JPS6314906A - Construction method for re-covering bridge concrete floor panel - Google Patents

Construction method for re-covering bridge concrete floor panel

Info

Publication number
JPS6314906A
JPS6314906A JP15756486A JP15756486A JPS6314906A JP S6314906 A JPS6314906 A JP S6314906A JP 15756486 A JP15756486 A JP 15756486A JP 15756486 A JP15756486 A JP 15756486A JP S6314906 A JPS6314906 A JP S6314906A
Authority
JP
Japan
Prior art keywords
main girder
liner
slab
steel deck
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15756486A
Other languages
Japanese (ja)
Other versions
JPH0680244B2 (en
Inventor
守 杉崎
和夫 橋本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP15756486A priority Critical patent/JPH0680244B2/en
Publication of JPS6314906A publication Critical patent/JPS6314906A/en
Publication of JPH0680244B2 publication Critical patent/JPH0680244B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は補修が必要となった橋梁コンクリート床版の張
替工法に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method for replacing bridge concrete deck slabs that require repair.

[従来の技術] 近年、重車両の増加等により橋梁鉄筋コンクリート床版
の老朽化か一段と進み、近い将来大量の鉄筋コンクリー
ト床版の張替えが必要とされている。
[Prior Art] In recent years, reinforced concrete deck slabs of bridges have become increasingly obsolete due to the increase in the number of heavy vehicles, and a large number of reinforced concrete deck slabs will need to be replaced in the near future.

従来、こうした張替えの必要が生じた場合は、第2図に
示す如く、主桁aのフランジa°上にジベルbを介して
一体に固定され且つ上面にアスファルトCを敷設された
鉄筋コンクリート床版dにおいて、まず、前記アスファ
ルトC及び鉄筋コンクリート床版dをエアーガウジング
或いはコアブレーカにより解体除去した後、従来の鉄筋
コンクリート床版の建設と同様に配筋し型枠を組んでコ
ンクリートを打設することにより第2図の状態に復旧さ
せるようにしている。
Conventionally, when the need for such resurfacing arose, as shown in Fig. 2, a reinforced concrete slab d was fixed integrally onto the flange a of the main girder a via a dowel b, and had asphalt C laid on the top surface. First, the asphalt C and the reinforced concrete slab d are dismantled and removed by air gouging or a core breaker, and then reinforcement is placed, formwork is constructed, and concrete is poured in the same manner as in the construction of conventional reinforced concrete slabs. I am trying to restore it to the state shown in Figure 2.

しかし上記従来方式においては、鉄筋コンクリート床版
を張替える際、再び鉄筋コンクリート床版を構成するよ
うにしているため、配筋、型枠の設置、足場の建設等多
大の現場作業が生じると共に、多大のコンクリート打設
量とその養生とにより非常に長い工期を要してしまう。
However, in the conventional method described above, when replacing the reinforced concrete slab, the reinforced concrete slab is constructed again, which requires a large amount of on-site work such as reinforcing, installing formwork, and constructing scaffolding. This requires a very long construction period due to the amount of concrete poured and its curing.

このように鉄筋コンクリート床版の張替えに長時間を要
することは、その間交通を遮断してしまうことになるの
で、近年の交通事情から重要な問題となっている。
The long time it takes to replace reinforced concrete slabs in this way means that traffic is blocked during that time, which has become an important problem in light of recent traffic conditions.

このため、前記したように、鉄筋コンクリート床版dを
解体除去した後、主桁aのフランジa°上に、第3図に
示すように鋼床版Cをボルトf等にて固定することによ
り、主桁a上に直接連結して鋼床版eにより張替えを行
うことが考えられている。
For this reason, as described above, after dismantling and removing the reinforced concrete deck slab d, the steel deck slab C is fixed onto the flange a° of the main girder a with bolts f, etc., as shown in Fig. 3. It is being considered to connect directly to the main girder a and re-clad it using a steel deck e.

[発明が解決しようとする問題点コ しかしこの方式においても、作業の邪魔になるフランジ
a°上の多数の既存ジベルb(第2図参照)を除去する
必要があり、しかも主桁aのフランジa°と新規鋼床版
eとを精密に位置合わせし現場調整することが大変であ
り(ボルト孔の位置ずれ及び孔数の問題)、更に上記操
作に起因して工期が延長されるといった問題を有してい
た。
[Problems to be solved by the invention] However, even in this method, it is necessary to remove the many existing dowels b (see Fig. 2) on the flange a° that obstruct work, and in addition, the flange of the main girder a It is difficult to precisely align and adjust the position of the new steel deck slab e on site (problems with bolt hole misalignment and number of holes), and the construction period is extended due to the above operations. It had

本発明はこうした実情に鑑み、コンクリート床版から鋼
床版に容易にしかも短期間に張替えられるようにしたも
のである。
In view of these circumstances, the present invention is designed to allow concrete deck slabs to be easily replaced with steel deck slabs in a short period of time.

[問題点を解決するための手段] 本発明では、コンクリート床版を除去した後に主桁フラ
ンジ上に残されたジベルの要所を完全処理すると共に他
の部分を簡易処理し、完全処理部にはライナを又簡易処
理部にはアスファルトフェルトを配置し、更にこれらラ
イナ及びアスファルトフェルト上に鋼床版を設置し、該
鋼床版と主桁フランジとをライナを介してボルトにより
連結し一体化するようにしている。
[Means for solving the problem] In the present invention, after removing the concrete slab, the key points of the dowel left on the main girder flange are completely treated, other parts are simply treated, and the fully treated part is A liner is placed and asphalt felt is placed in the simple treatment section, and a steel deck slab is installed on these liners and asphalt felt, and the steel deck slab and main girder flange are connected with bolts through the liner and integrated. I try to do that.

[作   用] 従って、アスファルトフェルトにより簡易処理部のジベ
ルの凹凸が平滑化され、アスファルトフェルト配置によ
る段差がライナにより均一化される。
[Function] Therefore, the asphalt felt smoothes the irregularities of the dowel in the simple treatment section, and the liner equalizes the level difference due to the asphalt felt arrangement.

[実 施 例] 以下、図面を参照して本発明の詳細な説明する。[Example] Hereinafter, the present invention will be described in detail with reference to the drawings.

第1図において1は鉄筋コンクリート床版を解体除去し
た後の主桁であり、本発明では、主桁フランジ1°上の
ジベル2を要所たけ完全に処理して完全処理部3を形成
し、一方他の部分のジベル2は例えばガス切断程度の簡
単な処理を行って簡易処理部4とする。
In Fig. 1, 1 is the main girder after the reinforced concrete slab has been dismantled and removed, and in the present invention, the dowel 2 1° above the main girder flange is completely treated to a required extent to form a completely treated part 3, On the other hand, other parts of the dowel 2 are subjected to simple processing such as gas cutting to form a simple processing section 4.

簡易処理部4にはアスファルトフェルト5を配置して切
断後のジベル2による凹凸を吸収させ、完全処理部3に
は、アスファルトフェルト5による段差を無くすようラ
イナ7を配置し、而して新床版である鋼床版8をこれら
ライナ7及びアスファルトフェルト5を介して主桁フラ
ンジ1゛上に載置し、予め合致するよう穿設しておいた
鋼床版8のボルト孔9、ライナ7のボルト孔10、主桁
フランジ1゛における完全処理部3のボルト孔11にハ
イテンションボルト12を通して締付けることにより、
鋼床版8と主桁1とを一体化する。尚、6は鋼床版8上
のアスファルト舗装である。
Asphalt felt 5 is placed in the simple treatment section 4 to absorb the unevenness caused by the dowel 2 after cutting, and a liner 7 is placed in the complete treatment section 3 to eliminate the level difference caused by the asphalt felt 5, thereby creating a new floor. A steel deck slab 8, which is a plate, is placed on the main girder flange 1'' via the liner 7 and the asphalt felt 5, and the bolt holes 9 of the steel deck slab 8, which have been drilled in advance to match, and the liner 7 are placed on the main girder flange 1''. By passing the high tension bolts 12 through the bolt holes 10 of the main girder flange 1 and the bolt holes 11 of the fully processed part 3 of the main girder flange 1,
The steel deck slab 8 and the main girder 1 are integrated. In addition, 6 is asphalt pavement on the steel deck slab 8.

前記において、ハイテンションボルト12を締付けるこ
とによって、簡易処理部4上に残存するジベル2はアス
ファルトフェルト5内に埋込まれ、アスファルトフェル
ト5によって被い隠される。又このことにより残存する
ジベル2に対しての防蝕加工を施したことにもなり、更
に鋼床版8からの振動の伝達が遮断され騒音の発生が防
止される。
In the above, by tightening the high tension bolt 12, the dowel 2 remaining on the simple treatment section 4 is embedded in the asphalt felt 5 and is covered by the asphalt felt 5. Moreover, this also means that the remaining dowel 2 is subjected to corrosion-proofing, and furthermore, the transmission of vibration from the steel deck slab 8 is blocked, and the generation of noise is prevented.

尚、本発明は前記実施例にのみ限定されるものではなく
、本発明の要旨を逸脱しない限り種々変更を加え得るこ
とは勿論である。
It should be noted that the present invention is not limited to the above embodiments, and it goes without saying that various changes can be made without departing from the gist of the present invention.

[発明の効果] 以上説明したように、本発明の橋梁コンクリート床版の
張替工法によれば、主桁フランジ上ノ総てのジベルを除
去する必要がないので、容易にしかも短期間に張替作業
を行うことかできる、と言う優れた効果を奏し得る。
[Effects of the Invention] As explained above, according to the bridge concrete deck resurfacing method of the present invention, there is no need to remove all the dowels on the main girder flange, so resurfacing can be done easily and in a short period of time. This has the excellent effect of making it possible to carry out replacement work.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例を示す説明図、第2図は従来
の張替工法の一般的な例を説明するための概略図、第3
図は鋼床版による従来の張替工法の例を示す説明図であ
る。 1は主桁、loはフランジ、2はジベル、3は完全処理
部、4は簡易処理部、5はアスフフルトフエルト、7は
ライナ、8は鋼床版、12はノ\イテンションボルトを
示す。
Fig. 1 is an explanatory diagram showing one embodiment of the present invention, Fig. 2 is a schematic diagram illustrating a general example of the conventional reupholstery method, and Fig. 3 is an explanatory diagram showing an embodiment of the present invention.
The figure is an explanatory diagram showing an example of a conventional recladding method using steel deck slabs. 1 is the main girder, lo is the flange, 2 is the dowel, 3 is the fully processed part, 4 is the simple processed part, 5 is the asphalt felt, 7 is the liner, 8 is the steel deck, and 12 is the tension bolt. .

Claims (1)

【特許請求の範囲】[Claims] 1)コンクリート床版を除去した後に主桁フランジ上に
残されたジベルの要所を完全処理すると共に他の部分を
簡易処理し、完全処理部にはライナを又簡易処理部には
アスファルトフェルトを配置し、更にこれらライナ及び
アスファルトフェルト上に鋼床版を設置し、該鋼床版と
主桁フランジとをライナを介してボルトにより連結し一
体化することを特徴とする橋梁コンクリート床版の張替
工法。
1) After removing the concrete slab, the key points of the dowel left on the main girder flange were completely treated, and other parts were lightly treated, with liner being applied to the fully treated area and asphalt felt to the lightly treated area. A bridge concrete deck tensioning method characterized in that a steel deck slab is installed on the liner and asphalt felt, and the steel deck and main girder flange are connected and integrated with bolts via the liner. Alternative method.
JP15756486A 1986-07-04 1986-07-04 Bridge concrete floor slab replacement method Expired - Lifetime JPH0680244B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15756486A JPH0680244B2 (en) 1986-07-04 1986-07-04 Bridge concrete floor slab replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15756486A JPH0680244B2 (en) 1986-07-04 1986-07-04 Bridge concrete floor slab replacement method

Publications (2)

Publication Number Publication Date
JPS6314906A true JPS6314906A (en) 1988-01-22
JPH0680244B2 JPH0680244B2 (en) 1994-10-12

Family

ID=15652437

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15756486A Expired - Lifetime JPH0680244B2 (en) 1986-07-04 1986-07-04 Bridge concrete floor slab replacement method

Country Status (1)

Country Link
JP (1) JPH0680244B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007278530A (en) * 2006-04-03 2007-10-25 Matsushita Electric Ind Co Ltd High-frequency heating device
JP2018059312A (en) * 2016-10-04 2018-04-12 Jfeエンジニアリング株式会社 Connecting structure between newly constructed steel floor slab and existing girder
JP2020012275A (en) * 2018-07-17 2020-01-23 佐藤鉄工株式会社 Floor slab removal method and rail fixture
JP2021046767A (en) * 2019-09-20 2021-03-25 株式会社横河ブリッジ Existing floor slab replacing method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007278530A (en) * 2006-04-03 2007-10-25 Matsushita Electric Ind Co Ltd High-frequency heating device
JP2018059312A (en) * 2016-10-04 2018-04-12 Jfeエンジニアリング株式会社 Connecting structure between newly constructed steel floor slab and existing girder
JP2020012275A (en) * 2018-07-17 2020-01-23 佐藤鉄工株式会社 Floor slab removal method and rail fixture
JP2021046767A (en) * 2019-09-20 2021-03-25 株式会社横河ブリッジ Existing floor slab replacing method

Also Published As

Publication number Publication date
JPH0680244B2 (en) 1994-10-12

Similar Documents

Publication Publication Date Title
US6237856B1 (en) Method for installing a steady rail track
KR101254043B1 (en) Replacement method for post-placing concrete of expansion joint
JP6074378B2 (en) Expansion device replacement method and temporary lining plate structure
JPS6314906A (en) Construction method for re-covering bridge concrete floor panel
JPH0115647B2 (en)
JPH022738Y2 (en)
KR20020082728A (en) Process and frame for substituting steel girder of a railway bridge for concrete slab
JPS6245804A (en) Re-covering of bridge reinforced concrete
JPS6059209A (en) Replacing method of bridge reinforced concrete floor panel
JP2000017618A (en) Replacement method of concrete bridge to steel bridge
JP2861219B2 (en) Bridge deck repair steel slab and its mounting method
JPH108429A (en) Structure of concrete protection fence and construction method therefor
JP2003082617A (en) Reinforcing structure of bridge structure and method for repairing bridge structure
KR100729842B1 (en) Repair work of railroad bridge and that structure
KR100603905B1 (en) Girder bridge make use of general girder and that construction method
JP2020186614A (en) Precast floor slab connection part structure and connection part construction method
KR20200134406A (en) An expansion joint
KR200240457Y1 (en) Frame for substitu ting steel girder of a railway bridge for concrete slab
JP2019206902A (en) Bridge structure and floor slab replacing method
KR100729844B1 (en) Repair work of railroad bridge and that structure
JPS62197507A (en) Construction of bridge steel floor panel
JP3434891B2 (en) Subbase end structure
JP3008040B2 (en) Large span composite slab erection method
JP2004150016A (en) Floor repair method and floor structure
KR200205091Y1 (en) Prefabricated deck panel for bridge

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term