KR100623005B1 - Underground outer wall construction method using temporary retaining wall - Google Patents

Underground outer wall construction method using temporary retaining wall Download PDF

Info

Publication number
KR100623005B1
KR100623005B1 KR1020030090003A KR20030090003A KR100623005B1 KR 100623005 B1 KR100623005 B1 KR 100623005B1 KR 1020030090003 A KR1020030090003 A KR 1020030090003A KR 20030090003 A KR20030090003 A KR 20030090003A KR 100623005 B1 KR100623005 B1 KR 100623005B1
Authority
KR
South Korea
Prior art keywords
pile
retaining wall
concrete
wall
temporary
Prior art date
Application number
KR1020030090003A
Other languages
Korean (ko)
Other versions
KR20050057811A (en
Inventor
우종열
Original Assignee
우종열
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 우종열 filed Critical 우종열
Priority to KR1020030090003A priority Critical patent/KR100623005B1/en
Publication of KR20050057811A publication Critical patent/KR20050057811A/en
Application granted granted Critical
Publication of KR100623005B1 publication Critical patent/KR100623005B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 에이치파일을 박고 토류판을 설치하여 형성되는 흙막이 벽, 에이치파일을 박고 소일 시멘트 월을 설치하여 형성되는 흙막이 벽, 에이치파일로 보강한 현장 타설 콘크리트말뚝을 설치하여 형성되는 흙막이 벽, 보강철근을 넣은 현장 타설 콘크리트말뚝을 설치하여 형성되는 흙막이 벽 또는 시트파일로 된 가설 시트파일을 설치하여 형성된 흙막이 벽을 갖는 가설 흙막이 구조물을 이용한 지하옹벽 시공방법을 제공한다. 이 시공방법은 흙막이 벽의 내측에서 터파기를 실시하고 이후 형성되어질 콘크리트 옹벽과의 일체화를 통한 내력 보강을 위해 에이치파일, 보강철근 또는 시트파일에 버팀기둥을 수직으로 부착시켜서 설치한 뒤 콘크리트를 타설하여 버팀기둥과 일체화되도록 콘크리트 옹벽을 시공한다. 이때 버팀기둥은 에이치파일, 보강철근 또는 시트파일에 부착되어 콘크리트 옹벽의 두께방향으로 연장되는 버팀기둥 수직대와 콘크리트 옹벽의 길이방향으로 길이를 갖도록 버팀기둥 가로대의 끝단에 부착되는 버팀기둥 수평대를 구비한다. The present invention is a mud wall formed by putting a pile of H pile and earth plate, a mud wall formed by putting a pile of H pile and soil cement wall, a mud wall formed by installing a site-pouring concrete pile reinforced with H pile, reinforcing bars It provides an underground retaining wall construction method using a temporary wall structure having a wall of mud walls formed by installing a temporary wall pile or a sheet pile of a pile pile formed by installing a cast-in-place concrete pile. This construction method is to excavate the inside of the retaining wall and install the supporting pillar vertically on the H-pile, reinforcing reinforcement or seat pile to reinforce the strength through the integration with the concrete retaining wall to be formed later. Construct the concrete retaining wall to be integrated with the support column. At this time, the brace is attached to the H pile, reinforcing bars or sheet piles and the brace column vertically extending in the thickness direction of the concrete retaining wall and the brace column horizontally attached to the end of the brace column horizontally so as to have a length in the longitudinal direction of the concrete retaining wall. Equipped.

Description

가설 흙막이 구조물을 이용한 지하옹벽 시공방법{UNDERGROUND OUTER WALL CONSTRUCTION METHOD USING TEMPORARY RETAINING WALL}Underground retaining wall construction method using temporary earthquake structure {UNDERGROUND OUTER WALL CONSTRUCTION METHOD USING TEMPORARY RETAINING WALL}

도 1은 본 발명의 시공방법을 설명하기 위한 플로우챠트;1 is a flow chart for explaining the construction method of the present invention;

도 2 및 도 3은 본 발명의 가장 기본적인 구성을 설명하기 위한 도면들;2 and 3 are views for explaining the most basic configuration of the present invention;

도 4 및 도 5는 데크 플레이트를 사용하여 콘크리트 옹벽을 형성하는 방법을 설명하기 위한 도면들;4 and 5 are views for explaining a method of forming a concrete retaining wall using a deck plate;

도 6은 본 발명의 시공방법에서 에이치파일을 건물 기초파일로만 적용하는 경우를 설명하기 위한 플로우챠트;6 is a flowchart for explaining a case in which the H file is applied only to the building foundation file in the construction method of the present invention;

도 7 및 도 8은 본 발명의 시공방법에서 에이치파일을 건물 기초파일로만 적용하는 경우 에이치파일에 전단키를 설치하는 방법을 설명하기 위한 도면들;7 and 8 are views for explaining a method for installing a shear key in the H file in the case of applying the H-file as a building foundation file in the construction method of the present invention;

도 9는 버팀기둥을 콘크리트에 묻히도록 시공하는 방법을 설명하기 위한 도면;9 is a view for explaining a method for constructing the support column to be buried in concrete;

도 10은 도 9와 같이 버팀기둥이 콘크리트에 묻히는 경우 데크 플레이트를 설치하는 방법을 설명하기 위한 도면;FIG. 10 is a view for explaining a method of installing a deck plate when the support pillar is buried in concrete as shown in FIG. 9; FIG.

도 11은 철근 콘크리트 보강용 전단키를 설명하기 위한 도면;11 is a view for explaining a shear key for reinforced concrete reinforcement;

도 12는 도 11의 철근 콘크리트 보강용 전단키를 지하옹벽의 시공에 적용한 예를 설명하기 위한 도면;FIG. 12 is a view for explaining an example in which the shear key for reinforcing concrete reinforcement of FIG. 11 is applied to the construction of an underground retaining wall; FIG.

도 13 및 도 14는 본 발명의 바람직한 실시예에 따른 지하옹벽의 시공방법을 설명하기 위한 도면들이다. 13 and 14 are views for explaining the construction method of the basement retaining wall according to a preferred embodiment of the present invention.

* 도면의 주요 부분에 대한 부호의 설명 * Explanation of symbols on the main parts of the drawings

10 : 에이치파일 20 : 버팀기둥10: H pile 20: Brace column

22 : 버팀기둥 수직대 24 : 버팀기둥 수평대22: support column vertical 24: support column horizontal

26 : 보조 수직대 30 : 데크 플레이트26: auxiliary vertical stand 30: deck plate

40 : 전단키 50 : 콘크리트 옹벽40: shear key 50: concrete retaining wall

70 : 철근 콘크리트 보강용 전단키 72 : 제 1 평강70: shear key for reinforcing concrete 72: first flat steel

74 : 위치 고정판 76 : 제 2 평강74: position fixing plate 76: second flat steel

78 : 봉강 80 : 옹벽 보강용 철근78: bar 80: retaining wall reinforcement

90 : 버팀기둥 보강용 철근 90: reinforcing bar reinforcement

본 발명은 가설 흙막이 구조물을 이용한 지하옹벽 시공방법에 관한 것으로, 좀 더 구체적으로는 터파기를 위하여 토압 등 외력을 지탱할 목적으로 시공되는 가시설인 흙막이 판을 건축의 지하옹벽 및 파일기초로 활용하도록 하는 가설 흙막이 구조물을 이용한 지하옹벽 시공방법에 관한 것이다. The present invention relates to a method for constructing an underground retaining wall using a temporary retaining structure, and more specifically, a hypothesis for utilizing a retaining plate, which is a temporary facility constructed for the purpose of supporting external forces such as earth pressure, for the excavation as a retaining wall and a pile foundation of a building. The present invention relates to a method for constructing an underground retaining wall using an earth block structure.

성토, 절토, 굴착 등을 실시하게 되면 통상 비탈면을 두어 지반의 안정을 유지시켜 주고 있지만, 토지의 보다 효과적인 이용도를 확보하거나 도시내의 구조물 의 기초 및 건물의 지하실을 시공하기 위한 굴착시에는 비탈면을 두지 못하고 통상 연직굴착을 실시하게 된다. 따라서 이로 인한 지반의 붕괴를 방지시켜 주기 위하여 이 연직면 위치에 여러 가지 종류의 흙막이 구조물을 설치하게 된다. When the soil is cut, cut, excavated, etc., slopes are usually provided to maintain the stability of the ground. However, slopes are used when excavating to secure more effective use of land or to construct the foundations and basements of structures in cities. Normally, vertical excavation is performed. Therefore, in order to prevent the collapse of the ground caused by this, various kinds of earthquake structures are installed at this vertical surface location.

한편 대한민국 특허등록 제0313720호 "가설 흙막이 벽용 철골 버팀대를 영구 구조물의 일부로 사용하는 건축물의 지하 구조물 구축방법"은 건축물의 지하 구조물용 터파기를 위하여 임시로 설치되는 가설 버팀대를 영구시설물의 일부로 활용하도록 함으로써 가설 버팀대의 설치와 해체작업을 줄일 수 있도록 하여 공사기간의 단축, 자원의 절약, 공사비를 절감할 수 있도록 제안하고 있다. Meanwhile, Republic of Korea Patent Registration No. 0313720 "Method for constructing underground structures of buildings using temporary steel wall braces as part of permanent structures" is to use temporary supports, which are temporarily installed for digs for underground structures, as part of permanent facilities. It is proposed to shorten construction period, save resources, and reduce construction cost by reducing installation and dismantling work of temporary braces.

본 발명은 이와 같은 맥락에서 가설 흙막이 구조물을 더욱 효과적으로 사용하여 영구시설물로 적용할 수 있도록 하는 새로운 형태의 가설 흙막이 구조물을 이용한 지하옹벽 시공방법을 제공하는 것을 목적으로 한다. 특히 본 발명은 콘크리트 옹벽의 시공을 용이하게 할 수 있는 새로운 형태의 가설 흙막이 구조물을 이용한 지하옹벽 시공방법을 제공하는데 있다. In this context, an object of the present invention is to provide a method for constructing a base retaining wall using a new type of temporary earthquake structure that can be used as a permanent facility by using the temporary earthquake structure more effectively. In particular, the present invention is to provide a method for constructing a base retaining wall using a new type of temporary retaining structure that can facilitate the construction of a concrete retaining wall.

또한 본 발명은 가설 흙막이 구조물을 지반여건과 건축물의 구조에 따라 적절하게 적용할 수 있는 새로운 형태의 가설 흙막이 구조물을 이용한 지하옹벽 시공방법을 제공하는데 있다. In addition, the present invention is to provide a construction method for underground retaining wall using a new type of temporary earthquake structure that can be applied to the temporary earthquake structure according to the ground conditions and the structure of the building.

상술한 목적을 달성하기 위한 본 발명의 특징에 의하면, 본 발명은 에이치파일을 박고 토류판을 설치하여 형성되는 흙막이 벽, 에이치파일을 박고 소일 시멘트 월을 설치하여 형성되는 흙막이 벽, 에이치파일로 보강한 현장 타설 콘크리트말뚝을 설치하여 형성되는 흙막이 벽, 보강철근을 넣은 현장 타설 콘크리트말뚝을 설치하여 형성되는 흙막이 벽 또는 시트파일로 된 가설 시트파일을 설치하여 형성된 흙막이 벽을 갖는 가설 흙막이 구조물을 이용한 지하옹벽 시공방법에 있어서, 상기 흙막이 벽의 내측에서 터파기를 실시하는 단계와; 이후 형성되어질 콘크리트 옹벽과의 일체화를 통한 내력 보강을 위해 상기 에이치파일, 보강철근 또는 시트파일에 버팀기둥을 수직으로 부착시켜서 설치하는 단계 및; 콘크리트를 타설하여 상기 버팀기둥과 일체화되도록 콘크리트 옹벽을 시공하는 단계를 포함하되; 상기 버팀기둥은 상기 에이치파일, 보강철근 또는 시트파일에 부착되어 상기 콘크리트 옹벽의 두께방향으로 연장되는 버팀기둥 수직대 및; 상기 콘크리트 옹벽의 길이방향으로 소정의 길이를 갖도록 상기 버팀기둥 가로대의 끝단에 부착되는 버팀기둥 수평대를 구비한다. According to a feature of the present invention for achieving the above object, the present invention is a mud wall formed by putting a pile of H pile and earth plate, a mud wall formed by installing a soil cement wall and a pile of H pile, reinforced with H pile Underground retaining wall using a temporary earthquake wall structure with an earthwork wall formed by installing a site-cast concrete pile, a soil wall formed by installing a site-cast concrete pile, or a temporary pile file made of a sheet pile A construction method comprising the steps of: carrying out a trench at an inner side of the earthen wall; A step of vertically attaching the support pillar to the H-pile, reinforcing bar or sheet pile to reinforce the strength through integration with the concrete retaining wall to be formed; Pouring concrete to construct a concrete retaining wall to be integrated with the support column; The bracing column is attached to the H-pile, reinforcing bars or sheet piles, and a plinth vertical stand extending in the thickness direction of the concrete retaining wall; And a support column horizontally attached to an end of the support column horizontally so as to have a predetermined length in the longitudinal direction of the concrete retaining wall.

이와 같은 본 발명에서 상기 콘크리트 옹벽을 시공하는 단계는 상기 버팀기둥 수평대에 의해 지지되도록 데크 플레이트를 설치하여 상기 콘크리트 옹벽의 내측벽을 형성할 수 있다. In the construction of the concrete retaining wall as described above, the deck plate may be installed to be supported by the support column horizontally to form an inner wall of the concrete retaining wall.

이와 같은 본 발명에서 상기 콘크리트 옹벽을 시공하는 단계는 상기 버팀기둥 수직대와 수평대가 콘크리트에 함몰되어 상기 버팀기둥 수평대가 외부로 노출되지 않도록 할 수 있다. 이때 상기 버팀기둥을 설치하는 단계는 상기 버팀기둥 수평대에 수직으로 부착되는 보조 수직대를 설치하는 단계를 더 포함하고, 상기 콘크리트 옹벽을 시공하는 단계는 상기 보조 수직대에 의해 지지되도록 데크 플레이트 를 설치하여 상기 콘크리트 옹벽의 내측벽을 형성할 수 있다. In the present invention, the step of constructing the concrete retaining wall may be such that the support column vertical bar and the horizontal bar is recessed in concrete so that the support column horizontal bar is not exposed to the outside. At this time, the step of installing the support column further comprises the step of installing an auxiliary vertical stand that is vertically attached to the horizontal support column, the step of constructing the concrete retaining wall is a deck plate to be supported by the auxiliary vertical stand It can be installed to form the inner wall of the concrete retaining wall.

이와 같은 본 발명의 청구범위 제 1 항 내지 제 4 항 중 어느 한 항에 따른 가설 흙막이 구조물을 이용한 지하옹벽 시공방법에서 상기 버팀기둥을 설치하는 단계는 상기 에이치파일, 보강철근 또는 시트파일 사이의 상부를 소정 깊이로 제거한 후 상기 에이치파일, 보강철근 또는 시트파일 사이에 철근 콘크리트 보강용 전단키를 설치하는 단계를 더 포함하고, 상기 콘크리트 옹벽을 시공하는 단계는 상기 철근 콘크리트 보강용 전단키와 상기 버팀기둥 및 콘크리트 옹벽이 일체화되도록 시공할 수 있다. 이때 상기 철근 콘크리트 보강용 전단키는 일정한 거리로 이격되어 수평하게 배치되고 위치 고정판에 의해 간격이 고정되는 한쌍의 제 1 평강과; 상기 제 1 평강으로부터 일정한 거리로 이격되고 상기 제 1 평강과 대응되도록 위치 고정판에 의해 간격이 고정되어 배치되는 한쌍의 제 2 평강 및; 상기 제 1 평강과 제 2 평강의 각 대응되는 상하의 평강에 각 끝단이 고정결합되는 봉강을 구비할 수 있다. The step of installing the support column in the underground retaining wall construction method using the temporary earthquake structure according to any one of claims 1 to 4 of the present invention is the upper portion between the H pile, reinforcing bars or sheet pile After the removal to a predetermined depth, and further comprising the step of installing a shear key for reinforced concrete reinforcement between the H-pile, reinforcing bars or sheet piles, and the step of constructing the concrete retaining wall is the shear key and the support column for the reinforced concrete reinforcement and It can be constructed to integrate the concrete retaining wall. At this time, the reinforced concrete reinforcement shear key is a pair of the first flat steel spaced apart by a predetermined distance and arranged horizontally by a fixed position plate; A pair of second flat steels spaced at a predetermined distance from the first flat steel and fixedly spaced by a positioning plate to correspond to the first flat steel; Each end is fixed to the upper and lower flat steel corresponding to each of the first flat steel and the second flat steel may be provided with a bar.

삭제delete

삭제delete

도 1은 본 발명의 시공방법을 설명하기 위한 플로우챠트이고, 도 2 및 도 3은 본 발명의 가장 기본적인 구성을 설명하기 위한 도면들이며, 도 4 및 도 5는 데크 플레이트를 사용하여 콘크리트 옹벽을 형성하는 방법을 설명하기 위한 도면들다. 1 is a flow chart for explaining the construction method of the present invention, Figures 2 and 3 are views for explaining the most basic configuration of the present invention, Figures 4 and 5 to form a concrete retaining wall using a deck plate Figures for explaining how to do.

도 1을 참조하면, 본 발명에 따른 가설 흙막이 구조물을 이용한 지하옹벽 시공방법은 건축물이 들어설 영역의 둘레를 따라 에이치파일, 보강철근 또는 시트파일을 사용한 흙막이 벽을 시공(S100)하고, 건축물의 지하구조물을 시공하기 위해 흙막이 벽의 내측 영역을 굴착하여 터파기(S110)를 한다. 그리고 터파기가 완료되거나 터파기 단계별로 에이치파일(H-pile), 보강철근 또는 시트파일(Sheet-pile)에 도 2 및 3에서 보는 바와 같은 버팀기둥 수직대(22)와 수평대(24)로 이루어지는 버팀기둥(20)을 용접 등의 방법으로 결합(S120)시킨다. 그리고 콘크리트를 타설하여 버팀기둥(20)과 일체화되도록 콘크리트 옹벽(50)을 시공(S150)한다. Referring to Figure 1, the base retaining wall construction method using the temporary earthquake structure according to the present invention (S100) to construct the earth wall using the H pile, reinforcement or sheet pile along the circumference of the building construction area, the basement of the building In order to construct the structure by excavating the inner region of the earthen wall is a trench (S110). Then, when the trench is completed or the trench stage is stepped into H-pile, reinforcing bars or sheet piles, as shown in FIGS. 2 and 3, the support column vertical pole 22 and the horizontal pole 24 are shown. Coupling column 20 made by coupling such as welding (S120). And the concrete is poured into the concrete retaining wall 50 to be integrated with the support pillar (20) (S150).

여기서 흙막이 벽의 시공(S100)은 이 분야에서 적용되거나 알려져 있는 일반적인 다양한 방법에 의해서 이루어질 수 있다. 예컨대, 본 발명에 따른 시공방법은 에이치파일을 박고 토류판을 설치하여 형성되는 흙막이 벽, 에이치파일을 박고 소일 시멘트 월(Soil cement wall)을 설치하여 형성되는 흙막이 벽, 에이치파일로 보강한 현장 타설 콘크리트말뚝을 설치하여 형성되는 흙막이 벽, 보강철근을 넣은 현장 타설 콘크리트말뚝을 설치하여 형성되는 흙막이 벽 및 시트파일로 된 가설 시트파일을 설치하여 형성된 흙막이 벽 등 건축물의 지하구조물을 설치하기 위해 가설되는 어떤 형태의 흙막이 벽에도 적용할 수 있는 것이다. 이하, 각 흙막이 벽의 파일을 에이치파일(10)로 설명한다. 그리고 터파기(S110)는 일반적으로 여러 차례의 굴착을 통해서 이루어지는데, 버팀기둥(20)은 각 굴착 단계별로 별도로 에이치파일(10)에 결합시키면서 진행할 수도 있고 터파기를 완료한 후 일괄해서 에이치파일(10)에 부착시켜서 설치할 수 있을 것이다. Here, the construction of the earth wall (S100) may be made by a variety of general methods applied or known in the art. For example, the construction method according to the present invention is a soil wall, which is formed by putting a pile of H pile and a soil plate, a soil wall, which is formed by installing a soil cement wall, and installing a soil cement wall (Hoil cement wall), reinforced by site pile concrete Any wall that is installed to install underground structures, such as a wall of mud walls formed by installing piles, a wall of mud walls formed by installing concrete piles, and a wall of mud walls formed by installing pile sheets. It can also be applied to the wall of the shape of the earth. Hereinafter, the file of each retaining wall is demonstrated by H pile 10. As shown in FIG. And the trench (S110) is generally made through a plurality of excavation, but the support pillar 20 may proceed by combining to the H pile 10 separately for each excavation step, or after completing the excavation collectively H pile ( 10) can be attached to the installation.

또한 도 2 및 도 3에서 보인 바와 같이 버팀기둥(20)은 버팀기둥 수직대(22)와 수평대(24)로 이루어져 흙막이 벽의 에이치파일(10)에 수직으로 부착된다. 이 때 버팀기둥 수직대(22)는 용접 등에 의한 방법으로 에이치파일(10)에 직접 부착되는 부분으로 콘크리트 옹벽(50)의 두께방향으로 연장되고, 버팀기둥 수평대(24)는 버팀기둥 수직대(22)의 끝단에 부착되는 것으로 콘크리트 옹벽(50)의 길이방향으로 일정한 길이를 갖는다. 한편 본 발명의 바람직한 실시예에서 버팀기둥(20)은 'ㅓ'형(도 2의 도시 상태에서 보는 형상)을 갖도록 도시하였지만, 이는 본 발명의 버팀기둥의 형상을 보이기 위한 것이고, 실제 버팀기둥 수직대(22)는 'ㄷ' 등 이형 단면을 갖는 판재, 형재 및 봉재 등을 적용할 수 있다. In addition, as shown in Figures 2 and 3, the brace 20 is composed of the brace vertical pole 22 and the horizontal pole 24 is attached to the H pile 10 of the earth wall vertically. At this time, the support column 22 is a part directly attached to the H pile 10 by welding or the like and extends in the thickness direction of the concrete retaining wall 50, and the support column 24 is the support column vertical stand. Attached to the end of the (22) has a constant length in the longitudinal direction of the concrete retaining wall (50). Meanwhile, in the preferred embodiment of the present invention, the support column 20 is shown to have a 'ㅓ' type (shape seen in the state shown in Figure 2), which is intended to show the shape of the support column of the present invention, the actual support vertical The base 22 may be applied to a plate member, a mold member and a bar member having a deformed cross section such as 'c'.

한편 도 4 및 도 5에서 보는 바와 같이 본 발명의 시공방법은 데크 플레이트(30)를 버팀기둥 수평대(24)에 의해 지지되도록 설치하여 콘크리트 옹벽(50)의 내측벽을 형성한다. 본 발명에 적용되는 데크 플레이트(30, deck plate)는 합성 데크 플레이트를 적용하여 콘크리트와 일체로 되어 건축물 구조체를 이루도록 한다. 이와 같이 버팀기둥(20)과 데크 플레이트(30)를 적용한 지하옹벽은 안정적으로 수평하중과 토압하중을 지지하게 된다. 그리고 도 11에서 보는 바와 같은 철근 콘크리트 보강용 전단키(70)를 도 12에서 보는 바와 같이 설치하여 가설 흙막이 벽과 콘크리트 옹벽(50)을 일체화시킬 수 있다. 이와 같은 철근 콘크리트 보강용 전단키(70)는 에이치파일(10) 사이의 파일(가설 흙막이벽 구조물)과 콘크리트 옹벽(50)을 일체화시켜서 지하옹벽에 가해지는 하중이 분산되도록 한다.
한편 철근 콘크리트 보강용 전단키(70)는 후술하는 본 발명의 바람직한 실시예의 전단키(40)와 약간의 차이점이 있는 것이다. 즉 철근 콘크리트 보강용 전단키(70)는, 도 12에서 보는 바와 같이, 에이치파일(10)과 콘크리트 옹벽(50)을 가로질러 위치되도록 설치되어 지하옹벽의 시공시 가설 구조물과 콘크리트 옹벽(50)의 일체화가 효과적으로 이루어지도록 하는 반면, 전단키(40)는 도 8에서 보는 바와 같이 에이치파일(10)의 사이를 수평으로 연결하여 콘크리트 옹벽(50)내에 설치되므로써 에이키파일(10)이 콘크리트 옹벽(50)과 함께 수직하중을 지지하도록 한다. 따라서 이와 같은 전단키(40)와 철근 콘크리트 보강용 전단키(70)는 후술하는 본 발명의 바람직한 실시예와 같이 각각 별개로 사용될 수 있고, 서로 엇갈리는 위치에 동시에 사용될 수도 있는 것이다.
Meanwhile, as shown in FIGS. 4 and 5, the construction method of the present invention installs the deck plate 30 to be supported by the support column horizontal bar 24 to form the inner wall of the concrete retaining wall 50. Deck plate (30, deck plate) applied to the present invention is applied to the composite deck plate to be integrated with the concrete to form a building structure. As such, the basement retaining wall to which the support column 20 and the deck plate 30 are applied stably supports the horizontal load and the earth pressure load. In addition, the shear key 70 for reinforcing concrete reinforcement as shown in FIG. 11 may be installed as shown in FIG. 12 to integrate the temporary retaining wall and the concrete retaining wall 50. The shear key 70 for reinforcing concrete reinforces the pile (temporary wall structure) and the concrete retaining wall 50 between the H pile 10 so that the load applied to the underground retaining wall is distributed.
Meanwhile, the shear key 70 for reinforced concrete is slightly different from the shear key 40 of the preferred embodiment of the present invention described later. That is, the shear key 70 for reinforcing concrete reinforcement is installed to be positioned across the H pile 10 and the concrete retaining wall 50, as shown in FIG. 12, so that the construction of the temporary retaining structure and the concrete retaining wall 50 when the underground retaining wall is installed. While the integration is effectively achieved, the shear key 40 is horizontally connected between the H pile 10 as shown in Figure 8 is installed in the concrete retaining wall 50, the achi pile 10 is a concrete retaining wall 50 ) To support vertical loads. Therefore, the shear key 40 and the shear key 70 for reinforcing concrete reinforcement may be used separately as in the preferred embodiment of the present invention to be described later, and may be used simultaneously at mutually staggered positions.

도 6은 본 발명의 시공방법에서 에이치파일을 건물 기초파일로만 적용하는 경우를 설명하기 위한 플로우챠트이고, 도 7 및 도 8은 본 발명의 시공방법에서 에이치파일을 건물 기초파일로만 적용하는 경우 에이치파일에 전단키를 설치하는 방 법을 설명하기 위한 도면들이다. FIG. 6 is a flowchart illustrating a case in which the H file is applied only to the building foundation file in the construction method of the present invention, and FIGS. 7 and 8 illustrate a case in which the H file is applied only to the building foundation file in the construction method of the present invention. Figures for explaining how to install the shear key on the file.

도 6 내지 도 8을 참조하면, 전술한 바와 같이 본 발명의 기술적 특징은 버팀기둥(20)과 데크 플레이트(30)를 설치하여 가설 흙막이 벽과 콘크리트 옹벽이 건축물에 작용하는 수평하중과 토압하중을 일체로 지지하도록 시공하는 방법에 있는데, 본 발명의 또 다른 기술적 특징은 전술한 특징과 동시에 또는 별개로 가설 흙막이 벽의 에이치파일(10)을 건축물의 파일기초로만 적용하여 콘크리트 옹벽과 함께 수직하중을 지지하도록 하는 것이다. 이를 위해 에이치파일(10)에는 도 7 및 도 8에서 보는 바와 같은 전단키(40)가 결합된다. 이 전단키(40)는 에이치파일(10)의 사이를 연결하도록 수평으로 에이치파일(10)에 용접 등의 방법으로 결합시킨다. 그리고 이 전단키(40)는 건축물의 설계에 적합한 수로 설치하고, 콘크리트를 타설하여 콘크리트 옹벽(50)과 일체화되도록 시공한다. 6 to 8, as described above, the technical feature of the present invention is to install the support column 20 and the deck plate 30 to the horizontal load and earth pressure load acting on the construction of the temporary retaining wall and concrete retaining wall In the method of construction to support integrally, another technical feature of the present invention is to apply vertical load together with the concrete retaining wall by applying the pile 10 of the temporary retaining wall only as the pile foundation of the building at the same time or separately. To support it. For this purpose, the shear file 40 is coupled to the H pile 10 as shown in FIGS. 7 and 8. The shear key 40 is horizontally coupled to the H pile 10 by welding or the like to connect the H pile 10. And the shear key 40 is installed in a number suitable for the design of the building, and the concrete is installed to be integrated with the concrete retaining wall (50).

다시 도 6 내지 도 8을 참조하면, 본 발명은 가설 흙막이 판의 에이치파일(10)을 영구 구조물로 적용하는데 있어서 전술한 바와 같이 데크 플레이트(30)를 적용할 수 있고, 에이치파일(10)을 영구 구조물(건축물)의 파일기초로만 적용할 수도 있다. 따라서 본 발명에 따른 가설 흙막이 구조물을 이용한 지하옹벽 시공방법은 에이치파일, 보강철근 또는 시트파일 등을 사용하여 흙막이 벽을 시공(S100)하고 터파기(S110)를 진행한 뒤, 데크 플레이트(30, 도 4 참조)를 적용(S200)하는 경우 버팀기둥을 설치(S120)하고 동시에 파일기초로 사용고자 하는 경우(S210) 철근 콘크리트 보강용 전단키(70)를 설치(S130)하고 데크 플레이트(30)를 설치(S140)하여 콘크리트 옹벽(50)을 시공하게 된다. 그리고 데크 플레이트(30)를 설치하지 않고 에이치파일(10)을 건축물의 파일기초로만 사용하고자 하는 경우(S210) 전단키(40)를 설치(S220')하고 콘크리트 옹벽(50)을 시공{선택적으로 철근콘크리트 보강용 전단키(70)를 설치한다(S130')}하게 되며, 데크 플레이트(30)만을 설치할 경우 버팀기둥(20)을 설치한 뒤 데크 플레이트(30)를 설치(S140')하고 콘크리트 옹벽(50)을 시공하게 된다. 6 to 8, the present invention may apply the deck plate 30 as described above in applying the H pile 10 of the temporary soil plate as a permanent structure, and the H pile 10 may be applied to the H pile 10. It can also be applied only as a pile foundation for permanent structures (buildings). Therefore, the underground retaining wall construction method using the temporary retaining structure according to the present invention using the H pile, reinforcing bars or sheet piles, such as constructing the earth wall (S100) and proceeding the trench (S110), the deck plate (30, In the case of applying (S200) (S120) to install the support column (S120) and at the same time to use as a pile foundation (S210) to install the shear key 70 for reinforced concrete reinforcement (S130) and the deck plate 30 Installation (S140) is to construct the concrete retaining wall 50. And if you want to use the H-pile 10 as the foundation of the building without installing the deck plate 30 (S210) Install the shear key 40 (S220 ') and construct the concrete retaining wall 50 {selectively reinforced The concrete reinforcement shear key 70 is installed (S130 ')}, and if only the deck plate 30 is installed, the support column 20 is installed and the deck plate 30 is installed (S140') and the concrete retaining wall ( 50) will be installed.

도 1 내지 도 8을 참조하여 전술한 바와 같이 본 발명의 가설 흙막이 구조물을 이용한 지하옹벽 시공방법은 수직대와 수평대를 구비한 버팀기둥을 흙막이 벽의 에이치파일 등과 결합시키고 콘크리트를 타설하여 콘크리트 옹벽과 일체화시킴으로써 건축물의 지하옹벽을 더욱 견고히 하면서도 비교적 간단하게 시공할 수 있도록 한다. 또한 본 발명의 가설 흙막이 구조물을 이용한 지하옹벽 시공방법은 버팀기둥에 의해 지지되는 데크 플레이트를 적용하여 콘크리트 옹벽의 내측벽을 형성하므로써 종래 재래식 거푸집 공법을 대체하여 공기를 단축시킬 수 있도록 하고 시공작업을 단순화시킨다. 그리고 전단키를 적용하여 흙막이 벽의 에이치파일 등을 파일기초로 사용할 때 지반상태가 좋지 않더라도 건축물의 수직하중에 효과적으로 작용하는 지하옹벽을 시공할 수 있도록 한다. As described above with reference to FIGS. 1 to 8, the underground retaining wall construction method using the temporary retaining structure of the present invention combines a support column having a vertical stand and a horizontal stand with an H-pile of a retaining wall, and casts concrete to retain the concrete retaining wall. By integrating with the building, the underground retaining wall of the building can be more firmly constructed and relatively simple to construct. In addition, the underground retaining wall construction method using the temporary soil structure of the present invention by applying a deck plate supported by the support column to form the inner wall of the concrete retaining wall to replace the conventional conventional formwork method to shorten the air and the construction work Simplify And by using shear key, it is possible to construct underground retaining wall that works effectively on the vertical load of the building even when the soil condition is not good when the pile of H.

이와 같은 본 발명에 따른 가설 흙막이 구조물을 이용한 지하옹벽 시공방법에 의하면, 건축시공시의 파일 수량이 감소되고 옹벽두께 및 철근배근량이 감소되므로 공사비를 절감할 수 있고, 시공의 편의성이 확보되며, 인접대지 경계선에서 이루어지는 파일공사가 필요없기 때문에 민원을 최소화할 수 있다. According to the method of constructing the underground retaining wall using the temporary earthquake structure according to the present invention, the number of piles during construction and the retaining wall thickness and the reinforcement amount are reduced, thereby reducing the construction cost and ensuring the convenience of construction. Complaints can be minimized because no pile work is required at the site boundary.

이하 본 발명의 바람직한 실시예를 첨부된 도면 도 9 내지 도 14에 의거하여 상세히 설명하며, 도 1 내지 도 14에 있어서 동일한 기능을 수행하는 구성 요소에 대해서는 동일한 참조 번호를 병기한다. 한편, 각 도면에서 일반적인 토목 및 건축 시공과 관련된 구성 및 가설 구조물을 영구 구조물로 적용하는 종래 시공방법으로 용이하게 알 수 있는 구성에 대한 도시 및 상세한 설명은 간략히 하거나 생략하고 본 발명과 관련된 부분들을 중심으로 도시하였다. 특히, 요소들 사이의 크기 비가 다소 상이 하게 표현되거나 서로 결합되는 부품들 사이의 크기가 상이하게 표현된 부분도 있으나, 이와 같은 도면의 표현 차이는 이 분야의 종사자들이 용이하게 이해할 수 있는 부분들이므로 별도의 설명을 생략한다. Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to FIGS. 9 to 14, and like reference numerals denote like elements for performing the same functions in FIGS. 1 to 14. Meanwhile, the drawings and detailed descriptions of the constructions which can be easily understood by the conventional construction method in which the general construction and construction structures related to general civil engineering and construction construction as permanent structures in each drawing are briefly or omitted, and center the parts related to the present invention. As shown. In particular, there are parts in which the size ratio between the elements is somewhat different or the sizes between the components coupled to each other are different. However, the differences in representation of the drawings are easily understood by those skilled in the art. A separate description is omitted.

도 9는 버팀기둥을 콘크리트에 묻히도록 시공하는 방법을 설명하기 위한 도면이고, 도 10은 도 9와 같이 버팀기둥이 콘크리트에 묻히는 경우 데크 플레이트를 설치하는 방법을 설명하기 위한 도면이다. FIG. 9 is a view for explaining a method of constructing a support column to be buried in concrete, and FIG. 10 is a view for explaining a method for installing a deck plate when the support pillar is buried in concrete as shown in FIG. 9.

도 9에서 보는 바와 같이 전술한 바와 같이 본 발명에 따른 지하옹벽의 시공방법은 버팀기둥(20')을 콘크리트에 함몰되도록 하여 버팀기둥 수평대(24, 도 2 참조)가 외부로 노출되지 않도록 할 수 있다. 이와 같은 경우 도 10에서 보는 바와 같이 버팀기둥 수평대(24)에 보조 수직대(26)를 용접 등의 방법으로 수직으로 부착하고, 보조 수직대(26) 사이에 데크 플레이트(30)를 설치하여 데크 플레이트(30)가 보조 수직대(26)에 의해 지지되도록 하여 콘크리트 옹벽(50)의 내측벽을 형성한다. 이와 같이 버팀기둥(20')이 지하옹벽의 내측으로 돌출되지 않도록 하는 것은 철골 구조의 버팀기둥(20')이 부식되는 것을 방지하고 외부로 노출됨으로써 미관이 떨어지는 것을 방지한다. As shown in FIG. 9, the construction method of the basement retaining wall according to the present invention, as described above, allows the support pillar 20 ′ to be recessed in concrete so that the support pillar horizontal legs 24 (see FIG. 2) are not exposed to the outside. Can be. In such a case, as shown in FIG. 10, the auxiliary vertical stand 26 is vertically attached to the support column horizontal stand 24 by welding or the like, and the deck plate 30 is installed between the auxiliary vertical stand 26. The deck plate 30 is supported by the auxiliary riser 26 to form the inner wall of the concrete retaining wall 50. In this way, the support pillar 20 'does not protrude to the inside of the basement retaining wall to prevent the support pillar 20' of the steel structure from being corroded and to prevent the beauty of the fall by exposing to the outside.

도 11은 철근 콘크리트 보강용 전단키를 설명하기 위한 도면이고, 도 12는 도 11의 철근 콘크리트 보강용 전단키를 지하옹벽의 시공에 적용한 예를 설명하기 위한 도면이다. FIG. 11 is a view for explaining a shear key for reinforcing concrete reinforcement, and FIG. 12 is a view for explaining an example in which the shear key for reinforcing concrete reinforcement of FIG. 11 is applied to the construction of an underground retaining wall.

전술한 바와 같이 본 발명에 따른 지하옹벽의 시공시 가설 구조물과 콘크리트 옹벽(50)의 일체화가 효과적으로 이루어지도록 하기 위해 철근 콘크리트 보강용 전단키(70)를 설치할 수 있다. 이 철근 콘크리트 보강용 전단키(70)는 에이치파일(10) 사이의 상부를 일정한 깊이로 제거한 후 그 사이에 설치되어 콘크리트 옹벽(50)의 시공시 콘크리트 옹벽과 일체화된다. 이와 같은 철근 콘크리트 보강용 전단키(70)는 본 발명자가 2003. 11. 12.자에 실용신안등록출원(20-2003-0035350)한 "기초 구조물용 휨/전단 겸용 보강재"를 적용한 것이다. 이 철근 콘크리트 보강용 전단키(70)는 도 11과 같이 한쌍의 제 1 및 제 2 평강(72, 76)과 이들 사이를 연결하는 봉강(78)로 이루어진다. 한 쌍의 제 1 평강(72)은 일정한 거리로 이격되어 수평하게 배치되고 위치 고정판(74)에 의해 간격이 고정되고, 한쌍의 제 2 평강(76)은 제 1 평강(72)으로부터 일정한 거리로 이격되고 제 1 평강(72)과 대응되도록 위치 고정판(74)에 의해 간격이 고정되어 배치되며, 봉강(78)은 제 1 평강(72)과 제 2 평강(76)의 각 대응되는 상하의 평강에 각 끝단이 고정결합된다. As described above, the shear key 70 for reinforcing concrete reinforcement may be installed to effectively integrate the temporary structure and the concrete retaining wall 50 during the construction of the base retaining wall according to the present invention. The reinforced concrete reinforcement shear key 70 is removed between the H piles 10 to a predetermined depth and is installed therebetween so as to be integrated with the concrete retaining wall when constructing the concrete retaining wall 50. Such shear key 70 for reinforced concrete reinforcement is applied by the inventor of the utility model registration application (20-2003-0035350) on November 12, 2003, the "bending / shear combined reinforcement for foundation structures". The reinforced concrete shear key 70 is composed of a pair of first and second flat steels 72 and 76 and a bar 78 connecting therebetween as shown in FIG. 11. The pair of first flat steels 72 are horizontally spaced apart at a constant distance and spaced apart by the positioning plate 74, and the pair of second flat steels 76 are fixed at a constant distance from the first flat steel 72. Spaced apart and spaced by the positioning plate 74 so as to correspond to the first flat steel 72, the bar 78 is in the upper and lower flat steel respectively corresponding to the first flat steel 72 and the second flat steel (76) Each end is fixedly coupled.

도 13 및 도 14는 본 발명의 바람직한 실시예에 따른 지하옹벽의 시공방법을 설명하기 위한 도면들이다. 13 and 14 are views for explaining the construction method of the basement retaining wall according to a preferred embodiment of the present invention.

먼저, 본 발명에 따른 지하옹벽을 시공하기 위한 토목 및 건축물 설계는 지반의 성질을 파악하여 토압의 크기를 계산, 지하수위를 예측하여 수압을 계산, 지 반 위에 실리게 될 상재 하중 등 옹벽에 걸리는 모든 하중요소를 계산하여 건축 옹벽에 작용되는 하중의 크기를 계산하게 된다. 그리고 건축 구조물에서 발생하는 하중, 즉 건물의 구조체에 의한 고정하중, 건물에 실리는 적재하중, 풍하중, 지진하중 등 제반 하중 요소에 의해 옹벽이 부담해야 하는 하중을 계산하게 된다. 이와 같은 하중들에 대하여 가설 흙막이 벽과 지하옹벽의 합성구조가 견뎌야 할 응력을 계산하여 지하옹벽을 데크 플레이트(30)로 시공할지와 에이치파일(10)을 건축물의 파일기초로만 사용할 지를 결정하게 된다. 도 13 및 도 14는 데크 플레이트(30)로 지하옹벽을 시공하고 동시에 에이치파일(10)을 건축물의 파일기초로 사용하는 경우 지하옹벽에 설치되는 구성을 보여주는 도면들이다. First, civil engineering and building design for constructing the underground retaining wall according to the present invention is to grasp the nature of the ground to calculate the size of the earth pressure, to predict the groundwater level to calculate the water pressure, the load on the retaining wall, such as the flooring load to be loaded on the ground All load components are calculated to calculate the magnitude of the load on the retaining wall. In addition, the load generated by the building structure, that is, the fixed load by the structure of the building, the loading load on the building, the wind load, the earthquake load, and the loads that the retaining wall must bear are calculated. For these loads, the stress that the composite structure of the temporary barrier wall and the base retaining wall must withstand is calculated to determine whether the base retaining wall is to be used as the deck plate 30 and whether the H pile 10 is to be used as the foundation of the building only. . FIG. 13 and FIG. 14 are views showing the construction installed in the basement retaining wall when the base retaining wall is constructed with the deck plate 30 and the H pile 10 is used as the pile foundation of the building.

도 13 및 도 14를 참조하면, 본 발명의 바람직한 실시예에 따른 가설 흙막이 구조물을 이용한 지하옹벽 시공방법은 에이치파일(10)에 버팀기둥 수직대(22)와 수평대(24)를 갖는 버팀기둥(20)을 설치하고, 철근 콘크리트 보강용 전단키(70), 데크 플레이트(30)를 설치하여 콘크리트 옹벽(50)을 시공한다. 이와 같은 콘크리트 옹벽(50)의 시공을 위한 작업순서는 다음과 같다. 우선 지하 흙막이용 가설 구조물을 시공할 경우 건축물이 설치될 곳의 경계선에 부지정지작업 및 지중매설물 등을 확인, 차단작업 후 흙막이 벽체를 형성하기 위해 지반을 천공하고 그 구멍에 에이치파일(10)을 집어 넣고 콘트리트를 주입한다. 다음으로 1단계 굴토시공을 실시한 후 터파기를 하여 노출된 에이치파일(10) 내측 콘크리트 부분을 제거한 후 에이치파일(10)에 철근 콘크리트 보강용 전단키(70) 및 버팀기둥(20)을 용접시킨다. 그리고 2단계 굴토시공을 실시한 후 동일한 방법으로 에이치파일(10)에 버팀기둥(20)을 용접시키고 필요에 따라 철근 콘크리트 보강용 전단키(70)를 설치한다. 이와 같은 순서로 연속적으로 최하단까지 굴토를 실시하고, 버팀기둥(20)도 상기와 같이 에이치파일(10)에 용접시킨다. 굴토과정이 끝난 이후 버팀기둥(20)내측에 데크 플레이트(30)를 설치하고 기초콘크리트를 타설하여 기초를 시공하여 기초시공이 완성된 후 최하단 지하외벽과 최하층의 골조 및 최상단의 지하외벽을 시공한다. 이때 버팀기둥(20) 및 철근 콘크리트 보강용 전단키(70)는 굴토시공에 의한 터파기가 완료된 후 에이치파일(10)에 설치할 수 있고, 옹벽 보강용 철근(80) 및 버팀기둥 보강용 철근(90)을 사용하여 콘크리트 옹벽(50)을 시공할 수 있다. 13 and 14, the underground retaining wall construction method using a temporary earthquake structure according to a preferred embodiment of the present invention is a support pillar having a support column vertical pole 22 and a horizontal pole 24 in the H pile (10) 20 is installed, and the concrete retaining wall 50 is constructed by installing the shear key 70 and the deck plate 30 for reinforcing concrete reinforcement. The work order for the construction of such a concrete retaining wall 50 is as follows. First of all, when constructing a temporary structure for underground mudstone, check the site stop work and underground buried works on the boundary line where the building is to be installed, and drill the ground to form the mud wall after blocking work, and then install the H pile (10) in the hole. Put it in and inject the concrete. Next, after performing the first step gulting construction to remove the exposed concrete portion inside the H pile (10) by digging and then weld the reinforced concrete reinforcement shear key 70 and the support column (20) to the H pile (10). And after performing the two-stage gulting construction welds the support pillar 20 to the H pile 10 in the same way and installs the shear key 70 for reinforced concrete reinforcement as needed. In this order, the bottom end is continuously excavated, and the support pillar 20 is also welded to the H pile 10 as described above. After the gulting process is completed, the deck plate 30 is installed inside the bracing column 20 and the foundation concrete is laid to install the foundation. After the foundation construction is completed, the lowermost basement outer wall, the lowermost frame and the uppermost basement outer wall are constructed. . At this time, the support pillar 20 and the shear key 70 for reinforced concrete reinforcement can be installed in the H pile 10 after the excavation due to the excavation construction is completed, the retaining wall reinforcement 80 and the reinforcing column reinforcement (90) It can be used to construct a concrete retaining wall (50).

이와 같은 본 발명의 바람직한 실시예의 가설 흙막이 구조물을 이용한 지하옹벽 시공방법에 의해 시공된 지하옹벽은 전술한 본 발명의 장점외에 가시설의 철골 버팀대와 지하옹벽(50)은 철근 콘크리트 보강용 전단키(70)에 의하여 일체로 거동하므로 건물 골조를 통하여 지하옹벽(50)으로 전달되는 수직하중은 에이치파일(10)을 포함하는 가시설의 철골 버팀대에도 동시에 전달된다. 그리고 이 하중은 가시설의 철골 버팀대 시공시 형성된 콘크리트 구근을 통하여 직접 지반으로 수직력을 전달하거나 철골 버팀대가 철골 콘크리트 보강용 전단키(70)를 통하여 건물과 일체로 거동하는 상태이므로 일부 수직력은 건물 기초바닥으로 전달되어 지반으로 하중이 전달되도록 하여 기초외벽하부의 편심에 의한 응력부담을 경감하는 효과를 가지며 파일로서 작용하도록 한 가시설의 철골 버팀대의 수직력 분담효과에 의하여 별도로 설치하던 파일기능을 대체하므로서 파일 물량을 절감하는 효과를 가진다. The base retaining wall constructed by the underground retaining wall construction method using the temporary earthquake structure according to the preferred embodiment of the present invention has the advantages of the present invention, in addition to the steel support and the base retaining wall 50 of the temporary reinforcement shear key 70 for reinforced concrete reinforcement. Since the vertical load transmitted to the basement retaining wall 50 through the building frame is integrally transferred to the steel brace of the temporary facility including the H pile (10) at the same time. And this load transfers the vertical force directly to the ground through the concrete bulbs formed during the construction of the steel braces of the temporary facility, or because the steel braces behave integrally with the building through the shear key 70 for steel concrete reinforcement, some vertical force is transferred to the foundation of the building. It has the effect of reducing the stress burden caused by the eccentricity of the lower part of the foundation outer wall by transferring the load to the ground, and by replacing the pile function installed separately by the vertical force sharing effect of the steel brace of the temporary facility, which acts as a pile. It has the effect of saving.

상술한 바와 같은, 본 발명의 바람직한 실시예에 따른 가설 흙막이 구조물을 이용한 지하옹벽 시공방법을 상기한 설명 및 도면에 따라 도시하였지만, 이는 예를 들어 설명한 것에 불과하며 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 다양한 변화 및 변경이 가능하다는 것을 이 분야의 통상적인 기술자들은 잘 이해할 수 있을 것이다. As described above, although the base retaining wall construction method using the temporary earthquake structure according to a preferred embodiment of the present invention has been shown in accordance with the above description and drawings, this is only an example, and the scope does not depart from the spirit of the present invention. It will be apparent to those skilled in the art that various changes and modifications can be made therein.

본 발명에 의한 가설 흙막이 구조물을 이용한 지하옹벽 시공방법에 의하면, 건물 지하옹벽을 이루는 콘크리트 옹벽이 흙막이 벽의 에이치파일 등과 용접 등으로 결합되는 버팀기둥과 일체되어 시공되므로 옹벽의 두께를 줄일 수 있고, 철근량을 감소시킬 수 있다. 또한 데크 플레이트를 적용하여 콘크리트 옹벽의 내측면을 시공하므로 재래식 거푸집공법에 비해 콘크리트 옹벽의 시공이 단순하게 되고 공기를 단축할 수 있다. 또한 에이치파일 등의 사이를 연결하여 수평으로 결합되는 전단키를 적용함으로써 파일기초의 수량을 감소시키면서 시공의 용이성을 향상시키고 파일시공 등으로 인한 민원을 최소화할 수 있다. According to the method of constructing a basement retaining wall using a temporary retaining structure according to the present invention, since the concrete retaining wall constituting the building retaining wall is integrally constructed with the support pillar coupled to the H-pile and the welding of the retaining wall, the thickness of the retaining wall can be reduced. You can reduce the amount of rebar. In addition, since the inner surface of the concrete retaining wall is applied by applying a deck plate, the construction of the concrete retaining wall can be simplified and the air can be shortened as compared with the conventional formwork method. In addition, by applying a shear key coupled horizontally by connecting between the H-pile, etc., it is possible to reduce the number of pile foundations, improve the ease of construction and minimize complaints due to pile construction.

Claims (9)

에이치파일을 박고 토류판을 설치하여 형성되는 흙막이 벽, 에이치파일을 박고 소일 시멘트 월을 설치하여 형성되는 흙막이 벽, 에이치파일로 보강한 현장 타설 콘크리트말뚝을 설치하여 형성되는 흙막이 벽, 보강철근을 넣은 현장 타설 콘크리트말뚝을 설치하여 형성되는 흙막이 벽 또는 시트파일로 된 가설 시트파일을 설치하여 형성된 흙막이 벽을 갖는 가설 흙막이 구조물을 이용한 지하옹벽 시공방법에 있어서,Retaining wall made of H-pile and earth plate, Retaining wall formed of H-pile and soil cement wall, Reinforced site of H-pile Retaining wall made of concrete pile, Reinforcing bar In the underground retaining wall construction method using a temporary wall structure having a wall of mud wall formed by installing a concrete pile pile or a sheet pile of a pile pile, 상기 흙막이 벽의 내측에서 터파기를 실시하는 단계와;Carrying out a trench on the inside of the retaining wall; 이후 형성되어질 콘크리트 옹벽과의 일체화를 통한 내력 보강을 위해 상기 에이치파일, 보강철근 또는 시트파일에 버팀기둥을 수직으로 부착시켜서 설치하는 단계 및;A step of vertically attaching the support pillar to the H-pile, reinforcing bar or sheet pile to reinforce the strength through integration with the concrete retaining wall to be formed; 콘크리트를 타설하여 상기 버팀기둥과 일체화되도록 콘크리트 옹벽을 시공하는 단계를 포함하되;Pouring concrete to construct a concrete retaining wall to be integrated with the support column; 상기 버팀기둥은 상기 에이치파일, 보강철근 또는 시트파일에 부착되어 상기 콘크리트 옹벽의 두께방향으로 연장되는 버팀기둥 수직대 및;The bracing column is attached to the H-pile, reinforcing bars or sheet piles, and a plinth vertical stand extending in the thickness direction of the concrete retaining wall; 상기 콘크리트 옹벽의 길이방향으로 소정의 길이를 갖도록 상기 버팀기둥 수직대의 끝단에 부착되는 버팀기둥 수평대를 구비하고, It is provided with a support column horizontally attached to the end of the support column vertical to have a predetermined length in the longitudinal direction of the concrete retaining wall, 상기 콘크리트 옹벽을 시공하는 단계는 상기 버팀기둥 수평대에 의해 지지되도록 데크 플레이트를 설치하여 상기 콘크리트 옹벽의 내측벽을 형성하는 것을 특징으로 가설 흙막이 구조물을 이용한 지하옹벽 시공방법.The construction of the concrete retaining wall is an underground retaining wall construction method using a temporary soil block structure, characterized in that to form an inner wall of the concrete retaining wall by installing a deck plate to be supported by the support column horizontal. 제 1 항에 있어서, The method of claim 1, 상기 버팀기둥을 설치하는 단계는 상기 에이치파일, 보강철근 또는 시트파일 사이의 상부를 소정 깊이로 제거한 후 상기 에이치파일, 보강철근 또는 시트파일 사이에 철근 콘크리트 보강용 전단키를 설치하는 단계를 더 포함하고, The step of installing the support column further includes the step of installing a shear key for reinforcing concrete reinforcement between the H pile, reinforcing bars or sheet piles after removing the upper portion between the H pile, reinforcing bars or sheet piles to a predetermined depth; , 상기 콘크리트 옹벽을 시공하는 단계는 상기 철근 콘크리트 보강용 전단키와 상기 버팀기둥 및 콘크리트 옹벽이 일체화되도록 시공하는 것을 특징으로 하는 가설 흙막이 구조물을 이용한 지하옹벽 시공방법. The construction of the concrete retaining wall is a method for constructing a basement retaining wall using a temporary earthquake structure, characterized in that the reinforced key reinforcement shear key and the support pillar and the concrete retaining wall is constructed to be integrated. 제 2 항에 있어서, The method of claim 2, 상기 철근 콘크리트 보강용 전단키는 일정한 거리로 이격되어 수평하게 배치되고 위치 고정판에 의해 간격이 고정되는 한쌍의 제 1 평강과;The reinforced concrete reinforcing shear key is a pair of first flat steel spaced at a predetermined distance and horizontally arranged and the interval is fixed by a position fixing plate; 상기 제 1 평강으로부터 일정한 거리로 이격되고 상기 제 1 평강과 대응되도록 위치 고정판에 의해 간격이 고정되어 배치되는 한쌍의 제 2 평강 및;A pair of second flat steels spaced at a predetermined distance from the first flat steel and fixedly spaced by a positioning plate to correspond to the first flat steel; 상기 제 1 평강과 제 2 평강의 각 대응되는 상하의 평강에 각 끝단이 고정결합되는 봉강을 포함하는 것을 특징으로 하는 가설 흙막이 구조물을 이용한 지하옹벽 시공방법. The base retaining wall construction method using a temporary earthquake structure, characterized in that it comprises a bar, each end is fixedly coupled to the upper and lower flat steel corresponding to each of the first flat steel and the second flat steel. 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR1020030090003A 2003-12-11 2003-12-11 Underground outer wall construction method using temporary retaining wall KR100623005B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020030090003A KR100623005B1 (en) 2003-12-11 2003-12-11 Underground outer wall construction method using temporary retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020030090003A KR100623005B1 (en) 2003-12-11 2003-12-11 Underground outer wall construction method using temporary retaining wall

Publications (2)

Publication Number Publication Date
KR20050057811A KR20050057811A (en) 2005-06-16
KR100623005B1 true KR100623005B1 (en) 2006-09-18

Family

ID=37251524

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020030090003A KR100623005B1 (en) 2003-12-11 2003-12-11 Underground outer wall construction method using temporary retaining wall

Country Status (1)

Country Link
KR (1) KR100623005B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102091972B1 (en) * 2019-06-04 2020-03-20 전종근 H-pile for earth retaining wall and construction method of earth retaining wall using the same

Also Published As

Publication number Publication date
KR20050057811A (en) 2005-06-16

Similar Documents

Publication Publication Date Title
KR102071225B1 (en) Construction method of sheathing temporary facility using steel sheet pile
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
KR20200029079A (en) Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method
KR100831332B1 (en) Underground retaining wall for public works and method for constructing the same
KR100313720B1 (en) Composite Underground Structure Construction Method
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR20100094140A (en) Wall structure capable of earth retaining and the building method of the same
KR20200029080A (en) Construction method for earth self-retaining wall using reinforcing member and PHC pile
KR100313721B1 (en) Method for designing synthetic underground retaining wall by temporary soil protection structure and working process of underground retaining wall of structure
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
JP2000352296A (en) Method o constructing passage just under underground structure
KR100376589B1 (en) Underground construction method using permanent reinforced concrete girders as temporary struts
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
KR20100104481A (en) Underground construction method of top-down with slurry walls
KR100912574B1 (en) Retaining wall system using strut assembly and excavating method using the same
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
KR100623005B1 (en) Underground outer wall construction method using temporary retaining wall
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
KR20080059951A (en) Underground outer wall construction method using temporary retaining wall and connecting member strengthening shearing force therefor
KR100722198B1 (en) Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same
KR101257905B1 (en) Method for constructing foundation work
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120904

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20130828

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140905

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20150903

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20160905

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20170905

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20180905

Year of fee payment: 13