JPH01268920A - Caisson construction work - Google Patents

Caisson construction work

Info

Publication number
JPH01268920A
JPH01268920A JP9359588A JP9359588A JPH01268920A JP H01268920 A JPH01268920 A JP H01268920A JP 9359588 A JP9359588 A JP 9359588A JP 9359588 A JP9359588 A JP 9359588A JP H01268920 A JPH01268920 A JP H01268920A
Authority
JP
Japan
Prior art keywords
caisson
segments
foundation
construction
connectors
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9359588A
Other languages
Japanese (ja)
Other versions
JPH055971B2 (en
Inventor
Nozomi Tanaka
望 田中
Tadashi Fujita
藤田 唯始
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP9359588A priority Critical patent/JPH01268920A/en
Publication of JPH01268920A publication Critical patent/JPH01268920A/en
Publication of JPH055971B2 publication Critical patent/JPH055971B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To enhance the efficiency of operations by a method in which the upper caissons formed by connecting segments with connectors are orderly set on the lower caisson to make the lower caisson a base, and then the segments are removed away. CONSTITUTION:An embankment 8 is constructed inside of a temporary cofferdam 6, and a lower caisson 1a having a cutting edge 9 on its lower end is set and settled gradually while excavating the inside of the caisson 1a. As the settlement proceeds, segments 3 are set on the caisson 1a while connecting them mutually with connectors in a breakable manner. The lower caisson 1a is taken as a base and the segments are gradually broken and removed from above by loosening the connectors.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明はケーソン工法に関するものである。[Detailed description of the invention] (Industrial application field) The present invention relates to a caisson construction method.

(従来の技術) ケーソン工法は、下端に刃口を備えた鉄筋コンクリート
製の筒状のケーソンを地盤上に設置し、ケーソン内部の
土砂を掘削、排土しながらケーソンを沈下させて所定の
支持地盤まで到達させ、こ゛れを構造物の基礎とする工
法である。このようなケーソン工法で例えば橋の基礎を
構築する場合には、ケーソンの下部を基礎として、その
上部を撤去するのであるが19.この時の撤去方法とし
ては、従来、火薬やブレーカを用いて上部ケーソンを分
断しながら撤去していた。
(Conventional technology) In the caisson construction method, a cylindrical caisson made of reinforced concrete with a cutting edge at the lower end is installed on the ground, and the earth and sand inside the caisson is excavated and removed while the caisson is lowered and placed on a designated supporting ground. This is a method of construction in which the structure is built up to a certain point, and this is used as the foundation of the structure. When constructing a foundation for a bridge using this caisson construction method, for example, the lower part of the caisson is used as the foundation and the upper part is removed.19. Conventionally, the removal method at this time was to use gunpowder or breakers to separate the upper caisson and remove it.

(発明が解決しようとする課題) しかし、上述の如く火薬やブレーカを用いると作業環境
が悪くなるし、また破砕したコンクリート塊の撤去が容
易でない等作業能率の点でも問題がある。
(Problems to be Solved by the Invention) However, as mentioned above, the use of explosives and breakers worsens the working environment, and also poses problems in terms of work efficiency, such as difficulty in removing crushed concrete blocks.

本発明は前記課題を有効に解決すべく創案するに至った
ものであって、その目的は上部ケーソンの撤去を作業環
境を良好に維持しつつ迅速に行い得るケーソン工法を提
供することにある。
The present invention has been devised to effectively solve the above-mentioned problems, and its purpose is to provide a caisson construction method that allows the removal of the upper caisson to be carried out quickly while maintaining a good working environment.

(課題を解決するための手段) 前記課題を解決するため本発明は、刃口部を有する下部
ケーソンの上に上部ケーソンを順次構築して、前記下部
ケーソンを支持地盤まで沈設した後、前記下部ケーソン
を構造物の基礎とし、その後前記上部ケーソンを撤去す
るようにしたケーソン工法において、前記上部ケーソン
を予め形成された複数のセグメントで構成するとともに
、前記下部ケーソンの沈設時にこのセグメントを締結具
によって分解可能に相互に締結し、前記下部ケーソンを
前記構造物の基礎とした後に、前記締結具を緩めて前記
セグメントをその上部から順次分解して撤去するように
した。
(Means for Solving the Problems) In order to solve the above problems, the present invention sequentially constructs an upper caisson on a lower caisson having a cutting edge portion, and after sinking the lower caisson to the supporting ground, In a caisson construction method in which a caisson is used as the foundation of a structure and the upper caisson is then removed, the upper caisson is composed of a plurality of pre-formed segments, and the segments are fastened by fasteners when the lower caisson is sunk. After the lower caisson has been used as the foundation of the structure by being removably fastened to each other, the fasteners are loosened and the segments are sequentially disassembled and removed from the top.

(作 用) 前記の如く構成したケーソン工法においては、上部ケー
ソンが分解可能な複数のセグメントで構築されているの
で、締結具を緩めるだけでセグメントを迅速に分解して
搬出することができる上、前記セグメントは再利用可能
であることから施工コストの低減を図れ、また火薬等を
使わないですむので作業環境が良好に維持される。
(Function) In the caisson construction method constructed as described above, the upper caisson is constructed of a plurality of segments that can be disassembled, so the segments can be quickly disassembled and carried out simply by loosening the fasteners. Since the segments are reusable, construction costs can be reduced, and since there is no need to use explosives, a good working environment can be maintained.

(実施例) 以下に本発明の一実施例を図面に基いて説明する。(Example) An embodiment of the present invention will be described below with reference to the drawings.

第1図は橋の基礎として用いられるケーソン1を河床2
から所定深さまで沈設した状態を示している。このケー
ソン1は鉄筋コンクリート製で第2図に示す如く円筒状
をなしている。ケーソン1はその下半分の下部、ケーソ
ン1aと上半分の上部ケーソン1bで構成されている。
Figure 1 shows the caisson 1 used as the foundation of the bridge and the river bed 2.
The figure shows the state where the pipe has been sunk to a predetermined depth. This caisson 1 is made of reinforced concrete and has a cylindrical shape as shown in FIG. The caisson 1 is composed of a lower half of the caisson 1a, and an upper caisson 1b.

上部ケーソン1bは多数のセグメント3からなり、各セ
グメント3は第3図に示す如くボルト4とす・ソト5に
よって分解可能に相互に締結されている。以下さらに詳
しく説明する。
The upper caisson 1b consists of a large number of segments 3, and each segment 3 is removably fastened to each other by bolts 4 and bolts 5, as shown in FIG. This will be explained in more detail below.

河床2には、筒状の仮締切り6が所定深さまで打設され
る。仮締切り6の上端は水面7からやや上方に突出し、
仮締切り6の内側に水が流れ込むのを阻lF、シている
。仮締切り6の内側には、内部の水を排除して土砂を投
入して築島8が構築され、この築島8からケーソン1が
沈設される。
A cylindrical temporary cofferdam 6 is driven into the riverbed 2 to a predetermined depth. The upper end of the temporary cofferdam 6 protrudes slightly above the water surface 7,
This prevents water from flowing into the inside of the temporary cofferdam 6. A built-up island 8 is constructed inside the temporary cofferdam 6 by removing the water inside and throwing earth and sand into it, and the caisson 1 is sunk from this built-up island 8.

ケーソン1の下部ケーソン1aは、その下端部に刃口部
9を具備しているとともに、その長さは構築される基礎
の長さに設定されている。この刃口部9は沈設抵抗を少
なくするためのものである。
The lower caisson 1a of the caisson 1 has a cutting edge 9 at its lower end, and its length is set to the length of the foundation to be constructed. This blade opening 9 is for reducing sinking resistance.

上部ケーソン1bは、分解可能な多数の既成の鉄筋コン
クリート製セグメント3を円周方向に並べるとともに、
上下方向に積層して構成されている。セグメント3の内
面壁3aには第3図に示す如く四部17が形成されてい
る。四部17の上下の側壁3bには上下方向に挿通孔1
8が形成され、この挿通孔18は上下に隣接した別のセ
グメント3の挿通孔18に連続している。そして連続し
た2つの挿通孔18に挿入されたボルト4と、このボル
ト4の先端に螺合されたナツトによって上下のセグメン
ト3が相互に締結されている。また四部17の左右の側
壁にも前記したような挿通孔が同様に形成され、同様の
ボルトとナツトによって左右のセグメント3が相互に締
結されている。なお最下段のセグメント3は下部ケーソ
ン1aの上端に突設したアンカーボルト19にナツト2
0で固定されている。
The upper caisson 1b has a large number of ready-made reinforced concrete segments 3 that can be disassembled arranged in the circumferential direction, and
It is constructed by stacking layers in the vertical direction. Four portions 17 are formed on the inner wall 3a of the segment 3, as shown in FIG. The upper and lower side walls 3b of the four parts 17 have insertion holes 1 in the vertical direction.
8 is formed, and this insertion hole 18 is continuous with the insertion hole 18 of another vertically adjacent segment 3. The upper and lower segments 3 are fastened to each other by bolts 4 inserted into two consecutive insertion holes 18 and nuts screwed onto the ends of the bolts 4. Furthermore, the above-mentioned through holes are similarly formed in the left and right side walls of the four parts 17, and the left and right segments 3 are fastened to each other by similar bolts and nuts. The lowermost segment 3 has a nut 2 attached to an anchor bolt 19 protruding from the upper end of the lower caisson 1a.
It is fixed at 0.

セグメント3の上下左右の接合面には防水のため必要に
応じシール材を取付ける。このシール材はなるべく接合
面の中央部に取付けるようにする。
Attach sealing material to the upper, lower, left, and right joint surfaces of segment 3 as necessary for waterproofing. This sealing material should be attached to the center of the joint surface as much as possible.

また接合面の内側の目地部にさらにコーキング材を充填
してもよい。
Further, the joint portion inside the joint surface may be further filled with caulking material.

セグメント3で構成される仮壁としての上部ケーソン1
6は、沈設時においては圧入支圧壁体として、また、沈
設後は止水壁体としての機能を合する。
Upper caisson 1 as a temporary wall consisting of segments 3
6 functions as a press-fit bearing wall when it is sunk, and as a water-stop wall after it is sunk.

次に本発明のケーソン工法の施工手順を追って説明する
。まず第1図に示す如く仮締切り6の内側に築島8を構
築した後、下部ケーソン1aは前述の如〈従来のケーソ
ン工法に準じて施工される。
Next, the construction procedure of the caisson construction method of the present invention will be explained one by one. First, as shown in FIG. 1, after constructing the built-up island 8 inside the temporary cofferdam 6, the lower caisson 1a is constructed according to the conventional caisson construction method as described above.

なお、下部ケーソン1aは、築島8の据付は位置に垂直
方向に数ロットに分割してコンクリートを打継ぎながら
形成するか、あるいは予め一体化したものであってもよ
い。そして、下部ケーソン1aの内部を掘削しながら、
下部ケーソン1aを徐々に沈設し、沈設の進行に伴って
この下部ケーソン1aの上にセグメント3を積層する。
Incidentally, the lower caisson 1a may be installed by dividing it into several lots in the vertical direction to the position and forming it by pouring concrete, or by integrating it in advance. Then, while excavating the inside of the lower caisson 1a,
The lower caisson 1a is gradually lowered, and as the lower caisson 1a is lowered, the segments 3 are stacked on top of the lower caisson 1a.

この工程を順次繰返して第1図に示す如く下部ケーソン
1aを必要な深さに沈設する。この沈設作業はセグメン
ト3相互の締結はボルト4を締付けるだけでよいから能
率よく行なえる。
This process is repeated in order to sink the lower caisson 1a to the required depth as shown in FIG. This sinking work can be carried out efficiently because the segments 3 can be connected to each other by simply tightening the bolts 4.

次に第4図に示す如く下部ケーソン1aの内側底部に底
版13を形成し、この底版13の上に中詰コンクリート
11を充填し、下部ケーソン1aの上端に頂板12を構
築して橋の基礎とし、頂板12上に橋脚10が構築され
る。
Next, as shown in Fig. 4, a bottom plate 13 is formed at the inner bottom of the lower caisson 1a, a filling concrete 11 is filled on top of this bottom plate 13, and a top plate 12 is constructed at the upper end of the lower caisson 1a to form the foundation of the bridge. Then, the pier 10 is constructed on the top plate 12.

橋脚10の構築を終えた後は上部ケーソン1bのセグメ
ント3を上から順番に分解していく。セグメント3はボ
ルト4を緩めるだけで簡単に分解できる。分解したセグ
メント3はクレーンで吊上げて撤去する。この際セグメ
ント3の大きさが一定なので撤去作業が容易で能率よく
行なえる。また従来のブレーカによる破壊撤去に比べる
と騒音もなくまた大がかりりで堅固な作業足場を構築す
る必要がなく、さらにコンクリート塊の鉄筋ひげなどが
ないので撤去作業が非常にやりやすい。なお上部ケーソ
ン1bを分解する際はそれに合わせて築島8を掘削、排
土するとともに、セグメント3の分解が終了すると、第
5図に示す如く、仮締切り6内に河床2面まで埋土を行
った後に、仮締切り6を撤去して工事が終了する。
After completing the construction of the pier 10, the segments 3 of the upper caisson 1b are disassembled in order from the top. Segment 3 can be easily disassembled by simply loosening bolt 4. The disassembled segment 3 will be lifted up with a crane and removed. At this time, since the size of the segment 3 is constant, the removal work can be easily and efficiently performed. In addition, compared to destruction and removal using conventional breakers, there is no noise, there is no need to construct large-scale, solid work scaffolding, and there is no need for reinforcing bars on concrete blocks, making removal work very easy. In addition, when disassembling the upper caisson 1b, the construction island 8 is excavated and earth is removed accordingly, and when the disassembly of the segment 3 is completed, earth is filled up to two sides of the river bed within the temporary cofferdam 6, as shown in Fig. 5. After that, the temporary cofferdam 6 will be removed and the construction will be completed.

以上本発明の一実施例につき説明したが本発明は上記実
施例に限定されることなく種々の変形が可能であって、
例えばケーソン1の断面形状は円形の他、楕円や長方形
などでもよい。またセグメント3を相互に締結する締結
具としてはボルトとナツトの他に連結板や支持桁等を併
用してもよい。
Although one embodiment of the present invention has been described above, the present invention is not limited to the above embodiment and can be modified in various ways.
For example, the cross-sectional shape of the caisson 1 may be circular, elliptical, rectangular, or the like. Further, as fasteners for fastening the segments 3 to each other, in addition to bolts and nuts, connecting plates, support beams, etc. may be used in combination.

(発明の効果) 本発明は上述の始<、最終的に撤去する上部ケーソンを
分解可能な複数のセグメントで構成しているので上部ケ
ーソンの構築ならびに分解、撤去が容易になり工期の短
縮化を図れるとともに、火薬やブレーカを使わないので
作業環境も良好に維持できる。
(Effects of the Invention) The present invention consists of a plurality of disassembleable segments for the upper caisson to be finally removed, which facilitates the construction, disassembly, and removal of the upper caisson, thereby shortening the construction period. In addition, since no explosives or breakers are used, the work environment can be maintained in a good condition.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の一実施例を示したものであって、第1図
は沈設完了時のケーソンの右半分縦断面図、第2図は第
1図の■−■線矢視横断面図、第3図は第1図の1部の
詳細断面図、第4図は橋脚の正面図、第5図は同橋脚の
工事完了正面図である。 1・・・・・・ケーソン    1a・・・下部ケーソ
ン1b・・・上部ケーソン  3・・・・・・セグメン
ト4・・・・・・ボルト     5・・・・・・ナツ
ト6・・・・・・仮締切り    8・・・・・・築 
島10・・・橋脚 特許出願人      株式会社 大 林 組代 理 
人      弁理士 −色 健 軸間       
 弁理士 松 本 雅 利j[4図 第 1 図 ソ 軍2図 第5図
The drawings show one embodiment of the present invention, in which Fig. 1 is a vertical cross-sectional view of the right half of the caisson when the submergence is completed, Fig. 2 is a cross-sectional view taken along the line ■-■ in Fig. 1, Fig. 3 is a detailed sectional view of a portion of Fig. 1, Fig. 4 is a front view of the pier, and Fig. 5 is a front view of the pier after completion of construction. 1...Caisson 1a...Lower caisson 1b...Upper caisson 3...Segment 4...Bolt 5...Nut 6...・Temporary deadline 8・・・・・・Construction
Island 10... Bridge pier patent applicant Obayashi Co., Ltd. Agent
People Patent Attorney - Ken Iro
Patent Attorney Masatoshi Matsumoto [Figure 4 Figure 1 Figure Soviet Army Figure 2 Figure 5

Claims (1)

【特許請求の範囲】[Claims] 刃口部を有する下部ケーソンの上に上部ケーソンを順次
構築して、前記下部ケーソンを支持地盤まで沈設した後
、前記下部ケーソンを構造物の基礎とし、その後前記上
部ケーソンを撤去するようにしたケーソン工法において
、前記上部ケーソンを予め形成された複数のセグメント
で構成するとともに、前記下部ケーソンの沈設時にこの
セグメントを締結具によって分解可能に相互に締結し、
前記下部ケーソンを前記構造物の基礎とした後に、前記
締結具を緩めて前記セグメントをその上部から順次分解
して撤去するようにしたことを特徴とするケーソン工法
A caisson in which an upper caisson is sequentially constructed on a lower caisson having a cutting edge, and after the lower caisson is sunk to supporting ground, the lower caisson is used as the foundation of a structure, and then the upper caisson is removed. In the construction method, the upper caisson is composed of a plurality of pre-formed segments, and the segments are removably fastened to each other by fasteners when the lower caisson is sunk,
A caisson construction method characterized in that after the lower caisson is used as the foundation of the structure, the fasteners are loosened and the segments are sequentially disassembled and removed from the upper part.
JP9359588A 1988-04-18 1988-04-18 Caisson construction work Granted JPH01268920A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9359588A JPH01268920A (en) 1988-04-18 1988-04-18 Caisson construction work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9359588A JPH01268920A (en) 1988-04-18 1988-04-18 Caisson construction work

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP7261881A Division JP2616750B2 (en) 1995-10-09 1995-10-09 Caisson method

Publications (2)

Publication Number Publication Date
JPH01268920A true JPH01268920A (en) 1989-10-26
JPH055971B2 JPH055971B2 (en) 1993-01-25

Family

ID=14086662

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9359588A Granted JPH01268920A (en) 1988-04-18 1988-04-18 Caisson construction work

Country Status (1)

Country Link
JP (1) JPH01268920A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100549649B1 (en) * 2002-11-28 2006-02-08 동양종합건업 주식회사 Precast Tall Pier for Bridge
CN107034908A (en) * 2017-06-20 2017-08-11 中铁二十四局集团新余工程有限公司 A kind of steel boxed cofferdam integral elevating equipment

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5016886A (en) * 1973-06-12 1975-02-21

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5016886A (en) * 1973-06-12 1975-02-21

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100549649B1 (en) * 2002-11-28 2006-02-08 동양종합건업 주식회사 Precast Tall Pier for Bridge
CN107034908A (en) * 2017-06-20 2017-08-11 中铁二十四局集团新余工程有限公司 A kind of steel boxed cofferdam integral elevating equipment

Also Published As

Publication number Publication date
JPH055971B2 (en) 1993-01-25

Similar Documents

Publication Publication Date Title
KR20000003270A (en) Tunnel construction method at area of thin soil surface
JPH01268920A (en) Caisson construction work
JP3041280B1 (en) Prefabricated embankment
KR20210119935A (en) Underground structure using strut and method construturing the same
JPS63280153A (en) Underground inverted lining method
JP2616750B2 (en) Caisson method
JP2755888B2 (en) Abutment
CN215669530U (en) Foundation pit supporting system capable of being turned over
JP2000096584A (en) Steel-made earth retaining wall
JP4146250B2 (en) Open caisson bottom plate construction method
JPS6062327A (en) Construction of underwater continuous wall
JPH10245847A (en) Retaining wall structure and its construction method
JPS5841227Y2 (en) Element for mountain retainer
US3306049A (en) Excavating method using prestressed loop girders
JPS6290445A (en) Block for foundation and its manufacture
JP3171716B2 (en) Foundation construction method on inclined surface
JPH09184116A (en) Construction method of snowslide/falling stone guard fence and the fence
JP2552863B2 (en) Basement method
JPH07180127A (en) Construction method of retaining wall for water-storage dam, checkdam, etc.
JPH0261573B2 (en)
JPH0868041A (en) Bank construction method
JPH056602B2 (en)
JPS62111028A (en) Construction of underground structure
JPH01174712A (en) Method of building breakwater
JPH031479B2 (en)