JPH11141740A - Method for transferring existing piping in cut and cover tunnel making work - Google Patents

Method for transferring existing piping in cut and cover tunnel making work

Info

Publication number
JPH11141740A
JPH11141740A JP9306090A JP30609097A JPH11141740A JP H11141740 A JPH11141740 A JP H11141740A JP 9306090 A JP9306090 A JP 9306090A JP 30609097 A JP30609097 A JP 30609097A JP H11141740 A JPH11141740 A JP H11141740A
Authority
JP
Japan
Prior art keywords
lining
tunnel
pit
pipe
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP9306090A
Other languages
Japanese (ja)
Inventor
Kanae Sawada
叶 澤田
Hirokatsu Ono
裕克 小野
Tatsuya Ikeda
龍也 池田
Kenji Kishi
研司 岸
Masaaki Yano
正明 矢野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP9306090A priority Critical patent/JPH11141740A/en
Publication of JPH11141740A publication Critical patent/JPH11141740A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Supports For Pipes And Cables (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve a working efficiency by loading and unloading a pipe body without stopping the construction work of a tunnel and increasing the length of the pipe body to be loaded or unloaded. SOLUTION: Bearing frames 22 are provided at prescribed intervals along through beams 11 below a lining beam 2 provided in the lining pit 1 of a drilled tunnel. The bearing frame 22 comprises column members 20 and a horizontal member 21 and is formed so as to surround an existing piping 13. Above the horizontal member 21, a pair of rails 23 are laid along the entire range of the lining pit 1 in the axial direction of the tunnel. A working carriage 24 is mounted on the rails 23 so as to travel in the lining pit 1. When the existing piping 13 is moved, a pipe body 13b to be removed from the piping 13 is removed and mounted on the working carriage 24 and conveyed to a material loading and unloading pit. Further, a pipe body to be newly provided is conveyed to a moving position from the pit by the working carriage 24. Thus, it is not necessary to build a working scaffold for each moving position, so that the construction work of the tunnel is not interrupted.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は開削トンネル工事に
於ける既設配管移設方法に関するものであり、特に、覆
工坑内の通し桁に吊りボルトを介して垂設された既設配
管の移設方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for relocating existing pipes in open-cut tunnel construction, and more particularly, to a method for relocating existing pipes suspended from a girder in a lining pit via suspension bolts. It is.

【0002】[0002]

【従来の技術】図4は開削トンネルの覆工坑内1を示
し、覆工坑内1の最上部にトンネルの軸方向(紙面の前
後方向)と直交して覆工桁2を所定間隔で設置し、該覆
工桁2の上部に覆工板3を蓋装してトンネルの天井開口
部を被蔽してある。前記覆工桁2は、土留め壁4或いは
既設構造部5の上部に設けた支持柱6によって支持さ
れ、水平方向には支保梁7,8が架設されている。
2. Description of the Related Art FIG. 4 shows an inside of a lining pit 1 of an open-cut tunnel. A lining plate 3 is provided on the upper part of the lining girder 2 to cover the opening of the ceiling of the tunnel. The lining girder 2 is supported by a retaining wall 4 or a supporting column 6 provided above the existing structure 5, and supporting beams 7 and 8 are erected in the horizontal direction.

【0003】前記覆工坑内1の下方部には地下2階部分
9の構築が進行しており、その上部に二点鎖線で示すよ
うに地下1階部分10が構築される。また、前記覆工桁
2の下部にトンネルの軸方向へ覆工坑内1の全線に亙っ
て複数の通し桁11を平行に設け、該通し桁11の所々
に吊りボルト12を垂設して水道や電気等の配管13を
支持している。
[0003] The construction of the second basement section 9 is progressing below the inside of the lining pit 1, and the first basement section 10 is constructed above the underground section 1 as shown by a two-dot chain line. Further, a plurality of continuous girders 11 are provided in parallel with the entire line of the inside of the lining pit 1 in the axial direction of the tunnel below the lining girder 2, and hanging bolts 12 are vertically installed at places of the girder 11. The pipe 13 for water supply, electricity, etc. is supported.

【0004】ここで、何らかの都合で前記配管13を移
設しようとする場合は、例えば図5に示すように、支保
梁8に作業用足場14を組み立てて配管13を部分的に
切断できるようにする。続いて、図6に示すように撤去
部分上方の覆工板3aを取り外してトンネルの天井部を
一部開放し、部分的に切断された撤去すべき管体13a
をクレーン15により吊り上げる。更に、前記配管13
の他の部分に於いても上記作業を繰り返し、既設の配管
13を順次撤去していく。
If the pipe 13 is to be relocated for any reason, as shown in FIG. 5, for example, a work scaffold 14 is assembled on the support beam 8 so that the pipe 13 can be partially cut. . Subsequently, as shown in FIG. 6, the lining plate 3a above the removed portion is removed to partially open the ceiling of the tunnel, and the partially cut pipe 13a to be removed.
Is lifted by the crane 15. Further, the pipe 13
The above operation is repeated in other parts of the above, and the existing pipes 13 are sequentially removed.

【0005】新たに敷設する配管については、上記とは
逆の手順で作業を行う。即ち、覆工板を部分的に開放し
て新設すべき管体を地上から搬入し、作業用足場で新設
管体を接続する。そして、この作業を順次繰り返して新
設配管の敷設作業を行う。
[0005] For a pipe to be newly laid, work is performed in the reverse order of the above. That is, the lining plate is partially opened, a pipe to be newly installed is carried in from the ground, and the new pipe is connected to the work scaffold. This operation is sequentially repeated to lay a new pipe.

【0006】[0006]

【発明が解決しようとする課題】従来、開削トンネル工
事に於いて既設の配管を移設する場合は、前述したよう
に先ず覆工坑内に作業用足場を組み立てる必要があり、
一定期間はトンネルの構築作業を中断しなければならな
い。また、撤去部分毎にその都度、上方の覆工板の撤去
及び設置の作業を繰り返すため作業効率が悪い。
Conventionally, when relocating an existing pipe in an open-cut tunnel construction, it is necessary to first assemble a work scaffold in a lining pit as described above.
The construction of the tunnel must be suspended for a certain period. In addition, the operation of removing and installing the upper lining plate is repeated for each removal portion, and the work efficiency is low.

【0007】また、覆工桁の間隔によって撤去すべき管
体の切断長が決定されるので、工事現場の状況によって
は切断長を短くせざるをえない場合があり、然るときは
切断箇所が増加して作業が煩雑になる。同様に、新設す
べき管体についても長さが制限され、定尺寸法(6m)
の管体が搬入できないという不具合があった。
Further, since the cutting length of the pipe to be removed is determined by the spacing of the lining girder, the cutting length may have to be shortened depending on the situation at the construction site. And the work becomes complicated. Similarly, the length of the pipe to be newly installed is also limited, and the standard size (6 m)
There was a problem that the tube could not be carried.

【0008】そこで、開削トンネルの覆工坑内に既設さ
れている配管を移設するに際して、トンネルの構築作業
を休止することなく管体の撤去及び搬入が行えるととも
に、撤去または搬入すべき管体の長さを長くして作業効
率を向上させるために解決すべき技術的課題が生じてく
るのであり、本発明はこの課題を解決することを目的と
する。
Therefore, when relocating the existing pipes in the lining pit of the excavation tunnel, the pipes can be removed and carried in without stopping the construction work of the tunnel, and the length of the pipes to be removed or carried in is reduced. There is a technical problem to be solved in order to increase the working efficiency and improve the working efficiency, and the present invention aims to solve this problem.

【0009】[0009]

【課題を解決するための手段】本発明は上記目的を達成
するために提案されたものであり、覆工坑内の最上部に
トンネルの軸方向と直交して覆工桁を所定間隔で設置
し、該覆工桁の上部に覆工板を蓋装してトンネルの天井
開口部を被蔽した開削トンネルであって、前記覆工桁の
下部にトンネルの軸方向へ覆工坑内全線に亙って複数の
通し桁を平行に設け、該通し桁の所々に吊りボルトを垂
設して配管を支持した開削トンネルに於いて、前記覆工
桁の下部であって且つ複数の通し桁の両側位置に、夫々
柱部材を垂設してその下端部を前記既設の配管の下方ま
で延設し、双方の柱部材の下端部を水平部材で連結して
前記配管を囲繞するように受け架台を形成し、該受け架
台の水平部材上部にトンネルの軸方向へ覆工坑内全線に
亙ってレールを敷設し、このレール上に作業台車を設置
して覆工坑内を走行可能にし、前記既設の配管を移設す
る際には、撤去すべき管体を前記作業台車にて構築範囲
外に設けられたピットまで搬送し、ピット上方の覆工板
を開放して撤去管体を地上へ搬出するとともに、新設す
べき管体を地上からピットへ搬入し、該新設管体を前記
作業台車にて移設箇所へ搬送する開削トンネル工事に於
ける既設配管移設方法を提供するものである。
DISCLOSURE OF THE INVENTION The present invention has been proposed to achieve the above-mentioned object, and lining girders are installed at predetermined intervals at the top of a lining pit at right angles to the axial direction of a tunnel. An open-cut tunnel in which a lining plate is covered on an upper part of the lining girder to cover an opening of a ceiling of the tunnel, and a lower part of the lining girder extends in the axial direction of the tunnel over the entire line in the lining mine. In an open-cut tunnel in which a plurality of continuous girders are provided in parallel and hanging bolts are suspended from places of the serial girders to support pipes, the lower part of the lining girder and both side positions of the plural serial girders In each, a pillar member is vertically provided, and a lower end thereof is extended below the existing pipe, and a lower frame of both pillar members is connected by a horizontal member to form a receiving stand so as to surround the pipe. Then, a rail is laid over the entire horizontal line in the lining mine in the axial direction of the tunnel above the horizontal member of the receiving base. A work cart is installed on this rail to enable travel in the lining mine, and when the existing piping is relocated, the pipe to be removed is moved to the pit provided outside the construction range by the work cart. Conveying, opening the lining plate above the pit, unloading the removed pipe to the ground, bringing in the pipe to be newly installed from the ground to the pit, and transporting the newly installed pipe to the relocation location using the work vehicle The purpose of the present invention is to provide a method of relocating existing pipes in open tunnel construction.

【0010】[0010]

【発明の実施の形態】以下、本発明の実施の形態を図面
に従って詳述する。尚、説明の都合上、従来と同一構成
部分には同一符号を付してその説明を省略する。図1及
び図2に示すように、開削トンネルの覆工坑内1には、
通し桁11の所々に吊りボルト12を垂設して水道や電
気等の配管13が支持されている。
Embodiments of the present invention will be described below in detail with reference to the drawings. For convenience of explanation, the same reference numerals are given to the same components as in the related art, and the description thereof will be omitted. As shown in FIGS. 1 and 2, in the lining pit 1 of the open tunnel,
Hanging bolts 12 are suspended from places of the continuous girder 11 to support pipes 13 for water supply, electricity, and the like.

【0011】また、覆工桁2の下部であって且つ複数の
通し桁11,11の両側位置に、夫々柱部材20,20
を垂設して前記既設の配管13の下方まで延設するとと
もに、双方の柱部材20,20の下端部を水平部材21
で連結し、前記配管13を囲繞するように受け架台22
を形成する。該受け架台22は、通し桁11に沿って所
定の間隔で連続的に設置される。
[0011] Also, at the lower portion of the lining beam 2 and on both sides of the plurality of continuous beams 11, 11, pillar members 20, 20 are provided, respectively.
And extend below the existing pipe 13, and lower end portions of both pillar members 20, 20 are connected to a horizontal member 21.
And the receiving stand 22 surrounds the pipe 13.
To form The receiving gantry 22 is installed continuously at predetermined intervals along the girder 11.

【0012】更に、該受け架台22の水平部材21の上
部に、トンネルの軸方向へ覆工坑内1の全線に亙って一
対のレール23を敷設する。そして、このレール23上
に作業台車24を載置して覆工坑内1を走行できるよう
にする。尚、該作業台車24は電動モータの駆動で自走
可能に形成されているが、駆動源を持たない手押し型の
作業台車であってもよい。
Further, a pair of rails 23 is laid on the horizontal member 21 of the receiving stand 22 over the entire line of the inside of the lining 1 in the axial direction of the tunnel. Then, the work cart 24 is placed on the rail 23 so as to be able to travel in the lining pit 1. Note that the work cart 24 is formed so as to be able to run on its own by driving an electric motor, but may be a push-type work cart having no drive source.

【0013】而して、前記既設の配管13を移設する際
には、撤去部分に前記作業台車24を移動し、配管13
から撤去すべき管体13bを取り外して作業台車24に
載置する。このとき、管体13bを安定して搬送するた
めに2台の作業台車24,24を使用する。
When the existing pipe 13 is to be relocated, the work carriage 24 is moved to the removed portion and the pipe 13 is moved.
The pipe 13b to be removed from the container is removed and placed on the work cart 24. At this time, two work carts 24, 24 are used to stably transport the tube 13b.

【0014】ここで、開削トンネルの覆工坑内1には、
図3に示すように構築範囲外に資材搬出入用のピット2
5が設けられており、前記作業台車24がレール23上
を走行して、撤去すべき管体13bをピット25まで搬
送する。該ピット25の上方は、所定範囲だけ覆工板3
を開放してあり、前記撤去すべき管体13bをクレーン
15により吊り上げて地上へ搬出する。更に、前記配管
13の他の部分に於いても上記作業を繰り返し、既設の
配管13を順次撤去してピット25から地上へ搬出して
いく。
Here, in the lining pit 1 of the open tunnel,
As shown in FIG. 3, a pit 2 for loading and unloading materials outside the construction area
The work carriage 24 travels on the rails 23 and conveys the pipe 13b to be removed to the pit 25. Above the pits 25, the lining plate 3
Is opened, and the pipe 13b to be removed is lifted by the crane 15 and carried out to the ground. Further, the above-described operation is repeated in other portions of the pipes 13, and the existing pipes 13 are sequentially removed and carried out from the pit 25 to the ground.

【0015】一方、新たに敷設する配管については、上
記とは逆の手順で作業を行う。即ち、新設すべき管体を
クレーン15により地上からピット25の内部に搬入
し、前記作業台車24に載置する。そして、2台の作業
台車24,24がレール23上を走行し、新設すべき管
体を覆工坑内1の移設箇所へ搬送する。
On the other hand, for a pipe to be newly laid, work is performed in the reverse order of the above. That is, the pipe to be newly installed is carried into the pit 25 from the ground by the crane 15 and placed on the work cart 24. Then, the two work vehicles 24, 24 run on the rails 23, and transport the pipe to be newly installed to the relocation location in the lining 1.

【0016】このように、既設の配管13の移設に当た
って、撤去すべき管体13bあるいは新設すべき管体を
作業台車24に載置し、移設箇所とピット25との間を
該作業台車24によって搬送するため、撤去部分毎にそ
の都度、上方の覆工板の撤去及び設置の作業を繰り返す
ことがなくなるとともに、トンネルの構築作業を中断せ
ずに、配管13の移設を行うことができる。また、ピッ
ト25の天井開放部分は広く開放されているので、撤去
または搬入すべき管体の長さが定尺寸法(6m)であっ
ても、ピット25へ搬出入することができ、移設作業の
効率が向上する。
As described above, when the existing pipe 13 is relocated, the pipe 13b to be removed or the pipe to be newly installed is placed on the work vehicle 24, and the space between the relocation location and the pit 25 is moved by the work vehicle 24. Since the transportation is carried out, the removal and installation of the upper lining plate is not repeated every time the removal is performed, and the pipe 13 can be relocated without interrupting the construction of the tunnel. In addition, since the open-to-ceiling portion of the pit 25 is widely open, even if the length of the pipe to be removed or carried in is a fixed size (6 m), the pit 25 can be carried in and out of the pit 25, and the relocation work can be performed. Efficiency is improved.

【0017】尚、本発明は、本発明の精神を逸脱しない
限り種々の改変を為すことができ、そして、本発明が該
改変されたものに及ぶことは当然である。
The present invention can be variously modified without departing from the spirit of the present invention, and it goes without saying that the present invention extends to the modified ones.

【0018】[0018]

【発明の効果】以上説明したように、本発明では既設の
配管を移設する際に、管体の撤去或いは新設箇所とは別
の位置に管体を搬出入するピットを設け、撤去或いは新
設すべき管体を作業台車によって搬送するため、移設箇
所毎に作業用足場を構築する必要がなくなって、トンネ
ルの構築作業を中断することがない。
As described above, according to the present invention, when relocating an existing pipe, a pit for carrying in and out the pipe is provided at a position different from the removal or the newly installed pipe, and the pipe is removed or newly installed. Since the pipes to be transported are transported by the work cart, there is no need to construct a work scaffold for each relocation location, and the construction work of the tunnel is not interrupted.

【0019】また、管体の搬出入のためにその都度、上
方の覆工板を開放する必要がなく、覆工板の開閉作業が
減少するとともに、撤去または搬入すべき管体の長さを
長くできるので、撤去時に於ける既設配管の切断箇所並
びに新設時に於ける管体の接続箇所が減少する。
Further, it is not necessary to open the upper lining plate every time the pipe is carried in and out, so that the opening and closing work of the lining plate is reduced and the length of the pipe to be removed or carried in is reduced. Since it can be lengthened, the number of cuts of existing pipes at the time of removal and the number of pipes connected at the time of new construction are reduced.

【0020】斯くして、開削トンネルに於いて、既設配
管を移設する際の作業効率が著しく向上する。
Thus, in the open tunnel, the work efficiency when relocating the existing pipe is remarkably improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態を示し、開削トンネルの覆
工坑内の縦断正面図。
FIG. 1 shows an embodiment of the present invention and is a longitudinal sectional front view of a lining pit of an open-cut tunnel.

【図2】本発明の実施の形態を示し、開削トンネルの覆
工坑内の縦断側面図。
FIG. 2 shows the embodiment of the present invention and is a longitudinal side view inside a lining pit of an open-cut tunnel.

【図3】本発明の実施の形態を示し、ピットの縦断側面
図。
FIG. 3 shows the embodiment of the present invention and is a longitudinal sectional side view of a pit.

【図4】従来技術を示し、開削トンネルの覆工坑内の縦
断正面図。
FIG. 4 is a longitudinal sectional front view of a lining pit of an open-cut tunnel showing a conventional technique.

【図5】従来技術を示し、作業用足場を構築した覆工坑
内の縦断正面図。
FIG. 5 is a longitudinal sectional front view of a lining mine in which a working scaffold is constructed, showing a conventional technique.

【図6】従来技術を示し、撤去部分上方の覆工板を取り
外した覆工坑内の縦断側面図。
FIG. 6 is a longitudinal sectional side view of a lining pit in which a lining plate above a removed portion is removed, showing a conventional technique.

【符号の説明】[Explanation of symbols]

1 覆工坑内 2 覆工桁 3 覆工板 11 通し桁 12 吊りボルト 13 配管 13b 撤去すべき管体 20 柱部材 21 水平部材 22 受け架台 23 レール 24 作業台車 25 ピット DESCRIPTION OF SYMBOLS 1 In a lining pit 2 Lining girder 3 Lining plate 11 Through girder 12 Hanging bolt 13 Piping 13b Pipe to be removed 20 Column member 21 Horizontal member 22 Receiving stand 23 Rail 24 Work cart 25 Pit

───────────────────────────────────────────────────── フロントページの続き (72)発明者 岸 研司 大阪府大阪市都島区片町2丁目10番5号 株式会社熊谷組大阪支店内 (72)発明者 矢野 正明 大阪府大阪市都島区片町2丁目10番5号 株式会社熊谷組大阪支店内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Kenji Kishi 2-10-5 Katamachi, Miyakojima-ku, Osaka City, Osaka Inside the Kumagaya Gumi Osaka Branch (72) Inventor Masaaki Yano 2-chome Katamachi, Miyakojima-ku, Osaka, Osaka 10th-5th Kumagaya Gumi Osaka Branch

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 覆工坑内の最上部にトンネルの軸方向と
直交して覆工桁を所定間隔で設置し、該覆工桁の上部に
覆工板を蓋装してトンネルの天井開口部を被蔽した開削
トンネルであって、前記覆工桁の下部にトンネルの軸方
向へ覆工坑内全線に亙って複数の通し桁を平行に設け、
該通し桁の所々に吊りボルトを垂設して配管を支持した
開削トンネルに於いて、前記覆工桁の下部であって且つ
複数の通し桁の両側位置に、夫々柱部材を垂設してその
下端部を前記既設の配管の下方まで延設し、双方の柱部
材の下端部を水平部材で連結して前記配管を囲繞するよ
うに受け架台を形成し、該受け架台の水平部材上部にト
ンネルの軸方向へ覆工坑内全線に亙ってレールを敷設
し、このレール上に作業台車を設置して覆工坑内を走行
可能にし、前記既設の配管を移設する際には、撤去すべ
き管体を前記作業台車にて構築範囲外に設けられたピッ
トまで搬送し、ピット上方の覆工板を開放して撤去管体
を地上へ搬出するとともに、新設すべき管体を地上から
ピットへ搬入し、該新設管体を前記作業台車にて移設箇
所へ搬送することを特徴とする開削トンネル工事に於け
る既設配管移設方法。
1. A lining girder is provided at a predetermined interval at an uppermost portion in a lining pit at right angles to an axial direction of a tunnel, and a lining plate is covered on an upper part of the lining girder to open a ceiling opening of the tunnel. An open-cut tunnel covered with a plurality of girder parallel to the lower part of the lining girder in the axial direction of the tunnel over the entire line in the lining mine,
In an open-cut tunnel that supports hanging pipes by suspending suspension bolts at locations of the girder, pillar members are respectively suspended at a lower portion of the lining girder and on both sides of a plurality of girders. The lower end thereof is extended to below the existing pipe, and the lower ends of the two column members are connected by a horizontal member to form a receiving rack so as to surround the pipe. A rail is laid in the axial direction of the tunnel over the entire line of the lining, and a work vehicle is installed on the rail to enable traveling in the lining, and when the existing piping is relocated, it must be removed. The pipe is transported to the pit provided outside the construction area by the above-mentioned work vehicle, the lining plate above the pit is opened, the removed pipe is carried out to the ground, and the pipe to be newly constructed is transferred from the ground to the pit. And transporting the new pipe to the relocation site using the work cart. In existing piping transfer method to excavation tunnel construction to butterflies.
JP9306090A 1997-11-07 1997-11-07 Method for transferring existing piping in cut and cover tunnel making work Withdrawn JPH11141740A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9306090A JPH11141740A (en) 1997-11-07 1997-11-07 Method for transferring existing piping in cut and cover tunnel making work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9306090A JPH11141740A (en) 1997-11-07 1997-11-07 Method for transferring existing piping in cut and cover tunnel making work

Publications (1)

Publication Number Publication Date
JPH11141740A true JPH11141740A (en) 1999-05-28

Family

ID=17952917

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9306090A Withdrawn JPH11141740A (en) 1997-11-07 1997-11-07 Method for transferring existing piping in cut and cover tunnel making work

Country Status (1)

Country Link
JP (1) JPH11141740A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010048398A (en) * 2008-08-25 2010-03-04 Kurita Water Ind Ltd Piping unit and connection structure of the same
JP2014009734A (en) * 2012-06-28 2014-01-20 Takasago Thermal Eng Co Ltd Replacement method of pipeline
JP5583832B1 (en) * 2013-09-30 2014-09-03 東芝プラントシステム株式会社 Tube support device, tube connection method and tube connection post-treatment method
CN105508732A (en) * 2015-12-24 2016-04-20 广船国际有限公司 Pipeline rack
CN108532740A (en) * 2018-04-24 2018-09-14 上海市隧道工程轨道交通设计研究院 Standby pipe structure cavity configuration and its application process are hung under a kind of upper cover building
CN109797776A (en) * 2019-01-10 2019-05-24 浙江交工集团股份有限公司 Underground pipe gallery based on cut and cover method meets the construction method of cross pipeline
CN113666260A (en) * 2021-09-02 2021-11-19 中国水利水电第三工程局有限公司 Method for dismounting and mounting pressure steel pipe under complex terrain condition
WO2023098074A1 (en) * 2021-12-03 2023-06-08 河北地质大学 Underground utility tunnel bearing damping capacity enhanced anti-seismic system

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010048398A (en) * 2008-08-25 2010-03-04 Kurita Water Ind Ltd Piping unit and connection structure of the same
JP2014009734A (en) * 2012-06-28 2014-01-20 Takasago Thermal Eng Co Ltd Replacement method of pipeline
JP5583832B1 (en) * 2013-09-30 2014-09-03 東芝プラントシステム株式会社 Tube support device, tube connection method and tube connection post-treatment method
CN105508732A (en) * 2015-12-24 2016-04-20 广船国际有限公司 Pipeline rack
CN108532740A (en) * 2018-04-24 2018-09-14 上海市隧道工程轨道交通设计研究院 Standby pipe structure cavity configuration and its application process are hung under a kind of upper cover building
CN109797776A (en) * 2019-01-10 2019-05-24 浙江交工集团股份有限公司 Underground pipe gallery based on cut and cover method meets the construction method of cross pipeline
CN109797776B (en) * 2019-01-10 2020-08-18 浙江交工集团股份有限公司 Construction method for underground pipe gallery to meet cross pipeline based on open cut method
CN113666260A (en) * 2021-09-02 2021-11-19 中国水利水电第三工程局有限公司 Method for dismounting and mounting pressure steel pipe under complex terrain condition
CN113666260B (en) * 2021-09-02 2023-10-31 中国水利水电第三工程局有限公司 Method for dismantling and installing pressure steel pipe under complex terrain condition
WO2023098074A1 (en) * 2021-12-03 2023-06-08 河北地质大学 Underground utility tunnel bearing damping capacity enhanced anti-seismic system

Similar Documents

Publication Publication Date Title
CN103726421A (en) Height and span adjustable track paver for metro construction
JP2012046877A (en) Construction apparatus and construction method of tunnel
JPH11141740A (en) Method for transferring existing piping in cut and cover tunnel making work
JP6283979B2 (en) Method and system for removing ceiling in tunnel
JPH08170486A (en) Tunnel excavated muck carry-out gantry
JP2013104196A (en) Tunnel execution device and tunnel construction method
CN110282557A (en) Assist mounting platform and the method with high vacant duct in bridge crane installation workshop
JP2019173435A (en) Floor system replacement method and floor system replacement device
CN111472783B (en) Shield tunneling machine split initial lengthened pipeline extending device and application method
JP3067939B2 (en) Telher
CN113216990A (en) Starting and rapid slag discharging method in limited space of shield tunneling machine
CN210418998U (en) Conveying device for large-diameter pipeline of circulating water system
JP3466007B2 (en) Underground transport truck and underground transport method
JP3897514B2 (en) How to load a segment
JP4057763B2 (en) Segment supply method when laying gas pipes
JPH10316365A (en) Installation structure for heavy object conveying crane in pit
JP2007231560A (en) Equipment and method for conveying segment
JP2020122359A (en) Floor slab erection system, additional floor slab installation method, and floor slab removing method
CN114622920B (en) Lateral split starting construction method for shield machine in narrow space
JP2567560B2 (en) Bridge construction method using precast girders
JP3031535B2 (en) Conveyed object transfer device for shield excavation
JP6719110B1 (en) Underground structure transportation device and underground structure transportation method in excavation method
CN216841788U (en) Escape pipeline positioning and detachable moving device
JPH09195230A (en) Construction method of reinforcing existing bridge floor system
JP4009038B2 (en) Rail laying method and apparatus in pipeline

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050201