JPH0449210Y2 - - Google Patents

Info

Publication number
JPH0449210Y2
JPH0449210Y2 JP1985083239U JP8323985U JPH0449210Y2 JP H0449210 Y2 JPH0449210 Y2 JP H0449210Y2 JP 1985083239 U JP1985083239 U JP 1985083239U JP 8323985 U JP8323985 U JP 8323985U JP H0449210 Y2 JPH0449210 Y2 JP H0449210Y2
Authority
JP
Japan
Prior art keywords
precast concrete
holes
steel girder
slab
bridge axis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1985083239U
Other languages
Japanese (ja)
Other versions
JPS61198312U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP1985083239U priority Critical patent/JPH0449210Y2/ja
Publication of JPS61198312U publication Critical patent/JPS61198312U/ja
Application granted granted Critical
Publication of JPH0449210Y2 publication Critical patent/JPH0449210Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【考案の詳細な説明】 本考案は、たとえば鋼桁に固定的に設置される
プレキヤストコンクリート床版の取付け部の構造
に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to the structure of a mounting portion of a precast concrete deck that is fixedly installed, for example, on a steel girder.

背景技術 第9図は、典型的な先行技術を示す斜視図であ
る。鋼桁1の上フランジ1aには、複数のジベル
2が植設される。この鋼桁1に固定的に設置され
るプレキヤストコンクリート床版3には、前記ジ
ベル2に対応した位置に透孔4が予め形成されて
いる。プレキヤストコンクリート床版3を鋼桁1
に取付けるに当つては、透孔4内にジベル2が配
置されるように上フランジ1a上にプレキヤスト
コンクリート床版3を乗載して、このような状態
で透孔4内にセメントモルタルやコンクリートな
どの充填材を注入し、一定期間養生する。これに
よつて、プレキヤストコンクリート床版3が鋼桁
1上に固定される。
BACKGROUND ART FIG. 9 is a perspective view showing a typical prior art. A plurality of dowels 2 are planted in the upper flange 1a of the steel girder 1. A precast concrete deck slab 3 fixedly installed on the steel girder 1 has through holes 4 formed in advance at positions corresponding to the dowels 2. Precast concrete slab 3 and steel girder 1
When installing the precast concrete slab 3 on the upper flange 1a so that the dowel 2 is placed in the through hole 4, cement mortar or Filler material such as concrete is poured into it and allowed to cure for a certain period of time. As a result, the precast concrete deck slab 3 is fixed onto the steel girder 1.

考案が解決しようとする問題点 上記先行技術では、プレキヤストコンクリート
床版3が老朽化して取替える際に、プレキヤスト
コンクリート床版3のみを切断し除去するだけで
なく、ジベル2をも除去しなければならず、した
がつて新たなプレキヤストコンクリート床版3を
取付けるときには、鋼桁1に新たなジベル2を打
直す必要がある。したがつて、取替作業の手間が
かかるとともにコストアツプにもつながる。ま
た、プレキヤストコンクリート床版3と鋼桁1と
を一体化する際に、充填材を注入する必要があ
り、この充填材の養生期間が必要となる。したが
つて、施工期間が比較的長くかかるという問題を
有する。
Problems to be solved by the invention In the above prior art, when the precast concrete slab 3 becomes obsolete and is replaced, not only the precast concrete slab 3 must be cut and removed, but also the dowel 2 must be removed. Therefore, when installing a new precast concrete deck slab 3, it is necessary to recast a new dowel 2 into the steel girder 1. Therefore, the replacement work is time-consuming and leads to an increase in costs. Further, when integrating the precast concrete slab 3 and the steel girder 1, it is necessary to inject a filler, and a curing period for this filler is required. Therefore, there is a problem that the construction period is relatively long.

また上述の先行技術では、橋軸直角方向に隣接
する各プレキヤストコンクリート床版は、相互に
対向する端面間の空隙に充填された充填材によつ
て接合されるけれども、昼間と夜間あるいは夏と
冬などの温度変化による鋼桁の橋軸方向の膨張ま
たは収縮によつて、各プレキヤストコンクリート
床版間にずれが生じ、隙間が発生してしまうとい
う問題がある。このような隙間が生じると、前記
充填材の欠損や陥没が生じ、これに起因して路床
の陥没を発生してしまう。この問題を解決するた
めに従来では、プレキヤストコンクリート床版の
相互に対向する各端面を凹凸状に形成して、接合
強度の向上が図られているけれども、そのように
すると、一定の範囲に限つてプレキヤストコンク
リート床版を撤去する必要がある場合に、撤去す
る必要のないプレキヤストコンクリート床版まで
破損してしまうという問題がある。
Furthermore, in the above-mentioned prior art, each precast concrete slab adjacent to each other in the direction perpendicular to the bridge axis is joined by a filler filled in the gap between the mutually opposing end surfaces, but during the daytime, nighttime, or summer. There is a problem in that the steel girder expands or contracts in the bridge axis direction due to temperature changes such as in winter, causing misalignment between the precast concrete slabs and creating gaps. When such a gap occurs, the filler material is missing or caves in, which causes the roadbed to cave in. In order to solve this problem, conventionally, the mutually opposing end surfaces of precast concrete slabs are formed into an uneven shape to improve the joint strength. In limited cases where it is necessary to remove the precast concrete slab, there is a problem in that the precast concrete slab that does not need to be removed is also damaged.

したがつて本考案の目的は、橋軸直角方向に隣
接するプレキヤストコンクリート床版間を相互に
大きな強度で接合し、取替える必要のないプレキ
ヤストコンクリート床版を破損することなしに容
易かつ迅速に老朽化したプレキヤストコンクリー
ト床版を交換することができるようにしたプレキ
ヤストコンクリート床版の取付け部の構造を提供
することである。
Therefore, the purpose of this invention is to connect precast concrete slabs adjacent to each other in the direction perpendicular to the bridge axis with great strength, and to easily and quickly connect the precast concrete slabs that do not need to be replaced without damaging them. To provide a structure of an attachment part of a precast concrete floor slab, which allows the aging precast concrete floor slab to be replaced.

問題点を解決するための手段 本考案は、上記フランジ22と、下フランジ2
3と、各フランジ22,23を連結する腹板24
とを有し、前記上フランジ22には橋軸方向に間
隔をあけて複数の第1透孔25が、前記腹板24
を含む仮想平面に関して両側に形成され、橋軸直
角方向に間隔をあけて橋軸方向に延びる複数の鋼
桁12と、 複数のスタツドジベル19が固定される抜止部
16と、接合部17と、抜止部16および接合部
17を連結するウエブ18とを有し、前記接合部
17には、前記上フランジ22に形成される第1
透孔25に対応して複数の第2透孔20が形成さ
れる軸直角断面が略C字状の取付部材41と、 橋軸方向の端部に少なくとも前記抜止部16が
埋設されて一体的に固定され、前記ウエブ18の
側面18aと同一平面内に端面14aが形成され
る平板状のコンクリート床版本体14と、 前記鋼桁12の上フランジ22上に前記取付部
材41の接合部17が乗載された状態で、第1お
よび第2透孔25,20に挿通されるボルト26
およびこのボルト26に螺着されるナツト27
と、 鋼桁12上で相互に対向する前記各側面18a
間と各端面14a間とにわたつて形成される空隙
に充填される充填材60とを含むことを特徴とす
るプレキヤストコンクリート床版の取付け部の構
造である。
Means for Solving the Problems The present invention provides the above flange 22 and the lower flange 2.
3, and a belly plate 24 connecting each flange 22, 23.
The upper flange 22 has a plurality of first through holes 25 at intervals in the bridge axis direction, and the belly plate 24 has a plurality of first through holes 25 at intervals in the bridge axis direction.
A plurality of steel girders 12 formed on both sides with respect to a virtual plane including the bridge axis and extending in the bridge axis direction at intervals in the direction perpendicular to the bridge axis, a retaining part 16 to which a plurality of stud dowels 19 are fixed, a joint part 17, and a retaining part 12. 16 and a web 18 connecting the joint part 17, and the joint part 17 has a first web formed on the upper flange 22.
A mounting member 41 having a substantially C-shaped cross section perpendicular to the axis, in which a plurality of second through holes 20 are formed corresponding to the through holes 25, and at least the retaining portion 16 is embedded in the end portion in the bridge axis direction, and are integrally formed. A flat concrete slab main body 14 is fixed to the main body 14 and has an end surface 14a formed in the same plane as the side surface 18a of the web 18. The bolt 26 is inserted into the first and second through holes 25 and 20 while being mounted on the vehicle.
and a nut 27 screwed onto this bolt 26
and each side surface 18a facing each other on the steel girder 12.
This is a structure of an attachment part of a precast concrete slab, characterized in that it includes a filler 60 filled in a gap formed between the end faces 14a and between the end faces 14a.

作 用 本考案に従えば、取付部材の抜止部にはコンク
リート床版本体が一体的に固定され、この取付部
材の接合部と鋼桁とは、ボルトおよびナツトによ
つて連結され、これによつてコンクリート床版本
体を含む取付部材と鋼桁とは着脱自在に固定され
る。したがつて、前記先行技術に関連して述べた
ように、鋼桁上のプレキヤストコンクリート床版
を取替える際に、ジベルなどを打直す必要がなく
なり、これによつてプレキヤスト床版の取替え時
間を短くして、取替え作業に要する労力およびコ
ストを低減することができる。また取付部材の側
面とコンクリート床版本体の端面とは同一平面内
に形成され、橋軸直角方向に隣接する各プレキヤ
ストコンクリート床版は、相互に対向する各側面
と各端面とによつて形成される空隙に充填された
充填材によつて大きな強度で接合され、各プレキ
ヤストコンクリート床版の橋軸方向のずれなどに
よつて充填材が剥離されることを防止することが
できる。
Effect According to the present invention, the concrete slab body is integrally fixed to the retaining part of the mounting member, and the joint part of the mounting member and the steel girder are connected by bolts and nuts. The mounting members including the concrete slab body and the steel girder are removably fixed. Therefore, as mentioned in relation to the prior art, when replacing the precast concrete slab on the steel girder, there is no need to recast the dowel etc., thereby reducing the time required to replace the precast concrete slab. By making it shorter, the labor and cost required for replacement work can be reduced. In addition, the side surfaces of the mounting members and the end surfaces of the concrete deck main body are formed in the same plane, and each precast concrete deck adjacent in the direction perpendicular to the bridge axis is formed with each side surface and each end surface facing each other. The filler filled in the voids between the two bridges creates a bond with great strength, and it is possible to prevent the filler from peeling off due to displacement of each precast concrete slab in the bridge axis direction.

実施例 第1図は本考案の前提となる構成を示す正面図
であり、第2図は第1図の分解斜視図である。橋
梁11は、橋軸直角方向(第2図の左右方向)に
一定の間隔をあけて配置される複数の鋼桁12
と、この鋼桁に固定的に配置されるプレキヤスト
コンクリート床版13とを含む。このプレキヤス
トコンクリート床版13は、平板状のコンクリー
ト床版本体14と、このコンクリート床版本体1
4を鋼桁12に取付けるための取付部材15とを
含む。取付部材15は、軸直角断面がI形であ
り、コンクリート床版本体14に埋設される抜止
部16と、鋼桁12に臨んで外部に露出した接合
部17と、抜止部16と接合部17とを連結する
ウエブ18とを含む。抜止部16には、複数のス
タツドジベル19が予め溶接などによつて植設さ
れている。そのため、取付部材15は確実にコン
クリート床版本体14に固定される。前記抜止部
16と接合部17とは、第7図からも明らかなよ
うに、相互に平行であつて、前記コンクリート床
版本体14とほぼ平行に延びる。
Embodiment FIG. 1 is a front view showing the basic structure of the present invention, and FIG. 2 is an exploded perspective view of FIG. 1. The bridge 11 includes a plurality of steel girders 12 arranged at regular intervals in the direction perpendicular to the bridge axis (left-right direction in FIG. 2).
and a precast concrete deck slab 13 fixedly arranged on the steel girder. This precast concrete slab 13 includes a flat concrete slab body 14 and a concrete slab body 1.
4 to the steel girder 12. The mounting member 15 has an I-shaped cross section perpendicular to the axis, and includes a retaining portion 16 buried in the concrete slab body 14, a joint portion 17 exposed to the outside facing the steel girder 12, and the retaining portion 16 and the joint portion 17. and a web 18 connecting the two. A plurality of stud dowels 19 are implanted in the retaining portion 16 in advance by welding or the like. Therefore, the mounting member 15 is reliably fixed to the concrete slab body 14. As is clear from FIG. 7, the retaining portion 16 and the joint portion 17 are parallel to each other and extend substantially parallel to the concrete slab body 14.

接合部17には、部材軸方向Aに沿つて複数の
透孔20が形成される。このような透孔20の透
孔列は、ウエブ18に関して左右両側にそれぞれ
一列ずつ形成されている。
A plurality of through holes 20 are formed in the joint portion 17 along the member axis direction A. One row of such through holes 20 is formed on each of the left and right sides of the web 18.

抜止部16と接合部17との間には、部材軸方
向Aに沿つて一定の間隔をあけて複数の補強部材
21が設けられる。この補強部材21は、部材軸
方向Aに対して直角に取付けられている。
A plurality of reinforcing members 21 are provided between the retaining portion 16 and the joining portion 17 at regular intervals along the member axis direction A. This reinforcing member 21 is attached at right angles to the member axial direction A.

鋼桁12は、上フランジ22と、下フランジ2
3と、上フランジ22と下フランジ23とを連結
する腹板24とを有する。上フランジ22には、
前記接合部17の透孔20に対応した位置に透孔
25が形成される。
The steel girder 12 has an upper flange 22 and a lower flange 2.
3, and a belly plate 24 that connects the upper flange 22 and the lower flange 23. The upper flange 22 has
A through hole 25 is formed at a position corresponding to the through hole 20 of the joint portion 17 .

このような構成を有する鋼桁12にプレキヤス
トコンクリート床版13を取付るにあたつては、
まず上フランジ22上に接合部17を乗載する。
このような状態で、ボルト26を透孔20,25
に順次挿通させ、このボルト26の透孔25から
下方に露出した部分にナツト27を螺合させて締
付ける。こうして、プレキヤストコンクリート床
版13が鋼桁12に固定される。
When installing the precast concrete slab 13 to the steel girder 12 having such a configuration,
First, the joint portion 17 is mounted on the upper flange 22.
In this state, the bolt 26 is inserted into the through holes 20 and 25.
are sequentially inserted through the bolts 26, and the nuts 27 are screwed into the portions of the bolts 26 exposed downward from the through holes 25 and tightened. In this way, the precast concrete deck slab 13 is fixed to the steel girder 12.

なお、こうして複数のプレキヤストコンクリー
ト床版13が鋼桁12に取付けられた後、隣接す
るコンクリート床版本体14間の空隙にセメント
モルタルなどの充填材60を注入する。これによ
つて、各隣接するコンクリート床版本体14が連
接される。
Note that after the plurality of precast concrete deck slabs 13 are attached to the steel girder 12 in this way, a filler 60 such as cement mortar is injected into the gap between the adjacent concrete slab bodies 14. Thereby, each adjacent concrete slab body 14 is connected.

こうして、ボルト26およびナツト27によつ
てプレキヤストコンクリート床版13を鋼桁12
に固定させるようにしたので、先行技術のように
セメントモルタルなどの充填材の養生期間を必要
とすることなく、プレキヤストコンクリート床版
13を鋼桁12に固定することができ、したがつ
て取付け作業時間を可及的に低減することが可能
となる。
In this way, the precast concrete slab 13 is attached to the steel girder 12 by the bolts 26 and nuts 27.
Since the precast concrete deck slab 13 can be fixed to the steel girder 12 without requiring a curing period for filler such as cement mortar as in the prior art, the installation It becomes possible to reduce working time as much as possible.

こうして、架設された橋梁11が長年の使用に
よりコンクリート床版本体14が老朽化して、そ
のためコンクリート床版本体14を取替える必要
が生じる。このようなコンクリート床版本体14
を取替えるにあたつては、ナツト27をボルト2
6から取外すことによつて、プレキヤストコンク
リート床版13が鋼桁12から取外される。そし
て、新たなプレキヤストコンクリート床版13を
前述した工程によつて、鋼桁12に取付ける。こ
うして、ナツト27をボルト26から取外すこと
によつて、プレキヤストコンクリート床版13を
鋼桁12から簡単に取外すことができ、そのため
比較的短時間でしかも簡単にプレキヤストコンク
リート床版13を鋼桁12から取外すことが可能
となる。したがつて、従来のように床版を切断・
除去およびジベルを打直す必要がなく、作業性が
格段に向上するとともに、取替えコストを低減す
ることが可能となる。
In this way, the concrete deck main body 14 of the constructed bridge 11 becomes obsolete due to long-term use, and therefore, it becomes necessary to replace the concrete deck main body 14. Such concrete slab body 14
When replacing the bolt, replace nut 27 with bolt 2.
6, the precast concrete deck slab 13 is removed from the steel girder 12. Then, a new precast concrete deck slab 13 is attached to the steel girder 12 by the process described above. In this way, by removing the nuts 27 from the bolts 26, the precast concrete deck slab 13 can be easily removed from the steel girder 12. Therefore, the precast concrete deck slab 13 can be easily removed from the steel girder 12 in a relatively short time. It becomes possible to remove it from 12. Therefore, it is necessary to cut and cut the floor slab as in the past.
There is no need to remove or reshape the dowel, which greatly improves work efficiency and reduces replacement costs.

前記プレキヤストコンクリート床版13は、以
下の方法によつて工場などで予め製作されてい
る。すなわち、第3図に示されるように、上方が
開口した軸直角断面が大略的にU字状の型枠30
と、この型枠30の上方を覆う軸直角断面が大略
的に逆U字状の支持部材31とを準備する。先
ず、取付部材15の接合部17をワイヤ32を介
して支持部材31に固定する。そしてこのとき、
取付部材15の抜止部16が型枠30内に位置す
るようにワイヤ32を調節して吊下げる。このよ
うな状態で、型枠30内にコンクリートを充填す
る。そして、一定期間養生することによつて、プ
レキヤストコンクリート床版13が製作される。
The precast concrete floor slab 13 is manufactured in advance at a factory or the like by the following method. That is, as shown in FIG. 3, the formwork 30 is open at the top and has a roughly U-shaped cross section perpendicular to the axis.
and a support member 31 that covers the upper part of the formwork 30 and whose cross section perpendicular to the axis has a roughly inverted U-shape is prepared. First, the joint portion 17 of the attachment member 15 is fixed to the support member 31 via the wire 32. And at this time,
The wire 32 is adjusted and suspended so that the retaining portion 16 of the attachment member 15 is positioned within the formwork 30. In this state, the formwork 30 is filled with concrete. Then, by curing for a certain period of time, the precast concrete floor slab 13 is manufactured.

プレキヤストコンクリート床版13の他の製造
方法としては、第4図に示されるように、半割れ
状の一対の型枠33a,33bを準備する。これ
らの型枠33a,33bの突合わせ面には、切欠
き34a,34bが形成されている。これらの切
欠き34a,34bによつて、挿通孔35が構成
される。まず、接合部17を地面36に当接させ
た状態で、取付部材15を立設する。そして、型
枠33a,33bの挿通孔35を、ウエブ18が
挿通するように各型枠33a,33bを突合わ
せ、さらに型枠33a,33bを支持台37上に
乗載する。このような状態で、型枠33a,33
b内にコンクリートを打設して一定期間養生す
る。その後、型枠33a,33bを取除くことに
よつて、プレキヤストコンクリート床版13が製
作される。
As another method for manufacturing the precast concrete slab 13, as shown in FIG. 4, a pair of half-split formworks 33a and 33b are prepared. Notches 34a and 34b are formed in the abutting surfaces of these forms 33a and 33b. The insertion hole 35 is constituted by these notches 34a and 34b. First, the mounting member 15 is erected with the joint portion 17 in contact with the ground 36. Then, the molds 33a and 33b are butted together so that the web 18 passes through the insertion holes 35 of the molds 33a and 33b, and the molds 33a and 33b are mounted on the support stand 37. In this state, the formworks 33a, 33
Concrete is poured in area b and allowed to cure for a certain period of time. Thereafter, the precast concrete floor slab 13 is manufactured by removing the forms 33a and 33b.

プレキヤストコンクリート床版13の他の構成
を示す例としては、第5図に示されるように抜止
部16およびジベル19がコンクリート床版本体
14に埋設するような構成であつてもよく、また
第6図に示されるようにジベル19のみがコンク
リート床版本体14に埋設されるような構成であ
つてもよい。
As an example showing other configurations of the precast concrete slab 13, as shown in FIG. As shown in FIG. 6, only the dowel 19 may be buried in the concrete slab body 14.

第7図は、本考案の一実施例の断面図である。
なお、第1図〜第6図に示される構成に対応する
部分には同一の参照符を付す。注目すべきは、プ
レキヤストコンクリート床版40には、コンクリ
ート床版本体14の端部に取付部材41が取付け
られている。この取付部材41は、軸直角断面が
略C字状に形成されており、抜止部16と、接合
部17と、抜止部16および接合部17を連結す
るウエブ18とを有する。そして、ウエブ18の
側面18aは、コンクリート床版本体14の端面
14aとほぼ同一平面内にある。
FIG. 7 is a sectional view of one embodiment of the present invention.
Note that parts corresponding to the configurations shown in FIGS. 1 to 6 are given the same reference numerals. What should be noted is that the precast concrete slab 40 has attachment members 41 attached to the ends of the concrete slab body 14. The mounting member 41 has a substantially C-shaped cross section perpendicular to the axis, and includes a retaining portion 16 , a joint portion 17 , and a web 18 connecting the retaining portion 16 and the joint portion 17 . The side surface 18a of the web 18 is substantially in the same plane as the end surface 14a of the concrete slab body 14.

このような構成を有するプレキヤストコンクリ
ート床版40を鋼桁12に取付けるにあたつて
は、各プレキヤストコンクリート床版40の取付
部材41間に空隙が形成されるような状態で、鋼
桁12に乗載する。
When installing the precast concrete deck slab 40 having such a configuration to the steel girder 12, the steel girder 12 must be installed in such a state that a gap is formed between the mounting members 41 of each precast concrete deck slab 40. to be boarded.

このような状態で、ボルト26およびナツト2
7によつて、コンクリート床版本体14を鋼桁1
2に固定する。その後、空隙にセメントモルタル
あるいはコンクリートなどの充填材60を打設し
て一定期間養生することによつて、各隣接するコ
ンクリート床版本体14が連接される。
In this state, bolt 26 and nut 2
7, the concrete slab body 14 is attached to the steel girder 1.
Fixed at 2. Thereafter, by pouring a filler 60 such as cement mortar or concrete into the gap and curing it for a certain period of time, the adjacent concrete slab bodies 14 are connected.

なお、取付部材41は、第8図に示されるよう
に抜止部16およびジベル19だけがコンクリー
ト床版本体14に埋設するような構成であつても
よい。
Note that the mounting member 41 may be configured such that only the retaining portion 16 and the dovetail 19 are buried in the concrete slab body 14, as shown in FIG.

前述の実施例では、橋梁の鋼桁12に取付けら
れるプレキヤストコンクリート床版13,40に
ついて説明したけれども、ビルデイングなどの床
にも本考案に従うプレキヤストコンクリート床版
13,40を好適に実施することができる。
In the above embodiment, the precast concrete deck slabs 13, 40 attached to the steel girder 12 of a bridge have been described, but the precast concrete deck slabs 13, 40 according to the present invention can also be suitably applied to floors of buildings, etc. I can do it.

効 果 以上のように本考案によれば、取付部材がコン
クリート床版本体の橋軸方向の端部に一体的に固
定され、この取付部材をボルトおよびナツトを用
いて鋼桁に連結するようにしたので、前記コンク
リート床版本体を含む取付部材と鋼桁とは着脱可
能であり、これによつて前記コンクリート床版本
体の交換時の交換作業を容易、かつ迅速に行うこ
とができ、交換作業の労力およびコストの低減を
図ることができるとともに、鋼桁上で隣接するプ
レキヤストコンクリート床版間の接合部を大きな
強度で鋼桁に連結することができる。また鋼桁上
には、相互に対向する取付部材の側面間およびコ
ンクリート床版本体の端面間にわたつて空隙が形
成され、この空隙に充填材を充填するようにした
ので、大きな付着面積で充填材と前記側面および
端面とを付着させることが可能となり、充填材と
側面および端面との間に隙間が生じることを可及
的に少なくすることができる。このようにして、
空隙内で充填材が確実に前記側面および端面に付
着するので、その空隙内の充填材が陥没したり欠
損してしまう恐れはなく、したがつてこのような
欠損および陥没に起因する路床の陥没を防止する
ことができ、路床表面を平坦に保つて車両の通行
などによる振動の発生を防ぐことができる。
Effects As described above, according to the present invention, the mounting member is integrally fixed to the end of the concrete deck body in the bridge axis direction, and this mounting member is connected to the steel girder using bolts and nuts. Therefore, the mounting members including the concrete slab body and the steel girder are removable, which makes it possible to easily and quickly perform the replacement work when replacing the concrete slab body. In addition, it is possible to reduce labor and costs, and to connect the joint between adjacent precast concrete slabs on the steel girder with great strength. In addition, gaps are formed on the steel girder between the sides of the mounting members that face each other and between the end faces of the concrete slab body, and this gap is filled with the filler material, so it is filled with a large adhesion area. It becomes possible to attach the filling material to the side surface and the end surface, and it is possible to minimize the occurrence of gaps between the filler material and the side surface and the end surface. In this way,
Since the filler material reliably adheres to the side surfaces and end faces within the void, there is no risk that the filler material within the void will cave in or be lost, and therefore the subgrade will not be damaged due to such defects or cave-ins. It is possible to prevent cave-ins, keep the roadbed surface flat, and prevent vibrations caused by vehicle traffic.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本考案の前提となる構成を示す正面
図、第2図は第1図の分解斜視図、第3図および
第4図はプレキヤストコンクリート床版13の製
造方法を説明するための図、第5図はプレキヤス
トコンクリート床版13の他の構成を示す断面
図、第6図はプレキヤストコンクリート床版13
のさらに他の構成を示す断面図、第7図は本考案
の一実施例の断面図、第8図は本考案の他の実施
例の断面図、第9図は典型的な先行技術を示す斜
視図である。 11……橋梁、12……鋼桁、13,40……
プレキヤストコンクリート床版、14……コンク
リート床版本体、15,41……取付部材、16
……抜止部、17……接合部、18……ウエブ、
19……ジベル、20,25……透孔、21……
補強材、26……ボルト、27……ナツト。
Fig. 1 is a front view showing the configuration that is the premise of the present invention, Fig. 2 is an exploded perspective view of Fig. 1, and Figs. 5 is a sectional view showing another configuration of the precast concrete floor slab 13, and FIG. 6 is a sectional view of the precast concrete floor slab 13.
FIG. 7 is a cross-sectional view of one embodiment of the present invention, FIG. 8 is a cross-sectional view of another embodiment of the present invention, and FIG. 9 is a typical prior art. FIG. 11...Bridge, 12...Steel girder, 13,40...
Precast concrete floor slab, 14...Concrete floor slab body, 15, 41...Mounting member, 16
...Keeping part, 17...Joint part, 18...Web,
19... Jibel, 20, 25... Through hole, 21...
Reinforcement material, 26...bolt, 27...nut.

Claims (1)

【実用新案登録請求の範囲】 上フランジ22と、下フランジ23と、各フラ
ンジ22,23を連結する腹板24とを有し、前
記上フランジ22には橋軸方向に間隔をあけて複
数の第1透孔25が、前記腹板24を含む仮想平
面に関して両側に形成され、橋軸直角方向に間隔
をあけて橋軸方向に延びる複数の鋼桁12と、 複数のスタツドジベル19が固定される抜止部
16と、接合部17と、抜止部16および接合部
17を連結するウエブ18とを有し、前記接合部
17には、前記上フランジ22に形成される第1
透孔25に対応して複数の第2透孔20が形成さ
れる軸直角断面が略C字状の取付部材41と、 橋軸方向の端部に少なくとも前記抜止部16が
埋設されて一体的に固定され、前記ウエブ18の
側面18aと同一平面内に端面14aが形成され
る平板状のコンクリート床版本体14と、 前記鋼桁12の上フランジ22上に前記取付部
材41の接合部17が乗載された状態で、第1お
よび第2透孔25,20に挿通されるボルト26
およびこのボルト26に螺着されるナツト27
と、 鋼桁12上で相互に対向する前記各側面18a
間と各端面14a間とにわたつて形成される空隙
に充填される充填材60とを含むことを特徴とす
るプレキヤストコンクリート床版の取付け部の構
造。
[Claims for Utility Model Registration] It has an upper flange 22, a lower flange 23, and a belly plate 24 that connects the flanges 22 and 23, and the upper flange 22 has a plurality of holes spaced apart from each other in the bridge axis direction. First through holes 25 are formed on both sides of the virtual plane including the belly plate 24, and a plurality of steel girders 12 extending in the bridge axis direction at intervals perpendicular to the bridge axis and a plurality of stud dowels 19 are fixed. It has a retaining part 16, a joint part 17, and a web 18 connecting the retaining part 16 and the joint part 17.
A mounting member 41 having a substantially C-shaped cross section perpendicular to the axis, in which a plurality of second through holes 20 are formed corresponding to the through holes 25, and at least the retaining portion 16 is embedded in the end portion in the bridge axis direction, and are integrally formed. A flat concrete slab main body 14 is fixed to the main body 14 and has an end surface 14a formed in the same plane as the side surface 18a of the web 18, and a joint 17 of the mounting member 41 is mounted on the upper flange 22 of the steel girder 12. The bolt 26 is inserted into the first and second through holes 25 and 20 while being mounted on the vehicle.
and a nut 27 screwed onto this bolt 26
and each side surface 18a facing each other on the steel girder 12.
A structure of an attachment part of a precast concrete floor slab, characterized in that it includes a filler 60 filled in a gap formed between the gap and between each end face 14a.
JP1985083239U 1985-05-31 1985-05-31 Expired JPH0449210Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1985083239U JPH0449210Y2 (en) 1985-05-31 1985-05-31

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1985083239U JPH0449210Y2 (en) 1985-05-31 1985-05-31

Publications (2)

Publication Number Publication Date
JPS61198312U JPS61198312U (en) 1986-12-11
JPH0449210Y2 true JPH0449210Y2 (en) 1992-11-19

Family

ID=30631684

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1985083239U Expired JPH0449210Y2 (en) 1985-05-31 1985-05-31

Country Status (1)

Country Link
JP (1) JPH0449210Y2 (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2556386B2 (en) * 1989-12-29 1996-11-20 インターナショナル ビルディング システムズ インコーポレーテド Steel studs and precast panels
KR20030094767A (en) * 2002-06-07 2003-12-18 심창수 Composite Bridge having Easy Replacing Shear Connection Structure and Constructing Method thereof
KR100519234B1 (en) * 2002-11-22 2005-10-06 한국건설기술연구원 joint structure of precast bridge slab and girder and bridge construction method using the same
JP4526989B2 (en) * 2005-03-25 2010-08-18 大和ハウス工業株式会社 Floor forming method and floor forming structure
JP4517950B2 (en) * 2005-06-16 2010-08-04 積水ハウス株式会社 Slab panel and floor structure
KR100791991B1 (en) 2006-02-16 2008-01-04 김선기 Temporary bridge consruction method using composite slab girder
KR100758878B1 (en) 2006-08-30 2007-09-19 중앙대학교 산학협력단 Method for repairing bridge using integrated girder-concrete slab assembly
KR101037478B1 (en) 2009-06-12 2011-05-26 고려대학교 산학협력단 Partially embedded composite slab
JP2012077585A (en) * 2010-10-06 2012-04-19 Kajima Corp Structure for reinforcing end of beam
JP6198576B2 (en) * 2013-10-31 2017-09-20 大成建設株式会社 Junction structure
JP7322354B2 (en) * 2019-02-27 2023-08-08 株式会社竹中工務店 Track berth structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS425727Y1 (en) * 1964-08-21 1967-03-22

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS425727Y1 (en) * 1964-08-21 1967-03-22

Also Published As

Publication number Publication date
JPS61198312U (en) 1986-12-11

Similar Documents

Publication Publication Date Title
US5311629A (en) Deck replacement system with improved haunch lock
JPH0449210Y2 (en)
CN108755405B (en) Assembly type steel plate bridge deck continuous structure and construction method
JP2012082622A (en) Construction method of bridge floor slab and joint structure of precast floor slab
JP2872346B2 (en) Prefab slab installation method
KR101107826B1 (en) Slab-type box girder made by precast concrete and method constructing the bridge therewith
JPH07102528A (en) Precast balustrade, and method for connecting precast balustrade to slab
KR20040105446A (en) Structures and Methods for Connection between Precast Decks and Prestressed Concrete Girders
JP2750556B2 (en) Manufacturing method of prestressed concrete girder
JP2001026909A (en) Connection structure of floor slab using three- dimensional truss with concrete form in bridge girder
JPH0971907A (en) Precast concrete girder for composite floor slab bridge
JP3322637B2 (en) Construction method of cast-in-place concrete slab of bridge
JPH0475322B2 (en)
JP3450054B2 (en) Installation method of floor slab on bridge girder and slab cradle
CN209741665U (en) Continuous structure of bridge floor shears
JP3406383B2 (en) Subgrade ground covering construction method
CN113293698A (en) Highway bridge multi-joint expansion device and installation method thereof
JP2001164504A (en) Repair execution method of joint section for viaduct
JP2861219B2 (en) Bridge deck repair steel slab and its mounting method
JPH0642039A (en) Joining method of end of precast concrete beam to precast concrete girder, and joining construction thereof
JPH022738Y2 (en)
JPH023843B2 (en)
KR100195786B1 (en) Coupling structure between existing concrete girder and steel beam, and executing method of it
JPH09273117A (en) Joint construction of floor slab
CN216947837U (en) Highway bridge multislice telescoping device