JPS56111722A - Driving method for steel-pipe pile - Google Patents
Driving method for steel-pipe pileInfo
- Publication number
- JPS56111722A JPS56111722A JP1463280A JP1463280A JPS56111722A JP S56111722 A JPS56111722 A JP S56111722A JP 1463280 A JP1463280 A JP 1463280A JP 1463280 A JP1463280 A JP 1463280A JP S56111722 A JPS56111722 A JP S56111722A
- Authority
- JP
- Japan
- Prior art keywords
- steel
- pipe pile
- pile
- monkey
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
PURPOSE: To eliminate public pollytions such as vibrations and noises and to settle the steel-pipe pile surely in a support layer by inserting into a vertical hole the steel- pipe pile provided in one body with a beam material supporting a shock load and by giving the shock load to the beam material by means of a monkey and the like.
CONSTITUTION: A plurality of beam materials 4 are stretched inside a cap 3 at the tip part of the steel-pipe P whose tip is closed and in the center thereof a receiver 6 for the monkey 5 is formed. A vertical longitudinal hole 2 is excavated in the ground 1 in which the pile is struck by means of an earth auger, etc. and then the steel-pipe pile P suspended by a crane is inserted into the excavated lingitudinal hole 2. And, the shock loas being given to the receiver 6 by the monkey 5 and the like and the pile P is sunk until it reaches the support layer. Next, proper grout of setting property such as cement mortar is filled up between the steel-pipe pile and the longitudinal hole and solidified.
COPYRIGHT: (C)1981,JPO&Japio
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1463280A JPS56111722A (en) | 1980-02-08 | 1980-02-08 | Driving method for steel-pipe pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1463280A JPS56111722A (en) | 1980-02-08 | 1980-02-08 | Driving method for steel-pipe pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS56111722A true JPS56111722A (en) | 1981-09-03 |
Family
ID=11866563
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1463280A Pending JPS56111722A (en) | 1980-02-08 | 1980-02-08 | Driving method for steel-pipe pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS56111722A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02279820A (en) * | 1989-01-11 | 1990-11-15 | Toshio Enoki | Method of laying pile |
-
1980
- 1980-02-08 JP JP1463280A patent/JPS56111722A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02279820A (en) * | 1989-01-11 | 1990-11-15 | Toshio Enoki | Method of laying pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE3269698D1 (en) | Foundation for a pole, a pillar or the like | |
SU946409A3 (en) | Method for driving lower ends of sheet piles into base soil in erecting sheet piling wall | |
JPS56111722A (en) | Driving method for steel-pipe pile | |
GB1308209A (en) | Method and apparatus for setting anchors in soil or rock | |
JPS5545960A (en) | Method of engineering embedded pile and device therefor | |
JPS5721622A (en) | Construction of large-diameter pile in site | |
RU2005190C1 (en) | Method of grappling anchor in rocks | |
JPS56111725A (en) | Constructing method for strip footing by using existing concrete pile | |
JPS57174527A (en) | Construction of underground pile | |
SU1652593A1 (en) | Method for fixing anchor in rocks | |
GB2008653A (en) | Method of Driving Sheet Piles into a Rock Substratum | |
ES8204790A1 (en) | Prestressed concrete support rod - has tube through which mortar is introduced to hold rod fast in soil | |
SU850801A1 (en) | Sagging soil compacting method | |
US3915231A (en) | Method for drilling through cavities during earth drilling operations | |
JPS641829A (en) | Construction foundation | |
JPS5532809A (en) | Pile foundation practice | |
RU1810554C (en) | Method for prevention of rock inrush into underground working | |
SU1615370A1 (en) | Method of supporting mine working by shotcreting | |
RU2052109C1 (en) | Method for sinking objects into rock | |
JPS5628942A (en) | Foundation structure of stationary crane | |
JPS5589526A (en) | Driving method for foundation pile | |
UA9599A (en) | Method for erection of basement | |
JPS56115418A (en) | Building of underground wall body | |
JPS57174530A (en) | Penetration of cylinder into ground | |
JPS5532812A (en) | Huge pole foundation practice |