JP2967876B1 - Method of forming concrete slab and method of constructing upper road suspension bridge - Google Patents

Method of forming concrete slab and method of constructing upper road suspension bridge

Info

Publication number
JP2967876B1
JP2967876B1 JP10230327A JP23032798A JP2967876B1 JP 2967876 B1 JP2967876 B1 JP 2967876B1 JP 10230327 A JP10230327 A JP 10230327A JP 23032798 A JP23032798 A JP 23032798A JP 2967876 B1 JP2967876 B1 JP 2967876B1
Authority
JP
Japan
Prior art keywords
plate
concrete
support structure
forming
floor slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP10230327A
Other languages
Japanese (ja)
Other versions
JP2000054319A (en
Inventor
謙一 齋藤
英雄 新井
博志 益子
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Construction Co Ltd
Original Assignee
Sumitomo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Construction Co Ltd filed Critical Sumitomo Construction Co Ltd
Priority to JP10230327A priority Critical patent/JP2967876B1/en
Application granted granted Critical
Publication of JP2967876B1 publication Critical patent/JP2967876B1/en
Publication of JP2000054319A publication Critical patent/JP2000054319A/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

【要約】 【課題】 大型の架設機械を用いることなく短い工期で
橋梁構造物のコンクリート床版を形成する方法を提供す
る。また、この方法を用いた上路式吊構造橋の構築方法
を提供する。 【解決手段】 プレキャストコンクリートの板状部材1
2を形成し、この板状部材の下面に車輪9を取り付け
て、既に架設された鋼桁5の上フランジ5b上を走行さ
せる。所定位置まで移動後、位置調整ボルト16を回転
して自重をこの位置調整ボルトで負担し、車輪9を除去
する。そして、板状部材を所定の高さに据え付ける。上
記のようにして複数のコンクリート部材を桁上に配列し
た後、これらの間にコンクリートを打設して一体化す
る。この方法は、上路式の吊構造橋の構築に適用するこ
とができ、固定構造物間に張架された吊材上に仮設レー
ルを設け、コンクリートの板状部材を走行移動させ、こ
れらを連結して上路桁とすることができる。
An object of the present invention is to provide a method for forming a concrete floor slab of a bridge structure in a short construction period without using a large-sized erection machine. The present invention also provides a method for constructing a suspension bridge of an upper road type using this method. SOLUTION: Plate member 1 of precast concrete
2 is formed, and wheels 9 are attached to the lower surface of the plate-like member, and run on the upper flange 5b of the steel girder 5 already installed. After moving to the predetermined position, the position adjusting bolt 16 is rotated to bear its own weight with the position adjusting bolt, and the wheel 9 is removed. Then, the plate member is installed at a predetermined height. After arranging a plurality of concrete members on the girder as described above, concrete is cast between them to be integrated. This method can be applied to the construction of a suspension bridge of an upper road type, a temporary rail is provided on a suspension member stretched between fixed structures, a concrete plate-like member is moved and moved, and these are connected. To be the upper girder.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本願発明は、プレキャストコ
ンクリートの板状部材を所定位置に複数を配列し、これ
らを連結して橋梁構造物の床版を形成する方法に関する
もの、およびこの方法を用い、複数の固定構造物間に張
架した吊材とこの上に支柱で支持された上路桁とを有す
る上路式吊構造橋を構築する方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of arranging a plurality of plate members of precast concrete at predetermined positions and connecting them to form a floor slab of a bridge structure, and using this method, The present invention relates to a method of constructing an upper suspension bridge having a suspension member stretched between a plurality of fixed structures and an upper girder supported by columns on the suspension member.

【0002】[0002]

【従来の技術】一般に橋梁構造物では、路面となる部分
にコンクリート床版を有するものが多い。このコンクリ
ート床版を構築する方法には、桁部分と同時に現場でコ
ンクリートを打設して構築する方法、架設された桁上に
コンクリートを打設して構築する方法、又はプレキャス
トコンクリートの板状部材を配列して構築する方法等が
ある。これらのうち、プレキャストコンクリートの板状
部材を用いる方法は、橋梁の架設現場で多くの型枠を組
み立てる必要がなく、現場における作業の減少および現
場における工期の短縮等の利点を有している。
2. Description of the Related Art In general, many bridge structures have a concrete floor slab in a portion to be a road surface. The method of constructing this concrete floor slab includes a method of casting concrete on site at the same time as a girder part, a method of casting concrete on an erected girder, and a method of constructing a precast concrete plate member. And constructing them. Among them, the method using a plate member made of precast concrete does not require assembling a lot of formwork at a construction site of a bridge, and has advantages such as reduction of work on site and shortening of construction period at site.

【0003】上記プレキャストコンクリートの板状部材
を用いて床版を形成する方法は、一般に次のような工程
によって実施される。橋台または橋脚等の下部構造物間
に荷重を支持する桁・トラス等が架設されると、あらか
じめ工場または製作ヤードで形成された複数のコンクリ
ート板が、上記桁またはトラス等の主構造物上に配列さ
れる。そして、これらを互いに連結するとともに主構造
物に強固に固定する。これらのコンクリート板を連結す
るために、橋の軸線方向にプレストレスが導入されるこ
とも多い。
[0003] A method of forming a floor slab using the above precast concrete plate-like member is generally carried out by the following steps. When a girder or truss supporting a load is erected between substructures such as an abutment or a pier, a plurality of concrete plates previously formed in a factory or a manufacturing yard are placed on the main structure such as the girder or truss. Are arranged. These are connected to each other and firmly fixed to the main structure. Prestressing is often introduced in the axial direction of the bridge to connect these concrete plates.

【0004】上記のようにプレキャストコンクリート板
を主構造物上に配列する作業は、クレーン等によってコ
ンクリート板を吊り上げ、主構造物上の所定位置に載置
することによって行われる。
[0004] As described above, the work of arranging the precast concrete plates on the main structure is performed by lifting the concrete plates with a crane or the like and placing them at predetermined positions on the main structure.

【0005】一方、上路式の吊構造橋、例えば上路式吊
床版橋は、橋台又は橋脚等の固定構造物間に連続した薄
いコンクリート部材である吊床版を張架し、この上に支
柱を立設して上路桁を支持するものであり、上路桁はコ
ンクリートの床版とされることが多い。このような上路
桁を構築する場合にも、プレキャストコンクリート部材
を用いることによって現場における高所作業の低減、工
期の短縮等、有利な点が多い。
[0005] On the other hand, an upper road type suspension structure bridge, for example, an upper road type suspension deck bridge, stretches a suspension deck, which is a thin concrete member continuous between fixed structures such as an abutment or a pier, and stands a support on the suspension deck. The upper girder is often used as a concrete floor slab. Also in the case of constructing such an upper girder, there are many advantages such as a reduction in work at a high place on site and a shortened construction period by using a precast concrete member.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、上記の
ようにプレキャストコンクリート部材を用いて床版を形
成する方法には、次のような問題点がある。プレキャス
トコンクリートの板状部材を橋梁の全長にわたって所定
位置に配列するためにクレーンが用いられるが、効率よ
く作業を行うためには、アームが長く作業範囲の大きな
クレーンが必要となる。また、このクレーンは架設しよ
うとする橋梁の軸線に沿って地盤上すなわち河床等を走
行して作業を行うのが望ましいが、深い渓谷に架設する
場合等には、上記のような走行式のクレーンでプレキャ
ストコンクリート部材を配列することは困難となる。一
方、上路式の吊床版橋を架設する場合にも、上路桁をプ
レキャストコンクリート部材を用いて構築しようとする
際に同様の問題点が生じる。
However, the method of forming a floor slab using a precast concrete member as described above has the following problems. A crane is used to arrange the precast concrete plate members at predetermined positions over the entire length of the bridge, but a crane with a long arm and a large working range is required in order to work efficiently. It is desirable that this crane works on the ground, that is, on the riverbed, etc., along the axis of the bridge to be erected, but it is desirable to carry out the work in deep valleys, etc. Therefore, it is difficult to arrange the precast concrete members. On the other hand, in the case of constructing an overhead-type suspended floor slab bridge, a similar problem occurs when an upper-road girder is to be constructed using a precast concrete member.

【0007】本願発明は、上記のような問題点に鑑みて
なされたものであり、その目的は、大型の架設機械を用
いることなく、短い工期でコンクリート床版を形成する
方法、又は上路式吊構造橋を構築する方法を提供するこ
とである。
The present invention has been made in view of the above-described problems, and has as its object to provide a method of forming a concrete floor slab in a short construction period without using a large erection machine, or an overhead road suspension. The purpose is to provide a way to build a structural bridge.

【0008】[0008]

【課題を解決するための手段】上記のような問題点を解
決するために、請求項1に記載の発明は、 複数のプレ
キャストコンクリートの板状部材を形成し、 この板状
部材の下面に車輪を取り付け、既に構築された支持構造
体上を所定位置まで前記車輪によって走行させ、 該板
状部材にほぼ垂直に螺合された位置調整ボルトを回転さ
せて突出した下端を前記支持構造体に当接させ、該板状
部材の重量を該位置調整ボルトで支持し、 前記車輪を
取り外した後、前記位置調整ボルトを回転させて該板状
部材の上下方向の位置を設定し、 前記板状部材に車輪
を取り付ける工程から、前記支持構造体上で、該板状部
材を所定位置に設定するまでの工程を、複数の板状部材
に付いて行ない、 これらの板状部材を前記支持構造体
に固定する、コンクリート床版の形成方法を提供するも
のである。
In order to solve the above-mentioned problems, a first aspect of the present invention is to form a plurality of plate members made of precast concrete, and to form a wheel on a lower surface of the plate members. Then, the wheel is run on the already constructed support structure to a predetermined position by the wheels, and a lower end protruding by rotating a position adjusting bolt screwed substantially perpendicularly to the plate-like member is applied to the support structure. Contacting, supporting the weight of the plate-shaped member with the position adjustment bolt, removing the wheel, rotating the position adjustment bolt to set the vertical position of the plate-shaped member, From the step of attaching the wheels to the step of setting the plate-like member at a predetermined position on the support structure, a step of attaching the plate-like member to a plurality of plate-like members is performed. Fixing, concrete There is provided a method for forming the plate.

【0009】上記方法において、支持構造体は車輪が取
り付けられたプレキャストコンクリートの板状部材を支
持し、上記車輪による走行が可能なものであれば、形状
・構造等が限定されるものではなく、既に架設された鋼
桁、コンクリート桁、鋼もしくはコンクリート又はこれ
らの複合構造によるトラス等を含む。また、完成した橋
梁構造物に含まれるものではなく、上記プレキャストコ
ンクリートの板状部材を走行移動させるために構築され
た仮設桁、仮設レール等であってもよい。
In the above method, the supporting structure supports a precast concrete plate-like member to which wheels are attached, and the shape and structure are not limited as long as the supporting structure can run on the wheels. Includes steel girders, concrete girders, trusses made of steel or concrete, or a composite structure of these, which have already been installed. Further, the bridge member is not included in the completed bridge structure, and may be a temporary girder, a temporary rail, or the like constructed to travel and move the plate member made of precast concrete.

【0010】また、上記位置調整ボルトは、下端が上記
プレキャストコンクリートの板状部材の下面より突出
し、回転によって突出量を変化させることができるもの
であれば形態等は限定されるものではないが、板状部材
の上側から回転させることができるものが望ましい。ま
た、プレキャストコンクリートの板状部材に対しては、
コンクリートに固着されたナット状の金具を介して螺合
されるものがよい。
The form of the position adjusting bolt is not limited as long as its lower end protrudes from the lower surface of the plate member made of precast concrete and the amount of protrusion can be changed by rotation. What can rotate from the upper side of a plate-shaped member is desirable. For precast concrete plate members,
It is preferable to be screwed via a nut-like metal fitting fixed to concrete.

【0011】上記のような構成のコンクリート床版の形
成方法では、あらかじめ工場又は製作ヤード等において
製作されたプレキャストコンクリートの板状部材を、条
件の良好な任意の位置で支持構造体上に載置すれば、あ
とは車輪によって走行させ、所定の位置に容易に設置す
ることができる。つまり、既に構築された桁等の支持構
造体上にプレキャストコンクリートの板状部材を橋台付
近で載置する場合には大型のクレーンは不要であり、小
規模な吊り上げ装置があれば、プレキャストコンクリー
トの板状部材を橋梁の全長にわたり所定の位置に配置す
ることができる。
In the method of forming a concrete floor slab having the above-described structure, a precast concrete plate-like member manufactured in advance in a factory or a manufacturing yard is placed on a support structure at an arbitrary position with favorable conditions. Then, the vehicle can be driven by wheels and can be easily installed at a predetermined position. In other words, a large crane is not required when a precast concrete plate-like member is placed near an abutment on a support structure such as a girder that has already been constructed.If a small lifting device is used, a precast concrete The plate-like member can be arranged at a predetermined position over the entire length of the bridge.

【0012】また、プレキャストコンクリートの板状部
材が所定位置まで移動されると、位置調整ボルトで該板
状部材を支持して車輪を取り外すことができ、さらにそ
のまま位置調整ボルトを回転させることによって該板状
部材を所定の高さに調整することができる。したがっ
て、ジャッキ等を用いることなく、簡易かつ迅速にコン
クリートの板状部材を設置することができる。
When the plate member made of precast concrete is moved to a predetermined position, the wheel can be removed by supporting the plate member with the position adjusting bolt, and the position adjusting bolt can be further rotated by directly rotating the position adjusting bolt. The plate member can be adjusted to a predetermined height. Therefore, the concrete plate-like member can be easily and quickly installed without using a jack or the like.

【0013】請求項2に記載の発明は、 請求項1に記
載のコンクリート床版の形成方法において、 前記板状
部材を支持構造体に固定する工程は、 前記複数の板状
部材を前記支持構造体上に配列した後、隣り合う板状部
材の対向する端面の双方及び前記支持構造体の上面に密
着するようにコンクリートを打設し、双方の板状部材を
一体化するとともに該支持構造体に固定するものとす
る。
According to a second aspect of the present invention, in the method of forming a concrete floor slab according to the first aspect, the step of fixing the plate-like member to a support structure comprises: attaching the plurality of plate-like members to the support structure. After being arranged on the body, concrete is cast so as to be in close contact with both opposing end surfaces of the adjacent plate members and the upper surface of the support structure, and both plate members are integrated and the support structure is formed. Shall be fixed to

【0014】このような方法では、配列された複数の板
状部材の間に打設されたコンクリートによって、これら
の板状部材が容易に一体化されるとともに、これらの板
状部材を支持する支持構造体にも固定化される。特に、
各々の板状部材および支持構造体からコンクリートを打
設する部分に、鉄筋・スタッドジベル・アンカー等が突
出するように配置されていると、これらの部材によって
強固に一体化される。
According to such a method, the plate members are easily integrated by the concrete cast between the arranged plate members, and the support for supporting these plate members is provided. It is also immobilized on the structure. Especially,
If a reinforcing bar, a stud dowel, an anchor, or the like is arranged so as to protrude from a portion where concrete is cast from each of the plate members and the support structure, the members are firmly integrated by these members.

【0015】請求項3に記載の発明は、 請求項2に記
載のコンクリート床版の形成方法において、 前記板状
部材の下面の、前記コンクリートと密着する端面付近
に、柔軟に変形する間詰部材を接着しておき、 前記板
状部材を所定位置に設定するときに、該板状部材の下面
と前記支持構造体の上面との間に前記間詰部材を挟み込
んで変形させ、 前記コンクリートの打設時に、前記間
詰部材によってコンクリートの漏出を防止するものとす
る。
According to a third aspect of the present invention, in the method of forming a concrete floor slab according to the second aspect, a filling member that is flexibly deformed on a lower surface of the plate-like member near an end surface that is in close contact with the concrete. When the plate-like member is set at a predetermined position, the filling member is sandwiched between the lower surface of the plate-like member and the upper surface of the support structure to be deformed. At the time of installation, the leakage of concrete is prevented by the filling member.

【0016】このような構成とすることにより、支持構
造体とプレキャストコンクリートの板状部材下面との間
に小さな空隙がある場合にも、板状部材を連結一体化す
るためのコンクリートを打設した時に、この空隙にコン
クリート又はセメントペースト等が流出するのが防止さ
れる。したがって、充填材や型枠によってコンクリート
打設部分を限定する作業を簡略化することができ、作業
効率が向上する。
[0016] With this configuration, even if there is a small gap between the support structure and the lower surface of the precast concrete plate member, concrete for connecting and integrating the plate members is cast. Occasionally, concrete or cement paste is prevented from flowing into these voids. Therefore, the work of limiting the concrete placing portion by the filler or the formwork can be simplified, and the working efficiency is improved.

【0017】請求項4に記載の発明は、 請求項1に記
載のコンクリート床版の形成方法において、 前記支持
構造体は、既に架設された鋼桁であり、 前記車輪は、
該鋼桁の上フランジ上を走行するものであり、 該車輪
の車輪フランジ又は前記板状部材に固定された突出部材
を前記鋼桁の上フランジの側縁に係合して、該車輪の走
行を案内させるものとする。
According to a fourth aspect of the present invention, in the method for forming a concrete floor slab according to the first aspect, the support structure is a steel girder already erected, and the wheel is
The vehicle travels on an upper flange of the steel girder. The wheel flange of the wheel or a protruding member fixed to the plate-like member is engaged with a side edge of the upper flange of the steel girder to travel the wheel. Shall be guided.

【0018】一般に鋼桁は、高い精度で構築することが
でき、その上フランジの上を直接車輪が走行することが
できる。そして、上フランジの側縁に車輪フランジ又は
移送する板状部材に固定された突出部材を係止すること
により、この鋼桁の上フランジに沿って車輪は正確に走
行する。したがって、仮設レール等が不要となり、作業
工数が低減される。
In general, steel girders can be constructed with a high degree of accuracy and the wheels can run directly on their upper flanges. By engaging a wheel flange or a protruding member fixed to a plate-like member to be transferred to the side edge of the upper flange, the wheel can travel accurately along the upper flange of the steel girder. Therefore, a temporary rail or the like becomes unnecessary, and the number of work steps is reduced.

【0019】請求項5に記載の発明は、 二つの固定構
造物間に張架された吊材と、この吊材上に立ち上げられ
た支柱と、この支柱上に架け渡されて路面を形成する上
路桁とを有する上路式吊構造橋の構築方法であって、
前記固定構造物間に、前記吊材を撓みが生じた状態で張
架し、 該吊材上に複数の支柱を立設し、 この支柱の
頂部間に水平部材を架け渡し、 下面に車輪を取り付け
たプレキャストコンクリートの板状部材を前記水平部材
上を走行させて所定位置に移動し、 該板状部材を前記
支柱の頂部に固定する上路式吊構造橋の構築方法を提供
するものである。
According to a fifth aspect of the present invention, there is provided a suspension member stretched between two fixed structures, a support standing on the support, and a road surface formed on the support. A method of constructing an upper suspension bridge having an upper girder,
Between the fixed structure, stretched in a state in which deflection the suspended material occurs, erected a plurality of posts on the Tsuzai, spanned a horizontal member between the top of the posts, the wheels on the lower surface An object of the present invention is to provide a method of constructing an upper road suspension structure bridge in which an attached precast concrete plate member is moved on a predetermined position by traveling on the horizontal member, and the plate member is fixed to the top of the column.

【0020】上記吊材は、例えばケーブル、又は柔軟に
変形が生じる程度に薄いコンクリート部材であって埋設
された鋼材で吊支持される吊床版等とすることができ
る。また、吊床版を形成するためのプレキャストコンク
リート部材をケーブルに懸垂支持した仮設途中の部材で
あってもよい。
The above-mentioned hanging material can be, for example, a cable or a suspended floor slab which is a concrete member which is thin enough to be deformed flexibly and which is suspended and supported by an embedded steel material. Further, a precast concrete member for forming a suspended floor slab may be a temporary member that is suspended from a cable.

【0021】上記上路式吊構造橋は、固定構造物間にた
わみ生じた状態で張架された吊材と、この吊材上に支
柱を立ち上げ、この支柱上にほぼ平坦に架け渡された上
路桁を支持する構造形式であり、吊材にケーブルを用い
たいわゆる逆吊橋や、吊材に薄いコンクリートの板状部
材を用いた上路式吊床版橋等を含むものである。なお、
上記上路桁は、I型、T型の断面を含むものに限らず、板
状のものも含む。
The structure bridge suspended above Raise formula is a Tsuzai stretched over a state in which bending occurs between the fixed structure, up the post to the hanging member on substantially is flat bridged on the supports And a so-called reverse suspension bridge using a cable as a suspension member, an upper road suspension deck bridge using a thin concrete plate-like member as a suspension member, and the like. In addition,
The upper girder is not limited to the one including the I-shaped and T-shaped cross sections, but also includes a plate-shaped one.

【0022】このような上路式吊構造橋の構築方法で
は、プレキャストコンクリートの板状部材が水平部材上
を走行して所定位置まで移動するので、大型のクレーン
等を用いることなく、橋の全長にわたって板状部材を配
列することができる。したがって架設のための設備・機
器を簡略化することができ、施工費用を低減することが
できる。また、吊材上に支柱を立設したときには、吊材
の剛性が極めて小さく、支柱の転倒に対する安定性を維
持するための措置が必要となる場合もあるが、複数の支
柱の頂部間に設けられる水平部材によって上記支柱の安
定性を確保することも可能となる。
In such a method for constructing a suspension bridge with an upper road type, since the precast concrete plate-like member travels on the horizontal member and moves to a predetermined position, the entire length of the bridge can be used without using a large crane or the like. Plate members can be arranged. Therefore, it is possible to simplify facilities and equipment for erection, and to reduce construction costs. In addition, when the support is erected on the suspension, the rigidity of the suspension is extremely small, and measures to maintain stability against falling of the support may be required.However, the support is provided between the tops of the plurality of supports. It is also possible to secure the stability of the support by the horizontal member.

【0023】[0023]

【発明の実施の形態】以下、本願発明の実施形態を図に
基づいて説明する。図1は、本願発明に係るコンクリー
ト床版の形成方法が適用される橋梁の一例を示す概略側
面図および断面図である。この橋梁は鋼桁を有する二径
間連続の道路橋であり、二つの橋台1a、1bと橋脚2
とによって鋼桁3が支持され、その上にコンクリート床
版4が形成されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a schematic side view and a cross-sectional view showing an example of a bridge to which a method for forming a concrete floor slab according to the present invention is applied. This bridge is a two-span continuous road bridge having steel girders, two abutments 1a and 1b and a pier 2
Supports the steel girder 3, on which a concrete slab 4 is formed.

【0024】上記鋼桁3は、図1(b)に示すように、
I型断面の二つの主桁5によって荷重を支持するもので
あり、これらの主桁5は横桁6によって相互に連結され
ている。なお、図1(b)中に示す符号7は主桁5のウ
エブ5aに沿って鉛直に設けられたリブである。
The steel girder 3 is, as shown in FIG.
The load is supported by two main girders 5 having an I-shaped cross section, and these main girders 5 are interconnected by cross girders 6. Reference numeral 7 shown in FIG. 1B is a rib provided vertically along the web 5 a of the main girder 5.

【0025】上記コンクリート床版4は、複数のプレキ
ャストコンクリートの板状部材を鋼桁3上に配列し、こ
れらを連結して一体化するとともに主桁5に固着して形
成されたものであり、橋軸方向および橋軸と直角方向に
プレストレスが導入されている。このようなコンクリー
ト床版4は、次のような工程によって形成される。な
お、このコンクリート床版の形成方法は請求項1又は請
求項4に記載の発明の一実施形態である。
The concrete floor slab 4 is formed by arranging a plurality of precast concrete plate members on a steel girder 3, connecting and integrating them, and fixing them to the main girder 5. Prestress is introduced in the bridge axis direction and at right angles to the bridge axis. Such a concrete floor slab 4 is formed by the following steps. This method of forming a concrete floor slab is an embodiment of the invention described in claim 1 or claim 4.

【0026】図2(a)に示すように、橋台1a、1b
及び橋脚2上に鋼桁3が架設されると、工場又は製作ヤ
ードで制作され、橋軸と直角方向にプレストレスが導入
されたプレキャストコンクリートの板状部材12をクレ
ーン11で吊り上げ、主桁5上に載置される。このと
き、上記板状部材12の下面には4つの車輪が取り付け
られており、図3及び図4に示すように、これらの車輪
9が主桁5の上フランジ5bの内側縁部上に載り、車輪
フランジが主桁の上フランジ5bの縁に係合されて、橋
軸方向に走行が可能となる。このように主桁5上に載置
されたプレキャストコンクリートの板状部材12は、図
2(b)に示すように、ウインチ13によりワイヤ14
を介して牽引され、所定の位置まで移動される。
As shown in FIG. 2A, the abutments 1a, 1b
When the steel girder 3 is erected on the pier 2, the precast concrete plate member 12, which is produced in a factory or a production yard and is prestressed in a direction perpendicular to the bridge axis, is lifted by the crane 11, and the main girder 5 Placed on top. At this time, four wheels are attached to the lower surface of the plate-like member 12, and these wheels 9 are mounted on the inner edge of the upper flange 5b of the main girder 5, as shown in FIGS. The wheel flange is engaged with the edge of the upper flange 5b of the main girder, and the vehicle can travel in the bridge axis direction. The precast concrete plate-like member 12 placed on the main girder 5 in this manner is connected to a wire 14 by a winch 13 as shown in FIG.
And is moved to a predetermined position.

【0027】所定位置まで移動された板状部材12は、
図5に示すように、位置調整ボルト16を回転すること
によって、この位置調整ボルト16で上フランジ5b上
に支持される。この位置調整ボルト16は、コンクリー
トの板状部材12に埋め込んで固着されたナット状の筒
状金具17と螺合されており、板状部材12の上側から
貫通して先端が下側に突出している。したがって、この
位置調整ボルト16を回転することによって、その先端
を上フランジ5bに当接し、さらに回転させることによ
って板状部材12を持ち上げて支持できるようになって
いる。このようにプレキャストコンクリートの板状部材
12の重量が位置調整ボルト16に負担され、車輪9が
無負担状態となると、車輪の取り付けボルト15を緩め
ることによって車輪9を枠体10とともに撤去すること
ができる。
The plate-like member 12 moved to a predetermined position is
As shown in FIG. 5, by rotating the position adjusting bolt 16, the position adjusting bolt 16 is supported on the upper flange 5b. The position adjusting bolt 16 is screwed with a nut-like cylindrical metal fitting 17 embedded and fixed in the concrete plate-shaped member 12, and penetrates from the upper side of the plate-shaped member 12 so that the tip projects downward. I have. Therefore, by rotating the position adjusting bolt 16, its tip abuts on the upper flange 5b, and by further rotating, the plate-like member 12 can be lifted and supported. As described above, when the weight of the precast concrete plate-shaped member 12 is borne by the position adjusting bolt 16 and the wheel 9 is in an unloaded state, the wheel 9 is removed together with the frame 10 by loosening the wheel mounting bolt 15. it can.

【0028】その後、図5(b)に示すように、位置調
整ボルト16を逆方向に回転させてプレキャストコンク
リートの板状部材12を下降させ、所定の高さに設定す
る。このとき、上フランジ5bの上面に立設されたスタ
ッドジベル8は、あらかじめ板状部材12に設けられて
いる穴12aに収容される。
Thereafter, as shown in FIG. 5 (b), the position adjusting bolt 16 is rotated in the reverse direction to lower the precast concrete plate member 12 to a predetermined height. At this time, the stud dowel 8 erected on the upper surface of the upper flange 5b is housed in a hole 12a provided in the plate member 12 in advance.

【0029】板状部材12が所定位置に設置されると、
上フランジ5bと板状部材12との間、および板状部材
12に設けられた穴12a内にモルタルを充填し、主桁
5と板状部材12とを一体化する。また、複数の板状部
材間にもコンクリート又はモルタルを打設し、硬化後に
橋軸方向のプレストレスを導入して一体化する。また、
位置調整ボルト16は板状部材12の下側に充填された
モルタルの硬化後に抜き取り、あとの貫通孔にはモルタ
ルを充填して橋面を平坦に仕上げる。
When the plate member 12 is set at a predetermined position,
Mortar is filled between the upper flange 5b and the plate member 12 and in the hole 12a provided in the plate member 12, and the main beam 5 and the plate member 12 are integrated. Also, concrete or mortar is cast between a plurality of plate members, and after hardening, prestress in the bridge axis direction is introduced to be integrated. Also,
The position adjusting bolt 16 is pulled out after the mortar filled in the lower side of the plate member 12 is hardened, and the remaining through hole is filled with mortar to finish the bridge surface flat.

【0030】上記のような工程でコンクリート床版4を
形成することによって、プレキャストコンクリートの板
状部材12は一方の橋台1a付近で吊り上げ、鋼桁3上
の同じ位置に載置しても、容易に移動して橋梁の全域に
板状部材12を配列することができる。したがって大き
なクレーン等の設備が不要となり、作業の効率が向上す
る。また、所定位置へ移動した後も、位置調整ボルト1
6を利用して、簡単に車輪9の取り外し、所定高さへの
据え付けを行うことができる。
By forming the concrete floor slab 4 in the above steps, the precast concrete plate member 12 can be easily lifted near one of the abutments 1a and placed at the same position on the steel girder 3. And the plate members 12 can be arranged over the entire area of the bridge. Therefore, equipment such as a large crane is not required, and work efficiency is improved. Also, after moving to the predetermined position, the position adjusting bolt 1
With the use of 6, the wheels 9 can be easily removed and installed at a predetermined height.

【0031】次に、請求項5に記載の発明の一実施形態
である上路式吊構造橋の構築方法について説明する。図
6は、請求項5に記載の方法によって構築することがで
きる上路式の吊床版橋の概略側面図及び断面図である。
この上路式吊床版橋は、アースアンカー23によって地
盤に固定された二つの橋台21、22と、これらの橋台
間に張架された吊床版24と、この吊床版24から鉛直
に立ち上げられた複数の支柱25と、この支柱上に支持
された上路桁26とで主要部が構成されている。
Next, a description will be given of a method of constructing an upper road suspension bridge according to an embodiment of the present invention. FIG. 6 is a schematic side view and a cross-sectional view of a road-type suspension deck bridge that can be constructed by the method according to claim 5.
This upper road type suspended deck bridge is provided with two abutments 21 and 22 fixed to the ground by an earth anchor 23, a suspended deck 24 stretched between these abutments, and vertically raised from the suspended deck 24. The main part is composed of a plurality of columns 25 and an upper path girder 26 supported on the columns.

【0032】上記橋台21、22は鉄筋コンクリートか
らなるものであり、地盤上に構築され、上記吊床版24
から伝達される水平力に対して転倒または滑動しないよ
うにアースアンカー23で地盤に強固に固着されてい
る。なお、アースアンカー23は地盤に削孔を行い、こ
の孔内にPC鋼材を挿入した後グラウトを施したもので
あり、このPC鋼材に緊張力を導入することによって橋
台を地盤に押し付けるように固定することができるもの
である。
The abutments 21 and 22 are made of reinforced concrete and are constructed on the ground.
Is firmly fixed to the ground by an earth anchor 23 so as not to fall or slide against a horizontal force transmitted from the ground. The ground anchor 23 is formed by drilling a hole in the ground, inserting a PC steel into the hole, and then grouting the ground. By applying a tension to the PC steel, the abutment is fixed to be pressed against the ground. Is what you can do.

【0033】上記吊床版24は、二つの橋台21、22
の間に連続するように形成された薄いコンクリートの版
であり、軸線方向に複数のPC鋼材が配置されている。
このPC鋼材は、吊床版のコンクリートと一体化されて
おり、このPC鋼材によって引張力に抵抗し、橋台間に
該吊床版が張架される。
The suspended floor slab 24 includes two abutments 21 and 22.
This is a thin concrete plate formed so as to be continuous between the steel plates, and a plurality of PC steel materials are arranged in the axial direction.
The PC steel material is integrated with the concrete of the suspended slab, and the PC steel material resists the tensile force, and the suspended slab is stretched between the abutments.

【0034】上記支柱25は、吊床版24の両側縁付近
から立ち上げられた鋼管からなるものであり、吊床版2
4上で自立するように固定されている。また、両側縁か
ら立ち上げられた鋼管は頂部で横方向部材27によって
互いに連結され、鋼管の上端にはほぼ水平にプレート2
8が接合されている。
The strut 25 is made of a steel pipe rising from both sides of the suspended slab 24.
4 so as to stand on its own. The steel pipes rising from both side edges are connected to each other at the top by a transverse member 27, and the upper end of the steel pipe is almost horizontally placed on the plate 2.
8 are joined.

【0035】上記上路桁26は、プレキャストコンクリ
ートの板状部材を橋軸方向に連結して形成されたもので
あり、橋軸方向にプレストレスが導入される。この上路
桁26は、二つの橋台間で連続するものであってもよい
し、適宜に分割して伸縮継手を設けた構造としてもよ
い。
The upper girder 26 is formed by connecting precast concrete plate members in the bridge axis direction, and prestress is introduced in the bridge axis direction. The upper girder 26 may be continuous between two abutments, or may be appropriately divided and provided with an expansion joint.

【0036】次に、上記上路式吊床版橋の構築方法につ
いて説明する。まず、図7(a)に示すように、二つの
橋台21、22を架設位置で対峙するように形成し、ア
ースアンカー23によって強固に地盤に固定する。そし
て、これらの橋台間にケーブル31を張架する。吊床版
24を形成するためのプレキャストコンクリートの板状
部材32は工場又は製作ヤードで形成され、一方の橋台
21付近においてクレーン33で吊り上げられ、上記ケ
ーブル31に懸垂支持される。
Next, a description will be given of a method of constructing the above-mentioned suspended slab bridge. First, as shown in FIG. 7A, two abutments 21 and 22 are formed so as to face each other at the erection position, and are firmly fixed to the ground by an earth anchor 23. Then, the cable 31 is stretched between these abutments. A plate member 32 of precast concrete for forming the suspended floor slab 24 is formed in a factory or a manufacturing yard, is lifted by a crane 33 near one of the abutments 21, and is suspended and supported by the cable 31.

【0037】この板状部材32は、上側に橋軸方向の溝
が形成されており、図10に示すように、この溝32a
内にケーブル31が納まるように吊り上げられ、ケーブ
ル31の上側から短い鋼棒34を溝の内側で係止して該
板状部材32の重量をケーブル31に負担させるように
なっている。また、上記板状部材32には、図10に示
すように、支柱25が既に取り付けられている。
The plate-like member 32 has a bridge-axis groove formed on the upper side, and as shown in FIG.
The cable 31 is lifted so as to be accommodated therein, and a short steel rod 34 is locked from the upper side of the cable 31 inside the groove so that the weight of the plate-shaped member 32 is borne by the cable 31. Further, as shown in FIG. 10, a support 25 is already attached to the plate-like member 32.

【0038】ケーブル31に懸垂支持された板状部材3
2には、図7(b)に示すように、ワイヤ35の一端が
連結され、反対側の橋台22付近に設けられたウインチ
36によって牽引して所定の位置まで移動される。この
ようにして複数の板状部材32が順次ケーブル31に懸
垂支持され、図8(a)に示すように、橋台間のほぼ全
域にわたって配列される。
The plate member 3 suspended from the cable 31
As shown in FIG. 7 (b), one end of a wire 35 is connected to 2, and the wire 35 is pulled to a predetermined position by a winch 36 provided near the abutment 22 on the opposite side. In this way, the plurality of plate-like members 32 are sequentially suspended from the cable 31, and are arranged over substantially the entire area between the abutments as shown in FIG.

【0039】上記支柱25の頂部は、L型断面の型鋼か
らなる水平部材44によって橋軸方向に連結され、この
水平部材44は上路桁を形成するためのプレキャストコ
ンクリート部材41を走行移動させるために仮設桁とな
る。そして、図8(b)に示すように、クレーン33に
よってプレストレストコンクリート部材41が吊り上げ
られ、上記水平部材44上に載置される。
The top of the column 25 is connected in the bridge axis direction by a horizontal member 44 made of L-shaped section steel, and the horizontal member 44 is used to move the precast concrete member 41 for forming the upper girder. It is a temporary girder. Then, as shown in FIG. 8 (b), the prestressed concrete member 41 is lifted by the crane 33 and placed on the horizontal member 44.

【0040】上路桁を形成するためのプレキャストコン
クリート部材41は、図11及び図12に示すように、
下面に枠体42を介して車輪43が取り付けられてお
り、上記水平部材44に載置されて橋軸方向に走行す
る。また、枠体の一部42aが車輪43の走行面より下
方に突き出しており、水平部材44の側面によって該水
平部材の軸線方向に案内される。なお、プレキャストコ
ンクリート部材41の走行は、図8(b)に示すように
吊床版を形成する板状部材32の移動と同様に、ウイン
チ36によってワイヤ35を牽引することによって行わ
れる。
As shown in FIGS. 11 and 12, the precast concrete member 41 for forming the upper girder is
Wheels 43 are mounted on the lower surface via a frame 42, and are mounted on the horizontal member 44 and run in the bridge axis direction. Further, a part 42 a of the frame projects below the running surface of the wheel 43, and is guided by the side surface of the horizontal member 44 in the axial direction of the horizontal member. The traveling of the precast concrete member 41 is performed by pulling the wire 35 by the winch 36 as in the movement of the plate member 32 forming the suspended floor slab as shown in FIG. 8B.

【0041】プレキャストコンクリート部材41が所定
の位置まで移動されると、図13に示すように、この部
材に筒状金具45を介してほぼ鉛直に螺合された位置調
整ボルト46を回転し、先端を支柱25上のプレート2
8に当接して、プレキャストコンクリート部材41の重
量をこの位置調整ボルト46によって支持させる。そし
て、車輪43を取り外すとともに、水平部材44も撤去
し、位置調整ボルト46の回転により、図14に示すよ
うにプレキャストコンクリート部材41を所定の高さに
設定する。
When the precast concrete member 41 is moved to a predetermined position, as shown in FIG. 13, a position adjusting bolt 46 screwed substantially vertically to the member via a cylindrical metal member 45 is rotated. The plate 2 on the support 25
8, the weight of the precast concrete member 41 is supported by the position adjusting bolt 46. Then, while removing the wheel 43, the horizontal member 44 is also removed, and the precast concrete member 41 is set at a predetermined height by rotating the position adjusting bolt 46 as shown in FIG.

【0042】上記のようにして、上路桁を形成するプレ
キャストコンクリート部材41が、図9に示すように橋
台間のほぼ全域にわたって配列されると、ケーブル31
に懸垂支持されたプレキャストコンクリートの板状部材
32間、及び板状部材上側の溝内にコンクリートを打設
し、板状部材32を連結して、橋台間で連続した吊床版
24とするとともにケーブルと一体化する。コンクリー
トが硬化後、吊床版24の軸線方向に配置した二次ケー
ブルに張力を導入することによって吊床版24のコンク
リートに適切なプレストレスが導入される。
As described above, when the precast concrete members 41 forming the upper girder are arranged over almost the entire area between the abutments as shown in FIG.
Concrete is poured between the plate-like members 32 of the precast concrete suspended and supported in the groove and in the upper groove of the plate-like members, and the plate-like members 32 are connected to form a continuous suspension deck 24 between the abutments and the cable. Integrate with After the concrete has hardened, an appropriate prestress is introduced into the concrete of the suspended slab 24 by introducing tension into the secondary cables arranged in the axial direction of the suspended slab 24.

【0043】一方、上路桁を形成するプレキャストコン
クリート部材41間にも、コンクリートが打設され連続
した部材とされる。プレキャストコンクリート部材41
は、埋め込まれた鉄筋の一部47がU字状に接合する端
面から突き出しており、接合される双方のプレキャスト
コンクリート部材41から突き出した鉄筋47を埋め込
むようにコンクリートが打設され、連続したコンクリー
トの板状の桁とされる。また、プレキャストコンクリー
ト部材間を連結するコンクリート48は、支柱25の頂
部に設けられたプレート28上に直接打設され、支柱の
頂部とコンクリート床版とを同時に接合することにな
る。
On the other hand, concrete is also cast between the precast concrete members 41 forming the upper girder to form a continuous member. Precast concrete member 41
The concrete 47 is protruded from the end face where the embedded reinforcing bar 47 joins in a U-shape, and concrete is cast so as to embed the reinforcing bar 47 projecting from the two precast concrete members 41 to be joined. And a plate-shaped girder. The concrete 48 connecting the precast concrete members is directly poured onto the plate 28 provided on the top of the column 25, and simultaneously joins the top of the column and the concrete floor slab.

【0044】このコンクリート打設を行うために、プレ
キャストコンクリート部材41の下面には柔軟に変形す
る弾性部材49があらかじめ貼着されている。この弾性
部材49は、部材間を埋めるコンクリートが打設される
端面に沿った部分に連続して貼着されており、プレキャ
ストコンクリート部材41が所定の高さに設置された時
に、図14に示すように、該プレキャストコンクリート
部材41の下面と支柱頂部のプレート28との間に挟ま
れ、変形して隙間を塞ぐようになっている。したがっ
て、プレキャストコンクリート部材間にコンクリートを
打設する際に隙間を目地材等で塞ぐ必要がなくなり、作
業効率が向上する。上記コンクリートが硬化すると、上
路桁の軸線方向に適宜プレストレスが導入され、橋梁の
主要な構造が完成する。
In order to perform this concrete casting, an elastic member 49 which is flexibly deformed is attached to the lower surface of the precast concrete member 41 in advance. This elastic member 49 is continuously adhered to a portion along the end face where concrete filling the space between the members is cast, and when the precast concrete member 41 is installed at a predetermined height, it is shown in FIG. As described above, the precast concrete member 41 is sandwiched between the lower surface of the precast concrete member 41 and the plate 28 at the top of the column, and is deformed to close the gap. Therefore, when placing concrete between the precast concrete members, it is not necessary to close the gap with a joint material or the like, and the working efficiency is improved. When the concrete hardens, prestress is appropriately introduced in the axial direction of the upper girder, and the main structure of the bridge is completed.

【0045】このような上路式吊床版橋の構築方法で
は、吊床版24と上路桁26との双方がプレキャストコ
ンクリートからなる部材を用いて形成され、これらを所
定の位置に設置するのに大型の機械や設備を用いること
なく、効率の良い施工が可能となる。なお、上記上路式
吊床版橋の構築方法において、連続したコンクリートの
床版からなる上路桁を形成する方法は、本願の請求項
1、請求項2又は請求項3に記載の発明の一実施形態で
ある。
In such a method of constructing a suspended slab bridge, both the suspended slab 24 and the upper girder 26 are formed using members made of precast concrete, and a large sized slab is required for installing these members at predetermined positions. Efficient construction is possible without using machinery and equipment. In the method of constructing an upper suspension slab, the method of forming an upper girder made of a continuous concrete slab is an embodiment of the invention described in claim 1, claim 2 or claim 3 of the present application. It is.

【0046】[0046]

【発明の効果】以上説明したように、本願発明に係るコ
ンクリート床版の形成方法では、橋長が大きい場合であ
っても大型の機器又は設備を用いることなく、コンクリ
ート床版を効率よく形成することができる。また、本願
発明に係る上路式吊構造橋の構築方法においても、大型
の機器又は設備を用いずに、効率の良い上路式吊構造橋
を構築することができる。
As described above, in the method for forming a concrete slab according to the present invention, even when the bridge length is long, the concrete slab can be efficiently formed without using large equipment or facilities. be able to. Also, in the method of constructing an upper suspension bridge according to the present invention, an efficient upper suspension bridge can be constructed without using large-sized equipment or facilities.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本願発明に係るコンクリート床版の形成方法が
適用される橋梁の一例を示す概略側面図及び断面図であ
る。
FIG. 1 is a schematic side view and a sectional view showing an example of a bridge to which a method for forming a concrete floor slab according to the present invention is applied.

【図2】図1の橋梁におけるコンクリート床版の形成方
法を示す施工要領図である。
FIG. 2 is a construction procedure diagram showing a method of forming a concrete slab in the bridge of FIG.

【図3】図2に示すコンクリート床版の形成方法におい
て、プレキャストコンクリートの板状部材を走行移動さ
せる状態を示す概略断面図である。
FIG. 3 is a schematic cross-sectional view showing a state in which a plate member of precast concrete travels and moves in the method of forming a concrete floor slab shown in FIG.

【図4】図3に示すプレキャストコンクリートの板状部
材の走行移動時の状態を示す概略側面図である。
4 is a schematic side view showing a state of the precast concrete plate member shown in FIG. 3 during traveling movement.

【図5】プレキャストコンクリートの板状部材に取り付
けられた車輪及び位置調整ボルトを示す拡大断面図であ
る。
FIG. 5 is an enlarged sectional view showing a wheel and a position adjusting bolt attached to a plate member made of precast concrete.

【図6】本願発明に係る上路式吊構造橋の構築方法によ
って構築することができる上路式吊床版橋の例を示す概
略側面図及び断面図である。
FIG. 6 is a schematic side view and a cross-sectional view showing an example of an upper road suspension deck bridge that can be constructed by the method of constructing an upper suspension bridge according to the present invention.

【図7】図6に示す上路式吊床版橋の構築方法を示す施
工要領図である。
FIG. 7 is a construction procedure diagram showing a method of constructing the upper road type suspended deck bridge shown in FIG.

【図8】図6に示す上路式吊床版橋の構築方法を示す施
工要領図である。
8 is a construction procedure diagram showing a method of constructing the upper road type suspended deck slab shown in FIG.

【図9】図6に示す上路式吊床版橋の構築方法を示す施
工要領図である。
9 is a construction procedure diagram showing a method of constructing the upper road type suspended floor slab bridge shown in FIG.

【図10】図7から図9に示す施工方法において、プレ
キャストコンクリートの板状部材をケーブルに懸垂支持
させた状態を示す概略断面図である。
10 is a schematic cross-sectional view showing a state in which a plate-like member of precast concrete is suspended from a cable in the construction method shown in FIGS. 7 to 9. FIG.

【図11】図7から図9に示す施工方法において、上路
桁を形成するためのプレキャストコンクリート部材を走
行移動させる状態を示す概略断面図である。
FIG. 11 is a schematic sectional view showing a state in which a precast concrete member for forming an upper girder is traveled and moved in the construction method shown in FIGS. 7 to 9;

【図12】図11に示すプレキャストコンクリート部材
の走行移動時の状態を示す概略側面図である。
12 is a schematic side view showing a state of the precast concrete member shown in FIG. 11 during traveling movement.

【図13】プレキャストコンクリート部材に取り付けら
れた車輪及び位置調整ボルトを示す拡大断面図である。
FIG. 13 is an enlarged sectional view showing wheels and position adjustment bolts attached to a precast concrete member.

【図14】位置調整ボルトによってプレキャストコンク
リート部材を所定位置に設置した状態を示す拡大断面図
である。
FIG. 14 is an enlarged sectional view showing a state where a precast concrete member is installed at a predetermined position by a position adjusting bolt.

【符号の説明】[Explanation of symbols]

1 橋台 2 橋脚 3 鋼桁 4 コンクリ
ート床版 5 主桁 6 横桁 7 リブ 8 スタッド
ジベル 9 車輪 10 枠体 11 クレーン 12 プレキャストコンクリートの板状部材 13 ウインチ 14 ワイヤ 15 車輪の取り付けボルト 16 位置調
整ボルト 21 橋台 22 橋台 23 アースアンカー 24 吊床版 25 支柱 26 上路桁 27 横方向部材 28 プレー
ト 31 ケーブル 32 プレキャストコンクリートの板状部材 33 クレーン 34 鋼棒 35 ワイヤ 36 ウイン
チ 41 プレキャストコンクリート部材 42 枠体 43 車輪 44 水平部材 45 筒状金
具 46 位置調整ボルト 47 鉄筋 48 現場で打設されるコンクリート 49 弾性部材
DESCRIPTION OF SYMBOLS 1 Abutment 2 Pier 3 Steel girder 4 Concrete floor slab 5 Main girder 6 Cross beam 7 Rib 8 Stud dowel 9 Wheel 10 Frame 11 Crane 12 Precast concrete plate member 13 Winch 14 Wire 15 Wheel mounting bolt 16 Position adjustment bolt 21 Abutment 22 Abutment 23 Earth anchor 24 Suspended floor slab 25 Prop 26 Upper girder 27 Lateral member 28 Plate 31 Cable 32 Precast concrete plate member 33 Crane 34 Steel rod 35 Wire 36 Winch 41 Precast concrete member 42 Frame 43 Wheel 44 Horizontal member 45 Cylindrical fitting 46 Position adjusting bolt 47 Reinforcing bar 48 Concrete cast on site 49 Elastic member

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E01D 21/00 E01D 11/02 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 6 , DB name) E01D 21/00 E01D 11/02

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 複数のプレキャストコンクリートの板
状部材を形成し、 この板状部材の下面に車輪を取り付け、既に構築された
支持構造体上を所定位置まで前記車輪によって走行さ
せ、 該板状部材にほぼ垂直に螺合された位置調整ボルトを回
転させて突出した下端を前記支持構造体に当接させ、該
板状部材の重量を該位置調整ボルトで支持し、 前記車輪を取り外した後、前記位置調整ボルトを回転さ
せて該板状部材の上下方向の位置を設定し、 前記板状部材に車輪を取り付ける工程から、前記支持構
造体上で、該板状部材を所定位置に設定するまでの工程
を、複数の板状部材に付いて行ない、 これらの板状部材を前記支持構造体に固定することを特
徴とするコンクリート床版の形成方法。
1. A plurality of plate members made of precast concrete are formed, wheels are attached to the lower surface of the plate members, and the wheels are moved to a predetermined position on a support structure already constructed, by the wheels. After rotating the position adjusting bolt screwed substantially vertically to the lower end protruding to contact the support structure, supporting the weight of the plate-like member with the position adjusting bolt, and removing the wheels, Rotating the position adjustment bolt to set the vertical position of the plate member, from the step of attaching wheels to the plate member, to setting the plate member at a predetermined position on the support structure The method of forming a concrete floor slab, wherein the step (c) is performed on a plurality of plate members, and the plate members are fixed to the support structure.
【請求項2】 請求項1に記載のコンクリート床版の
形成方法において、 前記板状部材を支持構造体に固定する工程は、 前記複数の板状部材を前記支持構造体上に配列した後、
隣り合う板状部材の対向する端面の双方及び前記支持構
造体の上面に密着するようにコンクリートを打設し、双
方の板状部材を一体化するとともに該支持構造体に固定
するものであることを特徴とするコンクリート床版の形
成方法。
2. The method for forming a concrete floor slab according to claim 1, wherein the step of fixing the plate-like member to a support structure includes: after arranging the plurality of plate-like members on the support structure;
Concrete is cast so as to be in close contact with both opposing end surfaces of adjacent plate members and the upper surface of the support structure, and both plate members are integrated and fixed to the support structure. A method of forming a concrete slab.
【請求項3】 請求項2に記載のコンクリート床版の
形成方法において、前記板状部材の下面の、前記コンク
リートと密着する端面付近に、柔軟に変形する間詰部材
を接着しておき、 前記板状部材を所定位置に設定するときに、該板状部材
の下面と前記支持構造体の上面との間に前記間詰部材を
挟み込んで変形させ、 前記コンクリートの打設時に、前記間詰部材によってコ
ンクリートの漏出を防止することを特徴とするコンクリ
ート床版の形成方法。
3. The method for forming a concrete floor slab according to claim 2, wherein a filling member that deforms flexibly is bonded to a lower surface of the plate-like member near an end surface that is in close contact with the concrete, When setting the plate-like member at a predetermined position, the filling member is sandwiched between the lower surface of the plate-like member and the upper surface of the support structure and deformed. A method for forming a concrete floor slab, wherein leakage of concrete is prevented by the method.
【請求項4】 請求項1に記載のコンクリート床版の
形成方法において、 前記支持構造体は、既に架設された鋼桁であり、 前記車輪は、該鋼桁の上フランジ上を走行するものであ
り、 該車輪の車輪フランジ又は前記板状部材に固定された突
出部材を前記鋼桁の上フランジの側縁に係合して、該車
輪の走行を案内させることを特徴とするコンクリート床
版の形成方法。
4. The method of forming a concrete floor slab according to claim 1, wherein the support structure is a steel girder already erected, and the wheel runs on an upper flange of the steel girder. A concrete floor slab characterized in that a wheel flange of the wheel or a projecting member fixed to the plate-like member is engaged with a side edge of an upper flange of the steel girder to guide the running of the wheel. Forming method.
【請求項5】 二つの固定構造物間に張架された吊材
と、この吊材上に立ち上げられた支柱と、この支柱上に
架け渡されて路面を形成する上路桁とを有する上路式吊
構造橋の構築方法であって、 前記固定構造物間に、前記吊材を撓みが生じた状態で張
架し、 該吊材上に複数の支柱を立設し、 この支柱の頂部間に水平部材を架け渡し、 下面に車輪を取り付けたプレキャストコンクリートの板
状部材を前記水平部材上を走行させて所定位置に移動
し、 該板状部材を前記支柱の頂部に固定することを特徴とす
る上路式吊構造橋の構築方法。
5. An upper road having a suspending member stretched between two fixed structures, a support raised on the support, and an upper girder spanning over the support to form a road surface. a method for constructing a Shikitsu structure bridge, between the fixed structure, stretched in a state in which deflection the suspended material occurs, erected a plurality of posts on the Tsuzai, between the top of the strut A precast concrete plate-like member with wheels attached to the lower surface is moved on the horizontal member to a predetermined position, and the plate-like member is fixed to the top of the column. To build an upper road suspension bridge.
JP10230327A 1998-08-01 1998-08-01 Method of forming concrete slab and method of constructing upper road suspension bridge Expired - Fee Related JP2967876B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10230327A JP2967876B1 (en) 1998-08-01 1998-08-01 Method of forming concrete slab and method of constructing upper road suspension bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10230327A JP2967876B1 (en) 1998-08-01 1998-08-01 Method of forming concrete slab and method of constructing upper road suspension bridge

Publications (2)

Publication Number Publication Date
JP2967876B1 true JP2967876B1 (en) 1999-10-25
JP2000054319A JP2000054319A (en) 2000-02-22

Family

ID=16906105

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10230327A Expired - Fee Related JP2967876B1 (en) 1998-08-01 1998-08-01 Method of forming concrete slab and method of constructing upper road suspension bridge

Country Status (1)

Country Link
JP (1) JP2967876B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011169073A (en) * 2010-02-22 2011-09-01 Yokogawa Sumikin Bridge Corp Installing method for floor slab construction panel and transfer carriage
US9874036B2 (en) 2015-05-08 2018-01-23 Cannon Design Products Group, Llc Prefabricated, deconstructable, multistory building construction
CN113682989A (en) * 2021-07-20 2021-11-23 中铁建工集团有限公司 Auxiliary hoisting device for bridge construction
CN114232502A (en) * 2022-01-18 2022-03-25 中铁十四局集团第三工程有限公司 Self-propelled sliding formwork truss and using method thereof

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4855311B2 (en) * 2007-03-27 2012-01-18 株式会社Ihiインフラシステム Precast erection method
JP4838329B2 (en) * 2009-03-16 2011-12-14 三井住友建設株式会社 Construction method of upper-floor type suspension floor slab bridge
JP5632212B2 (en) * 2010-06-25 2014-11-26 川田工業株式会社 Heavy goods transport installation equipment
JP5867451B2 (en) * 2012-06-21 2016-02-24 Jfeスチール株式会社 Temporary bridge construction method and precast slab used in the construction method
CN103556564B (en) * 2013-10-31 2016-06-29 福州大学 A kind of assembled slab bridge based on the connection of steel diaphragm plate and construction method thereof
JP6527074B2 (en) * 2015-11-27 2019-06-05 株式会社ピーエス三菱 Bridge construction method
KR101839001B1 (en) 2017-07-12 2018-03-15 이춘기 Precasting equipment
JP7371315B2 (en) * 2019-12-26 2023-10-31 株式会社竹中工務店 Precast floor slab construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011169073A (en) * 2010-02-22 2011-09-01 Yokogawa Sumikin Bridge Corp Installing method for floor slab construction panel and transfer carriage
US9874036B2 (en) 2015-05-08 2018-01-23 Cannon Design Products Group, Llc Prefabricated, deconstructable, multistory building construction
CN113682989A (en) * 2021-07-20 2021-11-23 中铁建工集团有限公司 Auxiliary hoisting device for bridge construction
CN114232502A (en) * 2022-01-18 2022-03-25 中铁十四局集团第三工程有限公司 Self-propelled sliding formwork truss and using method thereof
CN114232502B (en) * 2022-01-18 2023-09-29 中铁十四局集团第三工程有限公司 Self-propelled sliding template truss and use method thereof

Also Published As

Publication number Publication date
JP2000054319A (en) 2000-02-22

Similar Documents

Publication Publication Date Title
US7409807B2 (en) Methods and apparatus for forming and placing generally horizontal structures
CN203475598U (en) Shock-proof prefabricated building of steel bar truss shearing wall composite structure
JP2967876B1 (en) Method of forming concrete slab and method of constructing upper road suspension bridge
JP3844743B2 (en) Box girder bridge structure and its construction method
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
JP3737475B2 (en) Box girder bridge structure and construction method
CN110761165B (en) Steel web box girder installation system and construction method thereof
JP2000017613A (en) Connection of corrugated steel plate web girder
CN116837967A (en) Construction method of large-span cable-stayed truss structure
CN115162358B (en) Assembled steel-concrete combined support system for foundation pit engineering and construction method
CN114658002B (en) External prestress steel support supporting system and construction method thereof
CN214170072U (en) Steel construction factory building structure based on exposed foundation
CN114214920A (en) Large-span double-layer combined construction steel truss arch bridge and construction method thereof
KR20040054639A (en) External Prestressing Method of PS Concrete Composite Girder Bridge by Anchoring and Holding Tendon on Precast Cross-Beam
JP2003049407A (en) Bridge and its construction method
CN111472284A (en) Assembling method for cantilever of prefabricated segmental beam portal crane of urban viaduct
JP2000104220A (en) Erection of combined truss bridge
CN216891927U (en) Large-span double-layer combined construction steel truss arch bridge
JP7464914B2 (en) Precast floor slab installation jig and precast floor slab connection method
JP2003064621A (en) Hanging floor slab bridge and reinforcing method of hanging floor slab
JP7413233B2 (en) How to construct panel units and structures
CN115323924B (en) Construction method of highway-railway dual-purpose river-crossing A-type cable-stayed bridge main tower
CN215800924U (en) High-altitude in-situ cast-in-situ bridge
JP2003049487A (en) Connection structure between steel member and concrete member
CN116104101A (en) Foundation pit prestressed supporting system and construction method thereof

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990803

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090820

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090820

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100820

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110820

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110820

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120820

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120820

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130820

Year of fee payment: 14

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees