPH0782709A (en) Reinforcing method for concrete structure, employing hollow pc steel bar
KR100889140B1 (en) The assembly type hollow slab
JPH04289303A (en) Method for widening road bridge
JPH035442B2 (en)
JP3579167B2 (en) Deck for road surface and its laying method
JP2006112086A (en) Structure of bridge and method for rebuilding bridge
JP3450054B2 (en) Installation method of floor slab on bridge girder and slab cradle
JP2000064222A (en) Elevated bridge
JP2003193424A (en) Composite truss bridge and its construction method
KR101309005B1 (en) Rahmen bridge and constructing method thereof
JPS6059210A (en) Replacing method of bridge reinforced concrete floor panel
JP4627383B2 (en) Replaced steel deck bridge

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term