JP2000328572A - Temporary earth retaining timbering method in underground continuous wall - Google Patents

Temporary earth retaining timbering method in underground continuous wall

Info

Publication number
JP2000328572A
JP2000328572A JP13617199A JP13617199A JP2000328572A JP 2000328572 A JP2000328572 A JP 2000328572A JP 13617199 A JP13617199 A JP 13617199A JP 13617199 A JP13617199 A JP 13617199A JP 2000328572 A JP2000328572 A JP 2000328572A
Authority
JP
Japan
Prior art keywords
temporary
support
support member
earth retaining
continuous wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13617199A
Other languages
Japanese (ja)
Inventor
Kunio Kawakami
邦雄 川上
Junichi Wadano
純一 和田野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DAINIPPON CONSTRUCTION
Dai Nippon Construction
Teito Rapid Transit Authority
Original Assignee
DAINIPPON CONSTRUCTION
Dai Nippon Construction
Teito Rapid Transit Authority
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DAINIPPON CONSTRUCTION, Dai Nippon Construction, Teito Rapid Transit Authority filed Critical DAINIPPON CONSTRUCTION
Priority to JP13617199A priority Critical patent/JP2000328572A/en
Publication of JP2000328572A publication Critical patent/JP2000328572A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To prevent a working environment from deteriorating and a resulting cost from increasing at the time of removal produced in a temporary earth retaining timbering supporting walls applied with an external force such as earth pressure and hydraulic pressure. SOLUTION: A temporary earth retaining tempering supports a plurality of walls constructed under the ground and is removed after a specified process is completed. The temporary earth retaining timbering 1 comprises a support member 5 supporting the walls 10 in horizontal direction and a partition plate 4 provided between the support member 5 and the walls 10. After the temporary earth retaining timbering 1 is installed in an excavated groove corresponding to the size of the temporary earth retaining timbering 1, filler 2 is filled in a space between a ground 30 and the temporary earth retaining timbering 1, and the filler is collapsed when the ground surrounded by the walls and the temporary earth retaining timbering is excavated. Thus, the partition plate 4 and the support member 5 are allowed to be removed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地中連続壁におけ
る仮設土留支保構造の改良に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement of a temporary retaining structure for an underground continuous wall.

【0002】[0002]

【従来の技術とその課題】地中構造物の連続壁や床等の
後打ち躯体を構築する前には連続壁を支持するために必
要であるが、後打ち躯体構築後には不必要となり撤去さ
れる仮設の土留支保には図12に示す鉄筋コンクリート
にて構築するものがある。
2. Description of the Related Art It is necessary to support a continuous wall before constructing a post-cast body such as a continuous wall or a floor of an underground structure, but it is unnecessary after the post-cast frame is built and is removed. Some of the temporary earth retaining structures are constructed of reinforced concrete as shown in FIG.

【0003】この方法では後打ち躯体構築後の土留支保
の撤去の際にコンクリート粉砕に伴う粉塵によって作業
環境の悪化を招き、かつ撤去時間も長くなり、撤去コス
トの増大を招くといった問題がある。
[0003] In this method, there is a problem in that, when removing the earth retaining structure after the construction of the post-cast body, the work environment is deteriorated due to the dust accompanying the pulverization of the concrete, the removal time is increased, and the removal cost is increased.

【0004】上記問題を解決する方法として図13に示
す山留支保工法または図14に示すアースアンカー工法
を用いることも一般的に使用されているが、山留支保工
は施工条件が限られ、アースアンカー工法は連続壁の外
側にアースアンカーが侵入するため、外側にガス管等の
埋設物がある場合には採用することができないという制
約がある。
As a method for solving the above-mentioned problem, it is generally used to use a shore retaining method shown in FIG. 13 or an earth anchor method shown in FIG. 14, but the shore retaining method has limited construction conditions. The earth anchor method has a limitation that it cannot be used when there is a buried object such as a gas pipe on the outside because the earth anchor penetrates outside the continuous wall.

【0005】さらに図15に示すものは、連続壁の壁厚
を増加させて、連続壁自体の強度を増強することで、土
留支保を廃止したもので、壁内の空間を優先させると外
縁が既存の埋設物や構造物に干渉することが考えられ、
干渉を避けるには内縁を内側に移動せざるを得ず、結果
として内空間スペースを削減することになるというジレ
ンマが生じる。
[0005] Further, what is shown in FIG. 15 is one in which the retaining wall is abolished by increasing the wall thickness of the continuous wall and increasing the strength of the continuous wall itself. It may interfere with existing buried objects and structures,
In order to avoid interference, the inner edge must be moved inward, resulting in a dilemma of reducing the inner space space.

【0006】本発明は、これらの問題を解決する鉄筋コ
ンクリート構造物の地中連続壁における仮設土留支保工
法を提供することを目的とする。
SUMMARY OF THE INVENTION An object of the present invention is to provide a method for temporarily retaining a retaining ground in an underground continuous wall of a reinforced concrete structure which solves these problems.

【0007】[0007]

【課題を解決するための手段】第1の発明では、地中に
構築される複数の壁を支持し、所定の工程終了後に撤去
される地中連続壁における仮設土留支保工法において、
仮設土留支保は、前記壁を水平方向に支持する支持部材
と前記支持部材と壁との間に介装される仕切板と、を備
え、仮設土留支保の大きさに対応する掘削溝に土留支保
を据え付けた後に、地盤と仮設土留支保との空隙に充填
材を充填し、前記充填材は、壁と仮設土留支保に囲まれ
る地盤の掘削時に崩壊させ、前記仕切板と支持部材を撤
去可能とした。
According to a first aspect of the present invention, there is provided a method of supporting a plurality of walls constructed underground, and providing a temporary soil retaining support for an underground continuous wall which is removed after a predetermined process.
The temporary soil support includes a support member that supports the wall in a horizontal direction and a partition plate interposed between the support member and the wall, and the temporary soil support is provided in an excavation groove corresponding to the size of the temporary soil support. After installing, filling the gap between the ground and the temporary soil support with filler, the filler is collapsed when excavating the ground surrounded by walls and the temporary soil support, and the partition plate and the support member can be removed. did.

【0008】第2の発明は、第1の発明において、前記
充填材は、砕石または砂であるとした。
In a second aspect based on the first aspect, the filler is crushed stone or sand.

【0009】第3の発明は、第1または2の発明におい
て、前記支持部材は、鋼材からなる構成とした。
In a third aspect based on the first or second aspect, the support member is made of a steel material.

【0010】第4の発明は、第1から3のいずれか一つ
の発明において、前記支持部材は支持部材の長さを調整
可能とするをジャッキ手段を備えた。
According to a fourth aspect of the present invention, in any one of the first to third aspects, the support member has a jack means for adjusting the length of the support member.

【0011】第5の発明は、第4の発明において、前記
ジャッキ手段は、同一高さの隣り合った支持部材では、
支持部材の長さ方向で異なる位置に設置することとし
た。
According to a fifth aspect of the present invention, in the fourth aspect of the present invention, the jack means includes two supporting members having the same height.
The support members are installed at different positions in the length direction.

【0012】第6の発明は、第1から5のいずれか一つ
の発明において、前記仮設土留支保は、前記充填材の下
側をコンクリートによって固定されるとした。
[0012] In a sixth aspect based on any one of the first to fifth aspects, the temporary soil retaining support is fixed below the filler by concrete.

【0013】[0013]

【発明の作用および効果】第1から3の発明では、仕切
板と支持部材によって構成される仮設土留支保を所定の
掘削溝に据え付けた後に、充填材、たとえば砕石、砂を
充填することで、壁に作用する土圧、水圧等の外力に対
抗することができる。また、壁と仮設土留支保に囲まれ
た地盤を掘削するときに充填材も地盤と一緒に崩れ落ち
るので、仮設土留支保の撤去が容易となる効果もある。
According to the first to third aspects of the present invention, after a temporary earth retaining support composed of a partition plate and a support member is installed in a predetermined excavation groove, a filler, for example, crushed stone or sand is filled. It can resist external force such as earth pressure and water pressure acting on the wall. In addition, when excavating the ground surrounded by the wall and the temporary soil retaining support, the filler also collapses together with the ground, so that the temporary soil retaining support can be easily removed.

【0014】壁と仮設土留支保に囲まれた地盤を掘削
後、壁の間に床が構築されれば、外力は床によって支持
されるので、仮設土留支保を撤去することができるが、
本発明では、支持部材をたとえば、切断することで、き
わめて容易に、かつ短時間に撤去を行うことができる。
よって、全体施工期間の短縮および施工コストの削減が
可能となる。
If a floor is constructed between the walls after excavating the ground surrounded by the wall and the temporary retaining support, the external force is supported by the floor, so that the temporary retaining support can be removed.
In the present invention, the support member can be removed very easily and in a short time, for example, by cutting.
Therefore, it is possible to shorten the entire construction period and reduce the construction cost.

【0015】第4の発明は、支持部材は支持部材の長さ
を調整可能とするをジャッキ手段を備えたので、土留支
保を撤去するときにジャッキ手段を緩め、支持部材を短
縮することで、作業を安全にかつ効率的に実施すること
が可能である。
According to a fourth aspect of the present invention, the support member is provided with jack means for adjusting the length of the support member. Therefore, the jack means is loosened and the support member is shortened when removing the earth retaining support. Work can be performed safely and efficiently.

【0016】第5の発明は、ジャッキ手段は、同一高さ
の隣り合った支持部材では、支持部材の長さ方向で異な
る位置に設置することとしたので、ジャッキ手段を緩め
るときに隣り合うジャッキ手段が邪魔になることがな
く、作業を安全にかつ効率的に実施することが可能であ
る。
According to a fifth aspect of the present invention, the jack means are disposed at different positions in the longitudinal direction of the support member between adjacent support members having the same height. The work can be performed safely and efficiently without the means being in the way.

【0017】第6の発明は、仮設土留支保は、前記充填
材の下側をコンクリートによって固定されるので、仮設
土留支保を安定させ、充填材を安全、確実に充填するこ
とが可能である。
According to the sixth aspect of the present invention, since the temporary soil retaining support is fixed with concrete on the lower side of the filler, the temporary soil retaining support can be stabilized, and the filler can be safely and reliably filled.

【0018】[0018]

【発明の実施の形態】以下、本発明の実施形態を添付図
面に基づいて説明する。
Embodiments of the present invention will be described below with reference to the accompanying drawings.

【0019】図1には本発明の地中連続壁における仮設
土留支保工法の概略が示されている。
FIG. 1 shows an outline of a method of supporting a temporary soil retaining structure on an underground continuous wall according to the present invention.

【0020】これについて説明すると、図1は仮設土留
支保1と、仮設土留支保1によって支持される連続壁1
0が打設された状態を示しており、次工程において地盤
30が掘削されることで土圧、水圧等の外力Fが連続壁
10に作用し、連続壁10が変形することを仮設土留支
保1によって抑止するものである。
To explain this, FIG. 1 shows a temporary soil support 1 and a continuous wall 1 supported by the temporary soil support 1.
0 indicates a state in which the continuous ground 10 is excavated in the next step, and an external force F such as earth pressure and water pressure acts on the continuous wall 10 to deform the continuous wall 10. 1 is deterred.

【0021】図2は同じく土留支保構造の概略を示す断
面図であり、仮設支保1と地盤30との間の空隙には砕
石2が充填され、地盤30の崩壊を防止している。
FIG. 2 is a cross-sectional view schematically showing the earth retaining structure, in which a gap between the temporary support 1 and the ground 30 is filled with crushed stones 2 to prevent the ground 30 from collapsing.

【0022】なお充填材は砕石に限られるものではな
く、たとえば砂であってもよい。
The filler is not limited to crushed stone, but may be sand, for example.

【0023】また砕石2の下側には仮設支保1の根入れ
部分として、数メートルの深さにわたって、コンクリー
ト(下部コンクリート3)によって打設され、所定の位
置に固定されている。
The crushed stone 2 is cast with concrete (lower concrete 3) at a depth of several meters as a rooting portion of the temporary support 1 and is fixed at a predetermined position.

【0024】なお仮設土留支保1は連続壁10間にわた
って形成される必要は必ずしもなく、一部にのみ使用す
ることもできる。
The temporary soil retaining support 1 does not necessarily need to be formed over the continuous walls 10, but may be used only partially.

【0025】引き続き図3から5を用いて、仮設土留支
保1の構成について説明する。
Next, the structure of the temporary earth retaining support 1 will be described with reference to FIGS.

【0026】先行エレメントとしての仮設土留支保1は
連続壁10と接する鋼板からなる仕切板4と、2枚の仕
切板4間を保持する、たとえばH型鋼で形成される支持
部材5とから構成されている。
The temporary earth retaining support 1 as a preceding element is composed of a partition plate 4 made of a steel plate in contact with the continuous wall 10 and a support member 5 formed between the two partition plates 4 and formed of, for example, H-shaped steel. ing.

【0027】なお仮設土留支保1の長さによっては複数
の仕切板4を接続プレート6および接続ボルト7を用い
て接続することで長さを延長することも可能である。
Note that, depending on the length of the temporary soil retaining support 1, it is possible to extend the length by connecting the plurality of partition plates 4 using the connecting plate 6 and the connecting bolts 7.

【0028】また図5に示すごとく各支持部材5にジャ
ッキ8を設置することで、施工後に仮設土留支保1を撤
去する際に、ジャッキ8を緩めることで効率的に撤去を
行うことができる。
By installing jacks 8 on each support member 5 as shown in FIG. 5, when removing the temporary soil retaining support 1 after construction, the jacks 8 can be efficiently removed by loosening the jacks 8.

【0029】次に図6から11を用いて本発明の仮設土
留支保1の施工方法について説明する。
Next, a method of installing the temporary soil retaining support 1 of the present invention will be described with reference to FIGS.

【0030】まず、図6で、クレーン21から吊り下げ
られたクラムシェル20により仮設土留支保に対応する
溝を掘削する。このときに掘削面の保護のため掘削に応
じてベントナイトなどを含む泥水22を溝内に注入す
る。
First, in FIG. 6, a groove corresponding to the temporary soil retaining support is excavated by the clam shell 20 suspended from the crane 21. At this time, muddy water 22 containing bentonite or the like is injected into the trench according to the excavation to protect the excavated surface.

【0031】次に、図7に示すように、吊込具25を用
いて仮設土留支保1を溝内に吊り下ろす。
Next, as shown in FIG. 7, the temporary soil retaining support 1 is hung in the groove using the hanging tool 25.

【0032】その後図8に示すように、トレミー管26
を介して地上の生コン車27から下部コンクリート3を
形成する生コンクリートを溝内下部に投入する。生コン
クリートの投入に応じて溝内の泥水22は図示されない
抗口から排出される。
Thereafter, as shown in FIG.
The ready-mixed concrete which forms the lower concrete 3 from the ready-mixed concrete truck 27 on the ground is put into the lower part in the groove. The muddy water 22 in the groove is discharged from a headway (not shown) according to the input of the ready-mixed concrete.

【0033】このようにしてコンクリートの打設が完了
したら、引き続き砕石2を溝内に充填する。
When the concrete placement is completed in this way, the crushed stone 2 is continuously filled in the groove.

【0034】以上の工程にて、仮設土留支保1の構築を
終了し、後行エレメントである連続壁10の構築を行
う。
In the above steps, the construction of the temporary soil retaining support 1 is completed, and the continuous wall 10 as a subsequent element is constructed.

【0035】図9は所定の連続壁10のコンクリートを
打設養生した状態を示しており、この状態から連続壁1
0と仮設土留支保1で囲まれる地盤30を掘削する。こ
の地盤30掘削時に、仮設土留支保1内に充填された砕
石2も除去され、連続壁10間を結合する床11を下側
より構築する(図10中に破線で示す)。床11を構築
することで、連続壁10に作用する外力に抗する機能を
床11が担うので、仮設土留支保1の撤去が実施でき
る。
FIG. 9 shows a state in which the concrete of the predetermined continuous wall 10 has been poured and cured.
Excavate the ground 30 surrounded by 0 and the temporary soil retaining support 1. When the ground 30 is excavated, the crushed stone 2 filled in the temporary soil retaining support 1 is also removed, and a floor 11 connecting the continuous walls 10 is constructed from below (shown by a broken line in FIG. 10). By constructing the floor 11, the floor 11 has a function of resisting an external force acting on the continuous wall 10, so that the temporary soil retaining support 1 can be removed.

【0036】仮設土留支保1の撤去状態を図11に示
す。
FIG. 11 shows a state where the temporary soil retaining support 1 is removed.

【0037】仮設土留支保1の撤去は支持部材5を切断
することで容易に撤去することが可能であるが、前記し
たように支持部材5にジャッキ6を介装することでさら
に効率的に撤去作業を行うことができる。
The temporary soil retaining support 1 can be easily removed by cutting the support member 5, but as described above, the support member 5 can be more efficiently removed by interposing the jack 6 therein. Work can be done.

【0038】以上述べてきたように、本発明の仮設土留
支保工法では、仕切板4と支持部材5によって構成され
る仮設土留支保1を所定の掘削溝に据え付けた後に、砕
石3、を充填することで、連続壁10に作用する土圧、
水圧等の外力に対抗することができる。また、連続壁1
0と仮設土留支保1に囲まれた地盤30を掘削するとき
に砕石3も地盤30と一緒に崩れ落ちるので、仮設土留
支保1の撤去が容易となる効果もある。
As described above, in the temporary soil retaining method of the present invention, the temporary soil retaining structure 1 composed of the partition plate 4 and the support member 5 is installed in a predetermined excavation groove, and then the crushed stone 3 is filled. That is, the earth pressure acting on the continuous wall 10,
It can resist external force such as water pressure. In addition, continuous wall 1
When excavating the ground 30 surrounded by 0 and the temporary soil support 1, the crushed stone 3 also collapses together with the ground 30, so that the temporary soil support 1 can be easily removed.

【0039】さらに連続壁10と仮設土留支保1に囲ま
れた地盤30を掘削後、連続壁10の間に床11が構築
されれば、外力は床によって支持されるので、仮設土留
支保1を撤去することができ、本発明では、支持部材5
を切断もしくはジャッキ8を緩めることで、きわめて容
易に、かつ短時間に撤去を行うことができる。よって、
全体施工期間の短縮および施工コストの削減が可能とな
る。
Further, if a floor 11 is constructed between the continuous wall 10 after excavating the ground 30 surrounded by the continuous wall 10 and the temporary soil retaining support 1, external force is supported by the floor. The support member 5 can be removed.
By cutting or loosening the jack 8, removal can be performed very easily and in a short time. Therefore,
The entire construction period can be shortened and the construction cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施形態を示す平面図である。FIG. 1 is a plan view showing an embodiment of the present invention.

【図2】同じく断面図である。FIG. 2 is a sectional view of the same.

【図3】同じく仮設土留支保の構成を示す正面図であ
る。
FIG. 3 is a front view showing the structure of the temporary soil retaining support.

【図4】同じく側面図である。FIG. 4 is a side view of the same.

【図5】同じく平面図である。FIG. 5 is a plan view of the same.

【図6】同じく施工方法を示す正面図である(溝掘削状
態)。
FIG. 6 is a front view showing the construction method (ditch excavation state).

【図7】同じく施工方法を示す正面図である(仮設土留
支保溝内搬入状態)。
FIG. 7 is a front view showing the construction method (a state of being carried into a temporary retaining retaining groove).

【図8】同じく施工方法を示す正面図である(コンクリ
ート打設状態)。
FIG. 8 is a front view showing the construction method (concrete casting state).

【図9】同じく連続壁コンクリート打設完了状態を示す
平面図である。
FIG. 9 is a plan view showing a completed state of the continuous wall concrete casting.

【図10】同じく断面図である。FIG. 10 is a sectional view of the same.

【図11】同じく撤去状態を示す正面図である。FIG. 11 is a front view showing the disassembled state.

【図12】従来例を示す平面図である。FIG. 12 is a plan view showing a conventional example.

【図13】同じく従来例を示す平面図である。FIG. 13 is a plan view showing a conventional example.

【図14】同じく従来例を示す平面図である。FIG. 14 is a plan view showing a conventional example.

【図15】同じく従来例を示す平面図である。FIG. 15 is a plan view showing a conventional example.

【符号の説明】[Explanation of symbols]

1 仮設土留支保 2 砕石 3 下部コンクリート 4 仕切板 5 支持部材 6 接続プレート 7 接続ボルト 8 ジャッキ 10 連続壁 11 床 30 地盤 DESCRIPTION OF SYMBOLS 1 Temporary earth retaining support 2 Crushed stone 3 Lower concrete 4 Partition plate 5 Support member 6 Connection plate 7 Connection bolt 8 Jack 10 Continuous wall 11 Floor 30 Ground

───────────────────────────────────────────────────── フロントページの続き (72)発明者 和田野 純一 東京都新宿区市谷田町2−35 大日本土木 株式会社内 Fターム(参考) 2D049 AA07 AA08 EA02 GA16 GC03 ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Junichi Wadano 2-35 Yatacho, Shinjuku-ku, Tokyo Dainippon Civil Engineering Co., Ltd. F-term (reference) 2D049 AA07 AA08 EA02 GA16 GC03

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 地中に構築される複数の壁を支持し、所
定の工程終了後に撤去される地中連続壁における仮設土
留支保工法において、 仮設土留支保は、前記壁を水平方向に支持する支持部材
と 前記支持部材と壁との間に介装される仕切板と、を備
え、 仮設土留支保の大きさに対応する掘削溝に仮設土留支保
を据え付けた後に、地盤と仮設土留支保との空隙に充填
材を充填し、 前記充填材は、壁と仮設土留支保に囲まれる地盤の掘削
時に崩壊させ、 前記仕切板と支持部材を撤去可能としたことを特徴とす
る地中連続壁における仮設土留支保工法。
1. A method of supporting a plurality of walls constructed underground and removing the temporary underground continuous wall after a predetermined process is completed, wherein the temporary soil retaining support horizontally supports the walls. A support member and a partition plate interposed between the support member and the wall, and after installing the temporary soil support in an excavation groove corresponding to the size of the temporary soil support, the ground and the temporary soil support are connected to each other. Filling the gap with a filler, the filler collapses during excavation of the ground surrounded by the wall and the temporary soil retaining support, and the partition plate and the support member can be removed. Soil retaining method.
【請求項2】 前記充填材は、砕石または砂であること
を特徴とする請求項1に記載の地中連続壁における仮設
土留支保工法。
2. The method according to claim 1, wherein the filler is crushed stone or sand.
【請求項3】 前記支持部材は、鋼材からなることを特
徴とする請求項1または2に記載の地中連続壁における
仮設土留支保工法。
3. The method according to claim 1, wherein the support member is made of a steel material.
【請求項4】 前記支持部材は支持部材の長さを調整可
能とするをジャッキ手段を備えたことを特徴とする請求
項1から3のいずれか一つに記載の地中連続壁における
仮設土留支保工法。
4. The temporary retaining soil in an underground continuous wall according to claim 1, wherein the supporting member has a jack means for adjusting a length of the supporting member. Shoring method.
【請求項5】 前記ジャッキ手段は、同一高さの隣り合
った支持部材では、支持部材の長さ方向で異なる位置に
設置したことを特徴とする請求項4に記載の地中連続壁
における仮設土留支保工法。
5. The temporary installation in an underground continuous wall according to claim 4, wherein the jack means is installed at different positions in the length direction of the support member between adjacent support members having the same height. Soil retaining method.
【請求項6】 前記仮設土留支保は、前記充填材の下側
をコンクリートによって固定されることを特徴とする請
求項1から5のいずれか一つに記載の地中連続壁におけ
る仮設土留支保工法。
6. The method according to claim 1, wherein the temporary soil retaining support is fixed below the filler by concrete. .
JP13617199A 1999-05-17 1999-05-17 Temporary earth retaining timbering method in underground continuous wall Pending JP2000328572A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13617199A JP2000328572A (en) 1999-05-17 1999-05-17 Temporary earth retaining timbering method in underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13617199A JP2000328572A (en) 1999-05-17 1999-05-17 Temporary earth retaining timbering method in underground continuous wall

Publications (1)

Publication Number Publication Date
JP2000328572A true JP2000328572A (en) 2000-11-28

Family

ID=15168995

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13617199A Pending JP2000328572A (en) 1999-05-17 1999-05-17 Temporary earth retaining timbering method in underground continuous wall

Country Status (1)

Country Link
JP (1) JP2000328572A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193053A (en) * 2016-09-09 2016-12-07 中建三局集团有限公司 A kind of subway foundation pit assembled horizontal struts system and assembling constructing method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193053A (en) * 2016-09-09 2016-12-07 中建三局集团有限公司 A kind of subway foundation pit assembled horizontal struts system and assembling constructing method thereof

Similar Documents

Publication Publication Date Title
KR100656194B1 (en) Open cut and cover method applying tunnel cut method
JP6543176B2 (en) Building method
KR100313720B1 (en) Composite Underground Structure Construction Method
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP3453664B2 (en) Shaft construction method
JP4226954B2 (en) Underpinning method and viaduct
JPH1136338A (en) Construction method of underground structure
JP5378066B2 (en) Mountain fastening method
JP2000328572A (en) Temporary earth retaining timbering method in underground continuous wall
JP3194192B2 (en) Open shield method
JPH0762436B2 (en) Open shield method
KR102664851B1 (en) Existing underground building demolition method using sheet pile
JP7437336B2 (en) Temporary cofferdam method, temporary cofferdam structure
JP3030622B2 (en) How to build a tunnel
JP2963802B2 (en) How to build an underground parking
JP2745083B2 (en) Tunnel construction method
KR102087978B1 (en) A method of pressurizing steel pipe and a method of constructing an underground structure in a lower toe pipe section
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
JPH11269870A (en) Execution method of joint for underground continuous wall
JP3794097B2 (en) Construction method for underground structures
JP2949623B1 (en) How to build a tunnel
JP3113982B2 (en) Tunnel construction method on soft ground
JP3898929B2 (en) Liquefaction prevention structure
JP2848289B2 (en) Open caisson blade structure
JPH11152988A (en) Construction method of underground structure

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Effective date: 20040422

Free format text: JAPANESE INTERMEDIATE CODE: A712

RD03 Notification of appointment of power of attorney

Effective date: 20041021

Free format text: JAPANESE INTERMEDIATE CODE: A7423

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20041022

A621 Written request for application examination

Effective date: 20060428

Free format text: JAPANESE INTERMEDIATE CODE: A621

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080314

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080325

A02 Decision of refusal

Effective date: 20080729

Free format text: JAPANESE INTERMEDIATE CODE: A02