JPH055971B2 - - Google Patents

Info

Publication number
JPH055971B2
JPH055971B2 JP63093595A JP9359588A JPH055971B2 JP H055971 B2 JPH055971 B2 JP H055971B2 JP 63093595 A JP63093595 A JP 63093595A JP 9359588 A JP9359588 A JP 9359588A JP H055971 B2 JPH055971 B2 JP H055971B2
Authority
JP
Japan
Prior art keywords
caisson
segments
foundation
construction method
segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP63093595A
Other languages
Japanese (ja)
Other versions
JPH01268920A (en
Inventor
Nozomi Tanaka
Tadashi Fujita
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP9359588A priority Critical patent/JPH01268920A/en
Publication of JPH01268920A publication Critical patent/JPH01268920A/en
Publication of JPH055971B2 publication Critical patent/JPH055971B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 《産業上の利用分野》 本発明はケーソン工法に関するものである。[Detailed description of the invention] 《Industrial application field》 The present invention relates to a caisson construction method.

《従来の技術》 ケーソン工法は、下端に刃口を備えた鉄筋コン
クリート製の筒状のケーソンを地盤上に設置し、
ケーソン内部の土砂を掘削、排土しながらケーソ
ンを沈下させて所定の支持地盤まで到達させ、こ
れを構造物の基礎とする工法である。このような
ケーソン工法で例えば橋の基礎を構築する場合に
は、ケーソンの下部を基礎として、その上部を撤
去するのであるが、この時の撤去方法としては、
従来、火薬やブレーカを用いて上部ケーソンを分
断しながら撤去していた。
[Conventional technology] The caisson construction method involves installing a cylindrical caisson made of reinforced concrete with a cutting edge at the bottom on the ground.
This construction method excavates and removes the earth and sand inside the caisson, allowing the caisson to sink until it reaches a designated supporting ground, which then becomes the foundation of the structure. For example, when constructing the foundation of a bridge using this caisson construction method, the lower part of the caisson is used as the foundation and the upper part is removed.
Previously, explosives or breakers were used to separate the upper caisson and remove it.

《発明が解決しようとする課題》 しかし、上述の如く火薬やブレーカを用いると
作業環境が悪くなるし、また破砕したコンクリー
ト塊の撤去が容易でない等作業能率の点でも問題
がある。
<<Problems to be Solved by the Invention>> However, as mentioned above, the use of gunpowder and breakers worsens the working environment and also poses problems in terms of work efficiency, such as difficulty in removing crushed concrete blocks.

本発明は前記課題を有効に解決すべく創案する
に至つたものであつて、その目的は上部ケーソン
の撤去を作業環境を良好に維持しつつ迅速に行い
得るケーソン工法を提供することにある。
The present invention has been devised to effectively solve the above problems, and its purpose is to provide a caisson construction method that allows the removal of the upper caisson to be carried out quickly while maintaining a good working environment.

《課題を解決するための手段》 前記課題を解決するため本発明は、刃口部を有
する下部ケーソンの上に上部ケーソンを順次構築
して、前記下部ケーソンを支持地盤まで沈設した
後、前記下部ケーソンを構造物の基礎とし、その
後前記上部ケーソンを撤去するようにしたケーソ
ン工法において、前記上部ケーソンを予め形成さ
れた複数のセグメントで構成するとともに、前記
下部ケーソンの沈設時にこのセグメントを締結具
によつて分解可能に相互に締結し、前記下部ケー
ソンを前記構造物の基礎とした後に、前記締結具
を緩めて前記セグメントをその上部から順次分解
して撤去するようにした。
<<Means for Solving the Problems>> In order to solve the above problems, the present invention sequentially constructs an upper caisson on a lower caisson having a cutting edge, and after sinking the lower caisson to the supporting ground, In a caisson construction method in which a caisson is used as the foundation of a structure and the upper caisson is then removed, the upper caisson is composed of a plurality of pre-formed segments, and the segments are used as fasteners when the lower caisson is sunk. After the lower caissons have been fastened to each other in a disassembly manner and the lower caissons have been used as the foundation of the structure, the fasteners are loosened and the segments are sequentially disassembled and removed from the top.

《作用》 前記の如く構成したケーソン工法においては、
上部ケーソンが分解可能な複数のセグメントで構
築されているので、締結具を緩めるだけでセグメ
ントを迅速に分解して搬出することができる上、
前記セグメントは再利用可能であることから施工
コストの低減を図れ、また火薬等を使わないです
むので作業環境が良好に維持される。
<<Operation>> In the caisson construction method constructed as described above,
Since the upper caisson is constructed of multiple disassembly segments, the segments can be quickly disassembled and transported by simply loosening the fasteners.
Since the segments are reusable, construction costs can be reduced, and since there is no need to use explosives, a good working environment can be maintained.

《実施例》 以下に本発明の一実施例を図面に基いて説明す
る。
<<Example>> An example of the present invention will be described below based on the drawings.

第1図は橋の基礎として用いられるケーソン1
を河床2から所定深さまで沈設した状態を示して
いる。このケーソン1は鉄筋コンリート製で第2
図に示す如く円筒状をなしている。ケーソン1は
その下半分の下部ケーソン1aと上半分の上部ケ
ーソン1bで構成されている。上部ケーソン1b
は多数のセグメント3からなり、各セグメント3
は第3図に示す如くボルト4とナツト5によつて
分解可能に相互に締結されている。以下さらに詳
しく説明する。
Figure 1 shows caisson 1 used as the foundation of the bridge.
The figure shows the state in which it has been sunk from the river bed 2 to a predetermined depth. This caisson 1 is made of reinforced concrete and the second
As shown in the figure, it has a cylindrical shape. The caisson 1 is composed of a lower caisson 1a as its lower half and an upper caisson 1b as its upper half. Upper caisson 1b
consists of a number of segments 3, each segment 3
are removably fastened to each other by bolts 4 and nuts 5, as shown in FIG. This will be explained in more detail below.

河床2には、筒状の仮締切り6が所定深さまで
打設される。仮締切り6の上端は水面7からやや
上方に突出し、仮締切り6の内側に水が流れ込む
のを阻止している。仮締切り6の内側には、内部
の水を排除して土砂を投入して築島8が構築さ
れ、この築島8からケーソン1が沈設される。
A cylindrical temporary cofferdam 6 is driven into the riverbed 2 to a predetermined depth. The upper end of the temporary cofferdam 6 projects slightly upward from the water surface 7 to prevent water from flowing into the inside of the temporary cofferdam 6. A built-up island 8 is constructed inside the temporary cofferdam 6 by removing the water inside and throwing earth and sand into it, and the caisson 1 is sunk from this built-up island 8.

ケーソン1の下部ケーソン1aは、その下端部
に刃口部9を具備しているとともに、その長さは
構築される基礎の長さに設定されている。この刃
口部9は沈設抵抗を少なくするためのものであ
る。
The lower caisson 1a of the caisson 1 has a cutting edge 9 at its lower end, and its length is set to the length of the foundation to be constructed. This blade opening 9 is for reducing sinking resistance.

上部ケーソン1bは、分解可能な多数の既成の
鉄筋コンクリート製セグメント3を円周方向に並
べるとともに、上下方向に積層して構成されてい
る。セグメント3の内面壁3aには第3図に示す
如く凹部17が形成されている。凹部17の上下
の側壁3bには上下方向に挿通孔18が形成さ
れ、この挿通孔18は上下に隣接した別のセグメ
ント3の挿通孔18に連続している。そして連続
した2つの挿通孔18に挿入されたボルト4と、
このボルト4の先端に螺合されたナツトによつて
上下のセグメント3が相互に締結されている。ま
た凹部17の左右の側壁にも前記したような挿通
孔が同様に形成され、同様のボルトとナツトによ
つて左右のセグメント3が相互に締結されてい
る。なお最下段のセグメント3は下部ケーソン1
aの上端に突設したアンカーボルト19にナツト
20で固定されている。
The upper caisson 1b is constructed by arranging a large number of disassembleable ready-made reinforced concrete segments 3 in the circumferential direction and stacking them in the vertical direction. A recess 17 is formed in the inner wall 3a of the segment 3, as shown in FIG. An insertion hole 18 is formed in the upper and lower side walls 3b of the recess 17 in the vertical direction, and this insertion hole 18 is continuous with an insertion hole 18 of another vertically adjacent segment 3. and a bolt 4 inserted into two consecutive insertion holes 18,
The upper and lower segments 3 are fastened together by a nut screwed onto the tip of the bolt 4. Further, the above-mentioned insertion holes are similarly formed in the left and right side walls of the recess 17, and the left and right segments 3 are fastened to each other by similar bolts and nuts. The lowest segment 3 is the lower caisson 1.
It is fixed with a nut 20 to an anchor bolt 19 protruding from the upper end of a.

セグメント3の上下左右の接合面には防水のた
め必要に応じシール材を取付ける。このシール材
はなるべく接合面の中央部に取付けるようにす
る。また接合面の内側の目地部にさらにコーキン
グ材を充填してもよい。
Attach sealing material to the upper, lower, left, and right joint surfaces of segment 3 as necessary for waterproofing. This sealing material should be attached to the center of the joint surface as much as possible. Further, the joint portion inside the joint surface may be further filled with caulking material.

セグメント3で構成される仮壁としての上部ケ
ーソン16は、沈設時においては圧入支圧壁体と
して、また、沈設後は止水壁体としての機能を有
する。
The upper caisson 16, which is a temporary wall made up of segments 3, functions as a press-fit bearing wall during sinking, and as a water-stop wall after sinking.

次に本発明のケーソン工法の施工手順を追つて
説明する。まず第1図に示す如く仮締切り6の内
側に築島8を構築した後、下部ケーソン1aは前
述の如く従来のケーソン工法に準じて施工され
る。なお、下部ケーソン1aは、築島8の据付け
位置に垂直方向に数ロツトに分割してコンクリー
トを打継ぎながら形成するか、あるいは予め一体
化したものであつてもよい。そして、下部ケーソ
ン1aの内部を掘削しながら、下部ケーソン1a
を徐々に沈設し、沈設の進行に伴つてこの下部ケ
ーソン1aの上にセグメント3を積層する。この
工程を順次繰返して第1図に示す如く下部ケーソ
ン1aを必要な深さに沈設する。この沈設作業は
セグメント3相互の締結はボルト4を締付けるだ
けでよいから能率よく行なえる。
Next, the construction procedure of the caisson construction method of the present invention will be explained one by one. First, as shown in FIG. 1, after constructing the built-up island 8 inside the temporary cofferdam 6, the lower caisson 1a is constructed according to the conventional caisson construction method as described above. The lower caisson 1a may be vertically divided into several lots at the installation position of the island 8 and formed by splicing concrete, or may be formed in advance into one piece. Then, while excavating the inside of the lower caisson 1a,
is gradually lowered, and as the lower caisson 1a progresses, the segments 3 are stacked on top of the lower caisson 1a. This process is repeated in order to sink the lower caisson 1a to the required depth as shown in FIG. This sinking work can be carried out efficiently because the segments 3 can be connected to each other by simply tightening the bolts 4.

次に第4図に示す如く下部ケーソン1aの内側
底部に底版13を形成し、この底版13の上に中
詰コンクリート11を充填し、下部ケーソン1a
の上端に頂版12を構築して橋の基礎とし、頂版
12上に橋脚10が構築される。
Next, as shown in FIG. 4, a bottom plate 13 is formed at the inner bottom of the lower caisson 1a, and filling concrete 11 is filled on top of this bottom plate 13.
A top slab 12 is constructed on the upper end of the bridge as the foundation of the bridge, and a bridge pier 10 is constructed on the top slab 12.

橋脚10の構築を終えた後は上部ケーソン1b
のセグメント3を上から順番に分解していく。セ
グメント3はボルト4を緩めるだけで簡単に分解
できる。分解したセグメント3はクレーンで吊上
げて撤去する。この際セグメント3の大きさが一
定なので撤去作業が容易で能率よく行なえる。ま
た従来のブレーカによる破壊撤去に比べると騒音
もなくまた大がかりりで堅固な作業足場を構築す
る必要がなく、さらにコンクリート塊の鉄筋ひげ
などがないので撤去作業が非常にやりやすい。な
お上部ケーソン1bを分解する際はそれに合わせ
て築島8を掘削、排土するとともに、セグメント
3の分解が終了すると、第5図に示す如く、仮締
切り6内に河床2面まで埋土を行つた後に、仮締
切り6を撤去して工事が終了する。
After completing the construction of pier 10, the upper caisson 1b
Segment 3 of is disassembled in order from the top. Segment 3 can be easily disassembled by simply loosening bolt 4. The disassembled segment 3 will be lifted up with a crane and removed. At this time, since the size of the segment 3 is constant, the removal work is easy and efficient. In addition, compared to destruction and removal using conventional breakers, there is no noise, there is no need to construct large-scale, solid work scaffolding, and there are no reinforcing bars on concrete blocks, making removal work very easy. Furthermore, when disassembling the upper caisson 1b, the construction island 8 is excavated and earth is removed accordingly, and when the disassembly of the segment 3 is completed, earth is filled up to two sides of the river bed within the temporary cofferdam 6, as shown in Fig. 5. After this, the temporary cofferdam 6 will be removed and the construction will be completed.

以上本発明の一実施例につき説明したが本発明
は上記実施例に限定されることなく種々の変形が
可能であつて、例えばケーソン1の断面形状は円
形の他、楕円や長方形などでもよい。またセグメ
ント3を相互に締結する締結具としてはボルトと
ナツトの他に連結板や支持桁等を併用してもよ
い。
Although one embodiment of the present invention has been described above, the present invention is not limited to the above embodiment and can be modified in various ways. For example, the cross-sectional shape of the caisson 1 may be oval, rectangular, etc. in addition to being circular. Further, as fasteners for fastening the segments 3 to each other, in addition to bolts and nuts, connecting plates, support beams, etc. may be used in combination.

《発明の効果》 本発明は上述の如く、最終的に撤去する上部ケ
ーソンを分解可能な複数のセグメントで構成して
いるので上部ケーソンの構築ならびに分解、撤去
が容易になり工期の短縮化を図れるとともに、火
薬やブレーカを使わないので作業環境も良好に維
持できる。
<<Effects of the Invention>> As described above, in the present invention, the upper caisson to be finally removed is composed of a plurality of segments that can be disassembled, so that the construction, disassembly, and removal of the upper caisson are facilitated, and the construction period can be shortened. Additionally, since no explosives or breakers are used, a good working environment can be maintained.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の一実施例を示したものであつ
て、第1図は沈設完了時のケーソンの右半分縦断
面図、第2図は第1図の−線矢視横断面図、
第3図は第1図の部の詳細断面図、第4図は橋
脚の正面図、第5図は同橋脚の工事完了正面図で
ある。 1……ケーソン、1a……下部ケーソン、1b
……上部ケーソン、3……セグメント、4……ボ
ルト、5……ナツト、6……仮締切り、8……築
島、10……橋脚。
The drawings show one embodiment of the present invention, in which Fig. 1 is a longitudinal cross-sectional view of the right half of the caisson when the submergence is completed, Fig. 2 is a cross-sectional view taken along the - line in Fig. 1,
FIG. 3 is a detailed sectional view of the part shown in FIG. 1, FIG. 4 is a front view of the pier, and FIG. 5 is a front view of the pier after completion of construction. 1...Caisson, 1a...Lower caisson, 1b
... Upper caisson, 3 ... Segment, 4 ... Bolt, 5 ... Nut, 6 ... Temporary cofferdam, 8 ... Tsukishima, 10 ... Pier.

Claims (1)

【特許請求の範囲】[Claims] 1 刃口部を有する下部ケーソンの上に上部ケー
ソンを順次構築して、前記下部ケーソンを支持地
盤まで沈設した後、前記下部ケーソンを構造物の
基礎とし、その後前記上部ケーソンを撤去するよ
うにしたケーソン工法において、前記上部ケーソ
ンを予め形成された複数のセグメントで構成する
とともに、前記下部ケーソンの沈設時にこのセグ
メントを締結具によつて分解可能に相互に締結
し、前記下部ケーソンを前記構造物の基礎とした
後に、前記締結具を緩めて前記セグメントをその
上部から順次分解して撤去するようにしたことを
特徴とするケーソン工法。
1. The upper caisson is successively constructed on top of the lower caisson having the cutting edge portion, and after the lower caisson is sunk to the supporting ground, the lower caisson is used as the foundation of the structure, and then the upper caisson is removed. In the caisson construction method, the upper caisson is composed of a plurality of pre-formed segments, and when the lower caisson is sunk, the segments are removably fastened to each other by fasteners, and the lower caisson is connected to the structure. A caisson construction method characterized in that, after being set as a foundation, the fasteners are loosened and the segments are sequentially disassembled and removed from the top.
JP9359588A 1988-04-18 1988-04-18 Caisson construction work Granted JPH01268920A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9359588A JPH01268920A (en) 1988-04-18 1988-04-18 Caisson construction work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9359588A JPH01268920A (en) 1988-04-18 1988-04-18 Caisson construction work

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP7261881A Division JP2616750B2 (en) 1995-10-09 1995-10-09 Caisson method

Publications (2)

Publication Number Publication Date
JPH01268920A JPH01268920A (en) 1989-10-26
JPH055971B2 true JPH055971B2 (en) 1993-01-25

Family

ID=14086662

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9359588A Granted JPH01268920A (en) 1988-04-18 1988-04-18 Caisson construction work

Country Status (1)

Country Link
JP (1) JPH01268920A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100549649B1 (en) * 2002-11-28 2006-02-08 동양종합건업 주식회사 Precast Tall Pier for Bridge
CN107034908A (en) * 2017-06-20 2017-08-11 中铁二十四局集团新余工程有限公司 A kind of steel boxed cofferdam integral elevating equipment

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5016886A (en) * 1973-06-12 1975-02-21

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5016886A (en) * 1973-06-12 1975-02-21

Also Published As

Publication number Publication date
JPH01268920A (en) 1989-10-26

Similar Documents

Publication Publication Date Title
KR20000003270A (en) Tunnel construction method at area of thin soil surface
JPH055971B2 (en)
CN105569329A (en) Unilateral formwork support basement construction method and basement
JP2616750B2 (en) Caisson method
JPH06306853A (en) Construction of underground structure
JPS63280153A (en) Underground inverted lining method
JP3603134B2 (en) Mountain retaining method
JP4146250B2 (en) Open caisson bottom plate construction method
JPS6062327A (en) Construction of underwater continuous wall
JP3138129B2 (en) Reverse beam construction method and driving beam side formwork
JP3406370B2 (en) Horizontal shaft construction method
US3306049A (en) Excavating method using prestressed loop girders
JPH0768707B2 (en) Open caisson method
CN111648375B (en) Inner supporting structure based on shear wall as support
JPH10245847A (en) Retaining wall structure and its construction method
JP4319231B2 (en) Approach caisson and method for constructing tunnel approach section composed of caisson
JP3171716B2 (en) Foundation construction method on inclined surface
JPS6290445A (en) Block for foundation and its manufacture
JPS5853321Y2 (en) Element for mountain retainer
JP2022108444A (en) Reinforcement method for existing bank
JP2552863B2 (en) Basement method
JPH0381420A (en) Sinking method for open caisson
JP2002275921A (en) Reversed placing method
JPS62111028A (en) Construction of underground structure
JPH0329922B2 (en)