JPS6043529A - Mat foundation and its construction - Google Patents

Mat foundation and its construction

Info

Publication number
JPS6043529A
JPS6043529A JP15062883A JP15062883A JPS6043529A JP S6043529 A JPS6043529 A JP S6043529A JP 15062883 A JP15062883 A JP 15062883A JP 15062883 A JP15062883 A JP 15062883A JP S6043529 A JPS6043529 A JP S6043529A
Authority
JP
Japan
Prior art keywords
slab
formwork
concrete
trench
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15062883A
Other languages
Japanese (ja)
Other versions
JPH0324525B2 (en
Inventor
Keiichi Tomiyama
冨山 恵一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui House Ltd
Original Assignee
Sekisui House Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui House Ltd filed Critical Sekisui House Ltd
Priority to JP15062883A priority Critical patent/JPS6043529A/en
Publication of JPS6043529A publication Critical patent/JPS6043529A/en
Publication of JPH0324525B2 publication Critical patent/JPH0324525B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

PURPOSE:To permit direct setting of interiors of floor on the upside of a slab by a method in which a formwork is assembled along the periphery of the slab, many steel pipes for forming a hollow are set horizontally in parallel, and concrete is placed in to the space surrounded by the formwork. CONSTITUTION:A trench 11 is excavated along the peripheral footing portion of a slab and cobble stones 12 are laid in the trench 11 and on the building land surrounded by the trench 11. A moisture-proof sheet 16 is then laid over the whole surface of the cobble stones 12 on the building land. A formwork 13 is assembled along the periphery of the slab, reinforcing bars 14 are set, many steel tubes 15 for forming a hollow are horizontally set in parallel, and concrete is placed into the space surrounded by the formwork 13. The upside of the slab is leveled to enable the floor interior, e.g., carpet, mat, etc., to be directly set on the upside of the slab.

Description

【発明の詳細な説明】 本発明は、べた基礎とその施工方法に関するものである
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a solid foundation and its construction method.

従来一般のべた基礎は、スラブ前面にねた。て地盤を掘
削し、散票、配筋を行った後、スラブと基礎梁部分に分
けて二回のコンクリート打設を行っている。しかし、こ
のような工法では、スラブ部分全面にわたって地盤を掘
削するため、残土処理の問題が生じ、又、残土の運搬・
排出のための費用がかさむ欠点がある。そこで、このよ
うな残土処理の問題を解決した工法として、第1図に示
す方法が考えられている。この第1図の工法では、基礎
梁11)の通る部分のみ溝(2)を掘削し、この溝(2
)及び該溝(2)によって囲まれる宅盤上に散票と配筋
を行った後、まずスラブ(3)部分のコンクリート打設
を行い、しかる後、基礎梁(1)及び間仕切基礎(4)
部分のコンクリートを打ち継ぎ、溝(2)の掘削によ;
て排出された土は、基礎外周部の旧地盤GLI上へ散布
して新地盤OL2を得るようにしている。
Conventional solid foundations lay on the front of the slab. After excavating the ground, placing slabs and reinforcing, concrete was poured twice for the slab and foundation beams. However, with this construction method, the ground is excavated over the entire surface of the slab, which creates problems in disposing of the remaining soil.
It has the disadvantage of being expensive to discharge. Therefore, the method shown in Figure 1 has been considered as a construction method that solves this problem of disposal of residual soil. In the construction method shown in Fig. 1, a trench (2) is excavated only in the part where the foundation beam 11) passes;
) and the groove (2), then concrete is placed on the slab (3), and then the foundation beam (1) and the partition foundation (4) are placed. )
By pouring concrete in the area and excavating the trench (2);
The discharged soil is spread over the old ground GLI around the outer periphery of the foundation to obtain new ground OL2.

この第1図の方法によると、基礎梁(1)の通る部分の
み掘削し、この掘削によって得られた土は全て外周へ散
布処理されることから、残土処理の問題が解決される利
点があるが、しかし、この工法においても、やはりスラ
ブ(3)と基礎梁(1)及び間仕切基礎(4)部分に分
けてコンクリートを打設するため、二面のコンクリート
打設が必要となり、しかも、基礎梁(11内側と間仕切
基礎(4)部分にも型枠を組まなければならず、型枠の
使用量が大となるとともに、工事期間中に雨が降ると、
基礎梁+11の内側に雨水が溜るため、水抜き処理を行
うことが必要となる等の欠点がある。
According to the method shown in Figure 1, only the area where the foundation beam (1) passes is excavated, and all the soil obtained through this excavation is distributed around the outside, which has the advantage of solving the problem of disposal of remaining soil. However, even with this construction method, concrete is poured separately into the slab (3), foundation beam (1), and partition foundation (4), so it is necessary to pour concrete on two sides. Formwork had to be built on the inside of the beam (11) and the partition foundation (4), which required a large amount of formwork, and if it rained during the construction period,
Rainwater accumulates inside the foundation beam +11, so there are drawbacks such as the need to drain water.

本発明は、上記従来の欠点を解消したべた基礎とその施
工方法を提供するものであって、その構成として本発明
のべた基礎は、内部に中空部が形成され、かつ、その上
面が、絨穂や畳等の床内装材を直接施工できるような平
面状とされていることを特徴とし、更に本発明の施工方
法は、地中へ埋め込まれる根入れ足部分のみを掘削して
溝を形成し、この溝によって囲まれる電盤上に配筋とと
もに中空部形成用の鋼管を配置してコンクリートを打設
し、しかる後該コンクリート上面を、絨稙や畳等の床内
装材を直接施工できるような平面状とすべく均らしを行
うことを特徴するものである。
The present invention provides a solid foundation and its construction method that eliminate the above-mentioned conventional drawbacks, and the solid foundation of the present invention has a hollow part formed inside and the upper surface of the solid foundation is made of carpet. The method of the present invention is characterized in that it has a flat shape that allows for direct construction of floor interior materials such as earwood and tatami mats, and furthermore, the construction method of the present invention involves forming a trench by excavating only the foot part to be embedded into the ground. Then, a steel pipe for forming a hollow part is placed along with reinforcement on the electric panel surrounded by this groove, and concrete is poured, and after that, floor interior materials such as carpet and tatami mats can be directly applied to the upper surface of the concrete. It is characterized by leveling to make it flat.

以下、本発明の構成をその施工順序に従って説明すると
、まず、第2図で示すように、必要な根入れ深さを確保
するため、スラブ外周の根入れ足部分に沿って、溝(1
1)を掘削し、この溝(11)及び該溝(11)によっ
て囲まれる電盤上に栗石(12)を敷く。
The structure of the present invention will be explained below according to the construction order. First, as shown in Fig. 2, in order to secure the necessary penetration depth, a groove (1
1) is excavated, and a chestnut stone (12) is laid on this groove (11) and the electrical panel surrounded by the groove (11).

次いで、第3図の如く、スラブ外周部に沿って型枠(1
3)を組み、かつ、配筋(14)を行うが、その際、中
空部形成用の多数の鋼管(15) (15)・・・を水
平に並列して配置する。このような鋼管(15)として
は、通常ワインディングパイプとよばれる薄肉鋼管が用
いられる。又、定盤部分の栗石(12)上には防湿シー
ト(16)が全面にわたって敷かれる。
Next, as shown in Figure 3, formwork (1
3) and perform reinforcement (14), at which time a large number of steel pipes (15) (15) for forming hollow parts are arranged horizontally in parallel. As such a steel pipe (15), a thin-walled steel pipe commonly called a winding pipe is used. Further, a moisture-proof sheet (16) is spread over the entire surface of the chestnut stone (12) on the surface plate.

上記のようにして、配筋<14)及び型枠(13)組み
を行い、鋼管(15)と防湿シー)、 (16)を設置
した後、型枠(13)によって囲まれる空間部に、第4
図の如くコンクリートを打設し、しかる後、スラブ(1
7)の上面(17a)をセルフレベリング材等により均
らして、該上面(17a)に絨穂或いは畳等の床内装材
を直接施工できるような平面状とするものである。尚、
鋼管(15)の端部は、コンクリートによって密封され
る。又、溝(11)内には、コンクリートの根入れ足(
18)が形成され、最後に、前記溝(11)を掘削して
得られた土は、この溝(11)の埋戻しを行なうととも
に、スラブ(17)外周の田地盤上へ散布して新地盤G
L2を得る。
After assembling the reinforcement <14) and formwork (13) as described above, and installing the steel pipe (15) and moisture-proof sheathing (16), in the space surrounded by the formwork (13), Fourth
Concrete is poured as shown in the diagram, and then the slab (1
7) The upper surface (17a) is leveled with a self-leveling material or the like to make it flat so that a flooring material such as carpet or tatami can be directly applied to the upper surface (17a). still,
The ends of the steel pipes (15) are sealed with concrete. Also, in the groove (11), there is a concrete foot (
18) is formed, and finally, the soil obtained by excavating the trench (11) is used to backfill this trench (11) and to spread it over the field ground around the outer periphery of the slab (17) to create a new soil. Ground G
Obtain L2.

本発明のべた基礎及びその施工方法は上記の通りである
から、掘削土量が少なく残土処理の問題がないという第
1図と同様の利点の他に次のような効果が得られる。
Since the solid foundation and its construction method of the present invention are as described above, in addition to the same advantages as shown in Fig. 1, in which the amount of excavated soil is small and there is no problem of disposal of remaining soil, the following effects can be obtained.

■、コンクリートの打設は一回ですみ、工事期間が大幅
に短縮される。
■Concrete pouring is only required once, significantly shortening the construction period.

■、スラブ上面がそのまま内装材を施工できるようにな
っているから、従来の如く基礎梁を突出させる必要がな
(、それ故、工事期間中に雨が降っても雨水が溜ること
がなく、水抜き処理が不要である。
■Since interior materials can be constructed on the top surface of the slab, there is no need to protrude the foundation beams like in the past (therefore, even if it rains during the construction period, rainwater will not accumulate, No water removal process is required.

■、スラブ部分と基礎梁部分に分けて二面のコンクリ−
゛ト打設を行う必要がなく、型枠はスラブ外周部のみに
組めばよいから、必要な型枠面積は、約三分の−と大幅
に減少する。
■ Concrete on two sides, divided into slab part and foundation beam part.
Since there is no need to perform concrete pouring and the formwork only needs to be assembled on the outer periphery of the slab, the required formwork area is significantly reduced by about a third.

■、前記の如くスラブ上面に直接床内装材等が施工でき
るから、束石や床組みが不要で、コストが大幅に減少す
る。
(2) As mentioned above, floor interior materials, etc. can be applied directly to the top surface of the slab, so there is no need for stacking stones or floor assemblies, and costs are significantly reduced.

■、同じ(、スラブ上面に直接床材等が施工できるから
、床振動等が全(なくなる。
■Same (because flooring materials can be installed directly on the top of the slab, floor vibrations, etc. are completely eliminated).

■、スラブ部分の肉厚が大きくなり、しかも中空のため
、保温性が高い。
■The thickness of the slab part is large and it is hollow, so it has high heat retention.

■、内部は中空となっているから、コンクリート量は、
従来のべた基礎より僅かに増えるだけであり、しかも、
中空部があることにより、重量はさほど大きくならず、
この種べた基礎が施工される軟弱地盤に用いたとしても
何等不都合はない。
■Since the interior is hollow, the amount of concrete is
It is only slightly more than the conventional solid foundation, and moreover,
Due to the hollow part, the weight is not very large,
There is no problem in using this type of solid foundation on soft ground.

■、スラブの裏面に防湿シートを敷けば、床下の湿気を
完全に排除することができる。
■By laying a moisture-proof sheet on the back of the slab, you can completely eliminate moisture under the floor.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は、従来のべた基礎を示す横断面図、第2図及び
第3図は、本発明べた基礎の施工方法を示す横断面図、
第4図は、本発明べた基礎の要部横断面図である。 (1,1) −溝、(14) −配筋、(15) −・
−鋼管、(]7)−スラブ、(17a)−スラブ上面、
(18) −根入れ足。 特許 出願人 積木ハウス 株式会社 代理人弁理士 樽 本 久 幸
FIG. 1 is a cross-sectional view showing a conventional solid foundation, and FIGS. 2 and 3 are cross-sectional views showing a method of constructing a solid foundation according to the present invention.
FIG. 4 is a cross-sectional view of the main part of the solid foundation of the present invention. (1,1) - Groove, (14) - Reinforcement, (15) -・
- steel pipe, (7) - slab, (17a) - upper surface of slab,
(18) - Root foot. Patent Applicant: Block House Co., Ltd. Representative Patent Attorney Hisashi Tarumoto

Claims (1)

【特許請求の範囲】 ■、内部に中空部が形成され、かつ、その上面が、絨穂
や畳等の床内装材を直接施工できるような平面状とされ
ていることを特徴とするべた基礎。 2、地中へ埋め込まれる根入れ足部分のみを掘削して溝
を形成し、この溝によって囲まれる宅盤上に配筋ととも
に中空部形成用の鋼管を配置してコンクリート打設し、
しかる後該コンクリート上面を、絨穂や畳等の床内装材
を直接施工できるような平面状とすべく均らしを行うこ
とを特徴とするべた基礎の施工方法。
[Scope of Claims] (1) A solid foundation characterized by having a hollow part formed inside and the upper surface of the solid foundation having a flat shape to which floor interior materials such as carpets and tatami mats can be directly applied. . 2. Excavate only the foot part to be embedded into the ground to form a trench, place reinforcing and steel pipes for forming hollow parts on the building board surrounded by this trench, and pour concrete.
A method for constructing a solid foundation, characterized in that the upper surface of the concrete is then leveled to make it flat so that floor interior materials such as carpet and tatami mats can be directly applied.
JP15062883A 1983-08-18 1983-08-18 Mat foundation and its construction Granted JPS6043529A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15062883A JPS6043529A (en) 1983-08-18 1983-08-18 Mat foundation and its construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15062883A JPS6043529A (en) 1983-08-18 1983-08-18 Mat foundation and its construction

Publications (2)

Publication Number Publication Date
JPS6043529A true JPS6043529A (en) 1985-03-08
JPH0324525B2 JPH0324525B2 (en) 1991-04-03

Family

ID=15501010

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15062883A Granted JPS6043529A (en) 1983-08-18 1983-08-18 Mat foundation and its construction

Country Status (1)

Country Link
JP (1) JPS6043529A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01247614A (en) * 1988-03-28 1989-10-03 Kanegafuchi Chem Ind Co Ltd Foundation structure of building
JPH04330117A (en) * 1991-04-30 1992-11-18 Okumura Corp Constructing method and structure of building foundation
JPH07166556A (en) * 1993-12-17 1995-06-27 Kurimoto Ltd Construction method for hollow foundation slab
KR101040003B1 (en) 2010-01-22 2011-06-09 고준현 Installation-workshop constructing method for steel frame construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01247614A (en) * 1988-03-28 1989-10-03 Kanegafuchi Chem Ind Co Ltd Foundation structure of building
JPH04330117A (en) * 1991-04-30 1992-11-18 Okumura Corp Constructing method and structure of building foundation
JPH07166556A (en) * 1993-12-17 1995-06-27 Kurimoto Ltd Construction method for hollow foundation slab
KR101040003B1 (en) 2010-01-22 2011-06-09 고준현 Installation-workshop constructing method for steel frame construction

Also Published As

Publication number Publication date
JPH0324525B2 (en) 1991-04-03

Similar Documents

Publication Publication Date Title
US4843658A (en) Swimming pool and method of construction
US20210017755A1 (en) Composite wall and methods of constructing a composite wall
CA2673876A1 (en) Shoring free excavation and basement construction apparatus and method
JPS6043529A (en) Mat foundation and its construction
JPH05230845A (en) L-shaped block retaining wall structure and construction method thereof
JP3150612B2 (en) Foundation for low-rise buildings
JP2003105777A (en) Foundation constructing method
JP2000144769A (en) Method of landslide protection work for preparing housing lot
JPH0467533B2 (en)
JPH09111776A (en) Basement and construction method thereof
JP2835815B2 (en) Foundation structure for wooden buildings and its construction method
JP2001059228A (en) Mat foundation structure for detached house and its constructing method
JP2019044423A (en) Method of constructing basement
JPH02304150A (en) Floor construction method
JPH11172757A (en) Building structure
JPS61134434A (en) Method of building concrete retaining wall
JP3401282B2 (en) Construction method of soil between unit type buildings
JP2874860B2 (en) Soil floor structure and method of construction
JPH11350500A (en) Foundation structure of building and foundation work method
JPS5812917Y2 (en) Foundation formwork support structure
RU2070252C1 (en) Pre-cast reinforced concrete retaining wall
JPS63567B2 (en)
JPH0156215B2 (en)
JPH0759810B2 (en) Ground improvement method for foundation
JP2616366B2 (en) Underground foundation structure