JP2509395B2 - Structure of building foundation - Google Patents

Structure of building foundation

Info

Publication number
JP2509395B2
JP2509395B2 JP3098619A JP9861991A JP2509395B2 JP 2509395 B2 JP2509395 B2 JP 2509395B2 JP 3098619 A JP3098619 A JP 3098619A JP 9861991 A JP9861991 A JP 9861991A JP 2509395 B2 JP2509395 B2 JP 2509395B2
Authority
JP
Japan
Prior art keywords
underground
floor slab
building
building foundation
hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP3098619A
Other languages
Japanese (ja)
Other versions
JPH04330117A (en
Inventor
俊夫 大野
昇 白石
建 武田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP3098619A priority Critical patent/JP2509395B2/en
Publication of JPH04330117A publication Critical patent/JPH04330117A/en
Application granted granted Critical
Publication of JP2509395B2 publication Critical patent/JP2509395B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、地中梁と1階スラブ
を有する建物基礎部の構造に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a building foundation having an underground beam and a first floor slab.

【0002】[0002]

【従来の技術】従来、この種の建物基礎部としては、図
6,図7および図8に示すようなものがある(図6は建物
基礎部を上方から見たところを示し、図7は図6におけ
るVII−VII線断面、図8は図6におけるVIII−VIII線断
面を示している。)。この建物基礎部は、図6に示すよ
うに、建物外周の長手方向に延びる地中梁101,10
2と、各基礎111,112上でこの地中梁101,10
2に垂直に交わる地中梁200を備え、上記地中梁10
1,102の間にこれらに平行に小梁104,105を備
えている。図7,図8に示すように、地中梁101,10
2は、剛性を持たせるために梁成のほとんどの部分が地
中に埋設され、一部だけが地面110の上に出ている。
1階スラブ103が地表より一定高さになるように規制
されているからである。小梁104,105は1階スラ
ブ103を補強するものであって全体が地面110上に
設けられている。そして、これら地中梁101,102
および小梁104,105上に、1階スラブ103が設
けられている。
2. Description of the Related Art Conventionally, as a building foundation of this type, there is one as shown in FIGS. 6, 7 and 8 (FIG. 6 shows a view of the building foundation from above, and FIG. (A cross section taken along line VII-VII in FIG. 6 and FIG. 8 shows a cross section taken along line VIII-VIII in FIG. 6). As shown in FIG. 6, this building foundation portion has underground beams 101, 10 extending in the longitudinal direction of the outer periphery of the building.
2 and this underground girder 101,10 on each foundation 111,112
2 is provided with an underground beam 200 that vertically intersects with the above-mentioned underground beam 10.
Beams 104 and 105 are provided between 1 and 102 in parallel with them. As shown in FIGS. 7 and 8, the underground beams 101, 10
In No. 2, most of the beams are buried in the ground to have rigidity, and only a part of them are exposed on the ground 110.
This is because the first-floor slab 103 is regulated so as to have a constant height above the ground surface. The crossbeams 104 and 105 reinforce the first floor slab 103 and are entirely provided on the ground 110. And these underground beams 101, 102
The first floor slab 103 is provided on the cross beams 104 and 105.

【0003】上記建物基礎部は、まず、地中梁101,
102と200との交差部に予め基礎杭113,114
を打設しておき、以下、図5に示す施工手順にしたがっ
て次のようにして構築されている。まず、図7,図8に
示すように、地中梁101,102,200および基礎杭
111,112を設けるべき梁領域A,B,Cの掘削を行
う(S101)。実際には、各梁領域A,B,Cの両側(破
線a,b,cで示す範囲)も斜めに掘削して、側面にテーパー
を有する平坦な溝201,202,203を形成する。次
に、上記溝201,202,203の底部に砂利(割栗)1
31,132,231および小梁104,105用の砂利
135を敷設し(S102)、捨コンクリート133,1
34,232を打設する(S103)。次に、梁領域A,
B,Cに地中梁用の鉄筋124,125,224,225を
組み(S104)、続いて各鉄筋124,125,224,
225の両側に地中梁用の型枠を立設する(S105)。
そして、この型枠内にコンクリートを流し込んで、地中
梁101,102,200を形成する(S106)。基礎1
11,112の鉄筋組み,型枠組,コンクリート打設は前
記地中梁の施工と同時に行う。この状態で一定期間放置
して、流し込んだコンクリートの養生を行った後(S1
07)、上記地中梁用の型枠を取り除く(S108)。梁
領域A,B,Cに形成した溝201,202,203を埋め
戻した後(S109)、1階スラブと小梁用の型枠,鉄筋
126,127,128を組む(S110,S111)。こ
のとき、地中梁101,102,200の上部で1階スラ
ブ用の鉄筋126と地中梁用の鉄筋124,125,22
4,225とを接続する。次に、上記型枠内にコンクリ
ートを流し込んで、小梁104,105と1階スラブ1
03とを同時に形成する(S112)。1階スラブ103
と地中梁101,102,200とは鉄筋126と12
4,125,224,225とを介してつながった状態と
なる。最後に、流し込んだコンクリートの養生を行う
(S113)。
First, the above-mentioned building foundation is constructed by the underground beams 101,
Preliminary foundation piles 113, 114 at the intersection of 102 and 200
Is laid in advance and is constructed as follows according to the construction procedure shown in FIG. First, as shown in FIGS. 7 and 8, excavation of the beam regions A, B and C where the underground beams 101, 102 and 200 and the foundation piles 111 and 112 are to be provided is performed (S101). Actually, both sides (ranges indicated by broken lines a, b, and c) of each beam area A, B, and C are also excavated obliquely to form flat grooves 201, 202, and 203 having tapered side surfaces. Next, gravel (crack chestnuts) 1 on the bottom of the grooves 201, 202, 203.
31,132,231 and the gravel 135 for the beam 104,105 is laid (S102), and the waste concrete 133,1
34 and 232 are placed (S103). Next, the beam area A,
Reinforcing bars 124, 125, 224, and 225 for underground beams are assembled to B and C (S104), and subsequently each reinforcing bar 124, 125, 224,
The formwork for underground beams is erected on both sides of 225 (S105).
Then, concrete is poured into the mold to form the underground beams 101, 102, 200 (S106). Foundation 1
Reinforcing bar assembly, formwork and concrete placing of 11,112 are performed at the same time as the construction of the underground beam. After standing for a certain period of time in this state to cure the poured concrete (S1
07), the formwork for the underground beam is removed (S108). After the grooves 201, 202, 203 formed in the beam regions A, B, C are backfilled (S109), the first floor slab and the formwork for the beam, and the reinforcing bars 126, 127, 128 are assembled (S110, S111). At this time, the reinforcing bars 126 for the first floor slab and the reinforcing bars 124, 125, 22 for the underground beams are provided above the underground beams 101, 102, 200.
4,225 is connected. Next, concrete is poured into the formwork, and the beam members 104 and 105 and the first floor slab 1
And 03 are simultaneously formed (S112). First floor slab 103
And underground beams 101, 102, 200 are reinforcing bars 126 and 12.
4,125,224,225 are connected. Finally, cure the poured concrete
(S113).

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記従
来の建物基礎部の構造では、上に述べたように地中梁1
01,102,200と1階スラブ103(および小梁1
04,105)とを別工程でそれぞれ独自に形成すること
となるため、工程が複雑となり、施工期間が長くかかる
という問題がある。また、施工開始時(S101)に形成
した溝201,202,203を地中梁101,102,2
00形成後1階スラブ103形成前に全部埋め戻してお
り(S109)、無駄な手間をかけていると考えられる。
また、上記従来の建物基礎部の構造は、地中梁101,
102,200の剛性が不足しがちであり、剛性を高め
るために溝201,202,203を深く形成して地中梁
101,102,200を深く埋設しなければならないと
いう問題がある。
However, in the conventional structure of the building foundation, as described above, the underground beam 1 is used.
01, 102, 200 and 1st floor slab 103 (and girder 1
No. 04, 105) are separately formed in separate steps, so there is a problem that the steps are complicated and the construction period is long. Further, the grooves 201, 202, 203 formed at the start of construction (S101) are replaced with the underground beams 101, 102, 2.
After the formation of 00, before the formation of the first floor slab 103, the entire area is backfilled (S109), which is considered to be a waste of time.
Further, the structure of the conventional building foundation is the underground beam 101,
The rigidity of 102, 200 tends to be insufficient, and there is a problem that the grooves 201, 202, 203 must be deeply formed to deeply bury the underground beams 101, 102, 200 in order to increase the rigidity.

【0005】そこで、この発明の目的は、地中梁と1階
スラブを有する建物基礎部を単純な工程でもって短期間
に構築できる上、地中梁の剛性を高めて地中梁を埋設す
る溝の深さを浅くできる建物基礎部の構造を提供するこ
とにある。
Therefore, an object of the present invention is to construct a building foundation having an underground beam and a first-floor slab in a short period of time by a simple process, and to embed the underground beam by increasing the rigidity of the underground beam. The purpose is to provide a structure for the building foundation that can make the depth of the groove shallow.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するた
め、請求項1に記載の建物基礎部の構造は、地中梁と1
階スラブを有する建物基礎部の構造であって、上記地中
梁と1階スラブとは鉄筋コンクリートによって一体に形
成され、上記地中梁に挟まれた領域に、底面が略全面的
に地盤に接し、この地中梁の内側側面および上記1階ス
ラブの下面に接する中空の剛性を有する密閉箱体が配設
されていることを特徴としている。
In order to achieve the above object, the structure of the building foundation according to claim 1 is an underground beam and an underground beam.
A structure of a building foundation having a floor slab, wherein the underground girder and the first floor slab are integrally formed by reinforced concrete, and the bottom surface is almost entirely in contact with the ground in the area sandwiched by the underground girder. It is characterized in that a hollow closed box having rigidity is provided in contact with the inner side surface of the underground beam and the lower surface of the first floor slab.

【0007】また、請求項2に記載の建物基礎部の構造
は、地中梁と1階スラブを有する建物基礎部の構造であ
って、上記地中梁と1階スラブとは鉄筋コンクリートに
よって一体に形成され、上記地中梁に挟まれた領域に、
底面が略全面的に地盤に接し、この地中梁の内側側面お
よび上記1階スラブの下面に接する中空の剛性を有する
密閉箱体が配設され、上記密閉箱体の上部に、この密閉
箱体内部と上記建物の1階との出入りを可能にする扉が
設けられていることを特徴としている。
Further, the structure of the building foundation according to claim 2 is a structure of a building foundation having an underground beam and a first floor slab, and the underground beam and the first floor slab are integrally made of reinforced concrete. In the area that is formed and sandwiched by the underground beams,
A closed box having a hollow rigidity is provided, the bottom surface of which is almost entirely in contact with the ground, and which is in contact with the inner side surface of the underground beam and the lower surface of the first floor slab. The closed box is provided above the closed box. It is characterized in that a door is provided to allow access to the inside of the body and the first floor of the building.

【0008】また、請求項3に記載の建物基礎部の構造
は、地中梁と1階スラブを有する建物基礎部の構造であ
って、上記地中梁と1階スラブとは鉄筋コンクリートに
よって一体に形成され、上記地中梁に挟まれた領域に、
この地中梁の内側側面および上記1階スラブの下面に接
する中空の密閉体が配設され、上記密閉体の上部に、こ
の密閉体内部と上記建物の1階との出入りを可能にする
扉が設けられていることを特徴としている。
Further, the structure of the building foundation according to claim 3 is a structure of a building foundation having an underground beam and a first floor slab, wherein the underground beam and the first floor slab are integrally made of reinforced concrete. In the area that is formed and sandwiched by the underground beams,
A hollow sealing body is provided which is in contact with the inner side surface of the underground beam and the lower surface of the first-floor slab, and a door which allows access to the inside of the sealing body and the first floor of the building above the sealing body. Is provided.

【0009】[0009]

【作用】請求項1の建物基礎部の構造は次のような施工
手順で構築され得る。まず、建物を構築すべき敷地内
で、地中梁を設けるべき梁領域およびこの梁領域の内側
に挟まれた領域の地盤を掘削して、上記各領域を含む平
坦な溝を形成する。次に、上記溝内で上記梁領域に挟ま
れた領域に、この溝の深さを越える高さを有する中空の
密閉箱体を、底面を略全面的に地盤に接して配設する。
次に、上記梁領域の外側の溝底に上記密閉箱体の高さを
越える板状の型枠を立設すると共に、上記梁領域と上記
密閉箱体の上とにそれぞれ地中梁用と1階スラブ用の鉄
筋を組む。次に、上記型枠内にコンクリートを流し込ん
で、流しこんだコンクリートによって上記密閉箱体と型
枠との隙間に地中梁を形成すると同時に上記密閉箱体上
に1階スラブを形成する。このように地中梁と1階スラ
ブとが1回のコンクリート打設によって同時に形成され
るので、従来に比して、施工工程が単純化される。すな
わち、梁領域に挟まれた領域を埋め戻す作業と、上記梁
領域の内側に1階スラブや小梁用の型枠を設置したり取
り外したりする作業が省略される。これにより、施工期
間が短縮される。しかも、型枠を立設するのは建物外周
だけの作業となる一方、上記地中梁と1階スラブ用の鉄
筋組は建物の内側での作業となるので、前者を担当する
大工と後者を担当する鉄筋工との交錯が生じなくなる。
したがって、型枠立設と鉄筋組とを並行して進めること
ができ、さらに施工期間が短くなる。また、上記型枠内
にコンクリートを流し込む工程で、密閉箱体は底面が略
全面的に地盤に接しているので、上記密閉箱体に対して
浮力が発生することがない。したがって、密閉箱体のた
めのアンカーが省略され、または簡単なもので済ませら
れる。また、この密閉箱体は密閉体であるから、その内
部にコンクリートが浸入する心配もない。したがって、
コンクリート打設作業が短時間で円滑に行われる。ま
た、施工開始時に形成した溝は、上記地中梁の外側(建
物外周)の部分だけを埋め戻せば良く、地中梁の内側の
部分を埋め戻す手間が省略される。これらの結果とし
て、この建物基礎部の構造は、単純な工程でもって短期
間に構築される。また、この建物基礎部の構造では、地
中梁に囲まれた領域に、この地中梁の内側側面および上
記1階スラブの下面に接する中空の剛性を有する密閉箱
体が配設されているので、この密閉箱体の剛性によって
上記地中梁の剛性が高められる。これにより、上記地中
梁のうち地中に埋設される部分の長さを短くでき、施工
開始時に形成する溝の深さを浅くすることが可能とな
る。
The structure of the building foundation of claim 1 can be constructed by the following construction procedure. First, in a site where a building is to be constructed, a beam region in which an underground beam is to be provided and a region sandwiched inside the beam region are excavated to form a flat groove including each of the above regions. Next, in the region sandwiched by the beam regions in the groove, a hollow closed box body having a height exceeding the depth of the groove is arranged with its bottom surface substantially in contact with the ground.
Next, a plate-shaped formwork that exceeds the height of the closed box body is erected on the groove bottom outside the beam area, and for the underground beam on the beam area and the closed box body, respectively. Assemble the reinforcing bar for the 1st floor slab. Next, concrete is poured into the mold to form an underground beam in a gap between the closed box and the mold by the poured concrete, and at the same time, a first floor slab is formed on the closed box. In this way, the underground beam and the first floor slab are simultaneously formed by one-time concrete placing, so that the construction process is simplified as compared with the conventional method. That is, the work of backfilling the region sandwiched between the beam regions and the work of installing or removing the formwork for the first floor slab or the girder inside the beam region are omitted. This reduces the construction period. Moreover, while the formwork is erected only on the outer periphery of the building, the above-mentioned underground beam and the reinforcing bar for the first floor slab are the work inside the building, so the carpenter who is in charge of the former and the latter No more crossing with the reinforcing bar in charge.
Therefore, the form erection and the reinforcing bar assembly can be advanced in parallel, and the construction period can be shortened. Further, in the step of pouring concrete into the mold, since the bottom surface of the closed box body is almost entirely in contact with the ground, buoyancy is not generated in the closed box body. Therefore, the anchor for the closed box can be omitted or simplified. Further, since this closed box body is a closed body, there is no concern that concrete will enter the inside thereof. Therefore,
Concrete placing work can be done smoothly in a short time. In addition, the groove formed at the start of construction is required to backfill only the portion on the outer side (outer periphery of the building) of the underground beam, and the labor of backfilling the portion on the inner side of the underground beam is omitted. As a result of these, the structure of the building foundation is constructed in a short period of time with a simple process. Further, in the structure of the building foundation, a hollow rigid closed box which is in contact with the inner side surface of the underground beam and the lower surface of the first floor slab is disposed in the area surrounded by the underground beam. Therefore, the rigidity of the underground beam is enhanced by the rigidity of the closed box body. This makes it possible to shorten the length of the portion of the underground beam to be buried in the ground, and to make the depth of the groove formed at the start of construction shallow.

【0010】請求項2の建物基礎部の構造は、請求項1
の建物基礎部の構造と同様の手順で構築され得る。した
がって、請求項1と同様に、単純な工程でもって短期間
に構築される。また、密閉箱体の剛性によって地中梁の
剛性が高められるので、上記地中梁のうち地中に埋設さ
れる部分の長さを短くでき、施工開始時に形成する溝の
深さを浅くすることが可能となる。しかも、この建物基
礎部の構造では、上記密閉箱体の上部に、この密閉箱体
内部と建物の1階との出入りを可能にする扉が設けられ
ているので、この密閉箱体内部が様々な用途、例えば床
下収納庫などに使用可能となる。
The structure of the building foundation of claim 2 is the structure of claim 1.
It can be constructed by the same procedure as the structure of the building foundation of. Therefore, like the first aspect, it is constructed in a short period of time with simple steps. Further, since the rigidity of the underground beam is enhanced by the rigidity of the closed box body, the length of the portion of the underground beam embedded in the ground can be shortened, and the depth of the groove formed at the start of construction is shallow. It becomes possible. Moreover, in the structure of the building foundation, a door is provided above the closed box to allow access to the inside of the closed box and the first floor of the building. It can be used for various purposes, such as an underfloor storage.

【0011】請求項3の建物基礎部の構造は次のような
施工手順で構築され得る。まず、建物を構築すべき敷地
内で、地中梁を設けるべき梁領域およびこの梁領域の内
側に挟まれた領域の地盤を掘削して、上記各領域を含む
平坦な溝を形成する。次に、上記溝内で上記梁領域に挟
まれた領域に、この溝の深さを越える高さを有する中空
の密閉体を、地盤に設置して配設する。次に、上記梁領
域の外側の溝底に上記密閉体の高さを越える板状の型枠
を立設すると共に、上記梁領域と上記密閉体の上とにそ
れぞれ地中梁用と1階スラブ用の鉄筋を組む。次に、上
記型枠内にコンクリートを流し込んで、流しこんだコン
クリートによって上記密閉体と型枠との隙間に地中梁を
形成すると同時に上記密閉体上に1階スラブを形成す
る。このように地中梁と1階スラブとが1回のコンクリ
ート打設によって同時に形成されるので、従来に比し
て、施工工程が単純化される。すなわち、梁領域に挟ま
れた領域を埋め戻す作業と、上記梁領域の内側に1階ス
ラブや小梁用の型枠を設置したり取り外したりする作業
が省略される。これにより、施工期間が短縮される。し
かも、型枠を立設するのは建物外周だけの作業となる一
方、上記地中梁と1階スラブ用の鉄筋組は建物の内側で
の作業となるので、前者を担当する大工と後者を担当す
る鉄筋工との交錯が生じなくなる。したがって、型枠立
設と鉄筋組とを並行して進めることができ、さらに施工
期間が短くなる。また、型枠内にコンクリートを流し込
む工程で、密閉体の内部にコンクリートが浸入する心配
がないので、コンクリート打設作業が短時間で円滑に行
われる。また、施工開始時に形成した溝は、上記地中梁
の外側(建物外周)の部分だけを埋め戻せば良く、地中梁
の内側の部分を埋め戻す手間が省略される。これらの結
果として、この建物基礎部の構造は、単純な工程でもっ
て短期間に構築される。また、この建物基礎部の構造で
は、地中梁に囲まれた領域に、この地中梁の内側側面お
よび上記1階スラブの下面に接する中空の密閉体が配設
されているので、この密閉体の剛性によって上記地中梁
の剛性が高められる。これにより、上記地中梁のうち地
中に埋設される部分の長さを短くでき、施工開始時に形
成する溝の深さを浅くすることが可能となる。しかも、
この建物基礎部の構造では、上記密閉体の上部に、この
密閉体内部と建物の1階との出入りを可能にする扉が設
けられているので、この密閉体内部が様々な用途、例え
ば床下収納庫などに使用可能となる。
The structure of the building foundation of claim 3 can be constructed by the following construction procedure. First, in a site where a building is to be constructed, a beam region in which an underground beam is to be provided and a region sandwiched inside the beam region are excavated to form a flat groove including each of the above regions. Next, in the region sandwiched by the beam regions in the groove, a hollow hermetic body having a height exceeding the depth of the groove is installed and disposed on the ground. Next, a plate-shaped formwork that exceeds the height of the sealing body is erected on the groove bottom outside the beam area, and the beam area and the first floor are provided on the beam area and the sealing body, respectively. Assemble the rebar for the slab. Next, concrete is poured into the formwork, and an underground beam is formed in the gap between the sealing body and the formwork by the poured concrete, and at the same time, a first floor slab is formed on the sealing body. In this way, the underground beam and the first floor slab are simultaneously formed by one-time concrete placing, so that the construction process is simplified as compared with the conventional method. That is, the work of backfilling the region sandwiched between the beam regions and the work of installing or removing the formwork for the first floor slab or the girder inside the beam region are omitted. This reduces the construction period. Moreover, while the formwork is erected only on the outer periphery of the building, the above-mentioned underground beam and the reinforcing bar assembly for the first floor slab are the work inside the building, so the carpenter in charge of the former and the latter No more crossing with the reinforcing bar in charge. Therefore, the form erection and the reinforcing bar assembly can be advanced in parallel, and the construction period can be further shortened. Further, in the step of pouring the concrete into the mold, there is no concern that the concrete will enter the inside of the sealed body, so that the concrete placing work can be smoothly performed in a short time. In addition, the groove formed at the start of construction is required to backfill only the portion on the outer side (outer periphery of the building) of the underground beam, and the labor of backfilling the portion on the inner side of the underground beam is omitted. As a result of these, the structure of the building foundation is constructed in a short period of time with a simple process. In addition, in the structure of this building foundation, since a hollow sealing body that is in contact with the inner side surface of the underground beam and the lower surface of the first floor slab is arranged in the area surrounded by the underground beam, The rigidity of the body beam increases the rigidity of the underground beam. This makes it possible to shorten the length of the portion of the underground beam to be buried in the ground, and to make the depth of the groove formed at the start of construction shallow. Moreover,
In the structure of the building foundation, a door is provided on the upper part of the above-mentioned hermetically sealed body so that the inside of the hermetically sealed body and the first floor of the building can be moved in and out. It can be used as a storage cabinet.

【0012】[0012]

【実施例】以下、この発明の建物基礎部の構造を実施例
により詳細に説明する。
EXAMPLES The structure of the building foundation of the present invention will be described in detail below with reference to examples.

【0013】図1は一実施例の建物基礎部の断面構造を
示している。この建物基礎部は、建物外周に沿ってこの
断面に垂直に延びる地中梁1,2と、この地中梁1,2上
に形成された1階スラブ3を備えている。地中梁1,2
は、剛性を持たせるために下部が地中に埋設され、上部
だけが地面9の上に出ている。地中梁1,2に囲まれた
領域には、剛性を有する密閉箱体として直方体状をなす
3つの中空箱体6,7,8が互いに離間して配設されてい
る。各中空箱体6,7,8の上面は1階スラブ3の下面3
bに接し、両側の中空箱体6,8の外側側面は地中梁1,
2の内側側面に接している。また、各中空箱体6,7,8
の下面は略全面的に溝10の底の地盤に接している。上
記中空箱体6,7,8の隙間には小梁4,5が密接して形
成されている。上記1階スラブ3、地中梁1,2および
小梁4,5は、鉄筋コンクリートによって一体に形成さ
れている。また、各中空箱体6,7,8の上部には、1階
スラブ3の開口を通して、中空箱体6,7,8内部と建物
1階との出入りを可能にする扉21,22,23が設けら
れている。
FIG. 1 shows a sectional structure of a building foundation portion according to one embodiment. The building foundation includes underground beams 1 and 2 extending along the outer periphery of the building and perpendicular to the cross section, and a first floor slab 3 formed on the underground beams 1 and 2. Underground beams 1, 2
In order to have rigidity, the lower part is buried in the ground, and only the upper part is above the ground 9. In a region surrounded by the underground beams 1 and 2, three hollow box bodies 6, 7 and 8 each having a rectangular parallelepiped shape as a closed box body having rigidity are arranged separately from each other. The upper surface of each hollow box body 6, 7, 8 is the lower surface 3 of the first floor slab 3.
The outer side surfaces of the hollow box bodies 6 and 8 on both sides are in contact with b
It touches the inner side surface of 2. Also, each hollow box body 6, 7, 8
The lower surface of is almost entirely in contact with the ground at the bottom of the groove 10. Beams 4 and 5 are closely formed in the gaps between the hollow boxes 6, 7 and 8. The first floor slab 3, the underground beams 1, 2 and the small beams 4, 5 are integrally formed of reinforced concrete. In addition, the doors 21, 22, 23 that allow the inside and outside of the hollow boxes 6, 7, 8 and the building to enter and exit through the opening of the first floor slab 3 are provided above the hollow boxes 6, 7, 8. Is provided.

【0014】上記建物基礎部は、まず、基礎杭13,1
4を打設しておき、以下、図4に示す施工手順にしたが
って次のようにして構築される。まず、図1に示すよう
に、地中梁1,2を設けるべき梁領域A,Bおよびこの梁
領域A,Bに挟まれた領域の地盤を掘削して、上記各領
域を含む平坦な溝10を形成する(S1)。なお、梁領域
A,Bの外側(建物外周側)の溝側面は、従来と同様にテ
ーパーを有する状態となる。次に、上記溝10の底部
で、梁領域A,Bに砂利(割栗)31,32を敷設するとと
もに、梁領域A,Bに挟まれた領域にアンカー15,1
6,17をセットする(S2,S3)。これらのアンカー1
5,16,17は、中空箱体6,7,8を溝10の底部に固
定する働きをする。次に、梁領域A,Bにそれぞれ捨コ
ンクリート33,34を打設する(S4)。続いて、上記
梁領域A,Bに囲まれた領域に、この溝10の深さを越
える高さを有する中空箱体6,7,8を、底面を略全面的
に地盤に接して配設する(S5)。次に、上記梁領域A,
Bの外側の溝底に上記中空箱体6,7,8の高さを越える
板状の型枠を立設する。これと並行して、梁領域A,B
内および中空箱体6,7,8の上に、それぞれ地中梁用,
1階スラブ用の鉄筋を組む。同時に、中空箱体6と7,
7と8の隙間にそれぞれ小梁用の鉄筋を組む(S6)。こ
の時、鉄筋工は中空箱体6,7,8の上に乗って作業でき
るので、能率良く作業することができる。次に、上記型
枠内にコンクリートを流し込んで、流しこんだコンクリ
ートによって上記中空箱体6,8とその外側の型枠との
隙間に地中梁1,2を形成するとともに、上記中空箱体
6,7,8上に1階スラブ3を形成する。同時に、上記中
空箱体6,7,8の隙間に小梁4,5を形成する(S7)。
このとき、基礎11,12の鉄筋組み,コンクリート打設
も同時に行う。流し込んだコンクリートの養生を行った
後(S8)、上記型枠を取り外し、さらに地中梁1,2の
外側にテーパー状に一部残った溝10を埋め戻す。
The above-mentioned building foundation is first constructed of foundation piles 13 and 1.
4 is placed, and is constructed as follows according to the construction procedure shown in FIG. First, as shown in FIG. 1, excavating the beam regions A and B in which the underground beams 1 and 2 are to be provided and the region between the beam regions A and B are excavated, and a flat groove including each of the above regions is excavated. 10 is formed (S1). The groove side surfaces outside the beam regions A and B (outer peripheral side of the building) are tapered as in the conventional case. Next, at the bottom of the groove 10, gravel (split chestnuts) 31 and 32 are laid in the beam regions A and B, and anchors 15 and 1 are provided in the region sandwiched between the beam regions A and B.
Set 6 and 17 (S2, S3). These anchors 1
5, 16 and 17 serve to fix the hollow box bodies 6, 7 and 8 to the bottom of the groove 10. Next, waste concretes 33 and 34 are placed in the beam areas A and B, respectively (S4). Then, in the area surrounded by the beam areas A and B, hollow box bodies 6, 7, and 8 having a height exceeding the depth of the groove 10 are arranged with their bottom surfaces substantially in contact with the ground. Yes (S5). Next, the beam area A,
At the bottom of the groove on the outside of B, a plate-shaped mold which exceeds the height of the hollow box bodies 6, 7, 8 is erected. In parallel with this, beam areas A and B
On the inner and hollow boxes 6, 7 and 8 respectively,
Assemble the reinforcing bar for the 1st floor slab. At the same time, hollow boxes 6 and 7,
Reinforcing rods are assembled in the gaps 7 and 8 (S6). At this time, the reinforcing bar work can be carried out on the hollow boxes 6, 7 and 8 and work efficiently. Next, concrete is poured into the formwork, and the underground beams 1 and 2 are formed in the gap between the hollow box bodies 6 and 8 and the formwork outside thereof by the poured concrete. First floor slab 3 is formed on 6, 7, and 8. At the same time, the small beams 4, 5 are formed in the gaps between the hollow box bodies 6, 7, 8 (S7).
At this time, the reinforcing bars of the foundations 11 and 12 and concrete are placed at the same time. After the poured concrete is cured (S8), the form is removed, and the groove 10 partially remaining outside the underground beams 1 and 2 is backfilled.

【0015】このように、梁領域A,Bに挟まれた領域
に中空箱体6,7,8を配設することによって、地中梁
1,2と1階スラブ3、さらに小梁4,5を1回のコンク
リート打設によって同時に形成しているので、従来に比
して、施工工程を単純化できる。すなわち、梁領域A,
Bに挟まれた領域を埋め戻す作業と、梁領域A,Bの内
側に1階スラブ3,小梁4,5用の型枠を設置したり取り
外したりする作業を省略できる。これにより、施工期間
を短くすることができる。しかも、上記型枠を立設する
作業は建物外周だけで行う一方、地中梁と1階スラブ用
の鉄筋組は建物の内側で行うので、前者を担当する大工
と後者を担当する鉄筋工との交錯が生じなくなる。した
がって、型枠立設と鉄筋組とを並行して進めることがで
き、さらに施工期間が短くなる。また、この中空箱体
6,7,8は密閉体であるから、その内部にコンクリー
トが浸入する心配がなく、コンクリート打設作業を短時
間で円滑に行うことができる。実際には、施工期間を1
0日乃至2週間短縮することができる。また、施工開始
時(S1)に形成した溝10は、上記地中梁1,2の外
側(建物外周)の部分だけを埋め戻せば良く、地中梁
1,2の内側の部分を埋め戻す手間を省略することがで
きる。なお、この例では、上記型枠内にコンクリートを
流し込む工程で、中空箱体6,7,8は底面が略全面的に
地盤に接しているので、中空箱体6,7,8に対して浮力
が発生することがない。したがって、中空箱体6,7,8
についてのアンカー15,16,17の本数を減らした
り、極端な場合にはアンカーを設けず、アンカーをセッ
トするための作業を省略したりすることができる。
As described above, by arranging the hollow boxes 6, 7, 8 in the region sandwiched between the beam regions A, B, the underground beams 1, 2 and the first floor slab 3, and further the small beam 4, Since 5 is formed at the same time by one-time concrete pouring, the construction process can be simplified as compared with the conventional method. That is, the beam area A,
It is possible to omit the work of backfilling the region sandwiched between B and the work of installing and removing the formwork for the first floor slab 3, the joists 4 and 5 inside the beam regions A and B. Thereby, the construction period can be shortened. Moreover, while the work to erect the formwork is performed only on the outer periphery of the building, the underground beam and the reinforcing bar assembly for the first floor slab are performed inside the building, so the carpenter in charge of the former and the steel bar worker in charge of the latter are The intersection of will not occur. Therefore, the form erection and the reinforcing bar assembly can be advanced in parallel, and the construction period can be shortened. Further, since the hollow box bodies 6, 7 and 8 are closed bodies, there is no concern that concrete will enter the inside thereof, and the concrete placing work can be carried out smoothly in a short time. Actually, the construction period is 1
It can be shortened from 0 days to 2 weeks. In addition, the groove 10 formed at the start of construction (S1) needs to be filled only in the portion outside the underground beams 1 and 2 (outer periphery of the building), and is filled in the portion inside the underground beams 1 and 2. You can save the trouble. In this example, since the bottoms of the hollow boxes 6, 7, 8 are almost entirely in contact with the ground in the step of pouring concrete into the formwork, the hollow boxes 6, 7, 8 are Buoyancy does not occur. Therefore, the hollow box body 6, 7, 8
It is possible to reduce the number of the anchors 15, 16 and 17 for the above, or to omit the work for setting the anchor without providing the anchor in an extreme case.

【0016】また、構築した建物基礎部は、地中梁1,
2の内側側面に中空箱体6,8の外側側面が接し、1階
スラブ3の下面3bに中空箱体6,7,8が接した状態と
なる。したがって、この中空箱体6,7,8の剛性によっ
て地中梁1,2の剛性を高めることができる。また、こ
れにより、地中梁A,Bの地中に埋設される部分の長さ
を短くでき、施工開始の際に形成する溝10の深さを浅
くすることができる。また、1階スラブ3の直下に密閉
された中空箱体6,7,8を設けているので、従来と異な
り、1階床下に空気層が形成でき、したがって、1階床
の保温性を向上させることができる。
In addition, the constructed building foundation is composed of underground beams 1,
The outer side surfaces of the hollow box bodies 6 and 8 are in contact with the inner side surface of 2, and the hollow box bodies 6, 7, and 8 are in contact with the lower surface 3b of the first floor slab 3. Therefore, the rigidity of the underground beams 1, 2 can be increased by the rigidity of the hollow boxes 6, 7, 8. Further, this makes it possible to shorten the length of the portion of the underground beams A and B to be buried in the ground, and to make the depth of the groove 10 formed at the start of construction shallow. In addition, since the closed hollow boxes 6, 7, and 8 are provided directly below the first-floor slab 3, an air layer can be formed under the first-floor, unlike the conventional case, thus improving the heat retention of the first-floor. Can be made.

【0017】また、上記中空箱体6,7,8の上部に、こ
の中空箱体6,7,8内部と建物の1階との出入りを可能
にする扉21,22,23を設けているので、この中空箱
体6,7,8内部を様々な用途に使用することができる。
例えば、床下収納庫、配管ピット、点検ピット、涌水ピ
ット、貯水槽、設備機械室などに利用することができ
る。
Further, doors 21, 22 and 23 are provided on the upper parts of the hollow boxes 6, 7 and 8 to allow access to and from the interior of the hollow boxes 6, 7 and 8 and the first floor of the building. Therefore, the inside of the hollow box bodies 6, 7 and 8 can be used for various purposes.
For example, it can be used for an underfloor storage, a piping pit, an inspection pit, a water pit, a water tank, an equipment machine room, and the like.

【0018】なお、上に述べた例では密閉箱体として立
方体状の中空箱体6,7,8を配設したが、当然ながらこ
れに限られるものではない。図2に示すように、密閉体
として両端面が密閉された円筒状の中空管46,47,4
8を互いに隙間を空けて配設しても良い。上記中空管4
6,47,48は、図示のように中心軸の向きを揃えて並
べても良く、中心軸が直交するように並べても良い。あ
るいは斜め方向に並べても良い。この場合も、上記中空
管46,47,48の上部に、この中空管46,47,48
内部と建物の1階との出入りを可能にする扉21,22,
23を設けておくことにより、この中空管46,47,4
8内部を様々な用途に使用することができる。例えば、
床下収納庫、配管ピット、点検ピット、涌水ピット、貯
水槽、設備機械室などに利用することができる。
In the above-mentioned example, the cubic hollow boxes 6, 7 and 8 are arranged as the closed box, but the present invention is not limited to this. As shown in FIG. 2, a cylindrical hollow tube 46, 47, 4 whose both end faces are hermetically sealed as a hermetically sealed body.
8 may be arranged with a gap therebetween. The hollow tube 4
6, 47 and 48 may be arranged so that the directions of the central axes are aligned as shown in the figure, or may be arranged so that the central axes are orthogonal to each other. Alternatively, they may be arranged diagonally. Also in this case, the hollow tubes 46, 47, 48 are provided above the hollow tubes 46, 47, 48.
Doors 21,22 that allow access to and from the interior and the first floor of the building
By providing 23, this hollow tube 46, 47, 4
8 The inside can be used for various purposes. For example,
It can be used for underfloor storage, piping pits, inspection pits, water pits, water storage tanks, equipment machine rooms, etc.

【0019】また、中空管46,47,48(または中空
箱体6,7,8)を溝10の底に直接設けるのでなく、図
3に示すように、中空管46,47,48の下にスラブ8
3を形成しても良い。このようにした場合、上下のスラ
ブ3,83を地中梁1,2と連続させることができ(一枚
の分厚いスラブ中に中空管空間を形成した構造とも言え
る。)、地中梁1,2の剛性を高めることができる。そ
の施工は、中空管46,47,48(または中空箱体6,
7,8)を溝10にセットする前に、上記下側のスラブ
83用の鉄筋組作業を加えるだけで良い。
Further, instead of directly providing the hollow tubes 46, 47, 48 (or the hollow box bodies 6, 7, 8) at the bottom of the groove 10, as shown in FIG. 3, the hollow tubes 46, 47, 48 are provided. Under the slab 8
3 may be formed. In this case, the upper and lower slabs 3 and 83 can be connected to the underground beams 1 and 2 (it can be said that a hollow tube space is formed in one thick slab). It is possible to increase the rigidity of Nos. 2 and 2. The construction is performed by hollow tubes 46, 47, 48 (or hollow box body 6,
Prior to setting (7, 8) in the groove 10, all that is required is to add the reinforcing bar work for the lower slab 83.

【0020】また、上に述べた3例は、密閉箱体として
の中空箱体6,7,8の間、密閉体としての中空管46,
47,48の間にそれぞれ隙間を設けたが、これに限ら
れるものではなく、各中空箱体または中空管を密接させ
て小梁4,5を省略することもできる。
In the above-mentioned three examples, between the hollow box bodies 6, 7 and 8 as the closed box body, and the hollow tube 46 and the hollow tube body as the closed body.
Although a gap is provided between 47 and 48, the present invention is not limited to this, and the hollow beams or hollow tubes may be brought into close contact with each other to omit the beams 4 and 5.

【0021】[0021]

【発明の効果】以上より明らかなように、請求項1に記
載の建物基礎部の構造は、地中梁と1階スラブを有する
建物基礎部の構造であって、上記地中梁と1階スラブと
は鉄筋コンクリートによって一体に形成され、上記地中
梁に挟まれた領域に、底面が略全面的に地盤に接し、こ
の地中梁の内側側面および上記1階スラブの下面に接す
る中空の剛性を有する密閉箱体が配設されているので、
地中梁と1階スラブとを1回のコンクリート打設によっ
て同時に形成できる。したがって、従来に比して、施工
工程を単純化できる。すなわち、梁領域に挟まれた領域
を埋め戻す作業と、上記梁領域の内側に1階スラブや小
梁用の型枠を設置したり取り外したりする作業を省略で
きる。これにより、施工期間を短縮できる。しかも、型
枠を立設するのは建物外周だけの作業となる一方、上記
地中梁と1階スラブ用の鉄筋組は建物の内側での作業と
なるので、前者を担当する大工と後者を担当する鉄筋工
との交錯が生じなくなる。したがって、型枠立設と鉄筋
組とを並行して進めることができ、さらに施工期間を短
くできる。また、上記型枠内にコンクリートを流し込む
工程で、密閉箱体は底面が略全面的に地盤に接している
ので、上記密閉箱体に対して浮力が発生することがな
い。したがって、密閉箱体のためのアンカーを省略した
り、簡単なもので済ませたりすることができる。また、
密閉箱体は密閉体であるから、その内部にコンクリート
が浸入する心配がない。したがって、コンクリート打設
作業を短時間で円滑に行うことができる。また、施工開
始時に形成した溝は、上記地中梁の外側(建物外周)の部
分だけを埋め戻せば良く、地中梁の内側の部分を埋め戻
す手間を省略できる。このように、この建物基礎部の構
造は、単純な工程でもって短期間に構築することができ
る。また、この建物基礎部の構造では、地中梁に囲まれ
た領域に、この地中梁の内側側面および上記1階スラブ
の下面に接する中空の剛性を有する密閉箱体が配設され
ているので、この密閉箱体の剛性によって上記地中梁の
剛性を高めることができる。これにより、上記地中梁の
うち地中に埋設される部分の長さを短くでき、施工開始
時に形成する溝の深さを浅くすることができる。
As is apparent from the above, the structure of the building foundation according to claim 1 is the structure of the building foundation having the underground beam and the first floor slab. The slab is formed integrally with reinforced concrete, and the bottom surface is almost entirely in contact with the ground in the area sandwiched by the underground beams. Since a closed box body having is arranged,
The underground beam and the first floor slab can be simultaneously formed by one concrete placing. Therefore, the construction process can be simplified as compared with the related art. That is, it is possible to omit the work of backfilling the region sandwiched between the beam regions and the work of installing or removing the formwork for the first floor slab or the beam on the inside of the beam region. Thereby, the construction period can be shortened. Moreover, while the formwork is erected only on the outer periphery of the building, the above-mentioned underground beam and the reinforcing bar for the first floor slab are the work inside the building, so the carpenter who is in charge of the former and the latter No more crossing with the reinforcing bar in charge. Therefore, the formwork erection and the reinforcing bar assembly can be advanced in parallel, and the construction period can be further shortened. Further, in the step of pouring concrete into the mold, since the bottom surface of the closed box body is almost entirely in contact with the ground, buoyancy is not generated in the closed box body. Therefore, the anchor for the closed box can be omitted or a simple one can be used. Also,
Since the closed box is a closed body, there is no concern that concrete will enter the inside. Therefore, the concrete pouring work can be smoothly performed in a short time. In addition, the groove formed at the start of construction is required to backfill only the portion on the outer side (outer periphery of the building) of the underground beam, and the labor for backfilling the portion on the inner side of the underground beam can be omitted. In this way, the structure of the building foundation can be constructed in a short time by a simple process. Further, in the structure of the building foundation, a hollow rigid closed box which is in contact with the inner side surface of the underground beam and the lower surface of the first floor slab is disposed in the area surrounded by the underground beam. Therefore, the rigidity of the underground beam can be increased by the rigidity of the closed box body. As a result, the length of the portion of the underground beam embedded in the ground can be shortened, and the depth of the groove formed at the start of construction can be made shallow.

【0022】請求項2の建物基礎部の構造は、請求項1
と同様に、単純な工程でもって短期間に構築できる。ま
た、密閉箱体の剛性によって地中梁の剛性を高めること
ができるので、上記地中梁のうち地中に埋設される部分
の長さを短くでき、施工開始時に形成する溝の深さを浅
くすることができる。しかも、上記密閉箱体の上部に、
この密閉箱体内部と建物の1階との出入りを可能にする
扉が設けられているので、この密閉箱体内部を様々な用
途、例えば床下収納庫などに使用することができる。
The structure of the building foundation of claim 2 is the structure of claim 1.
Similar to, it can be built in a short time with simple steps. Also, since the rigidity of the underground beam can be increased by the rigidity of the closed box, the length of the portion of the underground beam embedded in the ground can be shortened, and the depth of the groove formed at the start of construction can be reduced. Can be shallow. Moreover, at the top of the sealed box,
Since a door is provided to allow access to and from the inside of the closed box and the first floor of the building, the inside of the closed box can be used for various purposes such as an underfloor storage.

【0023】また、請求項3に記載の建物基礎部の構造
は、地中梁と1階スラブを有する建物基礎部の構造であ
って、上記地中梁と1階スラブとは鉄筋コンクリートに
よって一体に形成され、上記地中梁に挟まれた領域に、
この地中梁の内側側面および上記1階スラブの下面に接
する中空の密閉体が配設されているので、地中梁と1階
スラブとを1回のコンクリート打設によって同時に形成
できる。したがって、従来に比して、施工工程を単純化
できる。すなわち、梁領域に挟まれた領域を埋め戻す作
業と、上記梁領域の内側に1階スラブや小梁用の型枠を
設置したり取り外したりする作業を省略できる。これに
より、施工期間を短縮できる。しかも、型枠を立設する
のは建物外周だけの作業となる一方、上記地中梁と1階
スラブ用の鉄筋組は建物の内側での作業となるので、前
者を担当する大工と後者を担当する鉄筋工との交錯が生
じなくなる。したがって、型枠立設と鉄筋組とを並行し
て進めることができ、さらに施工期間を短くできる。ま
た、型枠内にコンクリートを流し込む工程で、密閉体の
内部にコンクリートが浸入する心配がないので、コンク
リート打設作業を短時間で円滑に行うことができる。ま
た、施工開始時に形成した溝は、上記地中梁の外側(建
物外周)の部分だけを埋め戻せば良く、地中梁の内側の
部分を埋め戻す手間を省略できる。このように、この建
物基礎部の構造は、単純な工程でもって短期間に構築す
ることができる。また、この建物基礎部の構造では、地
中梁に囲まれた領域に、この地中梁の内側側面および上
記1階スラブの下面に接する中空の密閉体が配設されて
いるので、この密閉体の剛性によって上記地中梁の剛性
を高めることができる。これにより、上記地中梁のうち
地中に埋設される部分の長さを短くでき、施工開始時に
形成する溝の深さを浅くすることができる。しかも、こ
の建物基礎部の構造では、上記密閉体の上部に、この密
閉体内部と建物の1階との出入りを可能にする扉が設け
られているので、この密閉体内部を様々な用途、例えば
床下収納庫などに使用することができる。
Further, the structure of the building foundation according to claim 3 is a structure of a building foundation having an underground beam and a first floor slab, and the underground beam and the first floor slab are integrally made of reinforced concrete. In the area that is formed and sandwiched by the underground beams,
Since the hollow hermetic body that is in contact with the inner side surface of the underground beam and the lower surface of the first floor slab is provided, the underground beam and the first floor slab can be simultaneously formed by one-time concrete pouring. Therefore, the construction process can be simplified as compared with the related art. That is, it is possible to omit the work of backfilling the region sandwiched between the beam regions and the work of installing or removing the formwork for the first floor slab or the beam on the inside of the beam region. Thereby, the construction period can be shortened. Moreover, while the formwork is erected only on the outer periphery of the building, the above-mentioned underground beam and the reinforcing bar for the first floor slab are the work inside the building, so the carpenter who is in charge of the former and the latter No more crossing with the reinforcing bar in charge. Therefore, the formwork erection and the reinforcing bar assembly can be advanced in parallel, and the construction period can be further shortened. Further, in the step of pouring the concrete into the mold, there is no concern that the concrete will enter the inside of the closed body, so that the concrete placing work can be smoothly performed in a short time. In addition, the groove formed at the start of construction is required to backfill only the portion on the outer side (outer periphery of the building) of the underground beam, and the labor for backfilling the portion on the inner side of the underground beam can be omitted. In this way, the structure of the building foundation can be constructed in a short time by a simple process. Further, in the structure of the building foundation, since a hollow hermetic body that is in contact with the inner side surface of the underground beam and the lower surface of the first floor slab is arranged in the area surrounded by the underground beam, The rigidity of the body beam can increase the rigidity of the underground beam. As a result, the length of the portion of the underground beam embedded in the ground can be shortened, and the depth of the groove formed at the start of construction can be made shallow. Moreover, in the structure of the building foundation, since a door is provided on the upper part of the sealed body to allow entry and exit of the sealed body and the first floor of the building, the sealed body has various uses, For example, it can be used as an underfloor storage.

【図面の簡単な説明】[Brief description of drawings]

【図1】 この発明の一実施例の建物基礎部の構造を示
す断面図である。
FIG. 1 is a cross-sectional view showing a structure of a building foundation portion according to an embodiment of the present invention.

【図2】 この発明の別の実施例の建物基礎部の構造を
示す断面図である。
FIG. 2 is a cross-sectional view showing a structure of a building foundation portion according to another embodiment of the present invention.

【図3】 この発明のさらに別の実施例の建物基礎部の
構造を示す断面図である。
FIG. 3 is a cross-sectional view showing a structure of a building foundation portion according to still another embodiment of the present invention.

【図4】 この発明の建物基礎部の構築方法を説明する
工程図である。
FIG. 4 is a process diagram for explaining a method of constructing a building foundation according to the present invention.

【図5】 従来の建物基礎部の構築方法を説明する工程
図である。
FIG. 5 is a process diagram illustrating a conventional method of constructing a building foundation.

【図6】 従来の建物基礎部の構造を示す平面図であ
る。
FIG. 6 is a plan view showing a structure of a conventional building foundation.

【図7】 図6におけるVII−VII線矢視断面を示す図で
ある。
7 is a view showing a cross section taken along the line VII-VII in FIG.

【図8】 図6におけるVIII−VIII線矢視断面を示す図
である。
8 is a view showing a cross section taken along the line VIII-VIII in FIG.

【符号の説明】[Explanation of symbols]

1,2 地中梁 3 1階スラブ 4,5 小梁 6,7,8 中空箱体 9 地面 10 溝 11,12 基礎 13,14 基礎杭 15,16,17 アンカー 21,22,23 扉 24,25 地中梁用の鉄筋 26 1階スラブ用の鉄筋 27,28 小梁用の鉄筋 31,32 砂利敷 33,34 捨コンクリート 46,47,48 中空管 1,2 Underground beam 3 1st floor slab 4,5 Small beam 6,7,8 Hollow box 9 Ground 10 Groove 11,12 Foundation 13,14 Foundation pile 15,16,17 Anchor 21,22,23 Door 24, 25 Reinforcing bars for underground beams 26 Reinforcing bars for first floor slabs 27,28 Reinforcing bars for small beams 31,32 Gravel floor 33,34 Waste concrete 46,47,48 Hollow pipe

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 昭47−15908(JP,A) 特開 昭60−43529(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-47-15908 (JP, A) JP-A-60-43529 (JP, A)

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地中梁と1階スラブを有する建物基礎部
の構造であって、 上記地中梁と1階スラブとは鉄筋コンクリートによって
一体に形成され、 上記地中梁に挟まれた領域に、底面が略全面的に地盤に
接し、この地中梁の内側側面および上記1階スラブの下
面に接する中空の剛性を有する密閉箱体が配設されてい
ることを特徴とする建物基礎部の構造。
1. A structure of a building foundation having an underground beam and a first floor slab, wherein the underground beam and the first floor slab are integrally formed by reinforced concrete, and are formed in an area between the underground beams. The bottom of the building has a hollow rigid box which is almost entirely in contact with the ground and is in contact with the inner side surface of the underground beam and the lower surface of the first floor slab. Construction.
【請求項2】 地中梁と1階スラブを有する建物基礎部
の構造であって、 上記地中梁と1階スラブとは鉄筋コンクリートによって
一体に形成され、 上記地中梁に挟まれた領域に、底面が略全面的に地盤に
接し、この地中梁の内側側面および上記1階スラブの下
面に接する中空の剛性を有する密閉箱体が配設され、 上記密閉箱体の上部に、この密閉箱体内部と上記建物の
1階との出入りを可能にする扉が設けられていることを
特徴とする建物基礎部の構造。
2. A structure of a building foundation having an underground beam and a first floor slab, wherein the underground beam and the first floor slab are integrally formed by reinforced concrete, and are formed in an area sandwiched between the underground beams. , A bottom surface is almost entirely in contact with the ground, and an inner side surface of the underground beam and a lower surface of the first floor slab are provided with a hollow rigid closed box body, and the closed box body is provided above the closed box body. A structure of a building foundation, characterized in that a door is provided to allow access to the inside of the box and the first floor of the building.
【請求項3】 地中梁と1階スラブを有する建物基礎部
の構造であって、 上記地中梁と1階スラブとは鉄筋コンクリートによって
一体に形成され、 上記地中梁に挟まれた領域に、この地中梁の内側側面お
よび上記1階スラブの下面に接する中空の密閉体が配設
され、 上記密閉体の上部に、この密閉体内部と上記建物の1階
との出入りを可能にする扉が設けられていることを特徴
とする建物基礎部の構造。
3. A structure of a building foundation having an underground girder and a first floor slab, wherein the underground girder and the first floor slab are integrally formed by reinforced concrete and are located in a region sandwiched by the underground girder. , A hollow hermetic body that is in contact with the inner side surface of the underground beam and the lower surface of the first-floor slab is provided, and allows the inside of the hermetic body and the first floor of the building to enter and exit above the hermetic body. The structure of the building foundation, which is characterized by having a door.
JP3098619A 1991-04-30 1991-04-30 Structure of building foundation Expired - Lifetime JP2509395B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3098619A JP2509395B2 (en) 1991-04-30 1991-04-30 Structure of building foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3098619A JP2509395B2 (en) 1991-04-30 1991-04-30 Structure of building foundation

Publications (2)

Publication Number Publication Date
JPH04330117A JPH04330117A (en) 1992-11-18
JP2509395B2 true JP2509395B2 (en) 1996-06-19

Family

ID=14224575

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3098619A Expired - Lifetime JP2509395B2 (en) 1991-04-30 1991-04-30 Structure of building foundation

Country Status (1)

Country Link
JP (1) JP2509395B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3746595B2 (en) * 1997-07-07 2006-02-15 三井住友建設株式会社 Floor construction method for freezer / refrigerated warehouse
KR102031416B1 (en) * 2017-08-23 2019-10-11 주식회사 포스코 Mat slab

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6043529A (en) * 1983-08-18 1985-03-08 Sekisui Prefab Homes Ltd Mat foundation and its construction

Also Published As

Publication number Publication date
JPH04330117A (en) 1992-11-18

Similar Documents

Publication Publication Date Title
US20160340855A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
EP0458703A1 (en) Prefabricated concrete basement and process for constructing the same
KR102208793B1 (en) Under ground structure using column wall and construction method thereof
WO2012096639A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
JP2000352296A (en) Method o constructing passage just under underground structure
JPH1113072A (en) Basement structural body, and construction method thereof
JP2509395B2 (en) Structure of building foundation
KR100462236B1 (en) panel for external underground wall of building, structure and construction method using the same
JPS5829922A (en) Constructing method for underground outer wall
JPH07103583B2 (en) Construction method for large span underground structure
JPS6145028B2 (en)
JPS6024249B2 (en) How to build a basement
JPH0748848A (en) Construction method for underground skeleton by inverted construction method
JP2022121831A (en) Foundation structure and foundation structure construction method
JPH0427018A (en) Construction of concrete assembly-type basement
JPS59653B2 (en) Foundation construction method for main pillars such as fences
JP2877896B2 (en) Concrete basement basement
JP2669708B2 (en) Concrete assembling basement skeleton structure
JPH04323417A (en) Base structure
JPH10280434A (en) Construction method for basement under application of outside waterproofing
JP2936492B2 (en) Concrete assembling basement and concrete assembling basement construction method
JPH0427077A (en) House with concrete built-up type basement
JPH0427021A (en) Structure of concrete assembly-type basement
JP2002266357A (en) Basement by means of precast concrete wall unit
JPH076204B2 (en) How to build an underground structure