JP3471435B2 - Tunnel wall - Google Patents

Tunnel wall

Info

Publication number
JP3471435B2
JP3471435B2 JP21159394A JP21159394A JP3471435B2 JP 3471435 B2 JP3471435 B2 JP 3471435B2 JP 21159394 A JP21159394 A JP 21159394A JP 21159394 A JP21159394 A JP 21159394A JP 3471435 B2 JP3471435 B2 JP 3471435B2
Authority
JP
Japan
Prior art keywords
wall
tunnel
slab
portions
shape
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP21159394A
Other languages
Japanese (ja)
Other versions
JPH0882194A (en
Inventor
洋樹 染谷
敏美 伊野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP21159394A priority Critical patent/JP3471435B2/en
Publication of JPH0882194A publication Critical patent/JPH0882194A/en
Application granted granted Critical
Publication of JP3471435B2 publication Critical patent/JP3471435B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 【0001】 【産業上の利用分野】本発明は、内部空間を区画壁によ
り複数に分割し、分割された空間それぞれに、異なる共
益設備を配設する共同溝等に適用されるトンネル壁に関
するものである。 【0002】 【従来の技術】周知のように、複数の設備を敷設するト
ンネルにおいては、その内部空間を区画壁によって複数
に分割し、分割された空間内に各設備を敷設することが
ある。例えば、図7に示す共同溝1は、地中に埋設する
複数の公益設備を一つのトンネル内に配設するものであ
り、近年広く用いられている。この共同溝1は、一次覆
工壁2と、二次覆工壁3と、区画壁4及び5とから形成
されていて、例えば、区画壁4及び5によって分割され
た各空間6、7及び8内には、それぞれ導水管(上水道
管もしくは下水道管)9、電線10とガス管11、電話
ケーブル12が配設されている。 【0003】上記共同溝1を構築するには、まず、地中
を掘削してトンネルを形成し、該トンネル内に工場等に
おいて予め製作した鉄筋コンクリート製のセグメントを
搬入し、これらセグメントをトンネルの周方向及び軸線
方向に連結して一次覆工壁2を構築する。その後、一次
覆工壁2の内面及び区画壁4、5を形成すべき位置に鉄
筋及び型枠を設置し、該型枠内にコンクリートを打設す
ることによって二次覆工壁3及び区画壁4、5を形成す
る。 【0004】 【発明が解決しようとする課題】ところで、上記のトン
ネル壁においては、区画壁4、5が二次覆工壁3と一緒
に現場打ちで構築されるため、現場でのコンクリート打
ちの作業が複雑となり、施工期間が長くなると共に、コ
ストも高くなるという問題があった。そこで近年、区画
壁4、5をプレキャストコンクリート・スラブ(以下、
単にスラブと記す)によって構築することが試みられて
いる。しかし、区画壁4、5は共同溝1の側壁に加わる
土圧に対して側壁を補助する役目を合わせ持つため、ス
ラブの寸法は、側壁間の幅に対してほんの僅かしか短く
することが許されない。このため、トンネル内にスラブ
を付設する際、トンネル内でスラブを搬送することが困
難になるという問題があった。 【0005】本発明は、上述した事情に鑑みてなされた
もので、トンネルの構築現場において、トンネル内で区
画壁を構築するスラブの搬送作業が容易に行え、短時間
でコストのかからないトンネル壁を提供することを目的
とする。 【0006】 【課題を解決するための手段】請求項1記載のトンネル
壁は、地下を掘削したトンネル内に掘削面に沿って覆工
壁が形成され、この覆工壁の対向する側壁部間にトンネ
ル内を上下に区画する区画壁が設けられたトンネル壁に
おいて、対向する側壁部には、それぞれトンネルの軸線
方向に延在し、その上面を受け面とする突出壁部または
その上面を受け面とする溝状凹部が形成されている。こ
れら突出壁部または溝状凹部の受け面間には、区画壁を
構成するスラブが載置され、このスラブの形状が、矩形
形状の対角線上の少なくとも2つの角部が欠落した形状
とされていることを特徴としている。 【0007】 【作用】本発明では、矩形形状の対角線上にある少なく
とも2つの角部が欠落した形状のスラブを用いて区画壁
を構築する。この形状のスラブを用いることによって、
土圧に対して側壁を補助するという区画壁の一方の機能
を阻害することなく、トンネル内でのスラブの搬送が極
めて容易となる。 【0008】 【実施例】以下に、本発明の一実施例を図1から図4を
参照して説明する。本実施例は、先に説明した図7に示
す共同溝1と基本的な構造は同一であり、同一部分には
同一符号を付して説明を省略し、異なる部分について説
明する。 【0009】図1、図2において、一次覆工壁2の左右
の側壁部13、14には、これら側壁部13、14の上
下方向の中間位置に、トンネルの内方に向けて突出し、
かつ、トンネルの軸線方向に向かって延在する突出壁部
15、16が形成されている。突出壁部15、16に
は、更にトンネルの内方に突出する凸部17、18が形
成されている。これらの突出壁部15、16の上面に
は、凸部17、18の形成された部分を含む領域に凹部
19、20が形成されており、この凹部19、20の上
面は、スラブ21を載置するため受け面15a、16a
となっている。この場合、凹部19、20の深さ寸法
は、スラブ21の厚み寸法と一致しており、スラブ21
が載置されたときに、該スラブ21の上面と突出壁部1
5、16の上面とが面一状態になるように構成されてい
る。また、この凹部19、20の側面の形状は、スラブ
21の外形形状に略一致した形状となっており、湾曲面
21aに対応する部分は、湾曲面21aに対応する形状
となっている。そして、この凹部19、20内には、ス
ラブ21が嵌入され、受け面15a、16a上に載置さ
れている。 【0010】スラブ21は、図4に示すように、同一寸
法のH形鋼22a〜22c3本を溶接し、これら溶接し
たものの同一対角線上に位置する2箇所の角部を溶断し
て基材22を形成し、この基材22の溶断面に帯状鋼板
23、23を張り合わせ、溶接して形成したものであ
る。このスラブ21の形状は、図に示すように矩形形状
の対角線上にある2つの角部を欠落させた形状となって
おり、欠落させた部分が湾曲面21a、21aとされて
いる。また、スラブ21の長さ方向の寸法は、突出壁部
15、16の受け面15a、16aに載置された際、側
壁部13、14との隙間が僅かとなる寸法に造られてい
る。 【0011】次に、トンネル壁の構築方法について説明
する。まず、地中を掘削しトンネルを形成し、トンネル
の掘削面に沿って、図1に示す一次覆工壁2を構築す
る。そして、次にこの一次覆工壁2内にスラブ21を搬
入する。この場合、スラブ21は、同一対角線上に位置
する2つの角部を欠落させた形状にしてあるため、図に
2点鎖線で示すように斜めに傾けた状態で、トンネル内
を搬送する。スラブ21を所定の位置まで搬送してから
矢印Pの方向に回動させ、本来付設する向きにする。次
に、図2に示すように突出壁部15、16の上面にに形
成された凹部19、20に嵌め合わせるようにして落と
し込むことによって25の状態となり付設が完了する。
これを繰り返すことにより、トンネル全体に亘って順次
定められた間隔ごとにスラブを設置する。その後、現場
作業として二次覆工壁3とスラブの上下に壁26を鉄筋
コンクリートで構築する。 【0012】上記のトンネル壁によれば、側壁部13、
14及び突出壁部15、16とスラブ21との隙間は僅
かであるため、土圧に対して側壁を補助するという区画
壁の一方の機能を阻害することなく、トンネル内でのス
ラブ21の搬送が極めて容易となる。このため、スラブ
21の設置が能率よく行える。また、スラブ21は事前
に工場で造られるため、現場でのコンクリート打ち作業
が簡単化でき、短時間でコストのかからないトンネル壁
の構築が可能となる。 【0013】なお、上記実施例では、対向する2つの角
部のみを欠落させたが、4つの角部すべてを欠落させた
形状でも良い。また滑らかな曲面として角部を欠落させ
たが、トンネル内で回動することのできる寸法だけ欠落
させてあれば、欠落の形状は他の形状でもよい。さら
に、本実施例では、スラブ21を形成するのにH形鋼と
帯状鋼板を用いたが、RCプレキャストハーフスラブと
して形成しても良い。 【0014】また、上記実施例では、側壁部に突出壁部
を設け、その上面を受け面としたが、この受け面は図
5、図6に示すような構造としても良い。すなわち、一
次覆工壁2の左右の側壁部13、14の上下方向の中間
位置にトンネルの軸線方向に向かって延在する溝状凹部
27、28を形成し、これら溝状凹部27、28の上面
をスラブ21を載置する受け面27a、28aとする。
この場合、溝状凹部27、28間の寸法は、スラブ21
の長さ寸法と略一致しており、スラブ21が載置された
ときに、該スラブ21の側面と対向する側壁部13、1
4との間隙はごく僅かとなるようにする。 【0015】 【発明の効果】本発明によれば、スラブの形状を矩形形
状の対角線上にある少なくとも2つの角部を欠落させた
形状とすることによって、トンネル内において、極めて
容易にスラブを搬送することができる。これにより、ト
ンネルの構築現場でのスラブの付設作業が能率よく行え
るため、短期間でトンネル壁を構築することができると
共に、公益設備である共同溝を低コストで提供すること
が可能となる。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of dividing an internal space into a plurality of partitions by partition walls, and installing a common utility facility or the like in each of the divided spaces. It concerns the applicable tunnel wall. 2. Description of the Related Art As is well known, in a tunnel in which a plurality of facilities are laid, an internal space may be divided into a plurality of sections by partition walls, and each facility may be laid in the divided space. For example, a common ditch 1 shown in FIG. 7 is one in which a plurality of public utilities buried underground are arranged in one tunnel, and have been widely used in recent years. The common groove 1 is formed by a primary lining wall 2, a secondary lining wall 3, and partition walls 4 and 5, and for example, each space 6, 7 and Inside 8, a water guide pipe (water supply pipe or sewer pipe) 9, an electric wire 10, a gas pipe 11, and a telephone cable 12 are arranged. [0003] In order to construct the above-mentioned common groove 1, first, a tunnel is formed by excavating underground, and segments made of reinforced concrete manufactured in advance in a factory or the like are carried into the tunnel, and these segments are put around the tunnel. The primary lining wall 2 is constructed by connecting in the direction and the axial direction. Thereafter, a reinforcing bar and a formwork are installed at the inner surface of the primary lining wall 2 and the positions where the partition walls 4 and 5 are to be formed, and concrete is poured into the formwork to form the secondary lining wall 3 and the partition wall. 4 and 5 are formed. [0004] In the above-mentioned tunnel wall, since the partition walls 4 and 5 are constructed together with the secondary lining wall 3 by cast-in-place, the concrete cast-in site can be used. There is a problem that the work becomes complicated, the construction period becomes longer, and the cost becomes higher. Therefore, in recent years, the partition walls 4, 5 have been precast concrete slabs (hereinafter, referred to as precast concrete slabs).
Slabs). However, since the partition walls 4 and 5 have a role of assisting the side wall against the earth pressure applied to the side wall of the common groove 1, the dimension of the slab can be made only slightly shorter than the width between the side walls. Not done. For this reason, when the slab is attached in the tunnel, there is a problem that it is difficult to transport the slab in the tunnel. SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned circumstances, and in a tunnel construction site, a slab for constructing a partition wall in a tunnel can be easily transported, and a tunnel wall which is inexpensive in a short time. The purpose is to provide. According to a first aspect of the present invention, there is provided a tunnel wall, wherein a lining wall is formed along a digging surface in a tunnel in which an underground is digged, and between the opposing side wall portions of the lining wall. In a tunnel wall provided with partition walls vertically partitioning the inside of the tunnel, opposing side wall portions each extend in the axial direction of the tunnel and have a protruding wall portion as an upper surface receiving surface.
A groove-shaped concave portion having the upper surface as a receiving surface is formed. A slab constituting the partition wall is placed between the receiving surfaces of the protruding wall portions or the groove-shaped concave portions , and the shape of the slab is such that at least two corners on a diagonal line of a rectangular shape are missing. It is characterized by having. According to the present invention, a partition wall is constructed using a slab having at least two corners missing on a diagonal line of a rectangular shape. By using a slab of this shape,
The transfer of the slab in the tunnel becomes extremely easy without obstructing the function of one of the partition walls to assist the side wall against the earth pressure. An embodiment of the present invention will be described below with reference to FIGS. In this embodiment, the basic structure is the same as that of the above-described common groove 1 shown in FIG. 7, and the same portions are denoted by the same reference numerals, description thereof will be omitted, and different portions will be described. In FIGS. 1 and 2, the left and right side walls 13 and 14 of the primary lining wall 2 project toward the inside of the tunnel at intermediate positions in the vertical direction of the side walls 13 and 14.
In addition, projecting wall portions 15 and 16 extending in the axial direction of the tunnel are formed. On the protruding walls 15, 16, protruding portions 17, 18 protruding further inward of the tunnel are formed. On the upper surfaces of these protruding wall portions 15 and 16, concave portions 19 and 20 are formed in a region including the portions where the convex portions 17 and 18 are formed, and the upper surfaces of the concave portions 19 and 20 carry the slab 21 thereon. Receiving surfaces 15a, 16a for placing
It has become. In this case, the depth dimension of the concave portions 19 and 20 matches the thickness dimension of the slab 21 and
Is mounted, the upper surface of the slab 21 and the protruding wall 1
It is configured such that the upper surfaces of 5 and 16 are flush with each other. The shape of the side surfaces of the concave portions 19 and 20 substantially matches the outer shape of the slab 21, and the portion corresponding to the curved surface 21a has a shape corresponding to the curved surface 21a. The slab 21 is fitted into the recesses 19 and 20, and is placed on the receiving surfaces 15a and 16a. As shown in FIG. 4, a slab 21 is formed by welding three H-section steels 22a to 22c having the same dimensions and fusing two corners of the welded ones located on the same diagonal line. Are formed by laminating strip steel plates 23 and 23 on the melted surface of the base material 22 and welding them. As shown in the figure, the shape of the slab 21 is a shape in which two corners on a diagonal line of a rectangular shape are missing, and the missing portions are curved surfaces 21a, 21a. The length of the slab 21 in the length direction is such that the gap between the slab 21 and the side walls 13 and 14 is small when the slab 21 is placed on the receiving surfaces 15 a and 16 a of the protruding walls 15 and 16. Next, a method of constructing a tunnel wall will be described. First, a tunnel is formed by excavating underground, and a primary lining wall 2 shown in FIG. 1 is constructed along an excavated surface of the tunnel. Then, the slab 21 is carried into the primary lining wall 2. In this case, since the slab 21 has a shape in which two corner portions located on the same diagonal line are missing, the slab 21 is transported in the tunnel in a state of being inclined obliquely as shown by a two-dot chain line in the figure. After the slab 21 is transported to a predetermined position, the slab 21 is rotated in the direction of arrow P, so that the slab 21 is attached to the original position. Next, as shown in FIG. 2, the protruding walls 15 and 16 are fitted into recesses 19 and 20 formed on the upper surfaces of the protruding walls 15 and 16, respectively.
By repeating this, slabs are set at intervals determined sequentially over the entire tunnel. Thereafter, as the work on site, the walls 26 are constructed of reinforced concrete above and below the secondary lining wall 3 and the slab. According to the above-mentioned tunnel wall, the side wall portion 13,
Since the gap between the slab 21 and the projecting wall portions 15 and 16 is small, the slab 21 is transported in the tunnel without obstructing one of the partition walls, which assists the side wall against earth pressure. Becomes extremely easy. Therefore, the slab 21 can be efficiently installed. In addition, since the slab 21 is manufactured in advance at the factory, the concrete driving work on site can be simplified, and the construction of the tunnel wall in a short time and at low cost becomes possible. In the above embodiment, only two opposing corners are missing, but a shape in which all four corners are missing may be used. Although the corners are cut off as a smooth curved surface, other shapes may be used as long as the corners are cut out so as to be rotatable in the tunnel. Further, in the present embodiment, the H-shaped steel and the strip-shaped steel plate are used to form the slab 21, but may be formed as an RC precast half slab. In the above embodiment, the protruding wall portion is provided on the side wall portion, and the upper surface thereof is used as the receiving surface. However, the receiving surface may have a structure as shown in FIGS. That is, groove-shaped concave portions 27 and 28 extending toward the axial direction of the tunnel are formed at a vertical intermediate position between the left and right side wall portions 13 and 14 of the primary lining wall 2, and these groove-shaped concave portions 27 and 28 are formed. The upper surfaces are the receiving surfaces 27a and 28a on which the slab 21 is placed.
In this case, the dimension between the groove-shaped concave portions 27 and 28 is
And the side wall portions 13 and 1 facing the side surface of the slab 21 when the slab 21 is placed.
The gap with 4 is very small. According to the present invention, the slab can be transported very easily in the tunnel by forming the slab into a shape in which at least two corners on the diagonal of the rectangular shape are missing. can do. Accordingly, the work of attaching the slab at the tunnel construction site can be performed efficiently, so that the tunnel wall can be constructed in a short period of time, and the common groove, which is a utility facility, can be provided at low cost.

【図面の簡単な説明】 【図1】本発明の一実施例を示す図であって、トンネル
壁の要部平断面図である。 【図2】図1のA−A線矢印断面図である。 【図3】図1のB−B線断面図である。 【図4】本発明の一実施例を示す図であって、スラブの
構造を示す斜視図である。 【図5】トンネル壁の他の構成を示す要部平断面図であ
る。 【図6】図5のC−C線矢印断面図である。 【図7】従来のトンネル壁の縦断面図である。 【符号の説明】 13 側壁部 14 側壁部 15 突出壁部 16 突出壁部21 スラブ27 溝状凹部 28 溝状凹部
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a view showing one embodiment of the present invention, and is a plan sectional view of a main part of a tunnel wall. FIG. 2 is a sectional view taken along line AA of FIG. 1; FIG. 3 is a sectional view taken along line BB of FIG. 1; FIG. 4 is a view showing one embodiment of the present invention, and is a perspective view showing a structure of a slab. FIG. 5 is a plan sectional view of a main part showing another configuration of the tunnel wall. FIG. 6 is a sectional view taken along line CC of FIG. 5; FIG. 7 is a longitudinal sectional view of a conventional tunnel wall. [Description of Signs] 13 Side wall portion 14 Side wall portion 15 Projecting wall portion 16 Projecting wall portion 21 Slab 27 Groove-like concave portion 28 Groove-like concave portion

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平7−233698(JP,A) 特開 平8−60993(JP,A) 特開 平1−315596(JP,A) 特開 平8−68146(JP,A) 特開 平8−68147(JP,A) (58)調査した分野(Int.Cl.7,DB名) E21D 11/08 ────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-7-233698 (JP, A) JP-A-8-60993 (JP, A) JP-A-1-315596 (JP, A) JP-A 8- 68146 (JP, A) JP-A-8-68147 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E21D 11/08

Claims (1)

(57)【特許請求の範囲】 【請求項1】 地中を掘削したトンネル内に掘削面に沿
って覆工壁が形成され、該覆工壁の対向する側壁部間に
トンネル内を上下に区画する区画壁が設けられたトンネ
ル壁において、前記対向する側壁部には、それぞれトン
ネルの軸線方向に延在し、その上面を受け面とする突出
壁部またはその上面を受け面とする溝状凹部が形成さ
れ、これら突出壁部または溝状凹部の受け面間には、前
記区画壁を構成するスラブが載置され、該スラブの形状
が、矩形形状の対角線上にある少なくとも2つの角部が
欠落した形状とされていることを特徴とするトンネル
壁。
(57) [Claims 1] A lining wall is formed along a digging surface in a tunnel excavated in the ground, and a vertical wall is formed in the tunnel between opposing side walls of the lining wall. In the tunnel wall provided with a partition wall for partitioning, the opposing side wall portions each extend in the axial direction of the tunnel and have a protruding wall portion serving as an upper surface receiving surface or a groove shape serving as an upper surface receiving surface. A concave portion is formed, and a slab constituting the partition wall is placed between receiving surfaces of the protruding wall portions or the groove-shaped concave portions , and the shape of the slab is at least two corner portions on a diagonal line of a rectangular shape. A tunnel wall characterized by a missing shape.
JP21159394A 1994-09-05 1994-09-05 Tunnel wall Expired - Fee Related JP3471435B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21159394A JP3471435B2 (en) 1994-09-05 1994-09-05 Tunnel wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21159394A JP3471435B2 (en) 1994-09-05 1994-09-05 Tunnel wall

Publications (2)

Publication Number Publication Date
JPH0882194A JPH0882194A (en) 1996-03-26
JP3471435B2 true JP3471435B2 (en) 2003-12-02

Family

ID=16608339

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21159394A Expired - Fee Related JP3471435B2 (en) 1994-09-05 1994-09-05 Tunnel wall

Country Status (1)

Country Link
JP (1) JP3471435B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002147188A (en) * 2000-11-09 2002-05-22 Ishikawajima Constr Materials Co Ltd Tunnel constructing method

Also Published As

Publication number Publication date
JPH0882194A (en) 1996-03-26

Similar Documents

Publication Publication Date Title
US4075852A (en) Steel reinforced underground wall
US4055927A (en) Concrete walls and reinforcement cage therefor
JP2004232328A (en) Structure of half precast type arch culvert and its construction method
JP3471435B2 (en) Tunnel wall
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
JP2003193495A (en) Underground structure constructing method
EP2364399B1 (en) Modular lining for tunnels
JP2003193494A (en) Underground hollow structure constructing method and the underground hollow structure
JP2813807B2 (en) How to build an underground tunnel
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
JP3900684B2 (en) Construction method for underground structures
JP2509395B2 (en) Structure of building foundation
RU2138597C1 (en) Method for erection of underground structure
JPS5853321Y2 (en) Element for mountain retainer
JP3646698B2 (en) Construction method for underground structures
JP2887712B2 (en) Underground diaphragm wall method
JPH1161855A (en) Process for constructing underground space
CN116591222A (en) Connection node structure of foundation pit bottom plate and temporary intermediate wall and construction mode thereof
JPS61186623A (en) Method of building foundation of building
JPS60133117A (en) Method of constructing joint part of continuous underground wall
JPS6029292Y2 (en) Semi-prefabricated conduit for underground cable pipes
JPS6024249B2 (en) How to build a basement
JP3291544B2 (en) Split assembling method for box culvert construction
JPH07233698A (en) Method of constructing tunnel wall
JP2024024044A (en) Sheet pile connection structure and sheet pile connection method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20030805

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080912

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080912

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090912

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees