CN114622920B - Lateral split starting construction method for shield machine in narrow space - Google Patents
Lateral split starting construction method for shield machine in narrow space Download PDFInfo
- Publication number
- CN114622920B CN114622920B CN202210104247.2A CN202210104247A CN114622920B CN 114622920 B CN114622920 B CN 114622920B CN 202210104247 A CN202210104247 A CN 202210104247A CN 114622920 B CN114622920 B CN 114622920B
- Authority
- CN
- China
- Prior art keywords
- shield
- translation
- trolley
- machine
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明提供了一种狭小空间盾构机侧向分体始发施工方法,包括如下步骤:始发竖井选址,竖井横通道施工,横通道内平移准备,盾构机进场及吊装,电瓶车组吊装与平移,台车、设备桥吊装与平移,螺旋机、拼装机、反力架吊装与平移,盾体吊装与平移,盾构始发;其中,各设备的平移过程采用卷扬机、平移小车、钢轨的配合形式进行。本发明提出的始发施工方式跟普通始发方式有较大区别,可有效解决异形、非正线车站盾构始发难题,主要体现在:(1)可灵活设置盾构始发井位置,规避因车站盾构始发井方案不稳定而造成的盾构区间无法始发问题,加快工程推进;(1)提高施工效率高;(2)减少施工费用;(3)适用于狭小空间;(4)保证了安全生产。
The invention provides a construction method for lateral splitting of a shield machine in a narrow space, which includes the following steps: site selection of a starting shaft, construction of a vertical shaft cross passage, preparation for translation in the cross passage, entry and hoisting of the shield machine, and battery car Group hoisting and translation, trolley, equipment bridge hoisting and translation, screw machine, assembly machine, reaction force frame hoisting and translation, shield body hoisting and translation, shield starting; among them, the translation process of each equipment adopts hoisting machines and translation trolleys , The matching form of the rail is carried out. The originating construction method proposed by the present invention is quite different from the ordinary originating method, and can effectively solve the problem of shield tunneling at stations with special shapes and non-main lines. It is mainly reflected in: (1) The location of the shield tunnel can be flexibly set, Avoid the problem of inability to start the shield section caused by the unstable scheme of the shield tunnel launch shaft at the station, and speed up the progress of the project; (1) Improve construction efficiency; (2) Reduce construction costs; (3) Applicable to narrow spaces; ( 4) Safe production is guaranteed.
Description
技术领域technical field
本发明涉及隧道挖掘施工技术领域,尤其涉及一种狭小空间盾构机侧向分体始发施工方法。The invention relates to the technical field of tunnel excavation construction, in particular to a construction method for lateral splitting of a shield machine in a narrow space.
背景技术Background technique
随着城市的不断发展,地铁已经成为国内许多城市主要的出行方式之一。目前我国的城市地铁隧道施工中,盾构法因其开挖安全、施工速度快、对环境影响小、自动化程度高等优势,日臻成为城市轨道交通施工的首选方法。盾构法施工主要技术为始发、掘进、到达等几个方面,其中,盾构始发环节是盾构施工的一个关键环节,也是难点之一。盾构始发位置一般是在已建好的车站结构内或单独设置始发井,盾构始发的线路与隧道设计中心线方向保持一致,地铁线路位于道路红线内,大多数车站位于城市主干道下方。然而,在城市人口密集、周围建构筑物及社会交通繁忙地区修建地铁,受制于前期拆迁及交通导改因素,无法采用传统的盾构始发方法,并不具备盾构正常施工条件。With the continuous development of the city, the subway has become one of the main modes of travel in many cities in China. At present, in the construction of urban subway tunnels in my country, the shield tunneling method is increasingly becoming the preferred method for urban rail transit construction due to its advantages of safe excavation, fast construction speed, low impact on the environment, and high degree of automation. The main techniques of shield tunneling construction include several aspects such as starting, excavation, and reaching. Among them, the starting link of shield tunneling is a key link in shield tunneling construction, and it is also one of the difficulties. The starting position of shield tunneling is generally in the already built station structure or setting up the launching shaft separately. The starting line of shield tunneling is consistent with the direction of the center line of tunnel design. The subway line is located within the red line of the road, and most stations are located in the urban backbone. down the road. However, the construction of subways in areas with dense urban population, surrounding buildings and heavy social traffic is subject to the factors of demolition and traffic guidance in the early stage, and the traditional shield starting method cannot be used, and the normal construction conditions of shield tunneling cannot be used.
针对一些异形、非正线类型盾构始发施工,目前采用侧向分体始发施工方法,但现有方法在电瓶车、台车、盾构等的平移过程,多采用“滑轮运移”与“大型电动转盘旋转转向”相结合的方式进行,该方式不仅施工时间长、施工成本高,且由于采用了大型电动转盘这样的大型机械,致使场地要求高,无法用于狭小空间。For some special-shaped and non-normal shield tunneling constructions, the lateral splitting construction method is currently used, but the existing methods mostly use "pulley movement" and The combination of "large-scale electric turntable rotation and steering" is carried out. This method not only takes a long time for construction and high construction cost, but also requires a large site due to the use of large machinery such as a large electric turntable, which cannot be used in small spaces.
据此,目前急需设计出一种施工效率高、施工费用少,且适用于狭小空间的盾构机侧向分体始发施工方法。Accordingly, there is an urgent need to design a laterally split starting construction method of the shield machine that has high construction efficiency, low construction cost, and is suitable for narrow spaces.
发明内容Contents of the invention
本发明所要解决的技术问题在于提供一种施工效率高、施工费用少,且可狭小空间的盾构机侧向分体始发施工方法。The technical problem to be solved by the present invention is to provide a shield machine laterally split-starting construction method with high construction efficiency, low construction cost, and small space.
本发明采用以下技术方案解决上述技术问题:The present invention adopts the following technical solutions to solve the above-mentioned technical problems:
一种狭小空间盾构机侧向分体始发施工方法,包括如下步骤:A lateral split starting construction method of a shield machine in a narrow space, comprising the following steps:
S1、准备工作:S1. Preparation work:
①始发竖井选址:①Site selection for the originating shaft:
选址不受位置和空间拘束,但需满足以下要求:Site selection is not restricted by location and space, but the following requirements must be met:
1)始发竖井尺寸需满足吊装要求,防止无法吊装盾构机;1) The size of the starting shaft must meet the hoisting requirements to prevent the shield machine from being unable to be hoisted;
2)横通道净空需满足盾构机平移要求,盾体+始发架高度需小于横通道净空;2) The clearance of the cross passage must meet the translation requirements of the shield machine, and the height of the shield body + starting frame must be less than the clearance of the cross passage;
3)平移需提前进行模拟,防止平移受阻;3) The translation needs to be simulated in advance to prevent the translation from being blocked;
②竖井及横通道施工:②Construction of shafts and cross passages:
竖井及横通道施工需注意二衬施工强度需达到要求,地面需标高一致无明显凹凸位置,尽量不使用爆破施工,方便之后盾构平移施工;In the construction of vertical shafts and cross passages, it is necessary to pay attention to the construction strength of the second lining to meet the requirements, and the ground must be at the same elevation without obvious unevenness. Try not to use blasting construction, so as to facilitate the translational construction of the shield afterwards;
③横通道内平移准备工作:③Preparation for translation in the horizontal channel:
在横通道底板上铺设平移钢板,在区间铺设钢轨;其中,平移钢板用于后续电瓶车组与台车平移时安放轨道,或者,盾体平移时抹放黄油;钢轨直接用于后续电瓶车组与台车的区间平移;Lay translational steel plates on the bottom plate of the cross channel, and lay steel rails in the interval; among them, the translational steel plates are used to place the track when the subsequent battery car group and the trolley are translated, or to spread butter when the shield body is translated; the steel rails are directly used for the subsequent battery car group and the platform. Interval translation of the car;
S2、盾构机进场及吊装:S2. Shield machine approach and hoisting:
准备吊装场地,盾构吊装机械及盾构机进场;Prepare the hoisting site, and the shield hoisting machinery and shield machine enter the site;
S3、电瓶车组吊装与平移:S3. Hoisting and translation of the battery pack:
(1)电瓶机车吊装下井;(1) The battery locomotive is hoisted into the well;
(2)设置两台卷扬机,分别与两台平移小车连接;同时,在横通道的平移钢板上铺设垂直区间线路方向的电瓶车轨与台车轨,并在电瓶车轨上放置两台平移小车,两辆小车之间工字钢连接,小车上再铺设一层钢板,钢板上放置平行于区间线路方向的两条轨道,电瓶车放置于轨道上;(2) Set up two winches, which are respectively connected with two translation trolleys; at the same time, lay battery rails and trolley rails in the direction of the vertical section line on the translation steel plate of the transverse channel, and place two translation trolleys on the battery rails, two Two trolleys are connected by I-beams, and a layer of steel plate is laid on the trolley, and two tracks parallel to the direction of the section line are placed on the steel plate, and the battery car is placed on the track;
(3)使用卷扬机将载有电瓶车的平移小车平行拉入横通道至右线位置处,然后电瓶车行驶入区间小里程方向,到达指定位置;(3) Use the hoist to pull the translation trolley carrying the battery car parallel into the cross passage to the position on the right line, and then drive the battery car into the direction of the small mileage in the section to reach the designated position;
(4)将一辆浆车以同样方式运送到指定位置,并接入到电瓶车后;(4) Transport a paddle car to the designated location in the same way, and connect it to the battery car;
S4、台车、设备桥吊装与平移:S4, trolley, equipment bridge hoisting and translation:
(1)台车吊装下井;(1) The trolley is hoisted into the well;
(2)若台车为可拆卸台车,采用电瓶车的平移方式将其移至指定位置;若台车为不可拆卸台车,则采用斜向平移方式进行移动;其中,斜向平移方式为:横向平移过程与电瓶车方式相同,但在其平移至线路中线位置后,利用电瓶车拖拽台车至区间小里程侧;(2) If the trolley is a detachable trolley, use the translation method of the battery car to move it to the designated position; if the trolley is a non-detachable trolley, use the oblique translation method to move; where the oblique translation method is: The horizontal translation process is the same as that of the battery car, but after it is moved to the center line of the line, the battery car is used to drag the trolley to the small mileage side of the section;
(3)设备桥吊装下井,并在其底部安装两辆管片小车后,采用台车平移方式移至指定位置;(3) The equipment bridge is hoisted into the well, and after installing two segment trolleys at the bottom, move it to the designated position by means of trolley translation;
S5、螺旋机、拼装机、反力架吊装与平移:S5. Hoisting and translation of screw machine, assembly machine, reaction frame:
螺旋机、拼装机、反力架吊装下井,并按照设备桥移动方式平移至指定位置;The screw machine, assembly machine, and reaction frame are hoisted into the well, and moved to the designated position according to the movement mode of the equipment bridge;
S6、盾体吊装与平移:S6. Shield hoisting and translation:
始发架吊装下井,并放置在井口位置;同时,依次吊装并连接前盾、中盾、尾盾;待盾体安装完毕,将盾体与始发架焊接,并设置反力钢板准备顶退,以将盾体平移至指定位置;待盾体平移至指定位置,开始安装反力架,并调试盾构机;The starting frame is hoisted down the well and placed at the wellhead; at the same time, the front shield, middle shield, and tail shield are hoisted and connected in sequence; after the shield body is installed, the shield body and the starting frame are welded, and the reaction force steel plate is prepared to push back , to move the shield body to the specified position; when the shield body moves to the specified position, start to install the reaction frame and debug the shield machine;
S7、盾构始发。S7. The shield tunneling starts.
作为本发明的优选方式之一,所述步骤S1③中,横通道的平移钢板为2cm厚钢板,宽设置6m;所述平移钢板的布置方式为“T”字型,即,沿先横通道的长度方向延伸,待延伸到右线区间位置时再分别向其两侧的右线区间方向延伸。As one of the preferred modes of the present invention, in the step S1③, the translational steel plate of the transverse channel is a 2cm thick steel plate with a width of 6m; Extend in the length direction, and then extend to the right-line interval directions on both sides when extending to the right-line interval position.
作为本发明的优选方式之一,铺设所述平移钢板时,钢板用焊机焊接,焊缝平整饱满,钢板两侧利用植筋与钢板焊接牢固。As one of the preferred modes of the present invention, when laying the translational steel plate, the steel plate is welded with a welding machine, the weld seam is smooth and full, and both sides of the steel plate are firmly welded with the steel plate by planting bars.
作为本发明的优选方式之一,所述步骤S1中,区间的钢轨采用43轨,且分别包括电瓶车轨与台车轨;其中,电瓶车轨的43轨道间距97cm,台车轨的轨道间距218cm;同时,轨道尽头设置有防撞装置,该防撞装置由25双拼工字钢焊接而成,高度1m,与轨道焊接,后侧设置斜撑。As one of the preferred modes of the present invention, in the step S1, the steel rails in the section adopt 43 rails, and respectively include battery rails and trolley rails; wherein, the distance between the 43 rails of the battery rails is 97 cm, and the rail distance of the trolley rails is 218 cm; At the same time, an anti-collision device is installed at the end of the track. The anti-collision device is welded by 25 double-piece I-beams, with a height of 1m, welded to the track, and a diagonal brace is installed on the rear side.
作为本发明的优选方式之一,铺设所述钢轨前,先利用I20工字钢作为马凳及2cm钢板搭设工作平台,工字钢支架间距1m;接着,在混凝土面及工作平台上每隔1m铺设一道14槽钢并固定;最后,将钢轨直接铺设在14槽钢上,即完成钢轨的施工。As one of the preferred modes of the present invention, before laying described rail, earlier utilize I20 I-beam as horse stool and 2cm steel plate to set up work platform, I-beam support spacing 1m; Then, on concrete surface and work platform every 1m Lay a 14-channel steel and fix it; finally, lay the rail directly on the 14-channel steel to complete the construction of the rail.
作为本发明的优选方式之一,所述步骤S3中,关于电瓶机车吊装下井:吊车选用260T履带吊,将电瓶车吊至已设置好的平板小车上,再使用1t葫芦和ф32钢丝绳将电瓶车与下方的平板小车固定,接着吊装下井;As one of the preferred modes of the present invention, in the step S3, regarding the hoisting of the battery locomotive into the well: the crane uses a 260T crawler crane to hoist the battery car to the set flat trolley, and then uses a 1t hoist and a ф32 steel wire rope to connect the battery car to the bottom The flat trolley is fixed, and then hoisted down to the well;
关于电瓶机车平移:卷扬机采用植筋焊接的方法固定,植筋使用ф25的钢筋,设置8道,将卷扬机固定,避免卷扬机移动;同时,与卷扬机连接的两台平移小车载重60t、高0.7m,两辆小车利用I20a工字钢连接牢固,小车上铺设2cm厚钢板,钢板上放置两条轨道,轨道上放置电瓶车;当电瓶车被拉至右线且驶入区间小里程后,使用铁靴等防溜车装置将电瓶车给予固定。Regarding the translation of the battery locomotive: the hoist is fixed by planting reinforcement welding, and the planting reinforcement uses ф25 steel bars, and 8 lines are set to fix the hoist to prevent the hoist from moving; at the same time, the two translation trolleys connected to the hoist have a load of 60t and a height of 0.7m , the two trolleys are firmly connected by I20a I-beams, 2cm thick steel plates are laid on the trolley, two rails are placed on the steel plates, and the battery car is placed on the track; The anti-rolling device fixes the battery car.
作为本发明的优选方式之一,所述步骤S4中,关于台车吊装下井:台车到场后,利用吊车下钩将设备吊入盾构井平移小车上;As one of the preferred modes of the present invention, in the step S4, regarding the hoisting of the trolley to go into the well: after the trolley arrives at the scene, use the lower hook of the crane to hoist the equipment into the shield well translation trolley;
关于台车平移:台车分为可拆卸与不可拆卸两种;不可拆卸台车采用斜向平移方式移动;可拆卸台车拆卸后长度缩短至小于9.7m,直接利用平移电瓶车方式进行横向平移。About trolley translation: trolleys are divided into detachable and non-detachable two types; non-detachable trolleys are moved by oblique translation; detachable trolleys are disassembled and the length is shortened to less than 9.7m, and horizontal translation is directly performed by translational battery cars.
作为本发明的优选方式之一,所述步骤S4中,斜向平移方式具体包括如下步骤:As one of the preferred modes of the present invention, in the step S4, the oblique translation mode specifically includes the following steps:
①准备平移小车,小车自下而上安装顺序同电瓶车;①Prepare the translation trolley, and the installation sequence of the trolley from bottom to top is the same as that of the battery trolley;
②利用卷扬机拉拽平移小车前进,台车端头过横通道后,在区间小里程方向利用手拉葫芦拖拽钢板转向,并且,“小里程侧小车”每前进约25cm,“大里程侧小车”就跟进50cm,减小两个平移小车间距,利用两台卷扬机及区间内20t手拉葫芦调整钢板连带着台架进行转向,直至转至与右线轴线重合;台车轨道与区间轨道相进行连接,并采用I20工字钢支架支撑连接处;② Use the hoist to pull the translation trolley forward. After the end of the trolley passes through the cross passage, use the hand chain hoist to drag the steel plate to turn in the direction of the small mileage in the section, and the "small mileage side trolley" advances about 25cm, and the "long mileage side trolley" "Follow up 50cm, reduce the distance between the two translational small cars, use two hoists and 20t chain hoists in the section to adjust the steel plate and the platform to turn until it coincides with the axis of the right line; the track of the trolley is aligned with the track of the section Connect and use I20 I-beam brackets to support the connection;
③台车转至区间线路后,利用电瓶车拖拽至小里程侧。③ After the trolley transfers to the section line, use the battery car to drag it to the side with a small mileage.
作为本发明的优选方式之一,所述步骤S5中,螺旋机长度12.8m,直径1.1m,重量约22t;平移时,在螺旋机底部安装两辆管片小车,并利用平移小车运至区间端口,再利用管片小车运送至设备桥腹内;待盾体顶推完成后,再利用管片小车把螺旋机插入拼装机内,在设备桥两侧安装门架,用于组装螺旋机。As one of the preferred modes of the present invention, in the step S5, the length of the screw machine is 12.8m, the diameter is 1.1m, and the weight is about 22t; when translating, install two segment trolleys at the bottom of the screw machine, and use the translation trolley to transport to the section Then use the segment trolley to transport it to the belly of the equipment bridge; after the shield push is completed, use the segment trolley to insert the screw machine into the assembly machine, and install door frames on both sides of the equipment bridge for assembling the screw machine.
作为本发明的优选方式之一,所述步骤S6中,盾体安装及平移的具体步骤如下:As one of the preferred modes of the present invention, in the step S6, the specific steps of shield installation and translation are as follows:
①始发架安装①Start rack installation
始发架安装前,割除垫层钢板上加固的钢轨及其他杂物,钢板清理打磨干净后涂抹黄油;始发架下面也安装两张钢板,依靠钢板间的黄油减小平移摩擦;Before the starting frame is installed, the reinforced rails and other debris on the cushion steel plate are cut off, the steel plate is cleaned and polished, and then butter is applied; two steel plates are also installed under the starting frame, and the translational friction is reduced by the butter between the steel plates;
②盾构机分体吊装下井②The shield machine is hoisted separately and goes down the well
因场地限制,盾体需在盾构井下完成拼装,再推至始发洞门前;Due to site constraints, the shield body needs to be assembled underground in the shield shaft, and then pushed to the starting tunnel;
其中,盾构机盾体下井顺序为前盾-刀盘-中盾-盾尾;下井后,将盾体放在基座上,然后进行盾构机的拼装;其中,在前盾与刀盘拼装完成后,整体向大里程侧平移5m,为中盾吊装及尾盾吊装腾出空间,接着再依次安装中盾、盾尾;Among them, the shield body of the shield machine goes down in the order of front shield-cutterhead-middle shield-shield tail; after going down the well, put the shield body on the base, and then assemble the shield machine; among them, the front shield and cutterhead After the assembly is completed, the whole is moved 5m to the high-mileage side to make room for the hoisting of the middle shield and the tail shield, and then install the middle shield and the tail of the shield in sequence;
③盾构机侧向平移③Lateral translation of the shield machine
待盾体安装完毕,将盾体与始发架焊接,并利用千斤顶的推力使始发架与盾构机一起平移;平移时,两个200t液压千斤顶位于始发架同一侧,同一方向顶推,顶推速度设置为10cm/min,顶进过程中,液压千斤顶两侧各焊接挡块两个,用于固定液压千斤顶给,防止油缸侧向打滑;After the shield body is installed, weld the shield body and the starting frame, and use the thrust of the jack to make the starting frame and the shield machine translate together; when moving, two 200t hydraulic jacks are located on the same side of the starting frame and push in the same direction , the jacking speed is set to 10cm/min. During the jacking process, two stoppers are welded on both sides of the hydraulic jack, which are used to fix the hydraulic jack and prevent the cylinder from slipping laterally;
盾体平移完成后,使用焊接工字钢、植筋的方式,制作防扭头装置,始发架与洞门之间的空隙使用钢板进行填充,防止始发架移动。After the translation of the shield body is completed, the anti-twist device is made by welding I-beams and planting bars, and the gap between the starting frame and the portal is filled with steel plates to prevent the starting frame from moving.
本发明相比现有技术的优点在于:本发明提出的始发施工方式跟普通始发方式有较大区别,可有效解决异形、非正线车站盾构始发难题,主要体现在:Compared with the prior art, the present invention has the advantages that: the originating construction method proposed by the present invention is quite different from the common originating method, and can effectively solve the problem of originating shield tunneling at special-shaped and non-main line stations, which is mainly reflected in:
(1)加快工程推进(1) Accelerate the progress of the project
可灵活设置盾构始发井位置,规避因车站盾构始发井(或局部盾构区间)方案不稳定而造成的盾构区间无法始发(或掘进)的问题,加快工程推进;The position of the shield launching shaft can be flexibly set to avoid the problem that the shield section cannot start (or excavate) due to the unstable plan of the shield launching shaft (or local shield section) at the station, and accelerate the progress of the project;
(2)提高施工效率(2) Improve construction efficiency
①本工法只需相应场地内铺设平移区域即可,无需大型改造;①This construction method only needs to lay a translational area in the corresponding site, without large-scale transformation;
②针对不同部件可采用不同平移方式,减少所使用时间,且平移盾构时,内部可进行台车间管线的连接,缩短始发时间;②Different translation methods can be adopted for different components to reduce the time used, and when the shield is translated, the internal connection of the pipeline in the workshop can be carried out to shorten the starting time;
③始发后,只需拆除负环进行台车恢复即可,无需耽误其他时间。③After the start, it is only necessary to remove the negative ring and restore the trolley without delaying other time.
(3)减少了施工费用(3) Reduced construction costs
①无需使用大型机械,所采用的机械主要为卷扬机、液压千斤顶;① There is no need to use large machinery, and the machinery used is mainly winches and hydraulic jacks;
②铺设平移区域材料基本都可重复使用,皆可回收;②Materials for laying the translational area are basically reusable and recyclable;
(4)适用于狭小空间(4) Suitable for small spaces
本工法平移过程无需采用电动转盘这样的大型机械进行转向,因而所受场地限制较小,适用于狭小空间。The translation process of this construction method does not require the use of large-scale machinery such as electric turntables for steering, so it is less restricted by the site and is suitable for narrow spaces.
(5)保证了安全生产(5) Guaranteed safe production
①针对台车、盾体采用不同的平移方式,减少了安全隐患;① Different translation methods are adopted for trolleys and shields, which reduces potential safety hazards;
②施工过程中,不使用大型机械,有效的减小风险;② During the construction process, no large-scale machinery is used to effectively reduce the risk;
③平移操作过程中,皆使用远程操控,人员可远离风险源,降低了事故发生概率。③In the process of translation operation, remote control is used, and personnel can stay away from risk sources, reducing the probability of accidents.
附图说明Description of drawings
图1是实施例1中狭小空间盾构机侧向分体始发施工方法的步骤流程图;Fig. 1 is the flow chart of the steps of the construction method of the shield machine in narrow space laterally splitting in
图2是实施例1中盾构井横通道的平移钢板铺设图;Fig. 2 is the laying figure of the translational steel plate of shield well transverse channel in
图3是实施例1中区间钢轨铺设断面图;Fig. 3 is the sectional view of section rail laying in the middle section of
图4是实施例1中区间钢轨铺设平面图;Fig. 4 is the laying plane view of section rail in
图5是实施例1中电瓶车组平移断面图;Fig. 5 is the translation sectional view of battery car group in
图6是实施例1中电瓶车组平移俯视图;Fig. 6 is the top view of the translation of the battery car group in
图7是实施例1中电瓶车组示意图;Fig. 7 is a schematic diagram of battery car group in
图8是实施例1中短台车平移断面图;Figure 8 is a cross-sectional view of the translation of the short trolley in
图9是实施例1中长台车平移平面图;Fig. 9 is a plan view of the translation of the long trolley in
图10是实施例1中长台车平移转向步序图;Fig. 10 is a sequence diagram of the translational steering of the long trolley in
图11是实施例1中设备桥平移图;Fig. 11 is a translation diagram of the equipment bridge in
图12是实施例1中盾体平移正视图;Fig. 12 is the front view of shield translation in
图13是实施例1中盾体平移俯视图;Fig. 13 is the top view of the translation of the shield body in
图14是实施例1中反力架设置图;Fig. 14 is the setting diagram of reaction force frame in
图15是图14中的1-1剖视截面图;Fig. 15 is a sectional view of 1-1 in Fig. 14;
图16是图14中的2-2剖视截面图;Fig. 16 is a cross-sectional view of 2-2 in Fig. 14;
图17是图14中的3-3剖视截面图。Fig. 17 is a sectional view taken along line 3-3 in Fig. 14 .
具体实施方式Detailed ways
下面对本发明的实施例作详细说明,本实施例在以本发明技术方案为前提下进行实施,给出了详细的实施方式和具体的操作过程,但本发明的保护范围不限于下述的实施例。The embodiments of the present invention are described in detail below. This embodiment is implemented on the premise of the technical solution of the present invention, and detailed implementation methods and specific operating procedures are provided, but the protection scope of the present invention is not limited to the following implementation example.
实施例1Example 1
如图1所示,本实施例的一种狭小空间盾构机侧向分体始发施工方法,包括如下步骤:As shown in Figure 1, a construction method for laterally splitting the shield machine in a small space according to this embodiment includes the following steps:
1、准备工作:1. Preparation:
(1)进行现场勘测(1) Carry out on-site survey
根据吊装方案中吊车站位和运输车辆进出场线路布置,盾构机进场过程中,零构件运输过程中最大车辆长度为17m,盾构机运输过程中需整理场地,方便盾构机进场。According to the layout of the crane station and the entry and exit routes of the transport vehicles in the hoisting plan, when the shield machine enters the site, the maximum vehicle length during the component transportation process is 17m, and the site needs to be tidied up during the shield machine transportation to facilitate the shield machine entry .
(2)测量放线(2) Measurement and setting-out
测量组将需要铺设轨道标高、始发架位置以及始发架高度在相应位置标示。The measurement team will need to mark the elevation of the laid track, the position of the starting frame and the height of the starting frame at the corresponding positions.
(3)地面整平(3) Ground Leveling
根据测量结果,对场地进行平整,在坑洼位置进行填砂整平,对高出设计位置处进行凿除打磨。According to the measurement results, the site is leveled, the potholes are filled with sand and leveled, and the positions higher than the design are chiseled and polished.
(4)横通道底板上铺设平移钢板(4) Lay translational steel plates on the floor of the transverse channel
场地平整后,根据放样位置在横通道底板上铺设平移钢板;平移钢板为2cm厚钢板,宽设置6m,钢板放置方式如图2所示,即,沿先横通道的长度方向延伸,待延伸到右线区间位置时再分别向其两侧的右线区间方向延伸。After the site is leveled, a translational steel plate is laid on the bottom plate of the transverse aisle according to the stakeout position; the translational steel plate is a 2cm thick steel plate with a width of 6m. When the position of the right-line interval is located, it extends to the direction of the right-line interval on both sides respectively.
钢板用焊机焊接,焊缝平整饱满,钢板两侧利用植筋与钢板焊接牢固。第一阶段,钢板上安放轨道,用于电瓶车组、台车的平移;第二阶段,钢板上抹黄油以减少摩擦力,用于盾体的平移。The steel plate is welded with a welding machine, the weld seam is flat and full, and the two sides of the steel plate are firmly welded with the steel plate by planting bars. In the first stage, the track is placed on the steel plate for the translation of the battery car group and the trolley; in the second stage, butter is applied to the steel plate to reduce friction and used for the translation of the shield body.
(5)区间铺设钢轨(5) Laying rails in intervals
首先,利用I20工字钢作为马凳及2cm钢板搭设工作平台,工字钢支架间距1m;接着,在混凝土面及工作平台上每隔1m铺设一道14槽钢并固定;最后,在槽钢上铺设钢轨,如图3、图4所示。First, use I20 I-beam as a horse stool and 2cm steel plate to build a working platform, and the distance between I-beam brackets is 1m; then, lay a 14-channel steel every 1m on the concrete surface and working platform and fix it; finally, on the channel steel Lay rails, as shown in Figure 3 and Figure 4.
钢轨采用43轨,且分别包括电瓶车轨与台车轨。其中,电瓶车轨的43轨道间距(中至中)97cm,台车轨的轨道间距(中至中)218cm;轨道尽头需设置防撞装置,防撞装置由25双拼工字钢焊接而成,高度1m,与轨道焊接,后侧设置斜撑。The steel rail adopts 43 rails, and includes battery rails and trolley rails respectively. Among them, the 43 track spacing (medium to medium) of the battery track is 97cm, and the track spacing (medium to medium) of the trolley rail is 218cm; an anti-collision device must be installed at the end of the track, and the anti-collision device is welded by 25 double I-beams. The height is 1m, welded with the track, and the rear side is equipped with diagonal braces.
2、盾构机进场:2. The shield machine enters the site:
准备吊装场地,盾构吊装机械及盾构机进场;Prepare the hoisting site, and the shield hoisting machinery and shield machine enter the site;
3、电瓶车组吊装与平移:3. Hoisting and translation of the battery pack:
(1)将电瓶车组运输至场地,电瓶车组最大尺寸为电瓶车,长度7.8m,宽1.5m,平移过程中正常平移,不需侧向平移。(1) Transport the battery car group to the site. The maximum size of the battery car group is a battery car, with a length of 7.8m and a width of 1.5m. During the translation process, it will move normally without lateral translation.
(2)吊车选用260T履带吊,将电瓶车吊至已设置好的平板小车上,再使用1t葫芦和ф32钢丝绳将电瓶车与下方的平板小车固定,接着吊装下井(台车使用同样方式固定)。(2) The crane uses a 260T crawler crane to hoist the battery car to the set-up flat trolley, then use a 1t hoist and ф32 steel wire rope to fix the battery trolley and the flat trolley below, and then hoist it down the well (the trolley is fixed in the same way).
(3)设置两台卷扬机,分别与两台平移小车连接,为平移提供动力(卷扬机采用植筋焊接的方法固定,植筋使用ф25的钢筋,设置8道,将卷扬机固定,避免卷扬机移动);同时,在横通道的平移钢板上铺设垂直区间线路方向的电瓶车轨与台车轨,并在电瓶车轨上放置两台平移小车(载重60t、高0.7m),两辆小车之间采用I20a工字钢连接牢固,小车上再铺设一层2cm厚钢板,钢板上放置平行于区间线路方向的两条轨道,电瓶车放置于轨道上,如图5、图6所示。(3) Set up two winches, respectively connected with two translation trolleys, to provide power for the translation (the winches are fixed by planting bar welding, and the planting bars use ф25 steel bars, set 8 lines, fix the winches, and avoid the winches from moving); At the same time, lay battery rails and trolley rails in the direction of the vertical section line on the translational steel plates of the transverse aisle, and place two translational trolleys (load 60t, height 0.7m) on the battery rails, and use I20a I-shaped between the two trolleys The steel connection is firm, and a layer of 2cm thick steel plate is laid on the trolley. Two tracks parallel to the direction of the section line are placed on the steel plate, and the battery car is placed on the track, as shown in Figure 5 and Figure 6.
(4)由于电瓶车体积小,可直接使用卷扬机平行拉入横通道,电瓶车重量为42t(含电瓶),摩擦系数设置为0.1,两个5t卷扬机可完全满足需求,平移过程中两个卷扬机的操作必须基本一致,防止倾斜严重,影响平移安全,卷扬机工作过程中,由专人统一指挥,卷扬机在推进过程中,严格控制推进速度,使其保持在同一平面上。平移过程中若发生两侧行进速度不一致,应及时进行调整。(4) Due to the small size of the battery car, the hoist can be directly used to pull it into the horizontal passage in parallel. The weight of the battery car is 42t (including the battery), and the friction coefficient is set to 0.1. Two 5t hoists can fully meet the demand. The operation of the two hoists during the translation process It must be basically consistent to prevent serious inclination and affect the safety of translation. During the working process of the hoist, a special person is responsible for the unified command. During the propulsion process of the hoist, the propulsion speed is strictly controlled to keep it on the same plane. If the speed of the two sides is inconsistent during the translation process, it should be adjusted in time.
(5)使用卷扬机将载有电瓶车的平移小车平行拉入横通道至右线位置处,然后电瓶车行驶入区间小里程方向,到达指定位置;驶入后,使用铁靴等防溜车装置将电瓶车给予固定(之后台车也采用同样的固定方式)。(5) Use the hoist to pull the translation trolley carrying the battery car parallel into the cross passage to the position on the right line, and then drive the battery car into the direction of the small mileage in the section to reach the designated position; Give it a fix (later the trolley also adopts the same fixation method).
(6)将一辆浆车以同样方式运送到指定位置,并接入到电瓶车后。(6) Transport a paddle car to the designated location in the same way, and connect it to the battery car.
(7)将运送至电瓶车轨道处后接入电瓶车后,电瓶车编组为电瓶机车-浆车-平板车(即上述“平移小车”),如图7所示。(7) After being transported to the track of the battery car and connected to the battery car, the battery car is organized into a battery locomotive-a paddle car-flat car (that is, the above-mentioned "translation car"), as shown in Figure 7.
4、台车以及设备桥的吊装与平移:4. Hoisting and translation of trolley and equipment bridge:
(1)台车到场后,按照4#、3#、2#、1#台车顺序依次利用吊车缓慢下钩将设备吊入盾构井平移小车上,并进行相应的平移。(1) After the trolleys arrive at the site, use the crane to slowly hook down the equipment in sequence according to the order of 4#, 3#, 2#, and 1# trolleys to hoist the equipment into the shield well translation trolley, and perform corresponding translation.
平移分两种情况,一种台车可拆卸,台车长度缩短至8.2-9.4m,可直接利用平移电瓶车方式进行横向平移台车;另一种台车不可拆卸,长度为10.1-12.5m,需进行斜向平移,台车情况如表1所示;There are two situations for translation. One kind of trolley is detachable, and the length of the trolley is shortened to 8.2-9.4m, and the trolley can be translated horizontally by directly using the translation battery car; the other kind of trolley is not detachable, and the length is 10.1-12.5m. Oblique translation is required, and the condition of the trolley is shown in Table 1;
表1台车情况图Table 1 Situation diagram of the trolley
拆卸后长度小于9.7m的台车(4#、3#、1#台车),平移过程与电瓶车平移方式相同(如图8所示),平移速度控制在50cm/min左右,横向平移至线路中线位置后,利用电瓶车拖拽台车至区间内,台车移动到指定位置后,设置铁靴、钢板等防溜车装置。For trolleys (4#, 3#, 1# trolleys) whose length is less than 9.7m after disassembly, the translation process is the same as that of the battery trolley (as shown in Figure 8), the translation speed is controlled at about 50cm/min, and the horizontal translation reaches the line After the center line position, use the battery car to drag the trolley to the section, and after the trolley moves to the designated position, install anti-rolling devices such as iron shoes and steel plates.
长度大于9.7m的台车(2#台车)以及后续提到的设备桥,平移采用斜向平移法,方法如下:For trolleys with a length greater than 9.7m (2# trolley) and the equipment bridge mentioned later, the oblique translation method is used for translation, and the method is as follows:
①准备平移小车,小车自下而上安装顺序同电瓶车;平移时情况:横通道底板上铺设平移钢板,钢板上铺设垂直区间线路方向的4条轨道,钢轨上放置2台60t平移小车(0.7m高),两辆小车利用I20a工字钢连接牢固,小车上铺设2cm厚钢板,钢板上放置平行于区间线路方向的2条轨道,电瓶车放置于轨道上。平移小车错开6m,小车与钢板间涂抹黄油减小摩擦。①Prepare the translation trolley, the installation sequence of the trolley from bottom to top is the same as that of the battery car; the situation during translation: lay translation steel plates on the bottom plate of the transverse channel, lay 4 tracks in the direction of the vertical section line on the steel plates, and place two 60t translation trolleys (0.7m High), the two trolleys are firmly connected by I20a I-beams, 2cm thick steel plates are laid on the trolleys, two tracks parallel to the direction of the section line are placed on the steel plates, and the battery cars are placed on the tracks. The translation trolley is staggered by 6m, and butter is applied between the trolley and the steel plate to reduce friction.
②如图9、图10所示,利用卷扬机拉拽平移小车前进,台车端头过横通道后,在区间小里程方向利用手拉葫芦拖拽钢板转向,并且,“小里程侧小车”每前进约25cm,“大里程侧小车”就跟进50cm,减小两个平移小车间距,利用两台卷扬机及区间内20t手拉葫芦调整钢板连带着台架进行转向,直至转至与右线轴线重合;台车轨道与区间轨道相进行连接,并采用I20工字钢支架支撑连接处。②As shown in Figure 9 and Figure 10, use the hoist to pull the translation trolley forward. After the end of the trolley passes through the cross passage, use the hand chain hoist to drag the steel plate to turn in the direction of the small mileage in the section, and the "small mileage side trolley" Advance about 25cm, and the "large mileage side trolley" will follow up by 50cm, reduce the distance between the two translational trolleys, and use two hoists and 20t chain hoists in the interval to adjust the steel plate and the platform to turn until it turns to the axis of the right line Coincidence; the trolley track is connected with the section track, and the connection is supported by I20 I-beam brackets.
③台车转至区间线路后,利用电瓶车拖拽至小里程侧。③ After the trolley transfers to the section line, use the battery car to drag it to the side with a small mileage.
(2)设备桥吊装下井,并在其底部安装两辆管片小车后(因设备桥下部不含车轮),采用台车平移方式移至指定位置(如图11所示)。(2) The equipment bridge is hoisted into the well, and after two segment trolleys are installed at the bottom (because the lower part of the equipment bridge does not contain wheels), the trolley is used to move to the designated position (as shown in Figure 11).
5、螺旋机、拼装机、反力架的平移:5. Translation of screw machine, assembly machine and reaction frame:
螺旋机、拼装机、反力架吊装下井,并按照设备桥移动方式平移至指定位置。The screw machine, assembly machine, and reaction frame are hoisted down the well, and translated to the designated position according to the movement mode of the equipment bridge.
其中,螺旋机长度12.8m,直径1.1m,重量约22t;平移时,在螺旋机底部安装两辆管片小车,并利用平移小车运至区间端口,再利用管片小车运送至设备桥腹内;待盾体顶推完成后,再利用管片小车把螺旋机插入拼装机内,在设备桥两侧安装门架,用于组装螺旋机。Among them, the length of the screw machine is 12.8m, the diameter is 1.1m, and the weight is about 22t; during translation, two segment trolleys are installed at the bottom of the screw machine, and transported to the section port by the translation trolley, and then transported to the equipment bridge belly by the segment trolley ; After the push of the shield body is completed, insert the screw machine into the assembly machine with the segment trolley, and install the door frames on both sides of the equipment bridge for assembling the screw machine.
6、盾体安装及平移:6. Shield installation and translation:
(1)始发架吊装下井,并放置在井口位置;(1) The starting frame is hoisted down the well and placed at the wellhead;
(2)始发架安装(2) Starting frame installation
始发架安装前,割除垫层钢板上加固的钢轨及其他杂物,钢板清理打磨干净后涂抹黄油;始发架下面也安装两张钢板,依靠钢板间的黄油减小平移摩擦。Before the starting frame is installed, the reinforced rails and other sundries on the cushion steel plate are cut off, the steel plate is cleaned and polished, and butter is applied; two steel plates are also installed under the starting frame, and the translational friction is reduced by the butter between the steel plates.
(3)盾构机分体吊装下井(3) The shield machine is hoisted separately and goes down the well
因场地限制,盾体需在盾构井下完成拼装,再推至始发洞门前。盾构机盾体下井顺序为前盾-刀盘-中盾-盾尾;吊装过程中应待盾体平稳没有晃动后,平稳缓慢地将盾体放入竖井中,待盾体稳定后,将盾体缓慢放在基座上的准确位置,然后进行盾构机的拼装。其中,在前盾与刀盘拼装完成后,整体向大里程侧平移5m,为中盾吊装及尾盾吊装腾出空间,接着再依次安装中盾、盾尾。Due to space constraints, the shield body needs to be assembled underground in the shield shaft, and then pushed to the starting tunnel. The shield body of the shield machine is lowered in the following order: front shield-cutterhead-middle shield-shield tail; during the hoisting process, after the shield body is stable without shaking, put the shield body into the shaft smoothly and slowly, and when the shield body is stable, place the shield body The shield body is slowly placed on the base at an accurate position, and then the shield machine is assembled. Among them, after the assembly of the front shield and the cutter head is completed, the whole is moved 5m to the high-mileage side to make room for the hoisting of the middle shield and the tail shield, and then the middle shield and the tail of the shield are installed in sequence.
(4)盾构机侧向平移(4) Lateral translation of the shield machine
①如图12、图13所示,盾构机固定在始发架上后,利用千斤顶的推力使始发架与盾构机一起平移。平移时,2个200t液压千斤顶位于始发架同一侧,同一方向顶推,顶推速度不易过快,设置为10cm/min,顶进过程中,液压千斤顶两侧各焊接挡块2个,用于固定液压千斤顶给,防止油缸侧向打滑(盾体重量约为400t,其他设备5t,总共405t,摩擦系数设置为0.2,动力为两个200t液压千斤顶,F=(400)*0.2=80t<400t,满足需求)。① As shown in Figure 12 and Figure 13, after the shield machine is fixed on the starting frame, use the thrust of the jack to make the starting frame and the shield machine move in translation together. During the translation, the two 200t hydraulic jacks are located on the same side of the starting frame, pushing in the same direction, and the pushing speed is not too fast, set at 10cm/min. Use a fixed hydraulic jack to prevent the cylinder from slipping sideways (the weight of the shield body is about 400t, other equipment is 5t, a total of 405t, the friction coefficient is set to 0.2, and the power is two 200t hydraulic jacks, F=(400)*0.2=80t< 400t, to meet the demand).
②液压千斤顶在顶推过程中,严格控制推进速度,及时进行纠偏,防止始发架偏移,液压千斤顶作业人员与监视测量人员密切配合,每次推进不得超过1000mm。② During the pushing process of the hydraulic jack, the propulsion speed is strictly controlled, and the deviation is corrected in time to prevent the offset of the starting frame. The operators of the hydraulic jack cooperate closely with the monitoring and measuring personnel.
③每次推进过程中人员应撤退到安全区域,一旦始发架发生偏移,应立即停止继续加压,并由现场负责人及技术负责人安排人员对始发架基座的焊缝及基底钢板,双拼工25工字钢顶铁焊缝等外观进行检查,查看是否有焊缝开裂,构件变形等情况,并对检查记录进行记录,检查无误后方可继续顶推平移。同时,在液压推进设备上安装急停开关,由专人负责,防止出现紧急情况时能及时制停。③Personnel should retreat to a safe area during each propulsion process. Once the starting frame deviates, stop pressurization immediately, and the person in charge of the site and the technical person in charge arrange personnel to check the welding seam and base of the starting frame base. Check the appearance of the steel plate, Shuangpingong 25 I-steel top iron welds, etc. to check whether there are weld cracks, component deformation, etc., and record the inspection records. After the inspection is correct, the push and translation can be continued. At the same time, an emergency stop switch is installed on the hydraulic propulsion equipment, and a special person is responsible to prevent it from being stopped in time when an emergency occurs.
盾体平移完成后,使用焊接工字钢、植筋的方式,制作防扭头装置,始发架与洞门之间的空隙使用钢板进行填充,防止始发架移动。After the translation of the shield body is completed, the anti-twist device is made by welding I-beams and planting bars, and the gap between the starting frame and the portal is filled with steel plates to prevent the starting frame from moving.
(5)反力架设置(5) Reaction frame setting
反力架由两根横梁、两根竖梁和两个斜撑组成,横梁尺寸为600mm*400mm,竖梁尺寸为,600mm*450mm,长度分别为5.26m以及7.3m;斜撑由两根直径630钢管组成,长度为5.8m以及2.8m;横梁顶部及底部使用H40型钢制作斜撑,共设置6根,间距为1m,角度为45°,顶部斜撑需在反力架安装完成后测量焊接,保证焊接、受力点完好。可在盾体平移钱使用平移小车直接放至指定位置处,盾构组装完成后,将盾构机向洞门方向顶推,留出位置用于反力架的拼接,上方悬挂手拉葫芦,将反力架吊起进行焊接,吊起焊接顺序:底梁-竖梁-顶梁-斜撑;反力架的安装在尾盾安装完成之后、与连接桥连接之前进行。反力架应垂直于始发架摆放,且立柱垂直方向成7‰坡度俯角,各焊接部位应焊接牢固。The reaction frame is composed of two beams, two vertical beams and two diagonal braces. The beam size is 600mm*400mm, the vertical beam size is 600mm*450mm, and the lengths are 5.26m and 7.3m respectively; the diagonal braces are composed of two diameters Composed of 630 steel pipes, the length is 5.8m and 2.8m; the top and bottom of the beam are made of H40 steel, and there are 6 pieces in total, with a distance of 1m and an angle of 45°. The top diagonal braces need to be measured and welded after the reaction frame is installed. , to ensure that the welding and stress points are intact. The shield body can be moved directly to the designated position by using the translation trolley. After the shield machine is assembled, push the shield machine towards the door, leaving a place for the splicing of the reaction frame, and hang the chain hoist above it. Lift the reaction frame for welding. The sequence of lifting and welding is: bottom beam-vertical beam-top beam-slant brace; the installation of the reaction frame is carried out after the tail shield is installed and before it is connected to the connecting bridge. The reaction frame should be placed perpendicular to the starting frame, and the vertical direction of the column has a slope depression angle of 7‰, and all welding parts should be welded firmly.
竖梁焊接在事先预埋在底板的钢板上,钢板规格为2cm、1m*1m,其他部件按图纸进行焊接。The vertical beams are welded on the steel plate pre-buried on the bottom plate, the steel plate size is 2cm, 1m*1m, and other parts are welded according to the drawings.
盾构始发反力架为拼装式全钢架结构,以确保足够刚性。反力架示意图如图14-图17所示所示。The starting reaction frame of the shield machine is an assembled all-steel frame structure to ensure sufficient rigidity. The schematic diagram of the reaction frame is shown in Figure 14-Figure 17.
反力架安装时,首先测量反力架位置起始里程断面的中心线,并刻划在始发井侧墙上,以便反力架中心定位,反力架中心随发射架抬高而同时抬高20mm。定位关键是反力架紧靠负环管片的定位平面,并与此处的隧道轴线垂直。When the reaction frame is installed, first measure the center line of the initial mileage section of the reaction frame position, and mark it on the side wall of the launch shaft, so that the center of the reaction frame can be positioned. 20mm high. The key to positioning is that the reaction force frame is close to the positioning plane of the negative ring segment and is perpendicular to the tunnel axis here.
反力架底部的横梁和立柱下端,采用钢支撑块支顶在底部台阶处,位置确定之后,再焊接固定后部两排斜撑。斜撑采用Φ630钢管支撑,反力架上支撑于始发井中圈梁结构上,同时制作上方斜撑,使用H40型钢与反力架焊接,另一半顶撑在二衬上,与二衬钢架相连保证其固定。The beam at the bottom of the reaction frame and the lower end of the column are supported by steel support blocks at the bottom step. After the position is determined, the two rows of diagonal braces at the rear are welded and fixed. The diagonal brace is supported by Φ630 steel pipes, and the reaction frame is supported on the ring beam structure in the originating shaft. At the same time, the upper diagonal brace is made and welded with H40 steel and the reaction frame. Connect to ensure that it is fixed.
在盾构主机与后配套(设备桥和台车)连接之前,开始进行反力架的安装。安装时反力架与车站结构连接部位的间隙要垫实,以保证反力架脚板有足够的抗压强度。Before the main shield machine is connected with the rear support (equipment bridge and trolley), the installation of the reaction frame begins. During installation, the gap between the reaction frame and the connection part of the station structure shall be padded to ensure sufficient compressive strength of the foot plate of the reaction frame.
由于反力架和始发架为盾构始发时提供初始的推力以及初始的空间姿态,在安装反力架和始发架时,反力架左右偏差控制在±10mm之内,高程偏差控制在±5mm之内,上下偏差控制在±10mm之内。始发架水平轴线的垂直方向与反力架的夹角<±2‰,与设计轴线竖直趋势偏差<2‰,水平趋势偏差<±3‰。Since the reaction frame and the starting frame provide the initial thrust and the initial space attitude for the shield machine to start, when the reaction frame and the starting frame are installed, the left and right deviation of the reaction frame is controlled within ±10mm, and the elevation deviation is controlled Within ±5mm, the upper and lower deviations are controlled within ±10mm. The included angle between the vertical direction of the horizontal axis of the starting frame and the reaction frame is <±2‰, the vertical trend deviation from the design axis is <2‰, and the horizontal trend deviation is <±3‰.
7、盾构始发。7. The shield machine starts.
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention should be included in the protection of the present invention. within range.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210104247.2A CN114622920B (en) | 2022-01-28 | 2022-01-28 | Lateral split starting construction method for shield machine in narrow space |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210104247.2A CN114622920B (en) | 2022-01-28 | 2022-01-28 | Lateral split starting construction method for shield machine in narrow space |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN114622920A CN114622920A (en) | 2022-06-14 |
| CN114622920B true CN114622920B (en) | 2023-02-28 |
Family
ID=81897792
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210104247.2A Active CN114622920B (en) | 2022-01-28 | 2022-01-28 | Lateral split starting construction method for shield machine in narrow space |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN114622920B (en) |
Families Citing this family (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115628070A (en) * | 2022-09-28 | 2023-01-20 | 中铁十局集团第一工程有限公司 | A method for starting TBM lateral shaft |
| CN115853518B (en) * | 2022-10-26 | 2026-04-24 | 北京市政建设集团有限责任公司 | A shield tunneling method utilizing subway crossover layout |
| CN115788455A (en) * | 2022-12-07 | 2023-03-14 | 中交二公局东萌工程有限公司 | A rapid assembly method of TBM in narrow field outside the cave |
| CN117144966B (en) * | 2023-07-25 | 2026-04-21 | 中铁隧道局集团有限公司 | Shield tunneling foundation construction method |
| CN117365502A (en) * | 2023-10-24 | 2024-01-09 | 北京市政建设集团有限责任公司 | A reaction frame chamber and reaction frame installation method used for shield side launch |
| CN119641367A (en) * | 2024-12-31 | 2025-03-18 | 中铁十四局集团有限公司 | Method for assembling back dragging in back supporting trolley hole of oversized-diameter shield tunnel |
| CN119409072B (en) * | 2025-01-06 | 2025-03-28 | 中铁九局集团第四工程有限公司 | Hoisting method of shield machine of narrow vertical shaft |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000027591A (en) * | 1998-07-08 | 2000-01-25 | Kokudo Koki Kk | Small-bore shaft starting type pipe-jacking method for jacking-pipe by semi-shield machine |
| CN103711499A (en) * | 2014-01-08 | 2014-04-09 | 中铁十三局集团第六工程有限公司 | Shield tunneling machine split starting construction method |
| CN105298503A (en) * | 2015-09-16 | 2016-02-03 | 中铁十局集团第三建设有限公司 | Separate launching construction method of shield tunneling machine in narrow space |
| CN108131148A (en) * | 2018-01-22 | 2018-06-08 | 中交第二航务工程局有限公司 | Extra small starting well shield separate launching construction method |
| CN108756904A (en) * | 2018-06-12 | 2018-11-06 | 中铁隧道局集团有限公司 | Shield machine integrally originates construction method |
| CN210768900U (en) * | 2019-10-16 | 2020-06-16 | 中铁十一局集团城市轨道工程有限公司 | Translation device in shield machine station |
-
2022
- 2022-01-28 CN CN202210104247.2A patent/CN114622920B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000027591A (en) * | 1998-07-08 | 2000-01-25 | Kokudo Koki Kk | Small-bore shaft starting type pipe-jacking method for jacking-pipe by semi-shield machine |
| CN103711499A (en) * | 2014-01-08 | 2014-04-09 | 中铁十三局集团第六工程有限公司 | Shield tunneling machine split starting construction method |
| CN105298503A (en) * | 2015-09-16 | 2016-02-03 | 中铁十局集团第三建设有限公司 | Separate launching construction method of shield tunneling machine in narrow space |
| CN108131148A (en) * | 2018-01-22 | 2018-06-08 | 中交第二航务工程局有限公司 | Extra small starting well shield separate launching construction method |
| CN108756904A (en) * | 2018-06-12 | 2018-11-06 | 中铁隧道局集团有限公司 | Shield machine integrally originates construction method |
| CN210768900U (en) * | 2019-10-16 | 2020-06-16 | 中铁十一局集团城市轨道工程有限公司 | Translation device in shield machine station |
Also Published As
| Publication number | Publication date |
|---|---|
| CN114622920A (en) | 2022-06-14 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN114622920A (en) | Lateral split starting construction method for shield machine in narrow space | |
| CN113530553B (en) | Three-step construction process based on tunnel excavation and support integrated trolley | |
| CN110878530B (en) | Installation and construction method of steel box girder of steel structure bridge | |
| CN101537973B (en) | Method for continuously hoisting rolling mill housings by hydraulic pushing and lifting | |
| CN111255469B (en) | Modular disassembly construction method in closed narrow space of shield machine | |
| CN111794754B (en) | Pipe piece assembled derrick and construction method thereof | |
| CN110685701B (en) | A method for horizontal shifting and turning of shield machines in operating stations with limited space | |
| CN207525777U (en) | Prefabricated utility tunnel multidimension degree directional installation car | |
| CN116281606B (en) | Shield machine crane assembly method | |
| CN114109415A (en) | Construction method for disassembling tunnel of shield machine of non-expanding excavation chamber | |
| CN114933233B (en) | Reverse disassembly method for non-enlarged cavity in TBM cavity | |
| CN203308471U (en) | Open type TBM cast-in-place concrete inverted arch synchronous lining trolley | |
| CN209444345U (en) | Tunnel arch prefabricated segment construction device | |
| CN113090293A (en) | Shield subway tunnel segment repairing and reinforcing mechanical arm equipment | |
| CN110145317A (en) | A construction method for a shield machine passing a station | |
| CN113818478B (en) | Overweight prefabricated pipe gallery installation system and construction method thereof | |
| CN114370006A (en) | Construction method for transferring girder transport vehicle carrying bridge girder erection machine | |
| CN108643941A (en) | Gantry type arch installs trolley | |
| CN115628071A (en) | Long-distance rapid station passing method for shield/TBM complete machine | |
| CN119593766A (en) | A method for quickly assembling a split starter in a narrow space of a shield machine | |
| CN118242095B (en) | Construction method for shield dismantling machine in station of operation station | |
| CN118653846A (en) | A construction method for shield split start to quickly improve excavation efficiency | |
| CN118728422A (en) | A method for installing a template trolley for a high-altitude TBM rock burst tunnel | |
| CN215633005U (en) | Tunnel TBM stepping precast concrete member and tunnel | |
| CN117514211A (en) | A support platform for a split launch shield machine and its construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |

