JPH0381421A - Shaft construction method - Google Patents
Shaft construction methodInfo
- Publication number
- JPH0381421A JPH0381421A JP21660989A JP21660989A JPH0381421A JP H0381421 A JPH0381421 A JP H0381421A JP 21660989 A JP21660989 A JP 21660989A JP 21660989 A JP21660989 A JP 21660989A JP H0381421 A JPH0381421 A JP H0381421A
- Authority
- JP
- Japan
- Prior art keywords
- shaft
- wall
- caisson
- earth retaining
- continuous earth
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 51
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 83
- 238000000034 method Methods 0.000 claims description 31
- 238000007711 solidification Methods 0.000 claims description 10
- 230000008023 solidification Effects 0.000 claims description 10
- 206010016807 Fluid retention Diseases 0.000 claims description 4
- 230000000694 effects Effects 0.000 description 7
- 238000009412 basement excavation Methods 0.000 description 6
- 239000003673 groundwater Substances 0.000 description 6
- 230000003014 reinforcing effect Effects 0.000 description 6
- 206010067482 No adverse event Diseases 0.000 description 2
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 description 2
- 238000009933 burial Methods 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 2
- 230000002950 deficient Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 201000010099 disease Diseases 0.000 description 2
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000007788 liquid Substances 0.000 description 2
- 229910052760 oxygen Inorganic materials 0.000 description 2
- 239000001301 oxygen Substances 0.000 description 2
- 239000000126 substance Substances 0.000 description 2
- 238000004804 winding Methods 0.000 description 2
- 239000004115 Sodium Silicate Substances 0.000 description 1
- 239000000654 additive Substances 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- 229910000278 bentonite Inorganic materials 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000007654 immersion Methods 0.000 description 1
- 238000011534 incubation Methods 0.000 description 1
- 239000008267 milk Substances 0.000 description 1
- 210000004080 milk Anatomy 0.000 description 1
- 235000013336 milk Nutrition 0.000 description 1
- 230000001151 other effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 description 1
- 229910052911 sodium silicate Inorganic materials 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕・
本発明は立坑構築工法の係り、特にとう道工事のための
シールド掘削機の発進箇所や到達箇所となる立坑を簡易
に構築することができるように改良した立坑構築工法に
関する。[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a shaft construction method, and in particular to a method for easily constructing a shaft that serves as a starting point and a destination point for a shield excavator for tunnel construction. Concerning a shaft construction method that has been improved to enable the construction of vertical shafts.
最近のとう道工事は、大深度、高水圧となり、一連のと
う道工事の中では立坑施工の難易度が増すと同時に施工
条件も厳しくなっている。このような条件の下で行われ
ている従来の立坑構築工法としては、連続壁と逆巻工法
によるもの、あるいはニエーマチックケーソン工法が知
られている。Recently, tunnel construction has been carried out at great depths and under high water pressure, making vertical shaft construction more difficult and stricter in terms of construction conditions. Conventional shaft construction methods used under such conditions include the continuous wall and reverse winding method, and the Niematic caisson construction method.
前者は地中に掘り進みながら側壁を構築するもので、最
初一定深さ掘削した後に、周壁に鉄筋の建込みをしてコ
ンクリートの打設・養生を行う工程を1工程とし、順次
掘り下げつつ前記工程を繰り返し施工して所望の深さの
立坑を築造するものである、また、後者の方法はケーソ
ン下部室に圧気を供給して地下水圧とバランスさせつつ
掘削し、ケーソンの水平状態を保持させながら所定深さ
まで沈埋させて設置し、ケーソンをそのまま立坑壁体と
して利用する。In the former method, the side walls are built while digging into the ground.After first excavating to a certain depth, one step is to install reinforcing bars on the surrounding wall, and then to place and cure concrete. The process is repeated to build a vertical shaft of the desired depth.The latter method involves supplying pressurized air to the lower chamber of the caisson and excavating while balancing it with the groundwater pressure to maintain the horizontal state of the caisson. The caissons will be installed by being buried to a predetermined depth, and the caisson will be used as a shaft wall.
〔発明が解決しようとする!!lIB〕ところが、上記
従来の工法では、立坑壁体を順次下方に構築する方法で
あって鉄筋の建込みも必要とされるため、工事期間が長
期化してしまう問題がある。また、後者は圧気用コンプ
レッサの設置により騒音振動が発生してしまい周辺への
環境破壊を生じてしまうおそれがあった。しかも土質に
よっては周辺地盤が沈下してしまうおそれもあった。な
お、圧気ケーソン工法において、刃口下部の地盤改良を
なして刃口の傾き防止と自沈防止を行いつつ、掘削沈設
する方法も知られている力匁正気を利用するために、作
業効率の悪化を生じる問題は改善されていない。[Invention tries to solve! ! [lIB] However, in the above-mentioned conventional construction method, the shaft walls are constructed sequentially downward, and the installation of reinforcing bars is also required, so there is a problem that the construction period becomes long. Moreover, in the latter case, the installation of a compressor for compressed air generates noise and vibration, which may cause environmental damage to the surrounding area. Moreover, depending on the soil quality, there was a risk that the surrounding ground would sink. In addition, in the pressurized air caisson construction method, while improving the ground below the cutting edge to prevent the cutting edge from tilting and preventing scuttling, the work efficiency deteriorates due to the use of force mame, which is also known as a method of excavating and sinking. The problems causing this have not been improved.
本発明は、上記従来の問題点に着目し、立坑の構築のた
めの工事期間の大幅な短縮を図ることができ、また、施
工時の振動・騒音等の発生がなく、周辺地盤への悪影響
も生じない有効な立坑構築工法を提供することを目的と
する。The present invention focuses on the above-mentioned conventional problems, and can significantly shorten the construction period for constructing a shaft, and also eliminates the generation of vibrations and noise during construction, which does not adversely affect the surrounding ground. The purpose of this project is to provide an effective method for constructing a shaft that does not cause any damage.
(L1題を解決するための手段〕
上記目的を達成するために、本発明に係る立坑構築工法
は、予め泥水固化法により立坑予定部の周囲を囲む連続
土留止水壁を形威した後に、前記連続土留止水壁の内部
にオープンケーソンを構築し、前記連続土留止水壁の内
部において前記ケーソンを沈設することにより立坑を構
築するように構成した。この場合において、前記連続土
留止水壁は立坑底部より下方に突出する根切り長さを立
坑幅長さ程度に設定するようにすれば立坑予定部内に水
の回り込みが阻止され、オープンケーソン工法をそのま
ま適用できる。また、他の発明として、予め泥水固化法
により立坑予定部の周囲を囲む連続土留止水壁を形成す
るとともに、この連続土留止水壁の底部にジェットグラ
ウト等の地盤改良方法により底盤部を形威して立坑予定
部を周囲地盤から分離し、その後に、前記連続土留止水
壁の内部にオープンケーソンを構築し、前記連続土留止
水壁の内壁面に沿って前記ケーソンを沈設することによ
り立坑を構築するように構成した。(Means for Solving Problem L1) In order to achieve the above object, the shaft construction method according to the present invention includes forming a continuous earth retaining water-stop wall surrounding the planned shaft portion in advance by a mud solidification method, and then An open caisson is constructed inside the continuous earth retaining water cutoff wall, and a vertical shaft is constructed by sinking the caisson inside the continuous earth retention water cutoff wall.In this case, the continuous earth retention water cutoff wall If the length of the root cut protruding downward from the bottom of the shaft is set to approximately the width of the shaft, water will be prevented from entering the planned shaft area, and the open caisson construction method can be applied as is. In advance, a continuous earth retaining water stop wall surrounding the planned shaft area is formed using a mud solidification method, and a bottom layer is formed at the bottom of this continuous earth retaining water stop wall using a ground improvement method such as jet grouting to form a bottom part of the planned shaft area. is separated from the surrounding ground, and then an open caisson is constructed inside the continuous earth retaining water-stopping wall, and the caisson is sunk along the inner wall surface of the continuous earth-retaining water-stopping wall to construct a shaft. Configured.
上記構成によれば、最初に立坑予定部の周壁に沿って連
続土留止水壁を泥水固化法によって形成するため、鉄筋
の建込みやコンクリート打設がなく、早期硬化するため
大幅な後期短縮作用がある。According to the above configuration, a continuous earth retaining water stop wall is first formed along the circumferential wall of the planned shaft area using the mud solidification method, so there is no need to build reinforcing bars or place concrete, and it hardens early, resulting in a significant shortening effect in the later stages. There is.
そして、連続土留止水壁の内部においてその内壁に沿っ
てオーブンケーソンを沈設するので安定した沈埋施工を
行うことができる。この場合、連続土留止水壁の内壁と
ケーソン側壁との間隔をケーソン傾斜を許容する範囲に
設定することで、沈下ガイド機能を持たせることができ
る。地盤が軟弱で高水圧である場合には、連続土留止水
壁の根切り長さをその地盤水圧や立坑断面積から水の回
り込みが発生しない程度の長さにすることにより、オー
プンケーソン工法をそのまま適用できる。また、連続土
留止水壁の下部にはジェットグラウト等の地盤改良方法
により底盤部を形威し、連続土留止水壁と相俟って周辺
地盤から立坑予定部が分離遮蔽するように構成すれば、
深い連続土留止水壁を形成するより水回りの防止効果が
得られる。Since the oven caisson is sunk along the inner wall inside the continuous earth retaining water stop wall, stable immersion construction can be performed. In this case, by setting the distance between the inner wall of the continuous earth retaining water stop wall and the caisson side wall to a range that allows the caisson inclination, a sinking guide function can be provided. If the ground is soft and the water pressure is high, the open caisson construction method can be used by making the cut length of the continuous earth retaining water stop wall long enough to prevent water from flowing around due to the ground water pressure and the cross-sectional area of the shaft. It can be applied as is. In addition, a bottom layer will be formed at the bottom of the continuous earth retaining water cutoff wall using a ground improvement method such as jet grouting, and together with the continuous earth retaining water cutoff wall, the planned shaft will be separated and shielded from the surrounding ground. Ba,
The effect of preventing water leakage can be obtained by forming a deep continuous earth retaining wall.
このため地下水の立坑予定部内への回り込みがなく、周
辺地盤の沈下等の悪影響を与えることもない、この囲ま
れた立坑予定部にはオープンケーソンが構築され、連続
土留止水壁の内壁に沿って沈設するので、安定した沈埋
が行われ、かつコンプレッサの使用もないので騒音や振
動、その他正気の送排気等に伴う周辺住民への影響もな
く、迅速に施工することができる。For this reason, groundwater will not flow into the planned shaft area, and there will be no adverse effects such as subsidence of the surrounding ground.Open caissons will be constructed in this enclosed planned shaft area, and will be installed along the inner wall of the continuous earth retaining water stop wall. Because the system is submerged, stable burying is achieved, and since there is no use of a compressor, construction can be carried out quickly without noise, vibration, or other effects on surrounding residents due to normal air supply and exhaust.
〔実施例〕
以下に、本発明に係る立坑構築工法の具体的実施例を図
面を参照して詳細に説明する。[Example] Hereinafter, a specific example of the shaft construction method according to the present invention will be described in detail with reference to the drawings.
第1図は実施例に係る立坑構築工法による施工手順を示
す断面図である。この立坑構築工法は、立坑予定部の周
囲を囲む連続土留止水壁を最初に形威し、その根切り長
さを同辺地盤における地下水圧が連続土留止水壁により
囲まれた内部に回り込まないように設定する。その後に
、この分離された立坑予定部にオーブンケーソンを連続
土留止水壁の内壁に沿わせて沈設施工することによって
立坑を構築するものである。FIG. 1 is a sectional view showing a construction procedure using a shaft construction method according to an embodiment. This shaft construction method first forms a continuous earth retaining water stop wall surrounding the planned shaft area, and the length of the root cut is such that groundwater pressure in the ground in the same area wraps around the area surrounded by the continuous earth retaining water cut wall. Set it so that there is no Thereafter, a shaft is constructed by sinking an oven caisson into the separated planned shaft portion along the inner wall of the continuous earth retaining water stop wall.
まず、立坑予定部10の周囲に連続土留止水壁12を構
築するが、これは泥水固化法により構築するようにして
いる。すなわち、立坑予定部10の領域の周囲に取り囲
むように溝14をクローラパケット等により掘削する。First, a continuous earth retaining water stop wall 12 is constructed around the planned shaft portion 10, and this is constructed by a muddy water solidification method. That is, a groove 14 is excavated using a crawler packet or the like so as to surround the area of the planned shaft portion 10 .
この溝14はパケット幅に相当する幅で溝14長さ2〜
3m程度を一つのエレメントとして掘削する。最初の千
振の後に、泥水処理設備を設置してベントナイトを主成
分とする安定液(比重1.15〜1.20)を溝14に
供給して泥水化を図りつつ、ケーソン沈埋深さより深い
位置まで掘削する。この掘削後に前記泥水をエアジュツ
トによって攪拌混合させ、泥水中にケイ酸ソーダやセメ
ント・添加剤から構成される硬化剤を注入し、硬化させ
る。このような処理を全周にわたって行い、第3I!I
に示すような連続土留止水壁12を構築するのである(
第1図(1))、この場合に必要に応じて溝14中に鉄
筋やプレキャスト板を挿入して補強処理を1テったi読
上留止水壁12とすることができる。この連続土留止水
壁12は後述するケーソンとの間隔を60〜70C1に
とり、ケーソンの傾きを一定限度で許容するとともに、
それ以上の傾斜を連続土留止水壁12によって支承する
ものとしている。This groove 14 has a width corresponding to the packet width and a length of 2~
Excavate approximately 3m as one element. After the first shake, muddy water treatment equipment is installed and a stable liquid (specific gravity 1.15 to 1.20) mainly composed of bentonite is supplied to the trench 14 to turn it into muddy water. excavate until After this excavation, the muddy water is stirred and mixed using an air jut, and a hardening agent consisting of sodium silicate, cement, and additives is injected into the muddy water and hardened. This process is performed all around the 3rd I! I
A continuous earth retaining water stop wall 12 as shown in the figure is constructed (
In this case, reinforcing bars or precast plates may be inserted into the grooves 14 as needed to form an i-reading retaining water stop wall 12 that has been reinforced. This continuous earth retaining water stop wall 12 has an interval of 60 to 70 C1 between it and the caisson, which will be described later, and allows the inclination of the caisson within a certain limit.
A slope greater than that is supported by a continuous earth retaining water stop wall 12.
また、前記連続土留止水壁12は上述したようにケーソ
ンによる立坑予定深さHより深く設定するが、特に周辺
地盤から連続土留止水壁12によって囲まれた立坑予定
部10内への水の回り込みを防止するのに必要な根切り
深さhだけ深く連続土留止水壁12を構築する。これは
周辺地盤の水圧や、立坑の断面積等を基準にして所定の
設計手順で決定すればよい。In addition, the continuous earth retaining water stop wall 12 is set deeper than the planned depth H of the shaft formed by the caisson as described above, but in particular, water from the surrounding ground into the planned shaft portion 10 surrounded by the continuous earth retaining water stop wall 12 is A continuous earth retaining water stop wall 12 is constructed deep by a root cutting depth h necessary to prevent detouring. This can be determined using a predetermined design procedure based on the water pressure of the surrounding ground, the cross-sectional area of the shaft, etc.
上記めような前処理を行った後に、立坑予定部lOにケ
ーソン20を構築する。この実施例では上記のように連
続土留止水壁12が立坑予定深さHより周辺からの水の
回り込みがない根切り深さhをもって構築されて止水壁
が構築されているのでオーブンケーソン工法を採用でき
、このためケーソン20はオーブンケーソンとしいる。After performing the above-mentioned pretreatment, a caisson 20 is constructed in the planned shaft portion lO. In this embodiment, as described above, the continuous earth retaining water cutoff wall 12 is constructed with a cutting depth h that prevents water from entering from the surrounding area than the planned depth H of the shaft, and the water cutoff wall is constructed using the oven caisson construction method. Therefore, the caisson 20 is called an oven caisson.
まず、立坑予定部10の地表に対し、最初ケーソン20
の安定沈埋のために一次掘削を行う、これはバックホー
等を用い1〜2m程度の深さを掘削し、ケーソン刃口2
2を据え付け、第一ロット躯体24、を構築する(第1
図(2))、この躯体24の構築後に刃口22の外周囲
を埋め戻す、以後は第二ロット躯体24雪を構築すると
ともに沈下掘削をなし、立坑設定深さ(第nロット蟻体
24.)まで繰り返し施工する(第1rM(3))。First, the caisson 20 is first
Primary excavation is carried out to ensure stable burial of the caisson.
2, and construct the first lot frame 24 (the first
Figure (2)), after constructing this frame 24, the outer periphery of the cutting edge 22 is backfilled, and from then on, the second lot frame 24 is covered with snow and subsidence excavation is performed to reach the shaft setting depth (nth lot ant body 24). .) (1st rM (3)).
このようにしてケーソン20の沈設が立坑予定深さHま
で終了した後は、ケーソン20の刃口22部分の床面に
コンクリートを打設して床盤26を形成することによっ
て立坑28が構築されることになる。After the caisson 20 has been sunk to the planned depth H of the shaft in this manner, the shaft 28 is constructed by pouring concrete on the floor surface of the cutting edge 22 of the caisson 20 to form a floor plate 26. That will happen.
上記立坑28をシールド掘削機の発進坑とする場合には
、立坑28の内壁にシールドエントランス30を開口す
るが、この関口に先立ち、ケーソン20と連続土留止水
壁12との間の地盤が崩落するおそれがある場合には、
この壁間地盤に薬液注入をして硬化する地盤改良を施す
(第1図(4))。When the shaft 28 is used as a starting shaft for a shield excavator, a shield entrance 30 is opened in the inner wall of the shaft 28, but before this entrance, the ground between the caisson 20 and the continuous earth retaining water stop wall 12 collapses. If there is a risk of
A chemical solution is injected into the ground between the walls to harden the ground (Fig. 1 (4)).
これによって硬化した改良地盤32はシールドエントラ
ンス30を開口しても噴発することがないので、連続土
留止水壁12内の地盤の沈下を生じることがない、この
ような処理の後に、立坑28内にシールド掘削機34を
降ろし、開口したシールドエントランス30からシール
ド掘削機34を発進し、立坑28の後壁にバックトラス
36、仮セグメント38を介して改良地盤32、連続土
留止水g!12を貫通させ、とう道を形成するのである
(第1図(5))。The improved ground 32 hardened by this will not erupt even if the shield entrance 30 is opened, so the ground within the continuous earth retaining water stop wall 12 will not sink.After such treatment, the inside of the shaft 28 The shield excavator 34 is lowered to the ground, the shield excavator 34 is started from the opened shield entrance 30, and the back truss 36 is attached to the rear wall of the shaft 28, and the improved ground 32 is installed via the temporary segment 38, and the continuous earth retaining water stop g! 12 to form a tunnel (Fig. 1 (5)).
このような第一実施例に係る立坑構築工法によれば、立
坑予定部10の周囲に予め泥水固化法により連続土留止
水壁12を構築するため、鉄筋の建込みやコンクリート
の打設がなく、しかも逆巻工法に比較しても大幅に工期
の短縮が図れる。しかも連続土留止水壁12によって周
辺地盤と隔離した状態でのケーソン工法であることから
、立坑予定部10内への地下水の回り込みがない上に、
ケーソン20の沈下による周辺地盤の沈下や地中水位等
の変動を防止できる。そして、立坑予定部10への水の
回り込みが防止されているため、圧気ケーソン工法を使
用する必要がない、これにより圧気に起因するコンプレ
ッサの使用に伴う騒音・振動がなく、周辺地下室や井戸
への影響、酸欠空気の発生、および潜函病の発生と圧気
補正による作業能率の低下の問題もなくなる。また、特
にシールド掘削機34の発進時に連続土留止水壁12と
ケーソン20の壁間に形成する改良地盤32は、拘束さ
れた空間での改良であるため、改良効果が大きく、シー
ルドエントランス30の開口作業の安全性が向上し、経
済的でもあ・る。According to the shaft construction method according to the first embodiment, since the continuous earth retaining water stop wall 12 is constructed in advance around the planned shaft portion 10 by the mud solidification method, there is no need to build reinforcing bars or pour concrete. Moreover, compared to the reverse winding method, the construction period can be significantly shortened. Moreover, since the caisson construction method is isolated from the surrounding ground by the continuous earth retaining water stop wall 12, there is no leakage of groundwater into the planned shaft 10, and
Subsidence of the surrounding ground and fluctuations in underground water level due to the subsidence of the caisson 20 can be prevented. Since water is prevented from flowing into the planned shaft 10, there is no need to use the pressure caisson construction method.This eliminates the noise and vibrations associated with the use of compressors caused by pressure, and does not allow water to flow into surrounding basements or wells. This also eliminates the problems of the influence of water, the occurrence of oxygen-deficient air, the occurrence of latent disease, and a decrease in work efficiency due to air pressure correction. In particular, the improved ground 32 formed between the continuous earth retaining water stop wall 12 and the wall of the caisson 20 when the shield excavator 34 starts is improved in a restricted space, so the improvement effect is large, and the improvement effect is large. The safety of opening work is improved and it is also economical.
第2図は第二実施例に係る立坑構築工法による施工手順
を示す断面図である。この立坑構築工法は、立坑予定部
の周囲を囲む連続土留止水壁を最初に形成するとともに
、この連続土留止水壁の下部にジェットグラウトによっ
て底盤部を形成して立坑予定部を周囲の地盤から分離す
る。その後に、この分離された立坑予定部にオープンケ
ーソンを連続土留止水壁の内壁に沿わせて沈設施工する
ことによって立坑を構築するものである。FIG. 2 is a sectional view showing a construction procedure using a shaft construction method according to a second embodiment. In this shaft construction method, a continuous earth retaining water stop wall is first formed surrounding the planned shaft area, and a bottom layer is formed by jet grouting at the bottom of this continuous earth retaining water stop wall, and the planned shaft area is connected to the surrounding ground. Separate from. Thereafter, a shaft is constructed by sinking an open caisson along the inner wall of the continuous earth retaining water stop wall in the separated planned shaft portion.
まず、立坑予定部lOの周囲に連続土留止水壁12を構
築するが、これは前記第一実施例と同様に泥水固化法に
より構築する。すなわち、各エレメント毎に安定液を溝
14に供給して泥水化を図りつつ、ケーソン沈埋深さよ
り若干深い位置まで掘削し、泥水をエアジェツトによっ
て攪拌混合させつつ硬化剤を注入し、硬化させる。この
ような処理を全周にわたって行い、第3図に示すような
連続土留止水壁12を構築するのである(第2図(1)
)、この連続土留止水壁12もケーソンとの間隔を60
〜70cmにとり、ケーソンの傾きを一定限度で許容す
るとともに、それ以上の傾斜を連続土留止水壁12によ
って支承するものとしている。First, a continuous earth retaining water stop wall 12 is constructed around the planned shaft portion IO, which is constructed by the muddy water solidification method as in the first embodiment. That is, while supplying a stabilizing liquid to the groove 14 for each element to turn it into muddy water, excavation is carried out to a position slightly deeper than the caisson burial depth, and while the muddy water is stirred and mixed by an air jet, a hardening agent is injected and hardened. By performing this treatment all around the perimeter, a continuous earth retaining water stop wall 12 as shown in Figure 3 is constructed (Figure 2 (1)
), this continuous earth retaining water stop wall 12 also has an interval of 60 mm from the caisson.
~70 cm, allowing the inclination of the caisson within a certain limit, and further inclinations are supported by the continuous earth retaining water stop wall 12.
このような連続土留止水壁12を構築した後に、この第
二実施例では当該連続土留止水壁12の下部を閉塞して
周囲地盤と立坑予定部lOとを分離する工程を行う、こ
れは例えばジェットグラウトにより構築するもので、立
坑予定部lOの地表からパイプを連続土留止水壁12の
下端相当深さまで挿入し、パイプ先端部分に穿設したジ
ュツトノズルからセメントミルクを地中に浸透させて硬
化させる。これによってコア16が形成されるが、この
コア16が連接するように一定間隔をおいて前記パイプ
を挿入してグラウチングする。このような処理によって
、第2図(2)に示すように連続土留止水壁12の下部
に底盤部18を構築し、立坑予定部10内部を周辺地盤
から分離して遮水機能をもたせている。After constructing such a continuous earth-retaining water-stopping wall 12, in this second embodiment, a step is performed to close the lower part of the continuous earth-retaining water-stopping wall 12 to separate the surrounding ground from the planned shaft portion IO. For example, it is constructed using jet grouting, in which a pipe is inserted from the ground surface of the planned shaft portion IO to a depth equivalent to the lower end of the continuous earth retaining water stop wall 12, and cement milk is infiltrated into the ground from a jet nozzle drilled at the tip of the pipe. Let it harden. This forms the core 16, and the pipes are inserted and grouted at regular intervals so that the cores 16 are connected. Through such treatment, as shown in Fig. 2 (2), a bottom section 18 is constructed at the lower part of the continuous earth retaining water stop wall 12, and the inside of the planned shaft section 10 is separated from the surrounding ground to provide a water-blocking function. There is.
上記のような二工程処理を行った後に、立坑予定部10
にケーソン20を構築する。この実施例においても連続
土留止水壁12および底盤部18により止水壁が構築さ
れているのでオープンケーソン工法を採用でき、このた
めケーソン20はオープンケーソンとしいる。まず、立
坑予定部10の地表に対し、最初ケーソン20の安定沈
埋のために一次掘削を行う、これはバックホー等を用い
一次掘削し、ケーソン刃口22を据え付け、第一ロット
慣体24+を構築する(第2図0))、この、躯体24
の構築後に刃口22の外周囲を埋め戻す。After performing the two-step treatment as described above, the shaft planned area 10
Construct caisson 20. In this embodiment as well, the water stop wall is constructed by the continuous earth retaining water stop wall 12 and the bottom plate 18, so the open caisson construction method can be adopted, and therefore the caisson 20 is an open caisson. First, primary excavation is performed on the ground surface of the planned shaft 10 in order to stably bury the caisson 20. This is done using a backhoe, etc., and the caisson tip 22 is installed, and the first lot inert body 24+ is constructed. (Fig. 2 0)), this frame 24
After construction, the outer periphery of the cutting edge 22 is backfilled.
以後は第二ロット躯体248を構築するとともに沈下掘
削をなし、立坑設定深さ(第nロット躯体24、)まで
繰り返し施工する(第2図(4))。Thereafter, the second lot frame 248 is constructed and submerged excavation is performed, and the construction is repeated until the vertical shaft is set to the depth (nth lot frame 24,) (FIG. 2 (4)).
このようにしてケーソン20の沈設が終了した後は、ケ
ーソン20の刃口22は底盤部18に当接あるいはその
近傍深さに達しており、床面にコンクリートを打設して
床盤26を形成することによって立坑28が構築される
ことになる。After the caisson 20 has been sunk in this way, the cutting edge 22 of the caisson 20 touches the bottom plate 18 or has reached a depth close to the bottom plate 18, and concrete is poured on the floor surface to remove the bottom plate 26. By forming the shaft 28 will be constructed.
上記立坑28をシールド掘削機の発進坑とする場合には
、立坑2aの内壁にシールドエントランス30を開口す
るが、この開口に先立ち、ケーソン20と連続土留止水
壁12との間のiI!!盤が崩落するおそれがある場合
には、この壁間地盤に薬液注入をして硬化する地盤改良
を施す(第2図(5) )。When the shaft 28 is used as a starting shaft for a shield excavator, a shield entrance 30 is opened in the inner wall of the shaft 2a. ! If there is a risk of the slab collapsing, improve the ground by injecting chemicals into the ground between the walls to harden it (Figure 2 (5)).
このような処理の後に、立坑28内にシールド掘削機3
4を降ろし、開口したシールドエントランス30からシ
ールド掘削機34を発進し、立坑28の後壁にバックト
ラス36、仮セグメント3日を介して改良地盤32、連
続土留止水壁12を貫通させ、とう道を形成するのであ
る(第2図(6) )。After such processing, a shield excavator 3 is installed in the shaft 28.
4 was lowered, the shield excavator 34 was started from the opened shield entrance 30, and the back truss 36 was inserted into the rear wall of the shaft 28, and the improved ground 32 and the continuous earth retaining water stop wall 12 were penetrated through the temporary segment 3 days. They form roads (Figure 2 (6)).
第5yJに上記した第二実施例の工程を説明するフロー
チャートを示す。Section 5yJ shows a flowchart explaining the steps of the second embodiment described above.
このような第二実施例に係る立坑構築工法によれば、第
一実施例と同様に、立坑予定部10の周囲に予め泥水固
化法により連続土留止水壁12を構築するため、鉄筋の
建込みやコンクリートの打設がなく、しかも逆巻工法に
比較しても大幅に工期の短縮が図れる。特にこの第二実
施例では、連続土留止水壁12と底盤部18によって周
辺地盤と隔離した状態でのケーソン工法であることから
、立坑予定部lO内への地下水の回り込みを完全に防止
することができ、ケーソン20の沈下による周辺地盤の
沈下や地中水位等の変動をより確実に防止できる。そし
て、圧気ケーソン工法を使用する必要がないため、圧気
に起因するコンプレッサの使用に伴う騒音・振動がな(
、′周辺地下室や井戸への影響、酸欠空気の発生、およ
び潜函病の発生よ圧気補正による作業能率の低下の問題
もないのも第一実施例と同様である。According to the shaft construction method according to the second embodiment, similar to the first embodiment, in order to construct the continuous earth retaining water stop wall 12 in advance around the planned shaft portion 10 by the mud solidification method, the construction of reinforcing bars is required. There is no pouring or pouring of concrete, and the construction period can be significantly shortened compared to the reverse wrapping method. In particular, in this second embodiment, since the caisson construction method is used in a state where it is isolated from the surrounding ground by the continuous earth retaining water stop wall 12 and the bottom plate 18, it is possible to completely prevent groundwater from flowing into the planned shaft area IO. This makes it possible to more reliably prevent subsidence of the surrounding ground and fluctuations in the underground water level due to the subsidence of the caisson 20. Also, since there is no need to use the pressure caisson construction method, there is no noise or vibration associated with the use of compressors caused by pressure (
Similarly to the first embodiment, there are no problems of influence on surrounding basements and wells, occurrence of oxygen-deficient air, occurrence of incubation disease, and reduction in work efficiency due to air pressure correction.
なお、上記第一実施例と第二実施例では、連続土留止水
壁12の根切り深さhを長く取るか、これを短くして地
盤改良工法により底盤部18を構築するかで相違するが
、これは周辺地盤の現況から考慮して安定性と工費の少
ない工法を採用するようにすればよい。In addition, the difference between the first and second embodiments is whether the root cut depth h of the continuous earth retaining water stop wall 12 is made longer, or whether it is made shorter and the bottom part 18 is constructed by the ground improvement method. However, this can be done by considering the current state of the surrounding ground and adopting a construction method that is more stable and less expensive.
以上説明したように、本発明に係る立坑構築工法によれ
ば、立坑予定部の周囲を囲む連続土留止水壁を予め泥水
固化法により形威し、必要に窓じて水回り込みのない根
切り深さhとするか、あるいは連続土留止水壁の底部に
ジェットグラウト等の地盤改良工法により底盤部を形成
することにより立坑予定部を周囲地盤から分離し、その
後に、前記連続土留止水壁の内部にオーブンケーソンを
構築し、゛前記連続土留止水壁の内壁に沿って前記ケー
ソンを沈設して立坑を構築するため、立坑の構築のため
の工事期間の大幅な短縮を図ることができ、また、施工
時の振動・騒音等の発生がなく、周辺地盤への悪影響も
生じないという優れた効果が得られる。As explained above, according to the shaft construction method according to the present invention, a continuous earth retaining water-stop wall surrounding the planned shaft area is shaped in advance by a mud water solidification method, and roots are cut as necessary to prevent water from entering. The planned shaft part is separated from the surrounding ground by forming a bottom part with a depth h or by forming a bottom part at the bottom of the continuous earth retaining water cut-off wall using a ground improvement method such as jet grouting, and then the continuous earth retaining water cut-off wall is An oven caisson is constructed inside the shaft, and the shaft is constructed by sinking the caisson along the inner wall of the continuous earth retaining water stop wall. Therefore, the construction period for constructing the shaft can be significantly shortened. In addition, excellent effects such as no generation of vibration or noise during construction and no adverse effects on the surrounding ground can be obtained.
第1図(1)〜(5)は本発明の第一実施例に係る立坑
構築工法の作業工程を示す説明図、第211ffl(1
)〜(6)は同第二実施例に係る立坑構築工法の作業工
程を示す説明図、第3図は立坑構築状態の平面図、第4
図は同縦断面図、第5図は第二実施例における立坑構築
工法の作業工程のフローチャートである。
10・・・・・・立坑予定部、12・・・・・・連続土
留止水壁、18・・・・・・底盤部、20・・・・・・
オープンケーソン、32・・・・・・改良地盤。FIGS. 1 (1) to (5) are explanatory diagrams showing the work steps of the shaft construction method according to the first embodiment of the present invention, and No. 211ffl (1)
) to (6) are explanatory diagrams showing the work process of the shaft construction method according to the second embodiment, FIG. 3 is a plan view of the shaft construction state, and FIG.
The figure is a longitudinal sectional view of the same, and FIG. 5 is a flowchart of the working process of the shaft construction method in the second embodiment. 10... Planned shaft part, 12... Continuous earth retaining water stop wall, 18... Bottom plate part, 20...
Open caisson, 32...improved ground.
Claims (1)
連続土留止水壁を形成した後に、前記連続土留止水壁の
内部にオープンケーソンを構築し、前記連続土留止水壁
の内部において前記ケーソンを沈設することにより立坑
を構築することを特徴とする立坑構築工法。(2)、前
記連続土留止水壁は立坑底部より下方に突出する根切り
長さを立坑幅長さ程度に設定したことを特徴とする請求
項1に記載の立坑構築方法。 (3)、予め泥水固化法により立坑予定部の周囲を囲む
連続土留止水壁を形成するとともに、この連続土留止水
壁の底部にジェットグラウト等の地盤改良方法により底
盤部を形成して立坑予定部を周囲地盤から分離し、その
後に、前記連続土留止水壁の内部にオープンケーソンを
構築し、前記連続土留止水壁の内壁に沿って前記ケーソ
ンを沈設することにより立坑を構築することを特徴とす
る立坑構築工法。[Scope of Claims] (1) After forming in advance a continuous earth retaining water cutoff wall surrounding the planned shaft portion by a mud water solidification method, an open caisson is constructed inside the continuous earth retention water cutoff wall, and the continuous earth retaining water cutoff wall is constructed in advance. A shaft construction method characterized in that a shaft is constructed by sinking the caisson inside a water-stop wall. (2) The method for constructing a shaft according to claim 1, wherein the continuous earth retaining water stop wall has a root cutting length that projects downward from the bottom of the shaft and is set to be approximately the width of the shaft. (3) In advance, a continuous earth retaining water stop wall surrounding the planned shaft portion is formed using the mud solidification method, and a bottom layer is formed at the bottom of this continuous earth retaining water cut wall using a ground improvement method such as jet grouting. Separating the planned portion from the surrounding ground, then constructing an open caisson inside the continuous earth retaining water cutoff wall, and constructing the shaft by sinking the caisson along the inner wall of the continuous earth retention water cutoff wall. A vertical shaft construction method characterized by:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21660989A JP2874906B2 (en) | 1989-08-23 | 1989-08-23 | Shaft construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21660989A JP2874906B2 (en) | 1989-08-23 | 1989-08-23 | Shaft construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0381421A true JPH0381421A (en) | 1991-04-05 |
JP2874906B2 JP2874906B2 (en) | 1999-03-24 |
Family
ID=16691111
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP21660989A Expired - Lifetime JP2874906B2 (en) | 1989-08-23 | 1989-08-23 | Shaft construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2874906B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015001140A (en) * | 2013-06-18 | 2015-01-05 | 鹿島建設株式会社 | Excavation method, construction method for underground structure, wall body member, and wall body for excavation |
CN108824505A (en) * | 2018-07-11 | 2018-11-16 | 上海市政建设有限公司 | A kind of short distance open caisson group's sinking construction method |
CN115369902A (en) * | 2022-08-12 | 2022-11-22 | 中国一冶集团有限公司 | Water-rich geological open caisson structure and construction method thereof |
-
1989
- 1989-08-23 JP JP21660989A patent/JP2874906B2/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015001140A (en) * | 2013-06-18 | 2015-01-05 | 鹿島建設株式会社 | Excavation method, construction method for underground structure, wall body member, and wall body for excavation |
CN108824505A (en) * | 2018-07-11 | 2018-11-16 | 上海市政建设有限公司 | A kind of short distance open caisson group's sinking construction method |
CN115369902A (en) * | 2022-08-12 | 2022-11-22 | 中国一冶集团有限公司 | Water-rich geological open caisson structure and construction method thereof |
CN115369902B (en) * | 2022-08-12 | 2023-07-18 | 中国一冶集团有限公司 | Water-rich geological open caisson structure and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP2874906B2 (en) | 1999-03-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4496268A (en) | Method and apparatus for constructing reinforced concrete walls in the earth | |
JP3967473B2 (en) | Construction method of underground structure | |
JP2874906B2 (en) | Shaft construction method | |
KR100476839B1 (en) | Construction method for installing concrete underground structures | |
KR101021913B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
KR200296444Y1 (en) | Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method | |
JPS5936058B2 (en) | How to construct a structure using underground continuous walls | |
JPS6117696A (en) | Construction of underground head | |
JP3941429B2 (en) | Water stoppage / Yamadome construction method for rebuilding existing buildings | |
KR102610909B1 (en) | Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking | |
JP3728659B2 (en) | Basement extension method | |
JPH01121414A (en) | Excavation work of ground | |
JP7540678B1 (en) | System and method for backfilling narrow excess trenches in a mine with liquefied hardened soil | |
JPS601451B2 (en) | Water stop mountain stop wall construction method using Benoto pile excavator | |
JP2846248B2 (en) | Earth retaining wall and construction method | |
JP3027685B2 (en) | Earth retaining wall and construction method | |
JP3030622B2 (en) | How to build a tunnel | |
JPS6192235A (en) | Fixing of embedded pipe | |
JPH0510084A (en) | Execution method of deeper depth man hole | |
JP2022100109A (en) | Subsidence prevention structure for adjacent building and method thereof | |
CN110130372A (en) | A kind of construction method in prestress anchorage cable cofferdam | |
JPH10140557A (en) | Construction method of cast-in-place diaphragm wall with hollow | |
JPS60181426A (en) | Method of burying pipe in soft soil layer | |
CN112982385A (en) | Construction method for reinforcing open caisson foundation pit in deep silt stratum | |
JP2004143744A (en) | Construction method for diaphragm wall and diaphragm wall |