JPH11269870A - Execution method of joint for underground continuous wall - Google Patents

Execution method of joint for underground continuous wall

Info

Publication number
JPH11269870A
JPH11269870A JP7883198A JP7883198A JPH11269870A JP H11269870 A JPH11269870 A JP H11269870A JP 7883198 A JP7883198 A JP 7883198A JP 7883198 A JP7883198 A JP 7883198A JP H11269870 A JPH11269870 A JP H11269870A
Authority
JP
Japan
Prior art keywords
joint
concrete
bag
ground
bag body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7883198A
Other languages
Japanese (ja)
Inventor
Akiro Ueda
昭郎 上田
Muneo Yoshimura
宗男 吉村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP7883198A priority Critical patent/JPH11269870A/en
Publication of JPH11269870A publication Critical patent/JPH11269870A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To make it possible to surely bear concrete side pressure with a simple method in the case concrete for preceeding elements is cast when a steel plate is used for a joint, enable the reuse of a member for that purpose as well as the promotion of economical efficiency and to make it possible to manufacture the joint with high execution efficiency without requiring any casting height adjustment of concrete. SOLUTION: An execution method of a joint for an underground continuous wall is so constituted that ditches are excavated in the ground at specific intervals, concrete is cast to execute preceeding elements 1, ground between the preceeding elements 1 is excavated, concrete is cast therein to execute following elements and that the preceeding elements and following elements are continued at joint surfaces of their ends. Expansible bag bodies 9 are mounted to the outises of joint steel plates 4 arranged to the joint surfaces, the bag bodies 9 are expanded in the case concrete for the preceeding elements 1 is cast, side pressure in the case of concrete casting is borne on bedrocks 8 of the excavated ditches 2 through the bag bodies 9, and after the concrete is solidified, the bag bodies 9 are contracted to remove them from the insides of the excavated ditches 2.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地中連続壁の継手
の施工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a joint for an underground continuous wall.

【0002】[0002]

【従来の技術】地中連続壁を構築する場合、地中に間隔
をおいて溝を掘削し、この掘削溝内にコンクリートを打
設して先行エレメントを構築し、次に、この先行エレメ
ント間の地盤に溝を掘削し、この掘削溝内にコンクリー
トを打設して後行エレメントを構築し、先行エレメント
と後行エレメントをそれぞれの端部の継手面で連続させ
て連続壁を構築する。
2. Description of the Related Art When constructing an underground continuous wall, trenches are excavated at intervals in the ground, concrete is poured into the excavation trench to construct a leading element, and then, a space between the leading elements is formed. A groove is excavated in the ground, and concrete is poured into the excavation groove to construct a succeeding element, and a leading wall and a trailing element are connected to each other at a joint surface at each end to construct a continuous wall.

【0003】この地中連続壁の継手(エレメント間継
手)には種々の種類があるが、一例として継手面に鋼板
を用いるものがある。図9はその一例を示す接合鋼板継
手であり、先行エレメント1の掘削溝2内に配設した鉄
筋かご3の両端に接合鋼板4を取り付けてコンクリート
5を打設するもので、図10に示すように後行エレメント
6との継手面が接合鋼板4となる。
[0003] There are various types of joints (inter-element joints) for the underground continuous wall. One example is a steel plate used for the joint surface. FIG. 9 shows a joint steel plate joint showing one example of the joint, in which a joint steel plate 4 is attached to both ends of a reinforcing steel cage 3 arranged in a digging groove 2 of a preceding element 1 and concrete 5 is cast, and is shown in FIG. Thus, the joint surface with the following element 6 becomes the joining steel plate 4.

【0004】かかる接合鋼板継手では先行エレメント1
のコンクリート打設時の側圧を接合鋼板4で受けること
になるため、これに耐えるよう接合鋼板4を鉄筋かご3
の水平鉄筋の端部に溶接するなどしているが、通常使用
する6.0 mm〜9.0 mm程度の厚さの接合鋼板4では強
度が十分ではなく、接合鋼板4に過大な変形が生じたり
する。
In such a jointed steel plate joint, the leading element 1
The joint steel plate 4 receives the lateral pressure at the time of concrete casting of the steel plate 4 so that the steel plate 4 can withstand this.
Is welded to the end of the horizontal reinforcing bar, but the strength of the joint steel plate 4 having a thickness of about 6.0 mm to 9.0 mm which is usually used is not sufficient, and the joint steel plate 4 may be excessively deformed.

【0005】そこで、例えば図9にも示すように接合鋼
板4の外側箇所で掘削溝2内に砕石7などを投入してコ
ンクリート打設時の側圧に耐えるようにしている。この
砕石7の投入は、両側の継手への投入量のバランスをと
りながらコンクリート打込みに数m先行して行う。
Therefore, as shown in FIG. 9, for example, crushed stone 7 or the like is put into the excavation groove 2 at a position outside the joint steel plate 4 so as to withstand the lateral pressure at the time of placing concrete. The injection of the crushed stone 7 is performed several meters ahead of the concrete injection while balancing the input amounts to the joints on both sides.

【0006】[0006]

【発明が解決しようとする課題】前記のように接合鋼板
4を使用するタイプの継手で、打設するコンクリートの
側圧を支持する方法として砕石7を投入するものは、後
行エレメント6の掘削時に地山の掘削土とこの砕石が混
ざってしまうため、砕石7の回収・再利用が困難で経済
性がよくない。
As described above, the joint of the type using the joint steel plate 4 in which the crushed stone 7 is introduced as a method of supporting the lateral pressure of the concrete to be cast is used when the subsequent element 6 is excavated. Since the excavated soil of the ground is mixed with the crushed stone, it is difficult to recover and reuse the crushed stone 7 and the economic efficiency is not good.

【0007】また、砕石7の投入は、打設するコンクリ
ートの高さに合わせて徐々に量を増加させていく必要が
あり、打設するコンクリートと砕石の高さ調整を管理し
なければならず施工性がよくなかった。
In addition, it is necessary to gradually increase the amount of the crushed stone 7 in accordance with the height of the concrete to be cast, and it is necessary to control the height adjustment of the concrete to be poured and the crushed stone. Workability was not good.

【0008】さらに、継手に鋼板を使用するタイプで先
行エレメントの継手面に鉄筋などが後行エレメント側に
突出する剛結継手などの場合は、後行エレメントの施工
時に継手鉄筋を保護する必要があり、そのために保護板
などを建て込む必要もある。
Further, in the case of a type using a steel plate for the joint, such as a rigid joint in which a reinforcing bar or the like projects on the joint surface of the preceding element toward the succeeding element, it is necessary to protect the joint reinforcing bar when the succeeding element is constructed. Yes, it is necessary to build a protection plate and so on.

【0009】かかる不都合は継手に鋼板を使用しなけれ
ば解決され、鋼板を使用しないタイプとして例えば先行
エレメントの端部に断面円形の鋼管(インターロッキン
グパイプ)を建て込み、このインターロッキングパイプ
で打設コンクリートの側圧を負担するものがあり、打設
したコンクリートの硬化に合わせてインターロッキング
パイプを引き抜き、水平断面が半円形の空間を形成して
エレメント間を接続するものである。
This inconvenience can be solved by using no steel plate for the joint. For example, a steel pipe (interlocking pipe) having a circular cross section is erected at the end of the preceding element as a type that does not use a steel plate, and is driven by this interlocking pipe. Some of them bear the lateral pressure of concrete, and pull out the interlocking pipe in accordance with the hardening of the poured concrete to form a space having a semicircular horizontal section and connect the elements.

【0010】しかし、このインターロッキングパイプ継
手では、掘削精度が悪いためや肌落ちによってインター
ロッキングパイプと地山との隙間が大きくなり、パイプ
背面にコンクリートが回り込んで後行エレメントの掘削
が困難になることや、インターロッキングパイプの引き
抜き時期が不適切であると引き抜き不能になるおそれも
ある。
[0010] However, in this interlocking pipe joint, the gap between the interlocking pipe and the ground is increased due to poor excavation accuracy and skin fall, and concrete wraps around the pipe back surface, making it difficult to excavate the following element. If the timing of pulling out the interlocking pipe is inappropriate, pulling out may not be possible.

【0011】本発明の目的は前記従来例の不都合を解消
し、継手に鋼板を使用する場合に、先行エレメントのコ
ンクリート打設時のコンクリート側圧を簡単な方法で確
実に負担でき、そのための部材の再利用も可能で経済性
の向上を図ることができ、また、コンクリートの打設高
さ調整も不要で施工性のよい地中連続壁の継手の施工法
を提供することにある。
SUMMARY OF THE INVENTION An object of the present invention is to solve the above-mentioned disadvantages of the prior art, and when using a steel plate for a joint, it is possible to reliably bear the concrete side pressure at the time of placing concrete in the preceding element in a simple manner. An object of the present invention is to provide a method of constructing a joint of an underground continuous wall, which can be reused to improve the economic efficiency, does not require adjustment of the concrete placement height, and has good workability.

【0012】[0012]

【課題を解決するための手段】本発明は前記目的を達成
するため、第1に、地中に間隔をおいて溝を掘削し、コ
ンクリートを打設して先行エレメントを施工し、該先行
エレメント間の地盤を掘削し、ここにコンクリートを打
設して後行エレメントを施工し、先行エレメントと後行
エレメントとをそれぞれの端部の継手面で連続させる地
中連続壁の継手の施工法において、継手面に配設する接
合鋼板の外側に膨縮自在な袋体を取り付け、先行エレメ
ントのコンクリート打設時に前記袋体を膨らませ、コン
クリート打設時の側圧を該袋体を介して掘削溝の地山側
で負担し、コンクリート硬化後、袋体を収縮して掘削溝
内から撤去することを要旨とするものである。
According to the present invention, in order to achieve the above object, firstly, trenches are dug at intervals in the ground, concrete is cast, and a preceding element is constructed. In the method of excavating the ground in between, casting concrete here and constructing the succeeding element, and connecting the preceding element and the succeeding element at the joint surface at each end of the underground continuous wall joint construction method An inflatable bag is attached to the outside of the joint steel plate provided on the joint surface, the bag is inflated when the preceding element is poured into the concrete, and the side pressure at the time of casting the concrete is applied to the excavation groove through the bag. The gist is to bear the burden on the ground side and, after hardening the concrete, shrink the bag and remove it from the excavation trench.

【0013】第2に、袋体の膨張は、掘削溝内に注入す
る安定液または泥水を袋体内に移送することにより行う
こと、第3に、袋体の収縮、撤去は、内部の液体を排出
し、袋体に取り付けた金物を介してワイヤーなどの吊り
部材で吊り上げて行うことを要旨とするものである。
Second, the bag is inflated by transferring a stabilizing liquid or mud injected into the digging trench into the bag. Third, the bag is contracted and removed by removing the liquid inside. The gist of the present invention is to discharge the paper, lift it up with a hanging member such as a wire through metal fittings attached to the bag, and carry out the processing.

【0014】請求項1記載の本発明によれば、先行エレ
メントと後行エレメントとの継手面に接合鋼板を配設す
る地中連続壁の継手の施工法において、先行エレメント
のコンクリート打設時に接合鋼板の外側に設けた袋体を
膨らませることで、コンクリート打設時の側圧を該袋体
を介して掘削溝の地山側で負担できるから、接合鋼板を
補強でき変形を防止できる。また、コンクリート打設前
に袋体を膨らませておくことで、その後一気にコンクリ
ートを打設でき、コンクリートの打設高さを従来のよう
に砕石の投入量に合うように管理する必要もない。
According to the first aspect of the present invention, in a method of jointing an underground continuous wall in which a joining steel plate is disposed on a joint surface between a preceding element and a following element, the joining is performed when the preceding element is poured into concrete. By inflating the bag provided outside the steel plate, the lateral pressure during concrete casting can be borne on the ground side of the excavation trench through the bag, so that the bonded steel plate can be reinforced and deformation can be prevented. In addition, by inflating the bag body before the concrete is poured, the concrete can be poured at a stretch afterward, and it is not necessary to control the concrete placement height to match the amount of crushed stone as in the related art.

【0015】そして、コンクリート硬化後は袋体を収縮
すれば、掘削溝内から簡単に撤去でき、袋体の再使用も
可能であり経済性が向上する。
After the concrete is hardened, if the bag is shrunk, it can be easily removed from the inside of the excavation groove, and the bag can be reused, thereby improving the economic efficiency.

【0016】請求項2記載の本発明によれば、前記作用
に加えて、袋体の膨張は、掘削溝内に注入する安定液ま
たは泥水を袋体内に移送することにより行うことで、液
移送用の例えばポンプを設置するだけで簡単に袋体内に
液体を注入して膨張させることができる。この場合、袋
体内の水位を掘削溝内の水位と同一に保つことで、溝壁
の安定保持を損なわないようにできる。
According to the second aspect of the present invention, in addition to the above-described operation, the expansion of the bag body is performed by transferring the stable liquid or muddy water to be injected into the excavation groove into the bag body. For example, a liquid can be easily injected into the bag body and inflated simply by installing a pump. In this case, by maintaining the water level in the bag body equal to the water level in the excavation groove, it is possible to prevent the groove wall from being stably maintained.

【0017】請求項3記載の本発明によれば、前記作用
に加えて、袋体の収縮、撤去は、内部の液体を排出し、
袋体に取り付けた金物を介してワイヤーなどの吊り部材
で吊り上げて行えるから、容易である。そして、袋体内
の液体は回収後、掘削溝内に戻せば溝内の水位を一定に
保持でき溝壁の安定を図れる。
According to the third aspect of the present invention, in addition to the above functions, the shrinking and removing of the bag body discharges the liquid inside,
Since it can be lifted by a suspending member such as a wire through a hardware attached to the bag body, it is easy. Then, if the liquid in the bag is returned to the excavation groove after collection, the water level in the groove can be kept constant, and the groove wall can be stabilized.

【0018】[0018]

【発明の実施の形態】以下、図面について本発明の実施
の形態を詳細に説明する。図1は本発明の地中連続壁の
継手の施工法の実施形態を示す平面図、図2は同上正面
図、図3は要部の平面図で、図9、図10に示した従来例
と同一の構成要素には同一の参照符号を付してある。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a plan view showing an embodiment of a method of installing a joint of an underground continuous wall according to the present invention, FIG. 2 is a front view of the same, FIG. 3 is a plan view of a main part, and FIG. The same components as those described above are denoted by the same reference numerals.

【0019】本発明方法では図6の作業フローに示すよ
うに1エレメント分の先行エレメント1の溝を掘削した
ならば、泥土処分、スライム除去の後、別途組み立てて
おいた鉄筋かご3を掘削溝2内に建て込み、次いで鉄筋
かご3の両外側に継手となる接合鋼板4を取り付け、さ
らにその外側で地山8との間の隙間10に掘削溝2内に膨
縮自在な袋体9を建て込む(図8(a)参照)。
In the method of the present invention, if the groove of the preceding element 1 for one element is excavated as shown in the work flow of FIG. 6, after the disposal of the mud and the removal of the slime, the rebar cage 3 assembled separately is excavated. 2, and then, to both sides of the reinforcing steel cage 3, a joint steel plate 4 serving as a joint is attached. Further, a bag body 9 that can be expanded and contracted into the excavation groove 2 is provided in a gap 10 between the outside and the ground 8. It is built (see FIG. 8A).

【0020】この袋体9は例えばゴムチューブ製とし
て、縦横の幅は鉄筋かご3の側部の大きさにほぼ等し
く、厚さは収縮状態で隙間10より小さく、膨張状態で隙
間10を埋める幅となるように形成し、上面の適宜箇所に
給水孔11と排水孔12とを設け、また、ワイヤーロープ14
などの吊り部材で吊り上げるための金物13を埋め込んで
おく。
The bag body 9 is made of, for example, a rubber tube, and has a width in the vertical and horizontal directions substantially equal to the size of the side of the reinforcing cage 3, a thickness smaller than the gap 10 in a contracted state, and a width filling the gap 10 in an expanded state. And water supply holes 11 and drain holes 12 are provided at appropriate locations on the upper surface.
A metal member 13 to be lifted by a suspending member such as is embedded.

【0021】図中15は先行エレメント1のコンクリート
打設時にコンクリートが継手部に流出するのを防止する
ための硬質ゴム製のプレートによるゴムシートで、接合
鋼板4の端部に平鋼16で挟みビス17などの止め具で取り
付けたものである。
In the figure, reference numeral 15 denotes a rubber sheet made of a hard rubber plate for preventing the concrete from flowing out to the joint portion when the preceding element 1 is poured into the concrete. It is attached with fasteners such as screws 17.

【0022】さらに図5に示すように溝壁の安定を図る
ため掘削溝2に注入する安定液19や泥水を袋体9内に移
送するためのポンプ18を掘削溝2の上部などの適宜箇所
に設置する。前記安定液19は一例としてベントナイト
系、ポリマー系のものを使用する。
Further, as shown in FIG. 5, a stabilizing solution 19 to be poured into the excavation groove 2 and a pump 18 for transferring muddy water into the bag body 9 for stabilizing the groove wall are provided at appropriate locations such as the upper portion of the excavation groove 2. Installed in As the stabilizing solution 19, for example, a bentonite type or a polymer type is used.

【0023】以上のようにして掘削溝2内に鉄筋かご
3、袋体9を建て込み、コンクリート流出防止工が終了
したならば、掘削溝2内に安定液19または泥水を注入
し、これをポンプ18で袋体9内に給水孔11から移送し、
袋体9内の水位を掘削溝2内の水位と同一に保持し、溝
壁の安定が損なわれないようにする。
When the reinforcing cage 3 and the bag 9 are erected in the excavation groove 2 as described above and the concrete outflow prevention work is completed, a stabilizing solution 19 or muddy water is injected into the excavation groove 2 and the water is poured. It is transferred from the water supply hole 11 into the bag body 9 by the pump 18,
The water level in the bag 9 is kept the same as the water level in the digging groove 2 so that the stability of the groove wall is not impaired.

【0024】こうして図1〜図3に鎖線で示すように、
また図5(b)、図8(b)のように袋体9を隙間10内
に膨らませ、掘削溝2の側壁である地山8と接合鋼板4
とに密着させ、この状態で鉄筋かご3内にコンクリート
5を打設する。
Thus, as shown by a chain line in FIGS.
Further, as shown in FIGS. 5B and 8B, the bag body 9 is inflated into the gap 10, and the ground 8 which is the side wall of the excavation groove 2 and the bonded steel plate 4 are formed.
Then, concrete 5 is poured into the reinforced car 3 in this state.

【0025】コンクリート打設により接合鋼板4にかか
る側圧は袋体9を介して地山8に伝達され、ここで支持
される。よって、コンクリート側圧によって接合鋼板4
が変形することはない。
The lateral pressure applied to the bonded steel plate 4 by the concrete casting is transmitted to the ground 8 via the bag 9 and is supported there. Therefore, the joint steel plate 4
Is not deformed.

【0026】コンクリート5が硬化した後、排水孔12か
ら袋体9内の液をポンプ18で掘削溝2内に排出し、袋体
9を縮め(図8(c)参照)、これをワイヤーロープ14
などの吊り部材で吊り上げて掘削溝2から撤去する。こ
の場合、袋体9内の液は前記のように掘削溝2内に戻さ
れるから、掘削溝2内の水位を一定に保持できる。
After the concrete 5 has hardened, the liquid in the bag 9 is discharged from the drain hole 12 into the excavation groove 2 by the pump 18 to shrink the bag 9 (see FIG. 8 (c)). 14
And lift it off the excavation groove 2. In this case, the liquid in the bag body 9 is returned to the digging groove 2 as described above, so that the water level in the digging groove 2 can be kept constant.

【0027】そして、回収した袋体9は次の施工場所で
の再使用が可能である。
The collected bag 9 can be reused at the next construction site.

【0028】前記した第1実施形態では、鉄筋かご3を
建て込んだ後に袋体9を別工程で建て込むようにした
が、これに限定されるものではなく、図7に示すように
鉄筋かご3の両側の接合鋼板4の外側に袋体9を接着剤
などで予め仮止めしておき、鉄筋かご3の建て込みによ
り同時に袋体9を建て込むようにすることもできる。こ
の場合も第1実施形態と同様、コンクリート5が硬化し
た後、袋体9を撤去し、次のエレメントの施工で使用す
る。
In the above-described first embodiment, the bag 9 is built in a separate step after the reinforcing cage 3 is built. However, the present invention is not limited to this. The bag body 9 may be temporarily fixed to the outside of the joint steel plate 4 on both sides of the steel sheet 3 with an adhesive or the like in advance, and the bag body 9 may be simultaneously built by embedding the reinforcing basket 3. In this case, similarly to the first embodiment, after the concrete 5 has hardened, the bag 9 is removed and used for the construction of the next element.

【0029】[0029]

【発明の効果】以上述べたように本発明の地中連続壁の
施工法は、先行エレメントと後行エレメントとの継手面
に接合鋼板を配設する地中連続壁の継手工法において、
先行エレメントのコンクリート打設時に接合鋼板の外側
に設けた袋体を膨らませることで、コンクリート打設時
の側圧を該袋体を介して掘削溝の地山側で負担できるか
ら、接合鋼板を補強でき変形を防止できる。また、コン
クリート打設前に袋体を膨らませておくことで、その後
一気にコンクリートを打設でき、コンクリートの打設高
さを従来のように砕石の投入量に合うように管理する必
要がなく、施工性か向上する。
As described above, the method for constructing an underground continuous wall according to the present invention is a joint method for an underground continuous wall in which a joining steel plate is disposed on a joint surface between a preceding element and a following element.
By inflating the bag provided on the outside of the joint steel plate at the time of placing the concrete of the preceding element, the lateral pressure at the time of placing the concrete can be borne on the ground side of the excavation groove through the bag, so that the joint steel plate can be reinforced. Deformation can be prevented. In addition, by inflating the bag before casting concrete, the concrete can be poured at once, and there is no need to control the concrete placement height to match the amount of crushed stone as in the past. Improve sexuality.

【0030】そして、コンクリート硬化後は袋体を収縮
すれば、掘削溝内から簡単に撤去でき、袋体の再使用も
可能であり経済性が向上する。
After the concrete is hardened, if the bag is shrunk, the bag can be easily removed from the inside of the excavation groove, and the bag can be reused, thereby improving the economic efficiency.

【0031】また、袋体の膨張は、掘削溝内に注入する
安定液または泥水を袋体内に移送することにより行うこ
とで、液移送用の例えばポンプを設置するだけで簡単に
袋体内に液体を注入して膨張させることができる。この
場合、袋体内の水位を掘削溝内の水位と同一に保つこと
で、溝壁の安定保持を損なわないようにできる。
The inflation of the bag is performed by transferring a stable liquid or muddy water to be injected into the excavation groove into the bag, so that the liquid can be easily stored in the bag simply by installing a pump for transferring the liquid. Can be injected to inflate. In this case, by maintaining the water level in the bag body equal to the water level in the excavation groove, it is possible to prevent the groove wall from being stably maintained.

【0032】さらに、袋体の収縮、撤去は、内部の液体
を排出し、袋体に取り付けた金物を介してワイヤーなど
の吊り部材で吊り上げて行えるから、容易である。そし
て、袋体内の液体は回収後、掘削溝内に戻せば溝内の水
位を一定に保持でき溝壁の安定を図れるものである。
Further, shrinkage and removal of the bag can be easily performed by discharging the internal liquid and lifting the bag with a hanging member such as a wire through metal fittings attached to the bag. Then, if the liquid in the bag is returned to the excavation groove after collection, the water level in the groove can be kept constant, and the groove wall can be stabilized.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の地中連続壁の継手の施工法の平面図で
ある。
FIG. 1 is a plan view of a method of constructing a joint of an underground continuous wall according to the present invention.

【図2】本発明の地中連続壁の継手の施工法の正面図で
ある。
FIG. 2 is a front view of a method for constructing a joint of an underground continuous wall according to the present invention.

【図3】本発明の地中連続壁の継手の施工法の要部の平
面図である。
FIG. 3 is a plan view of a main part of a method of constructing a joint of an underground continuous wall according to the present invention.

【図4】本発明の地中連続壁の継手の施工法の図3の平
面図の要部の平面図である。
FIG. 4 is a plan view of a main part of the plan view of FIG. 3 of the method of installing a joint of an underground continuous wall according to the present invention.

【図5】本発明の地中連続壁の継手の施工法の袋体への
液注入状態を示す説明図である。
FIG. 5 is an explanatory view showing a state in which liquid is injected into a bag body by the method of installing a joint of an underground continuous wall according to the present invention.

【図6】本発明の地中連続壁の継手の施工法の袋体建て
込みの第1実施形態を示す作業のフローチャートであ
る。
FIG. 6 is a flow chart of a work showing a first embodiment of erection of a bag body by a method of constructing a joint of an underground continuous wall according to the present invention.

【図7】本発明の地中連続壁の継手の施工法の袋体建て
込みの第2実施形態を示す作業のフローチャートであ
る。
FIG. 7 is a flow chart of an operation showing a second embodiment of laying a bag in the method of constructing a joint of an underground continuous wall according to the present invention.

【図8】本発明の地中連続壁の継手の施工法の袋体の膨
張、収縮の過程を示す説明図である。
FIG. 8 is an explanatory view showing a process of inflation and shrinkage of a bag body in the method of constructing a joint of an underground continuous wall according to the present invention.

【図9】従来の地中連続壁の継手の施工法の一例を示す
先行エレメントの平面図である。
FIG. 9 is a plan view of a preceding element showing an example of a conventional method of constructing an underground continuous wall joint.

【図10】従来の地中連続壁の継手の施工法の一例であ
る接合鋼板継手の平面図である。
FIG. 10 is a plan view of a joint steel plate joint which is an example of a conventional method of constructing a joint for an underground continuous wall.

【符号の説明】[Explanation of symbols]

1…先行エレメント 2…掘削溝 3…鉄筋かご 4…接合鋼板 5…コンクリート 6…後行エレメント 7…砕石 8…地山 9…袋体 10…隙間 11…給水孔 12…排水孔 13…金物 14…ワイヤーロープ 15…ゴムシート 16…平鋼 17…ビス 18…ポンプ 19…安定液 DESCRIPTION OF SYMBOLS 1 ... Leading element 2 ... Excavation groove 3 ... Rebar cage 4 ... Joint steel plate 5 ... Concrete 6 ... Trailing element 7 ... Crushed stone 8 ... Ground mountain 9 ... Bag 10 ... Gap 11 ... Water supply hole 12 ... Drain hole 13 ... Hardware 14 ... wire rope 15 ... rubber sheet 16 ... flat steel 17 ... screw 18 ... pump 19 ... stabilizer

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 地中に間隔をおいて溝を掘削し、コンク
リートを打設して先行エレメントを施工し、該先行エレ
メント間の地盤を掘削し、ここにコンクリートを打設し
て後行エレメントを施工し、先行エレメントと後行エレ
メントとをそれぞれの端部の継手面で連続させる地中連
続壁の継手の施工法において、継手面に配設する接合鋼
板の外側に膨縮自在な袋体を取り付け、先行エレメント
のコンクリート打設時に前記袋体を膨らませ、コンクリ
ート打設時の側圧を該袋体を介して掘削溝の地山側で負
担し、コンクリート硬化後、袋体を収縮して掘削溝内か
ら撤去することを特徴とする地中連続壁の継手の施工
法。
1. Drilling a groove at an interval in the ground, casting concrete to construct a leading element, excavating the ground between the preceding elements, placing concrete in the ground, and setting a subsequent element. In the method of constructing a joint of an underground continuous wall in which the preceding element and the succeeding element are connected to each other at the joint surface at each end, a bag body which can be expanded and contracted outside the joint steel plate disposed on the joint surface At the time of placing concrete in the preceding element, the bag body is inflated at the time of concrete placement, and the side pressure at the time of concrete placement is borne by the ground side of the excavation groove through the bag body. Construction method of joint of underground diaphragm wall characterized by removing from inside.
【請求項2】 袋体の膨張は、掘削溝内に注入する安定
液または泥水を袋体内に移送することにより行う請求項
1記載の地中連続壁の継手の施工法。
2. The method according to claim 1, wherein the expansion of the bag body is performed by transferring a stabilizing liquid or muddy water injected into the excavation trench into the bag body.
【請求項3】 袋体の収縮、撤去は、内部の液体を排出
し、袋体に取り付けた金物を介してワイヤーロープなど
の吊り部材で吊り上げて行う請求項1または請求項2に
記載の地中連続壁の継手の施工法。
3. The ground according to claim 1 or 2, wherein the bag is contracted or removed by discharging the liquid therein and lifting the bag with a suspending member such as a wire rope through metal fittings attached to the bag. Construction method of the joint of the middle continuous wall.
JP7883198A 1998-03-26 1998-03-26 Execution method of joint for underground continuous wall Pending JPH11269870A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7883198A JPH11269870A (en) 1998-03-26 1998-03-26 Execution method of joint for underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7883198A JPH11269870A (en) 1998-03-26 1998-03-26 Execution method of joint for underground continuous wall

Publications (1)

Publication Number Publication Date
JPH11269870A true JPH11269870A (en) 1999-10-05

Family

ID=13672788

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7883198A Pending JPH11269870A (en) 1998-03-26 1998-03-26 Execution method of joint for underground continuous wall

Country Status (1)

Country Link
JP (1) JPH11269870A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858090A (en) * 2010-06-23 2010-10-13 天津深基工程有限公司 Construction method for soft connection of diaphram wall rigid joints
CN103015462A (en) * 2013-01-20 2013-04-03 张永忠 Cloth bag stone piecing device
CN111254916A (en) * 2020-01-20 2020-06-09 中国十七冶集团有限公司 Construction method for filling primary groove section joint of underground diaphragm wall
CN117266211A (en) * 2023-11-17 2023-12-22 中交第一航务工程局有限公司 Underground diaphragm wall circular lock catch embedded part isolation protection structure and process

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858090A (en) * 2010-06-23 2010-10-13 天津深基工程有限公司 Construction method for soft connection of diaphram wall rigid joints
CN103015462A (en) * 2013-01-20 2013-04-03 张永忠 Cloth bag stone piecing device
CN111254916A (en) * 2020-01-20 2020-06-09 中国十七冶集团有限公司 Construction method for filling primary groove section joint of underground diaphragm wall
CN117266211A (en) * 2023-11-17 2023-12-22 中交第一航务工程局有限公司 Underground diaphragm wall circular lock catch embedded part isolation protection structure and process
CN117266211B (en) * 2023-11-17 2024-02-06 中交第一航务工程局有限公司 Installation process of isolation protection structure of circular locking embedded part of underground diaphragm wall

Similar Documents

Publication Publication Date Title
JP6252842B2 (en) Construction method of outer shield tunnel
KR20060125129A (en) Design and construction method of a twin tunnel by pre-excavation of the tunnel's main section and double support of central part and method how to optimize reinforcement level of a tunnel by changing result of stresses and strains of the main structures of the tunnel
KR101078080B1 (en) Earth retaining wall and it's construction method using the precast pile and ground reinforcement
JP3893056B2 (en) Construction method of underground structure
JPH11269870A (en) Execution method of joint for underground continuous wall
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
KR20140082343A (en) Method for constructing tunnel by using pipe
KR100717849B1 (en) Construction method of 2-arch tunnel
JP2784317B2 (en) Open caisson structure
JP2697762B2 (en) Tunnel structure and construction method
JP4146250B2 (en) Open caisson bottom plate construction method
JP3168197B2 (en) Caisson anchor structure and construction method
JP2745083B2 (en) Tunnel construction method
CN211734897U (en) Support structure attached to mountain cliff for supporting tunnel
JPH0813494A (en) Fixing method of earth retaining wall and timbering
KR102118636B1 (en) Method for construction for underground tunnel
CN110318372B (en) Anchor rod butt joint method
JP2693028B2 (en) Construction method of human hole in middle of pipeline
JP2935634B2 (en) Steel pipe sheet pile wall construction method
JP4319122B2 (en) Branch and junction structure of branching tunnel and its construction method
JPH08177044A (en) Constructing method of cast-in-place concrete pile and form device for molding pile head used for constructing method
KR100623005B1 (en) Underground outer wall construction method using temporary retaining wall
JPH0340169B2 (en)
JP3904294B2 (en) Underground excavation method and underground structure construction method using this method
JP2000328572A (en) Temporary earth retaining timbering method in underground continuous wall