CN1837506B - Construction method for excavating box-shape structure over an operating tunnel - Google Patents

Construction method for excavating box-shape structure over an operating tunnel Download PDF

Info

Publication number
CN1837506B
CN1837506B CN2006100256530A CN200610025653A CN1837506B CN 1837506 B CN1837506 B CN 1837506B CN 2006100256530 A CN2006100256530 A CN 2006100256530A CN 200610025653 A CN200610025653 A CN 200610025653A CN 1837506 B CN1837506 B CN 1837506B
Authority
CN
China
Prior art keywords
tunnel
district
base plate
enclosure wall
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2006100256530A
Other languages
Chinese (zh)
Other versions
CN1837506A (en
Inventor
王海燕
潘松林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN2006100256530A priority Critical patent/CN1837506B/en
Publication of CN1837506A publication Critical patent/CN1837506A/en
Application granted granted Critical
Publication of CN1837506B publication Critical patent/CN1837506B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a method for constructing the box above the tunnel, which is characterized in that: arranging protective walls 1 and 2 at the basic hole which can divide the soil above the tunnel into three sections as I, II, and III; then strengthening the soil around the tunnel; digging at I and III sections to bottom plate and arranging steel support, then processing the bottom plate,middle plate, side plate and side wall, with keeping the steep support; in II section, digging the soil to the bottom plate and arranging steel support, and connecting the bottom plate to the bottom plates of I and III sections; removing the first support of II section, and removing part of protective wall 1, and processing the top plate of II section; removing the second support of II section, and part of protective wall 1, processing the middle plate of II section; removing the third support, removing left protective wall 1, and filling soil into ground. The invention can quickly construct a new box structure above the tunnel without affecting the normal operation of tunnel.

Description

A kind of job practices of the tunnel upper excavation box structure in operation
Technical field:
The present invention relates to the underground engineering construction technical field, specifically a kind of tunnel upper in operation is through the construct job practices of box structure of the mode of excavation section by section.
Background technology:
In recent years, along with the growing interest of Shanghai to underground space resources, building the tunnel becomes a kind of effective form that utilizes the underground space to improve traffic above-ground.It is for improving land utilization efficiency, alleviate traffic above-ground, improve the human residential environment, realize people's car three-dimensional branching off, reduce environment pollution, keeping urban history cultural landscape etc. all to have very significant effect.But the underground space in city is limited.Because Shanghai City lacked comprehensive planning to the exploitation in underground space, made that the underground space of bustling center is very crowded in the past, the underground space that reality can supply develop is very limited.Along with the development of urban underground space, run into the situation that newly-built underground structure need pass through tunnel in the operation of having built up through regular meeting.All there is the problem of building subterranean tunnel of passing through in comprehensive reformation projects such as the outbeach that will implement at present, Xujiahui, Jing'an Monastery.
Summary of the invention:
The object of the present invention is to provide a kind of tunnel upper in operation through the construct job practices of new box structure of the mode of excavation section by section, it can overcome the deficiency of the normal operation of established tunnel during the new box structure that can't guarantee in the prior art to construct.
To achieve these goals; Technical scheme of the present invention is: a kind of job practices of the tunnel upper excavation box structure in operation; It mainly comprises the foundation ditch of the box structure that is arranged on tunnel upper; It is characterized in that: described job practices comprise following step: a, the box structure that will excavate constitute by base plate, middle plate, top board and side wall; Second enclosure wall 2 that is parallel to the tunnel is set on the foundation ditch limit earlier, in foundation ditch, is provided with perpendicular to first enclosure wall, 1, the second enclosure wall 2 in tunnel and first enclosure wall 1 intersects vertically and the soil body of tunnel upper is divided into I district, II district and III district; B, the tunnel surrounding soil is reinforced; C, in the I district, the III district cuts the earth to the base plate position and steel is set supports, the base plate of constructing then, base plate reinforcing bar adopt with the cross section and break off, and are embedded in the base plate, then construction is accomplished in I, the III district plate, top board and sidewall structure and is kept the steel support; Cut the earth to the base plate position and steel are set and support in d, II district, construction II district's base plate also is communicated with I, III district base plate; E, dismounting first road, II district support, and cut part first enclosure wall (1), construction II district top board; Remove second road, II district and support, cut part, plate in the construction II district; Remove the 3rd road and support, cut remainder first enclosure wall (1), backfill is to ground.
Of the present inventionly disclose a kind of tunnel upper in operation, can guarantee under the situation of the normal operation of established tunnel the new box structure of above established tunnel, constructing safely and fast through the construct job practices of new box structure of the mode of excavation section by section.
Description of drawings:
Fig. 1 is a space enclosing structure layout plan of the present invention
Fig. 2 is a soil stabilization layout plan of the present invention
Fig. 3 is an A-A sectional schematic diagram among Fig. 2
Fig. 4 is a Construction Arrangement sketch map of the present invention
The specific embodiment:
Below in conjunction with accompanying drawing and embodiment the present invention is done further description.
The present invention mainly comprises the foundation ditch of the box structure that is arranged on tunnel upper; It is characterized in that: described job practices comprise following step: a, the box structure that will excavate constitute by base plate, middle plate, top board and side wall; Second enclosure wall 2 that is parallel to the tunnel is set on the foundation ditch limit earlier; In foundation ditch, be provided with perpendicular to first enclosure wall, 1, the second enclosure wall 2 in tunnel and first enclosure wall 1 intersects vertically and the soil body of tunnel upper is divided into I district, II district and III district; B, the tunnel surrounding soil is reinforced; C, in the I district, the III district cuts the earth to the base plate position and steel is set supports, the base plate of constructing then, base plate reinforcing bar adopt with the cross section and break off, and are embedded in the base plate, then construction is accomplished in I, the III district plate, top board and sidewall structure and is kept the steel support; Cut the earth to the base plate position and steel are set and support in d, II district, construction II district's base plate also is communicated with I, III district base plate; E, dismounting first road, II district support, and cut part first enclosure wall 1, construction II district top board; Remove second road, II district and support, cut part first enclosure wall 1, plate in the construction II district; Remove the 3rd road and support, cut remainder first enclosure wall 1, backfill is to ground.
As shown in Figure 1; Excavation of the present invention go along with sb. to guard him system by the foundation ditch limit perpendicular in the bored pile of established tunnel, the foundation ditch perpendicular to the bored pile (first enclosure wall 1) in tunnel and be parallel to limit, hole, tunnel (with the distance on limit, tunnel be 4 meters) diaphragm wall (second enclosure wall 2) form, the top of bored pile, diaphragm wall is provided with the concrete capping beam; The tunnel upper soil body is divided into 3 districts (I district, II district and III district) " piecemeal, symmetry, layering " construction.
For the stability that guarantees foundation ditch and the safety of operation tunnel, the fender post directly over the tunnel (space enclosing structure 1) degree of depth is top mark height top, tunnel 750mm.Hole internal drilling castinplace pile in the altitude range of newly-built box structure base plate~middle plate, inserts 200 * 200H shaped steel so that use during the construction of II district base plate.
As shown in Figure 2, all to reinforce inside and outside the foundation ditch before the excavation of foundation pit with SMW worker's method stake (being cement mixing method), the scope of reinforcing is in the whole foundation ditch and goes along with sb. to guard him in 7 meters in the outside.Soil stabilization must be carried out in two angular regions of tunnel upper semicircumference, and the concrete vertical scope of reinforcing is seen the A-A profile among Fig. 3.Cement mixing method is grid and arranges.In order to guarantee the safe operation in tunnel, the speed of application of SMW is controlled in strictness, and the soil pressure that produces when reducing to construct is to the influence in tunnel.The sequence of construction of soil stabilization should be carried out according to the tunnel is influenced minimum principle, and the order of " near earlier back far " is carried out promptly apart from the tunnel.Reinforcement material is selected the cement mortar of C20 for use; The hole inner bottom plating adopts 8% cement mixing content during with the soil stabilization on top; Base plate adopts 20% cement mixing content with down to the soil stabilization of established tunnel base section the time, and the outer soil stabilization of foundation ditch adopts 13% cement mixing content, and is as shown in Figure 3.
Concrete working procedure is:
At tunnel upper subregion piecemeal excavation, as shown in Figure 4.At first in the I district, the III district cuts the earth.Because the restriction of established tunnel buried depth, the insertion depth of space enclosing structure 1 maybe be not enough, can cut the earth to certain depth, and except that applying the steel support, the glass fiber anchor cable of constructing is again kept the stable of space enclosing structure.The glass fiber anchor cable is that a kind of resistance to tension is very strong but new material that shear resistance is not enough, both can guarantee the stability gone along with sb. to guard him, and after construction finishes, staying in the soil not to be influenced follow-up construction and exploitation by sliding trackle easily.
I district, the III district soil body are excavated the base plate of constructing to the base plate position, and the base plate bar splice is adopted between mechanical connection manner and the adjacent bottom plates and is connected, and bar splice is adopted with the cross section and broken off, and is embedded in this base plate, and joint must be protected and put in place.Treat that casting and compacting of concrete finishes back (before the concrete initial set), completely be layered on the base plate face back load application (sand pocket) on clamping plate immediately with clamping plate.I, the base plate shoveling of III district, base plate and total engineering time of load application were controlled in 24 hours.Adopt conventional method to carry out the construction of middle plate, top board and sidewall structure afterwards.After structure forms, support and do not remove (the support load transfering strip when constructing) as the II district.
After I district, the construction of III district are accomplished, excavation II district.II district soil excavation and the same I of support job practices, III district.Before the base plate construction of II district, the concrete chisel removal, the reinforcing bar that need will cheat in the internal drilling castinplace pile base plate boundary of works area cut off, and 200 * 200H shaped steel is exposed, and utilize H shaped steel directly to go up the top castinplace pile, and i iron welds steel plate for sealing water on base plate plane.Pre-buried reinforcing steel bar machinery joint links to each other in the middle reinforcing bar of base plate and I, the III district; Because to have I, III district embedded bar joint be same direction of rotation and can't adopt two-way mechanical connecting joint, so must adopt one joint form to give the reinforcing bar connection in the middle of the base plate.There is vertical constuction joint between II district base plate and the adjacent bottom plates.In base plate when construction in the II district, is with the fixing middle part of I, III three district's base plate constuction joints of water-swelling rubber water bar.
Base plate construction in II district than I, the III content of constructing more, and therefore, this piece base plate shoveling, base plate and total engineering time of load application were controlled in 48 hours.
After the base arrangement construction of II district is accomplished, remove first road, II district and support, cut and separate at the bottom of bored pile to the top board, construction II district top board; Remove second road, II district and support, cut and separate at the bottom of bored pile to the middle plate, plate in the construction II district; Remove the 3rd road and support, cut all the other and separate bored pile.
Will there be strict protection and the formulation emergency preplan of speedily carrying out rescue work construction period to established tunnel and multiple line thereof; Major measure is following: strengthen monitoring; Strengthen the monitoring of this section ground deformation and sedimentation on the one hand; Increase frequency, organize on the other hand for East Road, Yan'an cross-river tunnel and be out of shape the monitoring with sedimentation, in time obtain tunnel deformation information.Optimize construction organization and technology, reduce influence for East Road, Yan'an cross-river tunnel from construction technology.And accomplish fluently injected hole in advance, as the emergency management and rescue measure of protection East Road, Yan'an cross-river tunnel.In case the generation dangerous situation, tissue carries out rescue immediately.

Claims (5)

1. the job practices of the tunnel upper excavation box structure in operation; It mainly comprises the foundation ditch of the box structure that is arranged on tunnel upper; It is characterized in that: described job practices comprise following step: a, the box structure that will excavate constitute by base plate, middle plate, top board and side wall; Second enclosure wall (2) that is parallel to the tunnel is set on the foundation ditch limit earlier; First enclosure wall (1) perpendicular to the tunnel is set in foundation ditch, and second enclosure wall (2) and first enclosure wall (1) intersect vertically and the soil body of tunnel upper are divided into I district, II district and III district, and direction is arranged in order along the tunnel for I district, II district and III district; B, the tunnel surrounding soil is reinforced; C, in the I district, cutting the earth to the base plate position in the III district and by layer steel is set supports, the base plate of constructing then, base plate reinforcing bar adopt with the cross section and break off, and are embedded in the base plate, then construction is accomplished in I, the III district plate, top board and sidewall structure and is kept the steel support; Cut the earth to the base plate position and by layer steel are set and support in d, II district, construction II district's base plate also is communicated with I, III district base plate; E, dismounting first road, II district support, and cut part first enclosure wall (1), construction II district top board; Remove second road, II district and support, cut part first enclosure wall (1), plate in the construction II district; Remove the 3rd road and support, cut remainder first enclosure wall (1), backfill is to ground.
2. the job practices of a kind of tunnel upper excavation box structure in operation according to claim 1; It is characterized in that: in a step; Described second enclosure wall (2) is that 4 meters diaphragm wall constitutes by the distance with the limit, tunnel; First enclosure wall (1) is made up of bored pile, and second enclosure wall (2) and first enclosure wall (1) link together the distance from bottom tunnel top 700-800mm of first enclosure wall (1) and second enclosure wall (2) in position, wall top through the concrete capping beam.
3. the job practices of a kind of tunnel upper excavation box structure in operation according to claim 1; It is characterized in that: the tunnel surrounding soil is reinforced described in the b step is meant and utilizes cement mixing pile that the established tunnel surrounding soil is reinforced; Reinforcement material is selected the cement mortar of C20 for use; The sequence of construction of soil stabilization should be carried out according to order far away after near earlier apart from the tunnel; Foundation ditch inner bottom plating position is adopted 8% cement mixing content during with the soil stabilization on top, and 20% cement mixing content is adopted with down to the soil stabilization of tunnel bottom part the time in the base plate position, and the outer soil stabilization of foundation ditch adopts 13% cement mixing content.
4. the job practices of a kind of tunnel upper excavation box structure in operation according to claim 1 is characterized in that: in the c step, behind the construction base plate; The base plate bar splice is adopted between mechanical connection manner and the adjacent bottom plates and is connected; Bar splice is adopted with the cross section and is broken off, and is embedded in this base plate, and bar splice is protected; Treat after casting and compacting of concrete finishes to be before the concrete initial set; Completely be layered on the base plate face with clamping plate immediately, back load application on clamping plate, I, the base plate shoveling of III district, base plate and total engineering time of load application were controlled in 24 hours.
5. the job practices of a kind of tunnel upper excavation box structure in operation according to claim 1 is characterized in that: in c and the d step, outside the installation steel of cutting the earth supports, install the glass fiber anchor cable again additional.
CN2006100256530A 2006-04-12 2006-04-12 Construction method for excavating box-shape structure over an operating tunnel Active CN1837506B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2006100256530A CN1837506B (en) 2006-04-12 2006-04-12 Construction method for excavating box-shape structure over an operating tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2006100256530A CN1837506B (en) 2006-04-12 2006-04-12 Construction method for excavating box-shape structure over an operating tunnel

Publications (2)

Publication Number Publication Date
CN1837506A CN1837506A (en) 2006-09-27
CN1837506B true CN1837506B (en) 2012-02-15

Family

ID=37015003

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2006100256530A Active CN1837506B (en) 2006-04-12 2006-04-12 Construction method for excavating box-shape structure over an operating tunnel

Country Status (1)

Country Link
CN (1) CN1837506B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101413235B (en) * 2008-11-25 2011-11-30 中国一冶集团有限公司 Method for reinforcing railway before paving railway rail construction under underground way bridge
CN101748758B (en) * 2008-12-04 2012-03-21 中国二十冶集团有限公司 Timbering method of foundation ditches for reforming on-line equipment foundations in factory buildings
CN101768979B (en) * 2009-12-31 2011-06-08 上海市隧道工程轨道交通设计研究院 Enclosure structure with ultrashort underground wall
CN101781889B (en) * 2010-01-29 2014-10-08 中铁四局集团第五工程有限公司 H-shaped waterproof curtain construction process
CN102678127B (en) * 2011-03-09 2014-07-30 董勤银 Method for constructing weakly consolidated non-stratified sandstone tunnel
AU2012315417B2 (en) * 2011-09-27 2015-09-10 Lavih GARZON Retaining wall construction using site compaction and excavation
CN103590404B (en) * 2012-08-13 2016-04-27 上海市政工程设计研究总院(集团)有限公司 A kind of foundation ditch method for supporting being close to built underground structure
CN103225307B (en) * 2013-04-08 2014-12-24 广东省基础工程公司 Construction method for dynamic steel supporting system of deep foundation pit
CN103590406A (en) * 2013-11-29 2014-02-19 中船第九设计研究院工程有限公司 Construction method for synchronously excavating ultra-large type deep foundation pits in partitioned mode
CN104131816B (en) * 2014-06-20 2019-02-12 上海建工五建集团有限公司 The construction method in subway tunnel subterranean wall enabling hole in a kind of operation
CN104099944B (en) * 2014-07-24 2015-12-30 武汉市汉阳市政建设集团公司 The construction method of subway station and large span accessory structure interface
CN104947681B (en) * 2015-07-07 2017-05-10 中建三局第二建设工程有限责任公司 Super large super deep basement ground pit construction method
CN105484268A (en) * 2015-11-24 2016-04-13 上海建工一建集团有限公司 Construction method of bottom plate of foundation pit
CN114718075B (en) * 2022-04-21 2023-10-20 安徽省交通规划设计研究总院股份有限公司 Existing tunnel uplift control method under upper foundation pit excavation unloading condition

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4648743A (en) * 1984-11-26 1987-03-10 Gerhard Sauer Method of producing a subterranean structure
CN1155028A (en) * 1996-01-15 1997-07-23 同济大学 Method for predicting and controlling harm to environment resulted from digging foundation pit
CN1641114A (en) * 2004-01-17 2005-07-20 上海市城市建设设计研究院 Method for constructing deep-large foundation pit over operating tunnel an ddeformation-preventing strucutre

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4648743A (en) * 1984-11-26 1987-03-10 Gerhard Sauer Method of producing a subterranean structure
CN1155028A (en) * 1996-01-15 1997-07-23 同济大学 Method for predicting and controlling harm to environment resulted from digging foundation pit
CN1641114A (en) * 2004-01-17 2005-07-20 上海市城市建设设计研究院 Method for constructing deep-large foundation pit over operating tunnel an ddeformation-preventing strucutre

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JP特开平11-141740A 1999.05.28
JP特开平9-324417A 1997.12.16

Also Published As

Publication number Publication date
CN1837506A (en) 2006-09-27

Similar Documents

Publication Publication Date Title
CN1837506B (en) Construction method for excavating box-shape structure over an operating tunnel
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN109723065A (en) Deep basal pit freezing partly reinforced construction method in bracing means and rich water sandy pear variety
CN109914456B (en) Design and construction method for adjacent and simultaneous construction of bridge and subway tunnel
CN102352590A (en) Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN111456773A (en) Close-fitting open-and-underground excavation combined subway station structure and construction method thereof
CN113669073B (en) Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station
CN109958445A (en) The frame construction method in Large Underground space is buried for an ultra shallow
KR20180118009A (en) Duplex tunnel construction method
CN103334452A (en) Underground engineering mixed construction method
Zumrawi et al. Importance of deep excavation support and its influence on adjacent buildings
CN210195766U (en) Underground structure is built in same direction as digging to hunch lid
KR20210055980A (en) Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same
CN113529830B (en) Isolation-underpinning combined reinforcement structure of adjacent building of shallow tunnel and construction process thereof
CN112627002B (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof
CN212202085U (en) Close-adhesion type open-and-underground excavation combined subway station structure
JP2000291398A (en) Underground structure and construction method therefor
CN211200461U (en) Underground pipe gallery assembly structure
CN113898007A (en) Semi-inverse construction method for long-span corridor structure along street
KR20210055981A (en) Underground roadway using steel continuous wall in the earth with minimum traffic control in constructing by top-down method and method for constructing the same
Stacey et al. The influence of subsidence on planning and development in Johannesburg, South Africa
Van der Boom Tunnelling in urban areas: the use of lateral walls to protect ancient buildings

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant