JPH1161855A - Process for constructing underground space - Google Patents

Process for constructing underground space

Info

Publication number
JPH1161855A
JPH1161855A JP9214572A JP21457297A JPH1161855A JP H1161855 A JPH1161855 A JP H1161855A JP 9214572 A JP9214572 A JP 9214572A JP 21457297 A JP21457297 A JP 21457297A JP H1161855 A JPH1161855 A JP H1161855A
Authority
JP
Japan
Prior art keywords
concrete
steel
plate
iron
box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9214572A
Other languages
Japanese (ja)
Inventor
Kazuo Sasaki
和夫 佐々木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHIKA PLANNING KK
Obayashi Road Corp
Original Assignee
CHIKA PLANNING KK
Obayashi Road Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHIKA PLANNING KK, Obayashi Road Corp filed Critical CHIKA PLANNING KK
Priority to JP9214572A priority Critical patent/JPH1161855A/en
Publication of JPH1161855A publication Critical patent/JPH1161855A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a process of constructing an underground space, which is excellent in economical efficiency and workability by reducing labor and costs required for sheathing for protecting an excavated surface. SOLUTION: A steel box 11 composed of an inner steel sheet 13, an outer steel sheet 12, a widthwise opening stopping steel sheet 14 interposed between the steel sheets 13, 12 and having an opening 17 through which concrete can be placed, is continuously laid along an excavated surface so as to serve as sheathing material, and concrete is placed into the thus laid steel box 11 so as to form an integral underground concrete wall 21. Then, a floor slab 22 and a ceiling slab are formed being connected to the wall 21 so as to form an underground space.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、地下空間の構築
工法に関し、特に、地下室などの簡易な地下空間の構築
に適した地下空間の構築工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing an underground space, and more particularly to a method of constructing an underground space suitable for constructing a simple underground space such as a basement.

【0002】[0002]

【従来の技術】近年、敷地の高度利用の要請の高まりに
よって、特に地価の高い都市部等においては、地下室等
の地下空間を構築するための工事が増加しつつあり、個
人住宅の分野においても、その需要が増大している。
2. Description of the Related Art In recent years, construction for constructing underground spaces such as basements has been increasing in urban areas and the like where land prices are high, due to an increasing demand for advanced use of sites. , Its demand is increasing.

【0003】そして、このような地下空間は、特に個人
住宅の場合、狭い敷地内に安価かつ迅速に構築すること
が求められており、現場打ちコンクリート工法から、コ
ンクリート製や鋼製の部材を用いたプレハブ工法に、そ
の主流が移行しつつある。
[0003] Such an underground space, particularly in the case of a private house, is required to be constructed inexpensively and quickly in a narrow site, and the concrete and steel members are used instead of the cast-in-place concrete method. The mainstream is shifting to the prefabricated method.

【0004】また、これらの工法によれば、いずれも、
地盤を掘削し、掘削面を覆う土留材を設置して当該掘削
面を防護した後、型枠の組立やコンクリートの打設作
業、あるいはプレハブ部材の組立作業が行われることに
なるが、特に簡易な地下空間の場合、このような地盤の
掘削深さは、数m程度の浅いものであるため、土留材と
して、H鋼横矢板や軽量鋼矢板が使用されることにな
る。
[0004] Further, according to these construction methods,
After excavating the ground and installing earth retaining material covering the excavated surface to protect the excavated surface, work of assembling a formwork, placing concrete, or assembling a prefabricated member is performed. In the case of a natural underground space, the excavation depth of such a ground is as shallow as several meters, so that H steel horizontal sheet piles or lightweight steel sheet piles are used as soil retaining materials.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、上記従
来の地下空間の構築工法によれば、経済性や施工性の面
で改良の余地があり、特に、H鋼横矢板や軽量鋼矢板
は、仮設部材として用いられ、地下空間の完了後は撤去
されるべきものであるため、その設置作業や撤去作業の
手間や費用を軽減することが重要である。
However, according to the above-mentioned conventional underground space construction method, there is room for improvement in terms of economy and workability. Particularly, H steel horizontal sheet piles and lightweight steel sheet piles are temporarily installed. Since it is used as a member and should be removed after the completion of the underground space, it is important to reduce the labor and cost of installation and removal work.

【0006】そこで、この発明は、かかる従来の課題に
着目してなされたもので、掘削面を防護する土留作業に
要する手間や費用を軽減し、経済性や施工性に優れた地
下空間の構築工法を提供することを目的とするものであ
る。
Accordingly, the present invention has been made in view of such a conventional problem, and reduces the labor and cost required for earth retaining work for protecting an excavated surface, and constructs an underground space excellent in economy and workability. It is intended to provide a construction method.

【0007】[0007]

【課題を解決するための手段】この発明は、上記目的を
達成するためになされたもので、その要旨は、内側鉄板
と、外側鉄板と、これらの間に所定の間隔が保持される
ように介在する、コンクリートが流通可能な開口を有す
る幅止め用の板状鉄部材とからなる鉄箱を、掘削面に沿
って土留材として連続設置し、設置した鉄箱の内部にコ
ンクリートを打設して、前記掘削面を覆う一体化した鉄
コンクリート地下壁を形成し、しかる後に、前記鉄コン
クリート地下壁に接続して床スラブ及び天井スラブを形
成することを特徴とする地下空間の構築工法にある。
SUMMARY OF THE INVENTION The present invention has been made to achieve the above-mentioned object, and the gist of the invention is to provide an inner iron plate, an outer iron plate, and such that a predetermined distance is maintained between them. An iron box consisting of an interposed, plate-shaped iron member for width stop with an opening through which concrete can flow is continuously installed along the excavated surface as a retaining material, and concrete is poured into the installed iron box. Forming an integrated ferro-concrete underground wall covering the excavated surface, and thereafter connecting to the ferro-concrete underground wall to form a floor slab and a ceiling slab. .

【0008】そして、この発明の地下空間の構築工法に
よれば、掘削作業が終了した掘削面に沿って、予め工場
等において製作された鉄箱を建込んで設置する。
According to the method of constructing an underground space according to the present invention, an iron box manufactured in a factory or the like is erected and installed along the excavated surface on which the excavation operation has been completed.

【0009】ここで、鉄箱は、内側鉄板と、外側鉄板
と、幅止め用の板状鉄部材とからなり、この幅止め用の
板状鉄部材は、例えばエキスパンドメタルや、鉄板、連
続折曲げ鋼薄鉄板、山形鉄板、溝形鉄板等の板状ないし
は面状の鉄部材や鋼製部材に、コンクリートが流通可能
な大きさの穴を開口形成してなるもので、形成すべき鉄
コンクリート地下壁の厚さに相当する幅を備えていて、
これを縦方向に延長するように複数並行に配置すること
により、土圧や支保部材からの外圧、あるいは内部に打
設されたコンクリートによる内圧に耐えて、内側鉄板と
外側鉄板との間の間隔を強固に保持するように構成され
ている。
Here, the iron box comprises an inner iron plate, an outer iron plate, and a plate-like iron member for stopping the width. The plate-like iron member for stopping the width is made of, for example, an expanded metal, an iron plate, a continuous folding plate. Iron-concrete to be formed by forming a hole in a plate-like or planar iron member or steel member such as a bent steel thin plate, angle iron plate, channel iron plate, etc. It has a width equivalent to the thickness of the basement wall,
By arranging them in parallel so as to extend in the vertical direction, it can withstand the earth pressure, the external pressure from the support member, or the internal pressure due to the concrete cast inside, and the distance between the inner iron plate and the outer iron plate Is configured to be held firmly.

【0010】また、このような鉄箱の建込み作業は、各
種の建込み重機を使用して容易に行うことができるとと
もに、必要に応じてその底部を掘削地盤に押し込み、当
該鉄箱を所定の土留め位置にセットした後、例えばパイ
プサポート等の支保工材を用いて強固に固定する。
[0010] In addition, such a work of installing the iron box can be easily performed by using various types of heavy equipment, and if necessary, the bottom of the iron box is pushed into the excavated ground, and the iron box is put into a predetermined position. And then firmly fixed using a supporting material such as a pipe support, for example.

【0011】なお、隣接する鉄箱は、例えば内側鉄板や
外側鉄板の表面の接続部分に沿って継手板を押しつけて
密着させ、これを溶着することによって容易に連続一体
化してゆくことができる。
The adjacent iron boxes can be easily and continuously integrated by pressing and joining the joint plates along the connecting portions on the surfaces of the inner iron plate and the outer iron plate, for example, and welding them.

【0012】そして、掘削面に沿ってこれの全周を覆う
ようにして鉄箱を連続設置したら、これを型枠として内
部にコンクリートを打設する作業を行うが、幅止め用の
板状鉄部材には、コンクリートが流通可能な開口が形成
されていることから、打設されたコンクリートは、連続
設置した鉄箱の全周にわたって容易に流動してゆくこと
により充填され、コンクリートの硬化によってコンクリ
ートが連続するとともに鉄箱と一体化した鉄コンクリー
ト地下壁が形成されることになる。
[0012] Then, when an iron box is continuously installed along the excavated surface so as to cover the entire circumference thereof, the work of casting concrete into the inside using the iron box as a formwork is performed. Since the member has an opening through which concrete can flow, the poured concrete is filled by flowing easily over the entire circumference of the continuously installed iron box. And the iron concrete underground wall integrated with the iron box is formed.

【0013】すなわち、この発明によれば、中空土留材
としての鉄箱を使用し、これにコンクリートを打設して
地下壁を形成するので、プレハブ化と現場工程とを組合
わせて、精度が高く経済性のある地下壁を容易に形成し
てゆくことが可能になる。
That is, according to the present invention, an iron box is used as a hollow earth retaining material, and concrete is poured into the steel box to form an underground wall. Highly economical underground walls can be easily formed.

【0014】そしてさらに、コンクリートが硬化した
ら、鉄箱を支持固定していた支保工材のみを仮設部材と
して撤去し、鉄コンクリート地下壁に接続して床スラブ
及び天井スラブを形成することにより、地下空間が構築
されることになる。
Further, when the concrete is hardened, only the supporting material for supporting and fixing the iron box is removed as a temporary member, and is connected to the ferro-concrete basement wall to form a floor slab and a ceiling slab. Space will be built.

【0015】[0015]

【発明の実施の形態】次に、この発明の好ましい実施の
形態について、添付図面を参照しつつ詳細に説明する。
この実施形態によれば、一例として、個人住宅の敷地内
に地下室10を地下空間として設けるべく採用されたも
ので、まず、図1に示すように、敷地内の地盤を例えば
3m程度の深さで掘削してゆくとともに、これの掘削面
に沿って鋼箱11を土留材として連続設置してゆく作業
を行なう。
Next, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
According to this embodiment, as an example, the underground room 10 is adopted as an underground space in the premises of a private house. First, as shown in FIG. , And the steel box 11 is continuously installed along the excavated surface as soil retaining material.

【0016】そして、かかる掘削作業は、例えばバック
フォーなどの掘削重機を用いて容易に行うことができ、
また鋼箱11の設置作業は、各種の吊り重機を用いて鋼
箱11を所定の位置に建込み、上方から押さえつけてそ
の底部を掘削地盤に押し込むことにより、容易に行うこ
とができる。
[0016] Such excavation work can be easily performed by using a heavy excavator such as a back fork.
The installation work of the steel box 11 can be easily performed by building the steel box 11 at a predetermined position using various types of heavy lifting machines, pressing the steel box 11 from above, and pushing the bottom of the steel box 11 into the excavated ground.

【0017】ここで、鋼箱11は、例えば高さ2.8
m、長さ2m程度の大きさの鋼板を外側鋼板12及び内
側鋼板13として、これらの間に、幅20cm程度の大
きさの幅止め用の板状鉄部材としての中鋼板14を、当
該鋼箱11の立設状態において縦方向に延長するように
してサンドイッチ状に複数平行に挟み込むことによりボ
ックス状に形成され、また、上記立設状態における両側
端部には端部鋼板15が(図2参照)、底部には底鋼板
16が各々取り付けられている。なお、外側鋼板12は
内側鋼板13よりも、後述する天井スラブ23の厚さ分
だけ高くなるように組立てられることになる。
Here, the steel box 11 has a height of, for example, 2.8.
m, a steel plate having a length of about 2 m as the outer steel plate 12 and the inner steel plate 13, and a middle steel plate 14 as a plate-like iron member for width stop having a width of about 20 cm between the steel plates. The box 11 is formed in a box shape by sandwiching a plurality of pieces in a sandwich shape so as to extend in the vertical direction in the standing state, and an end steel plate 15 is provided at both ends in the standing state (FIG. 2). ), And a bottom steel plate 16 is attached to the bottom. The outer steel plate 12 is assembled to be higher than the inner steel plate 13 by the thickness of a ceiling slab 23 described later.

【0018】また、これらの中鋼板14及び端部鋼板1
5には、円形の開口部17が、複数段開口形成されてお
り、これをコンクリートの流通穴として、これらの中鋼
板14によって遮られれることなく、コンクリートを鋼
箱11の内部全体に容易に充填することが可能になると
ともに、端部鋼板15にも円形の開口部17が形成され
ていることにより、隣接する鋼箱11の端部鋼板15の
開口部17を一致させ、コンクリートを流通させて、隣
接する鋼箱11に各々打設されたコンクリートの連続性
が容易に保持されるようになっている。
The medium steel plate 14 and the end steel plate 1
5 has a plurality of circular openings 17 formed in a plurality of steps. The openings 17 serve as holes for concrete, and the concrete can be easily inserted into the entire inside of the steel box 11 without being interrupted by the medium steel plates 14. In addition to being able to be filled, the circular opening 17 is also formed in the end steel plate 15, so that the opening 17 of the end steel plate 15 of the adjacent steel box 11 matches, and concrete can be distributed. Thus, the continuity of the concrete poured into the adjacent steel boxes 11 is easily maintained.

【0019】このような鋼箱11は、施工現場に搬入さ
れる前に、工場等において、土圧や支保部材からの外
圧、あるいは内部に打設されたコンクリートによる内圧
に耐え得るような強度で、予め組立製作されることにな
るが、例えば外側鋼板12及び内側鋼板13に対する、
中鋼板14や端部鋼板15、底鋼板16等の組み付け作
業は、例えば中鋼板14をコの字状に折り曲げ加工し、
その側片部分18を介して外側鋼板12及び内側鋼板1
3との間でボルト19による接合を行ったり、フックボ
ルトや溶接によって容易に行うことができる。
Before being carried into the construction site, such a steel box 11 has a strength enough to withstand the earth pressure, the external pressure from the support member, or the internal pressure due to the concrete cast inside in a factory or the like. , Which will be assembled and manufactured in advance, for example, for the outer steel plate 12 and the inner steel plate 13,
The work of assembling the middle steel plate 14, the end steel plate 15, the bottom steel plate 16 and the like is, for example, bending the middle steel plate 14 into a U-shape,
The outer steel plate 12 and the inner steel plate 1 are provided via the side piece portions 18.
3 can be easily joined by bolts 19 or by hook bolts or welding.

【0020】なお、中鋼板14をコノ字状に折り曲げ加
工し、その側片部分18を外側鋼板12及び内側鋼板1
3の内面に当接させるようにして鋼箱11を組み立てる
ことにより、土圧や支保部材からの外圧を安定して支持
して、外側鋼板12と内側鋼板13との間の間隔を強固
に保持することができるようになっている。
It is to be noted that the middle steel plate 14 is bent in a cono shape, and the side piece 18 is formed into the outer steel plate 12 and the inner steel plate 1.
The steel box 11 is assembled in such a manner that the steel box 11 is brought into contact with the inner surface of the steel plate 3 to stably support the earth pressure and the external pressure from the support member, and firmly maintain the interval between the outer steel plate 12 and the inner steel plate 13. You can do it.

【0021】また、掘削面の角部に位置する鋼箱11
は、例えばその外側鋼板12や内側鋼板13として角部
の角度に応じて折り曲げたものを使用し、当該角部に沿
った形状の鋼箱11として組み立てることになる。
Further, the steel box 11 located at the corner of the excavation surface
For example, as the outer steel plate 12 and the inner steel plate 13, those bent according to the angles of the corners are used, and assembled as the steel box 11 having a shape along the corners.

【0022】一方、建込み設置される各鋼箱11を連続
一体化するには、図2に示すように、内側鋼板13及び
外側鋼板12の表面の接続部分に沿って、各々所定幅の
継手板20を押しつけて密着させ、これを溶着すること
によって容易に連続一体化してゆくことができる。ここ
で、このような継手板20は、先行設置される一方の鋼
箱11の表面端部に予め工場溶接等により側方に突出す
る状態で溶着固定しておき、先行設置された当該鋼箱1
1の継手板20の当該突出部分をガイドとして、後続す
る鋼箱11を建込み設置し、しかる後に、継手板20を
後続する鋼箱11の表面に溶着固定して、隣接する鋼箱
11を連続一体化するようにすることもできる。
On the other hand, in order to continuously integrate the steel boxes 11 to be built and installed, as shown in FIG. 2, joints having predetermined widths are respectively formed along the connecting portions on the surfaces of the inner steel plate 13 and the outer steel plate 12. The plate 20 is pressed against and brought into close contact with the plate 20, and can be easily and continuously integrated by welding. Here, such a joint plate 20 is welded and fixed to the surface end of one of the steel boxes 11 to be installed in advance in a state of being laterally protruded by factory welding or the like, and the steel box 11 to be installed in advance. 1
Using the projecting portion of the joint plate 20 as a guide, the succeeding steel box 11 is erected and installed, and thereafter, the joint plate 20 is welded and fixed to the surface of the succeeding steel box 11, and the adjacent steel box 11 is fixed. It can be made to be continuously integrated.

【0023】また、このようにして連続設置された鋼箱
11は、パイプサポートなどの支保工材を用いて、掘削
面からの土圧を支持した状態で当該設置位置に強固に固
定されることになる。なお、このようにして設置された
鋼箱11と掘削面との間に隙間が生じている場合には、
この隙間に適宜土砂が埋め戻されて、掘削面からの土圧
が、土留材としての鋼箱11によってスムースに支持さ
れるようになっている。
Further, the steel box 11 continuously installed in this manner is firmly fixed to the installation position while supporting the earth pressure from the excavation surface using a support material such as a pipe support. become. In addition, when there is a gap between the steel box 11 thus installed and the excavation surface,
The gap is appropriately filled with earth and sand, so that the earth pressure from the excavation surface is smoothly supported by the steel box 11 as a retaining material.

【0024】そして、掘削面に沿って全周を覆うように
して鋼箱11を連続設置したら、これを型枠として内部
にコンクリートを打設する作業を行なう。かかるコンク
リートの打設作業は、コンクリートポンプやシュートを
用いて、鋼箱11の上部の開口から容易に行うことがで
きるが、各鋼箱11を構成する中鋼板14には、コンク
リートの流通用の開口部17が形成され、また、隣接す
る鋼箱11同士は、端部鋼板15のコンクリートの流通
用の開口部17を介して連通しているため、打設された
コンクリートは、全周にわたって連続設置した鋼箱11
の全体にスムースに流通して、コンクリートの連続性が
容易に保持されるとともに、コンクリートの硬化によっ
て、鋼箱11とコンクリートが一体化した鋼コンクリー
ト地下壁21が形成されることになる。
When the steel box 11 is continuously installed so as to cover the entire circumference along the excavation surface, the concrete box is used as a formwork to cast concrete inside. The concrete placing operation can be easily performed from the upper opening of the steel box 11 using a concrete pump or a chute. The opening 17 is formed, and the adjacent steel boxes 11 communicate with each other through the opening 17 for the distribution of the concrete of the end steel plate 15, so that the poured concrete is continuous over the entire circumference. Steel box 11 installed
, The continuity of the concrete is easily maintained, and the hardening of the concrete forms the steel concrete basement wall 21 in which the steel box 11 and the concrete are integrated.

【0025】鋼コンクリート地下壁21を形成したら、
次に、鋼箱11を支持固定していたパイプサポートなど
の支保工材を撤去し、鋼コンクリート地下壁21の上端
部分と下端部分に接続するようにして、床スラブ22及
び天井スラブ23を形成する作業を行う。
After the steel concrete basement wall 21 is formed,
Next, a support material such as a pipe support that supports and fixes the steel box 11 is removed, and the floor slab 22 and the ceiling slab 23 are formed so as to be connected to the upper end portion and the lower end portion of the steel concrete basement wall 21. Do the work you want.

【0026】すなわち、床スラブ22を形成するには、
図3に示すように、まず掘削底盤上に栗石や砕石を敷設
して基層24を形成するとともに、この基層の上面を覆
って捨てコンクリート25を打設して作業床を設ける。
なお、かかる作業床は、鋼箱11内へのコンクリートの
打設作業に先立って設けておくこともできる。
That is, to form the floor slab 22,
As shown in FIG. 3, first, a base layer 24 is formed by laying rock or crushed stone on the excavated bottom, and at the same time, a concrete floor 25 is cast over the upper surface of the base layer to provide a work floor.
In addition, such a work floor may be provided prior to the work of placing concrete in the steel box 11.

【0027】そして、捨てコンクリート25の上面に、
床スラブ22の厚さと略等しい高さで立設する折れ曲が
った縁部を有するベース鉄板26を、その立設部分27
が鋼箱11の内面に沿うようにして載置するとともに、
立設部分27の内側全域にコンクリートを打設して硬化
させることにより、床スラブ22を容易に形成すること
ができる。なお、ベース鉄板26を設置する際に、ベー
ス鉄板26の立設部分27の外周面と、鋼箱11の内側
鋼板13の内面との間には、水膨張シール28を介在さ
せるとともに、コーキングを行い、さらに立設部分27
の上端部分を鋼箱11の内面に現場溶接32することに
より、止水性が十分に確保されるようにする。
Then, on the upper surface of the discarded concrete 25,
A base iron plate 26 having a bent edge that stands upright at a height substantially equal to the thickness of the floor slab 22 is attached to an upright portion 27 thereof.
Is placed along the inner surface of the steel box 11,
The floor slab 22 can be easily formed by casting concrete and hardening the entire area inside the standing portion 27. When the base iron plate 26 is installed, a water expansion seal 28 is interposed between the outer peripheral surface of the upright portion 27 of the base iron plate 26 and the inner surface of the inner steel plate 13 of the steel box 11, and coking is performed. And the standing part 27
The upper end portion is welded in-situ 32 to the inner surface of the steel box 11 to ensure sufficient water stoppage.

【0028】一方、天井スラブ23を形成するには、図
4に示すように、鋼箱11の内側鋼板13によって囲ま
れる領域を覆う大きさのスラブ鉄板29を、これの縁部
に設けられた下方に折曲がる係止部分30によって内側
鋼板13の上端を外側から覆うようにしつつ、内鉄板1
3の上端部分に載置するとともに、スラブ鉄板29の上
面には、エキスパンドメタルからなる折り曲げ板31を
補強材として載置した後(図5参照)、外鉄板12の天
端部分の高さまでコンクリートを打設して硬化させるこ
とにより(図1参照)、天井スラブ23を容易に形成す
ることができる。なお、スラブ鉄板29を設置する際
に、これを内側鋼板13に現場溶接33して強固に固定
するとともに、止水性を確保し、折り曲げ板31もまた
スラブ鉄板29に溶着しておくことにより、スラブコン
クリートの打設作業に先立って強固に固定しておく。
On the other hand, in order to form the ceiling slab 23, as shown in FIG. 4, a slab iron plate 29 having a size to cover a region surrounded by the inner steel plate 13 of the steel box 11 is provided at an edge portion thereof. While the upper end of the inner steel plate 13 is covered from the outside by the locking portion 30 bent downward, the inner iron plate 1
3 and a folded plate 31 made of expanded metal is placed on the upper surface of the slab iron plate 29 as a reinforcing material (see FIG. 5). The ceiling slab 23 can be easily formed by casting and curing (see FIG. 1). In addition, when installing the slab iron plate 29, it is welded to the inner steel plate 13 by in-situ welding 33 and firmly fixed, while ensuring water-stopping, and the bent plate 31 is also welded to the slab iron plate 29, Before slab concrete is cast, it should be firmly fixed.

【0029】このようにして、鋼コンクリート地下壁2
1と接続一体化して床スラブ22及び天井スラブ23を
設けることにより、地下室が形成されることになるが、
この実施形態によれば、中空土留材としての鋼箱11を
使用し、これにコンクリートを打設して一体的なコンポ
ジット材としての鋼コンクリート地下壁21を形成する
ので、プレハブ化と現場工程とを組合わせて、精度の高
い地下壁を容易に形成してゆくことができるとともに、
掘削面を防護する土留作業に要する手間や費用を容易に
軽減することができる。
In this manner, the steel concrete basement wall 2
The basement is formed by providing the floor slab 22 and the ceiling slab 23 by connecting and integrating with 1
According to this embodiment, the steel box 11 as a hollow earth retaining material is used, and concrete is poured into the steel box 11 to form the steel concrete basement wall 21 as an integrated composite material. By combining with, it is possible to easily form a highly accurate underground wall,
The labor and cost required for the earth retaining work for protecting the excavated surface can be easily reduced.

【0030】また、この実施形態によれば、地下室の周
囲が鋼製部材によって覆われていることにより、防水性
が高く湿気を生じさせないほど居住性に優れた地下空間
を得ることができる。
Further, according to this embodiment, since the periphery of the basement is covered with the steel member, it is possible to obtain an underground space having high waterproofness and excellent livability so as not to generate moisture.

【0031】さらに、土留材としての鋼箱11は、中空
であるとともに各鋼板の厚さも土圧やコンクリート圧に
耐え得る厚さで十分であるため軽量であり、運搬や建込
みも容易でかつ使用するトラックやクレーンも小型のも
のを使用することができる。
Further, the steel box 11 as the earth retaining material is lightweight because it is hollow and the thickness of each steel plate is sufficient to withstand the earth pressure and the concrete pressure, so that it can be easily transported and built. Small trucks and cranes can be used.

【0032】なお、この発明は、上記実施形態の実施の
態様のものに限定されるものではなく、請求項に記載さ
れた構成の範囲内において種々に変更して採用すること
ができる。例えば、床スラブ22及び天井スラブ23を
形成する際に、ベース鉄板26やスラブ鉄板29を用い
る必要は必ずしもない。
The present invention is not limited to the embodiment of the above embodiment, but can be variously modified and adopted within the scope of the constitution described in the claims. For example, when forming the floor slab 22 and the ceiling slab 23, it is not always necessary to use the base iron plate 26 and the slab iron plate 29.

【0033】[0033]

【発明の効果】以上詳細に説明したように、この発明の
地下空間の構築工法によれば、内側鉄板と、外側鉄板
と、これらの間に所定の間隔が保持されるように介在す
る、コンクリートが流通可能な開口を有する幅止め用の
板状鉄部材とからなる鉄箱を、掘削面に沿って土留材と
して連続設置し、設置した鉄箱の内部にコンクリートを
打設して、掘削面を覆う一体化した鉄コンクリート地下
壁を形成し、しかる後に、前記鉄コンクリート地下壁に
接続して床スラブ及び天井スラブを形成するので、プレ
ハブ化と現場工程とを組合わせて、地下壁を容易に形成
してゆくことができるとともに、掘削面を防護する土留
作業に要する手間や費用を容易に軽減することができ
る。
As described above in detail, according to the method of constructing an underground space according to the present invention, the concrete structure includes an inner iron plate, an outer iron plate, and a steel plate interposed therebetween so as to maintain a predetermined distance therebetween. An iron box consisting of a plate-like iron member for width stop having an opening through which it can be circulated is continuously installed along the excavation surface as earth retaining material, and concrete is poured into the installed iron box, and the excavation surface is To form an integrated ferro-concrete underground wall, and then connect to the ferro-concrete underground wall to form a floor slab and a ceiling slab. And the labor and cost required for earth retaining work for protecting the excavated surface can be easily reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の一実施形態にかかる地下空間の構築
工法によって構築される地下室を説明する破断断面図で
ある。
FIG. 1 is a cutaway sectional view illustrating a basement constructed by a construction method of an underground space according to an embodiment of the present invention.

【図2】図1のA−Aに沿った断面図である。FIG. 2 is a sectional view taken along line AA of FIG.

【図3】地下壁と接続して床スラブを形成する状況を説
明する図1のC部拡大図である。
FIG. 3 is an enlarged view of a portion C in FIG. 1 for explaining a situation where a floor slab is formed by connecting to a basement wall.

【図4】地下壁と接続して天井スラブを形成する状況を
説明する図1のD部拡大図である。
FIG. 4 is an enlarged view of a part D in FIG. 1 for explaining a situation where a ceiling slab is formed by connecting to a basement wall.

【図5】図1のB−Bに沿った断面図である。FIG. 5 is a sectional view taken along the line BB of FIG. 1;

【符号の説明】[Explanation of symbols]

10 地下室(地下空間) 11 鋼箱(鉄箱) 12 外側鋼板(外側鉄板) 13 内側鋼板(内側鉄板) 14 中鋼板(幅止め用板状鉄部材) 15 端部鋼板 16 底鋼板 17 開口部 20 継手板 21 鋼コンクリート地下壁(鉄コンクリート地下壁) 22 床スラブ 23 天井スラブ 26 ベース鋼板 29 スラブ鋼板 DESCRIPTION OF SYMBOLS 10 Basement (underground space) 11 Steel box (iron box) 12 Outer steel plate (outer iron plate) 13 Inner steel plate (inner iron plate) 14 Medium steel plate (plate-like iron member for width stop) 15 End steel plate 16 Bottom steel plate 17 Opening 20 Joint plate 21 Steel concrete basement wall (iron concrete basement wall) 22 Floor slab 23 Ceiling slab 26 Base steel plate 29 Slab steel plate

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 内側鉄板と、外側鉄板と、これらの間に
所定の間隔が保持されるように介在する、コンクリート
が流通可能な開口を有する幅止め用の板状鉄部材とから
なる鉄箱を、掘削面に沿って土留材として連続設置し、
設置した鉄箱の内部にコンクリートを打設して、前記掘
削面を覆う一体化した鉄コンクリート地下壁を形成し、
しかる後に、前記鉄コンクリート地下壁に接続して床ス
ラブ及び天井スラブを形成することを特徴とする地下空
間の構築工法。
1. An iron box comprising an inner iron plate, an outer iron plate, and a width-stopping plate-like iron member having an opening through which concrete can flow and interposed so as to maintain a predetermined distance therebetween. Are continuously installed along the excavated surface as earth retaining material,
Casting concrete inside the installed iron box, forming an integrated ferro-concrete underground wall covering the excavation surface,
Thereafter, a floor slab and a ceiling slab are formed by connecting to the ferro-concrete basement wall, and a method of constructing an underground space.
JP9214572A 1997-08-08 1997-08-08 Process for constructing underground space Pending JPH1161855A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9214572A JPH1161855A (en) 1997-08-08 1997-08-08 Process for constructing underground space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9214572A JPH1161855A (en) 1997-08-08 1997-08-08 Process for constructing underground space

Publications (1)

Publication Number Publication Date
JPH1161855A true JPH1161855A (en) 1999-03-05

Family

ID=16657945

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9214572A Pending JPH1161855A (en) 1997-08-08 1997-08-08 Process for constructing underground space

Country Status (1)

Country Link
JP (1) JPH1161855A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101389568B1 (en) * 2012-10-23 2014-05-21 임홍빈 Panel for being installed at underground structure
CN107402043A (en) * 2017-07-24 2017-11-28 沈阳工业大学 Half cover and cut method Construction of City Tunnel monitoring method and monitoring system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101389568B1 (en) * 2012-10-23 2014-05-21 임홍빈 Panel for being installed at underground structure
CN107402043A (en) * 2017-07-24 2017-11-28 沈阳工业大学 Half cover and cut method Construction of City Tunnel monitoring method and monitoring system

Similar Documents

Publication Publication Date Title
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
US5383319A (en) Method of erecting a foundation structure for a building substructure
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
JPH1161855A (en) Process for constructing underground space
JPH11310928A (en) Vibration isolation reinforcing method for existing structure
US20060239782A1 (en) Methods and apparatuses for shaping concrete slab-on-ground foundations
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof
JPH032422A (en) Construction of foundation sill
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
JPH09111776A (en) Basement and construction method thereof
JPH03199528A (en) Steel frame foundation of construction
JP3471435B2 (en) Tunnel wall
JP3677834B2 (en) Structure of connecting part of reinforced concrete basement building unit
JP2001003374A (en) Execution method of underground concrete wall using embedded form
JPS6024249B2 (en) How to build a basement
JPS6029292Y2 (en) Semi-prefabricated conduit for underground cable pipes
JP6206965B2 (en) Underground space structure and construction method of underground space structure
JP2877896B2 (en) Concrete basement basement
JPH10252083A (en) Assembly type concrete structure and its execution method
JPH11350500A (en) Foundation structure of building and foundation work method
JP2941893B2 (en) Concrete basement basement
JP3656873B2 (en) Foundation construction method
JP2859130B2 (en) Reservoir equipment implementation method
JP2936492B2 (en) Concrete assembling basement and concrete assembling basement construction method
JP2001323485A (en) Method of constructing underground structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040531

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20040531

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20040531

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060418

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060822