JPS5824024A - Backfilling work for empty portion of in-place pile - Google Patents

Backfilling work for empty portion of in-place pile

Info

Publication number
JPS5824024A
JPS5824024A JP12188281A JP12188281A JPS5824024A JP S5824024 A JPS5824024 A JP S5824024A JP 12188281 A JP12188281 A JP 12188281A JP 12188281 A JP12188281 A JP 12188281A JP S5824024 A JPS5824024 A JP S5824024A
Authority
JP
Japan
Prior art keywords
empty portion
place pile
backfilling
ground
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12188281A
Other languages
Japanese (ja)
Inventor
Daizo Kida
喜田 大三
Yuji Saito
斉藤 裕司
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ohbayashi Gumi Ltd
Obayashi Gumi Ltd
Original Assignee
Ohbayashi Gumi Ltd
Obayashi Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ohbayashi Gumi Ltd, Obayashi Gumi Ltd filed Critical Ohbayashi Gumi Ltd
Priority to JP12188281A priority Critical patent/JPS5824024A/en
Publication of JPS5824024A publication Critical patent/JPS5824024A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To ensure the passive earth pressure of soil and sand backfilling in the empty portion of in-place pile by a method in which a curable mud water is charged into the empty portion and then backfilling material, e.g., excavated soil, etc., is packed in the empty portion. CONSTITUTION:A curable mud water 3 composed of about 5-10% bentonite and about 10-20% a hardening agent, e.g., ordinary or slag cement, etc., is charged into the impty portion 2 from the upper end to the ground of an in-place pile, and then a backfilling material 4, e.g., excavated soil, etc., is packed into the empty portion to the ground level. In the empty portion 2 filled with the solidified mixture of the curable mud water 3 and the embedding material 4, sufficient passive earth pressure can be expected because no deformation and settlement occur in the peripheral area of the pile 1 owing to its higher strength than the surrounding ground.

Description

【発明の詳細な説明】 本発明は場所打ち杭の空打ち部分の埋戻し工法に関する
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for backfilling the blank portion of a cast-in-place pile.

軟弱な土層が厚く堆積する地盤に、地下部を含む構造物
を建造する場合、支持層まで到達する杭を打設して構造
物を支持させるのが一般的である。
When building a structure that includes an underground section on ground where a thick layer of soft soil has accumulated, it is common to support the structure by driving piles that reach the support layer.

杭として、地上から施工する場所打ち杭を採用する場合
、打設コンクリートは構造物の基礎底面刊近で打止めさ
れる。そして、コンクリートを打設しない基礎底面から
上部、すなわち空打ち部分は土砂などで埋戻されていた
When using cast-in-place piles that are constructed from the ground, the poured concrete is stopped near the bottom of the structure's foundation. The area from the bottom to the top of the foundation where no concrete was poured, that is, the blank area, was backfilled with earth and sand.

しかしながら、埋戻し土砂は十分に締固まることが不可
能で、乱された非常にゆるい状態であるため周囲地山に
較べて強度が著しく小さく、受動土庄を見込むことがで
きなかった。そのため、埋戻しを行わない部分の比率が
多いと、場所打ち杭工事に先行して施工した山留壁に、
掘削工事を始める以前に変形が起るなどのトラブルが多
々あった。
However, the backfill earth and sand could not be sufficiently compacted and was disturbed and extremely loose, so its strength was significantly lower than that of the surrounding ground, and it was not possible to expect a passive earth shoal. Therefore, if there is a large proportion of areas that are not backfilled, retaining walls constructed prior to cast-in-place pile construction may
Before excavation work began, there were many problems such as deformation.

本発明の目的は、上記欠点を解消するために場所打ち杭
の空打ち部分に埋戻した土砂に受動土庄をみこめるよう
にすることにある。
SUMMARY OF THE INVENTION In order to eliminate the above-mentioned drawbacks, it is an object of the present invention to allow passive soil to be incorporated into the earth and sand backfilled into the blank part of a cast-in-place pile.

以下、本発明の実施例を図面に従って説明する。Embodiments of the present invention will be described below with reference to the drawings.

lはアースドリルなどの適宜の掘削機で掘削した掘削孔
にコンクリートを打設して製した場所打ち杭である。該
場所打ち杭/の上端から地盤面までの空打ち部分ユには
、まず、ベントナイトs〜ノθ%、普通セメントあるい
は高炉セメントなどの硬化剤10〜.20%から成る硬
化性泥水3が化上部から所定量投入され、ついで掘削土
等の埋立材料グが化上部から投入され、地盤面まで埋戻
される。そして、掘削土等の埋戻し材料グ中の間隙には
硬化性泥水3で充満され、時間の経過とともに空打ち部
分ス内の硬化性泥水3と埋戻し材料グとが一体となって
固結する。
1 is a cast-in-place pile made by pouring concrete into a hole drilled with a suitable excavator such as an earth drill. The cast-in-place pile/dry part from the upper end to the ground surface is first coated with bentonite s to θ% and a hardening agent such as ordinary cement or blast furnace cement. A predetermined amount of hardening mud 3 consisting of 20% is poured from the upper part of the keratin, and then reclamation material such as excavated soil is thrown in from the upper part and backfilled to the ground level. Then, the gaps in the backfill material such as excavated soil are filled with hardening mud 3, and over time, the harden mud 3 in the blank space and the backfill material solidify as one. do.

これに代えて、地上であらかじめ硬化性泥水3と埋戻し
材料グを攪拌混合したものを空打ち部分−に投入充填し
てもよい。
Alternatively, the hardening mud 3 and the backfilling material may be stirred and mixed in advance on the ground and then charged into the blank part.

次表は硬化性泥水に埋戻し材料を混合した場合の固結体
の一軸圧縮強度を示す。これによれば、固結体は材令グ
週(2g日)でス〜lυ強度を示し、周囲地山(03〜
Zθ贅)以上の強度を有し、十分に受動土庄をみこめる
ことが確認された。
The following table shows the unconfined compressive strength of the solidified material when backfilling material is mixed with hardening mud. According to this, the solidified material shows a strength of lυ in the age of 3 weeks (2 g days), and the surrounding ground (03 to
It was confirmed that the strength was greater than Zθ, and that it was able to fully accommodate the passive tosho.

ない場合は、空打ち部分全体を硬化性泥水のみで充填固
結させたり、あるいは空打ち部分の掘削用泥水中に硬化
剤を混入して、硬化性泥水に変換して固結させることも
熱論可能である。
If this is not available, it is also a hot idea to fill and solidify the entire dry-shot area with hardening mud, or to mix a hardening agent into the drilling mud in the dry-shot area to convert it into hardenable mud and solidify it. It is possible.

本発明になる場所打ち杭の空打ち部分の埋戻し工法は、
上記のような過程によって施工゛されると、硬化性泥水
と掘削土等の埋戻し材料の混合固結体から成る空打ち部
分は周辺地山より強度を有して、杭周辺の地盤に変形・
沈下を与えることがないので、十分に受動土圧をみこめ
ることかでき、また、その混合固結体は低強度であるの
で、杭工事終了後、地下掘削工事が折り工事を伴うこと
なく円滑に進行できる利点も有する。
The method of backfilling the blank portion of cast-in-place piles according to the present invention is as follows:
When the pile is constructed using the above process, the hollow cast part, which is made of a solidified mixture of hardening mud and backfill materials such as excavated soil, has stronger strength than the surrounding ground and deforms into the ground around the pile.・
Since there is no subsidence, passive earth pressure can be fully accommodated, and the mixed solidity has low strength, so underground excavation work can be carried out smoothly without folding after the pile work is completed. It also has the advantage of allowing progress.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係る場所打ち杭の空打ち部分の埋戻し
工法の縦断面図である。
FIG. 1 is a longitudinal cross-sectional view of a method of backfilling the blank portion of a cast-in-place pile according to the present invention.

Claims (1)

【特許請求の範囲】[Claims] 場所打ち杭の空打ち部分に硬化性泥水を投入し、ついで
掘削土等の埋戻し材料を埋戻すことを特徴とする場所打
ち杭の空打ち部分の埋戻し工法。
A method for backfilling the hollow part of a cast-in-place pile, characterized by pouring hardening mud into the hollow part of the cast-in-place pile, and then backfilling with backfilling material such as excavated soil.
JP12188281A 1981-08-05 1981-08-05 Backfilling work for empty portion of in-place pile Pending JPS5824024A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12188281A JPS5824024A (en) 1981-08-05 1981-08-05 Backfilling work for empty portion of in-place pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12188281A JPS5824024A (en) 1981-08-05 1981-08-05 Backfilling work for empty portion of in-place pile

Publications (1)

Publication Number Publication Date
JPS5824024A true JPS5824024A (en) 1983-02-12

Family

ID=14822247

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12188281A Pending JPS5824024A (en) 1981-08-05 1981-08-05 Backfilling work for empty portion of in-place pile

Country Status (1)

Country Link
JP (1) JPS5824024A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111646742A (en) * 2020-06-30 2020-09-11 建平县万兴膨润土有限责任公司 Filling and curing slurry for horizontal directional drilling and preparation method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57100217A (en) * 1980-12-12 1982-06-22 Shimizu Constr Co Ltd Refilling work for vacant area of concrete pile driven in site

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57100217A (en) * 1980-12-12 1982-06-22 Shimizu Constr Co Ltd Refilling work for vacant area of concrete pile driven in site

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111646742A (en) * 2020-06-30 2020-09-11 建平县万兴膨润土有限责任公司 Filling and curing slurry for horizontal directional drilling and preparation method thereof

Similar Documents

Publication Publication Date Title
JP3669247B2 (en) Anchor anchor method for soft sandy ground
JPS5824024A (en) Backfilling work for empty portion of in-place pile
CN108149707A (en) A kind of basement building structure and its construction method
JPH06228947A (en) Construction of landslide protection wall in ground filled up with wastes
JPH05106222A (en) Embedding method for wooden pile
JPH0571730B2 (en)
JP4057873B2 (en) Foundation pile structure on support ground and construction method of foundation pile
JPS63315724A (en) Execution work of cast-in-place concrete pile with high yield strength
SU829785A1 (en) Method of making pits in sandy soils
JP3099040B2 (en) Embankment culvert
JP4080305B2 (en) Construction method of foundation using slag having expansibility and solidification
JPS57108328A (en) Formation of basement
JP3335593B2 (en) Underground structure construction structure
JP2797066B2 (en) Solid foundation method with stabilizer
JP3030622B2 (en) How to build a tunnel
SU945284A1 (en) Method of constructing cast-in-place pile
JP2003293354A (en) Execution method of foundation ground
JP2003221825A (en) Work execution method for foundation ground
JP2711029B2 (en) Soil improvement method of pile formation hollow moat
JPS62174415A (en) Formation of in-situ pile
JP4118694B2 (en) Ground improvement method
JP2000178983A (en) Foundation construction method
JPS6240488B2 (en)
JPH0639774B2 (en) Reinforcement method for residential land
JP2004197474A (en) Vibration isolation banking structure