JP2004143744A - Construction method for diaphragm wall and diaphragm wall - Google Patents

Construction method for diaphragm wall and diaphragm wall Download PDF

Info

Publication number
JP2004143744A
JP2004143744A JP2002308033A JP2002308033A JP2004143744A JP 2004143744 A JP2004143744 A JP 2004143744A JP 2002308033 A JP2002308033 A JP 2002308033A JP 2002308033 A JP2002308033 A JP 2002308033A JP 2004143744 A JP2004143744 A JP 2004143744A
Authority
JP
Japan
Prior art keywords
continuous wall
excavator
shield machine
core
underground continuous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002308033A
Other languages
Japanese (ja)
Other versions
JP4180347B2 (en
Inventor
Koichi Tanaka
田中 耕一
Yutaka Kotaki
小滝 裕
Yukinobu Sasaki
佐々木 幸信
Koichi Tsuruta
鶴田 浩一
Koji Morihira
森平 宏治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2002308033A priority Critical patent/JP4180347B2/en
Publication of JP2004143744A publication Critical patent/JP2004143744A/en
Application granted granted Critical
Publication of JP4180347B2 publication Critical patent/JP4180347B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method for a diaphragm wall constructed in a short period in a non-cutting-covering manner without being restricted by a ground and the diaphragm wall. <P>SOLUTION: A pit 30 is excavated to a natural ground 5 by a shield machine 3, and a cutter 13 for a continuous-wall excavator 9 is extended to the lower section of the pit 30 when the continuous-wall excavator 9 installed in the shield machine 3 reaches the construction prearranged place of the diaphragm wall 33. Cement milk injected from an injection pipe 14 and excavated materials are mixed/agitated, conducting a horizontal drawing excavation by the excavator 9 and excavating a ditch 25 to the lower section of the pit 30, and the inside of the ditch 25 is filled with soil mortar 27. A core material 31 is built into the ditch 25 by using a core-material building machine 19 installed into the shield machine 3 before soil mortar 27 is cured, and the diaphragm wall 33 is constructed. The core material 31 is built, and a segment 29 is mounted along the inner periphery of the pit 30. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明の属する技術分野】
本発明は、地中連続壁の構築工法および地中連続壁に関するものである。
【0002】
【従来の技術】
従来、地中連続壁を施工するには、地上にガイドウォールを敷設し、それに沿って連続壁掘削機で必要な深さの溝壁を掘削し、セメントミルクの混合撹拌および芯材の建て込みを行う。または、地盤中に掘削したトンネルと地表面との間に山留め処理を施し、トンネルの下方に、止水体を形成する(例えば、特許文献1参照)。
【0003】
【特許文献1】
P3027685
【0004】
【発明が解決しようとする課題】
しかしながら、地上を占有できない場合や、地盤内に埋設管等が設置されている場合等には、地表から溝壁を掘削するのが困難である。また、構築済みのトンネルの一部を解体して止水体を形成する場合、解体作業が複雑である。
【0005】
本発明は、このような問題に鑑みてなされたもので、その目的とするところは、地上の制約を受けずに、非開削で短期間に施工できる地中連続壁の構築工法および地中連続壁を提供することにある。
【0006】
【課題を解決するための手段】
前述した目的を達成するための第1の発明は、シールド機で地盤内に坑道を掘削する工程(a)と、前記坑道の下方に溝を掘削して充填材を充填する工程(b)と、前記溝内に芯材を設置する工程(c)と、前記坑道内にセグメントを設置する工程(d)とを具備することを特徴とする地中連続壁の構築方法である。
【0007】
工程(a)では、地中連続壁掘削機と芯材建込み機が設置されたシールド機を用いて、地盤内に坑道を掘削する。工程(b)では、地中連続壁掘削機を用いて坑道の下方に溝を掘削し、充填材を溝内に充填する。工程(c)では、芯材建込み機を用いて、溝内に芯材を設置する。工程(d)では、シールド機のエレクタ等を用いて、坑道内にセグメントを設置する。さらに、必要に応じて、芯材とセグメントとを一体化する。
【0008】
工程(b)では、充填材として、例えば、掘削位置で掘削土にセメントミルクを撹拌混合したソイルモルタルを溝に充填する。または、工程(b)で充填材として安定液を溝に充填し、例えば工程(c)の後、安定液をソイルモルタルに置き換える。
【0009】
溝を掘削する地盤中に地下水が存在する場合には、地中連続壁掘削機および芯材建込み機の周囲に圧気室が設けられる。地中連続壁掘削機には、例えば、チェーンソー型、オーガー型等のものが用いられる。
【0010】
第2の発明は、シールド機で地盤内に坑道を掘削する工程(a)と、前記坑道の下方に溝を掘削して充填材を充填する工程(b)と、前記坑道内にセグメントを設置する工程(c)と、前記溝内に芯材を設置する工程(d)とを具備することを特徴とする地中連続壁の構築方法である。
【0011】
工程(a)では、地中連続壁掘削機が設置されたシールド機を用いて、地盤内に坑道を掘削する。工程(b)では、地中連続壁掘削機を用いて坑道の下方に溝を掘削し、充填材を溝内に充填する。工程(c)では、シールド機のエレクタ等を用いて、坑道内にセグメントを設置する。工程(d)では、シールド機の後方に設置された芯材建込み機を用いて、溝内に芯材を設置する。さらに、必要に応じて、芯材とセグメントとを一体化する。
【0012】
工程(b)では、充填材として、例えば、掘削位置で掘削土にセメントミルクを撹拌混合したソイルモルタルを溝に充填する。または、工程(b)で充填材として安定液を溝に充填し、例えば工程(d)の後、安定液をソイルモルタルに置き換える。
【0013】
工程(c)で設置されるセグメントは、開閉可能な部分、例えば孔と蓋を有する。その場合、工程(d)では、セグメントに設けられた蓋を取り外し、孔に芯材を通して溝内に建て込んだ後、孔に蓋をする。
【0014】
溝を掘削する地盤中に地下水が存在する場合には、地中連続壁掘削機および芯材建込み機の周囲に圧気室が設けられる。地中連続壁掘削機には、例えば、チェーンソー型、オーガー型等のものが用いられる。
【0015】
第3の発明は、シールド機で地盤内に坑道を掘削する工程(a)と、前記坑道内にセグメントを設置する工程(b)と、前記坑道の下方に溝を掘削して充填材を充填する工程(c)と、前記溝内に芯材を設置する工程(d)とを具備することを特徴とする地中連続壁の構築方法である。
【0016】
工程(a)では、シールド機を用いて、地盤内に坑道を掘削する。工程(b)では、シールド機のエレクタ等を用いて、坑道内にセグメントを設置する。工程(c)では、地中連続壁掘削機を用いて坑道の下方に溝を掘削し、充填材を溝内に充填する。工程(d)では、シールド機の後方に設置された芯材建込み機を用いて、溝内に芯材を設置する。さらに、必要に応じて、芯材とセグメントとを一体化する。
【0017】
工程(b)で設置されるセグメントは、開閉可能な部分、例えば孔と蓋を有する。その場合、工程(c)では、セグメントに設けられた蓋を取り外し、孔に地中連続壁掘削機のカッタを通して溝を掘削する。そして、工程(d)で、孔に芯材を通して溝内に建て込んだ後、孔に蓋をする。
【0018】
工程(c)では、充填材として、例えば、掘削位置で掘削土にセメントミルクを撹拌混合したソイルモルタルを溝に充填する。または、工程(c)で充填材として安定液を溝に充填し、例えば工程(d)の後、安定液をソイルモルタルに置き換えて、孔に蓋をする。
【0019】
溝を掘削する地盤中に地下水が存在する場合には、地中連続壁掘削機および芯材建込み機の周囲に圧気室が設けられる。地中連続壁掘削機には、例えば、チェーンソー型、オーガー型等のものが用いられる。
【0020】
第4の発明は、シールド機で地盤内に坑道を掘削する工程(a)と、前記坑道の下方に溝を掘削して充填材を充填する工程(b)と、前記坑道内にセグメントを設置する工程(c)とを具備することを特徴とする地中連続壁の構築方法である。
【0021】
工程(a)では、シールド機を用いて、地盤内に坑道を掘削する。工程(b)では、地中連続壁掘削機を用いて坑道の下方に溝を掘削し、充填材を溝内に充填する。工程(c)では、シールド機のエレクタ等を用いて、坑道内にセグメントを設置する。
【0022】
工程(b)では、充填材として、例えば、掘削位置で掘削土にセメントミルクを撹拌混合したソイルモルタルを溝に充填する。または、工程(b)で充填材として安定液を溝に充填した後、安定液をソイルモルタルに置き換える。
地中連続壁掘削機の周囲には、必要に応じて圧気室が設けられる。地中連続壁掘削機には、例えば、チェーンソー型、オーガー型等のものが用いられる。
【0023】
【発明の実施の形態】
以下、図面に基づいて、本発明の第1の実施の形態を詳細に説明する。図1は、地中連続壁掘削装置Aを立坑1から発進させる工程を示す図、図2は、所定の深度まで連壁掘削機9のカッタ13を延長する工程を示す図、図3は、連壁掘削機9で溝25を掘削し、ソイルモルタル27を充填する工程を示す図、図4は、溝25内に芯材31を建て込む工程を示す図である。
【0024】
図1から図4に示すように、地中連続壁掘削装置Aは、シールド機3、連壁掘削機9、圧気室15、芯材建込み機19、圧気室21、材料ロック23等で構成される。連壁掘削機9、芯材建込み機19は、シールド機3の内部に設けられる。圧気室15は連壁掘削機9の周囲に、圧気室21は芯材建込み機19の周囲に設けられる。
【0025】
シールド機3は、筒状の本体、スクリューコンベア4、カッタ6等で構成される。シールド機3は、本体の端部に設けられたカッタ6で地山5を掘削し、スクリューコンベア4で掘削土を後方へ送る。
【0026】
連壁掘削機9は、油圧モータ11、カッタ13、注入管14、排土装置17等で構成される。油圧モータ11は、カッタ13を駆動させる。カッタ13は、シールド機3の下方の地山5を掘削する。カッタ13には、チェーンソー型、オーガー型等のものを用いる。図1に示すカッタ13は、複数のカッタブロックを接続することにより、図2から図4に示すように、所定の深度まで延長することができる。
【0027】
注入管14は、カッタ13で掘削された溝25にセメントミルク等を注入する。排土装置17は、カッタ13で掘削した排土をシールド機3の外部に排出する。連壁掘削機9は、シールド機3の下方に溝25を掘削して溝25内にソイルモルタル27を充填する。
【0028】
芯材建込み機19は、溝25内に芯材31を建て込む。芯材建込み機19には、例えば、簡易クレーン等を使用する。圧気室15と圧気室21は、溝25からシールド機3の内部への漏水を防ぐ。
【0029】
次に、地中連続壁掘削装置Aを用いて地中連続壁33を形成する方法について説明する。まず、図1に示すように、地山5中に立坑1を設け、立坑1の外部に適切な方法で地盤改良7を施し、立坑1からシールド機3を発進させる。シールド機3は、カッタ6で地山5を掘削し、スクリューコンベア4等で掘削土を排出しつつ前進する。連壁掘削機9が地中連続壁33(図4)の構築予定位置に達するまでは、連壁掘削機9のカッタ13は、図1に示すようにシールド機3内に格納されている。
【0030】
連壁掘削機9が地中連続壁33(図4)の構築予定位置に達すると、図2に示すように、油圧モータ11でカッタ13を駆動させてシールド機3の下方の地山5を垂直に掘削する作業と、油圧モータ11とカッタ13との間に中間カッタブロックを挿入する作業とを繰り返して、カッタ13を所定の長さまで延長する。そして、連壁掘削機9の周囲に排土装置17を有する圧力室15を取り付ける。
【0031】
次に、図3に示すように、カッタ13を延長した連壁掘削機9で横引き掘削を行い、溝25を形成する。同時に、注入管14からセメントミルクを注入し、原位置にて掘削土との混合および攪拌を行って、溝25にソイルモルタル27を充填する。不要な掘削土は、排土装置17を用いて排出される。
【0032】
溝25の掘削後、または、掘削と並行して、シールド機3内の連壁掘削機9の後方に芯材建込み機19を設置する。芯材建込み機19の周囲には圧気室21を設置し、圧気室21の後方には材料ロック23を設置する。
【0033】
そして、図4に示すように、芯材建込み機19を用いて、ソイルモルタル27が硬化しないうちに、溝25内に芯材31を建て込み、地中連続壁33を完成する。芯材31を建て込んだ後、シールド機3に設置されたエレクタ(図示せず)を用いて、シールド機3で掘削した坑30の内周に沿ってセグメント29を設置する。芯材31には、断面が矩形の鋼管や、H鋼等を用いる。芯材31は、例えば、複数の短い部材を継ぎ足して所定の長さにする。
【0034】
このように、第1の実施の形態では、シールド機3内に連壁掘削機9と芯材建込み機19を設置することで、地上から開削することなく地中連続壁33を形成できる。このとき、連壁掘削機9と芯材建込み機19とを分離することで、溝25の掘削工程と芯材31の建て込み工程とを分割して実施でき、工期を短縮することができる。
【0035】
なお、図1から図4に示す地中連続壁掘削装置Aでは、連壁掘削機9と芯材建込み機19のそれぞれに圧気室15、圧気室21を設置したが、圧気室の設置数はこれに限らない。圧気室の設置位置は、溝25からシールド機3内や坑30内への漏水を防げる位置であればよく、場合によっては、トンネル坑口部22(図3)や立坑部24(図3)に隔壁を設けて圧気室を設けてもよい。
【0036】
図5は、他の構成の地中連続壁掘削装置Bの断面図を示す。地中連続壁掘削装置Bは、シールド機3、連壁掘削機9、芯材建込み機19、圧気室35等で構成される。地中連続壁掘削装置Bのシールド機3、連壁掘削機9、芯材建込み機19の構造や動作は、地中連続壁掘削装置Aのものと同様であるが、圧気室35は、連壁掘削機9と芯材建込み機19の両方を囲むように設置される。
【0037】
地中連続壁掘削装置Bでは、連壁掘削機9で溝25を掘削してソイルモルタル27を充填した後、芯材建込み機19で溝25内に芯材31を建て込んで地中連続壁33を完成する。なお、圧気室35の大きさは図5に示すものに限らない。圧気室35を、連壁掘削機9と芯材建込み機19が独立して動ける程度の大きさとすることで、地中連続壁掘削装置Aと同様に、溝25の掘削工程と芯材31の建て込み工程とを分割して実施することができる。
【0038】
図6は、他の構成の地中連続壁掘削装置Cの断面図を示す。地中連続壁掘削装置Cは、シールド機3、連壁掘削機9、芯材建込み機19等で構成される。地中連続壁掘削装置Cのシールド機3、連壁掘削機9、芯材建込み機19の構造や動作は、地中連続壁掘削装置A、地中連続壁掘削装置Bのものと同様であるが、連壁掘削機9と芯材建込み機19を囲む圧気室は設置されない。地中連続壁33の構築予定位置付近に地下水がなく、シールド機3内への漏水の可能性がない場合は、地中連続壁掘削装置Cのように、圧気室を省略することができる。
【0039】
地中連続壁掘削装置Cでは、地中連続壁掘削装置A、地中連続壁掘削装置Bと同様に、連壁掘削機9で溝25を掘削してソイルモルタル27を充填する工程と、芯材建込み機19で溝25内に芯材31を建て込む工程とを分割して実施して地中連続壁33を形成することができる。
【0040】
次に、第2の実施の形態を詳細に説明する。図7は、連壁掘削機9aで溝25を掘削し、ソイルモルタル27を充填する工程を示す図、図8は、溝25内に芯材31aを建て込む工程を示す図、図9は、セグメント29b付近の拡大図である。
【0041】
図7、図8に示すように、地中連続壁掘削装置Dは、シールド機3、連壁掘削機9a、圧気室15a、芯材建込み機19a、圧気室21a、材料ロック23a等で構成される。
【0042】
地中連続壁掘削装置Dのシールド機3a、連壁掘削機9a、圧気室15aの構成や設置位置は、地中連続壁掘削装置Aのシールド機3、連壁掘削機9、圧気室15と同様である。連壁掘削機9aは、シールド機3の内部に設けられ、圧気室15aは連壁掘削機9aの周囲に設けられる。
【0043】
シールド機3は、筒状の本体の端部に設けられたカッタ6で地山5を掘削し、スクリューコンベア4で掘削土を後方へ送る。連壁掘削機9aは、シールド機3の下方に溝25aを掘削して、溝25aにソイルモルタル27aを充填する。
【0044】
地中連続壁掘削装置Dの芯材建込み機19a、圧気室21aの構成は、地中連続壁掘削装置Aの芯材建込み機19、圧気室21と同様であるが、設置位置は異なる。芯材建込み機19aは、シールド機3の後方で坑30aの内周に沿って組み立てられたセグメント29aの内側に設けられ、圧気室21aは芯材建込み機19aの周囲に設けられる。芯材建込み機19aは溝25a内に芯材31aを建て込み、圧気室21aは、溝25aからシールド機3で掘削した坑30aの内部への漏水を防ぐ。
【0045】
図9に示すように、シールド機3で掘削した坑30a内に設置されるセグメントのうち、溝25aの掘削位置の上方に設けられるセグメント29bは、孔37を有する。孔37は、図8での芯材31aの設置計画位置に設けられる。セグメント29bでは、蓋39の取り外し、取り付けにより、孔37を開閉することができる。
【0046】
次に、地中連続壁掘削装置Dを用いて地中連続壁33aを形成する方法について説明する。まず、立坑1からシールド機3を発進させて、連壁掘削機9aが地中連続壁33a(図8)の構築予定位置に達した後、カッタ13aを所定の長さまで延長する。そして、連壁掘削機9aの周囲に排土装置17aを有する圧力室15aを取り付ける。ここまでの工程は、第1の実施の形態の地中連続壁掘削装置Aと同様である(図1、図2)。
【0047】
次に、図7に示すように、カッタ13aを延長した連壁掘削機9aで横引き掘削を行い、溝25aを形成する。同時に、注入管14aからセメントミルクを注入し、原位置にて掘削土との混合および攪拌を行って、溝25aにソイルモルタル27aを充填する。不要な掘削土は、排土装置17aを用いて排出される。
【0048】
溝25aの掘削後、シールド機3の後方に設置されたエレクタ(図示せず)を用いて、坑30aの内周に沿ってセグメント29a、セグメント29bを設置する。このとき、溝25の上方には、図9に示すセグメント29aが設置される。そして、セグメント29a、セグメント29bの内側に芯材建込み機19aを設置する。芯材建込み機19aの周囲には圧気室21aを設置し、圧気室21aの後方には材料ロック23aを設置する。
【0049】
次に、図8に示すように、芯材建込み機19aを用いて、ソイルモルタル27aが硬化しないうちに、溝25a内に芯材31aを建て込んで、地中連続壁33aを完成する。
【0050】
芯材31aを建て込むには、図9に示すように、溝25aの上方に設置されたセグメント29bの蓋39を開け、坑37に芯材31aを通して溝25a内に吊り降ろした後、蓋39を閉じる。芯材31aには、断面が矩形の鋼管や、H鋼等を用いる。芯材31aは、例えば、複数の短い部材を継ぎ足して所定の長さにする。
【0051】
このように、第2の実施の形態では、シールド機3内に連壁掘削機9aを設置し、シールド機3の後方に芯材建込み機19aを設置することで、地上から開削することなく地中連続壁33aを形成できる。連壁掘削機9aと芯材建込み機19aとを分離することで、溝25aの掘削工程と芯材31aの建て込み工程とを分割して実施でき、工期を短縮することができる。
【0052】
なお、図7、図8に示す地中連続壁掘削装置Dでは、連壁掘削機9aと芯材建込み機19aのそれぞれに圧気室15a、圧気室21aを設置したが、圧気室の設置位置は、溝25aからシールド機3内や坑30a内への漏水を防げる位置であればよい。地中連続壁33aの構築予定位置付近に地下水がなく、シールド機3や坑30a内への漏水の可能性がない場合は、圧気室を省略することができる。
【0053】
次に、第3の実施の形態について説明する。図10は、地中連続壁掘削装置Eで坑30bを掘削する工程を示す図、図11は、連壁掘削機9bで垂直削孔を開始する工程を示す図である。図10、図11に示すように、地中連続壁掘削装置Eは、シールド機3、連壁掘削機9b、圧気室43、芯材建込み機19b、移動用パネル41等で構成される。
【0054】
地中連続壁掘削装置Eのシールド機3、連壁掘削機9b、芯材建込み機19b、圧気室43の構成は、地中連続壁掘削装置Aのシールド機3、連壁掘削機9、芯材建込み機19、圧気室15と同様である。但し、連壁掘削機9b、芯材建込み機19b、圧気室43の設置位置は、地中連続壁掘削装置Aの連壁掘削機9、芯材建込み機19、圧気室15の設置位置とは異なる。
【0055】
連壁掘削機9b、芯材建込み機19bは、シールド機3の後方で坑30bの内周に沿って組み立てられたセグメント45の内側に設けられ、圧気室43は、連壁掘削機9b、芯材建込み機19bの周囲に設けられる。連壁掘削機9bは、セグメント45上に設けられた移動用パネル41に取り付けられる。
【0056】
シールド機3は、筒状の本体の端部に設けられたカッタ6で地山5を掘削し、スクリューコンベア4で掘削土を後方へ送る。連壁掘削機9bは、移動用パネル41に沿って坑30bの軸方向に移動しつつ、坑30bの下方に溝49を掘削してソイルモルタル51を充填する(図13)。芯材建込み機19bは溝49内に芯材53を建て込む(図13)。圧気室43は、溝49からシールド機3で掘削した坑30bの内部への漏水を防ぐ。
【0057】
シールド機3で掘削した坑30b内に設置されるセグメント45のうち、溝49の掘削位置に設けられるセグメント45aは、連壁掘削機9bのカッタ13bや芯材53を通すための開閉可能な孔46(図11)を有する。
【0058】
次に、地中連続壁掘削装置Eを用いて地中連続壁55を形成する方法について説明する。まず、立坑からシールド機3を発進させて坑30bを掘削し、シールド機3の後部で坑30bの内周に沿ってセグメント45を設置する。そして、図10に示すように、地中連続壁55(図13)の構築予定位置のセグメント45上に移動用パネル41と連壁掘削機9bを配置する。
【0059】
そして、図11に示すように、移動用パネル41と連壁掘削機9bの周囲に圧気室43を設置し、地中連続壁55(図13)の構築予定位置の上方のセグメント45aの孔46を開放する。図12は、所定の深度まで連壁掘削機9bのカッタ13bを延長する工程を示す図である。図12に示すように、連壁掘削機9bの油圧モータ11bでカッタ13bを駆動させて孔46の下方の地盤47を掘削しつつ、カッタ13bを所定の長さまで延長する。
【0060】
図13は、溝49内に芯材53を建て込む工程を示す図である。図13に示すように、カッタ13bを延長した連壁掘削機9bで横引き掘削を行い、溝49を形成する。同時に、注入管14bからセメントミルクを注入し、原位置にて掘削土との混合および攪拌を行って、溝49にソイルモルタル51を充填する。不要な掘削土は、排土装置(図示せず)を用いて排出される。
【0061】
溝49の掘削後、芯材建込み機19bを用いて、ソイルモルタル51が硬化しないうちに、溝49内に芯材53を建て込む。芯材53には、断面が矩形の鋼管や、H鋼等を用いる。芯材53は、例えば、複数の短い部材を継ぎ足して所定の長さにする。
【0062】
図14は、セグメント45aの孔46の一部を閉鎖して圧気室43を移動させる工程を示す図である。芯材53を建て込んだ後、図14に示すように、芯材53を建て込んだ溝49の上方に設置されたセグメント45aの孔46を閉鎖する。そして、移動用パネル41と圧気室43を移動させる。
【0063】
溝49を掘削しつつソイルモルタル51を混合・撹拌する工程と、溝49内に芯材53を建て込む工程と、セグメント45aの孔46を閉鎖して圧気室43を移動させる工程とを繰り返して、地中連続壁55を完成する。
【0064】
このように、第3の実施の形態では、シールド機3の後方に連壁掘削機9bと芯材建込み機19bを設置することで、地上から開削することなく地中連続壁55を形成できる。
【0065】
なお、圧気室の設置位置は、溝49からシールド機3内や坑30b内への漏水を防げる位置であればよい。地中連続壁55の構築予定位置付近に地下水がなく、シールド機3や坑30b内への漏水の可能性がない場合は、圧気室43を省略することができる。
【0066】
次に、第4の実施の形態について説明する。図15は、地中連続壁掘削装置Fで坑30cを掘削する工程を示す図、図16、図17は、地中連続壁掘削装置Fの周方向の断面図である。図15は、図16のY1−Y1による断面図を示す。図16、図17は、それぞれ、図15のX1−X1、X2−X2による断面図を示す。
【0067】
図15に示すように、地中連続壁掘削装置Fは、シールド機3、連壁掘削機9c、芯材建込み機19c、形状保持ジャッキ63、圧気区間65等で構成される。連壁掘削機9c、芯材建込み機19cの構成は、第1の実施の形態の地中連続壁掘削装置Aの連壁掘削機9、芯材建込み機19と同様である。
【0068】
圧気区間65は、図15に示すように、シールド機3の本体の一部に設けられる。圧気区間65は、第1の実施の形態の圧気室15、圧気室21と同様に、内部が圧気され、連壁掘削機9cで掘削した溝67からシールド機3の内部への漏水を防ぐ。連壁掘削機9c、芯材建込み機19cは、圧気区間65内に設置される。
【0069】
図16、図17に示すように、圧気区間65では、シールド機3の筒状の本体の一部に開口64が設けられる。シールド機3の本体の開口64の端部60では、内側にガイド部材62が設けられる。
【0070】
連壁掘削機9cは、カッタ13cが開口64のガイド部材62に沿って移動可能なように設置される。連壁掘削機9cは、シールド機3の下方に溝67を掘削してソイルモルタル69を注入する。芯材建込み機19cは、圧気区間65内を移動しつつ開口64から芯材71を建込むことができるように設置される。芯材建込み機19cは、溝67内に芯材71を建て込む。
【0071】
形状保持ジャッキ63は、ガイド部材62とシールド機3の本体との間に設置される。複数の形状保持ジャッキ63は、独立して伸縮を制御できる。形状保持ジャッキ63は、シールド機3の本体と開口部64の形状を保持する。
【0072】
シールド機3は、筒状の本体の端部に設けられたカッタ6で地山5を掘削し、スクリューコンベア4および排土装置59で掘削土を後方へ送る。シールド機3は、圧気区間65に設置された折れ部61を用いて掘削方向を調整することができる。
【0073】
次に、地中連続壁掘削装置Fを用いて地中連続壁73を形成する方法について説明する。まず、第1から第3の実施の形態と同様に、地山5中に設けた立坑からシールド機3を発進させる。シールド機3は、カッタ6で地山5を掘削し、スクリューコンベア4、排土装置59等で掘削土を排出する。連壁掘削機9cが地中連続壁73の構築予定位置に達するまでは、連壁掘削機9cのカッタ13cは、シールド機3内に格納されている。
【0074】
連壁掘削機9cが地中連続壁73の構築予定位置に達すると、カッタ13cを用いてシールド機3の下方の地山5を垂直に掘削する作業と、油圧モータとカッタ13cとの間に中間カッタブロックを挿入する作業とを繰り返して、カッタ13cを所定の長さまで延長する。
【0075】
そして、図15に示すように、シールド機3の本体の開口64に沿って連壁掘削機9cのカッタ13cを移動させて横引き掘削を行い、溝67aを形成する。このとき、図15から図17に示すように、カッタ13cの位置にある形状保持ジャッキ63bは縮められる。また、他の形状保持ジャッキ63aは伸ばされ、開口64の形状を保持する。
【0076】
連壁掘削機9cは、延長したカッタ13cで溝67aを掘削すると同時に、掘削位置にてセメントミルクと掘削土との混合および攪拌を行い、溝67aにソイルモルタル69aを充填する。不要な掘削土は、排土装置17を用いて排出される。ソイルモルタル69aは、形状保持ジャッキ63の下端まで充填される。
【0077】
溝67aの掘削後、または、掘削と並行して、芯材建込み機19cを用いて、ソイルモルタル69aが硬化しないうちに、溝67a内に芯材71を建て込む。芯材71を建て込んだ後、シールド機3に設置されたエレクタ(図示せず)を用いて、シールド機3で掘削した坑30cの内周に沿ってセグメント57を設置する。芯材71には、断面が矩形の鋼管や、H鋼等を用いる。芯材71は、例えば、複数の短い部材を継ぎ足して所定の長さにする。なお、芯材71の上端の位置は、図17に示す形状保持ジャッキ63の下端の位置とする。
【0078】
図18は、芯材71を建て込んだ位置でのセグメント57の周方向の断面図、図19は、延長用芯材83を設置した位置でのセグメント57の周方向の断面図である。図18、図19は、それぞれ、図15のX3−X3、X4−X4による断面図を示す。
【0079】
図15に示すように、芯材71を建て込んだ後、シールド機3で掘削した坑30cの内周に沿って、セグメント57を設置する。図18に示すように、セグメント57は、芯材71を迂回して配置される。芯材71の上方に配置されたセグメント57aは、開閉可能な蓋70を有する。
【0080】
次に、図19に示すように、芯材71の上端付近とセグメント57との間に止水鉄板81を設置する。そして、セグメント57aの蓋70を取り外した孔に延長用芯材83を通し、延長用芯材83を芯材71の上端に溶接85によって固定する。
【0081】
さらに、シールド機3で掘削した坑30cとセグメント57との間のテールボイド77に、シールド機3の掘進時に裏込注入材79を注入する。また、芯材71と延長用芯材83との溶接85の周囲のソイルモルタル69を撤去する。全ての芯材71の上端に延長用芯材83を溶接して、芯材71とセグメント57aとを一体化し、地中連続壁73を完成する。
【0082】
このように、第4の実施の形態では、シールド機3内に連壁掘削機9と芯材建込み機19cを設置することで、地上から開削することなく地中連続壁73を形成できる。このとき、連壁掘削機9と芯材建込み機19cとを分離することで、溝67の掘削工程と芯材71の建て込み工程とを分割して実施でき、工期を短縮することができる。
【0083】
また、シールド機3の圧気区間65では、形状保持ジャッキ63を伸張することで開口64の形状を保持しつつ、溝67の掘削と芯材71の建て込みを行うことができる。さらに、地中連続壁73の芯材71に延長用芯材83を溶接してセグメント57aと一体化することで、芯材71の位置を固定することができる。
【0084】
なお、図15に示す地中連続壁掘削装置Fでは、シールド機3の本体の一部を圧気区間65としたが、シールド機3内に圧気室を設置してもよい。また、地下水位75の位置によっては、圧気区間65を設けなくてもよい。
【0085】
また、第1から第3の実施の形態の方法で地中連続壁33、地中連続壁55を形成する場合にも、芯材31、芯材31a、芯材53をセグメント29、セグメント29b、セグメント45aと一体化することで、第4の実施の形態と同様に、芯材31、芯材31a、芯材53の位置を固定することができる。
【0086】
次に、第5の実施の形態について説明する。図20は、地中連続壁掘削装置Gで坑30dを掘削する工程を示す図、図21、図22は、地中連続壁掘削装置Gの周方向の断面図である。図20は、図21のY2−Y2による断面図を示す。図21、図22は、それぞれ、図20のX5−X5、X6−X7による断面図を示す。
【0087】
図20に示すように、地中連続壁掘削装置Gは、シールド機3、連壁掘削機9d、形状保持ジャッキ63、圧気区間65等で構成される。シールド機3、連壁掘削機9d、形状保持ジャッキ63、圧気区間65の設置位置や構成は、第4の実施の形態の地中連続壁掘削装置Fのシールド機3、連壁掘削機9c、形状保持ジャッキ63、圧気区間65と同様である。地中連続壁掘削装置Fには、芯材建込み機は設置されない。
【0088】
シールド機3は、筒状の本体の端部に設けられたカッタ6で地山5を掘削し、スクリューコンベア4および排土装置59で掘削土を後方へ送る。連壁掘削機9dは、シールド機3の下方に溝67を掘削してソイルモルタル69を注入する。形状保持ジャッキ63は、シールド機3の本体と開口部64の形状を保持する。圧気区間65内は圧気され、溝67からシールド機3の内部への漏水を防ぐ。中折れ部61は、シールド機3の掘削方向を調整する際に用いられる。
【0089】
次に、地中連続壁掘削装置Gを用いて地中連続壁91を形成する方法について説明する。まず、第1から第4の実施の形態と同様に、地山5中に設けた立坑からシールド機3を発進させて地山5内に坑30dを掘削する。連壁掘削機9dが地中連続壁91の構築予定位置に達するまでは、連壁掘削機9dのカッタ13dは、シールド機3内に格納されている。
【0090】
連壁掘削機9dが地中連続壁91の構築予定位置に達すると、カッタ13dを用いてシールド機3の下方の地山5を垂直に掘削する作業と、油圧モータとカッタ13dとの間に中間カッタブロックを挿入する作業とを繰り返して、カッタ13dを所定の長さまで延長する。そして、図20、図21に示すように、シールド機3の本体の開口64に沿って連壁掘削機9dのカッタ13dを移動させて横引き掘削を行い、溝67aを形成する。
【0091】
このとき、図20から図22に示すように、カッタ13dの位置にある形状保持ジャッキ63bは縮められる。また、他の形状保持ジャッキ63aは伸ばされ、開口64の形状を保持する。
【0092】
カッタ13dを延長した連壁掘削機9dで溝67aを掘削すると同時に、掘削位置にてセメントミルクと掘削土との混合および攪拌を行い、溝67aにソイルモルタル69aを充填する。不要な掘削土は、排土装置17を用いて排出される。ソイルモルタル69aは、ガイド部材62の上端まで充填される。
【0093】
図23は、裏込注入材93を設置した位置でのセグメント89の周方向の断面図を示す。図23は、図20のX7−X7による断面図である。図20、図22に示すように、溝67にソイルモルタル69を充填して地中連続壁91を形成した後、シールド機3に設置されたエレクタ(図示せず)を用いて、シールド機3で掘削した坑30dの内周に沿ってセグメント89を設置する。さらに、坑30dとセグメント89との間のテールボイドに、シールド機3の掘進時に裏込注入材93を注入する。
【0094】
このように、第5の実施の形態では、シールド機3内に連壁掘削機9dを設置することで、地上から開削することなく芯材なしの地中連続壁91を形成できる。また、シールド機3の圧気区間65において、形状保持ジャッキ63を用いて開口64の形状を保持できる。
【0095】
なお、図20に示す地中連続壁掘削装置Gでは、シールド機3の本体の一部を圧気区間65としたが、シールド機3内に圧気室を設置してもよい。地下水位の位置によっては、圧気区間65を設けなくてもよい。
【0096】
次に、第6の実施の形態について説明する。図24は、連壁掘削機9eで溝99を掘削し、安定液101を充填する工程を示す図である。図24に示すように、地中連続壁掘削装置Hは、シールド機3、連壁掘削機9e、芯材建込み機19e、圧気室95、圧気室97等で構成される。
【0097】
連壁掘削機9e、芯材建込み機19eの構成、設置位置は、第1の実施の形態の地中連続壁掘削装置Aの連壁掘削機9、芯材建込み機19と同様である。圧気室95は連壁掘削機9eの周囲に、圧気室97は芯材建込み機19eの周囲に設けられる。
【0098】
シールド機3は、筒状の本体の端部に設けられたカッタ6で地山5を掘削し、スクリューコンベア4および排土装置(図示せず)で掘削土を後方へ送る。連壁掘削機9eは、シールド機3の下方に溝99を掘削して、安定液101やソイルモルタル107を注入する。芯材建込み機19eは、溝99内に芯材103を建込む。圧気室95、圧気室97は、内部が圧気され、連壁掘削機9eで掘削した溝99からシールド機3の内部への漏水を防ぐ。
【0099】
次に、地中連続壁掘削装置Hを用いて地中連続壁105(図25)を形成する方法について説明する。まず、第1から第5の実施の形態と同様に、地山5中に設けた立坑からシールド機3を発進させる。シールド機3は、カッタ6で地山5を掘削し、スクリューコンベア4、排土装置(図示せず)等で掘削土を排出する。連壁掘削機9eが地中連続壁105(図25)の構築予定位置に達するまでは、連壁掘削機9eのカッタ13eは、シールド機3内に格納されている。
【0100】
連壁掘削機9eが地中連続壁105(図25)の構築予定位置に達すると、カッタ13eを用いてシールド機3の下方の地山5を垂直に掘削する作業と、油圧モータとカッタ13eとの間に中間カッタブロックを挿入する作業とを繰り返して、カッタ13eを所定の長さまで延長する。
【0101】
そして、図24に示すように、カッタ13eを延長した連壁掘削機9eで横引き掘削を行って溝99を形成しつつ、溝99内に安定液101を注入する。安定液101は、溝壁の崩壊を防止するためのものである。溝99を掘削した際の掘削土は、排土装置17e等を介して安定液101とともに地上に排出される。シールド機3が泥水シールドの場合は、掘削土の排出にシールド機3の排泥管(図示せず)を用いてもよい。
【0102】
図25は、溝99内に芯材103を建て込んでソイルモルタル107を充填する工程を示す図である。溝99を掘削して安定液101を満たした後、図25に示すように、芯材建込み機19eを用いて溝99内に芯材103を建込む。そして、注入管14eを用いて、溝99内にソイルモルタル107を充填し、地中連続壁105を完成する。
【0103】
第6の実施の形態では、シールド機3の内部に連壁掘削機9eと芯材建込み機19eを設置することで、地上から開削することなく地中連続壁105を形成できる。
【0104】
なお、第6の実施の形態の方法で地中連続壁105を形成する場合にも、第4の実施の形態と同様にして芯材103をセグメント29と一体化することで、芯材103の位置を固定することができる。
【0105】
また、圧気室95、圧気室97の設置位置は、図24、図25に示した位置に限らず、溝99からシールド機3内や坑内への漏水を防げる位置であればよい。地中連続壁105の構築予定位置付近に地下水がなく、シールド機3や坑内への漏水の可能性がない場合は、圧気室95、圧気室97を省略することができる。
【0106】
第1から第5の実施の形態では、溝を掘削しつつ掘削土にセメントミルクを撹拌・混合してソイルモルタルを充填したが、第6の実施の形態と同様に、掘削した溝内に一旦安定液を満たした後、ソイルモルタルを安定液と置き換えて溝内に充填してもよい。
【0107】
第1から第4、第6の実施の形態の地中連続壁33、地中連続壁55、地中連続壁73、地中連続壁105は、1対の地中連続壁の間を掘削して地下構造物を構築する場合の山留め壁などとして用いられる。第5の実施の形態の地中連続壁91は、地下水位75以深でパイプルーフを施工する場合の遮水壁などとして用いられる。
【0108】
【発明の効果】
以上、詳細に説明したように、本発明によれば、地上の制約を受けずに、非開削で短期間に施工できる地中連続壁の構築工法および地中連続壁を提供することができる。
【図面の簡単な説明】
【図1】地中連続壁掘削装置Aを立坑1から発進させる工程を示す図
【図2】所定の深度まで連壁掘削機9のカッタ13を延長する工程を示す図
【図3】連壁掘削機9で溝25を掘削し、ソイルモルタル27を充填する工程を示す図
【図4】溝25内に芯材31を建て込む工程を示す図
【図5】他の構成の地中連続壁掘削装置Bの断面図
【図6】他の構成の地中連続壁掘削装置Cの断面図
【図7】連壁掘削機9で溝25を掘削し、ソイルモルタル27を充填する工程を示す図
【図8】溝25内に芯材31aを建て込む工程を示す図
【図9】セグメント29b付近の拡大図
【図10】地中連続壁掘削装置Eで坑30を掘削する工程を示す図
【図11】連壁掘削機9bで垂直削孔を開始する工程を示す図
【図12】所定の深度まで連壁掘削機9bのカッタ13bを延長する工程を示す図
【図13】溝49内に芯材53を建て込む工程を示す図
【図14】セグメント45aの孔46の一部を閉鎖して圧気室43を移動させる工程を示す図
【図15】地中連続壁掘削装置Fで坑30を掘削する工程を示す図
【図16】地中連続壁掘削装置Fの周方向の断面図
【図17】地中連続壁掘削装置Fの周方向の断面図
【図18】芯材71を建て込んだ位置でのセグメント57の周方向の断面図
【図19】延長用芯材83を設置した位置でのセグメント57の周方向の断面図
【図20】地中連続壁掘削装置Gで坑30を掘削する工程を示す図
【図21】地中連続壁掘削装置Gの周方向の断面図
【図22】地中連続壁掘削装置Gの周方向の断面図
【図23】裏込注入材93を設置した位置でのセグメント89の周方向の断面図
【図24】連壁掘削機9eで溝99を掘削し、安定液101を充填する工程を示す図
【図25】溝99内に芯材103を建て込んでソイルモルタル107を充填する工程を示す図
【符号の説明】
3………シールド機
5………地山
9、9a、9b、9c、9d、9e………連壁掘削機
13、13a、13b、13c、13d、13e………カッタ
15、21、21a、35、43、95、97………圧気室
19、19a、19b、19c、9e………芯材建込み機
25、25a、49、67、67a、99………溝
27、27a、51、69、69a、107………ソイルモルタル
29、29a、29b、45、45a、57、57a、89………セグメント
31、31a、53、71、103………芯材
33、33a、55、73、91、105………地中連続壁
37、46………孔
39………蓋
63、63a、63b………形状保持ジャッキ
65………圧気区間
83………延長用芯材
85………溶接
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to an underground continuous wall construction method and an underground continuous wall.
[0002]
[Prior art]
Conventionally, in order to construct an underground continuous wall, a guide wall is laid on the ground, a trench wall of the required depth is excavated along the guide wall, mixing and stirring of cement milk and embedding of core material I do. Alternatively, a mountain retaining process is performed between a tunnel excavated in the ground and the ground surface to form a water stopping body below the tunnel (for example, see Patent Document 1).
[0003]
[Patent Document 1]
P3027685
[0004]
[Problems to be solved by the invention]
However, when the ground cannot be occupied or when a buried pipe or the like is installed in the ground, it is difficult to excavate the trench wall from the surface of the ground. In addition, when a part of a constructed tunnel is dismantled to form a waterproof body, the dismantling operation is complicated.
[0005]
The present invention has been made in view of such a problem, and an object of the present invention is to provide an underground continuous wall construction method and an underground continuous wall that can be constructed in a short time without excavation without being restricted by the ground. Is to provide walls.
[0006]
[Means for Solving the Problems]
According to a first aspect of the present invention, there is provided a step (a) of digging a tunnel in the ground with a shield machine, and a step (b) of digging a groove below the tunnel to fill the filler. And a step (c) of installing a core material in the trench and a step (d) of installing a segment in the tunnel.
[0007]
In the step (a), a tunnel is excavated in the ground by using a shield machine provided with an underground continuous wall excavator and a core building machine. In the step (b), a trench is excavated below the tunnel using an underground continuous wall excavator, and a filler is filled in the trench. In step (c), a core material is installed in the groove using a core material building machine. In the step (d), the segments are installed in the tunnel using an erector of a shield machine or the like. Further, if necessary, the core material and the segments are integrated.
[0008]
In the step (b), as a filler, for example, soil mortar obtained by mixing and mixing cement milk with excavated soil at the excavation position is filled in the groove. Alternatively, in the step (b), a groove is filled with a stable liquid as a filler, and for example, after the step (c), the stable liquid is replaced with soil mortar.
[0009]
When groundwater exists in the ground where the trench is excavated, a pneumatic chamber is provided around the underground continuous wall excavator and the core building machine. As the underground continuous wall excavator, for example, a chain saw type, an auger type, or the like is used.
[0010]
According to a second aspect of the present invention, a step (a) of excavating a tunnel in the ground with a shield machine, a step (b) of excavating a groove below the tunnel and filling the filler, and installing a segment in the tunnel And a step (d) of installing a core material in the groove.
[0011]
In the step (a), a tunnel is excavated in the ground using a shield machine provided with an underground continuous wall excavator. In the step (b), a trench is excavated below the tunnel using an underground continuous wall excavator, and a filler is filled in the trench. In the step (c), the segments are installed in the tunnel by using an erector of a shield machine or the like. In the step (d), a core material is installed in the groove by using a core material building machine installed behind the shield machine. Further, if necessary, the core material and the segments are integrated.
[0012]
In the step (b), as a filler, for example, soil mortar obtained by mixing and mixing cement milk with excavated soil at the excavation position is filled in the groove. Alternatively, in the step (b), the groove is filled with a stable liquid as a filler, and for example, after the step (d), the stable liquid is replaced with soil mortar.
[0013]
The segment installed in step (c) has a part that can be opened and closed, for example, a hole and a lid. In this case, in step (d), the lid provided on the segment is removed, a core material is passed through the hole to be built into the groove, and then the hole is covered.
[0014]
When groundwater exists in the ground where the trench is excavated, a pneumatic chamber is provided around the underground continuous wall excavator and the core building machine. As the underground continuous wall excavator, for example, a chain saw type, an auger type, or the like is used.
[0015]
According to a third aspect of the present invention, a step (a) of excavating a tunnel in the ground with a shield machine, a step (b) of installing a segment in the tunnel, and a step of excavating a groove below the tunnel to fill the filler. And a step (d) of installing a core material in the groove.
[0016]
In the step (a), a tunnel is excavated in the ground using a shield machine. In the step (b), a segment is installed in the tunnel using an erector of a shield machine or the like. In the step (c), a trench is excavated below the tunnel using an underground continuous wall excavator, and a filler is filled in the trench. In the step (d), a core material is installed in the groove by using a core material building machine installed behind the shield machine. Further, if necessary, the core material and the segments are integrated.
[0017]
The segment installed in step (b) has a part that can be opened and closed, for example, a hole and a lid. In this case, in the step (c), the lid provided on the segment is removed, and the groove is excavated through the hole of the underground continuous wall excavator. Then, in step (d), the core material is passed through the hole and built into the groove, and then the hole is covered.
[0018]
In the step (c), for example, a soil mortar obtained by mixing and mixing cement milk with excavated soil at an excavation position is filled in a groove as a filler. Alternatively, in the step (c), a groove is filled with a stabilizing liquid as a filler, and for example, after the step (d), the stabilizing liquid is replaced with soil mortar and the hole is covered.
[0019]
When groundwater exists in the ground where the trench is excavated, a pneumatic chamber is provided around the underground continuous wall excavator and the core building machine. As the underground continuous wall excavator, for example, a chain saw type, an auger type, or the like is used.
[0020]
According to a fourth aspect of the present invention, a step (a) of excavating a tunnel in the ground with a shield machine, a step (b) of excavating a groove below the tunnel and filling the filler, and installing a segment in the tunnel (C) performing the step of constructing an underground continuous wall.
[0021]
In the step (a), a tunnel is excavated in the ground using a shield machine. In the step (b), a trench is excavated below the tunnel using an underground continuous wall excavator, and a filler is filled in the trench. In the step (c), the segments are installed in the tunnel by using an erector of a shield machine or the like.
[0022]
In the step (b), as a filler, for example, soil mortar obtained by mixing and mixing cement milk with excavated soil at the excavation position is filled in the groove. Alternatively, after filling the groove with a stable liquid as a filler in step (b), the stable liquid is replaced with soil mortar.
A pneumatic chamber is provided around the underground diaphragm excavator as needed. As the underground continuous wall excavator, for example, a chain saw type, an auger type, or the like is used.
[0023]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, a first embodiment of the present invention will be described in detail with reference to the drawings. FIG. 1 is a diagram showing a process of starting the underground continuous wall excavator A from the shaft 1, FIG. 2 is a diagram showing a process of extending the cutter 13 of the wall excavator 9 to a predetermined depth, and FIG. FIG. 4 is a diagram illustrating a process of excavating the groove 25 with the continuous wall excavator 9 and filling the soil mortar 27, and FIG. 4 is a diagram illustrating a process of embedding the core material 31 in the groove 25.
[0024]
As shown in FIGS. 1 to 4, the underground continuous wall excavator A includes a shield machine 3, a continuous wall excavator 9, a pneumatic chamber 15, a core material building machine 19, a pneumatic chamber 21, a material lock 23, and the like. Is done. The wall excavator 9 and the core building machine 19 are provided inside the shield machine 3. The pneumatic chamber 15 is provided around the wall excavator 9, and the pneumatic chamber 21 is provided around the core building machine 19.
[0025]
The shield machine 3 includes a cylindrical main body, a screw conveyor 4, a cutter 6, and the like. The shield machine 3 excavates the ground 5 with the cutter 6 provided at the end of the main body, and sends the excavated soil backward with the screw conveyor 4.
[0026]
The wall excavator 9 includes a hydraulic motor 11, a cutter 13, an injection pipe 14, an earth removal device 17, and the like. The hydraulic motor 11 drives the cutter 13. The cutter 13 excavates the ground 5 below the shield machine 3. As the cutter 13, a chain saw type, auger type or the like is used. The cutter 13 shown in FIG. 1 can be extended to a predetermined depth as shown in FIGS. 2 to 4 by connecting a plurality of cutter blocks.
[0027]
The injection pipe 14 injects cement milk or the like into the groove 25 excavated by the cutter 13. The earth discharging device 17 discharges the earth excavated by the cutter 13 to the outside of the shield machine 3. The continuous wall excavator 9 excavates the groove 25 below the shield machine 3 and fills the groove 25 with a soil mortar 27.
[0028]
The core building machine 19 builds the core 31 in the groove 25. For the core building machine 19, for example, a simple crane or the like is used. The compressed air chamber 15 and the compressed air chamber 21 prevent water leakage from the groove 25 into the shield machine 3.
[0029]
Next, a method of forming the underground continuous wall 33 using the underground continuous wall excavator A will be described. First, as shown in FIG. 1, the shaft 1 is provided in the ground 5, the ground improvement 7 is performed outside the shaft 1 by an appropriate method, and the shield machine 3 is started from the shaft 1. The shield machine 3 moves forward while excavating the ground 5 with the cutter 6 and discharging the excavated soil with the screw conveyor 4 or the like. Until the continuous wall excavator 9 reaches the planned construction position of the underground continuous wall 33 (FIG. 4), the cutter 13 of the continuous wall excavator 9 is stored in the shield machine 3 as shown in FIG.
[0030]
When the continuous wall excavator 9 reaches the construction planned position of the underground continuous wall 33 (FIG. 4), the cutter 13 is driven by the hydraulic motor 11 to remove the ground 5 below the shield machine 3 as shown in FIG. The work of vertically excavating and the work of inserting the intermediate cutter block between the hydraulic motor 11 and the cutter 13 are repeated to extend the cutter 13 to a predetermined length. Then, a pressure chamber 15 having an earth discharging device 17 is attached around the wall excavator 9.
[0031]
Next, as shown in FIG. 3, horizontal excavation is performed by the continuous wall excavator 9 with the cutter 13 extended to form a groove 25. At the same time, cement milk is injected from the injection pipe 14, mixed with the excavated soil and stirred at the original position, and the groove 25 is filled with the soil mortar 27. Unnecessary excavated soil is discharged using the discharging device 17.
[0032]
After excavation of the groove 25 or in parallel with the excavation, the core building machine 19 is installed behind the continuous wall excavator 9 in the shield machine 3. A compressed air chamber 21 is installed around the core material building machine 19, and a material lock 23 is installed behind the compressed air chamber 21.
[0033]
Then, as shown in FIG. 4, before the soil mortar 27 is hardened, the core material 31 is built in the groove 25 by using the core material building machine 19, and the underground continuous wall 33 is completed. After the core material 31 is erected, the segments 29 are installed along the inner periphery of the pit 30 excavated by the shield machine 3 using an erector (not shown) installed in the shield machine 3. For the core material 31, a steel pipe having a rectangular cross section, H steel, or the like is used. The core material 31 has a predetermined length, for example, by adding a plurality of short members.
[0034]
As described above, in the first embodiment, by installing the continuous wall excavator 9 and the core building machine 19 in the shield machine 3, the underground continuous wall 33 can be formed without digging from the ground. At this time, by separating the continuous wall excavator 9 and the core building machine 19, the excavation process of the groove 25 and the embedding process of the core material 31 can be performed separately, and the construction period can be shortened. .
[0035]
In the underground continuous wall excavator A shown in FIGS. 1 to 4, the pneumatic chamber 15 and the pneumatic chamber 21 are installed in the continuous wall excavator 9 and the core building machine 19, respectively. Is not limited to this. The installation position of the pneumatic chamber may be any position as long as it can prevent water leakage from the groove 25 into the shield machine 3 or the mine 30. In some cases, the pneumatic chamber is located at the tunnel entrance 22 (FIG. 3) or the shaft 24 (FIG. 3). A pneumatic chamber may be provided by providing a partition.
[0036]
FIG. 5 is a sectional view of an underground diaphragm excavator B having another configuration. The underground continuous wall excavator B includes a shield machine 3, a continuous wall excavator 9, a core building machine 19, a compressed air chamber 35, and the like. The structures and operations of the shield machine 3, the continuous wall excavator 9, and the core building machine 19 of the underground diaphragm excavator B are the same as those of the underground diaphragm excavator A, but the pneumatic chamber 35 It is installed so as to surround both the wall excavator 9 and the core building machine 19.
[0037]
In the underground continuous wall excavating apparatus B, after excavating the groove 25 with the continuous wall excavator 9 and filling the soil mortar 27, the core material 31 is built into the groove 25 by the core material building machine 19, and the underground continuous The wall 33 is completed. The size of the compressed air chamber 35 is not limited to that shown in FIG. By making the compressed air chamber 35 large enough to allow the continuous wall excavator 9 and the core building machine 19 to move independently, the excavation process of the groove 25 and the core 31 can be performed similarly to the underground continuous wall excavator A. Can be divided and implemented.
[0038]
FIG. 6 shows a sectional view of an underground diaphragm excavator C having another configuration. The underground continuous wall excavator C includes a shield machine 3, a continuous wall excavator 9, a core building machine 19, and the like. The structures and operations of the shield machine 3, the continuous wall excavator 9, and the core building machine 19 of the underground continuous wall excavator C are the same as those of the underground continuous wall excavator A and the underground continuous wall excavator B. However, a pneumatic chamber surrounding the wall excavator 9 and the core building machine 19 is not provided. If there is no groundwater near the planned location of the underground continuous wall 33 and there is no possibility of water leakage into the shield machine 3, the pneumatic chamber can be omitted as in the underground continuous wall excavator C.
[0039]
In the underground continuous wall excavator C, similarly to the underground continuous wall excavator A and the underground continuous wall excavator B, a step of excavating the groove 25 with the continuous wall excavator 9 and filling the soil mortar 27, The step of laying the core material 31 in the groove 25 by the material laying machine 19 can be performed separately to form the underground continuous wall 33.
[0040]
Next, a second embodiment will be described in detail. FIG. 7 is a diagram illustrating a process of excavating the groove 25 with the continuous wall excavator 9a and filling the soil mortar 27, FIG. 8 is a diagram illustrating a process of embedding the core material 31a in the groove 25, and FIG. It is an enlarged view near the segment 29b.
[0041]
As shown in FIGS. 7 and 8, the underground continuous wall excavator D includes a shield machine 3, a continuous wall excavator 9a, a pneumatic chamber 15a, a core material building machine 19a, a pneumatic chamber 21a, a material lock 23a, and the like. Is done.
[0042]
The configurations and installation positions of the shield machine 3a, the continuous wall excavator 9a, and the compressed air chamber 15a of the underground continuous wall excavator D are the same as the shield machine 3, the continuous wall excavator 9, and the compressed air chamber 15 of the underground continuous wall excavator A. The same is true. The continuous wall excavator 9a is provided inside the shield machine 3, and the compressed air chamber 15a is provided around the continuous wall excavator 9a.
[0043]
The shield machine 3 excavates the ground 5 with the cutter 6 provided at the end of the cylindrical main body, and sends the excavated soil backward with the screw conveyor 4. The continuous wall excavator 9a excavates a groove 25a below the shield machine 3, and fills the groove 25a with a soil mortar 27a.
[0044]
The configurations of the core building machine 19a and the pneumatic chamber 21a of the underground continuous wall excavator D are the same as those of the core building machine 19 and the pneumatic chamber 21 of the underground continuous wall excavator A, but the installation positions are different. . The core building machine 19a is provided inside the segment 29a assembled along the inner periphery of the pit 30a behind the shield machine 3, and the compressed air chamber 21a is provided around the core building machine 19a. The core building machine 19a builds the core 31a in the groove 25a, and the compressed air chamber 21a prevents water from leaking from the groove 25a into the pit 30a excavated by the shield machine 3.
[0045]
As shown in FIG. 9, among the segments installed in the pit 30 a excavated by the shield machine 3, the segment 29 b provided above the excavation position of the groove 25 a has a hole 37. The hole 37 is provided at the installation planned position of the core 31a in FIG. In the segment 29b, the hole 37 can be opened and closed by removing and attaching the lid 39.
[0046]
Next, a method of forming the underground continuous wall 33a using the underground continuous wall excavator D will be described. First, the shield machine 3 is started from the shaft 1, and after the continuous wall excavator 9a reaches the construction scheduled position of the underground continuous wall 33a (FIG. 8), the cutter 13a is extended to a predetermined length. Then, a pressure chamber 15a having an earth removal device 17a is attached around the wall excavator 9a. The steps so far are the same as those of the underground continuous wall excavator A of the first embodiment (FIGS. 1 and 2).
[0047]
Next, as shown in FIG. 7, horizontal pulling excavation is performed by the continuous wall excavator 9a with the cutter 13a extended to form a groove 25a. At the same time, cement milk is injected from the injection pipe 14a, mixed with the excavated soil and stirred at the original position, and the groove 25a is filled with the soil mortar 27a. Unnecessary excavated soil is discharged using the discharging device 17a.
[0048]
After the excavation of the groove 25a, the segments 29a and 29b are installed along the inner periphery of the pit 30a using an erector (not shown) installed behind the shield machine 3. At this time, the segment 29a shown in FIG. Then, the core building machine 19a is installed inside the segments 29a and 29b. A compressed air chamber 21a is installed around the core material building machine 19a, and a material lock 23a is installed behind the compressed air chamber 21a.
[0049]
Next, as shown in FIG. 8, before the soil mortar 27a is hardened, the core material 31a is built in the groove 25a using the core material building machine 19a to complete the underground continuous wall 33a.
[0050]
In order to lay the core material 31a, as shown in FIG. 9, the lid 39 of the segment 29b installed above the groove 25a is opened, the core material 31a is passed through the pit 37, and the segment 39b is suspended in the groove 25a. Close. For the core material 31a, a steel pipe having a rectangular cross section, H steel, or the like is used. The core material 31a has a predetermined length, for example, by adding a plurality of short members.
[0051]
As described above, in the second embodiment, the continuous wall excavator 9a is installed in the shield machine 3 and the core material building machine 19a is installed behind the shield machine 3 so that the ground excavation is not performed from the ground. The underground continuous wall 33a can be formed. By separating the continuous wall excavator 9a and the core material building machine 19a, the excavation process of the groove 25a and the embedding process of the core material 31a can be performed separately, and the construction period can be shortened.
[0052]
In the underground continuous wall excavator D shown in FIGS. 7 and 8, the pneumatic chamber 15a and the pneumatic chamber 21a are installed in each of the wall excavator 9a and the core building machine 19a. May be any position as long as it can prevent water leakage from the groove 25a into the shield machine 3 or the pit 30a. If there is no groundwater near the planned construction position of the underground continuous wall 33a and there is no possibility of water leakage into the shield machine 3 or the pit 30a, the pneumatic chamber can be omitted.
[0053]
Next, a third embodiment will be described. FIG. 10 is a diagram illustrating a process of excavating the pit 30b by the underground continuous wall excavator E, and FIG. 11 is a diagram illustrating a process of starting vertical drilling by the continuous wall excavator 9b. As shown in FIGS. 10 and 11, the underground continuous wall excavator E includes a shield machine 3, a continuous wall excavator 9b, a compressed air chamber 43, a core material erection machine 19b, a moving panel 41, and the like.
[0054]
The construction of the shield machine 3, the continuous wall excavator 9b, the core building machine 19b, and the compressed air chamber 43 of the underground continuous wall excavator E is as follows. It is the same as the core building machine 19 and the pneumatic chamber 15. However, the installation positions of the continuous wall excavator 9b, the core building machine 19b, and the compressed air chamber 43 are the installation positions of the continuous wall excavator 9, the core building machine 19, and the compressed air chamber 15 of the underground continuous wall drilling apparatus A. And different.
[0055]
The continuous wall excavator 9b and the core building machine 19b are provided inside the segment 45 assembled along the inner periphery of the pit 30b behind the shield machine 3, and the compressed air chamber 43 includes the continuous wall excavator 9b, It is provided around the core building machine 19b. The wall excavator 9b is attached to a moving panel 41 provided on the segment 45.
[0056]
The shield machine 3 excavates the ground 5 with the cutter 6 provided at the end of the cylindrical main body, and sends the excavated soil backward with the screw conveyor 4. The wall excavator 9b excavates the groove 49 below the pit 30b and fills the soil mortar 51 while moving in the axial direction of the pit 30b along the moving panel 41 (FIG. 13). The core building machine 19b builds the core 53 in the groove 49 (FIG. 13). The compressed air chamber 43 prevents water leakage from the groove 49 into the pit 30b excavated by the shield machine 3.
[0057]
Among the segments 45 installed in the pit 30b excavated by the shield machine 3, the segment 45a provided at the excavation position of the groove 49 is an openable / closable hole for passing the cutter 13b and the core material 53 of the continuous wall excavator 9b. 46 (FIG. 11).
[0058]
Next, a method of forming the underground continuous wall 55 using the underground continuous wall excavator E will be described. First, the shield machine 3 is started from the shaft and the pit 30b is excavated, and the segment 45 is installed at the rear of the shield machine 3 along the inner circumference of the pit 30b. Then, as shown in FIG. 10, the moving panel 41 and the continuous wall excavator 9b are arranged on the segment 45 at the planned construction position of the underground continuous wall 55 (FIG. 13).
[0059]
Then, as shown in FIG. 11, the pneumatic chamber 43 is installed around the moving panel 41 and the continuous wall excavator 9b, and the hole 46 of the segment 45a above the planned construction position of the underground continuous wall 55 (FIG. 13). To release. FIG. 12 is a diagram showing a process of extending the cutter 13b of the wall excavator 9b to a predetermined depth. As shown in FIG. 12, the cutter 13b is driven by the hydraulic motor 11b of the wall excavator 9b to excavate the ground 47 below the hole 46, and the cutter 13b is extended to a predetermined length.
[0060]
FIG. 13 is a diagram illustrating a process of setting the core material 53 in the groove 49. As shown in FIG. 13, a horizontal pulling excavator 9 b extending the cutter 13 b performs horizontal pulling excavation to form a groove 49. At the same time, cement milk is injected from the injection pipe 14b, mixed with the excavated soil and stirred at the original position, and the groove 49 is filled with the soil mortar 51. Unnecessary excavated soil is discharged using a discharging device (not shown).
[0061]
After excavation of the groove 49, the core material 53 is built in the groove 49 using the core building machine 19b before the soil mortar 51 is hardened. As the core material 53, a steel pipe having a rectangular cross section, H steel, or the like is used. The core material 53 has a predetermined length, for example, by adding a plurality of short members.
[0062]
FIG. 14 is a diagram illustrating a process of moving the compressed air chamber 43 by closing a part of the hole 46 of the segment 45a. After the core material 53 is installed, as shown in FIG. 14, the hole 46 of the segment 45a installed above the groove 49 in which the core material 53 is installed is closed. Then, the moving panel 41 and the compressed air chamber 43 are moved.
[0063]
The step of mixing and stirring the soil mortar 51 while excavating the groove 49, the step of embedding the core material 53 in the groove 49, and the step of closing the hole 46 of the segment 45a and moving the air chamber 43 are repeated. Then, the underground continuous wall 55 is completed.
[0064]
As described above, in the third embodiment, by installing the continuous wall excavator 9b and the core building machine 19b behind the shield machine 3, the underground continuous wall 55 can be formed without digging from the ground. .
[0065]
The installation position of the compressed air chamber may be any position as long as it can prevent water leakage from the groove 49 into the shield machine 3 or the pit 30b. When there is no underground water near the planned construction position of the underground continuous wall 55 and there is no possibility of water leakage into the shield machine 3 or the pit 30b, the pneumatic chamber 43 can be omitted.
[0066]
Next, a fourth embodiment will be described. FIG. 15 is a view showing a step of excavating the pit 30c by the underground diaphragm excavator F. FIGS. 16 and 17 are sectional views of the underground diaphragm excavator F in the circumferential direction. FIG. 15 is a sectional view taken along line Y1-Y1 of FIG. 16 and 17 are cross-sectional views taken along lines X1-X1 and X2-X2 of FIG. 15, respectively.
[0067]
As shown in FIG. 15, the underground continuous wall excavator F includes a shield machine 3, a continuous wall excavator 9c, a core building machine 19c, a shape retaining jack 63, a compressed air section 65, and the like. The configurations of the continuous wall excavator 9c and the core building machine 19c are the same as those of the continuous wall excavator 9 and the core building machine 19 of the underground continuous wall drilling apparatus A of the first embodiment.
[0068]
The air pressure section 65 is provided in a part of the main body of the shield machine 3 as shown in FIG. As in the pneumatic chamber 15 and the pneumatic chamber 21 of the first embodiment, the pneumatic section 65 is pressurized inside to prevent water leakage from the groove 67 excavated by the continuous wall excavator 9c into the shield machine 3. The wall excavator 9c and the core building machine 19c are installed in the compressed air section 65.
[0069]
As shown in FIGS. 16 and 17, in the compressed air section 65, an opening 64 is provided in a part of the cylindrical main body of the shield machine 3. At the end 60 of the opening 64 of the main body of the shield machine 3, a guide member 62 is provided inside.
[0070]
The wall excavator 9c is installed so that the cutter 13c can move along the guide member 62 of the opening 64. The continuous wall excavator 9c excavates the groove 67 below the shield machine 3 and injects soil mortar 69. The core building machine 19c is installed so that the core 71 can be built from the opening 64 while moving in the compressed air section 65. The core building machine 19c builds the core 71 in the groove 67.
[0071]
The shape maintaining jack 63 is installed between the guide member 62 and the main body of the shield machine 3. The plurality of shape holding jacks 63 can control expansion and contraction independently. The shape holding jack 63 holds the shape of the main body of the shield machine 3 and the shape of the opening 64.
[0072]
The shield machine 3 excavates the ground 5 with the cutter 6 provided at the end of the cylindrical main body, and sends the excavated soil backward with the screw conveyor 4 and the earth discharging device 59. The shield machine 3 can adjust the excavation direction using the bent part 61 installed in the compressed air section 65.
[0073]
Next, a method of forming the underground continuous wall 73 using the underground continuous wall excavator F will be described. First, as in the first to third embodiments, the shield machine 3 is started from the shaft provided in the ground 5. The shield machine 3 excavates the ground 5 with the cutter 6, and discharges the excavated soil with the screw conveyor 4, the earth discharging device 59, and the like. The cutter 13c of the continuous wall excavator 9c is stored in the shield machine 3 until the continuous wall excavator 9c reaches the construction planned position of the underground continuous wall 73.
[0074]
When the continuous wall excavator 9c reaches the position where the underground continuous wall 73 is to be constructed, the cutter 13c is used to excavate the ground 5 below the shield machine 3 vertically, and between the hydraulic motor and the cutter 13c. The operation of inserting the intermediate cutter block is repeated to extend the cutter 13c to a predetermined length.
[0075]
Then, as shown in FIG. 15, the cutter 13c of the continuous wall excavator 9c is moved along the opening 64 of the main body of the shield machine 3 to perform horizontal pulling excavation to form a groove 67a. At this time, as shown in FIGS. 15 to 17, the shape holding jack 63b at the position of the cutter 13c is contracted. Further, the other shape holding jack 63a is extended to hold the shape of the opening 64.
[0076]
The wall excavator 9c excavates the groove 67a with the extended cutter 13c, mixes and agitates the cement milk and the excavated soil at the excavation position, and fills the groove 67a with soil mortar 69a. Unnecessary excavated soil is discharged using the discharging device 17. The soil mortar 69a is filled up to the lower end of the shape holding jack 63.
[0077]
After or in parallel with the excavation of the groove 67a, the core material 71 is built into the groove 67a using the core material building machine 19c before the soil mortar 69a is hardened. After the core material 71 is erected, the segments 57 are installed along the inner periphery of the pit 30c excavated by the shield machine 3 using an erector (not shown) installed in the shield machine 3. For the core material 71, a steel pipe having a rectangular cross section, H steel, or the like is used. The core 71 has a predetermined length, for example, by adding a plurality of short members. The position of the upper end of the core 71 is the position of the lower end of the shape holding jack 63 shown in FIG.
[0078]
FIG. 18 is a circumferential sectional view of the segment 57 at a position where the core material 71 is erected, and FIG. 19 is a circumferential sectional view of the segment 57 at a position where the extension core material 83 is installed. 18 and 19 are cross-sectional views taken along lines X3-X3 and X4-X4 of FIG. 15, respectively.
[0079]
As shown in FIG. 15, after the core material 71 is erected, the segments 57 are installed along the inner periphery of the pit 30 c excavated by the shield machine 3. As shown in FIG. 18, the segment 57 is arranged so as to bypass the core 71. The segment 57a disposed above the core 71 has a lid 70 that can be opened and closed.
[0080]
Next, as shown in FIG. 19, a water stop iron plate 81 is installed between the vicinity of the upper end of the core material 71 and the segment 57. Then, the extension core 83 is passed through the hole of the segment 57 a from which the lid 70 is removed, and the extension core 83 is fixed to the upper end of the core 71 by welding 85.
[0081]
Further, a back filling material 79 is injected into the tail void 77 between the pit 30c excavated by the shield machine 3 and the segment 57 when the shield machine 3 excavates. Further, the soil mortar 69 around the weld 85 between the core 71 and the extension core 83 is removed. The extension core 83 is welded to the upper ends of all the cores 71 to integrate the core 71 and the segments 57 a to complete the underground continuous wall 73.
[0082]
As described above, in the fourth embodiment, by installing the continuous wall excavator 9 and the core building machine 19c in the shield machine 3, the underground continuous wall 73 can be formed without cutting from the ground. At this time, by separating the wall excavator 9 and the core building machine 19c, the excavation process of the groove 67 and the embedding process of the core material 71 can be performed separately, and the construction period can be shortened. .
[0083]
Further, in the compressed air section 65 of the shield machine 3, the excavation of the groove 67 and the embedding of the core 71 can be performed while maintaining the shape of the opening 64 by extending the shape holding jack 63. Further, the position of the core 71 can be fixed by welding the extension core 83 to the core 71 of the underground continuous wall 73 and integrating it with the segment 57a.
[0084]
In the underground continuous wall excavator F shown in FIG. 15, a part of the main body of the shield machine 3 is the compressed air section 65, but a compressed air chamber may be installed in the shield machine 3. Depending on the position of the groundwater level 75, the compressed air section 65 may not be provided.
[0085]
Also, when the underground continuous wall 33 and the underground continuous wall 55 are formed by the method of the first to third embodiments, the core material 31, the core material 31a, and the core material 53 are formed by the segments 29, 29b, By integrating with the segment 45a, the position of the core material 31, the core material 31a, and the core material 53 can be fixed similarly to the fourth embodiment.
[0086]
Next, a fifth embodiment will be described. FIG. 20 is a view showing a step of excavating the pit 30d by the underground continuous wall excavator G, and FIGS. 21 and 22 are sectional views of the underground continuous wall excavator G in the circumferential direction. FIG. 20 is a sectional view taken along line Y2-Y2 of FIG. 21 and 22 are cross-sectional views taken along lines X5-X5 and X6-X7 of FIG. 20, respectively.
[0087]
As shown in FIG. 20, the underground continuous wall excavator G includes a shield machine 3, a continuous wall excavator 9d, a shape maintaining jack 63, a compressed air section 65, and the like. The installation position and configuration of the shield machine 3, the continuous wall excavator 9d, the shape maintaining jack 63, and the compressed air section 65 are the same as the shield machine 3, the continuous wall excavator 9c, and the underground continuous wall excavator F of the fourth embodiment. This is the same as the shape holding jack 63 and the compressed air section 65. The underground diaphragm excavator F is not provided with a core building machine.
[0088]
The shield machine 3 excavates the ground 5 with the cutter 6 provided at the end of the cylindrical main body, and sends the excavated soil backward with the screw conveyor 4 and the earth discharging device 59. The continuous wall excavator 9d excavates the groove 67 below the shield machine 3 and injects soil mortar 69. The shape holding jack 63 holds the shape of the main body of the shield machine 3 and the shape of the opening 64. The inside of the pressurized section 65 is pressurized to prevent water leakage from the groove 67 into the shield machine 3. The center bent part 61 is used when adjusting the excavation direction of the shield machine 3.
[0089]
Next, a method of forming the underground continuous wall 91 using the underground continuous wall excavator G will be described. First, similarly to the first to fourth embodiments, the shield machine 3 is started from the shaft provided in the ground 5 to excavate the pit 30 d in the ground 5. The cutter 13d of the continuous wall excavator 9d is stored in the shield machine 3 until the continuous wall excavator 9d reaches the construction planned position of the underground continuous wall 91.
[0090]
When the continuous wall excavator 9d reaches the construction planned position of the underground continuous wall 91, the work of vertically excavating the ground 5 below the shield machine 3 using the cutter 13d is performed between the hydraulic motor and the cutter 13d. The operation of inserting the intermediate cutter block is repeated to extend the cutter 13d to a predetermined length. Then, as shown in FIGS. 20 and 21, the cutter 13d of the continuous wall excavator 9d is moved along the opening 64 of the main body of the shield machine 3 to perform horizontal pulling excavation to form the groove 67a.
[0091]
At this time, as shown in FIGS. 20 to 22, the shape holding jack 63b at the position of the cutter 13d is contracted. Further, the other shape holding jack 63a is extended to hold the shape of the opening 64.
[0092]
At the same time as excavating the groove 67a with the continuous wall excavator 9d having the cutter 13d extended, mixing and stirring of the cement milk and excavated soil are performed at the excavation position, and the groove 67a is filled with soil mortar 69a. Unnecessary excavated soil is discharged using the discharging device 17. The soil mortar 69a is filled up to the upper end of the guide member 62.
[0093]
FIG. 23 shows a sectional view of the segment 89 in the circumferential direction at the position where the back filling material 93 is installed. FIG. 23 is a sectional view taken along line X7-X7 of FIG. As shown in FIGS. 20 and 22, after filling the groove 67 with soil mortar 69 to form an underground continuous wall 91, the shield machine 3 is mounted on the shield machine 3 using an erector (not shown). A segment 89 is installed along the inner circumference of the pit 30d excavated in the above. Further, a back filling material 93 is injected into the tail void between the pit 30d and the segment 89 when the shield machine 3 excavates.
[0094]
As described above, in the fifth embodiment, by installing the continuous wall excavator 9d in the shield machine 3, the underground continuous wall 91 without a core material can be formed without digging from the ground. Further, in the compressed air section 65 of the shield machine 3, the shape of the opening 64 can be held by using the shape holding jack 63.
[0095]
In the underground continuous wall excavator G shown in FIG. 20, a part of the main body of the shield machine 3 is the compressed air section 65, but a compressed air chamber may be installed in the shield machine 3. Depending on the position of the groundwater level, the compressed air section 65 may not be provided.
[0096]
Next, a sixth embodiment will be described. FIG. 24 is a diagram showing a process of excavating the groove 99 with the wall excavator 9e and filling the stable liquid 101. As shown in FIG. 24, the underground continuous wall excavator H includes a shield machine 3, a continuous wall excavator 9e, a core building machine 19e, a pneumatic chamber 95, a pneumatic chamber 97, and the like.
[0097]
The configurations and installation positions of the continuous wall excavator 9e and the core builder 19e are the same as those of the continuous wall excavator 9 and the core builder 19 of the underground continuous wall excavator A of the first embodiment. . The pneumatic chamber 95 is provided around the continuous wall excavator 9e, and the pneumatic chamber 97 is provided around the core building machine 19e.
[0098]
The shield machine 3 excavates the ground 5 with the cutter 6 provided at the end of the cylindrical main body, and sends the excavated soil rearward with the screw conveyor 4 and the earth discharging device (not shown). The continuous wall excavator 9e excavates the groove 99 below the shield machine 3, and injects the stabilizing liquid 101 and the soil mortar 107. The core building machine 19e builds the core 103 in the groove 99. The inside of the compressed air chamber 95 and the compressed air chamber 97 is pressurized to prevent water leakage from the groove 99 excavated by the continuous wall excavator 9e to the inside of the shield machine 3.
[0099]
Next, a method of forming the underground continuous wall 105 (FIG. 25) using the underground continuous wall excavator H will be described. First, similarly to the first to fifth embodiments, the shield machine 3 is started from the shaft provided in the ground 5. The shield machine 3 excavates the ground 5 with the cutter 6 and discharges the excavated soil with the screw conveyor 4, an earth removal device (not shown), or the like. The cutter 13e of the wall excavator 9e is stored in the shield machine 3 until the wall excavator 9e reaches the construction planned position of the underground continuous wall 105 (FIG. 25).
[0100]
When the continuous wall excavator 9e reaches the planned construction position of the underground continuous wall 105 (FIG. 25), the cutter 13e is used to vertically excavate the ground 5 below the shield machine 3, and the hydraulic motor and the cutter 13e are used. And the operation of inserting the intermediate cutter block between them is repeated to extend the cutter 13e to a predetermined length.
[0101]
Then, as shown in FIG. 24, the stable liquid 101 is injected into the groove 99 while forming the groove 99 by performing horizontal pulling excavation with the continuous wall excavator 9 e having the cutter 13 e extended. The stabilizing liquid 101 is for preventing collapse of the groove wall. Excavated soil when excavating the groove 99 is discharged to the ground together with the stabilizing liquid 101 via the earth discharging device 17e and the like. When the shield machine 3 is a mud shield, a mud pipe (not shown) of the shield machine 3 may be used for discharging excavated soil.
[0102]
FIG. 25 is a view showing a process of filling the core mortar 103 in the groove 99 and filling the soil mortar 107. After excavating the groove 99 and filling it with the stable liquid 101, the core material 103 is built in the groove 99 by using a core material building machine 19e as shown in FIG. Then, the groove 99 is filled with the soil mortar 107 using the injection pipe 14e to complete the underground continuous wall 105.
[0103]
In the sixth embodiment, the underground continuous wall 105 can be formed without digging from the ground by installing the continuous wall excavator 9e and the core building machine 19e inside the shield machine 3.
[0104]
When the underground continuous wall 105 is formed by the method of the sixth embodiment, the core material 103 is integrated with the segment 29 in the same manner as in the fourth embodiment, so that the The position can be fixed.
[0105]
Further, the installation positions of the compressed air chamber 95 and the compressed air chamber 97 are not limited to the positions shown in FIGS. 24 and 25, and may be any position that can prevent water leakage from the groove 99 into the shield machine 3 or the mine. If there is no groundwater near the planned location of the underground continuous wall 105 and there is no possibility of water leaking into the shield machine 3 or the mine, the pneumatic chamber 95 and the pneumatic chamber 97 can be omitted.
[0106]
In the first to fifth embodiments, the soil mortar is filled by stirring and mixing the excavated soil with the cement milk while excavating the trench. However, similar to the sixth embodiment, the soil mortar is once filled in the excavated trench. After filling the stabilizer, the soil mortar may be replaced with the stabilizer and filled in the groove.
[0107]
The underground continuous wall 33, the underground continuous wall 55, the underground continuous wall 73, and the underground continuous wall 105 of the first to fourth and sixth embodiments excavate between a pair of underground continuous walls. It is used as a retaining wall when constructing underground structures. The underground continuous wall 91 according to the fifth embodiment is used as a water impervious wall when a pipe roof is constructed at a groundwater level of 75 or less.
[0108]
【The invention's effect】
As described above in detail, according to the present invention, it is possible to provide an underground continuous wall construction method and an underground continuous wall that can be constructed in a short period without cutting without being restricted by the ground.
[Brief description of the drawings]
FIG. 1 is a diagram showing a process of starting an underground diaphragm excavator A from a shaft 1.
FIG. 2 is a diagram showing a process of extending a cutter 13 of the wall excavator 9 to a predetermined depth.
FIG. 3 is a view showing a process of excavating a groove 25 by a wall excavator 9 and filling a soil mortar 27;
FIG. 4 is a view showing a process of setting a core material 31 in a groove 25;
FIG. 5 is a sectional view of an underground diaphragm excavator B having another configuration.
FIG. 6 is a sectional view of an underground continuous wall excavator C having another configuration.
FIG. 7 is a view showing a process of excavating a groove 25 by the wall excavator 9 and filling a soil mortar 27;
FIG. 8 is a view showing a step of setting a core material 31a in a groove 25;
FIG. 9 is an enlarged view of the vicinity of a segment 29b.
FIG. 10 is a diagram showing a process of excavating the pit 30 by the underground diaphragm excavator E;
FIG. 11 is a diagram showing a process of starting vertical drilling with the wall excavator 9b.
FIG. 12 is a diagram showing a process of extending a cutter 13b of the wall excavator 9b to a predetermined depth.
FIG. 13 is a view showing a step of setting a core material 53 in a groove 49;
FIG. 14 is a view showing a step of closing a part of a hole 46 of a segment 45a and moving a pneumatic chamber 43;
FIG. 15 is a diagram showing a process of excavating the pit 30 with the underground diaphragm excavator F;
FIG. 16 is a sectional view in the circumferential direction of the underground diaphragm excavator F;
FIG. 17 is a sectional view in the circumferential direction of the underground diaphragm excavator F;
FIG. 18 is a cross-sectional view in the circumferential direction of the segment 57 at a position where the core material 71 is erected.
FIG. 19 is a cross-sectional view in the circumferential direction of the segment 57 at a position where the extension core member 83 is installed.
FIG. 20 is a diagram showing a process of excavating the pit 30 with the underground diaphragm excavator G;
FIG. 21 is a cross-sectional view of the underground diaphragm excavator G in the circumferential direction.
FIG. 22 is a cross-sectional view of the underground diaphragm excavator G in the circumferential direction.
FIG. 23 is a circumferential cross-sectional view of the segment 89 at a position where the back filling material 93 is installed.
FIG. 24 is a diagram showing a step of excavating a groove 99 with a wall excavator 9e and filling a stabilizing liquid 101;
FIG. 25 is a view showing a step of burying a core material 103 in a groove 99 and filling a soil mortar 107;
[Explanation of symbols]
3. Shielding machine
5 ...
9, 9a, 9b, 9c, 9d, 9e ........... wall excavator
13, 13a, 13b, 13c, 13d, 13e ... cutter
15, 21, 21a, 35, 43, 95, 97 ... Compressed air chamber
19, 19a, 19b, 19c, 9e ... core material building machine
25, 25a, 49, 67, 67a, 99 ... groove
27, 27a, 51, 69, 69a, 107 ... soil mortar
29, 29a, 29b, 45, 45a, 57, 57a, 89 ... segment
31, 31a, 53, 71, 103 ... core material
33, 33a, 55, 73, 91, 105: Underground diaphragm wall
37, 46 ... holes
39 .... Lid
63, 63a, 63b ... shape holding jack
65 ... Pressure section
83 ............ Extension core material
85 ……… Welding

Claims (26)

シールド機で地盤内に坑道を掘削する工程(a)と、
前記坑道の下方に溝を掘削して充填材を充填する工程(b)と、
前記溝内に芯材を設置する工程(c)と、
前記坑道内にセグメントを設置する工程(d)と、
を具備することを特徴とする地中連続壁の構築方法。
Excavating a tunnel in the ground with a shield machine (a);
Excavating a trench below the tunnel and filling with filler material;
(C) installing a core material in the groove;
(D) installing a segment in the tunnel.
A method for constructing an underground continuous wall, comprising:
前記芯材を前記セグメントと一体化する工程(e)をさらに具備することを特徴とする請求項1記載の地中連続壁の構築方法。The method according to claim 1, further comprising the step (e) of integrating the core with the segment. 地中連続壁掘削機と芯材建込み機が前記シールド機内に設置されることを特徴とする請求項1記載の地中連続壁の構築方法。The underground continuous wall construction method according to claim 1, wherein an underground continuous wall excavator and a core building machine are installed in the shield machine. 前記地中連続壁掘削機および前記芯材建込み機の周囲に圧気室が設けられることを特徴とする請求項3記載の地中連続壁の構築方法。The method according to claim 3, wherein a pneumatic chamber is provided around the underground excavator and the core building machine. 前記充填材はソイルモルタルであることを特徴とする請求項1記載の地中連続壁の構築方法。The method according to claim 1, wherein the filler is a soil mortar. 前記充填材は安定液であり、前記安定液をソイルモルタルに置き換える工程(f)をさらに具備することを特徴とする請求項1記載の地中連続壁の構築方法。The method according to claim 1, wherein the filler is a stabilizing liquid, and the method further comprises the step (f) of replacing the stabilizing liquid with soil mortar. シールド機で地盤内に坑道を掘削する工程(a)と、
前記坑道の下方に溝を掘削して充填材を充填する工程(b)と、
前記坑道内にセグメントを設置する工程(c)と、
前記溝内に芯材を設置する工程(d)と、
を具備することを特徴とする地中連続壁の構築方法。
Excavating a tunnel in the ground with a shield machine (a);
Excavating a trench below the tunnel and filling with filler material;
(C) installing a segment in the tunnel;
(D) installing a core material in the groove;
A method for constructing an underground continuous wall, comprising:
前記芯材を前記セグメントと一体化する工程(e)をさらに具備することを特徴とする請求項7記載の地中連続壁の構築方法。The method according to claim 7, further comprising a step (e) of integrating the core with the segment. 前記セグメントは開閉可能な部分を有することを特徴とする請求項7記載の地中連続壁の構築方法。The method according to claim 7, wherein the segment has a part that can be opened and closed. 地中連続壁掘削機が前記シールド機内に設置され、芯材建込み機が前記シールド機の後方に設置されることを特徴とする請求項7記載の地中連続壁の構築方法。The method of constructing an underground continuous wall according to claim 7, wherein an underground continuous wall excavator is installed in the shield machine, and a core building machine is installed behind the shield machine. 前記地中連続壁掘削機および前記芯材建込み機の周囲に圧気室が設けられることを特徴とする請求項10記載の地中連続壁の構築方法。The method of constructing an underground continuous wall according to claim 10, wherein a pneumatic chamber is provided around the underground continuous wall excavator and the core building machine. 前記充填材はソイルモルタルであることを特徴とする請求項7記載の地中連続壁の構築方法。The method according to claim 7, wherein the filler is a soil mortar. 前記充填材は安定液であり、前記安定液をソイルモルタルに置き換える工程(f)をさらに具備することを特徴とする請求項7記載の地中連続壁の構築方法。The method for constructing an underground continuous wall according to claim 7, wherein the filler is a stable liquid, and the method further comprises a step (f) of replacing the stable liquid with soil mortar. シールド機で地盤内に坑道を掘削する工程(a)と、
前記坑道内にセグメントを設置する工程(b)と、
前記坑道の下方に溝を掘削して充填材を充填する工程(c)と、
前記溝内に芯材を設置する工程(d)と、
を具備することを特徴とする地中連続壁の構築方法。
Excavating a tunnel in the ground with a shield machine (a);
Installing a segment in the tunnel (b);
(C) excavating a trench below the tunnel and filling with filler material;
(D) installing a core material in the groove;
A method for constructing an underground continuous wall, comprising:
前記芯材を前記セグメントと一体化する工程(e)をさらに具備することを特徴とする請求項14記載の地中連続壁の構築方法。The method according to claim 14, further comprising a step (e) of integrating the core with the segment. 前記セグメントは開閉可能な部分を有することを特徴とする請求項14記載の地中連続壁の構築方法。The method according to claim 14, wherein the segment has a part that can be opened and closed. 地中連続壁掘削機と芯材建込み機が前記シールド機の後方に設置されることを特徴とする請求項14記載の地中連続壁の構築方法。The method of constructing an underground diaphragm wall according to claim 14, wherein an underground diaphragm wall excavator and a core building machine are installed behind the shield machine. 前記地中連続壁掘削機および前記芯材建込み機の周囲に圧気室が設けられることを特徴とする請求項17記載の地中連続壁の構築方法。18. The method of constructing an underground diaphragm wall according to claim 17, wherein a pneumatic chamber is provided around the underground diaphragm wall excavator and the core building machine. 前記充填材はソイルモルタルであることを特徴とする請求項14記載の地中連続壁の構築方法。The method according to claim 14, wherein the filler is a soil mortar. 前記充填材は安定液であり、前記安定液をソイルモルタルに置き換える工程(f)をさらに具備することを特徴とする請求項14記載の地中連続壁の構築方法。The method according to claim 14, wherein the filler is a stable liquid, and the method further comprises the step (f) of replacing the stable liquid with soil mortar. シールド機で地盤内に坑道を掘削する工程(a)と、
前記坑道の下方に溝を掘削して充填材を充填する工程(b)と、
前記坑道内にセグメントを設置する工程(c)と、
を具備することを特徴とする地中連続壁の構築方法。
Excavating a tunnel in the ground with a shield machine (a);
Excavating a trench below the tunnel and filling with filler material;
(C) installing a segment in the tunnel;
A method for constructing an underground continuous wall, comprising:
地中連続壁掘削機が前記シールド機内に設置されることを特徴とする請求項21記載の地中連続壁の構築方法。The method according to claim 21, wherein an underground continuous wall excavator is installed in the shield machine. 前記地中連続壁掘削機の周囲に圧気室が設けられることを特徴とする請求項21記載の地中連続壁の構築方法。22. The method according to claim 21, wherein a pneumatic chamber is provided around the underground excavator. 前記充填材はソイルモルタルであることを特徴とする請求項21記載の地中連続壁の構築方法。22. The method according to claim 21, wherein the filler is a soil mortar. 前記充填材は安定液であり、前記安定液をソイルモルタルに置き換える工程(d)をさらに具備することを特徴とする請求項21記載の地中連続壁の構築方法。22. The method according to claim 21, further comprising a step (d) in which the filler is a stabilizing liquid and replacing the stabilizing liquid with soil mortar. 請求項1から請求項25のいずれかに記載された地中連続壁の構築方法により構築されたことを特徴とする地中連続壁。An underground continuous wall constructed by the underground continuous wall construction method according to any one of claims 1 to 25.
JP2002308033A 2002-10-23 2002-10-23 Construction method of underground continuous wall and underground continuous wall Expired - Fee Related JP4180347B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002308033A JP4180347B2 (en) 2002-10-23 2002-10-23 Construction method of underground continuous wall and underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002308033A JP4180347B2 (en) 2002-10-23 2002-10-23 Construction method of underground continuous wall and underground continuous wall

Publications (2)

Publication Number Publication Date
JP2004143744A true JP2004143744A (en) 2004-05-20
JP4180347B2 JP4180347B2 (en) 2008-11-12

Family

ID=32454286

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002308033A Expired - Fee Related JP4180347B2 (en) 2002-10-23 2002-10-23 Construction method of underground continuous wall and underground continuous wall

Country Status (1)

Country Link
JP (1) JP4180347B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007170095A (en) * 2005-12-26 2007-07-05 Taisei Corp Construction method of underground structure, and jacking machine
CN107964941A (en) * 2017-12-26 2018-04-27 中建三局集团有限公司 A kind of synchronous cutting casting concrete continuous walls construction equipment and its construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007170095A (en) * 2005-12-26 2007-07-05 Taisei Corp Construction method of underground structure, and jacking machine
JP4705467B2 (en) * 2005-12-26 2011-06-22 大成建設株式会社 Construction method of underground structure
CN107964941A (en) * 2017-12-26 2018-04-27 中建三局集团有限公司 A kind of synchronous cutting casting concrete continuous walls construction equipment and its construction method

Also Published As

Publication number Publication date
JP4180347B2 (en) 2008-11-12

Similar Documents

Publication Publication Date Title
JP6661448B2 (en) Construction method of underground diaphragm wall
KR102248187B1 (en) Cast-in-place pile using reinforced grouting and construction method
JP4180347B2 (en) Construction method of underground continuous wall and underground continuous wall
JP3948655B2 (en) Construction method of retaining wall and underground structure
JPH07331998A (en) Constructing method of rock cavern
KR0179326B1 (en) Construction method of continuous continuous wall by steel support box
JPH03257215A (en) Pile constructing method
JP2874906B2 (en) Shaft construction method
JP2016008377A (en) Rectangular cross-section propulsion method
JPH04309692A (en) Underground space construction method
JPH06341140A (en) Construction method by which column-wall holes are bored within approximate line by 10-700mm from boundary by intermittent work and continuous wall, connection wall, butt-joint wall, superposed wall, and cut-off wall are erected by use of the hole, and these walls
JP2693028B2 (en) Construction method of human hole in middle of pipeline
JPS62206119A (en) Construction of continuous cut-off wall
JPH0823266B2 (en) Construction method of underground space
JP2024092472A (en) Method of entering an open shield machine into a vertical shaft in an open shield construction method and a vertical shaft of an open shield machine
JP3113982B2 (en) Tunnel construction method on soft ground
JPH10205280A (en) Tunnel construction method
JP3146375B2 (en) Existing structure retention method
KR101711393B1 (en) A method of construction for retaining wall
JP2000178983A (en) Foundation construction method
JP2000110158A (en) Retaining wall construction method using oblique wall
JP2002339691A (en) Earth retaining equipment and open-cut construction method using this equipment
KR200316681Y1 (en) The expanding tunnel and constructing method of the existing tunnel
JP3113981B2 (en) Tunnel construction method
JPH04231593A (en) Method of constructing base of deeper depth vertical shaft constructed with vertical type shield machine

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050627

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070528

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080603

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080730

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080826

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080827

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110905

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140905

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees