JPH11152988A - Construction method of underground structure - Google Patents

Construction method of underground structure

Info

Publication number
JPH11152988A
JPH11152988A JP9333721A JP33372197A JPH11152988A JP H11152988 A JPH11152988 A JP H11152988A JP 9333721 A JP9333721 A JP 9333721A JP 33372197 A JP33372197 A JP 33372197A JP H11152988 A JPH11152988 A JP H11152988A
Authority
JP
Japan
Prior art keywords
earth
ground
shaft
constructing
retaining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9333721A
Other languages
Japanese (ja)
Inventor
Masao Mimura
正男 三村
Tomoshi Yuki
知史 結城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Penta Ocean Construction Co Ltd
Original Assignee
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Penta Ocean Construction Co Ltd filed Critical Penta Ocean Construction Co Ltd
Priority to JP9333721A priority Critical patent/JPH11152988A/en
Publication of JPH11152988A publication Critical patent/JPH11152988A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce a constructing quantity of earth-retaining by constructing a shaft between a pair of earth-retaining walls constructed in the ground and hauling a shield excavator therein to excavate a hole for upper and lower floors and excavating the soil between the upper and lower floor slabs after these floor slabs have been formed. SOLUTION: A pair of right and left earth-retaining walls 10 are constructed in the ground from a road face. A starting shaft 15 and an arrival shaft are formed at the ends of the earth-retaining walls 10. Several small shield excavators are parallelly arranged in the starting shaft 15 to horizontally start in the lower floor part 19 to excavate the ground. In the same way, the upper floor part 24 is also excavated and segments with supports 21 are installed to support the natural ground 22. Reinforcements are arranged in the tunnel after the primary lining to connect them to the earth-retaining walls 10 and then, concrete is placed to construct the lower floor slab 27. After the upper floor slab 28 has been constructed likewise, the soil within the ground 29 is excavated and decorative walls 31 or the like of the side walls are finished and then the shaft 15 is filled back. The upper layer is not opened and hence, earth-retaining walls are not required and also a deep embedment is not required for the earth-retaining wall of the lower layer part and hence, a constructing quantity of the earth-retaining wall can be reduced.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は地下構造物の築造工
法、特に、大深度位置に矩形の構造物を築造するための
方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground structure, and more particularly to a method for constructing a rectangular structure at a large depth.

【0002】[0002]

【従来の技術】従来、地中に道路、鉄道、トンネル、共
同溝又はビルの地下室などの矩形の構造物を築造する方
法としては、開削工法とシールド工法とがある。
2. Description of the Related Art Conventionally, as a method of constructing a rectangular structure such as a road, a railroad, a tunnel, a common ditch or a basement of a building underground, there are an excavation method and a shield method.

【0003】[0003]

【発明が解決しようとする課題】然しながら、開削工法
は建設区域全面を路上から掘り進んでいくため、その全
面が路面覆工範囲となり、路面覆工範囲が広く、長期に
わたり全沿道住民に騒音、振動等の迷惑をかけ、土砂や
鋼材等の運搬が多く、覆工開閉による交通規制が多いな
どの欠点があった。
However, in the open-cutting method, since the entire construction area is dug from the road, the entire surface becomes a road covering area, and the road covering area is wide. There were drawbacks, such as inconveniences such as vibration, transportation of earth and sand, steel materials, etc., and traffic regulation by opening and closing the lining.

【0004】また、既設地下埋設物の切廻しや吊防護等
が必要で、その維持、管理も大変であった。
[0004] In addition, the existing underground buried objects need to be cut and suspended, and their maintenance and management are also difficult.

【0005】また、構造物の土被り部分が大きい程(構
造物が深い程)土量が増加し、また埋め戻し量が多かっ
た。
[0005] The larger the overburden portion of the structure (the deeper the structure), the larger the amount of soil and the larger the amount of backfill.

【0006】また、近年築造すべき構造物の地下の深さ
が深くなる程、地下水の圧力が工事の安全施工に重大な
影響を与える事となってきた。
In recent years, as the depth of the underground of a structure to be built becomes deeper, the pressure of groundwater has a more serious effect on the safe construction of construction.

【0007】この一つは“被圧水による盤ぶくれ”とい
う現象である。
One of these is a phenomenon called "blowing due to pressurized water".

【0008】“盤ぶくれ”とは図7に示すように地盤1
を掘り下げるにつれ土塊重量Wは小さくなってくるが、
地下水圧Pwが一定なら、全体の安定条件W>ΣPwは
どこかで逆転し、地盤が破壊してしまう。
[0008] "Bulling" refers to ground 1 as shown in FIG.
As the soil is dug down, the mass W becomes smaller,
If the groundwater pressure Pw is constant, the overall stability condition W> ΣPw is reversed somewhere and the ground is destroyed.

【0009】これらに対する一般的な対策として、[0009] As a general measure against these,

【0010】 地下水圧を低下させる。この場合、周
辺地盤の沈下が発生したり、井戸が涸れる恐れがある。
[0010] Reduce groundwater pressure. In this case, settlement of the surrounding ground may occur or the well may dry up.

【0011】 地盤改良で土塊重量を増加させる。こ
の場合工事費が高価となる。
[0011] The soil mass is increased by soil improvement. In this case, the construction cost becomes expensive.

【0012】 より深層にある不透水層2に土留め壁
3を貫入させ、地下水圧Pwを遮断する。この場合、一
般的に不透水層2は極めて深く、土留め壁工事が高価と
なり、さらに、地下水流の遮断を招く。
The earth retaining wall 3 is made to penetrate the deeper water-impermeable layer 2 to block the groundwater pressure Pw. In this case, generally, the water-impermeable layer 2 is extremely deep, the construction of the retaining wall becomes expensive, and further, the groundwater flow is interrupted.

【0013】 被圧水圧とバランスをとるために、土
留め掘削内に水を張る“水中掘削”を行い、掘削完了後
は水中コンクリートで耐圧盤を築造する。然しながら、
このような大規模な水中掘削は難工事で危険も多く、耐
圧盤もかなり厚いものになり工事は高価となる、などの
欠点があった。
[0013] "Underwater excavation" is performed by filling the earth retaining excavation with water in order to balance with the pressure to be applied. After the excavation is completed, a pressure-resistant board is constructed of underwater concrete. However,
Such a large-scale underwater excavation has difficulties and involves many dangers, and has a drawback that the pressure plate becomes considerably thick and the construction becomes expensive.

【0014】また、大型矩形断面をシールド工法(例え
ばMMST工法)で施工する場合は、掘削断面を一気に
シールド掘進できないので、図8に示すように必要掘削
断面を幾つかの断面4a〜4hに分割して上記各断面を
シールド掘削機5により順次掘進し(ボックスシールド
工法)、各分割断面4a〜4hの間6a〜6hを連絡す
る必要があるが、この連絡には、危険が多く、高価な補
強工事を必要とする。なお、図8において、7は一次覆
工部材(セグメント)、8は間隙連絡工、9は本体構造
物である。
When a large rectangular section is constructed by a shield method (for example, the MMST method), the excavated section cannot be excavated at a stretch, so the required excavated section is divided into several sections 4a to 4h as shown in FIG. Then, it is necessary to sequentially excavate each of the above sections by the shield excavator 5 (box shield method) and to communicate 6a to 6h between the divided sections 4a to 4h, but this communication is dangerous and expensive. Requires reinforcement work. In FIG. 8, 7 is a primary lining member (segment), 8 is a gap connecting member, and 9 is a main body structure.

【0015】シールド工法の更なる問題点を列記すれば
次の通りである。
[0015] Further problems of the shield method are listed below.

【0016】 シールド覆工部材には多大な水平力、
鉛直力が作用するため、剛性の高い一次覆工部材(セグ
メント)を使用しなければならない。また、矩形断面で
あることから、円形断面に比べて、セグメントの部材厚
はかなり大きくなる。
A large horizontal force is applied to the shield lining member,
Since a vertical force acts, a primary lining member (segment) having high rigidity must be used. Further, since the cross section is rectangular, the member thickness of the segment is considerably larger than that of the circular cross section.

【0017】 シールド掘削をし、セグメントを組立
てた大きな空間は、仮設の土留め壁の役目だけで、最終
的には本体構造物とは何の関係もなく、無駄なスペース
となってしまう。
[0017] The large space where the shield excavation is performed and the segments are assembled serves only as a temporary retaining wall, and ultimately has no relation to the main body structure and becomes a useless space.

【0018】上記のように従来の開削工法においても、
シールド工法においても夫々問題点があった。
As described above, in the conventional open-cutting method,
There were also problems with the shield method.

【0019】本発明は上記の欠点を除くようにしたもの
である。
The present invention has been made to eliminate the above disadvantages.

【0020】[0020]

【課題を解決するための手段】本発明の地下構造物の築
造工法は、路上より地中に左右一対の土留め壁を形成す
る工程と、上記左右の土留め壁間にシールド掘削機搬入
・搬出用の立坑を築造する工程と、上記立坑に搬入した
シールド掘削機を用いて、下床用の穴を掘削する工程
と、上記立坑に搬入したシールド掘削機を用いて、上床
用の穴を掘削する工程と、上記下床用及び上床用の穴を
施工して下床版及び上床版を夫々形成する工程と、上記
下床版と上床版間の土を掘削する工程と、より成ること
を特徴とする。
According to the method of constructing an underground structure of the present invention, a pair of left and right earth retaining walls are formed in a ground from a road, and a shield excavator is loaded between the left and right earth retaining walls. A step of constructing a shaft for carrying out, a step of excavating a hole for a lower floor using a shield excavator carried into the shaft, and a step of excavating a hole for an upper floor using a shield excavator carried into the shaft. Excavating, forming the lower floor slab and the upper floor slab by forming holes for the lower floor and the upper floor, and excavating soil between the lower floor slab and the upper floor slab. It is characterized by.

【0021】[0021]

【発明の実施の形態】以下図面によって本発明の実施例
を説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0022】本発明のトンネル築造工法においては、路
上から施工した連続地中壁(連壁)を構造物の側壁とし
て利用し、上床、下床版は、立坑からの矩形シールド工
法により施工するもので、具体的には、
In the tunnel construction method of the present invention, a continuous underground wall (continuous wall) constructed from the road is used as a side wall of the structure, and the upper floor and the lower floor slab are constructed by a rectangular shield construction method from a shaft. So, specifically,

【0023】 図1に示すように、路上から左右一対
の土留め壁(連壁)10,10を地中に築造する。この
連壁10,10は非開削ボックスカルバートの側壁本体
となるもので、図2に示すように、下方に従来の開削工
法では必要とされた土留め壁に長い根入れ11を設ける
必要がなく、また、上方に路面覆工や土留め用の余分な
壁12も不要で、この部分は砂埋若しくは無筋の泥水固
化壁により埋める。
As shown in FIG. 1, a pair of left and right earth retaining walls (continuous walls) 10, 10 are constructed underground from the road. As shown in FIG. 2, there is no need to provide a long embankment 11 below the earth retaining wall required by the conventional open-cutting method, as shown in FIG. In addition, there is no need for an extra wall 12 for road surface lining or earth retaining above, and this portion is filled with sand or a solid muddy solidified wall.

【0024】 上記左右の土留め壁10,10の端部
にシールド機を搬入、搬出すための発進・到達立坑1
5,16を築造する。本発明の場合、例えば図1に示す
ように、土留め壁10,10を築造する時に、撤去・移
設等が困難な地上にある既設物13を避けて、計画し、
撤去・移設の比較的容易な低木等14を移動してやれば
工事可能となる。
A starting and arriving shaft 1 for loading and unloading the shield machine to the ends of the left and right retaining walls 10, 10.
Build 5,16. In the case of the present invention, for example, as shown in FIG. 1, when constructing the retaining walls 10, 10, plan and avoid the existing object 13 on the ground where removal and relocation are difficult.
If the shrub 14 or the like 14 which is relatively easy to remove and relocate is moved, the construction becomes possible.

【0025】 上記発進位置立坑15の築造後、路上
で又は立坑15内で図3に示すように高さ1.0〜2.
0m、全横幅6.0〜20m位のスキンプレート17を
組立て、このスキンプレート17の中で矩形の小型シー
ルド掘削機18を横方向に必要台数並置する。
After the start position shaft 15 is built, on a road or in the shaft 15, as shown in FIG.
A skin plate 17 having a total width of about 6.0 m to 20 m is assembled, and a required number of small rectangular shield excavators 18 are juxtaposed in the horizontal direction in the skin plate 17.

【0026】 上記矩形シール掘削機18を下床部分
19内を水平方向に発進させ、下床部分19の掘削を行
い、図4に示すように掘削部分の上面及び下面に鋼製の
セグメント20,20を設置し、このセグメント20,
20間に複数の支柱21を設置し上部の地山22を支え
(一次覆工)、必要に応じてセグメント補強リブ23を
設ける。
The rectangular seal excavator 18 is started horizontally in the lower floor portion 19 to excavate the lower floor portion 19, and as shown in FIG. 20 and install this segment 20,
A plurality of columns 21 are installed between the bases 20 to support an upper ground 22 (primary lining), and segment reinforcing ribs 23 are provided as necessary.

【0027】 次に図2に示す上床部分24も同様に
矩形シールド掘削機18により掘削し、掘削部分の上面
及び下面に同様にしてセグメント20を設置し、そのセ
グメント20,20間に複数の支柱21を設置せしめ上
部の地山22を支える。
Next, the upper floor portion 24 shown in FIG. 2 is similarly excavated by the rectangular shield excavator 18, segments 20 are similarly installed on the upper and lower surfaces of the excavated portion, and a plurality of struts are provided between the segments 20. 21 to support the ground 22 at the top.

【0028】 図5に示すように上記一次覆工の終了
した坑内で鉄筋25を組立て、連壁10との取付け作業
を行い、一次覆工のセグメント20と支柱21を埋殺
し、または撤去して下床版19のための本体コンクリー
ト26を打設し、図6に示すように下床版27を築造す
る。同様にして上床版28を築造する。(二次覆工)
As shown in FIG. 5, the rebar 25 is assembled in the mine where the primary lining has been completed, and the work of attaching the reinforcing bar 25 to the connecting wall 10 is performed, and the primary lining segment 20 and the column 21 are buried or removed. A concrete body 26 for the lower slab 19 is cast, and a lower slab 27 is constructed as shown in FIG. Similarly, the upper floor slab 28 is constructed. (Secondary lining)

【0029】 なお、必要に応じて下床版27及び上
床版28の補強等のため、下床版27と上床版28間に
形成される地盤29内に地盤29全体の掘削に先立ち上
記下床版27と上床版28に連通する穴30を設け、こ
の穴30内に中柱(図示せず)を設置せしめる。
In order to reinforce the lower slab 27 and the upper slab 28 as necessary, the lower slab is formed in the ground 29 formed between the lower slab 27 and the upper slab 28 prior to the excavation of the entire ground 29. A hole 30 communicating with the plate 27 and the upper floor plate 28 is provided, and a center pillar (not shown) is installed in the hole 30.

【0030】 地盤29内の土砂を掘削し(非開削の
トンネル掘削)、地盤29内を整備し、側壁化粧壁31
等の築造を行い、立坑15、16の埋め立て等により工
事を終了せしめる。
The soil in the ground 29 is excavated (uncut tunnel excavation), the interior of the ground 29 is maintained, and the side wall decorative wall 31 is provided.
The construction is completed by reclaiming the shafts 15, 16.

【0031】本発明のトンネル築造工法は開削工法と比
較して、下記のような利点を有する。
The tunnel construction method of the present invention has the following advantages as compared with the open-cutting method.

【0032】 側壁(土留め壁)についていえば、上
層部は非開削であるため土留め壁が不要であり、下層部
はシールド掘進時の土留め壁としての根入れだけであ
り、一般的な開削の土留めとしての図2に示すような長
い根入れや地下水遮断のための長い根入れは不要であ
る。従って、連壁の施工数量を減ずることができる。
With respect to the side wall (retaining wall), the upper layer portion is not excavated, so that the retaining wall is not necessary, and the lower layer portion is only embedding as the retaining wall at the time of shield excavation. No long embedding as shown in Fig. 2 as earth retaining for excavation or long embedding for blocking groundwater is required. Therefore, it is possible to reduce the construction quantity of the connecting wall.

【0033】 地下水の被圧対策に、地下水位低下工
法などを併用する必要がないので、工事周辺の地下水を
低下させることなく、井戸涸れや、地盤沈下の原因とは
ならない。
Since it is not necessary to use a groundwater level lowering method or the like in combination with groundwater pressure control, the groundwater around the construction is not reduced, and the well does not dry or cause land subsidence.

【0034】 特に連壁の深い根入れがないので、地
下ダムとして作用する地下水の堰止め現象が発生しな
い。
In particular, since there is no deep embedding of the connecting wall, there is no occurrence of a damping phenomenon of groundwater acting as an underground dam.

【0035】 地下水被圧による盤ぶくれ対策として
開削工法では「遮水壁の深度化」,「地盤改良」,「地
下水低下」などの補助工法を必要とし、工期と工費的に
不利であるが、本発明工法の場合、密閉式のシールド工
法の採用で上記のような補助工事を必要としない。
As a countermeasure against board swelling due to groundwater pressure, the open-cutting method requires auxiliary methods such as “deepening of impermeable walls”, “ground improvement”, and “lowering of groundwater”, which is disadvantageous in terms of construction period and construction cost. In the case of the construction method of the present invention, the auxiliary construction as described above is not required by adopting the closed shield construction method.

【0036】 上床版の上部の土を掘削しないので、
地元住民への迷惑度が低い。また、既設埋設物の支障が
少なく、移設・復旧等の余分な工事が不要である。
Since the soil above the upper slab is not excavated,
Low annoyance to local residents. In addition, there is little hindrance to existing buried objects, and no extra work such as relocation and restoration is required.

【0037】 掘削土量が減少し、埋戻しは立坑部分
のみなので埋め戻し量を減らすことができる。
Since the amount of excavated soil is reduced and the backfill is performed only at the shaft, the amount of backfill can be reduced.

【0038】 下床部分、上床部分の夫々の掘削時に
おいて鉛直力は支柱を介して上下地山でバランスし、水
平力は連壁により受け持つことができる。即ち、反力を
常に周辺地盤でつりあわすことができる。構造物の築造
場所が深くなり、地下水圧が大きくなっても地下水の被
圧対策は大きな問題とはならない。
When excavating the lower floor portion and the upper floor portion, the vertical force is balanced at the upper ground pile via the pillar, and the horizontal force can be covered by the continuous wall. That is, the reaction force can always be balanced on the surrounding ground. Even if the place where the structure is built becomes deeper and the groundwater pressure increases, countermeasures against groundwater pressure will not be a major problem.

【0039】また、シールド掘削工法と比較して下記の
ような利点を有する。
The following advantages are obtained as compared with the shield excavation method.

【0040】 図4に示すように一次覆工時外力とし
ては水平力(H)と鉛直力(V)の作用が考えられる
が、本発明工法の場合、水平力は、剛性の高い連壁10
で受け持たれ、セグメントには作用しない。然し、鉛直
力はセグメントに作用する。即ち、本発明工法ではセグ
メントには水平力は作用せず、鉛直力だけが作用するの
で、支柱を適当に配置すれば、従来のシールド工法のセ
グメントのような高い剛性のセグメントは不要である。
(構造が簡易で桁高を小さくできる)
As shown in FIG. 4, the horizontal force (H) and the vertical force (V) can be considered as the external force at the time of the primary lining. In the case of the method of the present invention, the horizontal force is reduced by the rigid wall 10.
And has no effect on segments. However, vertical forces act on the segments. That is, in the method of the present invention, a horizontal force does not act on a segment, but only a vertical force acts. Therefore, if the columns are appropriately arranged, a segment having a high rigidity like the segment of the conventional shield method is unnecessary.
(The structure is simple and the girder height can be reduced)

【0041】 下床版又は上床版を一気に掘進できる
のでシールド各部との接続工程が不要であり、工程が大
幅に短縮される。
Since the lower floor slab or the upper floor slab can be excavated at a stretch, a connection step with each part of the shield is unnecessary, and the process is greatly shortened.

【0042】 本発明工法ではシールド掘進して出来
た空間そのものの中に本体構造物の床版を現場打コンク
リート工法で築造するので、仮設の無駄なスペースがご
く小さい。
In the method of the present invention, since the floor slab of the main structure is built by the cast-in-place concrete method in the space itself formed by excavating the shield, a temporary wasteful space is extremely small.

【0043】 水平方向に数台の小型シールド掘削機
を並べて使用でき、多少の改造で色々のシールド掘削機
の流用・転用も可能となる。
Several small shield excavators can be used side by side in the horizontal direction, and it is possible to divert and divert various shield excavators with some modifications.

【0044】[0044]

【発明の効果】上記のように本発明工法によれば、大規
模な開削工事を行うことなく大規模な仮設空間を作るこ
となく、また地下水の被圧対策はシールド工法の止水ぐ
らいですみ、地下水流を遮断したり、水位低下させたり
して自然を変化させなくてすむ。現状で大型矩形工事を
シールド工法で施工する場合、複数の小型矩形シールド
の組合せにより生じる数々の難題も解決できるという大
きな利益がある。
[Effect of the Invention] As described above, according to the method of the present invention, there is no need to perform large-scale excavation work, to create a large-scale temporary space, and to reduce the pressure of groundwater as much as the water stoppage of the shield method. No need to interrupt the groundwater flow or lower the water level to change nature. At present, when a large rectangular construction is constructed by a shield method, there is a great advantage that many difficulties caused by a combination of a plurality of small rectangular shields can be solved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の地下構造物の築造工法の説明用平面図
である。
FIG. 1 is a plan view for explaining a construction method of an underground structure according to the present invention.

【図2】本発明の地下構造物の築造工法の説明用縦断側
面図である。
FIG. 2 is a vertical sectional side view for illustrating a construction method of an underground structure according to the present invention.

【図3】本発明の地下構造物の築造工法に用いる大型地
盤シールド掘削機の組み立て状態を示す側面図である。
FIG. 3 is a side view showing an assembled state of a large ground shield excavator used in the method of constructing an underground structure according to the present invention.

【図4】本発明の地下構造物の築造工法の一次覆工の説
明用側面図である。
FIG. 4 is an explanatory side view of a primary lining method for constructing an underground structure according to the present invention.

【図5】本発明の地下構造物の築造工法の一次覆工の説
明用側面図である。
FIG. 5 is a side view for explaining a primary lining method for constructing an underground structure according to the present invention.

【図6】本発明の地下構造物の築造工法の二次覆工の説
明用側面図である。
FIG. 6 is a side view for explaining a secondary lining in the method of constructing an underground structure according to the present invention.

【図7】従来の開削工法の説明用側面図である。FIG. 7 is an explanatory side view of a conventional digging method.

【図8】従来のシールド工法の説明用縦断側面図であ
る。
FIG. 8 is a vertical sectional side view for explaining a conventional shield method.

【符号の説明】[Explanation of symbols]

1 地盤 2 不透水層 3 土留め壁 4a断面 4b断面 4c断面 4d断面 4e断面 4f断面 4g断面 4h断面 5 シールド掘削機 6a間 6b間 6c間 6d間 6e間 6f間 6g間 6h間 7 一次覆工部材 8 間隙連絡工 9 本体構造物 10 土留め壁(連壁) 11 長い根入れ 12 余分な壁 13 撤去困難な障害物 14 撤去可能な障害物 15 搬入するための発進位置用立坑 16 搬出するための到達位置の立坑 17 スキンプレート 18 小型シールド掘削機 19 下床部分 20 セグメント 21 支柱 22 地山 23 セグメント補強リブ 24 上床部分 25 鉄筋 26 本体コンクリート 27 下床版 28 上床版 29 地盤 30 穴 31 側壁化粧壁 Reference Signs List 1 ground 2 impermeable layer 3 retaining wall 4a section 4b section 4c section 4d section 4e section 4f section 4g section 4h section 5 Shield excavator 6a 6b 6c 6d 6d 6e 6f 6g 6h 7 Primary lining Member 8 Gap communication 9 Main body structure 10 Earth retaining wall (continuous wall) 11 Long embedding 12 Extra wall 13 Obstacle difficult to remove 14 Obstacle that can be removed 15 Starting shaft for carrying in 16 To carry out Shaft 17 skin plate 18 small shield excavator 19 lower floor part 20 segment 21 support 22 ground ground 23 segment reinforcement rib 24 upper floor part 25 steel bar 26 concrete body 27 lower floor slab 28 upper floor slab 29 ground 30 hole 31 side wall decoration wall

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 路上より地中に左右一対の土留め壁を形
成する工程と、 上記左右の土留め壁間にシールド掘削機搬入・搬出用の
立坑を築造する工程と、 上記立坑に搬入したシールド掘削機を用いて、下床用の
穴を掘削する工程と、 上記立坑に搬入したシールド掘削機を用いて、上床用の
穴を掘削する工程と、 上記下床用及び上床用の穴を施工して下床版及び上床版
を夫々形成する工程と、 上記下床版と上床版間の土を掘削する工程と、 より成ることを特徴とする地下構造物の築造工法。
1. A step of forming a pair of left and right earth retaining walls from the road in the ground, a step of constructing a shaft for loading and unloading a shield excavator between the left and right earth retaining walls, and loading the shaft into the shaft. Using a shield excavator to excavate a hole for the lower floor, and using a shield excavator carried into the shaft to excavate a hole for the upper floor, and forming the hole for the lower floor and the upper floor A method of constructing an underground structure, comprising: constructing a lower slab and an upper slab, respectively, and excavating soil between the lower slab and the upper slab.
JP9333721A 1997-11-19 1997-11-19 Construction method of underground structure Pending JPH11152988A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9333721A JPH11152988A (en) 1997-11-19 1997-11-19 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9333721A JPH11152988A (en) 1997-11-19 1997-11-19 Construction method of underground structure

Publications (1)

Publication Number Publication Date
JPH11152988A true JPH11152988A (en) 1999-06-08

Family

ID=18269223

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9333721A Pending JPH11152988A (en) 1997-11-19 1997-11-19 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JPH11152988A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110486019A (en) * 2019-07-22 2019-11-22 上海建工一建集团有限公司 The excavating construction method in subterranean communication road is added between new and old building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110486019A (en) * 2019-07-22 2019-11-22 上海建工一建集团有限公司 The excavating construction method in subterranean communication road is added between new and old building

Similar Documents

Publication Publication Date Title
CN107542108B (en) A kind of reverse construction method of building basement structure
CN1837506B (en) Construction method for excavating box-shape structure over an operating tunnel
CN102363961A (en) Deepwater single-wall steel plate pile cofferdam structure with low buried depth and construction method thereof
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
KR100656194B1 (en) Open cut and cover method applying tunnel cut method
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
JP6543176B2 (en) Building method
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP4206165B2 (en) Temporary deadline construction method
JP4226954B2 (en) Underpinning method and viaduct
JP4485006B2 (en) Construction method for underground structures
JP3948655B2 (en) Construction method of retaining wall and underground structure
JPH11152988A (en) Construction method of underground structure
JP2876076B2 (en) Underground structure construction method
CN214940194U (en) Supporting construction based on uncovered formula structure in underground
JP2000178966A (en) Structure of diaphragm wall
JPS6124624Y2 (en)
JP2949623B1 (en) How to build a tunnel
JP4031284B2 (en) Construction method for underground structures
McIntosh et al. HONG KONG MASS TRANSIT RAILWAY MODIFIED INITIAL SYSTEM: DESIGN AND CONSTRUCTION OF UNDERGROUND STATIONS AND CUT-AND COVER TUNNELS.
JP2745083B2 (en) Tunnel construction method
JPH0381421A (en) Shaft construction method
Farley et al. THE CONSTRUCTION OF LIMEHOUSE LINK TUNNEL.(WINNER OF 1995 REED AND MALIK MEDAL).
JPH10121465A (en) Continuos underground wall engineering method
JP2000328572A (en) Temporary earth retaining timbering method in underground continuous wall